P:\2007\07624\DOCS\Construction Administration\ConstReports\Field Reports\080731 field report.doc HOBBS+BLACK ASSOCIATES INC Architects, Planners & Interior Designers P.734.663.4189 F.734.663.1770 100 N. State Street Ann Arbor, Michigan 48104 www.hobbs-black.com ANN ARBOR | LANSING | PHOENIX | TOLEDO FIELD REPORT Owner Field Report #: 080731-01 Architect Project: Beaumont Medical Center - Commerce Consultant Project #: 07-624 Contractor Contract: CM Date: July 31, 2008 Temp. Range: 80 – 85 Time: 2:00 – 3:30 pm Est. % of Completion: 10% Weather: mostly sunny, breezy Conformance with Schedule: NA Items to Verify, Information or Action Required: Attached are photos and comments. The foundations for the various retaining walls, screen walls and canopies will be complete next week. The site water, sanitary and storm undergrounds have passed the required tests. Rough site grading is mostly complete, including the retention pond. There is still some work with the berms to complete. Steel lay down areas will be in various parking areas around the building and a View northwest at a footing pour for MRI port screen wall north of column line 13. center bay thru the building will provide a base for a crane or 2 for steel erection beginning August 18 th . Signature: David Downes Project Architect DD Copy to: Beaumont Commerce Team View north showing compacting operations along column line J at generator enclosure.

Upload: others

Post on 23-Feb-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 080731 field report - beaumont-land.com

P:\2007\07624\DOCS\Construction Administration\ConstReports\Field Reports\080731 field report.doc

HOBBS+BLACK ASSOCIATES INC Architects, Planners & Interior Designers

P.734.663.4189 F.734.663.1770 100 N. State Street Ann Arbor, Michigan 48104 www.hobbs-black.com ANN ARBOR | LANSING | PHOENIX | TOLEDO

FIELD REPORT

Owner Field Report #: 080731-01

Architect Project: Beaumont Medical Center - Commerce

Consultant Project #: 07-624

Contractor Contract: CM Date: July 31, 2008 Temp. Range: 80 – 85 Time: 2:00 – 3:30 pm Est. % of Completion: 10% Weather: mostly sunny, breezy Conformance with Schedule: NA Items to Verify, Information or Action Required: Attached are photos and comments.

The foundations for the various retaining walls,

screen walls and canopies will be complete next

week. The site water, sanitary and storm

undergrounds have passed the required tests.

Rough site grading is mostly complete, including

the retention pond. There is still some work with

the berms to complete. Steel lay down areas will be

in various parking areas around the building and a

View northwest at a footing pour for MRI port screen

wall north of column line 13.

center bay thru the building will provide a base for

a crane or 2 for steel erection beginning August

18th

.

Signature:

David Downes Project Architect DD Copy to: Beaumont Commerce Team

View north showing compacting operations along

column line J at generator enclosure.

Page 2: 080731 field report - beaumont-land.com

View east of layout for excavating for column footings

for the canopy at main north building entrance.

View north along west berm at storm outlet of retention

pond.

View northwest showing building pad and main drives

from berm along southeast of site.

View west along south stabilized berm at storm outlet of

retention pond.

Overall view south showing rough grading for a new

berm along the east side of the northeast parking area.

View east towards the free-standing sign showing the

access panel for replacing internal lamps.