before a board of inquiry transmission gully notices of ... · columbia, canada, specialising in...
TRANSCRIPT
Statement of rebuttal evidence of Timothy Simon Richmond Fisher
(Sediment Yield Peer Review) for the NZ Transport Agency and Porirua
City Council
Dated: 27 January 2012
REFERENCE: John Hassan ([email protected])
Nicky McIndoe ([email protected])
Before a Board of Inquiry
Transmission Gully
Notices of Requirement and Consents
under: the Resource Management Act 1991
in the matter of: Notices of requirement for designations and resource
consent applications by the NZ Transport Agency,
Porirua City Council and Transpower New Zealand
Limited for the Transmission Gully Proposal
between: NZ Transport Agency
Requiring Authority and Applicant
and: Porirua City Council
Local Authority and Applicant
and: Transpower New Zealand Limited
Applicant
1
042407977/1457188.10
STATEMENT OF EVIDENCE OF TIMOTHY SIMON RICHMOND
FISHER FOR THE NZ TRANSPORT AGENCY AND PORIRUA
CITY COUNCIL
INTRODUCTION
1 My full name is Timothy Simon Richmond Fisher.
2 I am a Senior Water Engineer and Director at Tonkin & Taylor
Limited (T&T), environmental and engineering consultants of
Auckland. I practise as a civil engineer with specialism in water and
environmental engineering. I am a member of the Institute of
Professional Engineers New Zealand and am a Chartered
Professional Engineer.
3 I have a Bachelor of Civil Engineer (1st Class Honours) and Masters
of Civil Engineering (Distinction) from the University of Canterbury
and a PhD in Civil Engineering from the University of British
Columbia, Canada, specialising in environmental hydraulics. I have
a Diploma in engineering management.
4 I have 17 years of experience in engineering research and
consulting spanning the transport, mining, hydropower, land
development, urban water infrastructure and river management
sectors. I have specialist expertise in hydrology, hydraulics,
stormwater, modelling, water quality and sediment transport.
5 I have extensive experience in the stormwater management,
streamworks and the water quality assessments for major roading
projects and other projects involving large earthworks. Recent
projects that I have been involved with include:
5.1 Huntly Section of the Waikato Expressway (SH1) where I was
the lead author of the stormwater and streamworks
assessment for the scheme assessment report (2011).
5.2 Puhoi to Warkworth (SH1) where I was the peer reviewer of
water reports (hydrology, stormwater, water quality and
erosion and sediment control (ESC)) at the scheme
assessment stage (2011).
5.3 Mt William Mine where I was the reviewer for West Coast
Regional Council of water quality assessment reports at the
pre-lodgement and notification stages (2011).
5.4 Waterview Connection Project (SH20/16) where I was the
stormwater team leader, expert witness for stormwater,
streamworks and flooding issues, and reviewer of modelling
undertaken to assess the effects of sediment on the
Waterview Inlet (2008-2010).
2
042407977/1457188.10
5.5 Northern Gateway Toll Road1 (NGTR) (SH1) where I was
stormwater team leader and stormwater treatment designer
for the 7.5 km motorway. I was onsite for the four years of
construction and was involved in technical advice to support
the design and operation of ESC systems (2004-2009).
5.6 Manukau Harbour Crossing (SH20) design of stormwater
treatment for resource consents (2007-2008).
5.7 Design and construction of the Mangakotukutuku Stream
diversion2 (1.4 km length) for Solid Energy (2005-2006).
5.8 Water management for the mining industry including
Rotowaro, Maramarua and Ohai mines for Solid Energy,
design and consents for Drury Quarry backfill and stream
diversion for Stevensons, and review of consent applications
for Holcim cement plants/quarries for Otago Regional Council.
5.9 I am currently undertaking reviews of water aspects
(hydrology, stormwater, flooding and ESC) of the MacKays to
Peka Peka (SH1) project for the Environmental Protection
Agency.
6 I offer the Board my advice based on my extensive experience with
water aspects of larger roading and earthworks projects and with
the advantage of my overview across all the water assessments in
my role as peer reviewer for the NZ Transport Agency (NZTA).
7 I am the reviewer of water aspects of the Project for NZTA that were
summarised in Assessment of Water Quality Effects Report
(Technical Report 15) and Assessment of Hydrology and Stormwater
Effects (Technical Report 14). I am the author of Transmission
Gully Project – Peer Review of Sediment Yield Aspects (19
December 2011). I was the author or reviewer of four working
review reports provided to NZTA during the development of
Technical Reports 14 and 15.
8 My evidence is given in support of the NZTA and Porirua City Council
(PCC) Project components of the Transmission Gully Proposal
(together the TGP or the Project). It does not relate to the
Transpower Project.
1 Winner of Association of Consulting Engineers Innovate Gold award for projects that
show excellence in technical skills, interaction with the client and team members and innovation. Winner of IPENZ Arthur Mead Award (Merit) for projects that best
exemplify sustainable management of resources and care for and consideration of
environmental values.
2 Winner IPENZ Arthur Mead award. Winner of Innovate Silver Award.
3
042407977/1457188.10
9 I am familiar with the area that the Project covers and the streams,
Porirua Harbour and topography in the vicinity of the Project. I have
visited the site.
10 I have read the Code of Conduct for Expert Witnesses as contained
in the Environment Court Consolidated Practice Note (2011), and I
agree to comply with it as if this Inquiry were before the
Environment Court. My qualifications as an expert are set out
above. I confirm that the issues addressed in this brief of evidence
are within my area of expertise. I have not omitted to consider
material facts known to me that might alter or detract from the
opinions expressed.
SCOPE OF EVIDENCE
11 My evidence will deal with the following:
11.1 Executive summary;
11.2 Background and role;
11.3 Existing sediment yield;
11.4 Construction sediment yield;
11.5 Managing uncertainty and risk; and
11.6 Proposed conditions.
12 My statement of evidence responds to submitters evidence by:
12.1 Dr Basher on behalf of Department of Conservation (DOC);
12.2 Mr Handyside on behalf of DOC; and
12.3 Ms Helen Kettles on behalf of DOC.
13 Those witnesses refer to my Peer Review of Sediment Yield Aspects
(19 December 2011) and peer reviews of earlier draft documents.
In order to present a complete picture, this statement describes my
work carried out, but only on sediment yield aspects.
14 Related to that, my statement of evidence also considers the
evidence by:
14.1 Ms Malcolm (both evidence in chief and rebuttal);
14.2 Mr Gough (evidence in chief and rebuttal); and
14.3 Mr Pathmanathan Brabhaharan (rebuttal).
4
042407977/1457188.10
15 I have reviewed the conferencing statements relevant to my area of
expertise, and comment on these where appropriate.
16 While I have reviewed Dr Hicks Section 42A Report dated January
2012, I have not had sufficient time to thoroughly comment on that
report in this evidence. Nor have I had an opportunity, at the time
of preparing this statement, to consider the Section 42A Report
which I understand is being prepared by Gregor McLean. I
understand there will be opportunities for me to comment on these
reports either in future evidence or at the hearing itself.
SUMMARY OF EVIDENCE
17 My evidence discusses the sediment yield aspects of Technical
Report 15.
18 The revised estimate of construction sediment yield3 provides a
better estimate than that provided in Technical Report 15 because
greater detail was considered in the assessment of USLE factors. I
consider the revised construction sediment yield to be suitable for
the assessment of effects. On the basis that the revised construction
sediment yield is higher than the estimates in Technical Report 15,
the values used in the assessment of ecological effects are
appropriate, subject to consideration by ecologists of the uncertainty
and the change of effects in the Kenepuru and Pauatahanui
catchments.
19 There remains uncertainty with regard to the estimates of baseline
and construction sediment yield estimate. This uncertainty is better
understood as a result of the rebuttal evidence of Ms Malcolm,
which includes statements on the uncertainty, sensitivity, and
potential conservatism in the construction sediment yield.
20 This uncertainty is inherent in sediment assessments for
construction projects and not different to other roading/earthworks
projects and consent applications that I have seen.
21 To manage remaining uncertainty, the focus needs to be on consent
conditions that:
21.1 Confirm the basis for the consent application (assumed
sediment yield and effects);
21.2 Minimise the uncertainty and risks by applying best practices
for ESC; and
3 SKM (20 January 2012) Revised Analysis attached to Expert Conferencing Joint
Report to the Board of Inquiry – Earthworks & Sediment Control Conferencing, 20 January 2011.
5
042407977/1457188.10
21.3 Require monitoring and adaptive management that ensure
that specified performance from construction and sediment
and erosion practices are achieved.
22 I recommend additional consent conditions to manage the
uncertainty and provide confidence to the Board of Inquiry.
BACKGROUND AND ROLE
23 NZTA engaged T&T in 2010 to undertake peer review of SKM and
DHI work on water aspects of the Project. These reviews covered
the full suite of water assessments that form the basis of Technical
Reports 14 and 15. Reviews were undertaken in October 2010 of
early assessment reports and then in May 2011 of draft versions of
Technical Reports 14 and 15. These peer reviews are listed below
as they are at times referred to by other witnesses:
23.1 T&T “Peer review of Draft modelling of sediment in the
streams and harbours” (20 October 2010);
23.2 T&T peer review “Transmission Gully – Workstream 12 – Peer
Review” (29 October 2010) which reported on review of
“Erosion and Sediment Control Philosophy”, “Sediment Yield
Calculations” and “Construction and Erosion and Sediment
Control” reports;
23.3 T&T “Transmission Gully – Peer Review of Water Quality
Assessment of Effects” (Draft, 5 May 2011); and
23.4 T&T “Transmission Gully – Peer Review of Hydrology and
Stormwater” (Draft, 13 May 2011).
24 In December 2011 NZTA asked me to finalise the peer review of the
sediment yield aspects of Technical Report 15. The purpose of the
peer review was to provide an independent opinion to NZTA on the
specific sediment yield aspects including sediment modelling and
sediment retention/ control assumptions. The report gave
consideration to the evidence of Ms Malcolm and Mr Gough,
Submitter 43 (Department of Conservation) and the expert caucus
statement 7/8 December 2011. This peer review is titled:
24.1 T&T “Transmission Gully Project – Peer Review of Sediment
Yield Aspects” (19 December 2011).
25 In anticipation of the need to prepare this evidence I participated in
the conferencing of Earthworks & Sediment Control experts on
20 January 2012.
6
042407977/1457188.10
EXISTING SEDIMENT YIELD
USLE method
26 The USLE4 method was used as the basis for the sediment yield
assessment. The method has a number of limitations including that
it is not calibrated for New Zealand conditions, it estimates average
annual sediment loss rather than events or unusual wet/dry
seasons, and is not able to accurately estimate the absolute
sediment yield. Its strength is in identifying hotspots for sediment
generation and where ESC efforts should be directed.
27 Despite the limitations with the USLE method, it remains the most
commonly applied method in New Zealand for assessing the
sediment yield and for designing sediment and erosion control
systems for engineering/development projects involving earthworks.
28 Dr Basher5 expresses considerable concerns with the USLE as it
does not represent landslides and bank erosion, it was not
developed for such steep terrain and it predicts average annual soil
loss that then requires temporal downscaling. These points are all
valid and I have made similar points in the past (T&T, 29 October
2010). However, by scaling to the SSYE6 estimate as has been
done for the Project, the USLE essentially becomes a SSYE estimate.
The perseverance with the underlying USLE model enables the
change in sediment estimate due to construction activities to be
assessed.
29 I accept Dr Basher’s opinion that other sediment generation models,
such as GLEAMS, are better than the USLE method, particularly
because of their temporal modelling e.g. direct modelling of events
or long term simulations. I have made a similar point in the past
(T&T, 29 October 2010). Although, it is important to note that other
sediment models also have their limitations as is recognised by Dr
Basher7 and Dr Hicks8 and limits on their suitability for this Project
(e.g. GLEAMS requires more detail).
30 Ms Malcolm9 makes the point that the USLE modelling approach is
pragmatic and suitable for a construction design that is not fully
developed as is the case for the Project. USLE is suited for such an
approach, whereas alternative models such as GLEAMS require more
detail of the construction methodology and ESC practices.
4 Universal Soil Loss Equation.
5 Dr Basher evidence in chief paragraphs 7, 29-35.
6 Suspended Sediment Yield Estimator developed by NIWA.
7 Dr Basher evidence in chief, paragraph 60.
8 Dr Hicks Section 42A Report dated Jan 2012 Section 3.4
9 Ms Malcolm evidence in chief, paragraph 119.
7
042407977/1457188.10
31 The Project has adopted a broad approach to construction design of
defining the maximum working areas, outlining the ESC philosophy
and broad plans. Examples of what the erosion and sediment plans
might look like are detailed in six separate Site Specific
Environmental Management Plans (SSEMPS). In general I agree
with this approach because it has been my experience with large
earthworks projects that detailed environmental management plans
and ESC plans change as a result of detailed design and
construction methodologies that a contractor brings to the project10.
I consider that prescribing a detailed construction methodology via
the consent process will reduce the ability of the contractor to
optimise and innovate to reduce Project cost and improve
performance (including that of ESC systems). My agreement to this
approach is conditional on the adequacy of the ESC philosophy,
assumed treatment efficiencies and the example SSEMPs to set a
benchmark for construction and to prove that ESC standards in
difficult areas can be achieved.
32 I accept Ms Malcolm’s point11 that a lumped model rather than one
that resolves all of the processes is suitable. The USLE and SSYE in
the way that they are applied are essentially lumped models
estimating sediment yield at point (harbours).
33 The caucusing statement of 7/8 December 2011 recognises that the
USLE is the best method for estimating the sediment yield from
construction for the Project1213.
34 It is my opinion that, on balance, the USLE (scaled to the SSYE)
sediment model can provide suitable sediment estimates and is
adequate for the assessment, provided that specific technical inputs
such as USLE factors are correctly applied and reasonable
assumptions are made for staging and ESC practices.
Existing sediment yields
35 The simulation of existing sediment yields and transport/distribution
was undertaken to provide a context (baseline) for the assessment
of construction effects due to sediment.
36 Overall, the modelling provides a suitable estimate of the existing
sediment yields and the transport/distribution of sediment in the
receiving environments. This is achieved largely by scaling the
USLE estimates to be similar to those estimated by the more
10 Mr Gough notes similar experience and cites similar views from Ms Rickard and
Mr Handyside. Refer to Mr Gough rebuttal evidence, paragraph 19.
11 Ms Malcolm evidence in chief, paragraph 106.
12 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment
Control Conferencing, 7&8 December 2011, paragraph 14.
13 Caveats to this statement are made by Dr Basher in his evidence in chief paragraph 71d.
8
042407977/1457188.10
accurate NIWA suspended-sediment yield estimator (SSYE). I have
confidence in the estimate of existing sediment yields due to the
following key steps in the modelling methodology:
36.1 The sediment yield model based on the USLE model was
scaled14 to the SSYE by adjustment of the sediment delivery
ratio (SDR). The SSYE is considered to be the best available
tool for estimation of suspended sediment for catchments in
New Zealand. The caucusing statement of 7/8 December
201115 recognised that the SSYE is the best model for
providing the baseline sediment estimates.
36.2 The sediment yield model was validated using Healy (1980)
observations with reasonable explanations for differences.
The limitations of this validation are noted by Dr Basher,16
and I accept he is correct in noting this.
36.3 The sediment rating curves were created to temporally
distribute the sediment to allow for subsequent analysis
(event and long-term simulations). These were validated by
comparison to observed suspended sediment data for
Horokiri, Pauatahanui and Porirua catchments. The caucusing
statement of 7/8 December 201117 states agreement that the
sediment rating curves are a good fit to observed data for the
Horokiri and Porirua catchments and appear to overestimate
(conservative) for the Pauatahanui catchment. I note
Dr Basher’s concerns18 with the methodology and
implementation of this step and Ms Malcolm’s rebuttal19 of
these issues.
36.4 The hydrological models that were used to create the
sediment rating curves were also calibrated.
36.5 Stream modelling was undertaken with HEC RAS20 models
using calibrated inflows but with not hydraulic calibration.
Observations of natural bed material were relied on for
qualitative verification. I note that the sediment yields used
14 It is more appropriate to describe this process as scaling than calibration as pointed
out by Dr Basher (evidence in chief paragraph 71a) as measured data is required for calibration.
15 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment Control Conferencing, 7&8 December 2011, paragraph 10.
16 Dr Basher evidence in chief, paragraph 71b.
17 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment
Control Conferencing, 7&8 December 2011, paragraph 13.
18 Dr Basher evidence in chief, paragraph 51-56.
19 Ms Malcolm rebuttal Appendix B.
20 HEC- RAS (Hydrologic Engineering Centers River Analysis System) is a 1-D hydraulic model produced by the United States Army Corps of Engineers.
9
042407977/1457188.10
for the stream modelling are those for the end of streams (at
harbours), but believe this to be appropriate21 as the USLE
estimates (scaled to SSYE) do not account for any retention
of sediment in streams. The results from the stream
modelling are not used for the harbour modelling.
36.6 Harbour modelling undertaken with the DHI MIKE suite of
models provide current best practice for the hydrodynamic
modelling. The harbour modelling was reviewed by T&T
(20 October 2010) and T&T (05 May 2011). The harbour
model was reasonably calibrated to field observations
(although with some limitations noted, which are considered
to be reasonable). Verifications are based on qualitative
comparison to observed historical sedimentation.
36.7 The sediment modelling suite (all models) predicts
accumulation in the harbours that is comparable to
historically observed sedimentation rates with reasonable
explanations for differences. . Therefore, the sediment
modelling suite provides an adequate simulation of the
baseline to enable the effects of the Project to be modelled.
CONSTRUCTION SEDIMENT YIELD
37 The most critical aspect of all the water assessments I have
reviewed is the estimation of sediment yields from the construction
sites22. The addition of sediment from the Project, over and above
the existing catchment sediment yields, is the change that causes
the greatest potential for effects on the environment. This was
agreed in the expert caucusing of 20 January 2012, where “the key
issue for all participants of the meeting is the difference between
the baseline and construction yield estimates”23.
38 The process I followed for my peer review of the construction
sediment yield and repeat here is to review the suitability of the
method, review the underlying assumptions, check the sediment
yields are reasonable and comment on the uncertainty. I comment
21 In my peer review report 19 December 2011, I noted that the sediment estimate
used for the stream modelling may be an underestimate due to in stream process.
This was used by Dr Basher in his evidence in chief paragraph 71c as support for his view that there was an underestimation of sediment supply to streams. I now
recognise that the sediment estimate (USLE based scaled to SSYE) does not
account for any sediment retention in the steam because this process is not
included in the SSYE, so that the sediment estimate used for the stream assessment is appropriate.
22 T&T Peer Review 29 October 2010 page 3.
23 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment Control Conferencing, 20 January 2012, paragraph 7.
10
042407977/1457188.10
on how these issues have been addressed in the USLE Revised
Analysis24 and the revised sediment estimate in that report.
USLE Methodology
39 The suitability of the USLE methodology was covered above. The
application of the method is covered here. In Technical Report 15
the USLE was applied broadly for the Project, for example,
earthwork areas were based on a 75 m working corridor. In the
USLE Revised Analysis the land area and factors were calculated
every 10 m, for example the earthworks areas were based on the
design widths with allowances for coincidental works to construct
stream diversions, access roads and fill sites. The allowance for
earthworks to construct the stream diversions was based on 20 m
width (Mark Edwards, caucus meeting 20 January 2012). The
greater detail that was used for the revised sediment estimate
results in a better estimate25.
USLE Assumptions
40 The USLE assumptions and factors have a significant impact on the
estimates of average annual sediment yield. Issues identified by
the review process are now covered.
41 K factor (soil erodibility) used in the USLE model is based on surface
soil types. The caucusing statement of 7/8 December 2011
recognised that the K factor in the construction scenario is
conservative because in the construction scenario there is less
erodible material26. In my peer review I highlighted that some of
the earthworks will occur in rock, which would likely reduce the
sediment yield estimates. In the USLE Revised Analysis the
proportion of the earthworks in rock is accounted for in the K factor.
Mr Brabhaharan assisted by providing much more detailed
information on the rock component of the earthworks material.
Overall, 70% of the estimated available cut volume is estimated to
be in rock. This significantly reduces the K factor and acts to reduce
the revised sediment estimate.
42 LS factor (length slope and steepness factor) has been more
accurately assessed in the USLE Revised Analysis based on design
cross-sections. There are a couple of limitations on how the LS
factor has been applied. The first limitation is that the design cross-
section for the finished road was used, whereas in reality there are
multiple, different cross-sections that occur during construction.
The second limitation is the arithmetic averaging that is used to
24 USLE Revised Analysis (20 Jan 2012) by SKM attached to Expert Conferencing Joint
Report to the Board of Inquiry – Earthworks & Sediment Control Conferencing, 20
January 2012
25 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment
Control Conferencing, 20 January 2012, paragraph 8.
26 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment Control Conferencing, 7&8 December 2011, paragraph 17.
11
042407977/1457188.10
determine a LS factor for each 10 m cross-section may skew the LS
factor. These simplifications are pragmatic and appropriate for the
accuracy of the USLE method. The USLE Revised Analysis report
says that the revised LS factors are generally similar to the
Technical Report 15 factors, although the revised LS factors have a
greater range of variability.
43 C factor (cover) is unchanged in the USLE Revised Analysis with the
exception of Ration, which is assumed to only have earthworks for
nine months. P factor (erosion control practise) was unchanged in
the USLE Revised Analysis.
44 The application of SRE (erosion removal efficiencies) is confused in
Technical Report 15 due to inconsistencies and contradictory
information. This has been clarified in the USLE Revised Analysis,
which says that that Technical Report 15 estimates did not allow for
erosion control, but only included sediment removal that was
applied to remove 70% in the Q2 and Q10, and 40% of sediment in
the Q50.
45 The USLE Revised Analysis accounts for both erosion control and
sediment controls. Erosion control is applied by proportioning the
earthworks areas as being stabilised, under erosion control or as
active earthworks. Sediment control is applied to erosion control
and active earthworks areas. The net effectiveness of the erosion
control and sediment controls is demonstrated in Table 1. The
inclusion of erosion control measures acts to decrease the revised
sediment estimate.
Table 1: Net effectiveness of erosion and sediment control
measures.
Erosion Control
Active
Earthworks
Erosion
Control
Stabilised
0%
erosion
control
75%
erosion
control
100%
erosion
control
Sedim
ent
Contr
ol
Chemical
Treatment
Ponds 3%
70% Q2
and Q10
removal
rate
70% 92.5% 100%
Other
Sediment
Devices
30%
removal
rate
30% 82.5% 100%
12
042407977/1457188.10
46 A SDR factor (sediment delivery ratio) of 0.17 was applied in
Technical Report 15 to scale the USLE sediment yield to that
predicted by the SSYE. I accept the process of global scaling of the
USLE estimate to be similar to the SSYE estimate. However, using
the SDR for this scaling is problematic as this global scaling
accounts for processes other than “sediment delivery”. This
becomes a problem for the construction sediment estimate, when a
different SDR may be appropriate for the construction areas versus
the unchanged areas of the catchment. Ideally a new separate
global factor should have been introduced to separate the global
scaling of USLE to SSYE to the SDR factor representing sediment
delivery “processes”. Technical Report 15 describes how very little
sediment is retained in the streams, suggesting a high SDR factor
would have been appropriate, if separated from the global scaling.
47 Dr Basher27 is critical of the downscaling using the SDR because the
same SDR value is used for construction areas. As a minimum he
believes that the modelling should be re-run using a more
conservative SDR factor of 0.5 or 0.7 depending on slope
steepness28. The caucusing statement 7/8 December 2011
recognised that using the same scaling factor that has been applied
to the overall catchment to the construction area does not account
for the higher connectivity of construction sites to receiving
environments29. In my peer review30 I suggested that values lower
than 0.5/0.7 would be justified to allow for sediment losses
(detention) in streams31. I accept that there is little sediment
detention in the streams based on evidence to this effect in
Technical Report 15 and that values of 0.5/0.7 are appropriate for
earthworks areas. Therefore, the Technical Report 15 estimates of
sediment yield from construction areas from the SDR assumption
alone are likely to be low.
48 Auckland Council32 suggests for earthworks sites SDR values of 0.5
should be used, increasing to 0.7 for slopes steeper than 10%. The
USLE Revised Analysis uses SDR values of 0.5 and 0.7 for steeper
catchments. This increase in the SDR factor acts to increase the
revised sediment estimate.
27 Dr Basher evidence in chief paragraph 8-10, 39-50.
28 Dr Basher evidence in chief paragraph 17.
29 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment Control Conferencing, 7&8 December 2011, paragraph 15.
30 Dr Fisher peer review of sediment yield aspects, 19 December 2011, Section 3.3.3.
31 This view was challenged by Dr Basher in his evidence in chief, paragraph 71.e.
32 Auckland Council (2011) Module 3 – Erosion and sediment control: Workshops for
plan preparers. Prepared by Erosion Management Ltd and Environmental Communications Ltd.
13
042407977/1457188.10
49 The revised sediment estimate that results from the USLE Revised
Analysis is lower overall than the Technical Report 15 estimate.
While, the higher SDR factors have increased the sediment yields,
the lower K factors and inclusion of erosion control measures cause
the revised sediment estimate to be lower overall.
50 The total of the Q10 estimates33 for the revised approach is 27%
lower than the Technical Report 15 estimate. For the Kenepuru and
to a lesser extent the Pauatahanui the revised sediment estimates
are higher, which Ms Malcolm addresses in her evidence34. On this
basis, the assessment of ecological effects that uses the higher
Technical Report 15 values is appropriate, subject to consideration
of uncertainty and the change of effects in the Kenepuru and
Pauatahanui catchments.
Sediment yields
51 The sediment yields from construction areas should ideally be
validated against measured sediment data from other locations.
However, there is a lack of measured data in the Wellington region
and sediment yields do vary widely with different site conditions,
which make validation difficult. Mr Brabhaharan35 says that based
on his experience in the Wellington region and knowledge of the
Project geology that “...the sediment generated from the earthworks
associated with TGP, is likely to be significantly less, compared to
major earthworks project in Auckland.” I make comments below on
the use of monitoring during construction to validate the estimated
sediment yields.
Uncertainty
52 Uncertainty in the sediment estimates was identified in my peer
review. In his evidence Dr Basher considers this uncertainty to be a
major issue. The caucusing statement of 20 January 2012
recognises that the revised sediment estimate provides a better
estimation and a reduced uncertainty in the USLE parameters36.
However, uncertainty remains, which is inherent in the methods
used and more generally in sediment science.
53 I consider that the uncertainty in the sediment modelling suite
detailed in Technical Report 15 occurs in a number of areas:
53.1 SSYE baseline
53.2 USLE method and factors
33 Ms Malcolm rebuttal evidence, Table 1.
34 Ms Malcolm rebuttal evidence, paragraphs 21 and 25.
35 Mr Brabhaharan rebuttal evidence paragraph 9.5.
36 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment Control Conferencing, 20 January 2012, paragraph 8.
14
042407977/1457188.10
53.3 Construction methodologies and ESC effectiveness
53.4 Transformation of sediment yields to harbour and stream
models
53.5 Assessment models (HEC RAS stream models and MIKE21
harbour model).
54 Ms Malcolm addresses the uncertainty in her rebuttal evidence37.
More data would help to confirm the SSYE baseline and I
recommend that this should be done prior to construction.
However, the uncertainty would still remain in many components of
the construction sediment estimate. I comment further on
managing this uncertainty in the following section.
MANAGING UNCERTAINTY AND RISK
55 All the sediment experts recognise the uncertainty with the
construction sediment estimates based on the USLE method. I
consider that there is uncertainty in the assessment and risk of poor
performance during project delivery and I treat these separately.
56 As a general comment the focus needs to be on management (of
mitigation measures), monitoring and responses to manage/reduce
the uncertainty. These need to be captured in consent conditions. I
agree with Dr Basher that if the applications for construction of TGP
were to be granted then conditions for ESC would need to be very
stringent and monitoring of performance, reporting and potential for
reviewing management approaches swiftly and comprehensively38.
Uncertainty in the assessment
57 Uncertainty is inherent in the estimation of sediment yields in
general and more so for construction sites. This uncertainty is
common to all similar projects and consent applications. A
precautionary approach is required for the Project given the scale of
the earthworks and the sensitivity of the receiving environments.
However, the Project has gone as far as any project that I have
been involved with to quantify the sediment loads and the
uncertainty associated with these. There is not much more that can
be done using the methods that SKM have employed for Technical
Assessment 15 and the additional work detailed in the Revised USLE
Analysis and uncertainty/sensitivity assessments in the rebuttal
evidence of Ms Malcolm. The risk that the sediment yields and
effects are different to those that have been assessed can be
managed by the conditions of consent that have been proposed and
with additional consideration of the conditions that I propose in my
evidence.
37 Ms Malcolm rebuttal evidence, Appendices A and B.
38 Dr Basher evidence in chief, paragraph 17.
15
042407977/1457188.10
58 I would recommend pre-construction monitoring of sediment in the
key streams affected by the construction of the Project to confirm
the existing sediment loads and the baseline environmental
conditions. Dr Basher39 agrees with this approach and says that the
checks should be in relation to the sediment rating curves as this is
all that can be checked. The checks should be to ascertain whether
the sediment rating curves are in the right “ball park” and should
focus on the catchments for which sediment rating curves were
derived without the benefit of local field measured data.
59 Concern has been expressed by myself and Mr Handyside during
caucusing about the ability of sediment ponds to remove 70% of
sediment during the Q10 event. I note Mr Gough’s replies to this
issue40. While there is sufficient evidence in Moores and Pattison
(2008) and the general literature to support the 70% pond removal
efficiencies for normal events used for the SRE, there is no data to
quantify the removal efficiencies for extreme events.
60 On this basis, the sediment estimates for the 10 year return period
events and higher have greater uncertainty and may be higher than
estimated. If this is an area of uncertainty then the consequence of
this should be understood, which is the point of Ms Malcolm’s
sensitivity assessment41. The adaptive management approach and
performance monitoring as described below are the best and only
course of action to manage the uncertainty regarding this issue of
pond performance.
61 Mr Gough advises that the sediment control efficiencies of sediment
control devices other than ponds (e.g. super silt fence, biosock and
decanting earth bunds) will have removal efficiencies that are
greater than the 30% than has been assumed in the USLE Revised
Analysis. Therefore, the revised sediment estimate may be
conservative in this area, although this only affects 5-20% of the
Project by area42.
62 The Project proposes extensive monitoring of ESC systems. These
are detailed in Appendix 15.L of Technical Report 15 (which is also
attached to the draft43 Construction Environmental Management
Plan in volume 5 of the application documents). The proposed
monitoring includes inspections of erosion control, surface water
control and sediment control, which are standard practices. The
Project also proposes performance monitoring of sediment control
39 Dr Basher evidence in chief, paragraph 71f.
40 Mr Gough rebuttal evidence, paragraph 25.
41 Ms Malcolm rebuttal evidence, Appendix A.
42 USLE Revised Analysis (20 January 2011), Table 11.
43 The consent conditions require draft plans to be updated and finalised.
16
042407977/1457188.10
devices and at catchment control points, which are significant
additional measures that I have not seen on a project before.
63 The performance monitoring measures are part of an adaptive
management approach that the Project proposes44. But these have
the secondary benefit of confirming the assumptions in the
assessment of effects. Should the measured sediment yield be
greater than that assumed in the assessment of effects, then
measures would need to be implemented to assess the actual effect
or to reduce the sediment yield. Such measures to reduce the
sediment yield could include more stringent ESCs including
improvements to the sediment pond designs (larger or changes to
chemical systems) or provisions for reduced earthworks area.
64 To respond to concerns raised by Dr Basher and Mr Handyside, I
understand the NZTA and PCC propose that a Sediment
Management Peer Review Panel be established using independent
professionals to support NZTA and the Greater Wellington Regional
Council in the management of ESC practices. A role of this panel
would be to review pre-construction monitoring and construction
performance monitoring. I have seen such panels successfully
operate in respect of mining operations (where water quality was
also a critical issue) and would support this proposal. I understand
that Ms Rickard will draft and circulate consent conditions for
consideration as part of the upcoming combined planner and
sediment engineering conferencing session. I have provided some
thoughts to Ms Rickard on the drafting of this.
65 There was concern expressed during caucusing of 20th January 2012
that the sediment generation from stream diversions is not well
quantified. More information is available on the stream diversions in
the report Diversion Staging Physical Design Parameters & Adaptive
Management that is appended to the Ecological Management and
Monitoring Plan.
66 Ms Malcolm addresses the issues of sediment generation from
stream diversions in her rebuttal evidence45. I agree with her that
the earthworks activities associated with the stream diversion are
included in the revised sediment estimate. I agree with her that the
sediment generated from the stream works within wetted stream
channels cannot be estimated using the USLE method and I know of
no reliable method to estimate the sediment from this source.
67 I consider that the sediment generation from stream works within
wetted stream channels to be relatively minor (compared to Project
earthworks activities), provided that the new stream channel is
44 Refer to the Ecological Management and Monitoring Plan page 35 for the principles
of the adaptive management approach.
45 Ms Malcolm rebuttal evidence, Appendix B.
17
042407977/1457188.10
properly stabilised and the diversion of the stream into the new
stream channel is quickly and carefully orchestrated. My view is
based on my experience with stream diversions made for the
Mangakotukutuku Stream diversion and for temporary diversions to
allow for the construction of culverts on the NGTR. In the case of
the Mangakotukutuku Stream diversion some suspended sediment
was added to the stream water due to earthworks to open the
upstream end of the diversion and from dust washed out of the
rocky substrate forming the bed of the new stream channel. This
suspended sediment discharge was relatively minor and equivalent
to the sediment concentrations experienced during high flows in the
stream, but it occurred for a much shorter duration (less than one
hour).
68 I have reviewed the proposed consent conditions that cover the
physical quality, sediment management and implementation of
streamworks including G.15(A), G.15(D), WS.1, WS.2, WS.3 and
WS.4. Based on my experience drafting the streamworks consent
conditions for the Waterview Connection project, I believe that the
consent conditions controlling streamworks should be more explicit
in a number of areas:
68.1 Inclusion of stream diversion plans in the requirements of the
SSEMPs, which is implied by the content of the example
SSEMPs but the inclusion of this as a consent condition
removes all doubt.
68.2 Inspection of the stream diversion by appropriately qualified
and experienced engineer and ecologist to certify that the
streamworks have been undertaken in accordance with the
drawings and plans within three months of completion of the
streamworks.
69 Ms Malcolm46 in her sensitivity assessments demonstrates the
importance of erosion and sediment control measures working
together. In her Scenario 1 the lower performance of sediment
controls (e.g. ponds and other devices) is offset by accounting for
deployment of erosion control measures when heavy rain is
forecast. The effectiveness of additional erosion control measures
deployed on the basis of forecast rain was not considered in the
Technical Report 15 estimates, or in the revised sediment estimate.
Therefore, the sediment yields are conservative in this regard. This
approach is a requirement of consent condition E.3(j), which
requires that all practicable erosion and sediment control measures
are put in place if a stabilisation trigger event47 is forecast.
46 Ms Malcolm rebuttal evidence, Appendix A.
47 The stabilisation trigger event is described in Mr Martell’s rebuttal paragraphs 21-25.
18
042407977/1457188.10
Risks during construction
70 There is also uncertainty that comes from the implementation of
ESC practices. Whilst these are uncertainties, I note that managing
these aspects on construction sites is increasingly standard practice.
71 The risks are greater for the Project due to the difficult terrain and
sensitive receiving environments. However the proposed consent
conditions, including an adaptive management approach based on
the proposed performance monitoring, provide strong measures to
manage this risk.
72 A specific measure to reduce the risk during heavy rainfall is the
deployment of erosion control measures in anticipation of a storm
(as mentioned previously in paragraph 69).Requirements for these
actions are included in the proposed consent conditions. This
approach will partially mitigates the risk of poorer pond performance
during extreme events.
73 Uncertainty has been created in the consent application by the lack
of ESC detail to support the ESC aspects of the Site Specific
Environmental Management Plans. This concern was expressed with
regard to Te Puka by Mr Handyside48 and reiterated by him in
caucusing4950. I have recommended to NZTA that additional work is
done in this area to report back to conferencing of Earthworks &
Sediment Control experts. I believe that extra detail will provide
confidence on the practicalities of construction of some of the works
e.g. Te Puka stream diversions and provide greater confidence in
the assessment of construction sediment load.
74 The adaptive management approach supported by monitoring (both
inspection and performance monitoring) provides mechanisms for
feedback and continuous improvement of ESC to ensure that they
met the performance standards set by condition E.3A. The addition
of a Peer Review Panel into the adaptive management framework
will provide additional robustness to this process.
75 The greatest risk of excess sediment comes from poor onsite
practices, which the controls that are proposed for the Project are
designed to prevent. A second risk is from failure of ESC devices
that work well for normal conditions, but are unable to cope with
extreme events (up to and beyond the design events). This risk
increases for steep terrain and for larger sites (as getting the detail
right everywhere over a wider area requires extra diligence and
vigilance).
48 Mr Handyside evidence in chief, paragraph 42.
49 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment
Control Conferencing, 7&8 December 2011, paragraph 20.
50 Expert Conferencing Joint Report to the Board of Inquiry – Earthworks & Sediment Control Conferencing, 20 January 2012, paragraph 12.
19
042407977/1457188.10
76 My experience from the NGTR in similarly steep terrain with 4
million m3 of earthwork is worth considering. The NGTR is
considered to be a case study for good ESC practice, but there were
still failures of devices, although without any environmental
consequences. Such failures were due to small construction details
being wrong, which are only exposed in extreme weather and that
can result in a cascading of consequences. For example, a diversion
channel overtops due to a low point in the bank or it breaches,
which adds more catchment and flow to a pond (over and above
what it was designed for) causing flow over the spillway to exceed
design flows, and partial washout of the spillway. Careful checking
and implementation of ESC practices is required. Consideration of
the performance of ESC devices for what could go wrong may lead
to better, more robust ESC practices.
77 Inclusion in ESC plans of risk assessments and with consideration of
the specific risks to the receiving environment and what could go
wrong with ESC systems would add rigor to the ESC planning. It is
recommended that risk assessments be included as a requirement
of condition E.5.
78 Independent checking of ESC practices is considered to be good
practice for earthworks sites. Frequent inspections are necessary,
but if these are undertaken by the same individuals, then their
benefit may diminish. Periodic review of the ESC practices by
independent professionals (with fresh eyes) can identify issues
and/or offer alternative approaches. It is recommended that this
independent checking role be undertaken by the Sediment
Management Peer Review Panel.
79 Education and performance incentives to contractors for good ESC
practice also can make a difference. I note and support the
condition G.12(A) that Ms Rickard has included for training of
contracting staff on construction and maintenance of ESC devices
and in the details of stream diversions. An example of performance
incentives is the construction of the NGTR where a key result area
was based on performance scoring by the Auckland Regional Council
during its weekly walkovers of the site to inspect the ESC systems.
Good performance in this key result area was linked to performance
bonuses for the alliance that delivered the project. The use of
performance measurements linked to incentives for the NGTR
helped to drive the excellent performance of the erosion and
sediment systems.
CONSENT CONDITIONS
80 I understand Ms Rickard is coordinating revisions to consent
conditions for discussion with the Earthworks and Erosion Control
Expert Caucusing group. With regard to the conditions of consent
20
042407977/1457188.10
that are appended to her rebuttal evidence I wish to make the
following points (some carried down from my evidence above):
81 I recommend before construction that additional baseline monitoring
of sediment in the key streams affected by the construction of the
Project be carried out to confirm the existing sediment loads and the
baseline environmental conditions for performance monitoring
control stations.
82 I recommend monitoring of sediment removal efficiencies and
sediment discharged to streams at control locations is required to be
undertaken to validate the Project assumptions and predicted
construction sediment yields. This is already a requirement of the
ESC monitoring plan (15L) and is partly covered by conditions
G.15(A).b.v and E.14 to E.16, but the differences should be
reviewed and reconciled if important.
83 I recommend a Sediment Management Peer Review Panel be
established using independent professionals to support NZTA and
the Greater Wellington Regional Council in the management of ESC
practices. This is considered to be beneficial due to the large
amount of monitoring to be undertaken and application of the
adaptive management approach, which may at times require
independent, expert advice.
84 I support area limits on active earthworks, but recommend that
these be changeable based on performance monitoring. This could
be achieved by including them in the ESC plans. The changes to
these would require review and recommendation from the Sediment
Management Peer Review Panel and approved by Council Manager.
85 I support the proposed adaptive management approach (consent
condition E.3(l)), but believe that more clarity is required on how
this process will work.
86 I recommend inclusion in ESC plans of risk assessments requiring a
change to condition E.5.
87 I recommend that consent condition E.19(c) include the specific
requirement for bench testing using the proposed flocculants, which
I understand to be the intention of the condition but this would
make it clearer and avoid doubt.
88 I recommend that the definition for the stabilisation trigger event
(e.g. mm of rainfall in a specific period) be defined in the conditions
of consent.
89 I believe that the consent conditions controlling streamworks should
be more explicit in a number of areas;