© JANET(UK) 2011

SWERN

JANET South West

Procurement & Transition

Neil ShewryProject Manager

JANET(UK)

1

© JANET(UK) 2011

Procurement• Prequalification Questionnaire• Competitive Dialogue• Call for Final Tenders• Preferred & Reserve Supplier• Contract Signed• What we’ve Bought

2

Transition• Rollout of the New Network• Migration of Connections

© JANET(UK) 2011

Prequalification Questionnaire (PQQ)

• Input: 11 suppliers

3

© JANET(UK) 2011

Prequalification Questionnaire (PQQ)

• Output: 5 suppliers

4

Competitive Dialogue

© JANET(UK) 2011

Competitive Dialogue

• Input: 5 Suppliers

Technical DialogueLegal Dialogue

Over 30 hours of meetings!

• Output: Call for Final Tenders (CFT)

5

Evaluation & Selection

© JANET(UK) 2011

Evaluation & Selection

• Preferred Supplier

• Reserve Supplier

• Final Contract Negotiation

6

Contract Signed?

© JANET(UK) 2011

What We’ve Bought

7

© JANET(UK) 2011

What We’ve Bought

8

© JANET(UK) 2011

What We’ve Bought

9

© JANET(UK) 2011

Rollout of the New Network

• Contract signature by 30 September 2011• Similar topology to existing SWERN network• Audit & survey all PoPs• New circuits delivered by end February 2012

– Retain a few existing circuits

• Re-use some existing equipment– Purchase spares for ease of transition

10

© JANET(UK) 2011

Migration of Connections

• Provisional plan in place• 2 phase approach

– 1. Core– 2. Access

• Estimated 6-8 week window– Dependent on circuit delivery

11

© JANET(UK) 2011

Questions?