capm - convert vce to pdf for free, download for all · capm number : ca0-001 passing score : 800...

201
CAPM Number : CA0-001 Passing Score : 800 Time Limit : 120 min File Version : 1.0 http://www.gratisexam.com/

Upload: dokhanh

Post on 02-Apr-2018

221 views

Category:

Documents


3 download

TRANSCRIPT

CAPM

Number: CA0-001Passing Score: 800Time Limit: 120 minFile Version: 1.0

http://www.gratisexam.com/

Exam A

QUESTION 1A scope management plan in which of the following scope management processes is the scope managementplan prepared

A. InitiationB. Colllect requirementsC. Define ScopeD. Verify Scope

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 2On what is project baseline development established?

A. Approved product requirementsB. Estimated project cost and schedule C. Actual project cost and scheduleD. Revised Project cost and schedule

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 3Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangiblecomponents of each deliverable are all part of which of the following

A. Work breakdown structure B. Organizational breakdown structureC. Resource breakdown structureD. Bill of materials

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 4What is the definition of project plan execution?

A. Integrating all planned activities B. Performing the activities included in the planC. Developing and maintaining the plan

D. Execution of deliverables

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 5what is a tool to improve team performance?

A. Staffing planB. External feedbackC. Performance reportsD. Co-location

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 6Which type of analysis is used to develop the communications management plan?

A. ProductB. Cost benefitC. Stakeholder D. Research

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 7Information distribution involves making needed information available to project stackholders in a timelymanner. What is an output from information distribution?

http://www.gratisexam.com/

A. Earned value analysisB. Trend analysisC. Project records D. Peformance reviews

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 8which type of analysis is used to examine project results through time to determine if performance is improvingor deterioring?

A. Control chartB. Earned ValueC. VarianceD. Trend

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 9You are assigned to implement the project control plan. What should you do to ensure the plan is effective andcurrent?

A. Perform periodic project performance review B. Identify quality project standardsC. Follow ISO 9000 quality standardsD. Complete the quality control checklist

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 10Which of the following is an example of risk symptom?

A. Failure to meet intermediate milestones B. Force of nature, such as a floodC. Risk threshold targetD. Crashing front loading or fast tracking

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 11During what process is the quality policy determined?

A. InitiatingB. ExecutingC. PlanningD. Controlling

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 12What is one of the MAJOR outputs of activity sequencing?

A. Responsibility assignment matrixB. Work breakdown structureC. Project network diagramD. Mandatory dependencies list

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 13Scope verification is PRIMARLY concerned with which of the following?

A. Acceptance of the work deliverablesB. Accuracy of the work deliverablesC. Approval of the scope statementD. Accuracy of the work breakdown structure

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 14Which of the following is an example of contract administration?

A. Negociating the ontractB. Authorizing contractor workC. Developing the statement of workD. Establishing evaluation criteria

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 15Who MUST know when a risk event occurs so that a response can be implemented?

A. CustomersB. Project sponsorC. Project management teamD. Insurance claims department

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 16A work package has been scheduled to cost $1.000 to complete, and was to be finished today. As of today, theactual expenditure is $1.200 and approximately half of the work has been completed.Was is the cost variance?

A. -$700B. -$200C. +$200D. +$500

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 17How is quality control performed?

A. By identifying quality standards that are relevant to the project and determing how to satisfy them.B. By monitoring specific project results in compliance with relevant quality standards and determining

corrective actions as neededC. By ensuring that the entire project team has been adequately trained in quality assurance prosessesD. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure conformance

to quality standards.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 18As part of mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost.You should calculate the forecast using which of the following methods?

A. BACB. EACC. ETCD. WBS

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 19How is scheduled variance calculated using the earned value technique?

A. EV less ACB. AC less PVC. EV less PVD. EV less PV

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 20The project management processes in the PMBOK Guide should

A. Always be applied uniformlyB. Be selected as appropriate by the sponsorC. Be selected as appropriate by project teamD. Be applied based on ISO guidelines

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 21Who is responsible for determining which processes from the Process Groups will be employed and who will beperforming them?

A. Project sponsor and project managerB. Project sponsor and functional managerC. Project manager and project teamD. Project team and functional manager

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 22Which of the following processes is necessary to ensure that the project employs all prosses needed to meet itsrequirements

A. Perform Quality ControlB. Quality PolicyC. Perform Quality AssuranceD. Quality Planning

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 23Which process occurs within the monitoring and controlling Process Group?

A. Cost ControlB. Quality Planning C. Quantitative Risk AnalysisD. Cost Budgeting

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 24The Define Scope Process is in which of the following process groups ?

A. Initiating

B. PlanningC. Monitoring & controllingD. Executing

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 25Which activity is an input to select sellers process?

A. Organizational process assetsB. Resource availabilityC. Change control processD. Team Performance assessment

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 26What name(s) is (are) associated with the Plan-Do-Check –Act-Cycle?

A. ParetoB. IshikawaC. Shewart – DemingD. Delphi

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 27Which of the following methods is a project selection technique?

A. FlowchartingB. Earned ValueC. Cost-benefit analysisD. Pareto Analysis

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 28While implementing an approved change, a critical defect was introduced. Removing the defect will delay theproduct delivery. What is the MOST appropriate approach to managing this situation?

A. Utilize the change control processB. Crash the schedule to fix the defectC. Leave the detect in and work around it.D. Fast-track the remaining development.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 29which tool is used to develop technical details within the project managemet plan?

A. Expert JudgmentB. Project Management MethodologyC. Project Management InformationD. Project Selection Methods

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 30Which of the following are outputs of the Monitor and Control Project Work process?

A. Requested changes, forecast, recommended corrective actionsB. Forecast, resources plan, bottom up estimatingC. Recommended corrective actions, cost baseline, forecasts.D. Requested changes, recommended corrective actions, project constraints.

Correct Answer: ASection: (none)

Explanation

Explanation/Reference:

QUESTION 31Which tool or technique measures performance of the project as it moves from project initiation through projectclosure?

A. Resource levelingB. Parametric measuringC. Pareto chartD. Earned Value

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 32 An input required to develop a preliminary project scope statement is:

A. Organizational structureB. Organizational Process AssetsC. Organizational matrixD. Organizational Breakdown Structures

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 33The product scope description is used to:

A. Gain stakeholder ‘s support for the projectB. Document the characteristics of the projectC. Describe the project in great detailD. Formally authorize the project.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 34What are the identified risks for doing excessive decomposition in a WBS?

A. Insufficient project funding and disqualification of sellers

B. Insufficient project funding and ineffective use of resourcesC. Disqualification of sellers an non-productive management effortsD. Non-productive management effort and inefficient use of resources

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 35Which of the following techniques is used during Control Scope?

A. Cost-Benefit AnalysisB. Variance AnalysisC. Reserve AnalysisD. Stakeholder Analysis

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 36Which is the document that presents a hierarchical project organization?

A. WBSB. CPIC. OBSD. BOM

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 37Which of the following inputs is required for the WBS creation?

A. Project Quality PlanB. Project Schedule NetworkC. Project Schedule NetworkD. Project Scope Management Plan

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 38Which of the following are inputs to activity Definition?

A. Project Scope Statement and Work Breakdown StructureB. Activity List and Arrow DiagramC. Change Requests list and organizational Process assetsD. Project Management Plan and Resource Availability

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 39Activity resource requirement and resource breakdown structure are outputs from what Project TimeManagement Process?

A. Schedule ControlB. Activity DefinitionC. Schedule DevelopmentD. Activity Resources Estimating

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 40Project scope statement and resource calendars are inputs to what Project Time Management process?

A. Activity SequencingB. Activity Resource EstimatingC. Schedule DevelopmentD. Schedule Control

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 41Which of the following tools or techniques is used for Estimate Activity Duration?

A. Critical pathB. Rolling waveC. PDMD. Parametric

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 42Which activity duration estimating technique incorporates additional timing for contingency purposes?

A. Analogous EstimatingB. Expert JudgmentC. Optimistic EstimatesD. Reserve Analysis

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 43Which of the following schedule network analysis techniques is applied when a critical path method calculationhas been completed and resources availability is critical?

A. Applying calendarsB. Resource LevelingC. Resource PlanningD. Resource Conflict Management

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 44Which of the following outputs from the schedule control process aids in the communication of SV, SPI or anyperformance status to stakeholders?

A. Performance organizations

B. Schedule baselinesC. Performance measurementsD. Change requests

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 45Which technique is utilized in the Schedule Control Process?

A. Performance MeasureB. Baseline ScheduleC. Schedule ComparisonD. Variance Analysis

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 46Cost Baseline is an output of which of the following processes?

A. Cost ControlB. Cost BudgetingC. Cost EstimatingD. Cost Planning

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 47Analogous Cost Estimating relies on which of the following techniques?

A. Expert JudgmentB. Project Management SoftwareC. Vendor Bid AnalysisD. Reserve Analysis

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 48The project budget is set at $150,000. The project Duration is planned be one year. At the completion of week16 of the project, the following information is collectedActual cost $50,000Plan cost $45,000Earned Value $40,000What is the cost performance index

A. 0.80B. 0.89C. 1.13D. 1.25

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 49The PV is $1000, EV is $2000 and AC is $1500. What is CPI

A. 1.33B. 2.00C. 0.75D. 0.5

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 50At the end of the project, what will be the value of SV

A. PositiveB. ZeroC. NegativeD. Greater than one

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 51Which is one of the determining factors used to calculate CPI?

A. EVB. SPI

C. PVD. ETC

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 52Based on the following metrics EV $20,000, AC $22,000 and PV $ 28,000 what is the project CV.

A. -$8,000B. -$2,000C. $2,000D. $8,000

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 53What does a CPI value greater than 1.0 indicate

A. Cost right at the estimated valueB. Cost under the estimated valueC. Cost right at the actual valueD. Cost over the estimated value

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 54Which type of tool would be used for the quality planning activity?

A. Schedule AnalysisB. Checklist AnalysisC. Assumption AnalysisD. Cost Benefit Anaysis

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 55Another name for an Ishikawa diagram is:

A. Cause and effect diagramB. Control ChartC. FlowchartD. Histogram

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 56Which type of control tool identifies whether or not a process has a predictable performance

A. Cause and effect diagramB. Control Charts C. Pareto ChartD. Histogram

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 57Which quality control technique illustrates the 80/20 Principle.

A. Ishikawa diagramB. Control ChartC. Run ChartD. Pareto Chart

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 58Which of the following is an input to Develop Human Resource Plan?

A. Team performance assessmentB. Roles and responsabilitiesC. Staffing management planD. Enterprise environments factors

Correct Answer: DSection: (none)

Explanation

Explanation/Reference:

QUESTION 59Which of the following is an input to the Qualitative Risk Analysis Process?

A. Risk RegisterB. Risk data quality assessmentC. Risk CategorizationD. Risk Urgency

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 60Which technique is commonly used for the Quantitative Risk Analysis activity?

A. BrainstormingB. Strategies for opportunitiesC. Decision Tree AnalysisD. Risk Data Quality Assesmet

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 61Which of the following strategies is used to deal with risk that may have a negative impact on projectobjectives?

A. Exploit B. ShareC. EnhanceD. Transfer

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 62Which of the following is a strategy to deal with positive risks or opportunities?

A. Mitigate

B. TransferC. ExploitD. Avoid

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 63A weighting system is a tool for which area of procurement?

A. Plan contractingB. Request Seller responsesC. Select sellersD. Plan purchase and acquisition

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

http://www.gratisexam.com/

QUESTION 64Projects contracts generally fall into which of the following three broad categories?

A. Fixed-price cost reimbursable, time and materialsB. Make-or-buy, margin analysis, fixed priceC. Make-or-buy, margin analysis, fixed priceD. Make-or-buy, lump-sum, cost-plus –incentive

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 65Which of the following choices is a contract closure tool or technique?

A. Contract planB. Procurement planC. Clousure processD. Procurement audits

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 66Which of the following is a project constraint?

A. Twenty-five percent sataff turnover is expectedB. The technology to be used is cutting-edgeC. Project leadership may change due to volatile political environmentD. The product is needed in 250 days.

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 67A project Management office (PMO) manages a number of aspects, including what?

A. Project scope, schedule, cost, and quality of the products of the work packagesB. Central coordinator of communication management across projects, and for the delivery of specific project

objectives, organization opportunity assessmentC. Assigns projects resources to best meet project objectivesD. Overall risk, overall opportunity and interdependencies among projects.

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 68Which of the following correctly explains the term (Progressive elaboration) ?

A. Changing project specifications continuoslyB. Elaborate tracking of the project progressC. Elaborate tracking of the project specifications with a change control systemD. Project specifications becoming more explicit and detailed as the project progresses

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 69What is a function of the project managemet office (PMO) ?

A. To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tiedto the parent organizations or the clients overall business objectives.

B. To coordinate and manage the procurement of projects relevant to the parent organizations businessobjectives and to administer the project charters accordingly

C. To administer performance reviews for the project manager and the project team members and to handleany personnel and payroll issues.

D. To focus on the specified project objectives and to manage the scope, schedule, cost and quality of thework packages.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 70A project manager is responsible for managing which of the following at the project level?

A. MethodologyB. StandardsC. ConstraintsD. Interdependencies

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 71Company A is launching a new communications satellite system. Resource B was assigned combined projectsof design, construction, integration, and launch of the satellite.Resource B s roles is that of a

A. Project managerB. Portfolio managerC. Work breakdown managerD. Program manager

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 72Which of the following defines a characteristic of a project?

A. RepetitiveB. UniqueC. No outcome

D. Permanent

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 73Initiating, planning, executing. Monitoring and controlling and closing are called:

A. Process groupsB. Phase gatesC. Knowledge areasD. Project phases

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 74Which of the following is the definition of a project?

A. Temporary endeavor undertaken to create a temporary business process or productB. Temporary endeavor undertaken to create a unique product service or result.C. Permanent endeavor that produces repetitive outputsD. Temporary endeavor that produces repetitive outputs

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 75The project Management Body of Knowledge (PMBOK Guide) should be considered as

A. Guide to project management processes tools and techniquesB. Methodology for managing projects.C. Guide for project, portfolio and program managementD. Standard for project, portfolio and program management.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 76Which of the following is a Process Group?

A. ScopingB. BudgetingC. ClosingD. Quality

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 77In which type of organizational structure are staff members grouped by specialty?

A. FunctionalB. ProjectizedC. MatrixD. Balanced

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 78Which of the following statements best describes the influence of stakeholders and the cost of changes asproject time advances?

A. The influence of stakeholders increases, the cost of changes increasesB. The influence of stakeholders decreases the cost of changes increasesC. The influence of stakeholders increases the cost of changes decreasesD. The influence of stakeholders decreases the cost of changes decreases

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 79Projects can be divides into phases to provide better management control. Collectively, what are these phasesknown as?

A. Complete project phaseB. Project lifeC. The project life cycleD. Project Cycle

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 80In an organization with a projectized organizational structure, who controls the project budget?

A. Functional managerB. Project managerC. Program managerD. Project management office

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 81At which of the project is the uncertainty the highest and the risk of failing the greatest?

A. Final phase of the projectB. Start of the projectC. End of the projectD. Midpoint of the project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 82When do stakeholders have the greatest influence?

A. At the start of the projectB. At the end of the projectC. During executionD. Stakeholders have constant influence

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 83Which of the following provides a comprehensive and consistent method of controlling the project and ensuringits success?

A. Stakeholder managementB. Monitoring and controllingC. Project governanceD. Project management methodology

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 84Company A is delivering a product in three parts. The contract allows for the parts to be delivered either oneafter other or at the same time.Which type of project phasing will allow for the most flexibility in the delivering the full product when productrequirements are subject to rapid change?

A. Sequencing the delivery phases one after otherB. Overlapping the delivery phasesC. Delivering the products iterativelyD. Delivering all of the products at the same time.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 85In which type of organization does a project manager have a moderate-to-high resource availability?

A. FunctionalB. Weak

C. BalancedD. Strong

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 86Which Stakeholder is responsible for managing related projects in a coordinated way?

A. Sponsor B. Portfolio ManagerC. Program managerD. Project manager

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 87In which of the following organizational structures does the project manager have full authority on a project?

A. FunctionalB. Strong MatrixC. Balanced MatrixD. Projectized

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 88What are three basic types of project phase-to-phase relationships?

A. Sequential, Overlapping, Non –OverlappingB. Sequential, Iterative, OverlappingC. Sequential, Non-overlapping, IterativeD. Iterative, Overlapping, Non-Overlapping

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 89Which is a true statement regarding project governance?

A. Project governance approach must be described in the project management plan.B. Project governance is independent of the organization or program sponsoring it.C. Once a project has begun, it is not necessary to formally initiate each project phaseD. Review of project performance and key deliverables is not required for each project phase.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 90A project manager has limited authority in which type of organizational structure?

A. Weak matrixB. FunctionalC. Balanced matrixD. Projectized

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 91Which of the following is an input to direct and manage project execution?

A. Requested changesB. Approved preventive actionC. Work performance informationD. Implemented defect repair

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 92Who selects the appropriate processes for a project?

A. Project stakeholdersB. Project sponsor and project stakeholderC. Project manager and project teamD. Project manager and project sponsor

Correct Answer: CSection: (none)

Explanation

Explanation/Reference:

QUESTION 93A project becomes officially authorized when which of the following occurs?

A. Project manager is appointedB. Stakeholders approve the project C. Project charter is approvedD. Project sponsor approves the project.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 94How is the process of collecting requirement defined?

A. Defining and documenting project sponsors needs to meet the project objectivesB. Defining and documenting stakeholders needs to meet the project objectivesC. Defining and documenting the project teams needs to meet the project objectivesD. Defining and documenting the project needs to meet the project objectives

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 95Monitor and control project work is a process of which of the following knowledge areas?

A. Project risk management.B. Project scope managementC. Project time managementD. Project integration management

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 96Which process group can be performed outside the projects scope of control?

A. Planning B. Monitoring and control

C. ClosingD. Initiating

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 97The procurement document is an input to which of the following processes?

A. Develop Project Management PlanB. Develop ScheduleC. Identify StakeholdersD. Determine Budget

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 98Which of the following is involved in the initiation process group?

A. Develop Project Management PlanB. Identify StakeholdersC. Plan CommunicationsD. Collect Requirements

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 99Which of the following is defined by a projects life cycle and varies by application area?

A. ProductB. Product oriented processesC. Project management process groupsD. Project management process groups

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 100How many knowledge areas are there according to PMBOK Guide?

A. 5B. 8C. 9D. 12

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

Exam B

QUESTION 1Perform quality assurance belongs to which of the following process groups?

A. PlanningB. ExecutingC. Monitoring and controlD. Closing

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Differences Between QA (Quality Assurance) & QC (Qu ality Control)

Suppose you are manufacturing Coke. QA would ensure that you have all the right processes in place tomanufacture and test the quality of the coke. Like the machines , people, recording mechanism etc. QC isdoing the actual testing on finished product. So when the coke bottle is out you do a sample test and it wouldeither pass or fail the Q standards.

So QC is to do with testing and verification after the deliverable is done and QA is before the deliverable ismade. Like giving trainings to people, Auditing the process, ensuring everyone understands the process etc areall QA activities.

QUESTION 2A project team is in which of the following processes when they finalize all activities across all of themanagement process groups to formally complete the project?

A. ClosingB. ExecutingC. Monitoring ControllingD. Monitoring Controlling

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 3Which process groups defines the course of action required to attain the objectives that the project wasundertaken to achieve?

A. InitiatingB. ExecutingC. PlanningD. Monitoring and Controlling

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 4How many process groups are there according to the PMBOK Guide?

A. 5B. 9C. 10D. 12

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 5The Monitoring and controlling process group contains which of the following processes?

A. Plan QualityB. Perform Quality AssuranceC. Perform Quality ControlD. Identify Stakeholders

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Differences Between QA (Quality Assurance) & QC (Qu ality Control)

Suppose you are manufacturing Coke. QA would ensure that you have all the right processes in place tomanufacture and test the quality of the coke. Like the machines , people, recording mechanism etc. QC isdoing the actual testing on finished product. So when the coke bottle is out you do a sample test and it wouldeither pass or fail the Q standards.

So QC is to do with testing and verification after the deliverable is done and QA is before the deliverable ismade. Like giving trainings to people, Auditing the process, ensuring everyone understands the process etc areall QA activities.

QUESTION 6Which Process group establishes the total scope of a project?

A. InitiatingB. PlanningC. Monitoring and ControllingD. Executing

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 7Who must accept the end product for a project to be considered closed?

A. Project TeamB. Project managerC. Project management officeD. Customer or sponsor

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 8Manage Project Team belongs to which knowledge area?

A. Project Integration ManagementB. Project Time ManagementC. Project Procurement ManagementD. Project Human Resource Management

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Project Human Resource Management includes the processes required to make the most effective use ofthe people involved with the project. It includes all the project stakeholders—sponsors, customers, individualcontributors, and others.

QUESTION 9Where are product requirements and characteristics documented?

A. Product scope descriptionB. Project charterC. Preliminary project scope statementD. Communications management plan

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 10

What are the formal and informal policies, procedures, and guidelines that could impact how the projects scopeis managed?

A. Organizational process assetsB. Enterprise environmental factorsC. Project management processesD. Project scope management plan

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The fourth edition PMBOK® defines Organizational Process Assets as “any or all process related assets,from any or all of the organizations involved in the project that can be used to influence the project’s success.”Examples include: plans, procedures, lessons learned, historical information, schedules, risk data and earnedvalue data. Organizational Process Assets fall into two broad categories—Processes and Procedures, andthe Corporate Knowledge Base. The key concept is that these are assets a project manager may use for thebenefit of the project. They work together with Enterprise Environmental Factors (EEF’s) to bring those thingsoutside the project team into focus.

QUESTION 11Which of the following is an input to the Direct and Manage Project Execution Process?

A. Approved corrective actionsB. Approved contract documentationC. Work Performance informationD. Rejected change requests

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 12Which of the following consists of the detailed project projects scope statement and its associated WBS andWBS dictionary?

A. Scope PlanB. Product scopeC. Scope management planD. Scope baseline

Correct Answer: DSection: (none)Explanation

Explanation/Reference:The Scope Management Plan only tells you how to manage the scope – how the requirements are collected,how are they documented, how are they verified, prioritised, updated, changed etc. But the scope managementplan itself is never part of the Scope Baseline. It is the other way round - The Scope Baseline is part of theScope Management Plan.

The Scope Management Plan only tells you how to manage the scope – how the requirements are collected,

how are they documented, how are they verified, prioritised, updated, changed etc. But the scope managementplan itself is never part of the Scope Baseline. It is the other way round - The Scope Baseline is part of theScope Management Plan.

QUESTION 13What scope definition technique is used to generate different approaches to execute and perform the work ofthe project?

A. Build vs buyB. Expert judgmentC. Alternatives IdentificationD. Product analysis

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 14The scope management plan is a subsidiary of which project document?

A. Schedule management planB. Project management planC. Quality management planD. Resource management plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:The Scope Management Plan only tells you how to manage the scope – how the requirements are collected,how are they documented, how are they verified, prioritised, updated, changed etc. But the scope managementplan itself is never part of the Scope Baseline. It is the other way round - The Scope Baseline is part of theScope Management Plan.

The Scope Management Plan only tells you how to manage the scope – how the requirements are collected,how are they documented, how are they verified, prioritised, updated, changed etc. But the scope managementplan itself is never part of the Scope Baseline. It is the other way round - The Scope Baseline is part of theScope Management Plan.

QUESTION 15What type of project structure is hierarchically organized depiction of the resources by type?

A. What type of project structure is hierarchically organized depiction of the resources by type?B. Resource Breakdown structure (RBS)C. Work Breakdown Structure (WBS)D. Project Breakdown Structure (PBS)

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

A Resource Breakdown Structure (RBS) is used to create an hierarchical list of the resources. There areorganizational and geographical RBS. Activity lists, resource calendar, and resource estimating are the majorRBS tools.Resource Breakdown Structure or RBS is an integral part of any effective project management in geneal andresource management in particular. Managing any project means organizing project resources and projectcomponents, such as the project team members, to ensure that they are strategically productive throughout thelifecycle of the project.

RBS ToolsActivity List — creating a list of all the project-based activities and every conceivable information about them.This includes the usual resources employed by the listed activities.Resource Calendar — making a list of diverse resources regarding their availability over a period of time toascertain whether they can be assigned for particular projects.Resource Estimating — making estimates regarding the variety/volumes of resources that would be employedfor each defined activity in the most cost-effective and productive manner.

QUESTION 16What cause replanning of the project scope?

A. Requested changesB. Project scope statement changesC. Variance analysisD. Approved change requests

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 17which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

A. WBS directoryB. Activity listC. WBSD. Project schedule

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Work breakdown structure , WBS, is a project management technique initially developed by the US DefenseEstablishment, which deconstructs a project with the intent to identify the deliverables required to complete theproject. The project management work breakdown structure, WBS, is utilized at the beginning of the project todefine the scope, estimate costs and organize Gantt schedules.Work breakdown structure, WBS, captures all the elements of a project in an organized fashion. Breaking downlarge, complex projects into smaller project pieces provides a better framework for organizing and managingthe project. WBS can facilitate resource allocation, task assignment, responsibilities, measurement and controlof the project.

QUESTION 18What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the projectobjectives and create the required deliverables?

A. Organizational Breakdown Structure (OBS)B. Work Performance informationC. Work PackageD. Work Breakdown Structure (WBS)

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Work breakdown structure , WBS, is a project management technique initially developed by the US DefenseEstablishment, which deconstructs a project with the intent to identify the deliverables required to complete theproject. The project management work breakdown structure, WBS, is utilized at the beginning of the project todefine the scope, estimate costs and organize Gantt schedules.Work breakdown structure, WBS, captures all the elements of a project in an organized fashion. Breaking downlarge, complex projects into smaller project pieces provides a better framework for organizing and managingthe project. WBS can facilitate resource allocation, task assignment, responsibilities, measurement and controlof the project.

QUESTION 19What component of the project scope definition defines project exclusions?

A. Project boundariesB. Project constraintsC. Project assumptionsD. Project objectives

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The boundaries of a project are measurable and auditable characteristics that define what belongs to theproject and what doesn’t belong to it. Project boundaries are closely linked to project objectives, they create aholistic perception of project work, and they define the content of the project in terms of expected results. Aclear boundary statement helps direct the things that are applicable to those areas within the project scope.

EXAMPLE An organization is going to sell office equipment within The United States. It makes an agreement with adomestic US distributor. This agreement actually states a project for selling office equipment. The boundariesof this project will affect US operations only. All other locations are out of scope (that is out of the definedboundaries).

QUESTION 20What tool and technique is used to determine whether work and deliverables meet requirements and productacceptance criteria?

A. DecompositionsB. BenchmarkingC. InspectionD. Checklist analysis

Correct Answer: CSection: (none)Explanation

Explanation/Reference:The term inspection refers to one of the most critical elements of the entire process that surrounds theexecution and successful completion of a given project. The term inspection refers specifically to the act inwhich the project management team, project management team leader, or other interested and significantparties take the effort to go review the entirety of the project in meticulous detail to determine whether or not theproject meets certain predetermined requirements for completion.

QUESTION 21Which of the following is an output of Define Scope?

A. Project document updatesB. Project management planC. Scope baselineD. Product analysis

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The Define Scope process involves defining detailed description of the project and major deliverables. TheInput, Tools and Techniques and Output of the Define Scope process are:

QUESTION 22What is an output of Control Scope?

A. Accepted deliverablesB. Work performance measurementsC. Requirements documentationD. Work performance information

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Control Scope process involves monitoring the status of project and managing scope changes. The Inputs,Tools and Techniques and Outputs of Control Scope process are:

QUESTION 23The decomposition technique is used to do which of the following?

A. Subdivide the estimated cost of individual activitiesB. Subdivide project deliverables and project work into smaller, more manageable componentsC. Relate the work packages to the performing organizational units.D. Shorten the project schedule duration and the amount of resources needed.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 24A project manager needs the project team to make group decision. Which of the following is a method that canbe used to reach a group decision?

A. Expert judgmentB. MajorityC. SWOT analysisD. Brainstorming

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 25Decompositions is a tool and technique used in which of the following?

A. Define Scope and Define ActivitiesB. Collect Requirements and Estimates Activity ResourcesC. Create WBS and Define ActivitiesD. Create WBS and Estimate Activity Duration

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 26Which of the following is a tool or technique of the Collect Requieremets process?

A. Group decision making techniquesB. Project management information systemC. Alternative identificationD. Communication requirement analysis

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 27Which of the following is an input to collect Requirements?

A. Stakeholder registerB. Requirements documentationC. PrototypesD. Organizational process assets

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Collect Requirements process involves documenting stakeholders needs to meet project objectives. TheInputs, Tools and Techniques, and Outputs of Collect Requirements process are given below.

QUESTION 28The use of group creativity techniques as a tool and technique is done in which of the following processes?

A. Plan qualityB. Collect RequirementsC. Define ScopeD. Perform Quality Control

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 29Which is an input of the collect Requirements process?

A. Requirement documentationB. Organizational process assetsC. Requirements management planD. Stakeholder register

Correct Answer: DSection: (none)

Explanation

Explanation/Reference:

QUESTION 30Which of the following can be used to track the requirements throughout the project life cycle?

A. Requirements traceability matrixB. Scope management planC. Project charterD. Work breakdown structure

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Requirements Traceability Matrix

Defining the RTMThe Requirements Traceability Matrix (RTM) is a tool to help ensure that the project’s scope, requirements, anddeliverables remain “as is” when compared to the baseline. Thus, it “traces” the deliverables by establishing athread for each requirement- from the project’s initiation to the final implementation.

The diagram shows that the RTM can be used during all phases of a project to:· Track all requirements and whether or not they are being met by the current process and design· Assist in the creation of the RFP, Project Plan Tasks, Deliverable Documents, and Test Scripts

· Help ensure that all system requirements have been met during the Verification process.The Matrix should be created at the very beginning of a project because it forms the basis of the project’sscope and incorporates the specific requirements and deliverables that will be produced.

How do you create an RTM? In each of the steps shown above, each requirement must be unique and clearly defined. The requirement isthen part of each critical component of the project. The references throughout the entire process must beconsistent and unique. In order to insure that this occurs, the Matrix traces each requirement and creates arelationship between each of the processes

Req#: Requirement Number; for each project requirement, begin to list them on the RTM in a numerical orderand group them by function.Name: Enter the name and brief description of the requirementRFP #: Request For Proposal (RFP); specify the identification number of the requirement as listed in the RFP.DDD #: Deliverable Definition Document (Also referred to as the Deliverable Expectation Document- DED);use the RFP requirement number as areference for the DDD that is created for the requirement. PPT #: List the MS Project Subtask and Task numbers that are associated with the requirement.TS #: Test scripts should be prepared for the actual testing process.Verification: Use this field to record completion of the signoff process

QUESTION 31Which of the following is an example of a group creativity technique?

A. Delphi techniqueB. UnanimityC. ObservationD. Presentation Technique

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The Delphi Method is an information gathering technique that was created in the 1950s by the RANDCorporation. The Delphi Method is based on surveys and makes use of the information of the participants, whoare mainly experts. By using this method, you can get qualitative and quantitative results. The expert surveysare conducted over multiple rounds until a consensus is reached. After each round, feedback is provided, whichencourages convergence of thought. A key point to note about the Delphi Technique is that while gatheringthoughts, the participants do not know who the other participants are. Hence, participants are not influenced byothers taking part in the process.

Uses of the Delphi Method in Project ManagementAs you might already suspect, the Delphi Method has many uses in project management. You can use theDelphi Method for any activity that requires the convergence of expert thought, such as in:

Risk Management: For identifying risks and quantifying risks.Time Management: For estimating stories or work activities.

QUESTION 32Which process includes facilitated workshops as a tool and technique?

A. Collect RequirementsB. Plan communicationsC. Develop Project TeamD. Report Performance

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 33Which of the following is a tool or technique used to verify scope?

A. Product analisys B. Ishikawa diagramC. InspectionD. Requirements Traceability Matrix

Correct Answer: CSection: (none)Explanation

Explanation/Reference:The term inspection refers to one of the most critical elements of the entire process that surrounds theexecution and successful completion of a given project. The term inspection refers specifically to the act inwhich the project management team, project management team leader, or other interested and significantparties take the effort to go review the entirety of the project in meticulous detail to determine whether or not theproject meets certain predetermined requirements for completion.

QUESTION 34Inspection is a tool and technique for wich of the following processes?

A. Create WBSB. Define Scope

C. Control scopeD. Verify Scope

Correct Answer: DSection: (none)Explanation

Explanation/Reference:The term inspection refers to one of the most critical elements of the entire process that surrounds theexecution and successful completion of a given project. The term inspection refers specifically to the act inwhich the project management team, project management team leader, or other interested and significantparties take the effort to go review the entirety of the project in meticulous detail to determine whether or not theproject meets certain predetermined requirements for completion.

QUESTION 35What is the lowest level in the WBS at which the cost and activity durations for the work can be reliablyestimated and managed?

A. Work ProductB. Work PackageC. Project deliverableD. Scope Baseline

Correct Answer: BSection: (none)Explanation

Explanation/Reference:A work package is a portion of the work breakdown structure that allows project management to define thesteps necessary for completion of the work package. A work package can be thought of as a mini project, thatwhen combined with other work package units, form the completed project. An individual work packagecontains essential steps involved in completion of the work package along with a deadline by which each of thesteps must be completed in order for project management to stay on track. A work package may in itself bethought of as a deliverable. Work packages allow for simultaneous work on many different components of aproject at the same time by multiple teams. Each team follows the steps defined in the work package andcompletes them by the specified deadline. When all teams have finished their individual work packages, thewhole project comes together with seamless integration. Completion of a work package is most often overseenby a specific person whether it is a manager, supervisor, team leader, or a designated team member. A workpackage is usually the bottom tier of the project management process. Related term: control account.

QUESTION 36Many organizations categorize requirements into which of the following two categories

A. Project and productB. Staffingand BudgetC. Stakeholder and CustomerD. Business and Technical

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 37Plurality is a type of which of the following?

A. Group creativity techniquesB. Group decision making techniquesC. Facilitated workshopsD. Prototypes

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 38Which of the followings events would result in a baseline update?

A. Your project is behind schedule and you want your baseline to reflect estimated actual completionB. Your customer has approved a change request broadening the project scope and increasing the budgetC. One of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.D. One of your key project team resources has left your team and no replacement is available

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 39Which Schedule compression technique has phases or activities done in parallel that would normally have beendone sequentially

A. CrashingB. Fast TrackingC. Leads and lags adjustmentD. Parallel task development

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Fast tracking means that you look at activities that are normally done in sequence and assign them insteadpartially in parallel. If you were fast-tracking, you would start constructing the solution in areas where you felt thedesign was pretty solid without waiting for the entire design to be completed.

"Crashing" the schedule means to throw additional resources to the critical path without necessarily getting thehighest level of efficiency. For instance, let’s say one person was working on a ten-day activity on the criticalpath. If you were really desperate to shorten this timeframe, you might add a second resource to this activity.

Similarities are:1) Both the approaches are aimed at reducing the schedule2) Both the approaches require addition of resources to achieve the goal3) Even though fast tracking doesn't mention the term Critical Path, it's obvious that the Critical Path tasks needto be done in parallel to reduce the schedule. So, both the approaches involve changes to Critical Pathactivities schedule.

QUESTION 40Wich Schedule development technique modifies the project schedule to account for limited resources?

A. Human resource planningB. Fast TrackingC. Critical Chain methodD. Rolling Wave planning

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Critical Chain Project Management (CCPM): According to PMBOK Critical chain method is a schedule network analysis technique that modifies the projectschedule to account for limited resources. It mixes deterministic and probabilistic approaches to schedulenetwork analysis. The critical chain concept was coined by Eliyahu Goldratt. Following few sections brieflydescribe the concepts Critical Chain depends on and are useful to understand the example that will followshortly after that.

QUESTION 41Which schedule development tool and technique produces a theoretical early start date late start date?

A. Critical Path methodB. Variance analysisC. Schedule comprenssionD. Schedule Comparison bar chart

Correct Answer: ASection: (none)

Explanation

Explanation/Reference:Critical Path Method (CPM): The Critical Path Method (CPM) is a schedule network analysis technique. CPM was developed by the DuPontCorporation in 1957.Critical path determines the shortest time to complete the project and it is the longestduration path through a network of tasks. Critical tasks (activities) are tasks (activities) on the critical path. To understand CPM further let's first understand nature of the task. According to PMBOK every scheduled taskcan be defined by the following four parameters. • Early Start (ES): Earliest possible point in time on which a task can start. • Early Finish (EF): Earliest possible point in time on which a task can finish. • Late Start (ES): Latest possible point in time on which a task can start. • Late Finish (EF): Latest possible point in time on which a task can finish.

Early Start and finish dates are calculated by means of Forward Pass and Late Start and Late Finish dates arecalculated by means of Backward Pass. Many Tasks have some amount of buffer added to them referred asSlack Time or Float. Float time is amount of time a task can slip before it delays project schedule. There aretwo common types of floats.

• Free Float: Amount of time a single task can be delayed without delaying the early start of any successortask. • Total Float: Amount of time a single task can be delayed without delaying project completion.

Mathematically Float is defined as: Float = LS - ES or LF - EF.

Critical path has zero or negative Total Float. A project can have several critical paths

QUESTION 42What is the minimum a project schedule must include?

A. Variance analysisB. A planned start date and a planned finish date for each schedule activityC. A critical path diagramD. Critical chain analysis

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 43What cost control technique is used to compare actual project performance to planned or expectedperformance?

A. Cost aggregationB. Trend AnalysisC. ForecastingD. Variance analysis

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Earned value is the Actual Amount of Work Accomplished whereas Variance Analysis is the Differencebeween the Amount of Work Planned and the Work actually accomplished. Variance Analysis is applicable(computed) to the triple constrains in the project i.e. you have 3 Variance Analyses: For A) Scope B) ScheduleC) Cost where as Earned Value is generally calculated for Cost. That is why you see variance Analysis as anoutput on all 3 KAs where as You see EV Analysis as an output only in the Cost Management

QUESTION 44Using the following data, what is the Schedule Performance Index (SPI)?EV= $500PV=$750AC=$1000BAC=$1200

A. 0.67B. 1.50C. 0.75D. 0.50

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Schedule performance Index (SPI) = EV/PV is an indicator whether the project is on time (SPI = 1) or behindthe schedule(<1).

Cost performance Index (CPI) = EV/AC is an indicator whether the project is incurring expenses more than(CPA<1)/less than(CPI >1)/ equal to (CPI = 1)

QUESTION 45Which enterprise enviromental factors are considered during cost estimating?

A. Marketplace conditions and commercial databasesB. Marketplace conditions and company structureC. Commercial databases and company structureD. Existing human resources and market place conditions

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 46Which process involves aggregating the estimated cost of the individual schedule activities or work packages?

A. Cost baselineB. Cost forecastingC. Cost varianceD. Cost budgeting

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 47What is the schedule performance index (SPI) using the following data?BAC=$ 100,000PV=$50,000AC=$80,000EV=$40,000

A. 1.00B. 0.40C. 0.50D. 0.80

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Schedule performance Index (SPI) = EV/PV is an indicator whether the project is on time (SPI = 1) or behindthe schedule(<1).

Cost performance Index (CPI) = EV/AC is an indicator whether the project is incurring expenses more than(CPA<1)/less than(CPI >1)/ equal to (CPI = 1)

QUESTION 48The project manager calculated a schedule performance index 0.80 and a cost performance index 1.1 for theproject. What is the actual status of this project?

A. Behind the schedule and over budgetB. Behind the schedule and under budgetC. Ahead of schedule and under budget D. Ahead of schedule and over budget

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Schedule performance Index (SPI) = EV/PV is an indicator whether the project is on time (SPI = 1) or behindthe schedule(<1).

Cost performance Index (CPI) = EV/AC is an indicator whether the project is incurring expenses more than(CPA<1)/less than(CPI >1)/ equal to (CPI = 1)

QUESTION 49EAC (Estimate and complete) is typically based on actual cost (AC) for work completed plus and ETC(Estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?

A. EAC= AC + [(BAC-EV)/(CUMULATIVE CPI* CUMULATIVE SPI)]B. EAC= BAC - ACC. EAC= 1-CPID. EAC =EV + [1-(CUMULATIVE CPI* CUMULATIVE SPI)/BAC]

Correct Answer: ASection: (none)Explanation

Explanation/Reference:There are 4 types of EAC forecast calculation formulas available, but confused when to use each type.

EAC = BAC / CPIEAC = ETC + ACEAC = (BAC-EV) + ACEAC = [BAC-EV / spi * cpi] + AC

ExplanationEAC = AC + Bottom up ETC -- Used when original estimate is fundamentally flawedEAC = BAC / Cumulative CPI - Used if no variances have occured and same rate of spending will continueEAC = AC + (BAC- EV) - Used when variances are atypical /irregularEAC = AC + ( BAC-EV / Cumulative CPI * Cumulative SPI) - Used when variances are typical(regular).Assumes poor cost performance

QUESTION 50Which of the following equations is used to calculate schedule variance?

A. EV/PVB. PV/EVC. EV-PVD. PV-EV

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Schedule Variance Formula Schedule Variance is calculated as follows:

Schedule Variance = Earned Value – Planned Value

Earned Value is also known as Budgeted Cost of Work Performed (BCWP). And Planned Value is also knownas Budgeted Cost of Work Scheduled (BCWS). So you may see the formula written as: Schedule Variance = BCWP - BCWS

What does Schedule Variance mean?The result of the Schedule Variance formula is a number. So what does this number mean? A value of less than zero means the project is behind schedule.And a value greater than zero means the project is ahead of schedule.(A value of zero means the project is exactly on schedule but this is very rare).

Exam C

QUESTION 1Which tool and technique uses a statical relationship between historical data and other variables to calculateestimates?

A. Analogous estimatingB. Three-poit estimatesC. Parametric estimatingD. Bottom-up estimating

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Parametric Estimating: Refers, primarily, to an estimation technique which utilizes the statistical relationshipthat exists between a series of historical data and a particular delineated list of other variables. Some examplesof these variables include square footage in a contraction project, the number of lines or code that exist in asoftware application, and other similar variables. This information is them implemented for the purposes ofcalculating and demonstrating an estimate for the entity of activity parameters. One valuable aspect ofparametric estimating is the higher levels of accuracy that can be built into it depending on how sophisticatedthe original data that was built into the estimate turns out to have been.

Analogous Estimating I t is also known as "Top Down" Estimation.It uses estimations from previous activities to estimate future durations. The validity of duration estimatesderived using this method depends on:- historical information- similarity of the historical projects- expert judgement

Three Point Estimation : is a technique used to estimate the time required for a project based on historicalinformation. This includes:Most Optimistic:Best case scenario in which nothing goes wrong and all conditions are optimal.Most Likely:The most likely duration and there may be some problem but a lot will go right.Most Pessimistic: The worst case scenario which everything goes wrong.

Bottom-Up Cost Estimation Is *An estimating the cost for each work package in the WBS.*The most accurate method but it is also the most challenging, costly and time consuming.

QUESTION 2Which of the following equations is used to calculate cost variance?

A. EV-ACB. AC-EVC. AC+EVD. AC/EV

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Cost Variance (CV) Is very important factor to measure project performance. Cost Variance (CV) indicateshow much over or under budget the project is.Cost Variance can be calculated as using the following formula

Cost Variance (CV ) = Earned Value (EV) - Actual Cost (AC)

OR

Cost Variance (CV) = BCWP - ACWP

The formula mentioned above gives the variance in terms of cost which will indicate how less or more cost hasbeen to complete the work as of date.

Positive Cost Variance Indicates the project is under budgetNegative Cost Variance Indicates the project is over budget

Cost Variance %Cost Variance % indicates how much over or under budget the project is in terms of percentage.Cost Variance % can be calculated as using the following formula

CV % = Cost Variance (CV) / Earned Value (EV)

OR

CV % = CV / BCWP

The formula mentioned above gives the variance in terms of percentage which will indicate how much less ormore money has been used to complete the work as planned in terms of percentage.

Positive Variance % indicates % under Budget.Negative Variance % indicates % over Budget.

QUESTION 3Given the following values, what is the calculated expected activity cost (CE) when using PERT?CO= $7,000CM= $10,500CP= $11,000

A. $4,750B. $9,500C. $10,000D. $11,500

Correct Answer: CSection: (none)Explanation

Explanation/Reference:CE = (CO + 4CM + CP)/6

QUESTION 4What is the expected activity cost for a projecct having a most likely cost of $140, a best case scenario of $115,and a worst case scenario of $165?

A. $115B. $138C. $140D. $165

Correct Answer: CSection: (none)Explanation

Explanation/Reference:EC=(140+115+165)/3

QUESTION 5What does a SPI value greather than 1.0 indicates?

A. Most work was completed than plannedB. Less work was completed than plannedC. Cost overrun for completed work has occurredD. Cost underrun for completed work has occurred

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Schedule performance Index (SPI) = EV/PV is an indicator whether the project is on time (SPI = 1) or behindthe schedule(<1)

QUESTION 6Total funding requirements and periodic funding requirements are derived from:

A. Funding limit reconciliationB. Scope baselineC. Activity cost estimatesD. Cost baseline

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 7What is the status of the project whose data is shown in the following S-curve?

A. Under budge and ahead of scheduleB. Over budget and behind scheduleC. Over budget and ahead of scheduleD. Under budget and behind schedule

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 8In the earned Value EV is $1000, actual cost AC is $800, and planned Value PV is $1500, what would be thecost performance index CPI

A. 0.66B. 0.8C. 1.25D. 1.5

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Cost performance Index(CPI) = EV/AC is an indicator whether the project is incurring expenses more than(CPA<1)/less than(CPI >1)/ equal to (CPI = 1)the budget allotted at that stage.

QUESTION 9Control, charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and techniques of whatprocess?

A. Perform Quality ControlB. Perform Quality AssuranceC. Quality planning

D. Performance Reporting

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 10Which Tool and technique identifies inefficient and ineffective policies, processes and procedures?

A. scope auditsB. Scope reviewsC. Quality AuditsD. Contro Chart

Correct Answer: CSection: (none)Explanation

Explanation/Reference:A quality Audit is an independent evaluation, inspection or review of a project's quality assurance system toimprove quality performance of a project.

The audits can take place at scheduled or random intervals.The result of a quality audit (eg lesson learned) are important for the current project as well as for later projectsor other parts of the organisation.

QUESTION 11What quality control tool graphically represents how various elements of a system interrelate?

A. Control chartB. FlowchartC. Run ChartD. Pareto Chart

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Flowchart shows the sequence of events and flow of inputs and outputs. It also shows the elements between aprocess or system.

It gets a definite beginning and end along with decision points clearly called out. This can be done with theactions to take based on the result of each decision.

QUESTION 12Which tool and technique of quality planning involves caomparing actual or planned practices to those of otherprojects to generate ideas for improvement and provide a basis by which to measure performance?

A. HistogramB. Quality auditsC. BenchmarkingD. Performance measurements analysis

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

Benchmarking is a tool used in Quality Planning. It Addresses the evaluation of a group's business or projectpractices- In comparison to those of other groups. - Identify best practics- In order to meet them

QUESTION 13In which domain of project management would a Pareto chart provide useful information?

A. Scope ManagementB. Time ManagementC. Communications ManagementD. Quality Management

Correct Answer: DSection: (none)Explanation

Explanation/Reference:A Pareto diagram/chart helps focus attention on the most critical issues.

It prioritises potential "causes" of the problems.

It is referred to as 80/20 rule that 80% of problems or defects are most often due to 20% of the causes.

QUESTION 14What is the primary benefit of meeting quality requirements?

A. Quality MetricsB. Less reworkC. Quality control measurementsD. Benchmarking

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 15What is the ame of the statiscal method that helps identify which factors may influence specific variables of aproduct or process under development or in production?

A. Failure modes and effects analysisB. Design of experimentsC. Quality ChecklistD. Risk analysis

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Design of Experiment (DOE) is:a technique to systematically identify varying levels of independent variables.It determines:

*which variable has the greatest effect.*what is the relationship between each variable and the quality specifications (with customer focused).*What is the best value for each variable, ensuring optimal quality or value.

QUESTION 16What is the term assigned to products or services having the same functional use but different technicalcharacteristics?

A. ScopeB. QualityC. SpecificationD. Grade

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Grade is “a category or rank used to distinguish items that have the same functional use (e.g., “hammer”), butdo not share the same requirements for quality (e.g., different hammers may need to withstand differentamounts of force)”.

QUESTION 17Which of the following provides a basis for assessing project performance?

A. Profitability and impact matrixB. Expert JudgmentC. BenchmarkingD. Risk Categorization

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Benchmarking is a tool used in Quality Planning. It Addresses the evaluation of a group's business or projectpractices- In comparison to those of other groups.

- Identify best practics- In order to meet them

QUESTION 18Regardless of style, what information is shown in a process flowchart?

A. Actions, decision points, and process driversB. Activities, decision points, and the order of processingC. Activities, process drivers, and the order of processingD. Actions, decision points, and activities

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Flowchart shows the sequence of events and flow of inputs and outputs. It also shows the elements between aprocess or system.

It gets a definite beginning and end along with decision points clearly called out. This can be done with theactions to take based on the result of each decision.

QUESTION 19Which quality assurance tool and technique confirms the implementation of approved change requests,corrective actions, defect repairs, and preventive actions?

A. Quality checklistsB. Quality MetricsC. Quality audits D. Process analysis

Correct Answer: CSection: (none)Explanation

Explanation/Reference:A quality Audit is an independent evaluation, inspection or review of a project's quality assurance system toimprove quality performance of a projectThe audits can take place at scheduled or random intervals.

The result of a quality audit (eg lesson learned) are important for the current project as well as for later projectsor other parts of the organisation.

QUESTION 20Which tool technique uses the 80/20 principle?

A. Pareto ChartB. Cause and effect diagramsC. Control ChartsD. Flowcharting

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

A Pareto diagram/chart helps focus attention on the most critical issues.

It prioritises potential "causes" of the problems.

It is referred to as 80/20 rule that 80% of problems or defects are most often due to 20% of the causes.

QUESTION 21What is cost of nonconformance?

A. ReworkB. InspectionsC. TrainingsD. Testings

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Cost of Non-Conformance

>>However, if there is a choice made not to conduct quality activities, there is a potential for costs associatedwith any resulting problems. These costs are referred to as the costs of non-conformance. This is money spentbecause of failures.>>Costs of non-conformance can include things such as payments made out on warranties, re-work or scrap,and/or damage to reputation.

QUESTION 22What is included in a control chart?

A. BaselinesB. Planned ValueC. Upper specification limitD. Expenditure

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Control Charts are graphs used to analyse and communicate the variability of a process (or project activity)over time.

The components include the process mean the Upper Control Limit (UCL) and the Lower Control Limit (LCL).Data points within this range are generally though of as "In Control".

QUESTION 23What tool and technique includes all cost incurred over the life of a product by investment in preventingnonconformance to requirements?

A. Cost of quality B. Measure of designC. Satatical controlD. Systematic analysis

Correct Answer: ASection: (none)Explanation

Explanation/Reference:COST OF QUALITY: CoQ can be defined as the costs associated with not creating a quality product. Inproject management, CoQ needs to be consider while estimating costs and performing Life-Cycle Costing(LCC).

Total Cost of Quality = External Failure + Internal Failure + Appraisal + Prevention Costs

External Failure Costs. These are associated with problems found in the product or service after the customerhas received it. For example, technical support calls, investigation of customer complaints, product refunds and recalls, lostcustomer goodwill, warranty costs, and liability costs.

Internal Failure Costs. These are associated with defects that have been found before giving the product orservice to the customer. For example, bug fixes, regression testing, wasted resource time, and rework.

Appraisal Costs. These are associated with finding quality problems. For example, inspection, testing, andaudits.

Prevention Cost. These are activities that are performed to prevent poor quality. For example, process reviews,quality improvement team, training, usability analysis, and collecting requirements.

QUESTION 24In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08, and 12. For the entireprocess, the goal is 10 and the standard deviation is 1. For this data set, it is correct to say that the process:

A. Is under controlB. Is out of control

C. Has increasing trendD. Has decreasing trend

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 25In which tool and technique is possible to find a correlation between dependent and independent variables?

A. Fishbone diagramB. Control chartC. Run chartD. Scatter diagram

Correct Answer: DSection: (none)Explanation

Explanation/Reference:This is one of the Tools and Techniques of the Perform Quality Control.

Scatter diagrams use two variables, one called an independent variable, which is an input, and one called adependent variable, which is an output. Scatter diagrams display the relationship between these two elementsas points on a graph.

The important thing to remember about scatter diagrams is that they plot the dependent and independentvariables and the closer the points resemble a diagonal line, the closer these variables are related.

QUESTION 26A project manager arranges for project specific training for the new team members. Under which category doesthis cost fall?

A. AppraisalB. Internal failureC. External failureD. Prevention

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 27Which of the following describes the purpose of the quality control process?

A. To identify quality requirements of the projectB. To identify ineffective processes and eliminate themC. To assess performance and recommend necessary changesD. To ensure quality standards are used

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 28What is an objective of the Developing Project Team Process?

A. Feelings of trust and improved cohesivenessB. Ground rules for interactionC. Enhanced resource availabilityD. Functional managers become more involved

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 29Which tools or techniques will the project manager use for developing the project team?

A. NegotiationB. Roles and responsabilitiesC. Recognition and rewardsD. Prizing and promoting

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 30When managing a project team, what helps to reduce amount of conflict?

A. Clear role definitionB. NegotiationC. Risk response planningD. Team member replacement

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 31Conflicts should be best addressed in which manner?

A. Early, in private, using a direct, collaborative approachB. Early, in plublic, using a indirect, collaborative approachC. Early, in private, using a indirect, cooperative approachD. As late as possible, in public, using a direct, confrontational approach

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 32What is the name of a graphic display of project team members and their reporting relationships?

A. Role dependencies chartB. Reporting flow diagramC. Project organization chartD. Project team structure diagram

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Organization Chart : A project organization chart is a graphic display of project team members and theirreporting relationships.

QUESTION 33Whitin a matrix organization, dual reporting of team members is a risk for project success. Who is responsiblefor managing this dual reporting relationship factor?

A. Functional managerB. Project ManagerC. Functional manager supported by the project managerD. Project management office

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Manage Project TeamManage Project Team involves tracking team member performance, providing feedback, resolving issues, andcoordinating changes to enhance project performance. The project management team observes teambehavior, manages conflict, resolves issues, and appraises team member performance. As a result ofmanaging the project team, the staffing management plan is updated, change requests are submitted, issuesare resolved, input is given to organizational performance appraisals, and lessons learned are added to theorganization's database.

Management of the project team is complicated when team members are accountable to both a functionalmanager and the project manager within a matrix organization (Section 2.3.3). Effective management of thisdual reporting relationship is often a critical success factor for the project, and is generally the responsibilityof the project manager.

QUESTION 34What provides information regarding the ways people, teams, and organizational units behave?

A. rganizational chartB. Organizational theoryC. Organizational StructureD. Organizational Behavior

Correct Answer: BSection: (none)

Explanation

Explanation/Reference:Refers to all the theories that attempt to explain what makes people, teams and work units perform the waythey do. I'll talk more motivation techniques (which are a type of organizational theory). "Developing the projectTeam." Organizational theory improves the probability that planning will be effective and helps shorten theamount of time it takes to produce the Develop Human Resource Plan outputs.

QUESTION 35In which of the following team development stages does the team meet and learn about the project an theirformal roles and responsibilities?

A. FormingB. StormingC. NormingD. Performing

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 36Which of the following is a technique for resolving conflict?

A. CollaborationB. Issue logC. LeadershipD. Motivation

Correct Answer: ASection: (none)Explanation

Explanation/Reference:CONFLICT RESOLUTION TECHNIQUES

Withdrawing or Avoiding : Here, the project manager simply chooses to avoid the conflict, and allows thepersons involved in conflict to find their own solution. No action is taken by the project manager.Smoothing or Accommodating: Here, the project manager is involved in the conflict, tries to avoid areas ofdisagreements, and focuses on commonalities. Smoothing is a way to avoid tough discussions.Compromising: It is a mid-way approach. Here, everybody loses and gain something. All parties get some sortof satisfaction. It is a lose-lose approach.Forcing: Here, decision is taken in favor of one’s viewpoint at the expense of others. It can demoralize theteam member and may cause to increase the conflicts. It is a win-lose approach.Collaborating : This is an example of win-win approach. Here, the project manager will work with all parties tofind a resolution that involves multiple viewpoints and negotiate for the best solution. This technique reinforcesmutual trust and commitment.Problem Solving or Confronting: Here, a conflict will be treated as a problem for which project manager hasto find a solution. The project manager will conduct an in-depth root cause analysis of the reason for theoccurrence of the conflict, encourage open discussions to allow parties to express their areas of disagreement,and then arrives at a solution.

QUESTION 37Which of the following is a conflict resolving technique that emphasizes areas of agreement rather than areasof difference?

A. Withdrawing/ AvoidingB. ForcingC. CollaboratingD. Smoothing/acommodating

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

Withdrawing or Avoiding : Here, the project manager simply chooses to avoid the conflict, and allows thepersons involved in conflict to find their own solution. No action is taken by the project manager.Smoothing or Accommodating: Here, the project manager is involved in the conflict, tries to avoid areas ofdisagreements, and focuses on commonalities. Smoothing is a way to avoid tough discussions.Compromising: It is a mid-way approach. Here, everybody loses and gain something. All parties get some sortof satisfaction. It is a lose-lose approach.Forcing: Here, decision is taken in favor of one’s viewpoint at the expense of others. It can demoralize theteam member and may cause to increase the conflicts. It is a win-lose approach.Collaborating : This is an example of win-win approach. Here, the project manager will work with all parties tofind a resolution that involves multiple viewpoints and negotiate for the best solution. This technique reinforcesmutual trust and commitment.Problem Solving or Confronting: Here, a conflict will be treated as a problem for which project manager hasto find a solution. The project manager will conduct an in-depth root cause analysis of the reason for theoccurrence of the conflict, encourage open discussions to allow parties to express their areas of disagreement,and then arrives at a solution.

QUESTION 38In which of the team development stages are the teams interdependent and work through issues smoothly andeffectively?

A. NormingB. FormingC. StormingD. Performing

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 39The resource calendars document is an output of which process?

A. Estimate Activity ResourcesB. Acquire Project TeamC. Develop ScheduleD. Develop Project Team

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 40In which of the following team development stages does the team begin to work together, develop trust, andadjust the work habits and behavior?

A. Norming B. FormingC. StormingD. Performing

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 41Project team members begin to address the project work and technical decissions. The project team is in whichof the following stages of team development?

A. StormingB. FormingC. NormingD. Performing

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 42Placing many or all of the most active project team members in the same physical location to enhance theirability to perform as a team is called which of the following?

A. Team trainingB. Co-locationC. Team locationD. Organizatin training

Correct Answer: BSection: (none)Explanation

Explanation/Reference:co-location represents an organizational technique in which the location of team members is determined in astrategic way to maximize productivity

QUESTION 43Emphasizing areas of agreement rather than areas of difference is part which of the following conflictmanagement techniques?

A. Smoothing B. CompromisingC. AvoidingD. Forcing

Correct Answer: ASection: (none)

Explanation

Explanation/Reference:

QUESTION 44Which knowledge area is concerned with the process required to ensure timely and appropriate generation,collection, distribution, storage, retrieval, and ultimate disposition of project information?

A. Project integration managementB. Project communications managementC. Project Information Management System (PIMS)D. Project scope Management

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 45Which of the following involves making information available to project stakeholders in a timely manner

A. Contract managementB. Performance reportingC. Project status reportsD. Information Distribution

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 46Forecasts, requested changes, recommended corrective actions, and organizational process asset updates areall outputs of which process?

A. Risk response planningB. Risk monitoring and controllingC. Performance reportingD. Manage stakeholders

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Performance Reporting is:The process of gathering and communicating information regarding the current status of a project as well asprojections for progress over time.Durng performance reporting:

Information regarding the work being accomplishedresources being used is collected, analysed and displayed in various report formats.

QUESTION 47Which of the folowing is contained within the communications management plan

A. An organizational chartB. Glossary of common terminologyC. Organizational Process assetsD. Enterprise enviromental factors

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 48Which knowledge area employs the processes required to ensure timely and appropriate generation, collection,distribution, storage, retieval, and ultimate disposition of project information?

A. Project Risk ManagementB. Project Integration Management

C. Project Communications ManagementD. Project Quality Management

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 49Approved change requests, approved corrective actions, and updates to organizational process assets are alloutputs of which project management process?

A. Risk response planningB. Manage stakeholdersC. Scope definitionD. Performance reporting

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 50What is a technique used in the performance reporting process?

A. Expert JudgementB. Project Management methodologyC. Stakeholder analysisD. Status review meetings

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

Exam D

QUESTION 1What is the number of stakeholders, if the project 28 potential communication channels?

A. 7B. 8C. 14D. 16

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Number of communication channels with “n” members = n*(n-1)/2

QUESTION 2What information does the stakeholder register contain?

A. Communication modelB. Identification informationC. Communication MethodD. Identification Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 3Stakeholder analysis identifies what information and realtes it to the purpose of the project?

A. Requirements, influence, and functional departmentB. Interest, requirements, and functional role.C. Requirements, expectations, and influenceD. Interest, expectations, and influence

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 4Which of the following is a tool or technique to the Manage Stakeholder Expectations Process?

A. Issue logB. Change registerC. Stakeholder registerD. Interpersonal skills

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 5When using the Delphi technique for gathering information, what forecasting method is being used?

A. Time series methodB. Casual methodC. Econometric methodD. Judgment method

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 6Which of the following is one of the key components of the basic communications model?

A. PushB. DecodeC. Pull D. Duration

Correct Answer: BSection: (none)Explanation

Explanation/Reference:The elements in this model are:

• Encode: To translate thoughts or ideas into a form of language that can be understood by the receiver; eg,written English, spoken French or a drawn diagram.• Message: What is sent: the output of encoding• Medium: The method used for sending the message (face-to-face, telephone, email)• Noise: Something that interferes with the sending or understanding of the message (distance, culture,language differences)• Decode: The translation of the message by the receiver from the medium into their thoughts.

A single communication is complete once the feedback-message has been decoded by the sender andchecked for accuracy against the original idea. Once this loop has been closed both people have a commonunderstanding of the idea. This does not require agreement or concurrence, but if there is to be adisagreement, it helps if everyone has the same basic understanding of the issue or idea in dispute.

Effective communication requires both the sender and the receiver to be engaged.

QUESTION 7Which of the following is a tool or technique for distribute information?

A. Project management plan B. Report performanceC. Communications requirements analysisD. Communication methods

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 8A project manager convenes a meeting to determine why the time to produce one product accordingspecifications has increased from one day to three days over the past months. Which tool or technique is usedin this case?

A. Expert judgmentB. Quality assuranceC. Quality controlD. Variance analysis

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 9There are seven members on the project team not counting the project manager and the sponsor. How manycommunication channels are there?

A. 21B. 28C. 36D. 42

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Number of communication channels with “n” members = n*(n-1)/2

QUESTION 10ABC project is a risk for failling to achieve a major project objective due to unresolved stakeholder issues.Team member morale is low.Who is primrily responsible for the project being a risk?

A. Team members who have low moraleB. Sponsor who is not actively supporting the projectC. Project manager who is responsible for managing stakeholder expectationsD. Stakeholders who have unrealistic expectations

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 11When communicating with large audiences, which communication method works most effectively?

A. PushB. InteractiveC. ParallelD. Pull

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Interactive Communication Interactive communication is the most efficient method of communication toensure a common understanding as it is real time.Interactive communication should be used when an immediate response is required and when thecommunication is sensitive or likely to be misinterpreted.

Push Communication Push communication is communication that is delivered by the sender to the recipients.

While the communication can be confirmed that it was sent, it does not necessarily mean it was received andunderstood. Push communication should be used when the recipients need the information but it does notrequire animmediate response and the communication is non-urgent or sensitive in nature.

Pull Communication Pull communication is a communication method that provides access to the informationhowever the receiver must proactively retrieve the information.Pull communication should be used when the communication is informational only. If the recipients don’t read it,it will not affect the project.

QUESTION 12What are assigned risk ratings based upon?

A. Root cause analysisB. Assessed probability and impactC. Expert judgmentD. Risk identification

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 13Which of the following processes includes prioritizing risks for subsequent further analysis or action byassessing and combining their probability of occurrence and impact?

A. Qualitative risk analysisB. Quantitative risk analysisC. Risk management planningD. Risk response planning

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Qualitative Risk AnalysisA qualitative risk analysis prioritizes the identified project risks using a pre-defined rating scale. Risks will bescored based on their probability or likelihood of occurring and the impact on project objectives should theyoccur.Probability/likelihood is commonly ranked on a zero to one scale (for example, .3 equating to a 30% probabilityof the risk event occurring).The impact scale is organizationally defined (for example, a one to five scale, with five being the highest impacton project objectives - such as budget, schedule, or quality).A qualitative risk analysis will also include the appropriate categorization of the risks, either source-based oreffect-based.

Quantitative Risk AnalysisA quantitative risk analysis is a further analysis of the highest priority risks during a which a numerical orquantitative rating is assigned in order to develop a probabilistic analysis of the project.A quantitative analysis:- quantifies the possible outcomes for the project and assesses the probability of achieving specific project

objectives- provides a quantitative approach to making decisions when there is uncertainty- creates realistic and achievable cost, schedule or scope targetsIn order to conduct a quantitative risk analysis, you will need high-quality data, a well-developed project model,and a prioritized lists of project risks (usually from performing a qualitative risk analysis)

QUESTION 14Which of the following documents allows the project manager to assess risks that may required near termaction?

A. Probability and impact matrixB. Contingency analysis reportC. Risk urgency assessmentD. Rolling wave plan

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 15Which of the following is an example of a technique used in quantitative risk analysis?

A. sensitivity analysisB. Probability and impact matrixC. Risk data quality assessmentD. Risk categorization

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Sensitivity AnalysisSensitivity analysis seeks to place a value on the effect of change of a single variable within a project byanalyzing that effect on the project plan. It is the simplest form of risk analysis. Uncertainty and risk arereflected by defining a likely range of variation for each component of the original base case estimate. Inpractice such an analysis is only done for those variables which have a high impact on cost, time or economicreturn, and to which the project is most sensitive.

QUESTION 16When does risk monitoring and control occur?

A. At project initiationB. During work performance analysisC. Throughout the life of the projectD. At project milestones

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 17A risk may be graded into different priorities by which process?

A. Risk monitoring and controllingB. Risk response planningC. Qualitative risk analysisD. Quantitative risk analysis

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 18Quality and credibility of the qualitative risk analysis prosess requires that different levels of the risk'sprobabilities and impacts be defined is the definition of what?

A. Risk breakdown Structure (RBS)B. Risk probability and impactC. Qualitative risk analysisD. Risk response planning

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 19What is one of the objectives of project risk management?

A. Decrease the probability and impact of event on the project objectivesB. Distinguish between a project risk and a project issues so that a risk mitigation plan can be put in place.C. Increase the probability and impact of positive eventsD. Removal of project risk

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 20Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

A. MitigateB. TransferC. ShareD. Avoid

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 21Taking out insurance in relation to risk management is called what?

A. TransferenceB. AvoidanceC. ExploringD. Mitigation

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 22What risk technique is used to quantify the probability and impact of risk on project objectives?

A. Expert judgmentB. Risk RegistryC. Risk response planningD. Interviewing

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Interviewing. Interviewing techniques are used to quantify the probability and impact of risks on projectobjectives. The information needed depends upon the type of probability distributions that will be used. Forinstance, information would be gathered on the optimistic (low), pessimistic (high), and most likely scenarios forsome commonly used distributions, and the mean and standard deviation for others. Documenting the rationaleof the risk ranges is an important component of the risk interview, because it can provide information onreliability and credibility of the analysis.

Probability distributions . Continuous probability distributions represent the uncertainty in values, such asdurations of schedule activities and costs of project components. Discrete distributions can be used torepresent uncertain events, such as the outcome of a test or a possible scenario in a decision tree.

Expert judgment. Subject matter experts internal or external to the organizations such as engineering orstatistical experts, validate data and techniques.

QUESTION 23What defines a portion of work included in a contract for items being purchased or acquired?

A. Procurement management planB. Evaluation CriteriaC. Work Break Structure (WBS)D. Contract Statement of Work (SOW)

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Contract Statement of Work (SOW)

Design : Details what is required in terms of physical characteristics.

Performance :Specifies measurable capabilities the end product must achieve in terms of operationalcharacteristics.

Functional: Defines what the deliverable is required to do but not necessarily how to do it. This allows theprospective sellers to offer different possible solutions for archiving the same end-use function.

QUESTION 24Which of the following is an example of the simplest fixed-price contract?

A. Purchase requisitionB. Purchase orderC. Verbal AgreegmentD. Request for quote

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 25Which of the following list contain processs

A. Plan purchases and acquisitions, plan contracting, request seller responses, select sellers.B. Plan purchases and acquisitions, request seller responses, select sellers, schedule controlC. Plan purchases and acquisitions, acquire project team, request seller responses, select sellersD. Plan purchases and acquisitions, acquire project team, contract approval, select sellers

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 26Which type of analysis is used as a general management technique within the Plan Procurements Process?

A. Risk assesment analysisB. Make or buy analysisC. Contract value analysisD. Cost impact analysis

Correct Answer: BSection: (none)

Explanation

Explanation/Reference:Make-or-Buy Analysis:Is a technique used to determine whether it would be more cost effective to produce a prudct or service in-house or from an outside vendor.Can significantly impact project time, cost, quality, scope, etc.

QUESTION 27A purchase order for a specific item to be delivered by specified date for a specified price is the simplest formof what type of contract?

A. Cost-reimbursableB. Time and materialC. Fixed Price or lump - sumD. Cost-plus-fixed-fee

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 28What is the tool and technique used to request seller responses?

A. Procurement documentsB. Expert judgmentC. Bidder conferencesD. Contract Types

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Bidder conference (also called a contractor or vendor conference)A meeting with prospective sellers to ensure all sellers have a clear understanding of the product or service tobe procured. Bidder conferences allow sellers to query the buyer on the details of the product to help ensurethat the proposal the seller creates is adequate and appropriate for the proposed agreement.

QUESTION 29A contract change control system defines which of the following?

A. Process by which the procurement is being satisfiedB. Process by which the procurement can be modifiedC. Process by which the procurement can be obtainedD. Process by which the procurement can be disposed

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 30In what type of contract is the seller reimbursed for all allowable cost for performing the contract work andreceives a predetermined fee based upon achieving certain performance objectives as set forth in the contract?

A. Cost -plus-fixed-feeB. Cost-plus-incentive-feeC. Firm-fixed-priceD. Fixed-price-incentive-fee

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Contract Types in ProcurementProcurement can generally be categorized between Fixed Price and Cost Reimbursable.

Fixed PriceFixed Price Plus Incentive Fee (FPIF) – 10000$ is paid plus for every month the work finished earlier thanschedule 1000$ will be paidFixed Price plus Award fee (FPAF) – 10000$ plus every month performance exceeds planned value 1000$ isawarded with the max award of 10000$Fixed Price Economic Price Adjustment – 10000$/ year plus a price will increase based on Consumer PriceIndex.Purchase Order – generally used for commodities

Time and Material –100$ /hr plus cost

Cost ReimbursableCost Contract – Seller receives no profit. Used by non profit organizationCost Plus Fees (CPF) or Cost plus Percentage of Cost (CPPC) – Cost plus 10% as feesCost Plus Fixed fee (CPFF) – Cost plus 10000$ in feesCost Plus Incentive Fee (CPIF) – Cost plus variable fee. Original estimate is done (target cost) and target fee isdetermined. The seller gets percentage of saving if actual cost is less than target cost based on Seller/Buyerratio.Cost Plus Award Fee (CPAF) – Cost plus fee plus award based on performance.

QUESTION 31Who decides buyer and seller roles in a teaming agreement?

A. Executive managementB. Project membersC. Project managerD. Contract administrator

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 32In which of the following contract types is a price ceiling set and any additional cost above the price ceiling

becomes the responsability of performing organization?

A. Firm-Fixed-Price Contracts (FFP)B. Fixed-Price-Incentive-Fee Contracts (FPIF)C. Cost-Reimbursable ContractorsD. Time and Material Contracts (T&M)

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Contract Types in ProcurementProcurement can generally be categorized between Fixed Price and Cost Reimbursable.

Fixed PriceFixed Price Plus Incentive Fee (FPIF) – 10000$ is paid plus for every month the work finished earlier thanschedule 1000$ will be paidFixed Price plus Award fee (FPAF) – 10000$ plus every month performance exceeds planned value 1000$ isawarded with the max award of 10000$Fixed Price Economic Price Adjustment – 10000$/ year plus a price will increase based on Consumer PriceIndex.Purchase Order – generally used for commodities

Time and Material –100$ /hr plus cost

Cost ReimbursableCost Contract – Seller receives no profit. Used by non profit organizationCost Plus Fees (CPF) or Cost plus Percentage of Cost (CPPC) – Cost plus 10% as feesCost Plus Fixed fee (CPFF) – Cost plus 10000$ in feesCost Plus Incentive Fee (CPIF) – Cost plus variable fee. Original estimate is done (target cost) and target fee isdetermined. The seller gets percentage of saving if actual cost is less than target cost based on Seller/Buyerratio.Cost Plus Award Fee (CPAF) – Cost plus fee plus award based on performance.

QUESTION 33The degree of risk shared between the buyer and seller is determined by the:

A. Contract TypeB. SponsorsC. Project ManagerD. Stakeholders

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 34Company A bought a well-defined project deliverable from Company B. Company A will pay a fixed total priceplus a percentage premium for the schedule target achieved.

For which type of contract have they subscribed?

A. Fixed-Price_Incentive_fee contracts (FPIF)B. Firm-fixed-price-Contracts (FFP)C. Fixed-Price with Economic Price Adjustment Contracts (FP-EPA)D. Time and Material Contract (T&M)

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Contract Types in ProcurementProcurement can generally be categorized between Fixed Price and Cost Reimbursable.

Fixed PriceFixed Price Plus Incentive Fee (FPIF) – 10000$ is paid plus for every month the work finished earlier thanschedule 1000$ will be paidFixed Price plus Award fee (FPAF) – 10000$ plus every month performance exceeds planned value 1000$ isawarded with the max award of 10000$Fixed Price Economic Price Adjustment – 10000$/ year plus a price will increase based on Consumer PriceIndex.Purchase Order – generally used for commodities

Time and Material –100$ /hr plus cost

Cost ReimbursableCost Contract – Seller receives no profit. Used by non profit organizationCost Plus Fees (CPF) or Cost plus Percentage of Cost (CPPC) – Cost plus 10% as feesCost Plus Fixed fee (CPFF) – Cost plus 10000$ in feesCost Plus Incentive Fee (CPIF) – Cost plus variable fee. Original estimate is done (target cost) and target fee isdetermined. The seller gets percentage of saving if actual cost is less than target cost based on Seller/Buyerratio.Cost Plus Award Fee (CPAF) – Cost plus fee plus award based on performance.

QUESTION 35Negotiated Settlements are an example of a technique used in which Project Procurement ManagementProcess?

A. Plan ProcurementsB. Conduct ProcurementsC. Administer ProcurementsD. Close Procurements

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 36Which procurement management process ensures the seller's performance meets procurement requirementsand that the buyer performs according to the terms of the legal contract?

A. Plan procurementsB. Perform Quality Assurance

C. Administer ProcurementsD. Conduct Procurements

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 37Which contract is tipically used whenever the seller's performance period spans a considerable period ofyears?

A. Fixed-Price-Incentive-Fee Contracts (FPIF)B. Fixed Price with Economics Price Adjustment contracts (FP-EPA)C. Cost-Plus-Fixed-Fee Contracts (CPFF)D. Time and Material Contracts (T&M)

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Contract Types in ProcurementProcurement can generally be categorized between Fixed Price and Cost Reimbursable.

Fixed PriceFixed Price Plus Incentive Fee (FPIF) – 10000$ is paid plus for every month the work finished earlier thanschedule 1000$ will be paidFixed Price plus Award fee (FPAF) – 10000$ plus every month performance exceeds planned value 1000$ isawarded with the max award of 10000$Fixed Price Economic Price Adjustment – 10000$/ year plus a price will increase based on Consumer PriceIndex.Purchase Order – generally used for commodities

Time and Material –100$ /hr plus cost

Cost ReimbursableCost Contract – Seller receives no profit. Used by non profit organizationCost Plus Fees (CPF) or Cost plus Percentage of Cost (CPPC) – Cost plus 10% as feesCost Plus Fixed fee (CPFF) – Cost plus 10000$ in feesCost Plus Incentive Fee (CPIF) – Cost plus variable fee. Original estimate is done (target cost) and target fee isdetermined. The seller gets percentage of saving if actual cost is less than target cost based on Seller/Buyerratio.Cost Plus Award Fee (CPAF) – Cost plus fee plus award based on performance.

QUESTION 38The project management information system is used as tools and techniques in which of the followingprocesses?

A. Develop Project CharterB. Develop Project Management PlanC. Direct and Manage Project ExecutionD. Monitor and control Project Work

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 39Final product transition is an output of which process?

A. Direct and Manage Project ExecutionB. Close Project or PhaseC. Perform Integrated Change ControlD. Monitor and Control Project Work

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 40Which of the following provides a standardized, effective, and efficient way to centrally manage approvedchanges and baselines within a project?

A. Project management information systemB. Configuration management SystemC. Change control boardD. Project management plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 41The approval of which of the following indicates formal initiation of the project?

A. Procurement management planB. Project management planC. Project Scope documentD. Project charter

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 42Which one of the following is true regarding the change control board?

A. Describes how changes are managed?B. Approves or rejects change requestsC. Needs updated project management plans to approve or reject a change.D. Describes how changes are documented

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Change control board can be referred to as a board or committee or group of stakeholder’s, that analyze andreview the change requests that have been forwarded by the project management team and accordingly takedecision whether the change request needs to be accepted or rejected.

*Consists of stakeholder’s.*Approve or reject changes.*Decisions are often accepted and considered final.*Role clearly defined.*All change requests should go through it.

QUESTION 43Which document is a narrative description of products or serices to be delivered by the project?

A. Project charterB. ContractC. Business caseD. Project statement of work

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Project Statement of WorkThe project statement of work (SOW) is a narrative description of products or services to be delivered by theproject and is provided by the project initiator or customer for external projects or the sponsor or requestingorganization for internal projects. If the project is being done for an external customer, the SOW may bereceived from the customer as part of a bid document.The SOW details the business need for the project, the product scope description, the strategic plan, and thecharacteristics of the product the project will create.

Business CaseThe business case will confirm the business need and drivers for the project and will most likely includeinformation on a cost benefit analysis, so as to justify the funding of the project, such as: net present value(NPV), internal rate of return (IRR), and/or return on investment (ROI).The business case should also reference the driver behind the project, such as: market demand, organizationalneed, customer request, technological advance, legal requirement, or social need.The business case is generally completed by the sponsor of the project.

QUESTION 44Reviewing, tracking, and regulating the process to meet performance objectives defined in the projectmanagement plan are part of which process?

A. Monitor and Control Project WorkB. Direct and Manage Project ExecutionC. Monitor and Control Risk

D. Perform Integrated Change Control

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 45Which document contains initial requirements that satisfy stakeholders needs and expectations?

A. Project charterB. Project management planC. Project statement of workD. Project scope statement

Correct Answer: ASection: (none)Explanation

Explanation/Reference:A Project Charter is a formal document that authorizes the start of a project. It names and appoints a projectmanager, assigns a summary budget, establishes a project time line, and documents key assumptions andconstraints. The project boundary, its key deliverables - the mission of the project are documented as much aspossible.

A Project management plan is the planning document, capturing the entire project end-to-end, covering allproject phases, from initiation through planning, execution and closure.

QUESTION 46The decision to approve or reject a particular change request is made in which of the following processes?

A. Perform integrated Change ControlB. Monitor and control Project workC. Develop Project Management PlanD. Direct and Management Project Execution

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 47Who authorizes a project?

A. SponsorB. Project ManagerC. Project TeamD. Buyer

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 48Providing forecasts to update current cost and schedule information is a part of which process?

A. Perform Integrated Change ControlB. Direct and Manage Project ExecutionC. Monitor and Control RisksD. Monitor and Control Project Work

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 49A business case is an input to which of the following processes?

A. Collect RequirementsB. Define ScopeC. Develop Project CharterD. Develop Project Mangement Plan

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 50What should be covered in an implementation when the change is approved?

A. Functional requirementB. Status reportC. Customer NeedD. Defect repair

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

Exam E

QUESTION 1What should be covered in an implementation when the change is approved?

A. Functional requirementB. Status reportC. Customer needD. Defect repair

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 2The project integration Management Knowledge area includes which of the following set of processes?

A. Develop project charter, direct and manage project Execution Perform integrated Change ControlB. Define Project Scope, Create WBS, Close Project or PhaseC. Develop project charter, Develop Human Resource Plan, Estimate CostD. Identify Stakeholders, plan communications, develop Project Management Plan.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 3What document should be reviewed by a project manager before finalizing the project clousure?

A. Customer acceptanceB. Statement of workC. Product reportD. User Manual

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 4Which of the following is a tool and technique for activity duration estimating?

A. Parametric estimating B. Monte Carlo AnalysisC. Top-down estimatingD. Bottom-up estimating

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Estimating techniques can be applied to resources, effort, duration, and costs. The following are differentmethods of estimating you can use, depending on the situation.

QUESTION 5Which process involves identifying and documentating the logical relationships among activities?

A. Schedule developmentB. Activity sequencingC. Create WBSD. Applying leads and lags

Correct Answer: BSection: (none)Explanation

Explanation/Reference:The Activity Sequencing process involves the identification and documentation of the logical relationshipsamong schedule activities. Schedule activities can be logically sequenced with appropriate precedencerelationships, leads and lags to enable a realistic, achievable project schedule. Sequencing may be performedusing project management software and/or manual techniques.

QUESTION 6What type of planning is used where the work to be accomplished in the near term is planned in detail, whilework in the future is planned at a higher level?

http://www.gratisexam.com/

A. Finish-to –start planningB. Rolling wave planningC. Short term planningD. Dependency determination

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Rolling wave planning is a project management technique that involves progressive elaboration to add detailto the Work Breakdown Structure (WBS) on an ongoing basis. At the beginning of the project, near termdeliverables are decomposed into individual components (work packages) and defined at the greatest level ofdetail. Deliverables and schedule activities that will take place several reporting periods in the future are morebroadly defined

QUESTION 7When would resource levelling be applied to a schedule model?

A. Before constraints have been identifiedB. Before it has been analyzed by the critical path methodC. After it has analyzed by the critical path methodD. After critical activities have been removed from the critical path

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 8Which is the duration of the project?

Task Duration Predecessor(s)

Start 0 NONE

A 6 START

B 4 START

C 7 A

D 10 A

E 8 B

F 9 D

G 11 C and E

END 0 F and G

A. 63B. 65C. 66D. 70

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 9Which tool and technique is used to sequence activities?

A. DecompositionB. Project management softwareC. Applying leads and lagsD. Expert judgement

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Leads and Lags:Leads and Lags are types of float. Let's take an example to understand this.

In project management, there are four types of dependencies:

Finish to Start (FS) - Later task does not start until the previous task is finishedFinish to Finish (FF) - Later task does not finish until the previous task is finishedStart to Start (SS) - Later task does not start until the previous task startsStart to Finish (SF) - Latter task does not finish before previous task starts

Take the scenario of building two identical walls of the same house using the same material. Let's say, buildingthe first wall is task A and building the second one is task B. The engineer wants to delay task B for two days.This is due to the fact that the material used for both A and B are a new type, so the engineer wants to learnfrom A and then apply if there is anything to B. Therefore, the two tasks A and B have a SS relationship.

The time between the start dates of the two tasks can be defined as a lag (2 days in this case).

If the relationship between task A and B was Finish to Start (FS), then the 'lead' can be illustrated as:

Task B started prior to Task A with a 'lead'.

Conclusion For a project manager, the concepts of float, lead, and lag make a lot of meaning and sense.These aspects of tasks are important in order to calculate project timeline variations and eventually the projectcompletion time.

QUESTION 10What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight,and complexity from a previous similar project as the basis for estimating the same parameter or measure for afuture project?

A. Bottom-up estimatingB. Analogous estimatingC. Parametric estimatingD. Three-point estimates

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Estimating techniques can be applied to resources, effort, duration, and costs. The following are differentmethods of estimating you can use, depending on the situation.

QUESTION 11Which schedule format usually shows both the project network logic and projects critical path scheduleactivities with activity date information?

A. Schedule TableB. Schedule network diagramC. Bar chartD. Milestone chart

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 12Which is the total float for the activity G?

A. 0B. 3C. 5D. 10

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 13Which of these are logical dependencies in a precedence diagram method?

A. End to endB. Finish-to-endC. Satrt-to-endD. Start-to-start

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

FINISH -TO- START

START-TO-START

FINISH - TO - FINISH

START -TO- FINISH

QUESTION 14In three point estimating technique, if the most likely estimates for an activity to completes is 100 days, theoptimistic estimates is 60 days and the pessimistic estimates is 200 days, what is the expected duration inwhich the activity will be completed?

A. 90 daysB. 100 daysC. 110 daysD. 660 days

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Ed= (Mop + 4Mest + Mpes)/6

QUESTION 15Which of the following techniques uses historical information to estimate the activity duration?

A. Three-point-estimatingB. Organizational process assetsC. Analogous estimatingD. Reserve analysis

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Estimating techniques can be applied to resources, effort, duration, and costs. The following are differentmethods of estimating you can use, depending on the situation.

QUESTION 16What is a specific advantage of analogous estimating in comparasion with other cost estimate techniques?

A. Uses contingency reservesB. Less costly and time consumingC. Can be applied to segments of workD. More accurate

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 17Which of the following is an output of the Estimate Activity Resources Process?

A. Alternative analysisB. Bottom-up-estimatingC. Resources breakdown structureD. Enterprise environmental factors

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 18In the precedence diagramming method, which of the following is a logical relationship for the activities?

A. Finish-to-startB. Applying leads and lagsC. Activity-on-nodeD. Dependency determination

Correct Answer: ASection: (none)Explanation

Explanation/Reference:When the work of Task 2 can start only after all the work of Task 1 is finished, the tasks have a Finish-to-Start(FS) dependency.Task 1 is the predecessor of Task 2, and Task 2 is the successor of Task 1.For example, you can start to print a manual only after it has been written.

QUESTION 19During the initial stages of the project, what do activity attributes include?

A. Activity name, dependencies, assumptionsB. Activity ID WBS ID, activity name C. Activity ID, assumptions, constraintsD. Activity name, WBS ID, activity description

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 20Which of the following is one of the tools and techniques for the Define Activities Process?

A. Rolling wave planningB. Dependency determinationC. Schedule network templateD. Applying leads and lags

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Rolling wave planning is the process of planning for a project in waves as the project becomes clearer andunfolds. It is important in such projects to at least highlight in the initial plan the key milestones for the project.

QUESTION 21Which of the following is a tool and technique to develop the schedule?

A. What-if scenario analysis?B. BenchmarkingC. Variance analysisD. SWOT analysis

Correct Answer: ASection: (none)Explanation

Explanation/Reference:What-if scenario analysis Thinking through potential outcomes, the What-If Scenario Analysis is a tool andtechnique of the Develop Schedule process and the Control Schedule process, both described in the fourthedition PMBOK®. This technique is used to estimate impacts to the project schedule if potential scenariosoccur. This technique simply repeatedly asks “what if” a certain event should happen. It is useful to have morethan one person’s perspective and ideas for this analysis. For example, Katy has two hours to bake three dozencookies. She and her family are doing a What-If Scenario Analysis for this cookie baking project. “What if youburn the first batch?” asks her husband. They estimate that will extend the schedule an hour. “What if Dad iseating the cookies as fast as you can make them?” asks her daughter. They estimate that he’ll become full at acertain point, so it’ll extend the schedule half an hour. In summary, What-If Scenario Analysis simply estimatesthe effect that potential events may have.

QUESTION 22Rolling wave planning is used as tool and technique in which of the following processes?

A. Estimate Activity DurationsB. Define ActivitiesC. Develop ScheduleD. Sequence Activities

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Rolling wave planning is the process of planning for a project in waves as the project becomes clearer andunfolds. It is important in such projects to at least highlight in the initial plan the key milestones for the project.

QUESTION 23Draw the precendence diagram for the dependencies and activity times below to answer the question. UseAON or another technique to derive the answer using F-S relationships.

What is the critical path duration for the given schedule network?

A. 22B. 23C. 24D. 25

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 24Draw the precendence diagram for the dependencies and activity times below to answer the question. UseAON or another technique to derive the answer using F-S relationships.

What is the total float on path BEG?

A. 0B. 1C. 2D. 3

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 25If the schedule Variance (SV) = $55, and the Planned Value (PV) = $11, What is the earned Value (EV)?

A. $0.2B. $5C. $44D. $66

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Earned Value (EV)

This is also referred to as Budgeted Cost of Work Performed (BCWP). Earned Value (EV) or BCWP is the totalcost of the work completed/performed as of a reproting date.This is calculated as:

EV or BCWP = Baselined Cost * % Complete Actual

Schedule Variance SV = EV - PV

QUESTION 26What is the status of the project if the cost Performance index is 1.25 and the schedule Performance Index is0.75?

A. Under budget and behind scheduleB. Over budget and ahead of scheduleC. Under budget and ahead of scheduleD. Over budget and behind schedule

Correct Answer: ASection: (none)Explanation

Explanation/Reference:CPI = EV / AC

QUESTION 27Which of the following will be required to perform simulation for schedule risk analysis?

A. Activity list and activity attributesB. Schedule network diagram and duration estimatesC. Schedule data and activity resource requirementD. Milestone list and resource breakdown structure

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 28The risk register contains which of the following?

A. Identified risks and potential responsesB. Identified risk and updates to scope baselineC. Risk management planD. Risk related contract decisions

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 29Which of the following is an input to identify risk?

A. Organizational process assetsB. Scope management planC. Communication management planD. Expert judgment

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 30Which analysis helps to determine the risks that have the most potential for impacting the project?

A. Expected monetary value analysisB. Sensitivity analysisC. Modeling and simulationD. Expert judgment

Correct Answer: BSection: (none)Explanation

Explanation/Reference: Sensitivity AnalysisSensitivity analysis seeks to place a value on the effect of change of a single variable within a project byanalyzing that effect on the project plan. It is the simplest form of risk analysis. Uncertainty and risk arereflected by defining a likely range of variation for each component of the original base case estimate. Inpractice such an analysis is only done for those variables which have a high impact on cost, time or economicreturn, and to which the project is most sensitive.

QUESTION 31Which of the following risk management processes uses brainstorming as a technique?

A. Identify RiskB. Monitor and control RiskC. Plan Risk ManagementD. Plan Risk Responses

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Brainstorming the ProjectBrainstorming is likely the most common approach to risk identification. It’s usually completed together as aproject team to identify the risks within the project. The risks are identified in broad terms and posted, and thenthe risks’ characteristics are detailed. The identified risks are categorized and will pass through qualitative andquantitative risk analysis later.

QUESTION 32Reserve analysis is a tool and technique used in which of the following processes?

A. Monitor and control RiskB. Qualitative Risk AnalysisC. Quantitative Risk AnalysisD. Plan Risk Responses

Correct Answer: ASection: (none)

Explanation

Explanation/Reference:Reserve analysis: refers to a specific technique that is often implemented by the project management teamand/or the project management team leader or leaders for the purposes of helping to better maintain andmanage the projects that they may have under their guise at that respective time.Specifically speaking, the technique of reserve analysis is a particular analytical technique that is used for thepurposes of making a complete and thorough determination of the entirety of the specific and exact featuresand or in many cases relationships of all of the individual project related components that currently exist as partof the previously determined project management plan. The purpose of the execution and implementation of areserve analysis is the establishment of an estimated reserve that can be used for the purposes of establishinga schedule duration, any and all estimated costs, the budget, as well as the complete funds assigned orallocated to the project.

QUESTION 33What is risk Tolerance?

A. Ability to manage risksB. Willingness to accept varying degrees of riskC. Ability to mitigate risksD. Willingness to develop a risk management plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 34Expected Monetary Value (EMV) analysis is commonly used in:

A. Probability distributionB. Decision tree diagramC. Sensitivity analysisD. Modeling and simulation

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Decision trees are predictive models, used to graphically organize information about possible options,consequences and end value.

QUESTION 35Expected Monetary Value (EMV) analysis is commonly used in:

A. Probability distributionB. Decision tree diagramC. Sensitivity analysisD. Modeling and simulation

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Decision trees are predictive models, used to graphically organize information about possible options,consequences and end value.

QUESTION 36An Ishiwaka of fishbone diagram is used for which of the following?

A. Identifying causes of risksB. Identifying frequency of occurrence of risksC. Developing a resource planD. Developing schedule

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Fishbone Diagram:Also Called: Cause–and–Effect Diagram, Ishikawa DiagramVariations: cause enumeration diagram, process fishbone, time–delay fishbone, CEDAC (cause–and–effectdiagram with the addition of cards), desired–result fishbone, reverse fishbone diagramThe fishbone diagram identifies many possible causes for an effect or problem. It can be used to structure abrainstorming session. It immediately sorts ideas into useful categories.When to Use a Fishbone DiagramWhen identifying possible causes for a problem.Especially when a team’s thinking tends to fall into ruts.

QUESTION 37Which analysis uses beta and triangular distributions as tool and technique?

A. Quantitative risk analysisB. Qualitative risk analysisC. Perform quality assuranceD. Perform quality control

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 38What should a project manager do with low-priority risks?

A. Ignore low-priority risksB. Monitor periodically with other low-priority risksC. Create a mitigation plan for the low-priority risksD. Increase the contingency reserve

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 39Which of the following is a technique for identify Risks?

A. Risk categorizationB. SWOT analysisC. Risk register categorizationD. Risk Probability and impact assessment

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Analyzing SWOTSWOT means strengths, weaknesses, opportunities, and threats. SWOT analysis is the process of examiningthe project from each of the characteristic’s point of view. For example, a technology project may identifySWOT as

Strengths The technology to be installed in the project has been installed by other large companies in ourindustry.Weaknesses We have never installed this technology before.Opportunities The new technology will allow us to reduce our cycle time for time-to-market on new products.Opportunities are things, conditions, or events that allow an organization to differentiate itself from competitorsand improve its standing in the marketplace .Threats The time to complete the training and simulation may overlap with product updates, new versions, andexternal changes to our technology portfolio.

QUESTION 40The project manager decides to conduct a meeting with the team and management after a new risk has beenidentified. After the meeting, the decision is to allow the risk to occur.

This is an example of which type of risk response strategy?

A. MitigateB. AcceptC. AvoidD. Transfer

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 41The project team reviews identified risks and the risks response strategy. For one of the risks, the team realizesthat the implementation of the risk response would generate another risk.

This new risk is which of the following types of risk?

A. This new risk is which of the following types of risk?B. PrimaryC. ResidualD. Tertiary

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 42What is the first step in preparing the risk register?

A. Qualitative risk analysisB. Quantitative risk analysisC. Risk response planningD. Risk identification

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 43What is the Project Porfolio Management?

A. Management of a project by dividing the project into more manageable sub-projects.B. Management of a project by utilizing a portfolio of general management skills, such as planning, organizing,

staffing, executing and controlling.C. Management of all projects undertaken by a company.D. Management of a collection of projects that are grouped together to facilitate effective management and

meet strategic business objectives

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 44When is a project finished?

A. After verbal acceptance of the customer or sponsorB. After lessons learned have been documented in contract closureC. When the project objectives have been metD. After resources have been released

Correct Answer: C

Section: (none)Explanation

Explanation/Reference:

QUESTION 45Define Activities and Estimate Activity Resources are processes in which project management knowledgearea?

A. Time managementB. Cost managementC. Scope managementD. Human resources management

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 46What characteristic do project and operational work share in common?

A. Performed by systemsB. Constrained by limited resourcesC. RepetitivenessD. Uniqueness

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 47What are the components of the “Triple constraint”?

A. Scope, time, requirementsB. Resources, time, costC. Scope, management, costD. Scope, time, cost

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 48Which statement is true about the project management body of knowledge?

A. Recognized by every project managerB. Constantly evolvingC. The sum of all knowledge related to project managementD. A sum of knowledge that should be applied on every project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 49What do composite organizations involve?

A. Functional and project managersB. Functional managers only C. Project managers onlyD. Technical manager and project managers

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 50Which of the following is TRUE about most project life cycles?

A. Staffing level is highest at the startB. The stakeholders influence is highest at the startC. The level of uncertainty is lowest at the startD. The cost of changes is highest at the start

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 51What Happens to a stakeholder´s project influence over time?

A. IncreasesB. DecreasesC. Stays the sameD. Has no bearing

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

Exam F

QUESTION 1To which process is work performance information an input?

A. Contract administrationB. Direction and management of project executionC. Create WBSD. Qualitative risk analysis

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 2Which of the following is an output of the information Distribution Process?

A. Project calendarB. Communication management planC. Requested changesD. Communication requirement plan

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 3Which process document the business needs of aproject and the new product, service or other result that isintended to satisfy those requirements?

A. Develop project management planB. Develop project charterC. Develop preliminary projects scope statementD. Scope planning

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 4Which process group typically consumes the bulk of a project budgets?

A. Monotoring & ControllingB. ExecutingC. PlanningD. Initiating

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 5What process determines which risks might affect the project?

A. Qualitative risksB. Identify riskC. Plan risk ManagementD. Quantitative risk analysis

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 6Verification of project deliverables occurs during which process?

A. Develop preliminary project scope satatementB. Close project or PhaseC. Develop project charterD. Create WBS

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 7Information collected on the status of project activities being performed to accomplish the project work is knowas what?

A. Project management information systemB. Work performance informationC. Work breakdown structureD. variance analysis

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 8Which is a tool used in monitoring and controlling project work?

A. Work performance informationB. Project management information system (PMIS)C. Activity duration estimatesD. Schedule network analysis

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 9Which is an input to the Scope Verification Process?

A. Performance ReportB. WBSC. Requested changesD. Project scope statement

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 10When are deliverables accepted or not accepted?

A. When the project is initiatedB. As an output of the scope verification processC. When the project is closingD. In the contract clousure process

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 11During what process would you obtain stakeholders formal acceptnce of the completed project scope?

A. Quality ControlB. Scope verificationC. Scope controlD. Close Project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 12The initial development of a Project Scope Management plan uses which technique?

A. Alternatives identifictionB. Scope decompositionC. Expert judgementD. Product analysis

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 13What is a hierarchically organized depiction of the identified project risk arranged by risk category?

A. Risk registerB. Risk Break Down Structure (RBS)C. Risk management planD. Risk category

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 14Which is a tool or technique used in scope definition?

A. Templates, forms and standadsB. Change requestsC. Stakeholder analysisD. Project Assumptions

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Stakeholder Analysis is done to prepare for the communication plan. Generally speaking, there are peoplewith various degrees of interest in projects who have similar authority in an organization. Communications tothese constituents needs to be respectful of their time. This is an optimal output from the Discovery team. The project may need services or support from individuals with:Q1 -- Low Authority and Low Interest, Monitor -- Do not bore with excessive communications Q2 -- High Authority and Low Interest, Satisfy -- Keep happy, do not bore Q3 -- High Authority and High Interest, Fully Engage Q4 – Low Authority and High Interest, Inform, Engage -- Often very helpful with detail of project, issues

All types need to be “properly” motivated to participate.

QUESTION 15what is the total float of the critical path?

A. Can be any numberB. Zero or positiveC. Zero or negativeD. Depends on the calendar

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 16Which of the following is the correct network diagram for the table?

A. Begin A-C-D-E- END -B-DB. Begin A-B-C-D-E-ENDC. Begin A-B-D-E- END -A-C-DD. Begin A-C-D-E-END-B-C

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 17Which of the following is a schedule network analysis technique that takes limited resources into account?

A. Network reserve analysisB. Critical chain methodC. Lead and lag adjustmentD. Critical path method

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 18Fast tracking is a schedule compression technique used to shorten the project schedule without changingproject scope. Which of the following can result from fast tracking?

A. The risk of achieving the shortened project time is increasedB. The critical path will have ositive total floatC. Contingency reserves are released for redeployment the project manager D. Duration buffers are added to maintain a focus on planned activity duration

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 19Which estimating technique uses the actual cost of previous similar projects as a basis for estimating the costof the current project?

A. AnalogousB. ParametricC. Bottom-upD. Top-down

Correct Answer: ASection: (none)Explanation

Explanation/Reference:AnalogousOne of the estimation common used in project management is the "Analogous Estimation". What exactly isAnalogous Estimation?It is also known as "Top Down" Estimation.It uses estimations from previous activities to estimate future durations. The validity of duration estimatesderived using this method depends on:- historical information- similarity of the historical projects- expert judgement

QUESTION 20Your project has an EV of 100 work-days, an AC of 120 work days, and a PV of 80 work days. What should beyour concern?

A. There is a cost under runB. There is a cost overrunC. May not meet deadlineD. The project is 20 days behind schedule

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 21Which ilustrate the connection between work that needs to be done and its project team members?

A. Work Breakdown structureB. Network diagramsC. Staffing management planD. Responsibility matrix

Correct Answer: DSection: (none)Explanation

Explanation/Reference:A Responsibility Assignment Matrix (RAM), also known as RACI matrix or Linear Responsibility Chart (LRC),describes the participation by various roles in completing tasks or deliverables for a project or businessprocess. It is especially useful in clarifying roles and responsibilities in cross-functional/departmental projectsand processes. RACI is an acronym derived from the four key responsibilities most typically used:

* Responsible: Those who do the work to achieve the task. There is typically one role with a participation typeof Responsible, although others can be delegated to assist in the work required.

* Accountable (also Approver or final Approving authority): The one ultimately accountable for the correct andthorough completion of the deliverable or task, and the one to whom Responsible is accountable. In otherwords, an Accountable must sign off (Approve) on work that Responsible provides. There must be only oneAccountable specified for each task or deliverable

* Consulted: Those whose opinions are sought; and with whom there is two-way communication.

* Informed: Those who are kept up-to-date on progress, often only on completion of the task or deliverable;and with whom there is just one-way communication.

QUESTION 22When can pre-assigmnet of the project team members occur?

A. Whe the project uses capital expendituresB. When the required staff can be acquired from outsides sourcesC. When the project would be ignored due to travel expensesD. When the project is the result of specific people being promised as part of a competitive proposal

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 23Which process uses occurrence probability and impact on project objectives to asses the priority of identifiedrisks?

A. Risk identificationB. Qualitative Risk analysisC. Risk management planning

D. Quantitative risk analysis

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 24In which process might you use risk reassesment as a tool and technique?

A. Qualitative risk analysisB. Risk monitoring and controlC. Monitoring and control project work D. Risk response planning

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 25A contract management plan is a subsidiary of what other type of plan?

A. Resource planB. Project management planC. Cost control planD. Expected monetary value plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 26A contract cannot contain ....

A. Illegal activitiesB. Deadline for the completion of the workC. Penalities and fines for disclousure of intellectual rightsD. All of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 27Which one of the following comes first in the project plan?

A. Scope statement B. Quality planC. WBSD. Development plan

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 28You are the project manager ofa project. During the process of selecting the seller, you reject one vendorbecause it does not have the manufacturing capability. This is an example of which selection tool?

A. Weigthing SystemB. Screening systemC. Seller rating systemD. Expert judgement

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Screening System – Establish minimum performance requirement for one or more criteria.

QUESTION 29_________________ Provides detail about how the project scope may be changed

A. Control Scope systemB. Verify ScopeC. Scope CharterD. Scope management plan

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 30Which of the following technique to identify the underlying cause of aproble and take steps to prevent furtheroccurences?

A. Root cause analysisB. Quality auditsC. Project auditsD. Risk audits

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Root Cause Analysis The technique of root cause analysis refers to the act of analyzing a series of variances,risks, or defect that may exist in and around the project or any specific or particular component of that projectand attempt to determine through careful review the actual root causes, or unique underlying factors, that mayexist which is ultimately leading to this unfavorable result, and which would need to be addressed and orcompensated for if there is the goal to alter the outcome.One single root cause can actually have a significantimpact, and can in fact be the cause of a number of defects or risks.

QUESTION 31Which of the following Provides the least accurate in estimating?

A. Rough order of magnitudeB. Budget estimateC. WBS estimateD. Definitive estimate

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Rough Order of Magnitude (ROM) Estimate

A rough order of magnitude (ROM) estimate is the least accurate estimate. ROMs are -50% to +50% accurate,or potentially even larger. ROMs are used very early in the project when there is limited information from whichto develop an accurate estimate.

QUESTION 32Who has the responsability for informing the final deliverable to all stakeholders?

A. Project managerB. SponsorC. Team leadD. Management

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 33What is corrective action?

A. An action that brings future projects events into alignment with the project planB. An action to correct something in the projectC. An action to prevent something in the projectD. Corrective action is not related to project

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 34Assumptions are factors that, for planning purposes, are considered to be ____________

A. True, real or certainB. True, real or uncertainC. RealD. Verbal

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 35A complete set of indexed project records is called_____________

A. Project archivesB. IndexC. SowD. Project History

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 36You are managing a project that will implement a new Insurance software package. Two project team membershave difficulty working together. They come to you, for help resolving the issues. You inmmediately set-up ameeting that includes the functional manager. After the meeting you and the functional manager discuss theissues and agree on a solution. What type of organizational structure you are working in?

A. FunctionalB. Balanced MatrixC. ProjectizedD. Strong Matrix

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 37You have been with the organization, you constantly hear rumours about a certain. CAPM failing to live up tothe CAPMCode. What you should do?

A. You can gather as much information as you can before proceedingB. Confront the person inmediatelyC. Ignore the rumours D. Ass the romours along

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 38Who is responsible for issuing the project charter?

A. The project managerB. The project sponsorC. The team leadD. The nianagement

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 39In the PMBOK, the seller is ____________to the projecct team.

A. IntegralB. ExternalC. OutsideD. Assigned

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 40

Project quality Management includes:

A. Customer satisfactionB. Prevention over inspectionC. Continuous improvementD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 41You are the project manager of the MKTG Project. The project has a budget of $200.000 andd is expected tolast 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?

A. $-00,00B. $200,00C. $50,00D. None of the above

Correct Answer: BSection: (none)Explanation

Explanation/Reference:The BAC is the budget at completion (Total budget cost) which is $200,00

Budget At Completion (BAC)

Budget At Completion (BAC) is the total budget allocated to the project.Budget At Completion (BAC) is generally plotted over time. Say like periods of reporting ( Monthly, Weekly etc. )BAC is used to compute the Estimate At Completion ( EAC ), explained in next section.BAC is also used to compute the TCPI and TSPIBAC is calculated using the following formulaBAC = Baselined Effort-hours * Hourly Rate

QUESTION 42A risk register is a part of:

A. Project scope statementB. Project manager planC. Project scheduling planD. Project charter

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 43A risk register is a part of:

A. Project scopeB. Project manager planC. Project Scheduling planD. Project charter

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 44Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?

A. Precedence Diagramming Method (PDM)B. Gant Chart diagram (GCD)C. Dependency Diagramming Method (DDM)D. Arrow diagramming Method (ADM)

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Network DiagramsOne of the more important topics to understand when planning project activities is creating network diagrams.Network diagrams provide a graphical view of activities and how they are related to one another.

QUESTION 45Create procurement document is done in _____________________

A. Plan procurementsB. Conduct ProcurementsC. Administer procurementsD. Close procurements

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 46Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of________________

A. Enterprise benefits measurements methods when selecting a projectB. Integral parts of the SOWC. Ways to ensure stakeholders commitment

D. Project selection methods

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 47Most changes requests are a result of ___________

A. Value added change (Enhancements)B. Schedule constraintsC. Regulatory constraintsD. Improvement to the project scope

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Most change requests (CRs) are a result of Value added change (Ennhancements)

QUESTION 48Based on the PMBOK, who is ultimately responsible for the project quality?

A. Project teamB. Project managerC. QA managerD. Validation engineer

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 49The end of the project comes after which of the following ?

A. Project charterB. Final deliverableC. ScheduleD. QA activities are done

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 50The product description of aproject can help to create procurement details. Which one of the following bestdescribes product description?

A. The product description defines the contracted work, based on the requirements of the project customerB. The product description defines the contracted workC. The product description defines the requirements for the contract workD. All of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

Exam G

QUESTION 1During the planning phase of your project, your project team members have discovered aanother way tocomplete a portion of the project scope. This method is safer for the project team, but may cost more for thecustomer. This is an example of ____________

A. Alternative selectionB. AssestmentC. Alternative identificationD. Product analysis

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 2What is the lowest level in a work breakdown structure?

A. Project TaskB. Work packagesC. sowD. None

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 3Administrative closure should occur ___________

A. At the end of each phase of the projectB. At the end of the whole projectC. At the end of 50% of the projectD. At the end of the 100% of the project

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 4In which phase project manager is assigned to a project?

A. During the planning stageB. During the initiation stage C. After approval of budget

D. After the project is proven feasible

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 5Who gives project acceptance?

A. SponsorB. CustomerC. Project managerD. Team Lead

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 6A requirement document is an input of ____________ process?

A. Collect requirementsB. Define scopeC. Integrated Change ControlD. Monitor and Control Project Work

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 7Make-or-buy decisions measure the cost of both options. What are the two options ?

A. Direct and indirect B. Tactical and StrategicC. Management and ProjectD. Only Tactical

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 8Which of the following are the inputs od Define Scope?

A. Requirements documents created in collect requirements processB. Project files from previous projectsC. Project charterD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 9Which document is best suited for tracking the assigment of all resources to sepecific tasks in a project

A. RACI MatrixB. SOWC. Staffing management plan D. CPI

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 10_____________Is the international organization that controls the standards for quality

A. ISOB. CAPMC. PMID. ISCN

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 11The Work Break Down Structure is _________________

A. Used to break down the project into manageable placesB. Set and does not change throughout the projectC. Needed as part of the project charterD. Needed as part of the project Scope statement

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 12Is a project with a SPI of 1.8, what you tell ?

A. The project is runnig ahead of the scheduleB. The project is running behind of the scheduleC. Resources assigned to the project cost 1.8 unitsD. None

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The SPI= EV/PV. A schedule performance Index of 1 or greater suggests that the project is aahead ofschedule.

QUESTION 13You are managing a project that will implement a new MARKETING software package. You are assigned theresources and want to keep the IT manager in the loop by informing him or her your decisions. Which type oforganizational structure are you working?

A. ProjectizedB. Strong MatrixC. Weak MatrixD. Functional

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 14At what point in a project do you have the highest probability that it will fail?

A. The begining of the projectB. Just before the end of the projectC. QA phaseD. Execution Phase

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 15From who do you need to gain the formal acceptance at project clousure?

A. The customer

B. The qualify director C. Project management officeD. Project manager

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 16Which statement is true about Bottom-Up estimating?

A. Estimating the cost of individual work items and then rolling up the costs to arrive at a project totalB. Uses the actual cost of a previous similar project as the basis for estimating the cost of the current projectC. Using the project characteristics (or parameters) in amathematical model to predict costsD. Cost of quality can also be used to prepare the schedule activity cost estimate

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 17Which is no part of the project plan?

A. Project scope Management planB. Schedule Management planC. Cost management planD. Project charter

Correct Answer: DSection: (none)Explanation

Explanation/Reference:All are part of Project Plan except Project charter

QUESTION 18Which of the following is the most important task of the project manager during the execution and controlphase?

A. Information managementB. Mantain scope statementC. Maintain charterD. Maintain closing document

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 19Which time estimating tools estimate the basis for activity durations can be quantitatively determined bymultiplying the quantity of work to be performed by the productivity rate?

A. Parametric estimatingB. Funding limit reconciliationC. Reserves analysisD. None of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 20You are the project manager and now in the middle of creating RFP (Request for Proposal) RFTP (Request forproposal) is done in ______________________

A. Plan procurementB. Conduct procurementC. Administer ProcurementsD. Close procurements

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 21Which of the following statements is true about Strategic Planning?

A. Strategic Planning determines which projects will be choosing in order to achieve the organizational goalsB. Strategic Planning determines which projects will be sponsor in order to achieve the organizations goalsC. Stratgic planning determines these are the projects that get chosen and fundedD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 22The Ishikawa diagram, Pareto chart, Control chart, and statical sampling are examples of____________________

A. Quality assuranceB. Quality control

C. Qulity rulesD. CMM

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 23Which risk response is most likely to involve contingency reserves?

A. AcceptanceB. ShareC. MitigateD. Transfer

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Acceptance is when NO change to the project is made for a risk. A contiengency can be set aside to offset theimpact of the risk

QUESTION 24Which of the following does not provided by scope statement?

A. Project justificationB. Project productC. Project manager authorityD. Project objective

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 25What is acommunication channel delta if the members in the communication plan are increased from 5 to 10?

A. 35B. 5C. 15D. 75

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Delta= n*(n-1)/2 - n1(n1-1)/2 where n= Individuals and n1= New individuals. No of communications channels n*

(n-1)/2

QUESTION 26Collect requirements process starts in Project Planning Phase ans uses the outputs of the ________________

A. Initiation ProcessB. Project closer ProcessC. Estimation ProcessD. Closing Process

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 27You are the project manager of a project that just went into extinction mode. This means that your project________________

A. Has ended before its started objectiveB. Still cunning but missing resourcesC. Will be closed due to lack of resourcesD. None of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 28When you are developing the estimates for the project, you choose to add the individuals estimates for theactivities that comprise each phase. What type of estimation method are you using?

A. Parametric estimatingB. Bottom-up estimatingC. Top-Down estimatingD. Analogous estimating

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 29Who is responsible for the creation of the final project plan?

A. Project ManagerB. Team LeaderC. Sponsor

D. Project Team

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 30Who has responsibility for Plan Quality?

A. Project managerB. QA managerC. Project PlannerD. Team Lead

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 31Assumptions in the project plan should be______________

A. Written downB. UnderstandableC. Not UnderstandableD. No need to write

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 32Who applies project selection methods to decide whether to accept or reject a project?

A. Project sponsorB. Project teamC. Project managerD. Senior management

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 33Which of the following statement is true about project charter?

A. Provides a high level definition of the effort and its stakeholdersB. Announces who is the project enginnerC. Tells the newspapers and media when the project will endD. Announces who is the project sponsor

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Project Charter: Formally authorizes the project, assign the project manager, and gives high-level definition ofthe project and its deliverables

QUESTION 34Which of the following is NOT an input of close project process?

A. project management planB. Contract documentationC. DeliverablesD. WBS

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 35Which of the following is conflict resolution techniques?

A. CompromiseB. SmoothingC. FormalD. Coercive

Correct Answer: BSection: (none)Explanation

Explanation/Reference:The rest are forms of leadership power exept Smoothing

QUESTION 36___________________ Is providing detailed plans for tasks that are about to start in the near future using themost current information and revisting future activities when they near their starting dates

A. Rolling wave planningB. Progresive elaborationC. Milestone detail planningD. Expert judgemnet

Correct Answer: ASection: (none)

Explanation

Explanation/Reference:

QUESTION 37Which of the following activities is not part of Plan Risk Management?

A. Updating Risk registerB. Determining risk roles and responsabilitiesC. Identifying risk categoriesD. Developing a risk management plan

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Updating Risk register first happens in Identify Risk Phase. Determining risk roles and responsabilities,Identifying risk categories, and Developing a risk management plan are part of Plan Risk Management

QUESTION 38PMI discusses procurement focusing on the ___________ relationship

A. Buyer or sellerB. Vendor or SellerC. PurchasingD. Sellino

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 39Administrative closure is the process that _____________

A. Closes all activities pertaning to a specific projectB. Collect user acceptances of the project product or serviceC. Includes all the activities needed to validate the project products and servicesD. All of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 40You are the project manager of a project, which of the following is not your responsability?

A. Quality in the organization

B. Acquiring HR Resources for the project teamC. Overall responsability for risk on the projectD. All of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Senior manager is responsible for Quality in the organization

QUESTION 41Project sucess can be achieved only if:

A. There is a clear link between the project deliverables and the bussiness strategyB. The project sponsor leads the initiativesC. The project manager is an expert in managing resourcesD. Team members like project manager

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 42You are a project manager of aproject and as part of the team acquisition process, you hire a new employeeand assigns him to your project team. According to Maslow's Hierarchy of needs, what needs level he mostlikely is at?

A. Social needB. Physical needC. Safety and securityD. Security

Correct Answer: ASection: (none)Explanation

Explanation/Reference:As anew to project he is most likely looking for acceptance and friendship. This comes under Social Need

QUESTION 43Which one of the following is not an output of contract clousure?

A. Close contractsB. Lessons learned documentationC. deliverable acceptanceD. Scope statement

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 44The intent of the risk management process group is to _____________

A. Increase the probability of positive outcomes in the projectB. Announce project risksC. Not consider risks affecting the companyD. Announce project deliverables

Correct Answer: ASection: (none)Explanation

Explanation/Reference: The risk management process groupserves as the road map used to reduce its impact on the project

QUESTION 45ISO satands for ____________________

A. International Organization for StandardizationB. International Standardized OrganizationC. Standardized OrganizationD. Indiana Standardized Organization

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 46The project Baseline is _________________

A. Original plans plus the approved changesB. Important in the project initiation plansC. Initial estimates for tasks and resource utilizationD. Original plans and the approved major changes

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 47Which of the following is NOT a form a leadership power?

A. CompromiseB. SmoothingC. FoimalD. Coercive

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 48_____________________ Is a group of processes required to purchase or acquire the products, services, orresults needed from outside the project team to perform the work

A. Procurement ManagementB. Planning ManagementC. Scope ManagementD. Control Management

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 49You are the project manager of a project. If there are approved changes to the original Scope, what you do withthe old original scope?

A. save the old versionB. No need to save the old versionC. Scrap the old versionD. Old version is not required

Correct Answer: ASection: (none)Explanation

Explanation/Reference:All version you need to keep in version control System

QUESTION 50Which of the following subsidiary plan conatains the quality objectives for the project?

A. Quality baselineB. Quality management planC. Process improvement planD. QA checklist

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

Exam H

QUESTION 1Function of the ________________ is to make sure that changes to anything in the project are recorded andagreed to by the stakeholders

A. SponsorB. Project managerC. Team LeadD. Management

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 2Which of the following is an output of verify scope?

A. Formal AccepatanceB. WBS templateC. SOW acceptanceD. Rework

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 3Delivery dates and availability of resources can be found in the details of the ______________________

A. SOWB. WBS C. Project charterD. Project Scope Satatement

Correct Answer: BSection: (none)Explanation

Explanation/Reference:A work breakdown structure (WBS) in project management and systems engineering, is a tool used to defineand group a project's discrete work packages in a way that helps organize and define the total work scope ofthe project. A work breakdown structure element may be a product, data, a service, or any combination. A WBSalso provides the necessary framework for detailed cost estimating and control along with providing guidancefor schedule development and control. Additionally the WBS is a dynamic tool and can be revised and updatedas needed by the project manager.

QUESTION 4How many communication channels will be required in aproject in which 5 individuals are participating?

A. 10B. 12C. 4D. 5

Correct Answer: ASection: (none)Explanation

Explanation/Reference:n*(n-1)/2

QUESTION 5Which of the following project document is best suited for tracking cost of resources?

A. Psk Breakdown structureB. WBSC. Organizational Breakdown structureD. Resource Breakdown structure

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 6If a project with CPI of 0.8 what you tell?

A. The project is falling behindB. The project is using fewer resources than anticipatedC. The project is consumed more resources than anticipatedD. The project is running ahead of schedule

Correct Answer: CSection: (none)Explanation

Explanation/Reference:If your cost performance index is above 1.0, it indicates that you have cost that are less the estimated CPI =EV/AC (Earned Value/Actual Cost)

CPI greater than 1 is good (under budget):

< 1 means that the cost of completing the work is higher than planned (bad);= 1 means that the cost of completing the work is right on plan (good);> 1 means that the cost of completing the work is less than planned (good or sometimes bad).Having a CPI that is very high (in some cases, very high is only 1.2) may mean that the plan was tooconservative, and thus a very high number may in fact not be good, as the CPI is being measured against apoor baseline. Management or the customer may be upset with the planners as an overly conservative baselineties up available funds for other purposes, and the baseline is also used for manpower planning

QUESTION 7Which monitoring or controling activities would not result in preventive action being applied?

A. Control ScopeB. Manage project TeamC. Quality controlD. Manage Scope Statement

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Scope schedule and Control costs can all result in corrective action , but Not preventive action.

QUESTION 8_______________ Is the road map for the execution of the project

A. Strategic PlanningB. sowC. WBSD. Project Plan

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 9You are the project manager of a project and budgeted money to provide cash awards to team members thatexceed expectations. A project team member that is motivated by chance to earn cash reward can mostaccurately be explained by which theory

A. Hierarchy of needsB. Expectancy theoryC. Achievement theory D. All of the above

Correct Answer: BSection: (none)Explanation

Explanation/Reference:The team member is working hard because he expects to be rewarded so it is Expectancy Theory.

Expectany Theory is: Employees who believe their efforts will lead to effective performance and who expectgto be rewarded for their accomplishments remian productive as rewards meet their expectation.

Achievement Theory: It is one of the motivation theories used for the developing project team. In the latestinformation era, people/employees need to be motivated beyond food & money as modern era overcome thestarvation.

According to Achievement Theory, people/employees are motivated mainly by three things.

1. Achievement It motivates based on the need to achieve or succeed.2. Power This is drived based on influencing others and pride on it.3. Affiliation Affiliation is mainly relationship based and people wants to develop with others.

QUESTION 10Which of the following are input of close project process?

A. Project management planB. Contract documentationC. DeliverablesD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 11The main purpose of project initiation is to ________________

A. Assign the project manager to the projectB. Formally describes the projectC. Produce the project charterD. Formally authorize the project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Output of project initiation is Formally authorize the project. Output of project scope initiation is: Project CharterPM assigned Constraints and Assumptions.

QUESTION 12Which documents formally authorizes a project?

A. The WBSB. Project scopeC. The project charterD. Project closing documnet

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 13Project just went into inclusion mode. This means that project _______________

A. Has become part of the business processesB. has been accepted by the sponsor and the clientC. Will be closed due to lack of resources D. None of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 14Main purpose of project initiation is ______________

A. Assign project managerB. Formally describes projectC. Do WBSD. Formally authorize the project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 15Who is responsibility for making sure that a message in the project team is understood

A. Project managerB. SenderC. Project coordinatorD. Sponsor

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Sender has to make sure that the receiver acknowledges the receip and message is understood, and thereceiver needs to ensure that the senser received the acknowledgement.

The sender-receiver model The sender-receiver model is the simplest communication model and underpins most others. The sender hasan idea or concept he/she wants the receiver to appreciate. Before any useful outcome can be achieved fromthe communication, the receiver has to accurately understand the sender’s idea! This means the message hasto be effective in the receiver’s space; if the message does not engage the receiver, the sender is wasting his/her time

The elements in this model are:

• Encode: To translate thoughts or ideas into a form of language that can be understood by the receiver; eg,written English, spoken French or a drawn diagram. • Message: What is sent: the output of encoding • Medium: The method used for sending the message (face-to-face, telephone, email) • Noise: Something that interferes with the sending or understanding of the message (distance, culture,language differences) • Decode: The translation of the message by the receiver from the medium into their thoughts.

A single communication is complete once the feedback-message has been decoded by the sender andchecked for accuracy against the original idea. Once this loop has been closed both people have a commonunderstanding of the idea. This does not require agreement or concurrence, but if there is to be adisagreement, it helps if everyone has the same basic understanding of the issue or idea in dispute. Effectivecommunication requires both the sender and the receiver to be engaged. The sender needs to check that the‘message’ has been received and validate the feedback

QUESTION 16_________________ Is always the lowest risk for the buyer if the scope of work is not well defined

http://www.gratisexam.com/

A. Purchase orderB. Fixed PriceC. Time and materialD. Cost plus incentive fee

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

What is Cost Plus Incentive Fee (CPIF)?Pays all cost an agreed upon fee plus a bonus for beating the performance objective stated in the contract.

QUESTION 17With 5 participant how many channels are required?

A. 10B. 5C. 8D. 20

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Communication Channels = (n)(n-1)/2, n= Numero de participantes.

QUESTION 18Acceptance of the product should be ___________

A. VerbalB. CosnsistentC. PersonalD. Formal

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 19You are creating your WBS and keep decomposing tasks into smaller units. How can you tell when you aredone?

A. keep decomposing tasks until you reach an amount of work that is small enough to reliably estimaterequired resources and duration

B. Keep decomposing work until you reach a predetermined number of hierarchy levels to keep the WBSbalanced

C. keep decomposing tasks until you reach an amount of work that can be accomplished in one DAYD. keep decomposing tasks until you reach an amount of work that can be accomplished in one WEEK

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 20If a project with a SPI of 0.80 what you tell??

A. Project is running ahead of the schedule

B. Project is running behind of the scheduleC. Resources assigned to the project cost 1.8 unitsD. None

Correct Answer: BSection: (none)Explanation

Explanation/Reference:SPI stands for Schedule Performance Index.It is a very powerful measure of the amount of work actually completed on a project. It is part of the EarnedValue Management Techniques.To calculate SPI for any project, get the Planned Value and the Earned Value. The formula for SPI isSPI = EV / PV

As a rule of thumb, for Schedule performance index (SPI), EV/PV greater than 1 is good (ahead of schedule),and less than 1 is bad ( behind schedule).

QUESTION 21If aproject with a CPI of 1.2 what you tell?

A. The project is consumed fewer resources than anticipatedB. The project is using fewer resources than anticipatedC. The project is falling behindD. The project is running ahead of schedule

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 22What are the inputs for initiation process?

A. Product description and Startegic PlanB. Selection CriteriaC. Historical InformationD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 23Which of the following are parts of project scope management?

A. Verify scopeB. Collect RequirementsC. Control ScopeD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:There are following processes which are part of Project scope management: Collect Requirements, Definescope, create WBS, verify scope, control scope

QUESTION 24Project scope is________________

A. The features and functions that are to be included in a product or serviceB. The work that must NOT be done in order to deliver a product with the specified feature and functionC. Part of the project charterD. Part of sow

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The work that must be done in order to deliver a product with the specified feature and function or The featuresand functions that are to be included in aproduct or service

QUESTION 25You have a piece of equipment that was purchased for your project recently for $5000 and is expected to last 5years in production, At the end of the 5 years the expected worth of the equipment is $2000. Using straight-linedepreciation, what is the amount that can be written off each year??

A. $600B. $1200C. $3000D. Zero

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The straight-line depreciation takes the purchase value of the item, minus the salvage price of the item, dividedby number of time periods. calculation is (5000-2000)/5 = $600

Depreciation is technique used to compute the estimated value of any object after few years. Straight line depreciation: The same amount is deprecated (reduced) from the cost each yearThe calculation of ‘straight line’ depreciation is very simple: ($purchase price – $disposal value)/years, where - Years = the expected life of the asset (actual or set by legislation*) - Disposal value = the likely sale price at the end of the assets useful life. *This is often standardised to a 5 year life and equates to 20% depreciation per annum

Double-declining balance - In the first year there is a higher deduction in the value - twice the amount of straightline. Each year after that the deduction is 40% less than the previous year.Accelerated depreciation Sum of year depreciation - Lets say the life of an object is five years. The total of oneto five is fifteen (The sum-of-the-years’-digits are: 5 + 4 + 3 + 2 + 1, or 15.). The numerator of the fraction forthe first year is the highest digit – in this case 5/15. The second year’s numerator is the next highest digit – in

this case – 4/15 – and so on.

QUESTION 26Which of the following plans is not done during the writting of a project plan??

A. Executive communicationB. Risk managementC. Quality ManagementD. Scope statement

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Executive communication may be a part of your communication process but not in project plan

QUESTION 27Stakeholders influence is greatest at the __________ of the project

A. BeginingB. ClosingC. ControllingD. Executing

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 28Which of the following is not part of project scope management?

A. Verify scopeB. Collect requirementsC. Create WBSD. None of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 29You are the project manager for the software Project. This project must be completed within one year. This isan example of which of the following?

A. ScheduleB. AssumptionC. ConstraintD. Planning Process

Correct Answer: CSection: (none)Explanation

Explanation/Reference:A project must be completed by a deadline is dealing with time constraints.

QUESTION 30The project management plan:

A. Identifies all the steps and processes that will be used after a project is initiatedB. Steps needed to complete a project taskC. Prepared at the begining and fixed throughout the execution of the project D. Includes project charter

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The project management plan provides the overall plan for executing, monitoring, and controlling closing theproject

QUESTION 31Which type of network diagram is also referred to Activity-on-Node (AON) diagrams ?

A. Precedence diagramming method (PDM)B. Gantt Chart Diagram (GCD)C. Dependency diagrams methods (DDM)D. Arrow diagramming method (ADM)

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Arrow diagramming method(ADM) is also referred to as Activity-on-Arrow (AOA) diagramming method.Precedence diagramming method (PDM) is also referred to as Activity-on-Node (AON) diagramming method

QUESTION 32What are commons types of cost-reimbursable contracts?

A. CPFB. CPFFC. CPIFD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:The Advantages on Cost Reimbursable Contract are:

Simpler contract statement of workusually requires less work to work the scope that fixed price

Generally lower cost than fixed price because the seller does not have add as much for risk.

QUESTION 33Information should be communicated to ________________

A. Everyone in the communication planB. Everyone on the teamC. SponsorD. Team lead

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 34You are a project manager of a project. Your project just went into integration mode. This means that yourproject _______________

A. Has been accepted by the sponsor and the clientB. Will be closed due to lack of resourcesC. Resources are being assigned other areas of the bussinessD. None of the above

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 35You are working with an organization and you found that one stakeholder not disclosing all of the costs involvedwith an upcoming project. Rather this CAPM is constructing a WBS that does not include all tasks necessary toget the project done. What you should do?

A. Talk to the CAPM about the WBS to see if you can rework it to reflect actual costs of the projectB. Confront the other project manager inmediatelyC. Mail to the PM headquartersD. Ignore IT

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 36Which document formally authorizes the project?

A. The project charterB.

C.D.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 37You are the project manager of a project and you are offering an estimate that you know will be changed afterthe contract is signed is _____________

A. Bad practiceB. Unprofessional practiceC. Bad for the buyer and sellerD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 38In PMBOK the buyer is ______________ to the project team

A. InternalB. ExternalC. OutsideD. Assigned

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Internal to the project team

QUESTION 39Define scope involves subdividing the major project deliverables into smaller, more manageable components to_______________________

A. Improve the accurancy of cost time and resource estimatesB. Define a baseline for performance measurement and controlC. Facilitate clear responsibility assigmentsD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 40Your company create software products, and introducing a new product. To determine the characteristics andfeatures of the new product line, you will have to perform ___________

A. Progressive elaborationB. Stakeholders reviewC. Plan project life cycleD. Fast backing

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The process of determining the characteristics and featuresof the product of the project is called Progressiveelaboration. Progressive elaboration is carried out via steps in detailed fashion.

Progressive Elaboration means that over time we elaborate the work packages in greater detail. ProgressiveElaboration refers to the fact that as the weeks and months pass we have planned to provide that missing,more elaborated detail for the work packages as they now appear on the horizon

QUESTION 41You are the project manager of a project. You have just completed the collect Requirement and Define Scope.What should you do next?

A. Create WBSB. Verify ScopeC. Value analysisD. Control Scope

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Create WBS is the process that follows collect Requirement and Define Scope

QUESTION 42Which process must occur after a project manager has been assigned to the project?

A. Collect requirementsB. Develop the project charterC. Develop the project statement of workD. Develop project closing document

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 43You are the project manager of a project. You have just complete the Define Activities, activity resources

estimating and Estimate Activity Durations processes. Which Process have you left out??

A. Control ScheduleB. Create WBSC. Sequence activitiesD. Operations

Correct Answer: CSection: (none)Explanation

Explanation/Reference:The PMBOK places Sequence activities between Define Activities and Estimate Activity Resources.

QUESTION 44Which of the following is NOT an input of Estimate Costs?

A. Earn Value AnalysisB. Scope BaselineC. Risk RegisterD. Human resources plan

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Earn Value Analysis is used during the execution of the project to determine resource consumption versusplanned

QUESTION 45Which of the following is NOT input of identify Risks?

A. Project CharterB. Stakeholder RegisterC. Risk Management planD. Activity Cost Estimates

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 46As a project manager of a project. You have just completed the Collect Requirement and define scope. Whatshould you do next?

A. Create WBSB. Control scopeC. Value analysisD. Verify scope

Correct Answer: A

Section: (none)Explanation

Explanation/Reference:

QUESTION 47If you are the project manager for a project and will need as many inputs to the initiation phase as possible. Ofthe following which is the best source of information for your project?

A. Historical informationB. WBSC. Bussiness PlanD. RBS

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 48Which of the following activity is not performed as part of the direct and manage project execution process?

A. Monitor implementation of approved changesB. Validate deliverablesC. Staff, train, and manage the project teamD. Manage risks and implemant risk responses

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 49You are the project manager and you have created a contract for your customer. The contract must have____________

A. Offer and considerationB. Start date and acceptance of start dateC. Signatures and stamp of a notary publicD. Signatures of all stakeholders

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 50If a project with a CPI of 1.6 what you tell?

A. The project is consumming fewer resources than anticipatedB. Is bad projectC. The project is falling behindD. The project is running ahead of schedule

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

Exam I

QUESTION 1Which is a most risky phase of a project?

A. PlanningB. ClosingC. ExecutionD. Control

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 2A lesson learned session should be held at what point in a project?

A. At the project conclusionB. At key milestonesC. When risk event occurD. When sponsor want

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Milestone is an event that receives special attention. It is often falsely put at the end of a stage to mark thecompletion of a work package or phase. But milestones are rather to be put before the end of a phase so thatcorrective actions in case of problems can still be met and the deliverable can be completed in time.In addition to signaling the completion of a key deliverable, a milestone may also signify an important decisionor the derivation of a critical piece of information, which outlines or affects the future of a project. In this sense,a milestone not only signifies distance traveled (key stages in a project) but also indicates direction of travelsince key decisions made at milestones may alter the route through the project plan.

QUESTION 3What are the outputs of initiation process?

A. Project charter and PM assignedB. ConstraintsC. AssumptionsD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 4Which process group is for detailed resource assigments and responsabilities?

A. Human resources management planB. Project charterC. AplanD. Project management plan

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Develop Human Resource Plan: Planning, identifying, documenting, and assigning project roles,responsabilities, and reporting relationships to individuals groups.

QUESTION 5You are the project manager for a project. Project is a global project. Some peoples are working from US andsome are from India. Client says budgets should no cost more than $12 millions. Because of the globalconcerns, the final budget must be in U.S. dollars. This is an example of which of the following?

A. InternationalizationB. Budget constraintsC. Management constraintsD. Quality constraints

Correct Answer: BSection: (none)Explanation

Explanation/Reference:This is an example of Budget constraints. The budgets must not exceed $12 millions.

Budget constrain t are anothe element of the classic Triple constraint (Cost, schedule, Scope). Budget limit theproject teams ability to obtain resources and might potentially limit the scope of the project. For exampleComponent X cannot be part of this project, because the budget does not support it.

QUESTION 6You are the project manager for a project. Project is installing AC to hotel rooms. You have done project costand time estimates, told the customer that the estimates provided will be accurate if the rooms meet therequirements like (Wooden Coated). This is an example of which of the following?

A. RiskB. AssumptionC. ConstraintsD. Budget

Correct Answer: BSection: (none)Explanation

Explanation/Reference:A and C are incorrect because the scenario did NOT describes a risk or constraint.This is an example ofassumptions because estimates provided will be accurate if the rooms meet the requirements like (WoodenCoated)

QUESTION 7When you are developing the estimates for project. you choose in amathematical model to predict estimate.What type of estimation method are you using?

A. Parametric estimatingB. Bottom-up estimatingC. Top-down estimatingD. Analogous estimating

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Analogous Analogous estimating is also referred to as top-down estimating. This is one of the most commonestimating tools because it uses the actual costs of a previous project as the basis for cost estimating the newproject. This method, though widely used, is simply a best-guess. The logic behind this estimate is that if thisproject is twice as big as the previous project, it is likely to cost twice as much. Although this estimate is basedon expert judgment, it is also inaccurate unless projects are, in fact, the same

Parametric Parametric estimating is a method that uses statistical relationships between historical data and asmany other variables as possible. We see this method commonly used in construction, as in price per squarefoot; or in software development, as in cost per line of code written. Parametric estimating is still notsignificantly detailed but is an excellent tool when quick budget or planning numbers are available. Parametricestimating also requires that an up-to-date and populous historical database exists that includes details andcosts on many previous projects.

Bottom-up Bottom-up estimating is done when individual project tasks or work packages are cost estimated,and then the sums of all tasks are averaged to get a project total. This is the most sophisticated estimatingmethod of the three methods and is the only one that should be considered legally binding. To complete abottom-up project estimate, you need to have a fully developed and detailed scope of work. The scope of workwill include detailed drawings, specifications, vendor quotes and any other details necessary to complete anaccurate estimate.

QUESTION 8Purchasing insurance is an example of _________________

A. TransferB. AcceptancesC. MitigationD. Contingency

Correct Answer: ASection: (none)Explanation

Explanation/Reference:It means transfer the risk to a third party

QUESTION 9How many communication channels exits in a team of 10 members?

A. 45B. 10C. 30D. 20

Correct Answer: ASection: (none)

Explanation

Explanation/Reference:(N)(N-1)/2

QUESTION 10The primary output of the project closing process _______________________

A. To formalize and distribute all information pertaining to the project closingB. Lesson learnedC. To get customer and sponsor approvalD. Milestone list

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 11Which type of network diagram allows you to depict four types of dependencies (Finish-to-start, finish-to-finsih,start-to-start, and start-to-finish)?

A. Precedence Diagramming Method (PDM)B. Gant Chart Diagram (GCD)C. Dependencie Diagram Method (DDM)D. Arrow Diagramming Method (ADM)

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Precedence Diagramming Method The PDM shows nodes, representing activities, connected byarrows that represent dependencies. To represent that activity B is dependent on activity A. (in other words,activity A must be complete before activity B starts), simply draw an arrow from A to B. PDM diagrams are alsoreferred to as activityon-node (AON) diagrams because the nodes contain the activity duration information.(You don’t have enough information yet to complete all theinformation presented here. You’ll fill in the duration information during activity duration estimating.) In fact,nodes generally contain several pieces of information, including:

➤Early star t—The earliest date the activity can start➤ Duration —The duration of the activity➤ Early finish —The earliest date the activity can finish➤ Late start —The latest date the activity can start➤ Late finish —The latest date the activity can finish➤ Slack —Difference between the early start and the late start dates

You can represent four types of dependencies with a PDM diagram:

➤➤➤➤ Finish-to-start (the most common dependency type)—The successor activity’s start depends on thecompletions of the successor activity.➤➤➤➤ Finish-to-finish —The completion of the successor activity depends on the completion of the predecessoractivity. ➤➤➤➤ Start-to-start —The start of the successor activity depends on the start of the predecessor activity.➤➤➤➤ Start-to-finish —The completion of the successor activity depends on the start of the predecessor activity

The PDM diagram in Figure shows eight activities, labeled A–H. The arrows show how some activities aredependent on other activities. For example, activity B cannot start until activities A and C are complete. Toshow this dual dependency, you draw an arrow from A to B and another arrow from C to B.

Arrow Diagramming Method The arrow diagramming method (ADM) is similar to the PDM, except thatall dependencies are finish-to-start. Also, durations are generally depicted on the arrows. For this reason, theADM diagram is also called the activity-onarrow (AOA) diagram. Figure shows an example of an ADMdiagram.

Dependencies are noted in a similar fashion to the PDM diagram, but there is another type of activity in ADMdiagrams. Look at the dependency between node 3 and node 2. The arrow has a dotted line, which means theactivity has no duration and is called a dummy activity. The purpose of dummy activities is simply to allow youto depict dependencies.

Gantt chart GCD is a type of bar chart, developed by Henry Gantt, that illustrates a project schedule. Ganttcharts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminalelements and summary elements comprise the work breakdown structure of the project. Some Gantt chartsalso show the dependency (i.e., precedence network) relationships between activities

QUESTION 12Which of the following best describes project scope?

A. The work that must be done in order to deliver a product with the specified feature an functionB. The description of the project deliverablesC. The authorizing document that allows the project manager to move forward with the project and to assign

resources to the tasksD. The process of planning and executing all of the required work to deliver the project

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 13In which phase you define the final deliverable?

A. ClosingB. ExecutionC. PlanningD. Initiation

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Project will close after the final deliverable. Final deliverables are defined in the closing phase.

QUESTION 14The activity that is most concerned with the current status of the project schedule is called ________________

A. Project time managementB. Control ScheduleC. Monitoring and controlling

D. All of the above

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 15Your project team is composed of team members in three countries plus a contrator team in a fourth country.What tool would optimize communication?

A. Extranet-based electronic document repositoryB. Manual filing systemC. War loomD. Verbal

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 16Conformance to specifications document is one description of ____________________

A. QualityB. ScopeC. IntegrationD. Procurement

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Quality on a project means that you are conforming to a standard that is set before you start the project

QUESTION 17Customer formally accepts the deliverable of each project phase. This process is know as___________________

A. Verify ScopeB. Quality AssuranceC. Quality controlD. Quality Measurement

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 18________________ Is the best choice for buyer when the item is well defined.

A. Cost plus incentive feeB. Fixed priceC. Time and materialD. None

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Cost plus incentive fee is always the lowest risk for the buyer if the scope of work is NOT well defined. Fixedprice and purchase order are the best choice for buyer when the item is well defined.

QUESTION 19You are the project manager of a project and the project is aminth into the executing phase. There are somecliques forming among the team members. Which leadership style you follow for best outcome?

A. SupportingB. DelegatingC. CoachingD. Directing

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Situational leadership style is coaching. Coaching is best for this example.

The leadership styles includes:

Directing: Telling others what to doFacilitating: Coordinating the input of othersCoaching: Instructing othersSupporting: Providing assistance along the wayAutocratic : Making decisions without inputLaissez Faire: Has a hands-off policy and the team is entirely self-led regarding the decision making processConsultative: Inviting ideas from othersConsensus: Problem solving in group with decision making based on group agreement

QUESTION 20Cost benefit analysis, score card modelling, paybacks periods, and internal rate of return are examples of:

A. Enterprise benefits measurements methods when selecting a projectB. Integarl parts of the SOWC. Ways to ensure stakeholders commitmentD. Project selection methods

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Projects are seeded from the recognition of a regulatory or bussines need.

QUESTION 21When the version control numbers should change?

A. Any change occursB. Major changes are madeC. Any change related to scope onlyD. Only if minor changes are made

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 22For 10 individuals how many communication channels exists?

A. 45B. 12C. 10D. 5

Correct Answer: ASection: (none)Explanation

Explanation/Reference:N0 Communication Channel = N*(N-1)/2, N= Numero de individuos

QUESTION 23Market conditions are part of ___________________

A. Enterprise environmental factorsB. Project management concernsC. Organizational process assetsD. Cost factor

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Market conditions will influence all factors of procurement

QUESTION 24Which of the following is an output of Define Scope?

A. PBS B. Project scope statementC. WBS TemplateD. Constraints

Correct Answer: BSection: (none)Explanation

Explanation/Reference:The project scope statement is the definition of the project—what needs to be accomplished. The DevelopPreliminary Project Scope Statement process addresses and documents the characteristics and boundaries ofthe project and its associated products and services, as well as the methods of acceptance and scope control.A project scope statement includes: · Project and product objectives· Product or service requirements and characteristics· Product acceptance criteria· Project boundaries· Project requirements and deliverables· Project constraints· Project assumptions· Initial project organization· Initial defined risks· Schedule milestones· Initial WBS· Order of magnitude cost estimate· Project configuration management requirements· Approval requirements

QUESTION 25The buyer and seller are bound by the ______________

A. ContractB. ResponsabilitiesC. WBSD. Identification

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 26Which is not the tool and techniques used in Contract Administration:

A. Contract change control SystemB. Contract negotiationC. Payment SystemD. Performance rating

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 27Which describes how cost variances will be managed?

A. Cost management planB. Cost baselineC. Cost estimateD. Chart of accounts

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 28A _________________ Is a series of actions bringing about a result.

A. Project planB. ProcessC. ScheduleD. Flowchart

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 29A project Cost Mangement plan is created as a part of:

A. Develop Project Management Plan processB. Control Cost ProcessC. Determine Budgets ProcessD. Estimate Cost Process

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Ther is no separate process in the Project cost estimation Knowledge area to develop a cost managementplan. It is developed in Develop Project Management Plan process

QUESTION 30_____________________ Involves using project characteristics in a mathematical model

A. Analogous estimatingB. Life-cycle costingC. Parametric ModellingD. Bottom Up estimating

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Parametric Modelling . Using a mathematical model example (Price per square foot)

Analogous Analogous estimating is also referred to as top-down estimating. This is one of the most commonestimating tools because it uses the actual costs of a previous project as the basis for cost estimating the newproject. This method, though widely used, is simply a best-guess. The logic behind this estimate is that if thisproject is twice as big as the previous project, it is likely to cost twice as much. Although this estimate is basedon expert judgment, it is also inaccurate unless projects are, in fact, the same

Parametric Parametric estimating is a method that uses statistical relationships between historical data and asmany other variables as possible. We see this method commonly used in construction, as in price per squarefoot; or in software development, as in cost per line of code written. Parametric estimating is still notsignificantly detailed but is an excellent tool when quick budget or planning numbers are available. Parametricestimating also requires that an up-to-date and populous historical database exists that includes details andcosts on many previous projects.

Bottom-up Bottom-up estimating is done when individual project tasks or work packages are cost estimated,and then the sums of all tasks are averaged to get a project total. This is the most sophisticated estimatingmethod of the three methods and is the only one that should be considered legally binding. To complete abottom-up project estimate, you need to have a fully developed and detailed scope of work. The scope of workwill include detailed drawings, specifications, vendor quotes and any other details necessary to complete anaccurate estimate.

QUESTION 31Adjusting Leads and Lags is atechnique for:

A. Develop ScheduleB. Estimate Activity DurationsC. Estimate Activity resourcesD. Sequence Activities

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 32Analogous Estimate Cost is ____________________

A. Generally AccurateB. Generally less accurateC. Bottom-Up estimatingD. None

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Analogous Estimate Cost is Generally less accurate. Analogous Estimate Cost Uses Expert Judgement. It isused when refernce projects are similar. It is useful in early phases of the project.

QUESTION 33With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is_________________

A. 30.0B. 22.5C. 25.0D. 27.5

Correct Answer: ASection: (none)Explanation

Explanation/Reference:mean= (20+30+40)/3

QUESTION 34what is the mean of PMBOK

A. Project Manager BookB. Project manager Body of KnowledgeC. Project Manager Book of knowledgeD. None of above

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 35Which of the following is an output of a Verify Scope process?

A. Formal acceptanceB. WBS templateC. SOW AcceptanceD. Rework

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 36What involves determining what quantities are to be used to perform project activities.

A. Resource planningB. Estimate costsC. Determine BudgetD. Control Costs

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Resource planning. Planning, identifying, documenting, and assigning projects roles, responsabilities, andreporting realtionships to individuals groups.

QUESTION 37Which of the following is NOT an example of a type of schedule report?

A. Gantt ChartB. Milestone ChartC. Fishbone DiagramD. Network diagram

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Fishbone diagrams otherwise called as Ishikawa diagrams (or cause-and-effect diagrams) are diagrams thatshow the causes of a certain event. In project management, this tool is used in Quality Management & RiskManagement processes.

QUESTION 38A change control Board should be ___________?

A. FlexibleB. Include the Project managerC. Appropriate authorityD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:CCB should have all the mentionated characteristics

Change Control Board Change control board can be referred to as a board or committee or group ofstakeholder’s, that analyze and review the change requests that have been forwarded by the projectmanagement team and accordingly take decision whether the change request needs to be accepted orrejected.

Consists of stakeholder’s.Approve or reject changes.Decisions are often accepted and considered final.Role clearly defined.All change requests should go through it.

QUESTION 39Project risk is defined as the cumulative effect of chances of _______________ which will adversely affectproject objectives.

A. Likely eventsB. Complex activitiesC. Complex schedulesD. Uncertain occurrences.

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 40Which of the following is not a tool or technique for a Source selection?

A. Contract negotiationB. Weighting systemC. Payment systemD. Screening system

Correct Answer: CSection: (none)Explanation

Explanation/Reference:The Source Selection process uses several tools and techniques to select the final vendor. This is usually acomplicated process, except for the cases where price is the only determining factor. Let’s examine each of thetools and techniques of this process.

Contract NegotiationIn contract negotiation, both parties come to an agreement regarding the contract terms. Negotiation skills areput into practice here as the details of the contract are ironed out between the parties. At a minimum, contractlanguage should include price, responsibilities, regulations or laws that apply, and the overall approach to theproject.

Weighting SystemsWeighting systems assign numerical weights to evaluation criteria, then multiply this by the weight of eachcriteria factor to come up with total scores for each vendor. Weighting systems are useful when you havemultiple vendors to choose from, as they allow you to rank order the proposals to determine the sequence ofnegotiations. There is an example of a weighted scoring system in Chapter 3. These systems are commonly used toevaluate vendor proposals.

Screening Systems Screening systems use predetermined performance criteria to screen out vendors. Perhaps your projectrequires board-certified engineers. One of the screening criteria would be that vendors propose project teammembers who are board-certified engineers. If they don’t, they’re eliminated from the selection process.Weighting systems and screening systems are often used in combination to come up with a selection.

Independent EstimatesYour procurement department might conduct an independent estimate of the costs of the proposal and use thisto compare to the vendor prices. If there are large differences between the independent estimate and theproposed vendor cost, one of two things is happening: The SOW, or the terms of the contract, was not detailedenough to allow the vendor to come up with an accurate cost, or the vendor simply failed to respond to all therequirements laid out in the contract or in the SOW.

QUESTION 41Which of the following is ensuring that aall features and functions are included in a product or service

A. Project ScopeB. Project VerificationC. Project ControlD. Product Scope

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 42A major assumption of all network schedulling methods is that the activity duration must be ________________

A. Statistically dependentB. Variance distributedC. Statistically independentD. Deterministic

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 43Which of the following is not part of the project cost baseline but is included in the project budget?

A. Management Contingency ReserveB. Management OverheadsC. Project management PlaningD. Activity Cost Contingency Reserve

Correct Answer: ASection: (none)Explanation

Explanation/Reference:The diference between the Cost Baseline and Funding requirement at Project competion is MnagementContingency Reserve Management Contingency Reserve is NOT part of aproject Baseline.

QUESTION 44In an optimal organization structure, the project manager is:

A. FunctionalB. Weak matrixC. ProjectizedD. Dedicated Project team

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 45Which of the following is not part of the Earned Value calculations?

A. Unknown UnknownsB. Project BudgetsC. Knowns UnknownsD. Amount of work completed

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 46What is the purpose of the WBS?

A. To show which work elements have been assigned to organizationals unitsB. To ensure that all work within a project is identified and defined within a common frameworkC. To show the organizational structure of a programD. All of the above

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 47A project scope Management includes:

A. InitiationB. Project plan executionC. Overall Change ControlD. Report Performance

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Project scope Management includes: initiation, Collect requirements, define Scope, verify scope and controlscope.

QUESTION 48At which stage, stakeholders have the maximum influence on a project?

A. Initial stageB. Closing StageC. Execution stageD. None of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 49An activity that consumes no time or resource and show only that a dependency exists between two activities iscalled:

A. A milestoneB. A hammockC. A dummy activityD. A and C

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 50

A change request can occur due to:

A. An external event such as a change in govermment regulationB. An error omission in defining the scope of the productC. An error omission in defining the scope of the projectD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

Exam J

QUESTION 1Another term for top down estimating is:

A. Anallogous estimatingB. Life-cycle costingC. Parametric modellingD. Bottom up estimating

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Analogous Estimating , is one form of expert judgment and it also known as Top-down Estimating. Thistechnique is used to determine the duration of the project. After finalizing the high level scope/requirement, thePM will refer & compare the previously completed project’s similar activities with the current activities anddetermine the duration.

This estimation technique will be applied to determine the duration when the detailed information about theproject is not available, usually during the early stages of the project. This technique will look the scope/requirement as a whole single unit to estimate. This estimate will give a ball-park idea about the estimation andwill have bigger variance.

Eg : To estimate the time required to complete the project of upgrading XYZ application’s database version to ahigher version, is to compare similar past projects and estimate the duration. This is done irrespective of thecomplexity, size and other factors.

QUESTION 2A Reserve Analysis is a technique for:

A. Estimate Activity DurationsB. Estimate Activity ResourcesC. Sequence ActivitiesD. Define Activities

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Reserve Analysis is one of the techniques used to determine a project budget. During Reserve Analysis, aproject is analyzed from a cost overruns point of view and buffers are placed in appropriate place. Thesebuffers are called Contingency and Management Reserves.It is also referred to as a “contingency reserve” or “buffer.” The concept is quite simple—we know to expect theunexpected, so we plan for it. Applicable to both time and cost , it is the technique of adding some extra time tocomplete activities and extra funds to the budget.

QUESTION 3The scope management provides:

A. A basis for future decisions about the project B. A baseline to accomplish verification measuresC. A baseline to evaluate potential scope changes

D. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 4A project plan is:

A. A formal approved document used guide both project execution and project controlB. A document issued by senior management that provides the project manager with the authority to apply

organizational resources to project activitiesC. A narrative description of products or services to be supplieD. A document describing the organizational breakdown structure of the company

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 5Which of the following relationship is used in the Arrow Diagramming Method (ADM)

A. Start-To-FinishB. Finish-to-StartC. Start-to-StartD. Finish-to-Finish

Correct Answer: BSection: (none)Explanation

Explanation/Reference:An arrow diagramming method (ADM) is a network diagramming technique in which activities arerepresented by arrows. It is used for scheduling activities in a project plan.The precedence relation between activities is represented by circles connecting to one or more arrows. Thelength of the arrow represents the duration of the relevant activity.Sometimes a "dummy task" is added, to represent a dependency between tasks, which does not represent anyactivity.

The ADM is also known as the activity-on-arrow (AOA) method, it only show finish-to-start relationship. ADMnetwork drawing technique the start and end of each node or event is connected to an arrow.

The start of the arrow comes out of a node while the tip of the arrow goes into a node. Between the two nodeslies an arrow that represents the activity.

The event represented by the circular node consumes neither time nor resources.A node is a specific, definable achievement in the project.It has zero duration and consumes nil resources.All activities that lead into a node must be completed before the activity lies following this node can start.

QUESTION 6When should a project mnager be assigned to a project?

A. As early in the project as feasibleB. Preferably before much project planning has been doneC. At least prior to the start of project plan executionD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 7Which of the following tools and techniques are commonly used in a Dfine Scope Process?

A. Product AnalysisB. Expert JudgementC. Alternative IdentificationD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 8Your project has a budget of $240,000 and is expect to las for 1 year, with the work and budget spread evenlyacross all months. The project is now in the fourth month, the work is on schedule, but you have spent$120,000 of the project budget. What is your COST Variance percentage in this case?

A. -50%B. 50%C. 40%D. 20%

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Solution:Execute Percentage > 12 ---------- 100% 04 ---------- X

X= 0.333333%

EV Earned Value= Execute Percentage% * Budget of the projectEV=0.33333%*240.000EV= 80.000AC= Actual Cost = 120.000

CV= EV - AC CV= 80.000-120.000 = -40.000

CV% = CV/EV CV% = -40.000/80.000 = -0.5CV% = -50%

Cost Variance (CV) is very important factor to measure project performance. Cost Variance (CV) indicateshow much over or under budget the project is.Cost Variance can be calculated as using the following formula

Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC)

OR

Cost Variance (CV) = BCWP - ACWP

The formula mentioned above gives the variance in terms of cost which will indicate how less or more cost hasbeen to complete the work as of date.

Positive Cost Variance Indicates the project is under budgetNegative Cost Variance Indicates the project is over budget

Cost Variance %Cost Variance % indicates how much over or under budget the project is in terms of percentage.

Cost Variance % can be calculated as using the following formula

CV % = Cost Variance (CV) / Earned Value (EV)

OR

CV % = CV / BCWP

The formula mentioned above gives the variance in terms of percentage which will indicate how much less ormore money has been used to complete the work as planned in terms of percentage.

Positive Variance % indicates % under Budget.Negative Variance % indicates % over Budget.

QUESTION 9Which of the following is a common characteristic of most project life cycle descriptions?

A. Cost and staffing are low at the start higher towards the end and drop rapidly as the project nearscompletion

B. The probability of succesfully completing the project is highest at the start of the projectC. Stakeholders have the most influence on the final characteristics of the product at the end of the projectD. A and B

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Project Life cycle : Cost and staffing Levels

QUESTION 10

A project manager is at the project Kick-off meeting. He confidently states the vision and mission for theproject. This PM is exhibiting the following leadership style:

A. HierarchalB. AuthoritarianC. CharismaticD. Associative

Correct Answer: CSection: (none)Explanation

Explanation/Reference:The leadership styles includes:

Directing: Telling others what to doFacilitating: Coordinating the input of othersCoaching: Instructing othersSupporting: Providing assistance along the wayAutocratic : Making decisions without inputLaissez Faire: Has a hands-off policy and the team is entirely self-led regarding the decision making processConsultative: Inviting ideas from othersConsensus: Problem solving in group with decision making based on group agreement

QUESTION 11Which of the following must be measured regularly to identify variances from the plan.

A. Stakeholder requirementsB. Project performanceC. Control scheduleD. Project Control

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 12Identification of Mandatory Dependencies is done during which of the following process:

A. Sequence ActivitiesB. Develop ScheduleC. Define ActivitiesD. Estimate Activity Durations

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Dependencies that are directly related to the nature of the work being performed. This is known as harddependency or hard logic. This is also referred as Mandatory Dependencies .This dependencies will be used duing the Project Planning specifically on Activity Sequencing in TimeManagement.

Purchase the Server, Install Operating System, Install and configure Patches and finally install the RequiredSoftware are examples of mandatory dependencies. The nature of the work itself dictates the order in which theactivities should be performed.

QUESTION 13Which is the most important element of a Project Management Plan that is usefull in the Develop Humanresources Plan Process

A. Risk Manahgement activitiesB. Activity Resources RequirementsC. Budget Control ActivitiesD. Quality Assurance Activities

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Activity resource requirements. This is normally a document that describes the number of resources for eachschedule activity, and the knowledge, skills and experience of each. The work effort may be described as totalhours, or as skills set per time period. An example for the latter might be three bricklayers for a period of twoweeks. It is helpful to include assumptions and other detail in support of such estimates for each activity.

QUESTION 14In which type of organization a project manager is in complete control of the project?

A. Projectized organizationB. Balanced Matrix OrganizationC. Strong MatrixD. Weak Matrix organization

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 15In which type of organization a project manager is in complete control of the project?

A. Balanced matrix OrganizationB. Projectized organizationC. Strong MatrixD. Weak Matrix organization

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 16A trend Analysis is best described as:

A. Calculating Earned ValueB. Calculating Earned varianceC. Examining project performance over timeD. Analyzing performance of similar projects over time

Correct Answer: CSection: (none)Explanation

Explanation/Reference:In project management trend analysis is a mathematical technique that uses historical results to predict futureoutcome. This is achieved by tracking variances in cost and schedule performance. In this context, it is aproject management quality control tool

QUESTION 17To calculate the late start and late finish dates for a set of tasks, you must do:

A. An analysis of the critical pathB. A forwards passC. A backwards pass

D. A and B

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Backward Pass A calculation method used to determine late start and late finish dates for activities in CriticalPath Method. Subtract the duration from the late finish date of the last activitiy and add one to get the late startdate. This calculation method is called as Backward Pass and this is quite opposite to Forward Pass.

Forward Pass is a calculation method used in Critical Path Method(CPM) to identify the early start date andearly finish date for the activities.Based on the relationship between current activity and preceeding/succeeding activity the PM will calculate theearly start date and early finish date of the activity. The PM will do this calculation from the starting point of theactivity list. This method is called as Forward Pass

QUESTION 18Which is NOT included in Performance Improvements:

A. Improvements in individual skillsB. Improvements in amount of overtime workedC. Improvements in team behavioursD. Improvements in team capabilities

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 19Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERTweighted average?

A. 4B. 6.3C. 6D. 6.1

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Simple Average Duration Estimate = (O + M + P)/3

PERT Duration Estimate = (O + 4M + P)/6

QUESTION 20A scope management plan, in which of the following scope management processes is the scope managementplan prepared?

A. InitiationB. Collect RequirementsC. Define ScopeD. Verify Scope

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Scope management plan is one of the major Scope communication documents. The Project ScopeManagement Plan documents how the project scope will be defined, managed, controlled, verified andcommunicated to the project team and stakeholders/customers. It also includes all work required to completethe project. The documents are used to control what is in and out of the scope of the project by the use of aChange Management system. Items deemed out of scope go directly through the change control process andare not automatically added to the project work items. The Project Scope Management plan is included in asone of the sections in the overall Project Management plan. It can be very detailed and formal or loosely framedand informal depending on the communication needs of the project.

QUESTION 21Project scope Is:

A. The features and functions that are to be included in a product or serviceB. A narrative description of work to be performed under contractC. The work that must be done in order to deliver a product with the specified features and functionsD. A and B

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Project Scope "The work that needs to be accomplished to deliver a product, service, or result with thespecified features and functions"Product Scope "The features and functions that characterize a product, service, or result"

QUESTION 22The planning process are:

A. Inputs, control, status reports, Risk controlB. Define Scope, team development, Control schedule, budget control, contract administrationC. Planning, Resource planning, Quality assurance, Risk controlD. Define Scope, Resource planning, Estimate Costs, Schedule development, Define Activities

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 23A resource Leveling is a technique for:

A. Estimate Activity DurationsB. Develop scheduleC. Estimate Activity resourcesD. Sequence Activities

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Resource leveling

Helps in utilising resources consistently throughout the project. Ensures resources are not over allocated. Helpsthe project manager avoid delays caused by bad allocations. Helps the project manager identify and takeadvantage of unused times by analysing task dependencies. MSP can automatically level resources based onresource calendar, task types, dependencies, and constraints, however, I have yet to find a project managerthat has felt comfortable with the way MSP does it. I level resources manually via the Resource Usage view, butif you insist in using the automatic feature of MSP, save a copy first. If you find resource conflicts (over or underallocations) you could:

Delay certain tasks.Assign a different resource.Change task dependencies.Remove tasks.Add tasks (instead of using the MSP's split task functionality, which is not supported by some projectmanagement systems i.e. Clarity).

QUESTION 24A process that is not part of a Project Risk Management is

A. IdentificationB. SolicitationC. QuantificationD. Response Development

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 25An example of project is:

A. Billing CustomersB. Managing an organizationC. Providing a buildingD. Contructing a Building

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

http://www.gratisexam.com/