chap006 mrp

Upload: priambodo-ariewibowo

Post on 01-Mar-2016

33 views

Category:

Documents


0 download

DESCRIPTION

aa

TRANSCRIPT

  • 7/18/2019 Chap006 Mrp

    1/30

    Copyright 2011 by The McGraw-Hill Companies, Inc. ll rights reser!e".McGraw-Hill#Irwin

    Manufacturing

    Planning and Control

    MPC 6thEdition

    Chapter 6

  • 7/18/2019 Chap006 Mrp

    2/30

    6-2

    Material Requirements

    Planning (MRP)

    Material Requirements Planning(MRP) has the managerial objective

    of providing the right part at theright time to meet the schedulesfor completed products!

    MRP provides a formal plan for eachpart number"ra# materials$components$ and finished products!

  • 7/18/2019 Chap006 Mrp

    3/30

    6-3

    %genda

  • 7/18/2019 Chap006 Mrp

    4/30

    6-4

    Resource

    planning

    &ales and operations

    planning

    'emand

    management

    Master productionscheduling

    'etailed capacit

    planning

    'etailed material

    planning

    Material and

    capacit plans

    &hopfloor

    sstems

    &upplier

    sstems

    EnterpriseResourc

    ePlanning(ERP

    )&stem

    Front End

    Engine

    Back End

    Manufacturing Planning and Control System

    *imephased

    requirement (MRP)

    records

    Routing

    file

    +ills of

    material

    ,nventor

    status

    data

  • 7/18/2019 Chap006 Mrp

    5/30

    6-5

    +asic MRP Record

  • 7/18/2019 Chap006 Mrp

    6/30

    6-6

    +asic MRP Record

    -n hand

    Period

    . / 0 1 2

    3ross requirements .4 14 .4

    &cheduled receipts 24

    Projected available balance 1 21 11 11 1 11

    Planned order releases 24

    5ead time . period5ot si7e 24

    % previousl

    released order

    due in period .

    % unreleased

    order due in

    period 2

    Requirements

    from all

    sources

  • 7/18/2019 Chap006 Mrp

    7/306-7

    +ill of Materials

    *he +-M sho#s thecomponents and

    subassemblies

    required to produce

    a product

  • 7/18/2019 Chap006 Mrp

    8/306-8

    Product &tructure 'iagram

    &ubassemblies

    are represented

    b separate

    levels

    8inished product is

    located at the top$

    components belo#

  • 7/18/2019 Chap006 Mrp

    9/30

  • 7/18/2019 Chap006 Mrp

    10/306-10

    E9plosion

    E9plosion"the process of translating product

    requirements into component part requirements

    Considers e9isting inventories and scheduled

    receipts

    Calculating the quantities of all components

    needed to satisf requirements for an given part!

    Continued until all parts have been considered$leading to e9act requirements for all purchased

    and:or ra# material parts

  • 7/18/2019 Chap006 Mrp

    11/30

    6-11

    3ross and ;et

    Requirements 3ross requirements represent the total planned usage for the part

    ;et requirements account for e9isting inventor and:or scheduled

    receipts

    .44 req

  • 7/18/2019 Chap006 Mrp

    12/30

    6-12

    'emand *pes in MRP

    'ependent"component or subassembl

    demand driven b net requirements from the

    ne9t higher level (e!g! scoop demand causedb net requirements for scoop assemblies)

    ,ndependent"demand driven b requirements

    from outside the firm (e!g! customer orders)

  • 7/18/2019 Chap006 Mrp

    13/30

    6-13

    5ead *ime -ffsetting

    3ross to net e9plosion sho#s ho# much of each

    part is required$ but not #hen

    *iming requires consideration of t#o factors5ead times"ho# long does it ta?e to obtain the

    component or subassembl

    Precedent relationships"the order in #hich parts

    must be assembled MRP considers both factors #hen developing the

    plan

  • 7/18/2019 Chap006 Mrp

    14/30

    6-14

    &cheduling 5ogic

    *#o common approaches to scheduling e9ist

    8ront schedule"schedule each step as earl as

    possible

    +ac? schedule"schedule each step as late as

    possible

    MRP combines bac? scheduling and gross to net

    e9plosionReduced inventories

    Minimi7ed storage time

  • 7/18/2019 Chap006 Mrp

    15/30

    6-15

    +ac? &cheduling

    *op handle

    assembl has the

    longest duration of

    an subassembl

    &coop assemblmust be complete

    before final

    assembl can begin

    -nl #hen all sub

    assemblies and

    components are

    available can final

    assembl begin

  • 7/18/2019 Chap006 Mrp

    16/30

    6-16

    MRP RecordsPlanned order release

    for top handle assembl

    becomes gross

    requirement for top

    handle component andnail (note / nails required

    per assembl)

    5otforlot order polic

    e9actl matches suppl

    to net requirements

    8i9ed lot si7e order

    polic requires orders in

    multiples of lot si7e

  • 7/18/2019 Chap006 Mrp

    17/30

    6-17

    MRP *echnical ,ssues

    Processing frequenc"recalculating all records and

    requirements is called regeneration *his is a computationall intensive process so it is often run

    in the bac?ground and during periods of lo# sstem demand ;et change approach onl recalculates those records

    that have e9perienced changes

    5ess frequent processing results in an outofdate

    picture More frequent processing increases computer costs

    and ma lead to sstem nervousness

  • 7/18/2019 Chap006 Mrp

    18/30

    6-18

    &afet &toc? and &afet

    5ead *ime

    &afet stoc? is buffer stoc? over and above the

    quantit needed to satisf gross requirements

    @sed #hen quantit uncertaint is the issue &afet lead time changes both the release and

    due date of shop and:or purchase orders to

    provide a margin for error

    @sed #hen timing of orders is the issue

    &afet lead time is not just an inflated lead time

  • 7/18/2019 Chap006 Mrp

    19/30

    6-19

    Pegging

    Pegging provides a lin? bet#een demand

    (order releases$ customer orders$ etc!) and

    the gross requirements for partsPegging records include the specific part

    numbers associated #ith a gross requirement

    Pegging information can trac? the impact of a

    problem (e!g! material shortage) bac? to theorder(s) it #ill affect

  • 7/18/2019 Chap006 Mrp

    20/30

  • 7/18/2019 Chap006 Mrp

    21/30

    6-21

    Planning Aori7on

    *otal amount of time included in MRP

    calculations

    5onger planning hori7on increasescomputational requirements

    &horter planning hori7on ma result in less

    effective plans if significant future demand is not

    visible%t a minimum$ should cover the cumulative lead

    time for all finished goods items

  • 7/18/2019 Chap006 Mrp

    22/30

    6-22

    &cheduled Receipts vs!

    Planned -rder Releases &cheduled receipts represent an actual commitment

    (purchase order$ production order$ etc!)

    Planned orders are onl the current plan and can be

    changed more easil &cheduled receipts for production orders alread have

    component materials assigned&cheduled receipts do not impact gross requirements

    Planned order releases do not have component materialsassignedPlanned order releases do impact gross requirements

  • 7/18/2019 Chap006 Mrp

    23/30

    6-23

    @sing the MRP &stem

  • 7/18/2019 Chap006 Mrp

    24/30

    6-24

    MRP Planner *as?s

  • 7/18/2019 Chap006 Mrp

    25/30

    6-25

    E9ception Codes

  • 7/18/2019 Chap006 Mrp

    26/30

    6-26

    +ottom@p Replanning

    @sing pegging data to guide efforts to solve

    material shortages

    Pegging data allo#s the planner to ta?eaction onl #hen actual customer orders are

    impacted

  • 7/18/2019 Chap006 Mrp

    27/30

    6-27

    MRP &stem -utputPart number and description MRP sstem data

    MRP planning data

    E9ception messages

  • 7/18/2019 Chap006 Mrp

    28/30

    6-28

    MRP &stem 'namics

  • 7/18/2019 Chap006 Mrp

    29/30

    6-29

    Principles

    Effective use of an MRP sstem allo#s development of a

    for#ardloo?ing approach to managing material flo#s!

    *he MRP sstem provides a coordinated set of lin?ed

    product relationships$ #hich permits decentrali7ed decisionma?ing for individual part numbers!

    %ll decisions made to solve problems must be implemented

    #ithin the sstem$ and transactions must be processed to

    reflect the resultant changes! Effective use of e9ception messages allo#s attention to be

    focused on the vital fe# rather than the trivial man!

  • 7/18/2019 Chap006 Mrp

    30/30

    6 30

    Bui7 " Chapter 6

    Material Requirements Planning (MRP) ta?es place in the front

    end sstems of the manufacturing planning and control sstem

    (*rue:8alse)

    ,n a Material Requirements Planning (MRP) sstem$ #hat does

    timephasing of gross requirements mean

    8ront scheduling logic starts each step of the process as late as

    possible (*rue:8alse)

    % lotforlot order polic generates orders for a fi9ed quantit$

    independent of actual requirements (*rue:8alse) Processing all Material Requirements Planning (MRP) records in

    a single computer run is called DDDDDDDDDDD

    &afet lead time involves inflating lead times to ensure stoc?

    availabilit (*rue:8alse)