city development strategy report for laoag city 9 … alliance project output city development...
TRANSCRIPT
Cities Alliance Project Output
City Development Strategy Report for Laoag City 9 Mar 2009
City Development Strategies in the Philippines: An Enabling
Platform for Good Governance and Improving Service Delivery
P098173
This project output was created with Cities Alliance grant funding.
City Development Strategies Report | 1
CITY DEVELOPMENT STRATEGIES IN THE PHILIPPINES: AN ENABLING PLATFORM FOR GOOD GOVERNANCE AND IMPROVING SERVICE DELIVERY
The CDS3 Project is a technical assistance grant funded by Cities Alliance and
supported by the Asian Development Bank, Japan International Cooperation
Agency, UN-Habitat, and the World Bank. The CDS project was developed
in response to the need to introduce an integrated, comprehensive, and
participatory approach to urban management. Founded on the principles
of livability, bankability, competitiveness and good governance, the CDS
process guides the cities in the preparation of comprehensive, long-
term development strategies, where the city government involves local
stakeholders in the entire strategic planning process-assessment, visioning,
strategy formulation and project prioritization and capital investment
planning-through a series of consultations.
The World Bank implemented the pilot phase in the 1999 with 7 cities.
Since then, the League of Cities of the Philippines, carried out 2 succeeding
phases, which expanded the program to 58 cities in all. In 2001, the Up-
scaling Poverty Focused City Development Strategies (CDS2) covered
31 new cities. In 2005, the project CDS in the Philippines: An Enabling
Platform for Good Governance and Improving Service Delivery (CDS3)
added 15 new cities to the roster of CDS cities in the Philippines. Under
the preparation grant for the City Development and Investment Project,
the League also carried out CDS for 5 new cities. As of 2008, 64 of 120 cities
have participated in the CDS program, including 3 cities assisted by ADB
under the Cities without Slums Project (Caloocan, Quezon and Taguig),
and the 3 cities that participated in the Local Environmental Planning and
Management Project of the UNDP (Lipa, Cagayan de Oro and Tagbilaran).
For more information on CDS, you may visit http:www.cdsea.org
ContactMayor : Hon. Michael V. FariñasAddress : City Hall, 2900 Laoag City, Ilocos Norte Tel. Nos. : (077) 7720001; 7731788Fax No. : (077) 7713168Mobile No : (0918) 9088826Email : [email protected] URL/web : www.laoag.com
C D S 2 0 0 8
Laoag CityI LO CO S N O R T E , P H I L I P P I N E S
C I T Y D E V E LO P M E N TS T R AT E G I E S I N T H E P H I L I P P I N E S
A n Enabling Pla tform for Good Governance and improving Ser vice Deliver y
C I T Y D E V E L O P M E N T S T R AT E G I E S R E P O R T
CDS Core TeamHon. Michael V. Fariñas - City Mayor
Hon. Yvonne B. Ranada - SP Member
Hon. Constante F. Dancel, Jr. - SP Member
Ms. Gloria F. Peralta - City Administrator
Ms. Maria Luisa F. Castro - City Planning and Development Coordinator
Mr. Edgar R. Pascual - City Accountant
Ms. Carlina V. Cumigad - City Budget Officer
Ms. Corazon Lillian Celia C. Rin - Social Welfare Officer III
Technical Working GroupMr. Oscar R. Recta - City Agriculturist
Dr. Renato R. Mateo - City Health Officer
Ms. Lilian R. Abijero - City Civil Registrar
Engr. Fred C. Agpaoa - Asst. City Engineer
Ms. Elena V. Asuncion - ICO, City Treasurer
Mr. Joseph H. Tamayo - Community Affairs Officer IV
Engr. Wilfredo R. Miranda, Jr. - Statistician II
TABLE OF CONTENTS
PAGE
SELECTED URBAN KARTE INDICATORS
INTRODUCTION 2
SITUATION ANALYSIS 8
LIVABILITY 8
COMPETITIVENESS 9
BANKABILITY 10
GOOD GOVERNANCE 10
VISION AND CITY BRAND 11
STRATEGIES 12
ANNExES
CAPITAL INVESTMENT PLAN 14
SUMMARY CAPITAL INVESTMENT PLAN 28
FINANCIAL ANALYSIS 30
SELECTED URBAN KARTE INDICATORS
A1
A2
A11
A7
A15
A17
A
B
C
A18
A
B
C
D
L1
L11
L14
L30
L41
L45
C18
A
B
C
D
C29
C32
B3
B4
FP2 - B
FP2 - D
2000 population
Total Population (2005)
Population Growth Rate (2000-2005)
Administrative Land Area (Km2)
Urban Population (projected 2005)
Number of Households (2000)
Estimated Employment by Industry Sector
Primary (agriculture, fishery, forestry)
Secondary (manufacturing, mining, processing)
Tertiary (services, banking, insurance, wholesale/retail trade)
What are the City’s geographical advantages?
Regional/provincial center
Accessibility to an airport of international standards
Accessibility to a port of international standards
Others (please describe)
% of HH with access to piped water (level 3)
Cohort survival rate for elementary (2005)
Cohort survival rate for high school (2005)
Infant mortality rate
Crime solution efficiency rate
Number of HH living in informal settlements
Building permits issued within the last 5 years
Residential
Commercial
Agricultural
Institutional
Unemployment rate (2001 vs. 2005)
% population with undergraduate degree
% Total Debt Servicing Needs to Total Regular Income
% of savings to expenditures (2007)
Per Capita Allocation to Health Services
Per Capita Allocation to Education Sector
INDICATORS LAOAG
94,466
99,880
1.12%
127.47 Km2
39,437
19,751
149
538
9,979
yes
yes
yes
accessibility to NCR and other provinces
58.30%
99.08%
95.08%
3.48%
86.25%
none
2,067
344
14
37
5.77%
14.19%
10.94%
9.63%
286.37
81.11
SELECTED URBAN KARTE INDICATORS
G2
G2
G7
G11
1
2
3
4
5
6
7
8
9
10
11
Average Number of days to issue a NEW business license (w/ complete documents)
Average Number of days to RENEW business license (w/ complete documents)
% of local revenue/total revenue
Frequency of meetings of the Local Development Council (LDC)
ADDITIONAL DATA (from the survey)
Poverty Incidence
Performance of elementary children in NAT
Performance of high school children in NAT
Percentage of participation of Local Special Bodies (LSBs) in public hearings conducted
Presence of ELA (if yes, proceed to questions 6 and 7; if no, proceed to question 8)
Percentage of Projects implemented from ELA derived from CLUP
Percentage of Projects implemented from AIP derived from ELA
No. of registered small and medium industries (2001 vs 2005 for all types)
Number of barangays practicing segregation at source and served by an MRF
Percent of waste generated diverted from disposal
Presence of sanitary landfill
INDICATORS LAOAG
1
1
56.76
twice a year
10.96%
74.35
45.77
50%
Yes
75%
100%
195
51
89.50%
Yes
2 | City of Laoag City Development Strategies Report | 3
INTRODUCTION
Location
The City of Laoag is located at the west central part of the Province of Ilocos Norte bordering the South China Sea. It is bounded on the east by the Municipality of Sarrat, in the southeast by the Municipality of San Nicolas, in the southwest by the Municipality of Paoay, in the northeast by the Municipality of Vintar, in the northwest by the Municipality of Bacarra, and in the west by the South China Sea. Laoag City may be reached via the Manila North Tollway, 488 kms. from Manila.
Land Area
Laoag City has a total land area of 127.4735 square kilometers. It consists of 80 barangays, 30 of which are urban and 50 are rural . The land available for development is 1,596.76 hectares as per land use plan.
An area of 930.847 hectares is occupied by the urban core or the poblacion, while 11,816.501 hectares are occupied by the rural barangays.
Population
Laoag City has a total population of 99,880 for the year 2005 based on the official report published by the Population Commission. In 2000, the total inhabitants of the city was 94,446, an increase of 5,434. The City’s average annual growth rate is 1.12%..
The growth trends over the last 5 years was primarily due to birth and in-migration (4.78%). Brgy 1 San Lorenzo(787) has the highest increase in population while the most dense barangay is Brgy. 14 Sto. Tomas (211/sq.km.).
Physical Characteristics
Based on a geohazard analysis, portions of the City are vulnerable to tsunamis, slitation/erosion, and flooding.
The city, which is located at the west central part of the Province of Ilocos Norte, becomes a natural water drain during heavy rains. Most flood prone areas are those along the river and other water bodies within the
city. Flooding, however, is now contained because of the construction of the Integrated Drainage System and the SABO Dam and Flood Control. Although Laoag City is along the South China Sea, the possibility of experiencing a tsunami or tidal wave is remote.
The Bangui Fault Line runs along the province from Bangui going southeast passing through Vintar, the municipality just east of Laoag.
Geographical Advantages
Laoag is strategically located at the west central part of the province of Ilocos. It is the capital of Ilocos Norte plays the following functional roles in relation to other towns, to the Province and to the region:
• Educational,Commercial, InformationandCommunicationCenterofthe province
• AccessibleinanInternationalAirport
• AccessibilitytoanInternationalSeaport
• IdentifiedasECOZONEbyPEZALaw(R.A.7916)
4 | City of Laoag City Development Strategies Report | 5
A. Ilocos NorteB. CagayanC. ILocos SurD. IfugaoE. IsabelaF. TarlacG. La UnionH. PangasinanI. Nueva EcijaJ. Aurora
AB
C D E
FG
H I
J
Laoag City
Adams
Laoag City
Pagudpud
Burgos Bangui
Dumaheg
Bacarra
Pasuquin
Paoay
Currimao
Badoc
Carasi
Solsona
Marcos
Nueva Era
Vintar
PiddigSarat
Batac
Pinili
Dingras
Bannar
Mindanao
Visayas
Luzon
Laoag City
South China Sea
6 | City of Laoag City Development Strategies Report | 7
8 | City of Laoag City Development Strategies Report | 9
COMPETITIVENESS
Background :
• TheAirportcaterstoflightstoandfromnearbycountries
• HasanefficientanddynamicTourismandSocialConcernsCouncil
• In 2001, tourist arrivals registered a total of 104,668. Of this figure,94.97% were domestic tourists. In 2005, there were 164,746 where 79.92% were domestic tourists
• Ofourtotallandarea,58.54%isdevotedtoagriculture
• 94.23% of the 63,624(63.70%) economically active population aregainfully employed
Key Opportunities/Strengths :
• InternationaltransporthubwithanInternationalAirportandSeaport
• HallofFameAwardee–GawadPangulosaK.A.P.A.L.I.G.I.R.A.N.
• Has a proven track record in the Discipline/Peace and OrderCampaign
• 58.74%ofitslandisdevotedtoagriculture
• Fertileagro-land
• EfficientandeffectiveTechno-PinoyCenter
Main Development Challenges :
• Lackofresearch/trainingcenters/institutions
• Needtomodernize,improveandupgradetheLIAandtheSeaportofCurrimao.
• LimitedNGOs,POs,andprivate-sectorinitiatedprojectsinadvancingtourism concerns
• Inadequatefundsfordevelopingandenhancingnatural,historicalaswell as man-made attraction/s
• Limitedjobopportunities.
• Rapid urbanization and commercial/economic advancement ofnearby LGUs
• Needtomaximizeitspotentialforforeigninvestorsandtouristsfromnorthern neighboring countries (i.e. China and Taiwan)
SITUATION ANALYSIS
LIVABILITY
Background:
• 57.64%familieshaveaccesstopotablewater(level3)
• One(1)PrimaryHospitaland40healthcentersservicingthetotalcitypopulace of 99,880.
• Thecityhas44elementaryand11secondaryschools.
• HeartDiseasesremainstobethetopcauseofmorbidity.
• Thecityisvisitedbyanaverageof12typhoonseveryyear,2ofwhichare super typhoons.
• Crimesolutionefficiencyis86.25%.
• Tourismisathriving industryandthis ismanifestedbythe influxoftourists (foreign and local)
Key Opportunities/Strengths:
• 100%energized;surplusofpowersupply
• Abundanceofwaterresources
• Goodairandwaterquality
• Lowcrimerate
• ResiliencyandindustriousnessofIlocanos
• Highlyskilled&trainablelaborforce
• EducationalcenterforthemostpartofNorthernLuzon
Main Development Challenges:
• Needformodernandadvancedmedicalfacilities
• Needtoexpandcoverageoflevel3watersupply
• Needforadditionalclassroomsforsecondaryschools.
• Institutionalize “Saving All Lives And properties Knowledgeably,NotablyInBarangays”(S.A.L.A.K.N.I.B)–aDisasterRiskManagementPreparedness of the City.
• Needtodevelopidentifiedeco-tourismsites
10 | City of Laoag City Development Strategies Report | 11
• Outofitstotalrevenuein2005,56.76%isfromitsIRAshare.
• Public participation in the city’s various undertakings is throughpulong-pulong, membership in other local special bodies, participation in public consultations, monthly People’s Day.
• Thereare28NGOmembersintheCityDevelopmentCouncil.
• Public disclosure initiatives and feedback mechanism such as theRang-ay ti Barangay (Progress of the Barangay), a continuing outreach program
Key Opportunities/Strengths :
• Trainableworkforce
• Effectivepartnershipwiththeprivatesector
• Efficientorganizationalstructureandoperationalsystem
• Presence of an efficient public disclosure program and feedbackmechanism
• Presenceofprogramforincentivesandawardsforcityemployees
Main Development Challenges :
• Needtoencouragetheprivatesectortoshareintheprovisionofbasicservices and utilities
• Needtointroduceotherresourcegenerationandresourcemobilizationschemes.
• Needtore-assessthecapabilityofthecitygovernmenttoeffectivelyutilize its resources
• NeedtoinstitutionalizetheOne-Stop-Shop
• Needtoinstitutionalizevaluesformationactivities
• Needforcapacitybuildingactivities
• Needtoempowerthepeople
CITY VISION
By the year 2022, Laoag, the Sunshine City and Northern Gateway of the Philippines, will be a “Metropolitan Center in the North” where economic growth and development abound for its people to equitably share and enjoy.
• Absence of investment promotion activities, incentives and supportmeasures for investors.
• Needtodeveloptheidentifiedeco-tourismsites
BANKABILITY
Background :
• TheCityhasanaveragesavingsof9.63%comparedtoExpendituresfor the past 5 years.
• TheCityhasavailedof3loansfromDBPamountingtoP187.4Mfrom1997 to 2004. Average debt servicing was 10.94% from 2001 to 2005.
• IRAdependencydecreasedfrom65.11%in2001to56.76%in2005.
Key Opportunities/Strengths :
• Identifiedasindustrialestate/ECOZONE
• Financial,commercialandcommunicationcenteroftheprovince
• NortherngatewayofthePhilippines
• IncludedintheNorthLuzonGrowthQuadrangle(SuperRegions)
Main Development Challenges :
• EnticinginvestorsfromnearbyAsian/ASEANcountries
• Establishmentofanewcommercialcenter
• Encouragingmorecommercialactivities
• Establish commercial linkages with other highly urbanized localgovernment units
• Needforlinkstoregional,nationalandinternationalmarkets
GOVERNANCE
Background :
• TheCityhasatotalworkforce(cityemployees)of788ofwhich670are regular. Fifty-0ne percent (51%) of its total revenue is allotted for personal services
12 | City of Laoag City Development Strategies Report | 13
Laoag is envisioned to become a secondary metropolitan center in the northern part while maintaining its present functional roles earlier mentioned.
To attain this vision, the city shall capitalize on its diversified economic base and strategic location in undertaking strategic policies, programs, projects along with the development schemes of commercial growth, industrialization and eco-tourism.
Attaining the vision shall elevate the city from its present status as a Primary Urban Center (Large Town) playing the role of a capital town and inter-regional center to Secondary Metropolitan Center with the expected role as international production and distribution center with such facilities like the international airport, tertiary specialized medical facilities, comprehensive industrial and commercial establishments, world-class tourism facilities and state-of-the-art educational facilities.
Nickname : Sunshine City
Brand : The Northern Gateway of the Philippines
STRATEGIES
LIVABILITY:
1. Provision of modern and advanced medical facilities
Laoag, as a metropolitan center, shall be expected to provide high-end, state-of-the-art tertiary facilities, hence, this strategy is given high priority. The existence of modern and advance medical facilities will provide security in terms of medical services for would-be investors and tourists.
2. Establish strong partnership with the local water district for expansion of level 3 coverage
One aspect that really attracts tourists and investors into a certain area is the presence of adequate and efficient utility services, one which is the water system. It is therefore, imperative that the city government maintain a strong partnership with the local water district.
COMPETITIVENESS:
1. Encourage public-private sector investment partnership in agro-related industries by providing them a favorable investment climate
2. Establish strong partnership with the private sector in the development and improvement of tourism sites and tourism- related facilities
The private sector, as trend indicates, is a key player in the industrialization process. To attract investments into the city, there will be a need for policy development in terms of providing the necessary investment incentives as well as putting up the needed infrastructure facilities and utilities, thereof.
BANKABILITY:
1. Productivity improvement on revenue generation, allocation, mobilization and utilization
2. Initiation of new resource generation and resource mobilization schemes to minimize dependency on Internal Revenue Allotment
These strategies go hand-in-hand, that if the city government succeeds in initiating or adopting new resource mobilization schemes to minimize dependency on the Internal Revenue Allotment (IRA) share from the national government, it will ultimately mean that productivity has improved in generating revenues as well as on revenue allocation, mobilization and utilization.
GOVERNANCE:
1. Institutionalize the One-Stop-Shop through the expansion of the City Hall (Phase II).
The construction of a new structure will house the One-Stop-Shop with appropriate staff for a more systematic processing of business permits and other similar concerns as well as other city front line offices such as the Office of the City Civil Registrar and the Office of the City Budget Officer.
2. Encourage the Private Sector to share in the provision of basic services and utilities
As the city at present is the only one undertaking the delivery of public services and the provision of public utilities and facilities such as the collection of garbage. In this way, the Private Sector can also help on a larger scale, the generation of revenues.
14 | City of Laoag City Development Strategies Report | 15
Project Name Total Project Cost 2007 2008 2009 2010 2011 2012-2022 Mode of Financing
CAPITAL INVESTMENT PLAN
1 Enactment of Incentive Code
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
2 General revision of Real Property
Tax / Revision of the Revenue Code
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
3 Laoag City Medical Center
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
200,000.00
200,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
200,000.00
500,000.00
500,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1,000,000.00
552,000,000.00
0.00
0.00
42,000,000.00
0.00
0.00
0.00
0.00
510,000,000.00
552,000,000.00
200,000.00
200,000.00
200,000.00
500,000.00
500,000.00
500,000.00
212,000,000.00
42,000,000.00
170,000,000.00
212,000,000.00
0.00
0.00
170,000,000.00
170,000,000.00
170,000,000.00
0.00
0.00
170,000,000.00
170,000,000.00
170,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
LGU Savings
LGU Savings/
Surplus
ODA-Grant, LGU
LGU Counterpart
ODA-Grant
16 | City of Laoag City Development Strategies Report | 17
1,000,000.00
500,000.00
500,000.00
1,000,000.00
500,000.00
5,000,000.00
5,000,000.00
2,000,000.00
2,000,000.00
2,000,000.00
Project Name Total Project Cost 2007 2008 2009 2010 2011 2012-2022 Mode of Financing
CAPITAL INVESTMENT PLAN
4 Development of Identified
Eco-tourism Sites
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
5 Expansion of the Laoag City Hall
(Phase II)
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
6 Establishment of Solid Waste
Management System
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
1,000,000.00
500,000.00
0.00
0.00
0.00
0.00
0.00
0.00
500,000.00
1,000,000.00
10,000,000.00
5,000,000.00
5,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
10,000,000.00
5,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
5,000,000.00
0.00
5,000,000.00
500,000.00
5,000,000.00
5,000,000.00
3,000,000.00
3,000,000.00
3,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
LGU
PS Investment
LGU Funds
Private Sector
Private Sector
18 | City of Laoag City Development Strategies Report | 19
40,000,000.00
0.00
0.00
00.00
Project Name Total Project Cost 2007 2008
CAPITAL INVESTMENT PLAN
7 Establishment of Traffic
Management System
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
8 Establishment of Wastewater
Treatment System
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
9 Establishment of Industrial
Estate
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
40,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
40,000,000.00
40,000,000.00
100,000,000.00
100,000,000.00
100,000,000.00
3,000,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
3,000,000,000.00
0.00
3,000,000,000.00
20,000,000.00
20,000,000.00
20,000,000.00
0.00
0.00
2009 2010 2011 2012-2022 Mode of Financing
20,000,000.00
20,000,000.00
40,000,000.00
40,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
ODA, Private Sector
Private Sector
ODA
ODA Grant
20 | City of Laoag City Development Strategies Report | 21
40,000,000.00
0.00
0.00
00.00
Project Name Total Project Cost 2007 2008
CAPITAL INVESTMENT PLAN
7 Establishment of Traffic
Management System
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
8 Establishment of Wastewater
Treatment System
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
9 Establishment of Industrial
Estate
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
40,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
40,000,000.00
40,000,000.00
100,000,000.00
100,000,000.00
100,000,000.00
3,000,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
3,000,000,000.00
0.00
3,000,000,000.00
20,000,000.00
20,000,000.00
20,000,000.00
0.00
2000,000,000.00
2000,000,000.00
2000,000,000.00
2009 2010 2011 2012-2022 Mode of Financing
20,000,000.00
20,000,000.00
100,000,000.00
40,000,000.00
40,000,000.00
2000,000,000.00
2000,000,000.00
2000,000,000.00
0.00
40,000,000.00
30,000,000.00
30,000,000.00
2000,000,000.00
2000,000,000.00
2000,000,000.00
0.00
30,000,000.00
30,000,000.00
30,000,000.00
2000,000,000.00
2000,000,000.00
2000,000,000.00
0.00
30,000,000.00
0.00
2000,000,000.00
2000,000,000.00
2000,000,000.00
ODA, Private Sector
Private Sector
ODA
ODA Grant
22 | City of Laoag City Development Strategies Report | 23
0.00
0.00
2,300,000.00
2,300,000.00
2,300,000.00
Project Name Total Project Cost 2007 2008
CAPITAL INVESTMENT PLAN
10 Commercial Complex
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
11 Expansion and sustainability of the
Geographical Information System
Treatment System
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
12 Expansion of potable water
supply
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
100,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
100,000,000.00
0.00
100,000,000.00
10,000,000.00
10,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
10,000,000.00
2,300,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2,300,000.00
2,300,000.00
0.00
3,000,000.00
5,000,000.00
5,000,000.00
0.00
2009 2010 2011 2012-2022 Mode of Financing
50,000,000.00
50,000,000.00
50,000,000.00
5,000,000.00
5,000,000.00
0.00
25,000,000.00
25,000,000.00
25,000,000.00
0.00
0.00
15,000,000.00
15,000,000.00
15,000,000.00
0.00
0.00
10,000,000.00
10,000,000.00
10,000,000.00
0.00
0.00
ODA-BOT
LGU Counterpart
Private Sector
24 | City of Laoag City Development Strategies Report | 25
2,000,000.00
2,000,000.00
2,000,000.00
1,000,000.00
1,000,000.00
1,000,000.00
300,000.00
300,000.00
300,000.00
Project Name Total Project Cost 2007 2008
CAPITAL INVESTMENT PLAN
13 Conversion of Controlled Dumpsite
to Engineered Sanitary Landfill
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
14 Construction of Integrated
Drainage System
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
15 Establishment, development and
promotion of industries engaged
in the processing of agricultural
products
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
200,000,000.00
0.00
0.00
5,000,000.00
0.00
0.00
0.00
0.00
195,000,000.00
200,000,000.00
200,000,000.00
0.00
2,000,000.00
8,000,000.00
0.00
190,000,000.00
0.00
0.00
0.00
200,000,000.00
1,000,000.00
300,000.00
0.00
0.00
0.00
0.00
0.00
0.00
700,000.00
1,000,000.00
43,000,000.00
3,000,000.00
40,000,000.00
43,000,000.00
1,000,000.00
1,000,000.00
1,000,000.00
700,000.00
700,000.00
700,000.00
2009 2010 2011 2012-2022 Mode of Financing
50,000,000.00
50,000,000.00
50,000,000.00
4,000,000.00
4,000,000.00
4,000,000.00
0.00
35,000,000.00
35,000,000.00
35,000,000.00
0.00
00.00
190,000,000.00
190,000,000.00
0.00
0.00
35,000,000.00
35,000,000.00
35,000,000.00
0.00
00.00
0.00
0.00
LGU, ODA-Grant
LGU Counterpart
ODA-Grant
LGU, Bank Loan
LGU
LGU
Bank Loan
LGU
LGU Counterpart
ODA-Grant
35,000,000.00
35,000,000.00
35,000,000.00
4,000,000.00
4,000,000.00
0.00
26 | City of Laoag City Development Strategies Report | 27
0.00
500,000.00
500,000.00
500,000.00
0.00
Project Name Total Project Cost 2007 2008
CAPITAL INVESTMENT PLAN
16 Provision of adequate pre and post
harvest facilities
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
17 Institutionalization of Capacity
Building and Value Formation
activities
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
18 Expansion of Animal Breeding
Station
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
50,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
50,000,000.00
50,000,000.00
500,000.00
500,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
500,000.00
5,000,000.00
0.00
1,000,000.00
0.00
0.00
0.00
0.00
0.00
4,000,000.00
5,000,000.00
0.00
0.00
1,000,000.00
1,000,000.00
1,000,000.00
2009 2010 2011 2012-2022 Mode of Financing
20,000,000.00
20,000,000.00
20,000,000.00
0.00
2,000,000.00
2,000,000.00
2,000,000.00
0.00
15,000,000.00
15,000,000.00
0.00
2,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
LGU
LGU
LGU/NGA
LGU Counterpart
PS
0.00
15,000,000.00
15,000,000.00
0.00
2,000,000.00
2,000,000.00
2,000,000.00
28 | City of Laoag City Development Strategies Report | 29
0.00
0.00
0.00
Project Name Total Project Cost 2007 2008
CAPITAL INVESTMENT PLAN
19 Establishment of Child-Minding
Drop-in Center
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
20 Fish Nursery of Tilapia and Bangus
Fingerlings Production
Mode of Financing
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h.Grant/subsidyfromNG,&others
T o t a l
5,000,000.00
0.00
0.00
500,000.00
0.00
0.00
0.00
0.00
4,500,000.00
5,000,000.00
1,000,000.00
1,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1,000,000.00
500,000.00
500,000.00
500,000.00
0.00
2009 2010 2011 2012-2022 Mode of Financing
2,500,000.00
2,500,000.00
2,500,000.00
1,000,000.00
1,000,000.00
1,000,000.00
0.00
0.00
0.00
0.00
0.00
0.00
LGU/PS Fundings
LGU Counterpart
ODA-Grant, NGA
LGU
LGU Counterpart
ODA-Grant
2,000,000.00
2,000,000.00
2,000,000.
00
0.00
7,000,000
1,000,000
44,000,000
0
0
0
2,000,000
172,800,000
226,800,000
Mode of Financing Total 2007 2008
SUMMARY OF CAPITAL INVESTMENT PLAN
a. Budgetary Surplus/Savings
b. Tax collection improvement
c. Revision of City Revenue Code
d. Income from projects - user charges
e. Bank loan
f. Bond flotation
g. BOT/Joint Venture
h. Grant/subsidy from NG, and others
Grand T o t a l
18,000,000
8,000,000
55,500,000
0
190,000,000
0
3,105,000,000
907,000,000
4,283,500,000
5,000,000
7,000,000
3,500,000
0
0
0
203,000,000
230,700,000
449,200,000
2009 2010 2011 2012-2022
6,000,000
0
4,000,000
0
0
0
250,000,000
304,500,000
564,500,000
0
0
0
0
190,000,000
0
215,000,000
80,000,000
485,000,000
0
0
0
0
0
0
2,210,000,000
35,000,000
2,245,000,000
0
0
4,000,000
0
0
0
225,000,000
84,000,000
313,000,000
30 | City of Laoag City Development Strategies Report | 31
Financial Analysis
A detailed study was made on the income and expenditures of the city for the past 5 years (CY 2001-2005) reviewing the trends. As per analysis, however, the growth rates computed were not reliable, hence, these were not taken into consideration in making the forecast from 2006 to 2012.
The figures presented in the analysis for 2006-2007 were taken from the annual budget for 2006 and the proposed 2007 annual budget.
As to revenues, the following assumptions were made:
1. There will be an increase ranging from 2% to 10% from CY 2008 to 2012.
2. Estimated savings were also included. For the past 5 years, average savings rate was 9.63%.
3. Adjustment in IRA share was included in 2007 because what was projected in the 2007 annual budget was the level for CY 2006.
4. Income shall increase as a result of the General Revision of Real Property Tax and the revision of the Revenue Code.
5. A proposed reduction in market rentals in 2007 (5%), 2008 (10%) and 2009 onwards (15%) to encourage full occupancy in the Laoag City Commercial Complex.
Forecast in expenditures from 2008-2012 is based on the level of needs of the different sectors. Budget proposals were required from the various offices concerned to determine expected expenditures. We also took into consideration the expected implementation of the Salary Standardization Law III, hence, the 5% increase on Personal Services from 2008 to 2011. The cityexpects to fullypay the loansas follows: 2008–LaoagCityCentralTerminal,2009–LaoagCityCommercialComplexand2010–IntegratedDrainage System.
On the overall, projected income shall be more than enough to cover projected expenditures with net surplus to fund projects identified in the Capital Investment Program.