Building Information Modelling (BIM)
Leeds Arena – Case Study
![Page 2: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/2.jpg)
Leeds Arena – BIM Time-line
April 2010
Appointed Preferred Bidder
Design Currently 2D
No BIM Requirement
April 2010 to March 2011
Tender Second Stage
Design starting to be developed in 3D
2D Design still being under taken
No BIM Requirement
March 2011
Contract signed
No BIM Requirement
April 2011
BAM Decision to trial BIM on Leeds Arena
![Page 3: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/3.jpg)
- Fabrication Model
Arup M.E.P
Revit 3D
Arup –
Structures –
Revit 3D
Arup 3D Civil
Populous – Rhino
3D & Microstation
2D
Steel – FEL –
Telka 3D M&E – Rotary –
CAD Duct 3D
Precast –
Creagh –
Tekla 3D
Glazing
Contractor 2D
Other design
subcontractors
3D & 2D
• Lifts
• Escalators
• Metalwork
• etc
Envelope –
Lakesmere –
3D DWG
Design Data Model
BAM model co-ordination
![Page 4: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/4.jpg)
Design Data Model – By Design Consultants
![Page 5: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/5.jpg)
Fabrication Model – Co-ordination of subcontractor & Design
Consultants
![Page 6: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/6.jpg)
Leeds Arena Model
![Page 7: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/7.jpg)
Populous Secondary Steel Model FEL Steel Model
Combined Model Lakesmere Stub Model
Example of Supply Chain Design Coordination
![Page 8: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/8.jpg)
Clash in design data model Co-ordinated in Fabrication model
![Page 9: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/9.jpg)
Clash in Fabrication model Co-ordinated in Fabrication model
![Page 10: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/10.jpg)
Repositioning of ductwork around
steelwork
![Page 11: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/11.jpg)
Temporary Propping to Wing Wall Edge Protection to Metal Deck Areas
Handrail locations for temporary and Permanent Schemes High Level Duct, Gantry & Steel Coordination
Zero Harm by design
![Page 12: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/12.jpg)
Building Information Modelling (BIM)
Planning
![Page 13: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/13.jpg)
Initial Concrete roof and external Cladding Sequencing
Precast Wall Slabs
Roof decking erection
Roof Truss erection
![Page 14: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/14.jpg)
4D Planning
![Page 15: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/15.jpg)
Logistics;- Precast and Structural Steel
Precast
Steel
Steel
Precast
Steel
![Page 16: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/16.jpg)
4D Planning
![Page 17: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/17.jpg)
Progress monitoring
![Page 18: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/18.jpg)
Planned (Target Programme)
![Page 19: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/19.jpg)
Actual
![Page 20: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/20.jpg)
Planned (Target Programme) v Actual
![Page 21: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/21.jpg)
Actual
Planned (Target programme) v Actual
Planned (Target Programme)
![Page 22: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/22.jpg)
Work package coordination
![Page 23: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/23.jpg)
From the 3D Model it is clear that we need to remove steel to allow the unit to be erected in place
Steel highlighted in Blue is to be left out during Steel erection
ESCALATOR LOCATION
Installation Methodology
![Page 24: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/24.jpg)
Escalator lifted into position from ground floor by means of A frames supported on existing structural steel above
Installation Methodology
![Page 25: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/25.jpg)
![Page 26: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/26.jpg)
Building Information Modelling (BIM)
Quantities
![Page 27: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/27.jpg)
Revit Concrete quantity checks
Steel quantity Checks with Solibri
![Page 28: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/28.jpg)
Building Information Modelling (BIM)
What next
![Page 29: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/29.jpg)
Efficient Cost Planning & Procurement
• Quick measures from models
• Cost plans
• Direct take offs
![Page 30: Richard beaumont bam](https://reader033.vdocuments.site/reader033/viewer/2022052204/554a0908b4c905507a8b5737/html5/thumbnails/30.jpg)
Handover & Aftercare
• Snagging & Handover
• O&M Manuals
• Field BIM
• Defects management
• Lifecycle