bitterent) 9 lab chemicals 10000kgkspcb.gov.in/ph/exec_sum_eng_askins biofuels_2052020.pdf ·...
TRANSCRIPT
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 1
EXECUTIVE SUMMARY
ES.1 Introduction
M/s. Askins Biofuels Pvt Ltd is proposed to establish 60 KLPD (Juice/syrup based)
distillery, 6 TPD Bio CNG, 20 TPD fertilizer powder, 42 TPD CO2, captive Power
generation of 3 MW/hr at 106/2 (P), 106/3, 109/1& 109/3 Alagawadi Village, Raybag
Taluk Belagavi District.
EIA Notification dated 14th September 2006, amended on SO 1960 (E) dated 13th
June, 2019, all non-molasses based distillery of ≤200 KLPD, is categories as “B” of
schedule, 5 (g) (Distillery). Therefore, M/s Shri Bramhanand Jaggery Industries had to
obtain Environmental Clearance from KSEIAA, Karnataka for the Proposed 60 KLPD
(Juice/syrup based) distillery, 6 TPD Bio CNG, 20 TPD fertilizer powder, 42 TPD CO2,
137 TPD Khandasari Sugar unit, expansion of captive Power generation from 900
KW/hr to 4.4 MW/hr in the existing premises of 168 TPD Jaggery powder plant
located at Survey. No. 106/2, 106/3, 109/1& 109/3 Alagawadi Village, Raybag Taluk
Belagavi District. TOR application was submitted on 26-09-2019
(SIA/KA/IND2/43701/2019). The subject was placed in 232nd KSEAC meeting held on
17th October 2019. Accordingly, TORs for the project was issued vide ref SEIAA 36
IND 2019 dated: 11.12.2019. Due to management decisions, it was decided that, the
establishment of 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG, 20 TPD
fertilizer powder, 42 TPD CO2, captive cogeneration Power generation of 3 MW/hr
will be taken up by the new industry namely M/s Askins Biofuels Pvt Ltd., excluding
existing Jaggery industry operated by M/s Shri Bramhanand Jaggery Industries.
Based on this, the TOR application was resubmitted on 27.12.2019. The subject was
placed in 237th KSEAC meeting on 3rd January 2020 for issue TORs. Accordingly, TORs
for the project was issued vide ref SEIAA 47 IND 2019 dated: 25.02.2020 & is
enclosed in this report.
ES.2 Project Description
M/s. Askins Biofuels Pvt Ltd is proposed to establish 60 KLPD (Juice/syrup based)
distillery, 6 TPD Bio CNG, 20 TPD fertilizer powder, 42 TPD CO2, captive Power
generation of 3 MW/hr at Alagawadi Village, Raybag Taluk Belagavi District. Salient
features of the proposed project are detailed below:
ES
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 2
Table ES.1 Salient features of the proposed Project
Sl.
No Items Particulars
1 Objective of the
Project
Proposed 60 KLPD (Juice/ Syrup based) distillery, 6 TPD Bio
CNG, 20 TPD fertilizer powder, 42 TPD CO2, Captive Power
generation of 3 MW/hr
2 Promoters M/s. Askins Biofuels Pvt Ltd
3 Total Investment, Rs Rs 80.29 Crores
4 Project location Survey. No 106/2 (P), 106/3, 109/1& 109/3 Alagawadi Village,
Raybag Taluk Belagavi District
5 Latitude & Longitude 16°30'5.54"N; 74°53'53.19"E
6 Extent of land 9 Acres 12 Gunta
7 Category of Project 5 (g) Distillery
8 Man Power During Construction: 100 No’s
During Operation : 79 No’s
9 Water demand and
Source
Fresh water demand for distillery: 478 KLD
Source: Borewell
10 Boiler 30 TPH
11 Steam Steam generation: 30TPH
Steam required: 13.19TPH
12 Fuel 100% Bagasse
13 Power supply Total power generation and utilisation: 3 MW/hr
Proposed DG Set of capacity: 2 X 250 KVA
14 Number of working
days
250 days
15 Project
implementation
period
12 months after obtaining EC and CFE
ES 2.1 Raw material Requirement
List of raw material required for Distillery unit are as follows:
Table ES.2 Raw Material Statement–Distillery
Sl.
No Raw Material Quantity Transportation Source Storage
1. Sugarcane juice 233 TPD
Through
pipeline
Local -
2. Chemicals
1 Sulfuric Acid 105 Kg/day By road through
Lorry
Local/
Maharashtra
Closed chemical
storage rooms 2 Urea 105 Kg/day
3 TRO 3 ltr of Alcohol
production
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 3
4 Hydrated Lime 600 kg/day
5 Commercial
Hydrochloric Acid
110 Kg/day
6 Sodium Hydroxide 90 Kg/day
7 Sodium Hypo-
Chloride
0.2Ltr. Per Kl. of
Alcohol
8 Sodium Hypo-
Chloride
(Denatured &
Bitterent)
0.002 Kg./ Per
Ltr
9 Lab Chemicals 10000Kg /
Month
Table ES.3 Fuel for boiler
Sl
No Fuel Quantity Source Transportation Storage
01 Bagasse
(100%) 12900 Kg/hr
Neighbouring
industry
Bagasse
conveyor
Stored in
Bagasse Yard
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 4
ES 2.2 Process flow sheet
Following flowchart details the manufacturing process of distillery.
Fig ES.1 Process Flow diagram of distillery (60 KLPD)
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 5
Fig ES.2 Process flow chart- Simplified
Fig ES 3 Process Flow Diagram for Dehydration Process
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 6
Fig ES 4 Process flow chart-BioCNG
Fig ES 5 Process Flow diagram of cogeneration
ES 2.4 Products and by products
Following table lists the final product and by product details.
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 7
Table ES.4 List of Proposed products
Sl. No Products Quantity
1 Ethanol / Extra Neutral Alcohol/RS 60 KLPD
2 Bio CNG 6 TPD
3 Fertilizer powder 20 TPD
4 CO2 42 TPD
5 Power 3 MW/Hr
ES.3 Description of the Environment
In order to assess the baseline environmental status of the project, monitoring of
various environmental attributes were conducted by M/s EHSConsultants Private Ltd.,
during October 2019 – December 2019. In addition to the baseline environmental
monitoring, field inspection in the study area, collection of secondary information for
all the environmental components and discussions with the officials and local public
were conducted by the study team.
3.1 Land Use: buffer zone is dominated by Fallow land (38.22%) followed by
Cultivated land (32.80%), Harvested Land (16.88%) and Barren land (10.51%). Next in
the order is water body and built-up. The ground truth survey revealed that the
buffer zone dominated by the Fallow land followed by Cultivated land.
The Digital Elevation Model (DEM) for the study area indicate that, the difference is
elevation for study area is approximately 444 m - 576 m (refer DEM map) above
Mean sea level. The Project Area may lie at the elevation of 500-520 m above Mean
Sea Level.
The slope of the study area varies from 0-18 degrees from Very gentle slope to
Moderately Steep slope. Major portion of the study area covers very Gentle Slope;
the project site falls under very gentle slope i.e. 0-5 degree.
3.2 Land Environment: Soil samples were collected at 9 locations. It is observed
that, soil type in the study area varied from loam to sandy loam. Rill erosion is found
in the study area. In the study area Maximum pH of 6.61 was recorded at S-4
Hunashikodi indicating Neutral soil reaction and minimum of 6.07 was recorded at
Project site-east indicating Moderately acidic soil reaction.
3.3 Meteorology: Meteorological monitoring was carried out at project site during
the study period. Watchdog 2900 ET was installed at site to record Solar Radiation
(Watt / sq.m), Relative Humidity (%), Temperature (°C), Rainfall (mm), Wind Direction
(Deg), Wind Gust (km/hr). Temperature during the study period was in the range of
15.2°C-30.8°C.
3.4 Air Environment: Ambient air quality monitoring was carried out at eight
locations. The results of the AAQM reveals that, measured values for PM10, PM2.5,
SO2, NO2 and CO were within the NAAQ standards, 2009 and The lead and nickel
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 8
detected in small quantities in some instances ranging 0.012µg/m3 ans 1.15-3.57 ng/
m3 respectively in some location of the study area. Values for Arsenic, Benzene,
benzo (a) pyrene were found to be BDL at all point of time during the study period
3.5 Noise Levels: Ambient noise level monitoring conducted at 8 locations in and
around the proposed project site. The result of the noise levels during day and night
time was found to be within the CPCB standards.
3.6 Surface and ground water quality:
a) Surface water: Surface water quality were analysed from Harugeri Kere,
Ghataprabha left canal (Branch)-(Near Badabyakud) & Krishna River and results
reveals that, BOD varied between 8 mg/l -13mg/l, COD from 32mg/l -56 mg/l. Total
dissolved oxygen was found to be in the range of 4.8 mg/l to 5.2 mg/l, TDS varied
between 162 mg/l -540 mg/l confirming to Class D in the both samples. Indicates
Most of the heavy metals were not detected. Pesticides were absent. DO level
observed to be good. Organic Pollution is minimal.
b) Ground water quality: The study area comprises of majority of the
wells/Borewells/Tubewells/ located at all the village settlements. Additionally, farmers
with their own tube wells/bore wells in their fields were using the water for irrigation
purpose & domestic needs. Seven Groundwater (Bore well water) samples were
collected in the study area and have been analyzed for describing the baseline water
environment. Total dissolved solids in the sample ranged from 572 mg/l to 1636
mg/l, Total Hardness was found to be in the range of 100 mg/l - 622 mg/l. The
measured values for the parameters for those standards have been specified were
observed to be within the said standards except Total Hardness (622mg/L) against
standard of 200-600mg/L. Most of the heavy metals were not detected. Pesticides
were absent. Overall suitable for potable and domestic use..
3.7 Geology: The study area and its environs comprise Basalt belonging to Deccan
Traps of Upper Cretaceous to Lower Eocene age. Basalt is the litho unit observed in
the project area. Geomorphology of the study area environs is Plateau weathered
with few Valleys.
3.8 HYDROGEOLOGY:
The study area comprises rock formations belonging to Upper Cretaceous to lower
Eocene age. Fissured basalt constitutes major aquifers in the Region. Secondary
structures like joints, fissures and fractures present in these formations act as
conduits for movement and storage of water. Groundwater occurs in weathered and
fractured zones. The occurrence, movement and recharge to aquifers are controlled
by various factors like fracture pattern, degree of weathering, Geomorphologic setup
and amount of rainfall received. The recharge conditions are moderate.
The depth to water level varied between 2.0 to 76.0 m. In general, the water levels are
between 46.0 to 70.0m bgl. The annual water level fluctuation is reported to be
varying between 3.0 to 15.0 m in the study area. The flow direction follows the
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 9
general topography of the area. The general flow direction of groundwater in the
study area is towards west.
3.9 Biological Environment: The existing green belt at the project site contains 20
tree species (141 trees) with all the dominant trees with the girth size of maximum
trees ranging from 1-60 cm with medicinal, timber and ornamental values. The study
area supports a good number of trees with the girth size of maximum trees ranging
from 30-90 cm. However, the tree species diversity in the study area is considered to
be very low with only few dominant (repeated) species such as Eucalyptus tereticornis,
Cocosnucifera and Sennasiamea recorded in large numbers which may be due to its
economic value and rest of the species recorded between values 1-7. A total of 39
bird species were recorded in the study area indicating that the study area provides
the necessary resources such as food, habitat and breeding grounds. Subsequently, a
fair number of butterfly species along with mammals and reptiles were also recorded
in the study area.
3.10 Socio Economic Studies: As part of the survey, eight villages considered for the
socio-economic study, located within 10 Km radius of the project site are spread
across Rayabag taluk of Belagavi district. The total geographical area of the villages is
about 15624 ha with 14007 households. Area wise Harugeri have maximum area of
4130 ha and Bomanal village have minimum area of 762 ha.
During the focus group discussions, it was revealed that nearly 94% of the
respondents are aware of the proposed project and feel that industrial development
is necessary for employment generation, especially for the current and future
generations in the area. Development planned projects are necessary to uplift
standard of living of the people, revives economics and alleviate poverty. With rising
literacy levels and awareness about growing opportunities, the youth in the area are
focused more on non-farm sector and service sector employment.
ES.4 Anticipated Environmental Impacts and Mitigation
Measures
ES 4.1 Land Environment
During construction phase: The land use of the project site area will get modified
by the implementation of the proposed project. Activities such as clearing, levelling,
cutting and filling, foundation works through excavation will significantly leads to
dislodging of soil particles and intern erosion due to loosening of top soil.
Preserving the top soil and reusing it for the greenbelt development, slope
stabilisation and soil embankment, soil conservation measures, water sprinkling
undertaken as part of mitigation measures.
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 10
ES 4.2 Air Environment
During construction phase:
Impact of construction activities on air quality is a cause for concern mainly in the dry
months due to settling of dust particles. The main sources of emission during the
construction period are the movement of equipments at site and dust emitted during
the leveling, grading, earthworks, foundation works and other construction related
activities. The dust emitted during the above mentioned activities depend upon the
type of soil being excavated and the ambient humidity levels. The impact is likely to
be for short duration and confined locally to the construction site itself. The impact
will, however, be reversible, marginal, and temporary in nature and levels decreases
gradually as project progresses. However, frequent watering of unpaved roads and
disturbed roads, restriction of speed of vehicles, covering the tarpaulin sheet for the
vehicles carrying loose and fine materials will reduce the emission of dust.
During the operation Phase:
The main sources of Air Pollution in the proposed project will be the operation of
Boiler. Due to operation of boiler (30TPH), emission of PM is anticipated. Deposition
of PM on the surrounding agricultural fields (gradually on a long term) will reduce
the crop yield and indirectly on the economy of livelihood of marginal workers
located nearby. ESP will be provided to 30 TPH boiler with stack height of 45mt.
From the air quality modeling studies, it is found that, impact on air quality will be
minimum during this stage with the installation of APC. Greenbelt development of
33% of total land will create aesthetic environment and also acts as a pollution sink
for pollutant emissions. Stacks/chimneys will be provided to Boiler and D.G.Sets as
per KSPCB Norms.
ES 4.3 Noise Environment
During construction phase: The various sources of noise pollution will be from the
operation of machineries like compactors, concrete plant, cranes etc. Other sources
of noise pollution during construction period includes movement of vehicles for
unloading of construction materials, fabrication, handling of equipment and
materials, operation of batching plants. Overall, the impact of noise generated on the
environment is likely to be insignificant, reversible and localized in nature and mainly
confined to the day time.
By providing the proper PPEs and restriction of construction timings to day time only
will reduce the adverse effect.
During the operation Phase: Noise generating machinery operations at Distillery
unit are operation of boiler, turbine operations, noise making equipments such as
cutters, crushers, etc. During operation phase, various industrial activities viz.,
movement of vehicles, turbine operations will result in increase of Ambient Noise
levels to 90 dB (A) (Baseline value: 72.57 dB (A)-during day) thereby affecting the
Fauna. All connecting roads to industry will be metalled one. Vehicle maintenance,
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 11
proper lubrication to machinery will be arranged. Tree plantation on the campus and
on the connecting roads is initiated and will be done each year.
ES 4.4 Water Environment
During construction phase: Impact on the surface water is not likely anticipated
since there are no nearby (<500m radius)/adjacent surface water sources).
Unscientific disposal of sewage from the labour camps, impacts on the neighbouring
agricultural fields due to seepage/draining affecting the crops yield. Improper
treatment of sewage (8 KLD) from labor camps leads to infiltration into the
subsurface soil and finally affects the ground water quality of the region. This will
also create unaesthetic conditions in the site, attracts mosquitoes/flies, thereby
chances of deteriorating the health of the workers in unhygienic conditions will arise
resulting ill conditions, thereby affecting productivity at work. Extraction of ground
water will result in depletion of ground water levels.
As a precautionary measure, Sewage generated from labour camps will be treated in
mobile STP (10KLD). This will avoid anticipated impacts on the ground water quality
of the region. Rainwater recharging measures (surface run-off) will improve the
groundwater regime of the area positively on a long term. Water for construction
activities will be sourced from private water tankers.
During operation phase: If process condensate effluent is not treated to KSPCB
discharge standards, in case if the same is discharged onto the land for
irrigation/greenbelt development/gardening, impact on the neighboring agricultural
fields is anticipated through seepage/infiltration factors by affecting the crop yield
including contaminating sub soil surface. Impact on groundwater/subsoil due to
disposal of spent wash. Both surface/Ground water and land will get polluted if
disposed without any treatment. It will affect surrounding flora, fauna & also the
health of the people.
The process condensate generated is treated in CPU of capacity 400 KLD. The treated
water is reused in the process. The treated condensate quality will be ensured
through implementation of Continuous Online Effluent Monitoring System (CEMS).
This will ensure to take remedial action immediately for effective treatment and also
help in minimizing the residual impacts on the water environment of the region.
Spent wash generated during the process of distillation will be Biomethenated and
further will be treated in multiple effective evaporators to concentrate the spent wash
till 30% solids and further will be dried through ATFD Agitated Thin Film Drying
Process and it will be converted to Fertilizer to achieve Zero Discharge.
ES 4.5 Biological Environment
During construction phase, Excavation of Soil activities causes risk of soil erosion,
Loss of soil fertility, Deposition of dust on trees and water bodies and generation of
Noise, emission of CO2 & Dust will emit during the vehicular movement.
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 12
During operation phase, generation of waste water leads to water pollution, affects
aquatic fauna. Emission of fly ash & emission of air pollutants can be anticipated due
to the operation of boiler. Improper disposal of bagasse & Unaesthetic conditions.
As part of Mitigation Measures, green belt will be developed in and around the
project site to sequest the emitted CO2. Erection of higher barricades around the
industry will reduce the deposition of dust on the tree foliage and nearby
streams/nalas around the industry. Soil erosion will be controlled after the
development of green belt. Frequent watering of roads and trees to remove
deposition of dust. Noise will be mitigated by providing acoustic enclosure, wildlife
signs, Traffic signs and speed limits may decrease the impact of noise on wildlife
behavior and movements.
Proper management and disposal of effluents after treating them at ETP, avoiding
leakages, removal of chemical residues before reutilization of treated water.
Utilization of Electro Static Precipitators (ESPs) to reduce the impacts of emission of
air pollutants. The bagasse can be stored in bagasse yards to avoid its spreading due
to wind and water. Aromatic floral species will be planted around the STP, ETP and all
along the periphery of the industrial boundary, internal roads to minimize the odour
generated.
ES 4.6 Socio Economic Environment:
Due to the Increased influx of people during project construction phase there would
impact.. During the influx of migrants, there is a possibility new health problem or
diseases aggravate due to the change in population density.
The project will improve the socio-economic status of the people also contributed to
the development of infrastructural facilities. The road net connectivity to the villages
on the road connecting to the plant will be improved during operation of plant.
There will be lots of direct and indirect employment generation due to the project.
This project requires a total of 79 employees in the factory and as far as possible,
majority of them will be selected from the surrounding (within 10km radius) villages.
In addition to this, there are several indirect employments created by the factory
such as the truck owners, drivers, caterers, etc
ES.5 Environmental Monitoring Program
Responsibility of environmental monitoring lies with M/s. Askins Biofuels Pvt Ltd.,
Table ES.5 Environmental Monitoring Programme during Construction Phase
Sl.
No
Particulars of
the Monitoring
No. And Place of
Monitoring
Monitoring
frequency
Parameters for
Monitoring
Monthly
Budget*
(Rs.)
1 Ambient Air
Quality
3 Nos
Near main gate
Monthly PM10, PM2.5, SO2,
NO2
13,500/-
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 13
Sl.
No
Particulars of
the Monitoring
No. And Place of
Monitoring
Monitoring
frequency
Parameters for
Monitoring
Monthly
Budget*
(Rs.)
Monitoring – 24
Hrs
Construction
area- distillery
Labour camp
2 Ambient Noise
Level Monitoring
– 24 hrs
3 Nos
Near main gate
Construction
area- distillery
Labour camp
Monthly Leq Day dB(A)
and Leq Night
dB(A)
3,600/-
3 Ground Water
Quality
Near project site Monthly As per drinking
water quality
standards
(IS10500:2012)
6,300/-
4 Soil quality 2 Nos
Near Labour camp
Once in
season
Colour, pH,
Conductivity,
Moisture Content,
Calcium,
magnesium,
Nitrogen
Phosphorous,
Potassium,
Organic Matter,
Sulphate,
Chloride.
2,800/-
Total 26,200/-
Table ES.6 Monitoring Schedule for Environmental Parameters during operation
phase
Sl.
No. Particulars
Monitoring
frequency
Duration/
type of
monitoring
Important
parameters for
monitoring
Monthly
Budget*
(Rs.)
I Air Quality
1 Ambient Air Quality
Monitoring within
premises – 4 locations
Near main gate
Near Boiler house
Distillery unit
Near CPU
Once in a
month
24 hrly
sample
PM10, PM2.5, SO2,
NO2
22,500/-
2 Stack/Chimney
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 14
Sl.
No. Particulars
Monitoring
frequency
Duration/
type of
monitoring
Important
parameters for
monitoring
Monthly
Budget*
(Rs.)
Monitoring for Boilers,
30 TPH – 45 m
chimney
Once in a
month
Grab SO2, PM, NMHC &
CO
6,900/-
2X 250 KVA DG -
5 m ARL each
Once in a
month
Grab SO2, PM, NMHC &
CO
II Water Quality
1 Ground water analysis
near project site and
and nearby Alagwadi
village – 2 samples
Once in a
month
Grab As per drinking
water quality
standards
(IS10500:2012)
12,600/-
2 Ground water at 2
locations at
Bastawada & Harugeri
Once in 6
months
Grab As per drinking
water quality
standards
(IS10500:2012)
2,100/-
3 Surface water at 2
locations at Down
Stream of Nala Near
Morab & Up Stream
of Nala Near
Alagawadi
Once in 6
months
Grab pH, Turbidity, BOD,
COD,DO, TSS, Total
hardness, Oil &
Grease, TKN, NH3-N,
Total Nitrogen , Ca,
Mg, NO3, Mn, Total
Coliform, Feacal
Coliform & E.Coli
1513/-
4 Sewage – STP inlet &
outlet
Once in a
month
Grab pH, Turbidity, TSS,
BOD3, COD, NH4-
N, N-Total,
Residual Chlorine,
& E.Coli
2,400/-
5 Effluent – CPU inlet &
outlet
Once in a
fortnight
Grab BOD, COD, pH, TSS,
oil and grease
7,600/-
6 Effluent- ETP inlet &
outlet
Once in a
fortnight
Grab pH, BOD, COD, TSS,
Oil & Grease
7,600/-
III Soil Quality
1 Soil quality analysis
(landscape area where
treated water is being
utilised)
Once in
season
Grab pH, C, Organic
matter, N, K, P.
4,67/-
IV Ambient Noise level
monitorin(5 locations)
Near Main
Once in a
Month
24Hrs
Monitoring
Noise levels in dB
(A) both during day
& night time.
6,000/-
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 15
Sl.
No. Particulars
Monitoring
frequency
Duration/
type of
monitoring
Important
parameters for
monitoring
Monthly
Budget*
(Rs.)
Gate/Boundary
Boiler Section
Turbine Section
Distillery section
D.G Set Room,
Total 69,680/-
Continuous online monitoring of emission and effluent will be provided and the
same will be connected to CPCB server. M/s. Askins Biofuels Pvt Ltd will implement
various productivity management programs in the plant to improve the work
environment, effective housekeeping and environment quality. All the necessary
steps will be taken in the plant to meet standards prescribed by the Karnataka State
Pollution Control Board and Central Pollution Control Board
ES.6 Risk Assessment and Disaster Management Plan
The plant will be equipped with adequate number of portable fire extinguishers, CO2
extinguishers, Dry powder chemical extinguishers, Fire hydrant measures, foam
dispensing systems and allied measures as per OISD (Oil Industry Safety Directorate)
norms. Portable fire extinguishers in various strategic areas of the plant including the
control room, administration building, stores, pump house, etc., will be provided.
ES 6.1 Occupational Health and Safety
Occupational Health Surveillance (OHS) will be undertaken as regular exercise
for all the employees specifically for those engaged in handling hazardous
substances.
All the first aid facilities will be provided in the Occupational Health Centre.
The medical records of each employee will be maintained separately.
Occupational health centre for medical examination of employees with all the
basic facilities will be established with in the plant.
The noise levels in critical area will be monitored regularly and the workers at
high noise level generating areas will undergo audiometric tests once in six
months.
The equipment and facilities such as first aid medical units, safety belts, ear
muffs, masks against dusts, aprons against chemical spillage, shock proof
gloves and mats, leather aprons, safety items - shoes, gum shoes, hand gloves,
helmets, goggles, safety ladder, face masks & gas masks, breathing apparatus,
stretchers and oxygen cylinder, emergency lighting facilities will be kept at
administrative building/stores building and will be under the control of
emergency coordinator.
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 16
ES.7 Project Benefits
The company’s management will recruit semi skilled & unskilled workers of
about 100No’s from the nearby villages, thereby improving in the social status
of the villagers. It creates employment opportunities to 100 No's directly 79
No's indirectly.
The easy availability of infrastructure, man power, raw materials will reduce the
production cost as well as demand supply gap. The same will bring revenue to
the state exchequer by way of Duties and Taxes.
Further, the management will support the local administration and provide
assistance for the development of public amenities viz., water distribution,
building of school rooms, health centres, Education programme, Health
camps, Agricultural programmes & sponsorships to meritorious students
under the CSR activities.
The industry is established in the rural region of the state. The establishment
of industry will provide direct and indirect employment to more than 100 local
rural persons. Major part of these labors will be mainly from local villagers
who are expected to engage themselves both in agriculture and project
activities. This will enhance their income and lead to overall economic growth
of the area.
The road connectivity will get improved due to the industry. This improved
physical infrastructure will be an added facility to the community for surface
transport.
Efforts will be more focused on recycling of wastewater after adequate
treatment. Thus water extraction for process will be minimized
Green belt will be developed within the plant premises covering a 33 % of
total area and also in the buffer zone. This will not only help to create healthy
environment in the area but also acts as pollution sink. Further avi-fauna
population of the area will increase.
With the implementation of the total project, the socio-economic status of the
local people will improve and infrastructure facilities like roads,
communication systems, drinking water, etc. will also develop. The land rates
in the area will escalate due to the project. This will help in upliftment of the
social status of the people in the area. Educational institutions will also come-
up and will lead to improvement of educational status of the people in the
area. Medical facilities will certainly develop due to the project.
The implementation of Rain Water Harvesting Scheme will help in increasing
the ground water level of the area.
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 17
ES.8 Environmental management plan
Responsibility of maintainace of Environmental Management Plan lies with the EMP
cell of M/s. Askins Biofuels Pvt Ltd
Table ES.7 EMP during operational phase of the project
Activity Anticipated Impacts Environmental Management Plan
1. Land
Disposal of wastewater/
spentwash
Soil contamination &
Groundwater
contamination
The condensate generated is treated in CPU
of capacity 400 KLD. The treated water is
reused in the process.
Spent wash generated during the process of
distillation will be Biomethenated and further
will be treated in multiple effective
evaporators to concentrate the spent wash till
30% solids and further will be dried through
ATFD Agitated Thin Film Drying Process and it
will be converted to Fertilizer to achieve Zero
Discharge.
2. Air
Boilers, Process, storage,
transportation of raw
materials and finished
products, DG sets
Gaseous and fugitive
emissions
Boiler of 30 TPH will be connected with ESP
and to the chimney of 30 mt and 45 mt
respectively.
5 mt above the roof with acoustic enclosures
will be provided for DG Set (2X250KVA) and
HSD (High Speed Diesel) with sulphur content
of <0.05% will be used for D.G.Sets
Monitoring of stack emissions will be carried
out monthly to ascertain the performance of
the air pollution control equipments including
installation of continuous online emission
monitoring system.
Ladder, porthole, power supply points will be
provided to the boiler for monitoring of
emissions.
Water spraying will be adopted at loading,
unloading points and storage yards which will
reduce fugitive emissions.
All the internal roads will be asphalted to
reduce the fugitive dust due to vehicular
movement.
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 18
Activity Anticipated Impacts Environmental Management Plan
Greenbelt will be developed (33% of the
project area).
A good housekeeping and proper
maintenance will be practiced in the industry,
which helps in controlling pollution.
Regular maintenance air pollution control
equipments.
Regular maintenance of vehicles and
machinery’s in order to control emissions.
Bagasse storage Minimising the distance that bagasse falls
during movement;
Fully enclosing the bagasse handling
conveyors, particularly transfer points;
Installing belt cleaning systems so that
bagasse is not carried back on the underside
of conveyor belts;
Implementing bagasse dust management
plan that prescribes mitigation measures for
unfavourable weather conditions;
Installing water spray system to reduce dust
emissions around and from, the site;
Vehicular traffic Exhaust Emissions
The conditions of the internal roads will be
checked & maintained at least once in a year.
Trained securities will be deployed to guide
the vehicles for smooth entry/exit without
causing any traffic congestion.
Greenery development will create aesthetic
environment and also acts as a pollution sink
for dust emissions.
3. Surface and Ground Water
Process Effluent, Sewage,
Storm water run off
Ground water & soil
pollution, flooding The condensate generated is treated in CPU
of capacity 400 KLD. The treated water is
reused in the process.
Spent wash generated during the process of
distillation will be Biomethenated and further
will be treated in multiple effective
evaporators to concentrate the spent wash
till 30% solids and further will be dried
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 19
Activity Anticipated Impacts Environmental Management Plan
through ATFD Agitated Thin Film Drying
Process and it will be converted to Fertilizer
to achieve Zero Discharge.
The domestic water generated is treated will
be treated in STP
Storm water drains will be provided to avoid
flooding in the proposed site. Storm water
gutters/drains will be constructed in the
premises on either side of the haul roads (0.8
m X 0.6 m) and along the periphery of 1.0 m
X 0.6 m.
Garland channels will be provided around the
storage yards.
Harvested rainwater will be reused for
greenery development/sprinkling applications
and non potable uses thereby conservation
fresh water requirement.
Rainwater harvesting sump of capacity 1 X
6000KL is proposed for implementation
4. Geology and Hydrology
Extraction of water Depletion of water table
Implementation of recharge structures will
improve the ground water table in and
around the project site.
Percolation pits at 8 places shall be
constructed with dimensions 4m X 3 m X 3m
depth all along the periphery of the
proposed site on the North and west to
recharge the aquifer as part of social
responsibility
5. Noise
Manufacturing process,
cogeneration unit,
transportation of raw
materials and finished
products, D.G Set
operation, Vehicular
traffic,
Increase in noise levels
Personnel working near noisy areas will be
provided with adequate personal protective
equipment such as earplugs and earmuffs,
use of which will be strictly enforced.
Sophisticated and low noise generating
equipments will be selected.
Proper mounting of equipments and
providing noise insulating enclosures or
paddling where practicable.
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 20
Activity Anticipated Impacts Environmental Management Plan
Appropriate advanced silencers, acoustic
barriers; vibration-reducing pads will be
provided for all noise generating equipments.
The sources of continuous noise generating
equipment such as compressors, pumps etc
will be designed to have noise level not
exceeding 85-90 dB (A).
Boundary walls and dense greenery will be
erected to act as acoustic barriers.
Adequate and appropriate type of greenery
will be developed in and around the
proposed project site for noise mitigation in
the area.
Proper maintenance of machineries especially
oiling and greasing of bearing and gears etc.
Trees will be planted on either side of the
roads within the industry premises and within
the vicinity around the factory.
6. Solid and Hazardous Waste
Domestic garbage, solid
waste from Distillery
industry, cogeneration
unit
Improper handling will
affect the land/soil and
water environment
Bagasse generated will be sent to
cogeneration unit to use it as fuel for boiler
for power generation
Boiler ash will be sent to brick manufacturers
Yeast sludge & sludge from CPU will me
Mixed in required proportions and sold to
member farmers as manure
Used oil from DG set, spent turbine oil will be
used as lubricant within the industry.
Domestic organic solid waste will be
composted, while the inorganic solid waste
will be handed over to nearby municipal
agencies & recyclers.
7. Ecology and biodiversity
Production of Ethanol,
Operation of boilers,
Operation of DG Sets,
Generation of soild &
industrial waste, Sewage
treatment
Generation of waste water,
water pollution, affects
aquatic fauna,
Emission of air pollutants,
Generation of waste water,
Emission of fly ash,
Utilization of Electro Static Precipitators
(ESPs) to reduce the impacts of emission of
air pollutants.
Frequent watering of roads and trees to
remove deposition of dust.
Proper management and disposal of
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 21
Activity Anticipated Impacts Environmental Management Plan
Generation of Noise,
Emission of air pollutants,
Increase in the content of
heavy metals may affect
the soil composition,
Improper disposal of
bagasse,
Improper disposal of
effluents,
Unaesthetic conditions,
Odour
effluents after treating them at ETP, avoiding
leakages, removal of chemical residues
before reutilization of treated water
There is no removal of trees for the project.
However, a three tire plantation of native
species shall be carried out along the
periphery of the industry to enhance the
carbon sequestration capacity of trees and
thereby reducing the impacts of air pollution.
Further, the green belt development plan
also provides habitat to several avifaunal
species, butterflies and small sized mammals.
Greenbelt development of native species will
reduce the GHG levels in the study area.
Frequent watering (daily basis) of trees, herbs
and shrubs in the project site will remove the
dust deposited on the foliage thereby
balancing the rate of photosynthesis and
transpiration.
Awareness programmes to the local people
on importance of tree species especially trees
with GBH >77 cm will be carried out.
Erection of higher barricades around the
industry will reduce the deposition of dust on
the tree foliage and nearby
streams/nalasaround the industry. This will
reduce the exposure of animals to noisy
conditions caused due to the industry.
D G sets will be placed on rubber cushion
padding, enclosed and maintained well in
good condition to avoid vibrations.
Aromatic floral species will be planted
around the STP, ETP and all along the
periphery of the industrial boundary, internal
roads to minimize the odour generated.
8. Socio-economics
Quality of Life,
Sharing of local resources
Employment generation,
Improvement in quality of
life, development of
infrastructure facilities,.
There is a possible
emergence of increased
The project has very strong positive impact,
which is likely to result in the improvement of
economic situation of nearby villages.
Improvements in the annual incomes of
about 10% p.a in the surrounding areas
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 22
Activity Anticipated Impacts Environmental Management Plan
and unfair competition in
local markets adversely
impacting businesses and
livelihoods of some,
Increased pressure on
residential
accommodation, water
supply and sanitation in
neighbourhood
Development of ancillary industries in this
region
Creation of employment opportunities for
about 79 local skilled workers during
operation phase.
Employment generation to about 100 to 120
unskilled & semi-skilled workers during
construction, operation phase.
Improvement to dwellings, educational
facilities and healthcare facilities in the
surrounding Taluks’s.
Road and power network in the area may get
strengthened.
Potable water supply will be improved.
The lifestyles are expected to improve in tune
with the rise in incomes and improvement in
infrastructure facilities.
The skill sets of the local residents are
expected to improve in keeping with the
emerging employment opportunities
Occupational Safety and
Health
All precautionary methods will be adopted by
the company to reduce the risk of exposure
of employees to occupational safety and
health hazards.
Pre & post medical check-ups will be done of
all the employees. Employees will be regularly
examined and the medical records will be
maintained for each employee. Pulmonary
function test and periodical medical check-up
shall be done once in every year. The
following tests will be conducted for each
worker as Occupational health surveillance
programme: Lung Function Test, Radiology –
X-ray, Pulmonary Function Test, and
Audiometric Test.
For the safety of workers, personnel
protective appliances like hand gloves,
goggles, aprons, ear mufflers, nose mask etc.
will be provided.
Proposed 60 KLPD (Juice/syrup based) distillery, 6 TPD Bio CNG,
20 TPD fertilizer powder, 42 TPD CO2, Captive Power generation of 3MW/Hr Draft EIA Report
M/s. Askins Biofuels Pvt Ltd M/s. EHS Consultants Pvt Ltd 23
Budgetary provision: Capital investment to be made on environmental management
measures is Rs 3.96 Crores and Rs. 114.5Lakhs/-per year will be reserved for the
recurring expenditure.