cern cryomodule requirements for crab c avities
DESCRIPTION
CERN Cryomodule Requirements for Crab C avities. O. Capatina (CERN). Functional specification. https ://espace.cern.ch/HiLumi/WP4/Lists/Team%20Discussion/AllItems.aspx. General. SPS tests LHC final configuration. General. LHC environment. Q4. D2. IP. D2. Q4. General. - PowerPoint PPT PresentationTRANSCRIPT
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404.
CERN Cryomodule Requirements for Crab Cavities
O. Capatina (CERN)
LHC Crab Cryomodule meetingOC, 2/August/2013 1
Functional specification
OC, 2/August/2013 LHC Crab Cryomodule meeting 2
https://espace.cern.ch/HiLumi/WP4/Lists/Team%20Discussion/AllItems.aspx
• SPS tests
• LHC final configuration
General
OC, 2/August/2013 LHC Crab Cryomodule meeting 3
• LHC environment
General
OC, 2/August/2013 LHC Crab Cryomodule meeting 4
• LHC environment
~ 10m
General
OC, 2/August/2013 LHC Crab Cryomodule meeting 5
D2 Q4Q4 D2IP
• LHC environment
General
OC, 2/August/2013 LHC Crab Cryomodule meeting 6
• SPS environment
General
OC, 2/August/2013 LHC Crab Cryomodule meeting 7
• SPS environment
General
OC, 2/August/2013 LHC Crab Cryomodule meeting 8
• SPS :• 2 (identical) cavities in a cryomodule• 3 different cryomodules
General
OC, 2/August/2013 LHC Crab Cryomodule meeting 9
• SPS :• 2 (identical) cavities in a cryomodule• 3 different cryomodules
General
OC, 2/August/2013 LHC Crab Cryomodule meeting 10
• SPS :• 2 (identical) cavities in a cryomodule• 3 different cryomodules
General
OC, 2/August/2013 LHC Crab Cryomodule meeting 11
• SPS :
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 12
• SPS :
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 13
• SPS :
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 14
• SPS dummy beam pipe :
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 15
LHC configurationSPS configuration
• SPS - dummy beam pipe :• Dummy LHC beam pipe at 194mm horizontally
from the SPS beam pipe• Dummy beam pipe can be on either side of the
cavity but preference opposite to Y chamber
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 16
• SPS - dummy beam pipe :• Dummy LHC beam pipe at 194mm horizontally
from the SPS beam pipe• Dummy beam pipe can be on either side of the
cavity but preference opposite to Y chamber
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 17
• SPS - dummy beam pipe :• Dummy LHC beam pipe at 194mm horizontally
from the SPS beam pipe• Dummy beam pipe can be on either side of the
cavity but preference opposite to Y chamber
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 18
• SPS – Y chamber apperture:• With new Y chamber (510 mm aperture),
SPS cryomodule transverse dimensions coherent to LHC => could allow similar SPS/LHC basic solutions for tuner, coupler position
• SPS cryomodule design should not be over-constrained
• Baseline: replacing the existing SPS Y chamber
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 19
• SPS interfaces:• Connexions to main coupler
• From top, vertically
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 20
• SPS interfaces:• Connexions to main
coupler • Limit risk of loads
transmitted directly to the cavity from connection to RF module – Double walled tube could be used as part of the supporting system of the cavity
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 21
• SPS interfaces:• Connection to cryo
• From top, vertically for main circuits• N2 warm return may be sidewise
Geometrical constraints
OC, 2/August/2013 LHC Crab Cryomodule meeting 22
helium tank
crab cavity
common pumping collector
thermal screen at ~80 Kcryostat interface
CWT
Power coupler intercept
CWT
• LHC - Alignment requirements (position accuracy and position stability) – based on general beam dynamics considerations:• Transverse rotation per cavity should be less than 5 mrad• Transverse misalignment per cavity (in both planes) should
be less than 0.7 mm• Cavity tilt with respect to the longitudinal axis should be
less than 1 mrad• Cavity longitudinal misalignment should be less than 10
mm
• Active alignment will be studied in a dedicated set-up
Alignment
OC, 2/August/2013 LHC Crab Cryomodule meeting 23
• SPS • Alignment required for operation less than LHC
• To limit SPS crymodule complexity (win time and limit risk)• No active alignment needed for SPS tests • Foresee a system for monitoring the cavity
positions instead
Alignment
OC, 2/August/2013 LHC Crab Cryomodule meeting 24
• Operated at 2 K saturated helium bath -> ~30 mbar• Two circuits: 2 K and 80 K• Main interface from the top with 4 main lines
(LHe IN, GHe pumping, 80 K IN and 80 K OUT):• internal pipes welded, external envelope bolted
Process & instrumentation
OC, 2/August/2013 LHC Crab Cryomodule meeting 25
helium tank
crab cavity
common pumping collector
thermal screen at ~80 Kcryostat interface
CWT
Power coupler intercept
CWT
See Krzysztof’s talk
• 80 K screening will be provided with He or LN2• Power couplers and Cold/Warm Transitions
intercepts at 80 K, then outgoing gas directed to recovery line
Process & instrumentation
OC, 2/August/2013 LHC Crab Cryomodule meeting 26
helium tank
crab cavity
common pumping collector
thermal screen at ~80 Kcryostat interface
CWT
Power coupler intercept
CWT
• In general: maximize instrumentation for the prototypes• Minimum instrumentation requirements:
• Gauge for helium level measurement from the bottom through the phase separator to be installed for each helium tank (LT x 2)
• Pressure measurement on the saturated helium bath (PT x 1)• Temperature measurement on the bottom each helium tank
(suggested CERNOX type transducer, TT x 2)• Electrical heaters of 50 W on each helium tank (EH x 2)
Process & instrumentation
OC, 2/August/2013 LHC Crab Cryomodule meeting 27
helium tank
crab cavity
common pumping collectorthermal screen at ~80 K
cryostat interface
CWT
Power coupler intercept
CWT
SKETCH
LT PT
EH
TT
EH
TT
LT
• Temperature measurement on 80 K screen line (TT x 2 on inlet and outlet)
• Instrumentation for 80 K intercept circuits – definition underway• JT valve and sub-cooling HX are foreseen to be installed out of
the cryostat • All sub atmospheric instrumentation/safety devices with ambient
air interface will have to be equipped with appropriated helium guard.
Process & instrumentation
OC, 2/August/2013 LHC Crab Cryomodule meeting 28
helium tank
crab cavity
common pumping collector
thermal screen at ~80 Kcryostat interface
CWT
Power coupler intercept
CWT
SKETC
HLT PT
EH
TT
EH
TT
LT
• Pumping collector sizing (recommended 100mm dia)• Gas speed lower than 5 m/s• Min 50 mm for level regulation, additional buffer
for ~ 20 min of operation• Compatibility with safety devices for pressure limit
requirements to be confirmed
Piping sizing
OC, 2/August/2013 LHC Crab Cryomodule meeting 29
0 20 40 60 80 100 1200.001.002.003.004.005.006.007.008.00
Pumping collector gas speed *
Level of liquid in the double phase line [mm]
He g
as sp
eed
[m/s
]
92
* Calculation done assuming: collector diameter of 100 mm, He mass flow = 2 g/s, GHe temp = 2 K, GHe press = 20 mbar.
100 mm~90 mm
0 mm
Liquid level
~50 mmRegulation
maxi: 5 m/s
• Helium tank to be dimensioned correctly to extract maximum heat load • Heat flux in He II depend on bath temp. and
channel dimension
Helium tank sizing
OC, 2/August/2013 LHC Crab Cryomodule meeting 30
• Helium tank to be dimensioned correctly to extract maximum heat load • If helium cross section expected to
extract (order of magnitude) 1 W/cm2 => detailed calculations needed
• Minimize reasonably the liquid helium volume (max. 40 L/cavity if possible)
Helium tank sizing
OC, 2/August/2013 LHC Crab Cryomodule meeting 31
Heat load budget
OC, 2/August/2013 LHC Crab Cryomodule meeting 32
HL per cryomodule HL @2 K [W] HL @ 80 K
(TS) Comment
Dynamic
Deflecting mode 5.0 - Confirmed? Other Order
Modes TBD TBD
RF Coupler TBD TBD Beam Current 0.5 Tentative
Static
Radiation (cavity +Phase Sep. Cold surface + Thermal
Shield
0.2 6.8
Rescaling from LHC o W/ m2 @ cold mass
o 1.7 W/ m2 @ Thermal shield
CWT
0.557(rad) + 0.892(cond) =
1.5W x 2 = 3.0
0.625(rad) + 5.926 (cond) =
6.6W x 2 = 12.6
1 heat intercept @ 80K in the middle
Supporting System 1.0 3.3 6 tie rods/cavity
RF Coupler
0.501(rad) + 0.853(cond) =
1.4W x 2 = 2.7
0.587(rad) + 5.662 (cond) =
6.3W x2 = 12.6
1heat intercept @ 80K in the middle
Cables & Instrumentation 1.0 - Tentative
Other order modes TBD TBD Design dependent
Totals ~13.4 + TBD ~34.9 +TBD
• Given its designated function, we are in the presence of ‘high safety relevance’ equipment, i.e., special equipment according to CERN’s SR-M;
• The HSE Unit Safety Commission shall give clearance from design’s release to commissioning;
• A Safety File with all relevant technical documentation to be approved by the Safety Commission shall be prepared from day 1 (EDMS);
Safety equipment
OC, 2/August/2013 LHC Crab Cryomodule meeting 33See talk of Luis
• Two design strategies are possible: to EN Standards or to ASME Section VIII + specific technical requirements;
• Combined design (EN+ASME) can be accepted if justified;
• Design shall target the hydrostatic test pressure of 2.6 bar (abs, helium vessel);
• Equivalent to EN conventional material grades are preferred;
• ‘Non-conventional’ material properties are to be demonstrated by testing.
Safety equipment
OC, 2/August/2013 LHC Crab Cryomodule meeting 34
• Helium tank material not imposed; however titanium involves
• More complex interfaces • Not covered by the Harmonised
European Standards
• Stainless steel flanges (1.4429, AISI 316LN) for beam pipe interface
• Equivalent to EN conventional material grades are preferred
Materials
OC, 2/August/2013 LHC Crab Cryomodule meeting 35
• Static magnetic field shielding required• The field to be below 1 µT at the outer
surface of the cavity • Numerical simulations to determine the
material thickness and specification, as well as geometry
Magnetic shielding
OC, 2/August/2013 LHC Crab Cryomodule meeting 36
• Integration into cryostat at CERN - most likely location SM18
Cryostating
OC, 2/August/2013 LHC Crab Cryomodule meeting 37
• SPS cryomodule:• Expected 3 different conceptual designs
by the end of the year
• Collaboration with regular working sessions to merge CERN requirements and LARP/UK effort
• CERN is ready to help with several competencies
Concluding remark
OC, 2/August/2013 LHC Crab Cryomodule meeting 38