appendix g - contamination report · 2019-09-28 · appendix g contamination report . report no....

97
Appendix G Contamination report

Upload: others

Post on 21-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Appendix G

Contamination report  

 

 

 

Page 2: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

REPORT NO. 115085_V7

STAGE 1 PRELIMINARY SITE INVESTIGATION

NEW ENGLAND HIGHWAY UPGRADE –

BELFORD TO GOLDEN HIGHWAY

ENVIRONMENTAL EARTH SCIENCES NSW PREPARED FOR ARUP PTY LTD 21 FEBRUARY 2017

Page 3: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7

EXECUTIVE SUMMARY Environmental Earth Sciences was commissioned by Arup Pty Ltd (Arup) to undertake this Stage 1 Preliminary Site Investigation (PSI) for the areas involved in the proposed upgrade of the Golden Highway and New England Highway, Belford, NSW. This report has been prepared to support the overarching Review of Environmental Factors (REF) study commissioned by Roads and Maritime. The study area incorporated current lots and road easements both within and adjacent to the project area. A historical report identified one lot within the project area where suspect cattle tick dipping may have occurred and a timber treatment yard was suspected to have been located. Based upon findings of the inspection no evidence of commercial / industrial land use within the project area was identified. Potential contamination from the suspected cattle tick dip and timber treatment yard was not observed. The inspection identified the following land uses outside of the project area whereby commercial activity or development has taken place, however no indications or observations of contamination relating to these adjacent lots were noted to impact the project area:

Lot 21 in DP1014307 – retail service station operating underground petroleum storage system (UPSS);

Lot 35 in DP1128981 – abattoir operation with associated cattle pens and water treatment / irrigations paddocks. The main works area is situated far south of the proposed works corridor; and

Lot 24 in DP1128978 – now vacant property that was used as a construction compound during the Great Northern Railway line bridge over the Golden Highway upgrade circa 2009.

During the site inspection indications of surface salt scalding consistent with dryland salinity were noted within the project area (along the northern margin of Lot 35 in DP1128981). Although not an indicator of contamination, potential saline conditions could potentially degrade concrete used in construction. Potential salinity issues are recommended to be investigated across a range of landscapes over the site with assessment undertaken with reference to should be planned with reference to the Department of Land and Water Conservation (2002) – Site Investigations for Urban Salinity (DLWC, 2002). Prior to commencement of proposed construction works it is recommended that a Construction Environmental Management Plan (CEMP) be prepared to include (but not limit) procedures for controls / management of:

soil erosion, sedimentation and dust generation;

soil / spoil stockpile management including onsite / off-site material tracking and beneficial reuse / waste disposal options;

general erosion, sediment and water quality control safeguards (e.g. sediment basins, stockpile areas, wash-downs, batch plants, refuelling and chemical storage sites) involving lining and/or bunding if they are located within 50 m of a shallow groundwater source);

Page 4: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7

rehabilitation of works area;

dewatering management;

spill response and associated emergency planning;

personal protective equipment (PPE) controls for construction workers;

Unexpected Findings Protocol (UFP) procedure for managing instances where gross contamination and/or hazardous materials are encountered, with appropriate consideration of WH&S controls for mitigating risk to construction workers.

On behalf of Environmental Earth Sciences NSW Project Manager Chris Newland Senior Environmental Scientist Project Director Alice Plioplis Senior Environmental Scientist

REVISION HISTORY

Version Author / Reviewer Notes Date Signature

V1 Chris Newland /

Alice Plioplis Draft for review

by Arup 22-Feb-2016

V2 Chris Newland /

Alice Plioplis Arup comments 10-Mar-2016

V3 Chris Newland /

Alice Plioplis Arup / RMS comments

29-Apr-2016

V4 Chris Newland /

Alice Plioplis Arup / RMS comments

25-May-2016

V5 Chris Newland /

Alice Plioplis Arup / RMS comments

2-Jun-2016

V6 Chris Newland /

Alice Plioplis Arup / RMS comments

24-Nov-2016

V7 Chris Newland /

Alice Plioplis Arup / RMS comments

21-Feb-2017

Page 5: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7

TABLE OF CONTENTS

1 INTRODUCTION & BACKGROUND ............................................................................ 1

2 OBJECTIVE ................................................................................................................. 3

3 WORKS UNDERTAKEN .............................................................................................. 3

4 SITE CONDITION AND SURROUNDING ENVIRONMENT.......................................... 4

4.1 SITE IDENTIFICATION 4

4.2 NEARBY LAND USES 6

4.3 SENSITIVE RECEPTORS 6

4.5 REGIONAL GEOLOGY 7

4.6 REGIONAL SOIL 7

4.7 TOPOGRAPHY AND DRAINAGE 7

4.8 ACID SULFATE SOILS 7

4.9 SALINITY 8

4.10 HYDROGEOLOGY 9

4.11 METEOROLOGY 10

5 HISTORICAL REVIEW ............................................................................................... 11

5.1 REVIEW OF HISTORICAL AERIAL PHOTOGRAPHS 11

5.2 COUNCIL PLANNING CERTIFICATE 12

5.3 SAFEWORK NSW DANGEROUS GOODS SEARCH 12

5.4 NSW EPA CONTAMINATED SITES REGISTER 13

5.5 REVIEW OF HISTORICAL REPORT PERTAINING TO SITE 14

6 SITE OBSERVATIONS & POTENTIAL FOR CONTAMINATION .............................. 14

7 CONCEPTUAL SITE MODEL .................................................................................... 17

8 CONCLUSION ............................................................................................................ 20

9 RECOMMENDATIONS ............................................................................................... 21

9.1 GENERAL CONSTRUCTION MANAGEMENT 21

9.2 SPOIL AND FILL MANAGEMENT 22

9.3 SPECIFIC CONTAMINATION MITIGATION MEASURES 22

9.4 SPILL MANAGEMENT 23

9.5 DEWATERING MANAGEMENT 23

10 LIMITATIONS ............................................................................................................. 23

11 REFERENCES ........................................................................................................... 24

APPENDICES

A SOIL REPORTS

B REGISTERED BORE INFOROMATION

C COUNCIL PLANNING CERTIFICATE

Page 6: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7

D DANGEROUS GOODS INFORMATION

E LAND TITLES CERTIFICATES

F PHOTOGRAPHS

Page 7: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 1

1 INTRODUCTION & BACKGROUND Roads and Maritime Services (Roads and Maritime) propose to upgrade the New England Highway between Belford and the Golden Highway. The road upgrade would improve traffic flow, travel times and safety for motorists along a busy section of the New England Highway. The proposal would provide a divided road with two travel lanes in each direction between Belford and the Golden Highway and a flyover for vehicles turning right from the Golden Highway towards Maitland and Newcastle. The project is located within the Singleton local government area (LGA) and the Hunter region of the Roads and Maritime network. Key features of the project include:

Widening the New England Highway for around 3.2 km to provide a divided road with two travel lanes in each direction between Belford and the Golden Highway

Replacing the existing right turn movement from the Golden Highway to the New England Highway with a right turn flyover

Removal of the Whittingham rest area adjacent to the New England Highway and Golden Highway intersection.

Environmental Earth Sciences was commissioned by Arup Pty Ltd (Arup) to undertake this Stage 1 Preliminary Site Investigation (PSI) for the corridor of the abovementioned project near Belford, NSW (the “project area”). The assessment also reports on potential contamination in lots adjacent to the project area that have been historically developed or currently used for commercial purposes (the “study area”). Refer to Figure 1 for location of the project area. A preliminary environmental investigation report prepared by Hills Environmental Pty Ltd (2014) - SH9 New England Highway Upgrade - Belford Deviation to SH27 Golden Highway Junction Preliminary Environmental Investigation (ref: RPT-PEI-J000134-2014-06-V 02.docx; dated 19 June 2014) (the “PEI”) identified the following current and historical potentially contaminating land uses:

Onsite former timber treatment post yard.

Onsite former rail cattle yard on the northern side of the New England Highway about 350 metres east of the Golden Highway intersection.

Offsite retail service station situated on the western side of the New England Highway. Inspection of historical aerial images reported other potentially offsite features such as a former building compound and an abattoir which could pose a potential offsite risk to works within the works corridor.

Page 8: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Title: Site Location

Location: Junction A15 and B84

Belford NSW

Client: Arup Pty Ltd Job No: 115085

Drawn By: CN Scale: NTS Source: Google Proj Man: TC Date: Feb 2016 Figure 1

SITE

Page 9: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 3

2 OBJECTIVE With reference to requirements of the NSW Office of Environment and Heritage (OEH) (2011) – Contaminated Sites: Guidelines for Consultants Reporting of Contaminated Sites (OEH, 2011) this report aims to:

review site history and other available information to identify potential sources and areas on site affected by current and historical contamination;

identify potentially affected media (soil and groundwater);

determine potential contaminants of concern; and

identify potential human and ecological receptors and complete exposure pathways that could pose an unacceptable risk to future users of the site and the environment.

The Stage 1 PSI will ascertain if current / historical activities in the study area (west) have resulted in contamination which may require appropriate Stage 2 detailed assessment to further delineate and characterise risk and/or require management to ensure that the contamination in the corridor does not present unacceptable risk to users of the site and the environment.

3 WORKS UNDERTAKEN Works undertaken for this Stage 1 PSI included:

review of the PEI report;

inspection of the study area undertaken on 21 January 2016 to ascertain land-use features and assess locations of potential contamination identified in the PEI report;

general desktop assessment including the obtaining information from the following sources:

o geology, soil, acid sulfate soils, hydrology and meteorology maps and databases (undertaken 17 January 2016);

o Section 149 (1) and (5) council planning certificate for a service station property adjacent to the project area (undertaken 30 October 2015);

o SafeWork NSW dangerous goods information for service station property adjacent to the project area (undertaken 11 February 2016);

o historic aerial photography;

NSW Environment Protection Authority (EPA) search of register of notified properties under the Contaminated Land Management act 1997 (CLM Act) subject to investigation / remediation orders (search undertaken on 17 January 2016);

preparation of this Stage 1 PSI report to detail findings.

Page 10: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 4

4 SITE CONDITION AND SURROUNDING ENVIRONMENT

4.1 Site Identification The site is a combination of entire lots and portions of lots within a mainly rural area approximately 40 kilometres south of Singleton. The ‘study area’ for this assessment encompasses an area slightly larger than the ‘project area’ and constitutes the boundary for this Stage 1 PSI. Most lots within the project area have only historically been used for rural / agricultural purposes, or developed for highway corridors. A summary of the site details are presented in Table 1.

TABLE 1 SITE DETAILS

Item Details

Address Junction of New England Highway & Golden Highway, Belford NSW

Lot & DP number

Study Area

Lots 23 - 25 in Deposited Plan (DP) 1128978;

Lots 22 in DP1014307;

Portion of Lot 1 in DP653039;

Portion of Lot 4 in DP621020;

Lot 303 in DP1179681;

Portion of Lots 34 - 36 in DP1128981; and

Portions of highway easements for New England Highway and Golden Highway.

Project Area

Portion of Lot 1 in DP653039.

Portion of Lot 4 in DP621020.

Portion of Lot 34 in DP1128981.

Portions of road easements for New England Highway and Golden Highway.

Zoning

Singleton LEP (2013)

RU1 – Primary production

SP2 –Infrastructure

Local Government Singleton Council

Study Area &

Project Area

Figure 2

- Study area marked inside ‘blue’ polygon.

- Project area marked inside ‘white’ polygons.

Page 11: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

LEGEND:

Study boundary

White polygons indicate project boundary

Title: Study and Project Boundaries

Location: Junction A15 and B84

Bedford NSW

Client: Arup Pty Ltd Job No: 115085

Drawn By: CN Scale: NTS Source: NSW LPI

Proj Man: CN Date: May 2016 Figure 2

New England Highway

Golden Highway

Abattoir operations

Former Construction

Compound

Service Station

Abattoir treatment water irrigation

paddocks

Abattoir treatment water irrigation

paddocks

Page 12: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 6

4.2 Nearby land uses Due to the large area of the site and the irregular shape, all features are given with reference to the approximate latitude / longitude location of the junction of the Golden Highway and New England Highway (ref: 32o 38’ 33.62” S; 151o 14’ 1,26” E), with associated distances from this reference given ‘as-the-crow-flies’. The following general land uses / features summarised in Table 2 were noted at the time of the site inspection on 21 January 2016:

TABLE 2 NEARBY LAND USES

Direction from Junction

Feature Approximate

Distance Location

West Great Northern Railway main line 635 m 32

o 38’ 33.62” S; 151

o 14’ 1,26” E

Mudie’s Creek 1,500 m 32o 38’ 34.25” S; 151

o 13’ 3.72” E

South E.C. Throsby Pty Ltd Abattoir 900 m 32

o 39’ 5.61” S; 151

o 14’ 2.54” E

Belford township 6,500 m 32o 41’ 38.51” S; 151

o 16’ 8.33” E

East

Unnamed creek 1 200 m 32o 38’ 39.93” S; 151

o 14’ 8.05” E

Unnamed creek 2 1,200 m 32o 38’ 46.48” S; 151

o 14’ 44.7” E

Jumpup Creek 3,800 m 32o 39’ 9.83” S; 151

o 16’ 22.54” E

Belford National Park 5,000 m 32o 38’ 54.78” S; 151

o 17’ 5.27” E

North

Service station 300 m 32o 38’ 26.42” S; 151

o 13’ 53.4” E

Hunter River 2,100 m 32o 37’ 24.89” S; 151

o 14’ 11.9” E

Singleton township 9,000 m 32o 34’ 0.25” S; 151

o 10’ 29.19” E

Refer to Figure 2 for project and assessment boundaries, lot boundaries, area features and commercial / industrial land uses in the nearby area.

4.3 Sensitive receptors

The following potential receptors have been identified for the site:

onsite human –

o residents, visitors and employees of rural properties;

o construction workers during proposed upgrade works; and

o maintenance workers (roads and utilities);

offsite human –

o residents, visitors and employees of rural properties and service station site;

o recreational users of the Hunter River and Jumpup Creek;

onsite ecological –

o surface water (two unnamed creeks to the east of the service station);

o groundwater (freshwater environment);

Page 13: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 7

offsite ecological –

o surface water (Mudie’s Creek to the west; Jumpup Creek to the east; Hunter River to the north).,

o groundwater (freshwater environment).

4.5 Regional Geology

A search of the Rasmus et al (1969) Singleton 1:250,000 Geological series sheet S1/56-01 undertaken on 17 January 2016 reported that the site is directly underlain by the Permian-aged Mulbring Siltstone Formation of the Maitland Group, consisting of siltstones and sandstone.

4.6 Regional Soil A search of the Kovac and Lawrie (1991) - Soil landscapes of the Singleton 1:250,000 sheet undertaken on 17 January 2016 reported that regional soils belong in the ‘Rothbury’ landscape. Soils typical of this landform are noted to consist of the following characteristics:

red podzolic soils (Dr3.21, Dr5.21) on upper slopes;

yellow Podzolic soils (Dy2.41) on mid slopes;

yellow solodic soils (Dy.42) and Brown Soloths (Db3.40) on lower slopes; and

prairie soils (Gn4.22) in the drainage lines.

4.7 Topography and drainage The site is situated from approximately 86 metres above Australia Height Datum (mAHD) just west of the picnic area, to approximately 62 mAHD in a drainage depression just south of the highway junction. Landscapes in this area generally consist of undulating to rolling hills with elevations ranging from 60 – 140 metres. Average slopes are 6 – 10% with some slopes up to 12%. Slope lengths are 800 – 1,000 metres with local relief of 60 – 80 metres. Drainage lines are common throughout the area and occur at intervals between 200 – 1,000 metres (Kovac and Lawrie, 1991). At the time of inspection on 21 January 2016 the majority of the existing rural properties comprising the study area were unsealed. As such there would be a high degree of infiltration and recharge to groundwater. Sealed areas within the study area comprise the tarmac sections of the highway corridor, where precipitation would run-off onto adjacent off-seal areas, or be redirected into engineered stormwater infrastructure.

4.8 Acid Sulfate Soils A search of the Singleton LEP (2013) undertaken on 17 January 2016 reported that the site does not lie in an area requiring management for potential inland acid sulfate soils (PASS).

Th is w as conf irm ed t h rough t he Department of Land and Water Conservation acid sulfate soil risk map for Singleton (Naylor, 1995) which indicated a low likelihood for PASS occurrence in the vicinity of the site.

Page 14: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 8

4.9 Salinity A search of the online NSW Soil and Land Information System (eSPADE) undertaken on 17 January 2016 indicated that three exploratory test pit excavations have been advanced in the vicinity of the site at the Belford-Singleton Abattoir site. Of the three pits two were reported with no salting evident, and one indicating that salting was strongly evident. Refer to the individual eSPADE soil profile reports and associated locality map in Appendix A.

Page 15: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 9

4.10 Hydrogeology A search of the NSW Office of Water “waterinfo.nsw” website undertaken on 17 January 2016 identified four registered groundwater bores located at the service station adjacent to the study area (Lot 21 in DP1014307). All bores were used for monitoring purposes with details search results and a map of bore locations included in Appendix B. A summary of bore information is included in Table 3.

TABLE 3 SUMMARY OF REGISTERED BORES

Bore ID

Final Depth

(mBGL)

Standing water level

(mBGL)

Geology

GW201778

(United service station)

8.10 Dry

0.00 – 0.40 m: Fill (silty sand, light brown, medium grained).

0.40 – 2.20 m: SILTY CLAY (light brown / orange mottling, med-low plasticity, some fine angular gravel inclusions).

2.20 – 4.00 m: SANDSTONE (extremely weathered, light orange/brown mottling, fine grained sand, becoming denser below 3m).

4.00 – 8.10 m: SILTSTONE

GW201779

(United service station)

8.20 Dry

0.00 – 0.10 m: Asphalt

0.10 – 0.60 m: Fill (Gravelly Sand, light brown, medium-coarse sand, medium angular gravel).

0.60 – 0.90 m: SILTY CLAY (light brown/orange mottling, some grey throughout, medium-low density fines).

0.90 - 1.70 m: SANDSTONE (extremely weathered, light orange/brown, fine grained sand, medium plasticity).

1.70 – 3.20 m: SANDSTONE (extremely weathered, orange/brown mottling, fine grained sand).

3.20 – 8.20 m: SILTSTONE (light brown/grey, becoming denser below 6m).

GW201780

(United service station)

5.05 Dry

0.00 – 0.18 m: Concrete;

0.18 – 0.50 m: SILTY CLAY (light brown, trace sand).

0.50 – 1.20 m: SILTY CLAY (light orange / brown).

1.20 – 2.00 m: SILTY CLAY (tends to sandy clay, low moisture).

2.00 – 2.60 m: SILTY CLAY (brown / orange. Tends to weathered siltstone).

2.60 – 5.05 m: SANDSTONE (fine grained, moderately to slightly weathered, minor weathered siltstone bands).

GW201781

(United service station)

3.50 Dry

0.00 – 0.15 m: Concrete;

0.15 – 0.50 m: SILTY CLAY (brown).

0.50 – 1.10 m: SILTY CLAY (brown / orange).

1.10 – 1.20 m: SILTY CLAY (brown / orange mottled).

1.20 – 3.00 m: CLAYEY SILT (orange brown, tends to weathered siltstone).

3.00 – 14.00 m: SILTSTONE (grey, fresh & unweathered, minor mud bands.

Page 16: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 10

4.11 Meteorology Regional meteorological data has been sourced from the Bureau of Meteorology (2015) (www.bom.gov.au, verified 4 November 2015) Singleton STP weather station, approximately 5.5 km northwest from site. Mean maximum and minimum monthly temperatures and mean monthly rainfall recorded between 2002 and the present are presented in Table 4.

TABLE 4 AVERAGE MONTHLY CLIMATE DATA

Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec

Maximum Temperature (

oC)

31.7 30.2 28 24.5 21.3 18.2 17.7 19.9 23.4 26.3 28.8 29.8

Minimum Temperature (

oC)

17.7 17.5 14.9 11 6.8 5.7 4.3 4.1 7 9.9 14 15.8

Rainfall (mm) 59.2 98.2 63.5 63.2 30.6 65.8 26.1 31.7 37.8 44.7 84 70.3

Page 17: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 11

5 HISTORICAL REVIEW This section includes a detailed review of pertinent available information and documents which exist for the site. Information is summarised in the following subsections.

5.1 Review of Historical Aerial Photographs Details on the review of aerial photographs for the site are presented in Table 5.

TABLE 5 REVIEW OF AERIAL PHOTOGRAPHS

Date Photo Run

Details / Comments

11-Mar-2004 Google Earth

The majority of the study area is rural with the exception of the service station (Lot 21 in DP1014307), and the abattoir.

Associated with the abattoir (Lot 35 in DP1128981), large expanses are seemingly utilised for irrigation with treatment water, as paddocks to the south of the New England Highway appear quite fertile;

Property Lot 24 in DP1128978 appears to have miscellaneous tipping evident. It also appears to have been cleared in places;

The wider area appears to be predominantly rural-residential with the exception of the following features:

- small township of Belford approximately 5km east.

- Dochra Airfield approximately 2km west.

- Singleton Military Area approximately 7km southwest.

- Walkworth coal mine approximately 12km west.

13-Jan-2009 Google Earth

No change to site.

No change to area.

2-Oct-2009 Google Earth

Portion of site between service station and the main Great Northern

Railway line used as a construction and stockpiling compound to service new road and bridge construction works over rail line.

Old road bridge over the Great Northern Great Northern Railway line still evident. New bridge pylons under construction. New Golden Highway road connection to junction of New England Highway under construction.

Extensive earthworks visible north and south of the new Golden Highway bridge over the railway line, adjacent to and along the eastern side of the railway line.

11-Oct-2013 Google Earth

New Golden Highway bridge over the Great Northern Railway line seemingly complete.

Construction and stockpiling compound cleared of all buildings and storage, although footprints still visible.

No other changes to areas surrounding site.

Page 18: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 12

5.2 Council Planning Certificate The Council planning certificates issued under Section 149 [2] & [5] of the NSW Environmental Planning and Assessment Act 1979 (EP&A Act) were obtained for the service station property (Lot 21 in DP 1014307 - issued 30 October 2015) situated adjacent to the project area. These certificates state:

Lot not significantly contaminated within the meaning of that CLM Act at the date when the certificate was issued;

Lot not subject to a management order within the meaning of the CLM Act at the date when the certificate was issued;

Lot not the subject of an approved voluntary management proposal (VMP) with the meaning of that CLM Act when the certificate was issued;

Lot not the subject of an ongoing maintenance order within the meaning of that CLM Act when the certificate was issued; and

Lot not subject to a site audit statement within the meaning of the CLM Act if a copy of such a statement has been provided at any time to the local authority issuing the certificate.

The Section 149 (2) and (5) certificate is included for reference in Appendix C.

5.3 SafeWork NSW Dangerous Goods Search A search of hazardous chemical storage records held by SafeWork NSW was undertaken for the offsite service station property (Lot 1 in DP1014307). This property currently has records pertaining to licence 35/035078. Earliest available records pertain to design drawings for seven underground depots and one above-ground depot dated 1997 and approved on 14 June 2000. It would appear that the eight underground storage tanks originally constructed circa 2000 are still in commission, and that there have been no alterations or equipment replacement. At the time of the site inspection this service station offsite was operational. Details of product licensing and dates of associated storage information provided are not exhaustive or complete, and information returned from by NSW WorkCover represents available information only. Returned information is summarised in Table 6 and included in Appendix D.

Page 19: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 13

TABLE 6 OFFSITE SERVICE STATION STORAGE SUMMARY

Type Depot

Identifier Goods Licensed to Store Class

Licensed

Quantity (L)

Licence Period

UST 1 Petrol (UN 1203) 3 45,000 Feb-2003

Apr-2009

UST 2 Petrol (UN 1203) 3 30,000 Feb-2003

Apr-2009

UST 3 Petrol (UN 1203) 3 25,000 Feb-2003

Apr-2009

UST 4 Diesel (UN 00C1) C1 50,000 Feb-2003

Apr-2009

UST 5 Diesel (UN 00C1) C1 50,000 Feb-2003

Apr-2009

AGST 6 LPG (UN 1075) 2.1 7,500 Feb-2003

Apr-2009

UST 7 Petrol (UN 1203) 3 15,000 Feb-2003

Apr-2009

UST 8 Diesel (UN 00C1) C1 25,000 Feb-2003

Apr-2009

Notes: UST – Underground storage tank AGST – Above-ground storage tank LPG – Liquid petroleum gas

5.4 NSW EPA Contaminated Sites Register A search of the NSW EPA contaminated land public record database showed no notices or records for the lots within the study area. There is no record for any lots within the study area having ever been included on the following list of NSW EPA notices issued in accordance with CLM Act:

declaration of an investigation area (under Section 15 of the CLM Act);

declaration of a remediation site (under Section 21 of the CLM Act);

investigation order (under Section 17 of the CLM Act);

remediation order (under Section 23 of the CLM Act);

voluntary investigation proposal (under Section 19 of the CLM Act);

voluntary remediation proposal (under Section 26 of the CLM Act); and

site audit statement (SAS) with (under Section 53B of the CLM Act).

Page 20: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 14

5.5 Review of historical report pertaining to site The only environmental report available for review was the PEI report. This report identified the following current and historical potentially contaminating land uses within the site:

former timber treatment post and cattle rail yard (Lot 4 in DP621020) located on the northern side of the New England Highway; and

service station situated outside of the project area on the western side of the New England Highway (Lot 21 in DP1014307).

The report noted that facilities such as a cattle rail yard usually contained cattle dip or spray infrastructure which used organochlorine pesticides to treat parasites, with these facilities used in Australia up until the early 1960’s. Arsenic was also noted in the PEI report to have been used in sheep dips in Australia up until the late 1980’s (Meat and Livestock Australia, 2014) although no remaining physical evidence of this infrastructure was observed during the site inspection. A potential for residual organochlorine pesticide and arsenic contamination was identified as possibly existing in Lot 4 in DP 6121020 in the PEI report. The PEI report noted that a search of acid sulfate soil risk map (Naylor, 1995) was undertaken, which did not identify risk of acid sulfate soils at any level within their subject study area.

6 SITE OBSERVATIONS & POTENTIAL FOR CONTAMINATION

A site walkover was undertaken by Environmental Earth Sciences on 21 January 2016. Access was granted and walkover undertaken upon the following works corridor areas and adjacent lots:

Lot 24 in DP1128978 (former works compound);

Lot 23 in DP1128978;

Lot 4 in DP621020 (cattle yard);

Lot 35 in DP1128981 (abattoir land); and

Lot 34 in DP1128981;

Rest stop / picnic area. Limited inspection of the following lots was able to be undertaken from the road corridor:

Lot 1 in DP653039; and

Lot 22 in DP1014307. Refer to Figure 2 for layout of lots comprising the site. Details on site features relating to each lot are included in Table 7. Photographic plates highlighting indicative features of the site inspection are included in Appendix E, with reference to the individual plates made herein.

Page 21: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 15

TABLE 7 SITE INSPECTION SUMMARY

Lot Features

Lot 4 in DP621020

(inspected via walkover)

Agricultural land to the north of the New England Highway road corridor. Former cattle yard was located adjacent to the highway. Features included:

Entirely covered with vegetation, predominantly grass. Riparian vegetation noted in the vicinity of creek (eastern portion of lot); [Plates 1 - 3]

Cattle yard holding pen inspected with no evidence of tick dip(s) noted;

Animal manure noted throughout property;

Two small stockpiles of organic matter mixed with sandy clay noted (central portion of lot);

Stormwater culvert under New England Highway noted (SW portion of lot). Pooled water beneath was stagnant and discoloured; [Plate 4]

No visual or olfactory indications of contamination noted;

Limited surface inspection for the presence of possible ACM did not report any suspicious fragments.

Lot 24 in DP1128978

(inspected via walkover)

Location of former works compound for construction of new Golden Highway road bridge over the Great Northern Railway line (circa 2010 – 2013). Features included:

Surfaces in places covered with blue metal / road base seemingly remnant from use of the site as a works compound; [Plates 5, 8, 11]

Non-putrescible waste spread sporadically across the lot, including chairs, metal objects, stockpiles of aggregate. Of note are two stockpiles of soil / fill material approximately 300 – 400 cubic metres (m

3) each; [Plates 7, 12]

Small area (3 x 3 metres) of black asphalt hardstand noted at the entry from Golden Highway; [Plate 13]

Vegetation consists of predominantly grass and weeds with small pockets of riparian vegetation. Northern portion contains a farm dam, with down-gradient vegetation showing signs of stress (discoloured leaves);

Limited surface inspection for the presence of possible Asbestos Containing Materials (ACM) did not report any suspicious fragments.

Lot 35 in DP1128981

(inspected via walkover)

Property operating an abattoir with associated water effluent treatment. Abattoir itself, treatment ponds and filter bed areas are outside of the proposed works area. Study area is strip of land immediately to the south of the New England Highway road corridor: Features include:

Potential scalding noted in the central portion of lot adjacent to the New England Highway road corridor. Vegetation upon this area shows signs of stress (dead trees noted); [Plate 14]

Treatment pond in the western portion of lot spills into natural drainage channel that flows northward through a culvert under the New England Highway; [Plate 15]

No visual or olfactory indications of contamination noted;

Limited surface inspection for the presence of possible ACM did not report any suspicious fragments.

Lot 23 in DP1128978

(inspected via walkover)

Cleared area. Features include:

Lot almost entire cleared of trees and covered in grass [Plate 22];

Possible in-filled farm dam noted in southwest portion of lot;

No visual or olfactory indications of contamination noted;

Limited surface inspection for the presence of possible ACM did not report any suspicious fragments.

Lot 34 in DP1128981

(inspected via

Area adjacent to the south of the Golden Highway road corridor. Majority of lot formerly situated in the old Golden Highway road corridor prior to construction of the

Page 22: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 16

Lot Features

walkover) new bridge and approach. Features include:

Predominantly covered with trees as a result of rehabilitation after construction works;

No visual or olfactory indications of contamination noted;

Limited surface inspection for the presence of possible ACM did not report any suspicious fragments.

Lot 1 in DP653039

(inspected from roadway)

Cleared area seemingly used for cattle grazing [Plate 19]. Features include:

Lot almost entire cleared of trees;

Three small farm dams situated in close proximity to the highway corridor;

No visual or olfactory indications of contamination noted.

Lot 22 in DP1014307

(inspected from roadway)

Densely forested area between former works compound (Lot 24 in DP1128798) and United Service Station property [Plate 20]:

No visual indications of contamination noted from the edge of the lot;

Lot heavily forested;

Three small farm dams situated in close proximity to the highway corridor.

Lots 1-2 in DP246454

Small lots adjacent to New England Highway road corridor, north of abattoir land:

Partly forested

Lot 3 contains a dirt track that links the highway at two locations.

Lot 2 has a depression and a culvert that allows water to flow north under New England Highway toward Lot 4 in DP621020.

No visual or olfactory indications of contamination noted.

Rest stop / picnic area

(inspected via walkover)

Area used for car / truck parking off the Golden Highway at junction of New England Highway [Plate 17 and 18]. Features include:

Toilet facilities provided (long drop);

Picnic table shelter;

rubbish bins provided;

No visual or olfactory indications of contamination noted;

Limited surface inspection for the presence of possible ACM did not report any suspicious fragments.

Page 23: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 17

7 CONCEPTUAL SITE MODEL A conceptual site model (CSM) of the site can be formed by considering the likelihood of pathways between any source(s) of contamination onsite and potential receptors. An initial CSM for the project area had been undertaken for in the PEI report, which identified certain lots within the project area suspected to be potentially contaminated from historical activities. Re-evaluation of the CSM in this assessment was undertaken through review of available desktop information and site inspection A summary on the source-pathway-receptor evaluation is provided in Table 8.

Page 24: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 18

TABLE 8 SOURCE PATHWAY RECEPTOR EVALUATION

Source Pathway Receptor Risk Notes / Proposed Control

UPON PROJECT BOUNDARY

Potential soil contamination from former cattle holding pen & timber treatment yard

Lot 4 in DP621020

Ingestion / direct contact

Human

(Owner & visitors) LOW

Potential industrial contamination considered negligible based upon inspection.

No evidence of cattle tick dips noted during Environmental Earth Sciences site inspection (21 January 2016), hence this would present a low risk. If during construction evidence is discovered it should be managed appropriately as an unexpected find.

Human

(Construction workers) LOW

Potential industrial contamination considered negligible. However potential organic impact to soil from cattle pasture may exist, but is considered to present a low risk.

Workers operating in contact with subsurface groundwater should consider wearing appropriate protective clothing and using PPE.

Inhalation

particulates / dust

Human

(Owner & visitors) LOW

Although contamination risk is considered to be low, it is recommended that site users do not agitate soils such that dust is generated.

Human

(Construction workers) LOW Workers coming into contact with soil should consider wearing appropriate PPE.

Contaminant leaching through

soil profile

Ecology

(Groundwater) LOW Contamination likely to be low based upon the non-industrial land use at the lot.

OFF PROJECT BOUNDARY

Potential soil contamination from former works compound

Lot 24 in DP1128978

Ingestion / dermal contact

Human

(Owner & visitors) LOW

Stockpiles noted on this offsite property present a low risk to works on the proposed works corridor.

As this area is not involved in the proposed works corridor, no further management of potential contamination is warranted.

Human

(Construction workers) LOW

As this area is not involved in the proposed works corridor, no further management of potential contamination is warranted.

Inhalation

particulates / dust

Human

(Owner & visitors) LOW

As this area is not involved in the proposed works corridor, no further management of potential contamination is warranted.

Human

(Construction workers) LOW

As this area is not involved in the proposed works corridor, no further management of potential contamination is warranted.

Contaminant leaching through

soil profile

Ecology

(Groundwater) LOW Likelihood of any contamination migrating onto proposed works corridor is considered low.

Page 25: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 19

Source Pathway Receptor Risk Notes / Proposed Control

Potential soil contamination from abattoir land

Lot 35 in DP1128981

Ingestion / direct contact

Onsite Human

(Owner & visitors) LOW

Potential industrial contamination considered negligible.

As this area is not involved in the proposed works corridor, no further management of potential contamination is warranted.

Onsite Human

(Construction workers) LOW

As this area is not involved in the proposed works corridor, no further management of potential contamination is warranted.

Inhalation

particulates / dust

Onsite Human

(Owner & visitors) LOW

As this area is not involved in the proposed works corridor, no further management of potential contamination is warranted.

Onsite Human

(Construction workers) LOW

As this area is not involved in the proposed works corridor, no further management of potential contamination is warranted.

Contaminant leaching through

soil profile

Ecology

(Groundwater) LOW

Contamination likely to be low based upon the site seemingly being used for cattle grazing / holding.

Likelihood of any contamination migrating onto proposed works corridor is considered low.

Potential soil or groundwater contamination from offsite service station

Lot 21 in DP1014307

Ingestion / direct contact

Onsite Human

(Authorised site users) LOW

If fuel system is managed appropriately under the NSW EPA (2014) – Protection of the Environment (Underground Petroleum Storage Systems) Regulation (UPSS Regulation), risk of migration of potential contamination onto works corridor considered low.

Any impact noted in the works corridor from this offsite source should be managed under an unexpected findings protocol (UFP).

Inhalation

particulates / dust

Onsite Human

(Authorised site users) LOW

If fuel system is managed appropriately under the UPSS Regulation, risk of migration of potential contamination onto works corridor considered low.

Any impact noted in the works corridor from this offsite source should be managed under a UFP.

Vapour

(ambient air)

Onsite Human

(Owner & visitors) LOW

If fuel system is managed appropriately under the UPSS Regulation, risk of migration of potential contamination onto works corridor considered low.

Any impact noted in the works corridor from this offsite source should be managed under a UFP.

Notes: 1. HIGH RISK - desktop review and site inspection have identified potentially contaminating site activities and intrusive works must be carried out to confirm the presence or absence of

contamination

2. MODERATE RISK - desktop review and site inspection cannot rule out the presence of potentially contaminating site activities without undertaking recommended intrusive works MODERATE 1 - potential for contamination is limited in either likelihood or extent and the presence or absence of contamination is expected to be resolved by limited targeted sampling MODERATE 2 - potential for contamination is greater or more extensive than Moderate 1 and will require a detailed site investigation to confirm the presence or absence of contamination

3. LOW RISK - desktop review and site inspection have not identified any potentially contaminating site activities

Page 26: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 20

8 CONCLUSION Roads and Maritime Services (Roads and Maritime) propose to upgrade the New England Highway between Belford and the Golden Highway. The road upgrade would improve traffic flow, travel times and safety for motorists along a busy section of the New England Highway. The proposal would provide a divided road with two travel lanes in each direction between Belford and the Golden Highway and a flyover for vehicles turning right from the Golden Highway towards Maitland and Newcastle. The project is located within the Singleton local government area (LGA) and the Hunter region of the Roads and Maritime network. Key features of the project include:

Widening the New England Highway for around 3.2 km to provide a divided road with two travel lanes in each direction between Belford and the Golden Highway

Replacing the existing right turn movement from the Golden Highway to the New England Highway with a right turn flyover

Removal of the Whittingham rest area adjacent to the New England Highway and Golden Highway intersection.

Environmental Earth Sciences was commissioned by Arup to undertake this Stage 1 PSI for the above-mentioned works. Works included a review of the PEI report, obtaining relevant desktop information on site setting, and undertaking an inspection of the following two locations reported in the PEI as being potential sources of contamination:

cattle holding pen and possible tick dip within the project area (Lot 4 in DP621020); and

service station adjacent to project area (Lot 21 in DP1014307). The inspection was undertaken by Environmental Earth Sciences on 21 January 2016 and noted the study area to consist of various rural lots and highway corridors. During the inspection the following offsite land uses adjacent to the project area were also noted as posing potential sources of contamination:

former works compound (Lot 24 in DP1128978) adjacent to project area that was involved in the upgrade of the Golden Highway vehicular bridge over the Great Northern Railway line between 2009 – 2013; and

operational abattoir and process water treatment/irrigation area to the south of the project area (Lot 35 in DP1128981).

Based on the findings of the desktop assessment and site inspection, the CSM for potential contamination risk was re-evaluated. In summary:

No potential sources of contamination or observations of contamination impact were noted in the project area which would pose unacceptable risk to human health or the environment. Hence an overall low risk posed by contamination;

Potential risks posed from current operation of the abattoir /irrigation paddocks adjacent to the project area were evaluated as posing a low risk;

Potential risk posed by operation of the service station adjacent to the project area were evaluated as posing a low risk pending that operations comply with the UPSS regulations;

Page 27: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 21

Potential risks posed from residual contamination in the former bridge construction works compound adjacent to the project area were evaluated as posing a low risk;

Based on the above no further Stage 2 Detailed Site Investigation is recommended to be undertaken in the project area. General management recommendations are provided in Section 9.

9 RECOMMENDATIONS

9.1 General construction management Prior to commencement of proposed construction works it is recommended that a Soil Management Plan (SMP) be prepared in accordance with QA Specification G38 and implemented as part of any overarching Construction Environmental Management Plan (CEMP). This plan should include (but not limit) procedures for:

Identification of all reasonably foreseeable risks relating to subsurface impacts and pollution associated with construction of the proposal and description on how these risks would be managed and minimised.

Stockpile generation and management in accordance with RTA Stockpile Site Management Guideline. Batters would be designed and constructed to minimise risk or exposure, instability and erosion, and to support long-term, on-going best practice management, in accordance with the Roads and Maritime Guideline for Batter Stabilisation Using Vegetation.

Environmental controls during earthworks, including management / controls for erosion, sedimentation, dust generation and water quality safeguards.

Identification of, and associated procedures / controls for lining / bunding the following areas located within 50 m of a shallow groundwater source:

o Sediment basins.

o Stockpiles.

o Wash-downs.

o Batch plants;

o Refuelling sites; and

o Chemical storage sites;

Managing pollution risks associated with spillage or soil contamination on the site and adjoining areas, and monitoring during and post-construction;

Onsite / off-site soil material tracking of soil / spoil.

Appropriate classification of soil / spoil that requires disposal to waste facility. This is to be undertaken in accordance with the NSW EPA (2014) – Waste Classification Guidelines.

Appropriate certification of Virgin Excavated Natural Material (VENM) or Excavated Natural Material in accordance with the NSW Protection of the Environment Operations Act 1997 (POEO Act).

General PPE controls for construction workers;

Page 28: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 22

Consistent with any specific requirements of an approved Erosion and Sedimentation Control Plan (ESCP) and the SMP, control measures should be implemented to minimise risks associated with erosion and sedimentation and entry of materials into the creek / drainage lines. This may include, but not necessarily be limited to:

o Sediment management devices, such as sediment fencing, straw bales or sand bags;

o Installation of measures at work entry and exit points to minimise movement of material onto adjoining roads, such as rumble grids or wheel wash bays

o Appropriate location and storage of construction materials, fuels and chemicals, including bunding where appropriate.

Unexpected Findings Protocol (UFP) procedure for managing instances where gross contamination and/or hazardous materials are encountered, with appropriate consideration of WH&S controls for mitigating risk to construction workers.

Pre-construction preliminary salinity field investigation is to be considered with locations, profile descriptions, soil tests and laboratory analyses planned with reference to the Department of Land and Water Conservation (2002) – Site Investigations for Urban Salinity (DLWC, 2002).

Rehabilitation of disturbed areas would be carried out progressively as construction stages are completed, and in accordance with:

o Landcom's Managing Urban Stormwater: Soils and Construction series;

o RTA Landscape Guideline;

o Roads and Maritime Guideline for Batter Stabilisation Using Vegetation.

9.2 Spoil and fill management A Spoil and Fill Management Plan (SFMP) is to be prepared and implemented as part of any overarching CEMP. The SFMP should identify:

Locations of any spoil / stockpiles;

Sources of imported fill, and methods to re-use or dispose of excess or unsuitable spoil material including estimated volumes and disposal sites

9.3 Specific contamination mitigation measures If contaminated areas are encountered during construction, appropriate control measures are to be implemented to manage the immediate risks of contamination, such as:

Diversion of surface runoff;

Capture of any contaminated runoff; or

Temporary capping. All other work that may impact on the contaminated area should cease until the nature of the contamination has been confirmed and any necessary site-specific controls or further actions are identified in consultation with the Environment Manager and/or EPA.

Page 29: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 23

9.4 Spill management A site specific emergency spill plan is to be developed and implemented. The plan should be prepared in accordance with the Roads and Maritime Code of Practice for Water Management and/or relevant EPA guidelines. The plan should include measures to be implemented in the event of a spill, including:

initial response and containment;

notification of emergency services and relevant authorities (including Roads and Maritime and EPA officers).

Procedures for managing pollution risks associated with spillage or soil contamination on the site and adjoining areas.

9.5 Dewatering management Where groundwater is intercepted during construction works, such as around the flyover, management measures to minimise potential adverse impacts are to be implemented in accordance with the RTA Technical Guideline: Environmental management of construction site dewatering. These may include, but not necessarily be limited to:

Options to collect and store groundwater to enable recharge of the water table (such as via grassed swales);

Where recharge is not appropriate or feasible, discharging groundwater to the surface water drainage system following;

Appropriate treatment to ensure discharged water is of sufficient quality;

Prior to any dewatering activities being carried out, an approval must first be obtained in accordance with Section 92 of the Water Management Act.

10 LIMITATIONS This report has been prepared by Environmental Earth Sciences NSW ABN 109 404 006 in response to and subject to the following limitations:

The specific instructions received from Arup Pty Ltd;

The specific scope of works set out in PO115146 issued by Environmental Earth Sciences NSW;

May not be relied upon by any third party not named in this report for any purpose except with the prior written consent of Environmental Earth Sciences NSW (which consent may or may not be given at the discretion of Environmental Earth Sciences NSW);

This report comprises the formal report, documentation sections, tables, figures and appendices as referred to in the index to this report. This report has been issued for information purposes to support an REF and may be summarised within the overarching REF document to which the report is appended. The appendix within the REF must not be copied in part without all the material included for any reason;

The report only relates to the site referred to in the scope of works being located at various lots and portions of lots located at the junction of the New England Highway and Golden Highway, Whittingham NSW (the “site”);

Page 30: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7 24

The report relates to the site as at the date of the report as conditions may change thereafter due to natural processes and/or site activities;

No warranty or guarantee is made in regard to any other use than as specified in the scope of works and only applies to the depth tested and reported in this report;

Fill, soil, groundwater and rock to the depth tested on the site may be fit for the use specified in this report. Unless it is expressly stated in this report, the fill, soil and/or rock may not be suitable for classification as clean fill if deposited off site; and

Our General Limitations set out at the back of the body of this report.

11 REFERENCES

Rasmus P.L., Rose D.M. and Rose G., (1969) - Singleton 1:250 000 Geological Sheet SI/56-01, 1st edition, Geological Survey of New South Wales, Sydney

Kovac, M and Lawrie, J. W., (1991) - Soil landscapes of the Singleton 1:250,000 sheet, Soil Conservation Service of New South Wales, Sydney

National Environment Protection Council (NEPC) 2013, National Environment Protection (Assessment of Site Contamination) Amendment Measure 2013

National Uniform Drillers Licensing Committee (NUDLC) (2012) - Minimum Construction Requirements for Water Bores In Australia (3rd Edition). Australian Government National Water commission

Naylor, S. D., (1995) - Acid Sulfate Soil Risk of the Singleton Map Sheet. Sydney: Department of Land and Water Conservation.

NSW Department of Environment Climate Change and Water (DECCW) (2009) Guidelines for Implementing the Protection of the Environment Operations (Underground Petroleum Storage Systems) Regulation 2008

NSW Office of Environment & Heritage (2011) Contaminated sites: Guidelines for consultants reporting on contaminated sites

NSW Department of Land and Water Conservation (2002) – Site Investigations for Urban Salinity

NSW EPA (2014) – Waste Classification Guidelines Part 1: Classifying Waste

.

Page 31: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Limitations 6 April 2009 Page 1 of 1

ENVIRONMENTAL EARTH SCIENCES GENERAL LIMITATIONS Scope of services The work presented in this report is Environmental Earth Sciences response to the specific scope of works requested by, planned with and approved by the client. It cannot be relied on by any other third party for any purpose except with our prior written consent. Client may distribute this report to other parties and in doing so warrants that the report is suitable for the purpose it was intended for. However, any party wishing to rely on this report should contact us to determine the suitability of this report for their specific purpose.

Separation of information and data This formal report in its entirety will be appended within the overarching REF and will comprise the report body, tables, figures and appendices as referred to in the index of this report. It may be summarised only within the overarching REF document prepared for Roads and Maritime, but the appended report must not be copied in part without all the material included for any reason.

Subsurface conditions change Understanding an environmental study will reduce exposure to the risk of the presence of contaminated soil and or groundwater. However, contaminants may be present in areas that were not investigated, or may migrate to other areas. Analysis cannot cover every type of contaminant that could possibly be present. When combined with field observations, field measurements and professional judgement, this approach increases the probability of identifying contaminated soil and or groundwater. Under no circumstances can it be considered that these findings represent the actual condition of the site at all points. Environmental studies identify actual sub-surface conditions only at those points where samples are taken, when they are taken. Actual conditions between sampling locations differ from those inferred because no professional, no matter how qualified, and no sub-surface exploration program, no matter how comprehensive, can reveal what is hidden below the ground surface. The actual interface between materials may be far more gradual or abrupt than an assessment indicates. Actual conditions in areas not sampled may differ from that predicted. Nothing can be done to prevent the unanticipated. However, steps can be taken to help minimize the impact. For this reason, site owners should retain our services.

Problems with interpretation by others Advice and interpretation is provided on the basis that subsequent work will be undertaken by Environmental Earth Sciences NSW. This will identify variances, maintain consistency in how data is interpreted, conduct additional tests that may be necessary and recommend solutions to problems encountered on site. Other parties may misinterpret our work and we cannot be responsible for how the information in this report is used. If further data is collected or comes to light we reserve the right to alter their conclusions.

Obtain regulatory approval The investigation and remediation of contaminated sites is a field in which legislation and interpretation of legislation is changing rapidly. Our interpretation of the investigation findings should not be taken to be that of any other party. When approval from a statutory authority is required for a project, that approval should be directly sought by the client.

Limit of liability This study has been carried out to a particular scope of works at a specified site and should not be used for any other purpose. This report is provided on the condition that Environmental Earth Sciences NSW disclaims all liability to any person or entity other than the client in respect of anything done or omitted to be done and of the consequence of anything done or omitted to be done by any such person in reliance, whether in whole or in part, on the contents of this report. Furthermore, Environmental Earth Sciences NSW disclaims all liability in respect of anything done or omitted to be done and of the consequence of anything done or omitted to be done by the client, or any such person in reliance, whether in whole or any part of the contents of this report of all matters not stated in the brief outlined in Environmental Earth Sciences NSW’s proposal number and according to Environmental Earth Sciences general terms and conditions and special terms and conditions for contaminated sites. To the maximum extent permitted by law, we exclude all liability of whatever nature, whether in contract, tort or otherwise, for the acts, omissions or default, whether negligent or otherwise for any loss or damage whatsoever that may arise in any way in connection with the supply of services. Under circumstances where liability cannot be excluded, such liability is limited to the value of the purchased service.

Page 32: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7

APPENDIX A SOIL REPORTS

Page 33: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 34: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

NSW SOIL LAND INFORMATION SYSTEM Soil profile report

SITE DETAILS:

Site Location: Profile 1

Profile Details: BELFORD-SINGLETON ABATTOIR Survey (1000497), Profile 1, collected from a pit by Linda Henderson on April 07, 1993

Map Reference: MGA Grid Reference: Zone 56, Easting 334405, Northing 6386640 CESSNOCK (9132) 1:100,000 sheet

Physiography: plain in low hills under grassland/herbland on not identified lithology with nil rock outcrop; local relief low (30-90 m), run-on is high, run-off is high

Vegetation/Land Use:

grassland/herbland, with limited clearing at the site, used for volun./native pasture, with volun./native pasture in the general area

Surface Condition: expected to be hardsetting when dry, ground cover is 100%

Erosion/Land Degradation:

strongly evident

Soil Hydrology: no free water

Soil Type: Subnatric Brown Sodosol (ASC), Soloth (Solod)(GSG), Dy3.41(PPF)

Profile Field Notes:

SOIL DESCRIPTION:

Layer 1

00.00 - 00.04 m A1 Horizon

Texture: silty clay loam

Colour: dark yellowish brown (dark brown) (10YR 3/4) with no recorded mottles

Structure: weak pedality (crumb, 2 - 5 mm, fabric is rough-faced peds),

Coarse Fragments:

Pans:

Segregations:

Roots: many (25-100/10x10cm) (Root size <1 mm),

Page 35: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, non-sticky, disruptive test result was very weak force, shearing test result was crumbly,

Erodibility Tests:

Field chemical tests: Field pH is 6 (Raupach),

Sample taken: disturbed

Layer Notes:

Lower Boundary: smooth clear (20-50 mm) boundary to ...

Layer 2

00.04 - 00.15 m A2 Horizon

Texture: fine sandy clay loam

Colour: strong brown (brown) (7.5YR 4/6) with 20% - 50% distinct weathered orange mottles

Structure: weak pedality (sub-angular blocky, 50 - 100 mm, fabric is rough-faced peds),

Coarse Fragments:

Pans:

Segregations:

Roots: common (10-25/10x10cm) (Root size <1 mm), common (10-25/10x10cm) (Root size 1-2 mm),

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, non-sticky, disruptive test result was very weak force, shearing test result was crumbly,

Erodibility Tests:

Field chemical tests: Field pH is 6 (Raupach),

Sample taken: disturbed

Page 36: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Layer Notes:

Lower Boundary: irregular clear (20-50 mm) boundary to ...

Layer 3

00.15 - 01.10 m B21 Horizon

Texture: light medium clay

Colour: brown (dull orange) (7.5YR 5/4) with 20% - 50% prominent weathered orange mottles

Structure: moderate pedality (sub-angular blocky, 50 - 100 mm, fabric is rough-faced peds),

Coarse Fragments:

Pans:

Segregations:

Roots: common (10-25/10x10cm) (Root size <1 mm), common (10-25/10x10cm) (Root size 1-2 mm),

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: slightly plastic, moderately sticky, disruptive test result was very weak force, shearing test result was crumbly,

Erodibility Tests:

Field chemical tests: Field pH is 6 (Raupach),

Sample taken: disturbed

Layer Notes:

Lower Boundary: smooth diffuse (>100 mm) boundary to ...

Layer 4

01.10 - 02.00 m B22 Horizon

Texture: medium clay

Colour: brownish yellow (bright yellowish brown) (10YR 6/6) with 20% - 50% distinct weathered yellow mottles

Structure: moderate pedality (sub-angular blocky, 50 - 100 mm, fabric is rough-faced peds),

Page 37: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Coarse Fragments: very few (< 2%), other, dispersed, reoriented, weakly weathered, rounded, coarse gravel (20-60 mm),

Pans:

Segregations:

Roots: few (1-10/10x10cm) (Root size <1 mm),

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: moderately plastic, very sticky, disruptive test result was very weak force, shearing test result was crumbly,

Erodibility Tests:

Field chemical tests: Field pH is 8 (Raupach),

Sample taken: disturbed

Layer Notes: Layer continues.

Lower Boundary: boundary to ...

LABORATORY TESTS:

No lab data available

For information on laboratory test data and units of measure, please see Soil survey standard test methods

Soil profile report To contact us email:[email protected]

Generated: Wed Nov 04 04:39 2015

© Office of Environment and Heritage (OEH)

Page 38: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

NSW SOIL LAND INFORMATION SYSTEM Soil profile report

SITE DETAILS:

Site Location: PIT 2

Profile Details: BELFORD-SINGLETON ABATTOIR Survey (1000497), Profile 2, collected from a pit by Linda Henderson on April 07, 1993

Map Reference: MGA Grid Reference: Zone 56, Easting 334405, Northing 6386490 CESSNOCK (9132) 1:100,000 sheet

Physiography: hillslope in low hills under grassland/herbland on siltstone/mudstone lithology with nil rock outcrop; Slope 2% (estimated), elevation 70 m, aspect north east, run-on is moderate, run-off is high

Vegetation/Land Use:

grassland/herbland, with extensive clearing at the site, used for volun./native pasture, with volun./native pasture in the general area

Surface Condition: expected to be hardsetting when dry, ground cover is 100%

Erosion/Land Degradation:

no salting evident

Soil Hydrology: profile is slowly permeable and mod. well drained, no free water

Soil Type: Subnatric Brown Sodosol (ASC), Non-calcic Brown Soil(GSG), Db1.22(PPF)

Profile Field Notes:

SOIL DESCRIPTION:

Layer 1

00.00 - 00.02 m A1 Horizon

Texture: fine sandy loam

Colour: dark brown (7.5YR 3/3) with no recorded mottles

Structure: weak pedality (crumb, 5 - 10 mm, fabric is rough-faced peds),

Coarse Fragments:

Pans:

Segregations:

Roots: many (25-100/10x10cm) (Root size <1 mm),

Page 39: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, disruptive test result was very weak force, shearing test result was crumbly,

Erodibility Tests:

Field chemical tests: Field pH is 6 (Raupach),

Sample taken: disturbed

Layer Notes:

Lower Boundary: smooth abrupt (5-20 mm) boundary to ...

Layer 2

00.02 - 00.20 m A2 Horizon

Texture: fine sandy clay loam

Colour: brown (7.5YR 4/3) with < 2% faint weathered orange mottles

Structure: weak pedality (sub-angular blocky, 50 - 100 mm, fabric is rough-faced peds),

Coarse Fragments:

Pans:

Segregations:

Roots: common (10-25/10x10cm) (Root size <1 mm),

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, disruptive test result was very weak force, shearing test result was brittle,

Erodibility Tests:

Field chemical tests: Field pH is 6 (Raupach),

Sample taken: disturbed

Layer Notes:

Page 40: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Lower Boundary: smooth sharp (<5 mm) boundary to ...

Layer 3

00.20 - 00.65 m B21 Horizon

Texture: light medium clay

Colour: brown (7.5YR 4/4) with 2% - 10% distinct weathered orange mottles

Structure: (angular blocky, 10 - 20 mm, also prismatic, 50 - 100 mm, fabric is smooth-faced peds),

Coarse Fragments: few (2-10%), charcoal, dispersed, reoriented, non-weathered, angular, fine gravel (2-6 mm),

Pans:

Segregations: few (2% - 10%), strong, fine (< 2 mm), manganiferous, nodules,

Roots: common (10-25/10x10cm) (Root size <1 mm), common (10-25/10x10cm) (Root size 1-2 mm),

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, moderately plastic, moderately sticky, disruptive test result was moderately firm force, shearing test result was crumbly,

Erodibility Tests:

Field chemical tests: Field pH is 6.5 (Raupach),

Sample taken: disturbed

Layer Notes:

Lower Boundary: smooth gradual (50-100 mm) boundary to ...

Layer 4

00.65 - 01.00 m B22 Horizon

Texture: light medium clay

Colour: (dark reddish brown) (5YR 3/6) with 20% - 50% prominent weathered red mottles, and 20% - 50% prominent weathered grey subdominant mottles

Structure: (angular blocky, 10 - 20 mm, also prismatic, 50 - 100

Page 41: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

mm, fabric is smooth-faced peds),

Coarse Fragments:

Pans:

Segregations:

Roots: few (1-10/10x10cm) (Root size <1 mm), few (1-10/10x10cm) (Root size 1-2 mm),

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, moderately plastic, moderately sticky, disruptive test result was moderately firm force, shearing test result was crumbly,

Erodibility Tests:

Field chemical tests: Field pH is 7 (Raupach),

Sample taken: disturbed

Layer Notes:

Lower Boundary: smooth gradual (50-100 mm) boundary to ...

Layer 5

01.00 - 02.00 m C Horizon

Texture: silty clay

Colour: light brown (dull orange) (7.5YR 6/4) with 20% - 50% prominent weathered red mottles, and 20% - 50% prominent weathered grey subdominant mottles

Structure: massive (fabric is earthy),

Coarse Fragments:

Pans:

Segregations:

Roots:

Soil fauna: Activity is nil

Page 42: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry,

Erodibility Tests:

Field chemical tests: Field pH is 6.5 (Raupach),

Sample taken:

Layer Notes:

Lower Boundary: boundary to ...

LABORATORY TESTS:

No lab data available

For information on laboratory test data and units of measure, please see Soil survey standard test methods

Soil profile report To contact us email:[email protected]

Generated: Wed Nov 04 04:42 2015

© Office of Environment and Heritage (OEH)

Page 43: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

NSW SOIL LAND INFORMATION SYSTEM Soil profile report

SITE DETAILS:

Site Location: PIT 3

Profile Details: BELFORD-SINGLETON ABATTOIR Survey (1000497), Profile 3, collected from a pit by Linda Henderson on April 07, 1993

Map Reference: MGA Grid Reference: Zone 56, Easting 334905, Northing 6386140 CESSNOCK (9132) 1:100,000 sheet

Physiography: hillcrest in low hills under woodland grass u'storey on siltstone/mudstone lithology with nil rock outcrop; elevation 80 m, run-on is none, run-off is low

Vegetation/Land Use:

woodland grass u'storey, with extensive clearing at the site

Surface Condition: expected to be hardsetting when dry, ground cover is 100%

Erosion/Land Degradation:

no salting evident

Soil Hydrology: profile is moderately permeable and well drained, no free water

Soil Type: Bleached Mesotrophic Red Kandosol (ASC), Soloth (Solod)(GSG), Dr2.41(PPF)

Profile Field Notes:

SOIL DESCRIPTION:

Layer 1

00.00 - 00.03 m A1 Horizon

Texture: fine sandy clay loam

Colour: dark brown (brownish black) (7.5YR 3/2) with no recorded mottles

Structure: moderate pedality (sub-angular blocky, 5 - 10 mm, also crumb, 2 - 5 mm, fabric is rough-faced peds),

Coarse Fragments:

Pans:

Segregations:

Roots: abundant (>100/10x10cm) (Root size <1 mm), many (25-100/10x10cm) (Root size 1-2 mm),

Page 44: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, disruptive test result was very weak force, shearing test result was crumbly,

Erodibility Tests:

Field chemical tests: Field pH is 5.5 (Raupach),

Sample taken: disturbed

Layer Notes:

Lower Boundary: smooth clear (20-50 mm) boundary to ...

Layer 2

00.03 - 00.15 m A2 Horizon

Texture: silty clay loam

Colour: brown (7.5YR 4/3) with 2% - 10% faint weathered orange mottles

Structure: weak pedality (sub-angular blocky, 50 - 100 mm, fabric is rough-faced peds),

Coarse Fragments:

Pans:

Segregations:

Roots: many (25-100/10x10cm) (Root size <1 mm),

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, disruptive test result was very weak force, shearing test result was brittle,

Erodibility Tests:

Field chemical tests: Field pH is 6 (Raupach),

Sample taken: disturbed

Layer Notes:

Page 45: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Lower Boundary: wavy sharp (<5 mm) boundary to ...

Layer 3

00.15 - 00.45 m B21 Horizon

Texture: light medium clay

Colour: yellowish red (reddish brown) (5YR 4/6) with 2% - 10% faint weathered orange mottles, and 2% - 10% faint weathered grey subdominant mottles

Structure: strong pedality (angular blocky, 20 - 50 mm, also prismatic, 100 - 200 mm, fabric is smooth-faced peds),

Coarse Fragments:

Pans:

Segregations:

Roots: many (25-100/10x10cm) (Root size <1 mm),

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, moderately plastic, moderately sticky, disruptive test result was very firm force,

Erodibility Tests:

Field chemical tests: Field pH is 6 (Raupach),

Sample taken: disturbed

Layer Notes:

Lower Boundary: smooth gradual (50-100 mm) boundary to ...

Layer 4

00.45 - 00.75 m B22 Horizon

Texture: medium clay

Colour: strong brown (bright brown) (7.5YR 5/6) with 10% - 20% distinct weathered grey mottles, and 10% - 20% distinct weathered red subdominant mottles

Structure: strong pedality (angular blocky, 20 - 50 mm, also prismatic, 100 - 200 mm, fabric is smooth-faced peds),

Page 46: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Coarse Fragments:

Pans:

Segregations:

Roots:

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, moderately plastic, moderately sticky, disruptive test result was very firm force,

Erodibility Tests:

Field chemical tests: Field pH is 5 (Raupach),

Sample taken: disturbed

Layer Notes:

Lower Boundary: smooth gradual (50-100 mm) boundary to ...

Layer 5

00.75 - 02.30 m C Horizon

Texture: light medium clay

Colour: reddish yellow (orange) (7.5YR 6/6) with no recorded mottles

Structure: massive (fabric is earthy),

Coarse Fragments:

Pans:

Segregations:

Roots:

Soil fauna: Activity is nil

Cracks/Macropores: Cracks are nil, macropores are nil

Moisture/Consistence: dry, moderately plastic, moderately sticky, disruptive test result was very firm force,

Page 47: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Erodibility Tests:

Field chemical tests: Field pH is 5 (Raupach),

Sample taken: disturbed

Layer Notes: Layer continues.

Lower Boundary: boundary to ...

LABORATORY TESTS:

No lab data available

For information on laboratory test data and units of measure, please see Soil survey standard test methods

Soil profile report To contact us email:[email protected]

Generated: Wed Nov 04 04:43 2015

© Office of Environment and Heritage (OEH)

Page 48: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7

APPENDIX B REGISTERED BORE INFORMATION

Page 49: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 50: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

NSW Office of Water

Work Summary

GW201778

Licence: 20BL169588 Licence Status: ACTIVE

Authorised Purpose(s):

MONITORING BORE

Intended Purpose(s):

MONITORING BORE

Work Type: Bore

Work Status: Equipped

Construct.Method:

Owner Type: Private

Commenced Date:

Final Depth: 8.10 m

Completion Date: 27/09/2004 Drilled Depth: 8.10 m

Contractor Name:

Driller: Unkown Unknown

Assistant Driller:

Property: MOBIL SERVICE STATION NEW ENGLAND HIGHWAY WHITTINGHAM NSW

Standing Water Level:

GWMA: Salinity:

GW Zone: Yield:

Site Details

Site Chosen By:

County Parish Cadastre

Form A: NORTH NORTH.66 21//1014307

Licensed:

Region: 20 - Hunter CMA Map: 9132-4S

River Basin: 210 - HUNTER RIVER Grid Zone: Scale:

Area/District:

Elevation: 0.00 m (A.H.D.) Northing: 6387182.0 Latitude: 32o38'25.9"S

Elevation

Source: Unknown Easting: 334119.0 Longitude: 151

o 13'53.5"E

GS Map: - MGA Zone: 0 Coordinate Source:

GIS - Geographic Information System

Page 51: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Construction

Negative depths indicate Above Ground Level; C-Cemented; SL-Slot Length; A-Aperture; GS-Grain Size; Q-Quantity; PL-Placement of Gravel Pack; PC-Pressure Cemented; S-Sump; CE-Centralisers

Hole Pipe Component Type From (m)

To (m)

Outside Diameter (mm)

Inside Diameter (mm)

Interval Details

1 Hole Hole 0.00 8.10 0 (Unknown)

1 Annulus Drill Cuttings 0.00 3.50

1 Annulus Bentonite 3.50 4.00

1 Annulus Waterworn/Rounded 4.00 8.10 Graded

1 1 Casing 0.00 8.10 Seated on Bottom

1 1 Opening Slots 5.00 8.10 1 ()

Water Bearing Zones

From (m)

To (m)

Thickness (m)

WBZ Type S.W.L. (m)

D.D.L. (m)

Yield (L/s)

Hole Depth (m)

Duration (hr)

Salinity (mg/L)

Geologists Log

Drillers Log

From (m)

To (m)

Thickness (m)

Drillers Description Geological Material

Comments

0.00 0.40 0.40 Fill; Silty Sand, light brown, medium grained, dry

Fill

0.40 2.20 1.80 Silty Clay; light brown with orange mottling, medium-low plasticity, some fine angular gravel inclusions throughout, gre

Silty Clay

2.20 4.00 1.80 Sandstone; extremely weathered, light orange/brown mottling, fine grained sand, becoming denser below 3m, dry

Sandstone

4.00 8.10 4.10 Siltstone; dry Siltstone

Remarks

27/09/2004: Form A Remarks: Nat Carling, 8-May-2012; All details were taken from consultants log & location map.

*** End of GW201778 ***

Warning To Clients: This raw data has been supplied to the NSW Office of Water by drillers, licensees and other sources. The NOW does not verify the accuracy of this data. The data is presented for use

by you at your own risk. You should consider verifying this data before relying on it. Professional hydrogeological advice should be sought in interpreting and using this data.

Page 52: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

NSW Office of Water

Work Summary

GW201779

Licence: 20BL169588 Licence Status: ACTIVE

Authorised Purpose(s):

MONITORING BORE

Intended Purpose(s):

MONITORING BORE

Work Type: Bore

Work Status: Equipped

Construct.Method:

Owner Type: Private

Commenced Date:

Final Depth: 8.20 m

Completion Date: 27/09/2004 Drilled Depth: 8.20 m

Contractor Name:

Driller: Unkown Unknown

Assistant Driller:

Property: MOBIL SERVICE STATION NEW ENGLAND HIGHWAY WHITTINGHAM NSW

Standing Water Level:

GWMA: Salinity:

GW Zone: Yield:

Site Details

Site Chosen By:

County Parish Cadastre

Form A: NORTH NORTH.66 21//1014307

Licensed:

Region: 20 - Hunter CMA Map: 9132-4S

River Basin: 210 - HUNTER RIVER Grid Zone: Scale:

Area/District:

Elevation: 0.00 m (A.H.D.) Northing: 6387191.0 Latitude: 32o38'25.6"S

Elevation

Source: Unknown Easting: 334106.0 Longitude: 151

o 13'53"E

GS Map: - MGA Zone: 0 Coordinate Source:

GIS - Geographic Information System

Page 53: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Construction

Negative depths indicate Above Ground Level; C-Cemented; SL-Slot Length; A-Aperture; GS-Grain Size; Q-Quantity; PL-Placement of Gravel Pack; PC-Pressure Cemented; S-Sump; CE-Centralisers

Hole Pipe Component Type From (m)

To (m)

Outside Diameter (mm)

Inside Diameter (mm)

Interval Details

1 Hole Hole 0.00 8.20 0 (Unknown)

1 Annulus Drill Cuttings 0.00 2.50

1 Annulus Bentonite 2.50 3.50

1 Annulus Waterworn/Rounded 3.50 8.20 Graded

1 1 Casing 0.00 8.20 Seated on Bottom

1 1 Opening Slots 5.00 8.20 1 ()

Water Bearing Zones

From (m)

To (m)

Thickness (m)

WBZ Type S.W.L. (m)

D.D.L. (m)

Yield (L/s)

Hole Depth (m)

Duration (hr)

Salinity (mg/L)

Geologists Log

Drillers Log

From (m)

To (m)

Thickness (m)

Drillers Description Geological Material

Comments

0.00 0.10 0.10 Fill; Asphalt, gravelly, black medium angular gravel

Fill

0.10 0.60 0.50 Fill; Gravelly Sand, light brown, medium-coarse sand, medium angular gravel, dry

Fill

0.60 0.90 0.30 Silty Clay; light brown/orange mottling, some grey throughout, medium-low density fines, dry

Silty Clay

0.90 1.70 0.80 Sandstone; extremely weathered, light orange/brown, fine grained sand, medium plasticity, dry

Sandstone

1.70 3.20 1.50 Sandstone; extremely weathered, orange/brown mottling, fine grained sand, dry

Sandstone

3.20 8.20 5.00 Siltstone; light brown/grey, becoming denser below 6m, dry

Siltstone

Remarks

27/09/2004: Form A Remarks: Nat Carling, 8-May-2012; All details were taken from consultants log & location map.

Page 54: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

*** End of GW201779 ***

Warning To Clients: This raw data has been supplied to the NSW Office of Water by drillers, licensees and other sources. The NOW does not verify the accuracy of this data. The data is presented for use

by you at your own risk. You should consider verifying this data before relying on it. Professional hydrogeological advice should be sought in interpreting and using this data.

Page 55: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

NSW Office of Water

Work Summary

GW201780

Licence: 20BL169588 Licence Status: ACTIVE

Authorised Purpose(s):

MONITORING BORE

Intended Purpose(s):

MONITORING BORE

Work Type: Bore

Work Status: Equipped

Construct.Method:

Owner Type: Private

Commenced Date:

Final Depth: 5.05 m

Completion Date: 28/09/2004 Drilled Depth: 5.05 m

Contractor Name:

Driller: Unkown Unknown

Assistant Driller:

Property: MOBIL SERVICE STATION NEW ENGLAND HIGHWAY WHITTINGHAM NSW

Standing Water Level:

GWMA: Salinity:

GW Zone: Yield:

Site Details

Site Chosen By:

County Parish Cadastre

Form A: NORTH NORTH.66 21//1014307

Licensed:

Region: 20 - Hunter CMA Map: 9132-4S

River Basin: 210 - HUNTER RIVER Grid Zone: Scale:

Area/District:

Elevation: 0.00 m (A.H.D.) Northing: 6387179.0 Latitude: 32o38'26.0"S

Elevation

Source: Unknown Easting: 334054.0 Longitude: 151

o 13' 51"E

GS Map: - MGA Zone: 0 Coordinate Source:

GIS - Geographic Information System

Page 56: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Construction

Negative depths indicate Above Ground Level; C-Cemented; SL-Slot Length; A-Aperture; GS-Grain Size; Q-Quantity; PL-Placement of Gravel Pack; PC-Pressure Cemented; S-Sump; CE-Centralisers

Hole Pipe Component Type From (m)

To (m)

Outside Diameter (mm)

Inside Diameter (mm)

Interval Details

1 Hole Hole 0.00 5.05 0 (Unknown)

1 Annulus Drill Cuttings 0.00 1.00

1 Annulus Bentonite 1.00 1.50

1 Annulus Waterworn/Rounded 1.50 5.05 Graded

1 1 Casing 0.00 5.05 Seated on Bottom

1 1 Opening Slots 2.00 5.00 1 ()

Water Bearing Zones

From (m)

To (m)

Thickness (m)

WBZ Type S.W.L. (m)

D.D.L. (m)

Yield (L/s)

Hole Depth (m)

Duration (hr)

Salinity (mg/L)

Geologists Log

Drillers Log

From (m)

To (m)

Thickness (m)

Drillers Description Geological Material

Comments

0.00 0.18 0.18 Fill; Concrete Fill

0.18 0.50 0.32 Silty Clay; trace sand, ligth brown

Silty Clay

0.50 1.20 0.70 Silty Clay; light orange/brown Silty Clay

1.20 2.00 0.80 Silty Clay; tends to sandy caly, low moisture content

Silty Clay

2.00 2.60 0.60 Silty Clay; brown orange, tends to weathered siltstone

Silty Clay

2.60 5.05 2.45 Sandstone; fine grained, moderately to slightly weathered, minor weathered siltstone bands

Sandstone

Remarks

28/09/2004: Form A Remarks: Nat Carling, 8-May-2012; All details were taken from consultants log & location map.

*** End of GW201780 ***

Warning To Clients: This raw data has been supplied to the NSW Office of Water by drillers, licensees and other sources. The NOW does not verify the accuracy of this data. The data is presented for use

by you at your own risk. You should consider verifying this data before relying on it. Professional hydrogeological advice should be sought in interpreting and using this data.

Page 57: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

NSW Office of Water

Work Summary

GW201781

Licence: 20BL169588 Licence Status: ACTIVE

Authorised Purpose(s):

MONITORING BORE

Intended Purpose(s):

MONITORING BORE

Work Type: Bore

Work Status: Equipped

Construct.Method:

Owner Type: Private

Commenced Date:

Final Depth: 14.00 m

Completion Date: 29/09/2004 Drilled Depth: 14.00 m

Contractor Name:

Driller: Unkown Unknown

Assistant Driller:

Property: MOBIL SERVICE STATION NEW ENGLAND HIGHWAY WHITTINGHAM NSW

Standing Water Level:

GWMA: Salinity:

GW Zone: Yield:

Site Details

Site Chosen By:

County Parish Cadastre

Form A: NORTH NORTH.66 21//1014307

Licensed:

Region: 20 - Hunter CMA Map: 9132-4S

River Basin: 210 - HUNTER RIVER Grid Zone: Scale:

Area/District:

Elevation: 0.00 m (A.H.D.) Northing: 6387154.0 Latitude: 32o38'26.8"S

Elevation

Source: Unknown Easting: 334097.0 Longitude: 151

o13'52.6"E

GS Map: - MGA Zone: 0 Coordinate Source:

GIS - Geographic Information System

Page 58: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Construction

Negative depths indicate Above Ground Level; C-Cemented; SL-Slot Length; A-Aperture; GS-Grain Size; Q-Quantity; PL-Placement of Gravel Pack; PC-Pressure Cemented; S-Sump; CE-Centralisers

Hole Pipe Component Type From (m)

To (m)

Outside Diameter (mm)

Inside Diameter (mm)

Interval Details

1 Hole Hole 0.00 14.00 0 (Unknown)

1 Annulus Drill Cuttings 0.00 8.50

1 Annulus Bentonite 8.50 9.00

1 Annulus Waterworn/Rounded 9.00 14.00 Graded

1 1 Casing 0.00 14.00 Seated on Bottom

1 1 Opening Slots 10.90 14.00 1 ()

Water Bearing Zones

From (m)

To (m)

Thickness (m)

WBZ Type S.W.L. (m)

D.D.L. (m)

Yield (L/s)

Hole Depth (m)

Duration (hr)

Salinity (mg/L)

Geologists Log

Drillers Log

From (m)

To (m)

Thickness (m)

Drillers Description Geological Material

Comments

0.00 0.15 0.15 Fill; Concrete Fill

0.15 0.50 0.35 Silty Clay; brown Silty Clay

0.50 1.10 0.60 Silty Clay; orange/brown Silty Clay

1.10 1.20 0.10 Silty Clay; orange, brown mottled

Silty Clay

1.20 3.00 1.80 Clayey Silt; orange brown, tends to weathered siltstone

Clayey Silt

3.00 14.00 11.00 Siltstone; grey, fresh & unweathered, minor mud bands

Siltstone

Remarks

29/09/2004: Form A Remarks: Nat Carling, 8-May-2012; All details were taken from consultants log & location map.

*** End of GW201781 ***

Warning To Clients: This raw data has been supplied to the NSW Office of Water by drillers, licensees and other sources. The NOW does not verify the accuracy of this data. The data is presented for use

by you at your own risk. You should consider verifying this data before relying on it. Professional hydrogeological advice should be sought in interpreting and using this data.

Page 59: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7

APPENDIX C COUNCIL PLANNING CERTIFICATE

Page 60: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 61: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 62: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 63: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 64: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 65: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 66: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 67: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 68: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 69: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 70: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 71: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 72: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 73: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7

APPENDIX D DANGEROUS GOODS INFORMATION

Page 74: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 75: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 76: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 77: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 78: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 79: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 80: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 81: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 82: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 83: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 84: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 85: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions
Page 86: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

115085_V7

APPENDIX E PHOTOGRAPHS

Page 87: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 1

Lot4 in DP621020. General open space / paddock.

Plate 2

Lot4 in DP621020. General open space / paddock.

Page 88: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 3

Lot4 in DP6210. Erosion / possible scalding evident near highway.

Plate 4

Lot4 in DP6210. Stream near culvert in west of lot near highway.

Page 89: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 5

Lot 24 in DP1128978. Former works compound main track.

Plate 6

Lot 24 in DP1128978. Former works compound adjacent to railway line.

Page 90: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 7

Lot 24 in DP1128978. Former works compound. Scrap metal pile.

Plate 8

Lot 24 in DP1128978. Former works compound. Soil stockpiles.

Page 91: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 9

Lot 24 in DP1128978. Former works compound. Soil stockpiles.

Plate 10

Lot 24 in DP1128978. Former works compound. Farm dam.

Page 92: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 11

Lot 24 in DP1128978. Former works compound. Access road.

Plate 12

Lot 24 in DP1128978. Former works compound. Dumped office furniture.

Page 93: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 13

Lot 24 in DP1128978. Former works compound. Main entrance track. Bitumen present..

Plate 14

Lot 35 in DP1128981. Possible scalding adjacent to New England Highway.

Page 94: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 15

Lot 35 in DP1128981. Main abattoir treatment pond.

Plate 16

Lot 35 in DP1128981. Paddocks under irrigation.

Page 95: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 17

Picnic / roadstop area off Golden Highway.

Plate 18

Picnic / roadstop area. off Golden Highway.

Page 96: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 19

Lot 1 in DP653039. Grazing land visible.

Plate 20

Lot 21 (service station) and Lot 22 (open space) in DP1014307.

Page 97: Appendix G - Contamination report · 2019-09-28 · Appendix G Contamination report . REPORT NO. 115085_V7 STAGE 1 PRELIMINARY SITE INVESTIGATION NEW ENGLAND HIGHWAY UPGRADE ... Portions

Plate 21

Lot 21 in DP1014307. Operational service station.

Plate 22

Lot 23 in DP1128978. Cleared paddock.