Page 1: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Ambition for Ageing

Provider & Stakeholder Event

Bury – 12th February 2015

Page 2: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

• Is this an age-friendly event?

Page 3: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Purpose of today

• Inform you of GMCVO’s plans • Generate interest in the programme of

work• Explain the procurement process for a

local lead• Hear your views on GMCVO’s approach

Page 4: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Our Ambition

We believe Greater Manchester’s ageing

population is an opportunity

Page 5: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Our Ambition

Page 6: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

The Ageing Better Programme

• £80m nationally funding 15 partnerships• Reducing the social isolation of older

people• Test and learn approach• Driven by older people• Equality issues are important

Page 7: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

What we’ve done so far

• 2-stage application process• Consultation• Profiling • Built Partnership

Page 8: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Our Approach

• Recruit expert designers (older people)• Identify local priorities & challenges• Identify local assets & resources• Provide support and small payments to

increase social connections• In later years, investment in scaled

programmes

Page 9: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Delivery

• £10m over 5 years• 24 wards in 8 Local Authorities• 15-20 small projects per year per ward• Equalities Board exploring role of

identity within places• Evaluation and research through UoM,

New Economy & GMCVO

Page 10: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

How will we achieve this?

• Funding a network of Local Delivery Leads (LDLs) who will manage the programme at a local level

• Approx. £650k per district (3 wards) over 5 years

• Bury wards - Moorside, Radcliffe North and St Mary’s

Page 11: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

What do we want from LDLs? • Reach-in and trust of local communities• Enable older people to design age-friendly

communities • Community development approach• Recruitment and support of older volunteers• Manage a range of small payments• Asset-based & participatory approach• Test & Learn

Page 12: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Procurement Process

• GMCVO must treat the funding as public money – therefore EU Procurement Regulations apply

• This impacts on application processes, timescales and communication

Page 13: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Procurement Timeline – (Subject to Change)

• Mid April – Release PQQ• End of May – PQQ Submission deadline• Early June - Shortlisting• Mid June – Release ITT• End of July – ITT Submission deadline• August – Assessment, successful bidders

informed• Late August – Stand Still period• September – Contracts awarded, delivery starts

Page 14: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Outcomes (1/4)

The majority of older people in GM engaged by the

programme will identify their neighbourhood as more

age-friendly

Page 15: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Outcomes (2/4)

In areas supported by this project more older people will undertake activities of interest

and the capacity of local assets will increase

Page 16: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Outcomes (3/4)

Initiatives to reduce social isolation will be

mainstreamed into public and voluntary & community

sector delivery

Page 17: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Outcomes (4/4)

The contribution of older people to civic, cultural and economic life

will be recognised in GM strategies. Clear structures will be

developed to enable older people's voices to be influential.

Page 18: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Questions?

Page 19: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Break – 15 mins

Page 20: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Group Dicussion – Question 1

• How could bidders demonstrate they have trust and reach in local communities?

Page 21: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Group Discussion – Question 2

About Bury• What do older people value within the

wards?• What priorities should we address in the

wards?

Page 22: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Group Discussion – Question 3

• “Age-friendly” to me means………

Page 23: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Group Discussion – Question 4

• Engaging and empowering older people are central to the ethos of the programme, but how might we measure these things?

Page 24: Ambition for Ageing Provider & Stakeholder Event Bury – 12 th February 2015

Communications

• From this point forward the only point of contact will be through [email protected]

• In early April GMCVO will launch our procurement portal – potential bidders will need to register to access documents