areva prc-24 white paper clean

Upload: nitish-kumar-gupta

Post on 05-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    1/21

    AREVA NP White Paper on PRC-24

    AREVA acknowledges the need for transient ride through criteria for voltage andfrequency and applauds the NERC Standard Drafting Team for tackling such difficult

    subject matter. AREVA has worked to fulfill Grid Code and Transmission System

    Operators requirements in other countries where our nuclear power plants are beingoperated and constructed. These include new EPR plants under construction in Finland and

    France as well as operating plants in Germany, France and around the world. We also have

    personnel with extensive experience in generation related NERC Standards activities. Wewould like to offer to leverage the knowledge gained in these endeavors to support the

    NERC standard effort.

    Draft NERC Standard PRC-24 proposes the standard ride through criteria forvoltage shown in Figure 1, which shows the proposed standard for the high and low voltage

    excursions.

    AREVA understands this criteria was developed partly based on a study of the WECCregion (reference WECC paper) and the resulting criteria was based on bounding system

    response for all operating areas, including those where wind generating power plant

    characteristics are understood to delay voltage recovery once the fault is cleared However,

    Proposed Voltage Ride-Through Standard

    0.0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.6

    0.7

    0.8

    0.9

    1.0

    1.1

    1.2

    1.3

    1.4

    -1.0 0.0 1.0 2.0 3.0 4.0

    Time (seconds)

    Voltage(PU)

    Pre Fault

    Period

    No-Trip

    Envelope

    0.15

    Figure 1

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    2/21

    this criterion is not technically feasible for large thermal/nuclear generating plants for the

    following reasons.

    1. NERC standards appear to see generators as a discreet part of the overall bulk

    power system. While this is accurate for small wind powered induction generators,

    each large generation plant consists of a generator and a plant auxiliary distributionpower system which must be designed and coordinated with the transmission power

    system.

    2. In the face of an extended voltage decrease and a very slow voltage recovery, asbeing proposed, the stability of large inertia generators is questionable and has to be

    investigated.

    3. The assumption of a near to the plant short-circuit failure with a LVRT is not

    technically correct. The behavior of the auxiliary systems and especially of largeMV motors inherent in a steam plant is different when there is a short-circuit and

    when there is only a voltage drop at the grid connection.

    In Order No. 672, FERC has identified 15 points of justification that will be used toanalyze standards that NERC proposes for approval. These criteria ensure the proposed

    standard is just, reasonable, not unduly discriminatory or preferential, and in the publicinterest. Two of these include

    Proposed standards must be designed to achieve a specified reliability goal

    Proposed standards must contain a technically sound method to achieve the goal

    AREVA understands the specified reliability goal is identified in the purpose of the

    standard, which for PRC-24 is:

    Ensure that generators remain connected to the Bulk Electric System during

    voltage and frequency excursions within the defined criteria of this standard incoordination with other system protection schemes to support transmission systemtransient stability.

    AREVA believes the current criteria for Low Voltage Ride Through as writtenmisses the target for these two points and thus likely will not be approved by FERC.

    AREVA also believes the discussion of record on the PRC-24 standard should clearly state

    that the superposition of extended off nominal voltage and frequency is not technicallypossible with US equipment design standards and thus not required.

    Below, AREVA offers a technical discussion on our concerns with the existing

    standard approach and offers an alternative approach for the SDTs consideration.

    The Voltage Ride through criteria curves consists of several diverse parts, as described

    in the White Paper developed by the Wind Generation Task Force (WGTF) see Figure 2.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    3/21

    Figure 2.

    Voltage Ride Trough Boundaries

    1. Normal and Emergency Voltage Conditions Voltage Tolerance Boundaries

    The normal voltage boundaries have been specified to be for the steady-state

    operating conditions based on the ANSI C84.1-2006 American National Standard forElectric Power Systems and Equipment Voltage Ratings (60Hz)as follows:

    a. Normal Conditions: 5% Continuous Durationb. Emergency Conditions: 10% not specified Duration

    These Criteria are currently widely used in practice and can be complied with by all

    types of new generating plants designed with an in-plant voltage regulation capability.In connection with these criteria, all new equipment, both on the transmission system

    and in new generation plants must be chosen in order to be able to operate and

    withstand these voltage excursions.

    However, many existing power plants were built prior to standards for normal

    transmission system voltage operating bands and thus were designed without in-plantvoltage regulation capabilities. In some cases, assuring nuclear plant offsite power

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    4/21

    voltage adequacy requires minimum voltage limits very near nominal system voltage.

    For these plants, close coordination between the transmission system operations and the

    plant are required to1. Select the main step up transformer and auxiliary transformer taps

    settings to optimize the MVAR support available from the plant under grid

    conditions expected most of the time. (e.g. When operating on VoltageSchedule as Required by NERC Standard VAR-2).

    2. Assure the transmission system is operated to assure that system

    voltage near operating nuclear power plants, with the single contingency (plantaccident, trip and application of safety system loads) maximum voltage drop,

    will be adequate to support the safety system operation as required by NRC

    regulations and new NERC Standard NUC-1.

    Thus, requirements for generation to be able to support a wide band of operating

    transmission system voltage is, in essence, a requirement to back fit these old plants with

    voltage regulation capability. While this might be the best choice in selected situations, it

    might be a less cost effective solution in some regions of the interconnection where thereare higher concentrations of generation. This also may run counter to regulations in some

    states, where the utilities make these system design decisions during the long term planningprocesses and are required by the states to design the system on a least overall fleet cost

    basis. It is important that the transmission operator and the connected generation fleet

    cooperate on these issues as now mandated for nuclear plants through NUC-1.

    In the course of sighting plants in the US, AREVA has had discussions with some US

    transmission operators who interpret these draft standards to require the superposition of an

    extended ability to withstand Emergency Voltage Conditions together with Frequency at95%. Imposing these conditions on plant auxiliary systems are contrary to motor

    manufacturing standards in NEMA MG-1 which state

    Section III MG 1-2006 LARGE MACHINESINDUCTION

    MACHINES Part 20, Page 11

    20.14 VARIATIONS FROM RATED VOLTAGE AND RATED FREQUENCY

    20.14.1 Running

    Induction machines shall operate successfully under running conditions at ratedload with a variation in the voltage or the frequency up to the following:

    a. Plus or minus 10 percent of rated voltage, with rated frequency

    b. Plus or minus 5 percent of rated frequency, with rated voltagec. A combined variation in voltage and frequency of 10 percent (sum of

    absolute values) of the rated values, provided the frequency variation does

    not exceed plus or minus 5 percent of rated frequency.

    Performance within these voltage and frequency variations will not necessarily be

    in accordance with the standards established for operation at rated voltage and

    frequency.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    5/21

    AREVA appreciates the basis for Voltage Ride Through Clarification #6 and

    encourages the SDT to keep this clarification in the final standard.

    AREVA designs our new plant power systems with voltage regulation capability to

    support long-term variations in transmission system voltage, but believes that capitoldecisions on when to add plant voltage controls on existing plants should be made on an as

    needed basis to facilitate improved MVAR support and not to support an arbitrary criterion.

    A requirement to mandate Automatic Tap changers at existing units when transformers arereplaced may be a reasonable long term approach.

    2. LVRT Three-Phase Fault Clearing Boundary

    This part of the curve addresses the bolted three-phase fault boundary with normal

    clearing, as a worst-case scenario for short-circuit fault, after which the generators are

    required to remain in service.

    The short-circuit fault in the proximity of the power plant will be seen from the point ofview and response of the power plant similar as the short-circuit fault at the grid connection

    (switchyard) of the plant. During the time the fault is connected, the generator terminal

    voltage lowers, depending on the type and distance of the fault to the plant and thegenerator is able to deliver only a part of the pre-fault active power (MW) to the grid. Since

    the Turbine torque is still constant, the generator experiences an acceleration proportional

    to output power imbalance. If not cleared within certain time boundaries, which are

    individual to every plant, it will lead to the loss of the transient stability.

    Consistent with FERC expectations, the proposed standard clearing time is 9 cycles or

    150ms. This is the clearing time of the Zone 1 protection in the connected grid and consistsof:

    - Relay operation time

    - Communication time- Breaker time

    The voltage drop for the duration of the fault is proposed to be down to 0% which is

    very conservative but acceptable and is consistent with the statement that a near to plantfault will be seen as a fault in the switchyard connecting the plant to the grid.

    AREVA believes this is a reasonable basis for the fault clearing time and 150ms shouldbe used for the US standard. The time 150ms is comparable to the clearing time specified

    in the German Grid Code from E.ON and is smaller than the requirement from NORDEL

    (Nordic Countries Grid Union) which is requiring the generators to withstand 250msclearing time of the fault based on their weak grid conditions.

    It does not appear that breaker-failure protection times were taken into account as a part

    of the standards effort. This protection is typically set to wait between 0.1 to 0.35

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    6/21

    seconds for the main protection to clear the fault and should be based on the critical

    clearing time for the local generator. This criteria is also correspondent with the definition

    that the normal design contingencies include among others a permanent three-phase faulton any generator, transmission circuit, transformer or bus section, with normal fault

    clearing and with due regard to reclosing facilities [Kundur, 1993]. It would seem that a

    complete standard for transients might address the requirement for the transmissionsystem/switchyard equipment owners to set these breaker failure units and updates the

    settings as necessary based on the latest stability study results.

    Because the required grid protection clearing times needed to assure stability vary, it is

    again important for the Generation Owners and the Transmission Owners and Planners to

    collaborate on an on going basis to assure the system design is maintained as needed to

    assure reliable operation of the bulk power system as additional generation is added as iscurrently projected.

    3. LVRT Voltage Recovery Boundary

    This is the part of the standard which addresses the system voltage recovery after the

    fault is cleared. It is important to keep in mind that, while part 2 of the curve can be seen asquasi-static and be stated uniformly for all plants, the expected voltage recovery will vary

    location by location depending on nearby plant characteristics and its real shape can be

    determined only by dynamic simulation. For the proposed criteria, the initial condition isthat the voltage is still at 0% and linearly recovers to 90% 1.6 seconds after the fault

    clearing. While this criteria is certainly bounding for all types of generation, it is unrealistic

    for large generation plants for the reasons stated above.

    There is also an important difference between synchronous (mostly used in thermal,

    nuclear and hydro generating power plants) and asynchronous (wind generating plants)

    generators that requires the stator of the asynchronous generator to be magnetized from thegrid before it works and therefore needs reactive power in order to build up the magnetic

    field.

    The asynchronous generator is able to operate also in a stand alone system, if it is

    provided with capacitors which supply the necessary magnetization current. It is also

    required that there is some remnant magnetization in the rotor iron, i.e. some leftover

    magnetism during the start of the turbine. Otherwise there is a need for a battery and powerelectronics, or a small diesel generator to start the system). This means that after voltage

    drops in the supplying grid the asynchronous generator needs relative longer time for

    supporting the voltage recovery, because it needs the extra time to rebuild itselectromagnetic field compared to the synchronous generator.

    Synchronous generators are equipped with AVR systems which provide a fault forcingfunction to help the transmission system recover from faults. With these generators

    nearby, the system voltage will recover quickly to >90% once the fault is cleared at

    150msec.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    7/21

    In this part after the fault was cleared, the leading magnet wheel of the synchronous

    generator will be slowed down by the recurrent electrical torque and reaches in the stable

    state under declining oscillations the synchronous rpm based on the grid frequency (60Hz).The proposed standard attempts to describe this dynamic behavior trough the linearly

    increasing part of the curve.

    If the synchronizing capability of the grid not sufficient to slow down the accelerated

    magnet wheel after the fault was cleared, the turbo-generator set will transit into slip mode

    operation, which is associated with enormous mechanical stress. This is in fact the loss ofthe transient stability. Areva believes the standard should consider this and use a criteria

    based on ensuring the generator will not reach this undesired operating condition.

    Other parameters influence the after fault voltage recovery at the grid connection:

    oThe inertia of the turbo-generating set (higher inertia means higher stability)

    oThe position of the generator voltage regulator and the resulting operation

    mode either leading, lagging or cos=1 (measure for the level of stability of the

    generator prior to the fault=> leading =>max angular displacement =>worst-case)

    oThe grid connection voltage level and the related short-circuit current

    capacity (it is the measure for the resynchronization capability of the grid)

    The purpose for this introduction is to show how complicated correlations are in an

    attempt to represent the entire transmission system by a simple curve of the standard.

    According to the WGTF white paper, the voltage points during voltage recovery for

    Zone 2 three-phase fault with normal clearing time have been drawn into the diagram and acurve was chosen to begin at 0% voltage and 150ms to reach the 90% voltage in a manner

    that ensures all the voltage points will be within the area specified/marked-off by the curve(Figure 3).

    Note that only handful (12) of the voltage points were available for this study which

    makes it less reliable in terms of statistical evaluation and is unlikely that all possible

    scenarios are covered. This criteria forces large plants connected to grids with high voltageand higher short-circuit capability (in the Fig.3 represented by the points Nine Mile 230kV

    (PAC) and Foote Creek 230kV (PAC)) to assure they can ride trough very poor voltage

    conditions that can not realistically occur on their grid connections.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    8/21

    Figure 3

    Existing and new LVTR standard for WECC with Zone 2 Relay Results added

    Fig.4 shows a comparison of the proposed standard LVRT vs. a generator stability

    study from a 1300MW unit which clearly shows how far the proposed boundary and the

    voltage recovery for the generator terminals after 150ms short-circuit fault differ. In the

    study the voltage recovery up to 100% is achieved after 900ms versus the by standardproposed 1.6s.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    9/21

    Figure 4

    Proposed LVTR standard for WECC vs. 1300MW unit stability study.

    The proposed criteria may be acceptable for the generators if they can maintain

    stability, but likely will cause problems for the auxiliary systems of the thermal and nuclearplants, because of the impact on the voltage in the auxiliary systems. The voltage drop will

    be propagated through the whole system and the relative slow recovery can cause under-

    voltage trips for vital consumers which will lead to a plant trip even if the generatorremains stable. Even newer plants equipped with On Line Tap Changers can not workagainst the voltage drop, because the whole event is too fast for the OLTC to react.

    AREVA has extensively studied the ability of in-plant power systems to ride throughgrid initiated voltage transients resulting from the near to plant short-circuit failures.

    Several slides based on these studies are included in the Fig 5 and 6.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    10/21

    Figure 5

    Figure 5 shows the voltage recovery profiles at the MV system distributions within

    the auxiliary systems of a plant after the clearing of the near-to-plant short-circuit

    failures, cleared after 150ms and 210ms. These curves are very similar to the voltagerecovery profile on the main generator terminals and clearly show the impact of theshort-circuit failure to the whole auxiliary system.

    This impact is caused by the ratio of the impedances of the equipment which aredecisively involved in the Short-Circuit Impedance such as the Step-Up (ZStT),

    Auxiliary Transformer (ZAUX) and the MV-Motors (ZMot), and determine the resulting

    short-circuit current in the system.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    11/21

    Figure 6

    In the Figure 6 you can observe the behavior of a MV-Motor during and after a

    short-circuit. In the first 200ms to 300ms, the motor Short-Circuit Current contribution

    decreases almost to zero. This means that the motor has spent the storedelectromagnetic field and will be stalled or tripped by the associated undervoltage

    monitoring (this case is not shown in the Figure 6). The Short-Circuit Failure is cleared

    after 300ms and after this period a re-acceleration of the stalled/tripped motors occurs.Clearly observed can be the Motor Starting Current which is 3,8 times the Motor rated

    current and also the voltage recovery.

    The technical limit for the time plant bus voltage can be depressed due to external

    faults is based on time constants for the decay of the electromagnetic field in plant

    motors, which will support plant voltage until the magnetic fields collapse. The limit is

    ~ 200mSec and thus, the clearing time of 150mSec is appropriate from this perspective.

    As a conclusion we would like to state, that the proposed approach is not feasible

    for thermal and nuclear power plants and that a meaningful standard to address thestated reliability goal must not only consider the main generator unit protection settings

    and the turbo generator set stability but also the whole auxiliary system of the plant.

    Due to technology differences, developing criteria for all plants based a study focusingon wind generating plants seems inappropriate.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    12/21

    AREVA suggests that in order to ensure that the all plants can ride through

    disturbances such as a short-circuit in the grid, stability studies are needed (and already

    required to be performed by TPL standards) to document the expected voltagerecovery, which should be provided to the generation owners. Generation owners

    should then be required to have documented studies to show all plant equipment can

    withstand this transient or to identify any limitations. These studies should also showthat plant relaying should be coordinated with the simulation of a short-circuit fault in

    the plant switchyard which will be cleared within 150ms and show that the generator

    remains stable. Note that loads that may cause a plant trip due to a low voltage mightrequire a dynamic analyses to asses the ability to survive the transient. Suggested

    standard language is included in attachment 1.

    4. HVRT High Voltage Boundary

    This section addresses the high voltage ride trough which covers the high voltage

    period after the fault was cleared.

    A concern would be that the specified voltage level in the first (120%) second(118%) and third (115%) step of the HVRT will be propagated trough the whole

    auxiliary system of thermal and nuclear power plants and could lead to over voltage on

    the consumers. The NEMA MG 1-2006 standard is stating for AC Motors that theyshould be able to operate at plus/minus 10% of the rated voltage at rated load under

    running conditions but there is no guidance for such a very short-term voltage

    variations (1s duration) as described in the HVRT curve.

    For example the Nordic Grid Code is specifying 110% voltage level as the

    maximum for short-term overvoltage (up to 1h duration) with a small power output

    decrease allowable (up to 10%). The document European utility Requirements forLWR Nuclear Power Plants specifies the short-term overvoltage with max 107.5% for

    maximum 30min.

    The impact of such fast voltage swells on plant power systems should be investigated

    prior to making a standard HVRT.

    5. References:

    a. The Technical Basis for the new WECC Voltage Ride-Trough (VTR)

    Standard, June 13 2007, Developed by Wind Generation Task Force

    (WGTF)b. Power System Stability and Control, 1993, Kundur

    c. Nordic Grid Code 2007, NORDEL

    d. Grid Code (High and Extra High Voltage), 1. August 2003, E-ON/Netze. European utility Requirements for LWR Nuclear Power Plants Rev C,

    April/2001, EUR

    f. NEMA Standard MG 1-2006

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    13/21

    6. Lack of Design Guidance in US Standards

    AREVA is not aware of any guidance in US generation plant design standards thataddress these issues, hence many new plants may be built that do not address these

    issues. NERC should engage IEEE to develop design standards to be applied to the next

    generation of plants.

    7. AREVA Recommendations for Voltage Ride-Trough

    NERC Reliability Standards Development Procedure allows for the development of a

    white paper, defined as

    An informal paper stating a position or concept. A white paper may be used topropose preliminary concepts for a standard or one of the documents above.

    AREVA is not aware of a white paper considering characteristics for all types of

    generation for this issue and would support the development of one. AREVA suggests onthe following approach for the voltage ride through standard to fully address the technical

    issues associated with voltage ride through.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    14/21

    A. Introduction

    1. Title: Generator Performance During Frequency and

    Voltage Excursions

    2. Number: PRC-024-2

    3. Purpose: Ensure that generators remain connected to

    the Bulk Electric System during voltage and frequency excursions

    within the defined criteria of this standard in coordination with other

    system protection schemes to support transmission system transient

    stability.

    4. Applicability4.1. Generator Owner

    4.2. Transmission Planners

    4.3. Transmission System Owners

    B. Requirements

    R1. Generator Owners shall document studies to confirm each

    set generatorion plant protective relaying to meet the

    following performance requirements for generator units20 MVA and greater, or generating plants/ facilities

    consisting of one or more units with total generation > 75

    MVA (gross aggregate nameplate rating) at the point of

    interconnection to the Bulk Electric System to remain

    connected during steady-state and system frequency

    excursions as follows:

    R1.1. Operate continuously within a frequency range of

    59.5 Hz to 60.5 Hz.

    R1.2. Generators shall remain connected during

    frequency excursions in accordance with

    Attachment 1of -PRC-024-2.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    15/21

    R1.3. Instantaneous underfrequency relay trips setting

    shall be set no higher than 57.8 Hz.

    R1.4. Instantaneous overfrequency relay trip settings shall

    be set no lower than 61.2 Hz.

    R1.5. The Generator Owner shall provide to Regional

    Entities, Reliability Coordinators and Transmission

    Operators generator protection frequency trip

    settings as specified by requirements R1.1 through

    R1.4 within 30 days of any change or request for

    data, to coordinate with regional Off Nominal

    Frequency Load Shedding and Restoration

    programs.

    R2. The transmission planner shall

    R2.1. Develop and communicate results of stability

    studies required by the TPL standards to determine

    critical clearing time and subsequent post fault

    voltage recovery transient expected at the

    switchyard based on worst case conditions (unit at

    full power and worst case reactive power output).

    R2.2. Use any design limitations identified by thegeneration owner per in their transmission models

    used to perform studies

    R3. The owner of the switchyard and the transmission lines

    coming to the plant switchyard shall use the calculated

    critical clearing time to set breaker and breaker failure

    protective relaying timing to assure all faults will be

    cleared prior to the unit reaching an unstable state.

    R4. Generator Owners shall document studies to confirm the

    generator protective relaying to can meet the following

    performance requirements for generator units 20 MVA

    and greater, or generating plants/facilities consisting of

    one or more units with total generation > 75 MVA (gross

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    16/21

    aggregate nameplate rating) at the point of

    interconnection to the Bulk Electric System to will remain

    connected during steady-state and system voltage

    excursions as follows:

    R4.1. Operate continuously within 95% to 105% of rated

    generator terminal voltage with transformer taps

    selected to optimize the level of MVAR support

    available with switchyard voltage on schedule as

    defined per the VAR-1 standard.

    R4.2. Operate on the site specific switchyard voltage

    schedule per VAR-1 and identify any limitations to

    the normal transmission system voltage bands due

    to plant design issues (such as those covered by

    NUC-1).

    R4.3. Generators will remain connected during transient

    voltage excursions measured at the point of

    interconnection to the Bulk Electric System in

    accordance with the plant specific voltage recovery

    curves as determined by periodic transmission

    system stability studies. No other plant trips should

    occur due to the limiting voltage recovery transient.

    R4.3.1. Plant undervoltage relaying shall be

    designed to coordinate with the worst case

    voltage recovery for which the plant will be

    stable.

    R4.3.2. If there are plant design issues that require a

    trip during the defined voltage recover

    period, the Generation owner shallcommunicate these limitations to the

    transmission planner.

    R4.3.3. Generators are permitted to be tripped after

    fault initiation if this action is intended as

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    17/21

    part of a special protection scheme (SPS) or

    remedial action scheme (RAS).

    R4.3.4. Generators are permitted to be tripped when

    clearing a system fault necessitates

    disconnecting the generator.

    R4.4. The Generator Owner shall provide to Regional

    Entities, Planning Coordinators, Transmission

    Operators and Transmission Planners generator

    protection trip settings that are affected by

    voltagethe study as specified by requirement

    R2.2R4 within 30 days of any change or request for

    data.

    R5. Existing generators (at the time of regulatory approval of

    this standard) that are unable to comply with any of the

    following requirements, R1 and sub requirements R1.1

    through R1.4, R2 and sub requirements R2.1 through

    R2.2, due to equipment limitations shall notify the

    Regional Entity and provide documentation that explains

    the technical limitation and prepare a mitigation plan for

    such equipment limitations.

    C. Measures

    M1. Generator Owners demonstrate compliance by having

    documentation that generator protective relays have

    been set in accordance with the requirements in R41.

    M2. The transmission planners shall demonstrate

    compliance by showing results of studies and showing

    proof that the results were provided to the Generation

    Owner as required by R2.M3. The transmission/switchyard equipment owners shall

    demonstrate compliance by showing that Breaker

    Failure protection time settings were set based on the

    local units CCTs.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    18/21

    M4. Generator Owners demonstrate compliance by having

    documentation that generator protective relays have

    been set in accordance with the requirements in R2.

    M5. Generator Owners demonstrate compliance by having

    documentation and a mitigation plan for any

    generator/plant that do not comply due to equipment

    limitations in accordance with R3.

    D. Regional Differences

    D1. Reference Documents

    The Technical Justification for the New WECC Voltage Ride-Through (VRT)

    Standard, A White Paper Developed by the Wind Generation Task Force (WGTF),

    dated June 13, 2007, a guideline approved by WECC Technical Studies Subcommittee.

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    19/21

    Attachment 1-PRC-024-2

    PROPOSED OFF NOMINAL FREQUENCY CAPABILITY CURVE

    55

    56

    57

    58

    59

    60

    61

    62

    63

    64

    65

    0.01 0.1 1 10 100 1000 10000

    TIME (sec)

    FRE

    QUENCY(Hz)

    Frequency (hertz) 61.2 60.5 59.5 57.8

    Time (seconds) .0095 to 2 600 to 10,000 1800 to10,000

    .0095 to 2

    No Trip

    Zone

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    20/21

    Attachment 2-PRC-024-2

    Proposed Example of a Voltage Ride-Through Curve

    Voltage Ride-Through Curve Clarifications

    1. This curve is based upon normal operating voltages as

    measured at the point of interconnection to the Bulk ElectricSystem.

    2. Generator protection relays monitor low side voltage. If the

    main generator step transformer tap is set for other than 1.0

    per unit, then the generator protection relay settings must

    account for this.

    3. This voltage standard may be met by installing additional

    equipment (such as dynamic VAR compensation) within the

    generating facility.

    4. When applying the above curve to three-phase Zone 1 faults

    with normal clearing, utilize actual fault clearing times, but not

    greater than 9 cycles.

    Proposed Voltage Ride-Through Standard

    0.0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.6

    0.7

    0.8

    0.9

    1.0

    1.1

    1.2

    1.3

    1.4

    -1.0 0.0 1.0 2.0 3.0 4.0

    Time (seconds)

    Voltage(PU)

    Pre Fault

    Period

    No-Trip

    Envelope

    0.15

    Proposed Voltage Ride-Through Standard

    0.0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.6

    0.7

    0.8

    0.9

    1.0

    1.1

    1.2

    1.3

    1.4

    -1.0 0.0 1.0 2.0 3.0 4.0

    Time (seconds)

    Voltage(PU)

    Pre Fault

    Period

    No-Trip

    Envelope

    0.15

  • 7/31/2019 AREVA PRC-24 White Paper Clean

    21/21

    5. Within the voltage ride-through standard fault recovery and

    high voltage boundaries, referred to as the No Trip Envelope

    in the above curve generators are required to remain in-service

    after fault clearing.

    6. The curve depicted in this Attachment 2 assumes system

    frequency of 60 Hertz.