2nd qatar bim user day bim technology case study #1
DESCRIPTION
Speaker: Gunnar Godawa – Hochtief ViCon -Scheduling at the Nile Corniche Project About the Qatar BIM User Day: Qatar University, HOCHTIEF ViCon and Teesside University proudly take the initiative to facilitate modern and innovative methods in the Gulf construction industry. The focus is Building Information Modeling (BIM), and our aim is to establish a knowledge platform with government, research and industry experts. The User Day aims to help people to share knowledge, discuss new technologies, and identify new potentials for BIM. More information: www.bimuserday.com Follow BUD on Twitter @bimuserdayTRANSCRIPT
1 Gunnar Godawa
HOCHTIEF ViCon
BIM for Project Scheduling
Case study: The Nile Corniche Project – Cairo, Egypt Gunnar Godawa HOCHTIEF ViCon Qatar W.L.L. www.hochtief-vicon.com
2 Gunnar Godawa
HOCHTIEF ViCon
Key facts:
Started in August 2008 9,361 m² Footprint – ±200,000 m2 GFA Includes a 5-star hotel and restaurants 37 stories 4-level parking facility ± 165,000m3 concrete ± 40,000t reinforcement
BIM Use Cases:
3D Design Coordination Full Quantification from the 3D Model 4D Construction Model Integration of BoQ and unit cost in the database 4D Progress and Cost Monitoring
1. The Project
The Nile Corniche
3 Gunnar Godawa
HOCHTIEF ViCon
1. The Project
A collaborative BIM project setup
• Project developer is the driver of BIM
• BIM Manager coordinates 4D model and ensures quality of data delivery
• PM/ CM uses BIM for project controls
• Contractor provides the BIM services related to his scope of works
• Designer and Consultants use BIM results
Project Developer
PM/CM
BIM
Manager
Contractor Consultant Designer
4 Gunnar Godawa
HOCHTIEF ViCon
1. The Project
Overview of used software systems
3D Quantity
Model
3D Model
creation
4D Schedule
and Progress
So
ftw
are
S
oftw
are
A
pp
lie
d U
se
-c
ase
5 Gunnar Godawa
HOCHTIEF ViCon
Design Coordination System
Building Information System
User interface
Construction Design
2D
ARC/STR
2D
MEP WBS
3D model
4D model
3D design coordination
4D program verification
4D progress monitoring
4D cost monitoring
Model based quantity takeoff
Project
schedule
Cost
estimate
Specs.
BoQ
2. Applied Use-cases
Project phases and supported processes
6 Gunnar Godawa
HOCHTIEF ViCon
2. Applied Use-cases
Quantification from the 3D Model
Usage for Estimation and Scheduling Bill of Quantities / Database 3 4
3D Quantity Take Off 2
Calculation of Quantities
Linking of Specification with 3D Model
Export of Quantities to the database
3D Modeling
Specifications
WBS
3D model
Consolidated 3D model
1
3D Quantity
Model
© HOCHTIEF ViCon
7 Gunnar Godawa
HOCHTIEF ViCon
2. Applied Use-cases
Quantification from the 3D Model – Success factors
• Modeling Guidelines to ensure the re-usage of the model in the project life-cycle
• The 3D model is developed according to the project WBS
• Additional attributes in the 4D model support the easy link with the schedule
• Split of 3D geometry and numerical data enable the flexibility to reuse data in various software tools
3D Model and QTO
Specs
POMI
BoQ
8 Gunnar Godawa
HOCHTIEF ViCon
2. Applied Use-cases
Verification of the Construction Program
4D modeling
Project
Schedules
3D model
Consolidated 3D model
Linking
1
4D program verification meeting 3
Revision of schedules 4
4D
Database
4D schedule analysis 2
Product integrity: Detection of errors
Constructability check and report
Process integrity: Detection of conflicts
© HOCHTIEF ViCon
9 Gunnar Godawa
HOCHTIEF ViCon
2. Applied Use-cases
Verification of the Construction Program – Success factors
• Ensure quality of 4D model by checking that all activities are linked to the model
• Visualize the construction sequence to allow additional schedule analysis
• Include automated verification of the resource distribution over time
• Create reports to document the results of the program verification
10 Gunnar Godawa
HOCHTIEF ViCon
2. Applied Use-cases
Usage of the 4D Model for Progress and Cost monitoring
Progress recording
Actual/planned working schedule
4D progress monitoring/
4D cost monitoring
4
1
4D model update 2
4D
database
Actual/ planned
Schedule
Update database & Visualization 3
4D Construction
Progress Visualization
Building Information System (BIS)
© HOCHTIEF ViCon
11 Gunnar Godawa
HOCHTIEF ViCon
2. Applied Use-cases
Usage of a 4D Model for Progress Monitoring – Success factors
• Define a database structure to ensure data integrity
• Enable the team to access the project schedule without expert software
• Implement regular progress updates in the project database
• Integrate the provided information in regular project tasks such as progress reporting
• Visualize the construction progress for better evaluation and common understanding
12 Gunnar Godawa
HOCHTIEF ViCon
2. Applied Use-cases
Collaboration in the project– One data pool
Approach
Ensure quality and save time and costs through:
• Re-usage of data by all stakeholders
• Better collaboration through common data
• Improved data interoperability
Scheduler
Draftsman
Qto specialist
Management
Estimator
global project
data base
CM
Procurement
Project database
Contractor
© HOCHTIEF ViCon
13 Gunnar Godawa
HOCHTIEF ViCon
3. Case study
Project and Site Management – BIM interface
• One single system with remote access to 3D model and information
• Various project documents are integrated in database
• Considers progress definition of planning department
© HOCHTIEF ViCon
14 Gunnar Godawa
HOCHTIEF ViCon
• Always current data available through remote access to the information
• 4D/ 5D Model is continuously used for reporting purposes
• Database with life-cycle approach will support later operation phase
• Easy user interface supports the usage of BIM data
Valuable Project Experiences
Proven Team Benefits - Survey
15 Gunnar Godawa
HOCHTIEF ViCon
Gunnar Godawa
Senior Project Manager
HOCHTIEF ViCon Qatar W.L.L.
E-Mail: [email protected] Mobile: +974 66 60 91 63 (Qatar) www.hochtief-vicon.com