Ruggiero Processing Facility Section Vll Operating Plan Permit No. DES-SW-SP- 12-001 Prepared for: Ruggiero Processing Facility, LLC P.O. Box 434 Saxtons River, VT 05154 November 2010 revised thru July 10,2014 Page 1 28 p:\project\k1998 ruggiero rubbish removal\docs\permit apps\solid wasle\section 7 2O14-O7-07 k1998 operating plan.doc F dtrTvtr

Upload: others

Post on 22-May-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Facility

Section Vll

Operating Plan

Permit No. DES-SW-SP- 12-001

Prepared for:

Ruggiero Processing Facility, LLC

P.O. Box 434

Saxtons River, VT 05154

November 2010

revised thru July 10,2014Page 1 oÍ 28

p:\project\k1998 ruggiero rubbish removal\docs\permit apps\solid wasle\section 7 2O14-O7-07 k1998 operating plan.doc

F dtrTvtr

Page 2: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River, VT 05154

Operating PlanRevised 7l1Ol2O14

DES-SW-SP-12-OO1

E

....5

Ê

Table of Contents

Section 1.0 Facility lnformation .................. 5

1.01. Facility Contact information

1.02. FacilityType............

1.03. FacilityCapacity

:EENVtrff\---1ta:t:[

?r?0]4Ïtt 0r t|'/Ylf,oltlt,|tr,lI& SEnvrCEs

1.04.FacilityServiceType,.''..'.'.'.'....'.,,,...5

1.05. Facility Service 4rea........... ................ 6

1.06. Facility Permittee, Operator, and Property Owner lnformation ...................6

Section 2.0 Authorized and Prohibited Materia|s............... ............6

2.01 . Authorized Materials.... ....-.................. 6

2.02. Prohibited Materials.... ........................6

Section 3.0 Routine Operations P1an........... ................. 7

3.01. Hours of Operation ..........7

3.02. Access Control and On-site Traffic Patterns .........7

3.02(1). lncoming Traffic - Loading ........8

3.02(2). Outbound Tratfic ........................ B

3.03. Materials Acceptance, lnspection and rejection procedures..........................................9

3.04. lncoming Materials Quantity and Source Determination................. ............9

3.05. Outgoing materials - Quantity and Destination Recording Procedures.............. .........10

3.06. Storage Time and Capacity Limits and Monitoring Procedures...................................10

3.07. Collection, Processing, Storage, Transfer and Off-site Diçosa/..... .........11

3.07(1). Recyclables............ ..................11

3.07(2). Masonry & Concrete Products .................... 11

3.07(3). Metal .......... ...........11

3.07(4). Wood......... ............11

3.07(5). Non-Recyclables.......... ............ 1 1

3.07(6). Municipal Solid Waste

Section 4.0 Residuals Management Plan ...................12

4.01. Type and Quantity of Residuals .......12

2of28

Page 3: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FaôililyP.O. Box 434Saxtons River, W 05154

4.02. Res/duals Management Procedures...........

4.02(1\. Moisture from waste............

4.02(2\. Liquids from the trailer loading tunnel.

4.02(3). Non+ecyclable l\¡atenal ......................

4.02(4\. General Shop waste ...........................

4.03. Waste D¡sposal...

4.04. Qual¡ty Assurance/Quality Control Prov¡s¡ons.................

Section 5.0 Fac¡lity Maintênance, lnspection and Monitoring P|an..........

5.01. Sponlaneous Combustion.....

5.02. Other F¡re Hazards...

5,03. Vector Contro|...........

5.04. Methane, Hazardous and/or Explos¡ve Gas Generation

Section6.0 Cont¡ngencyPlan.........

6.01. Emergency P|annin7..............

6.01(1). Severe Storm......

6.01(2). FireiExplosion

6.01(3). Hot 1oads............

6.01(4). Medical Emergency/Personal lnjury

6.01(5). Major Spills

6.01(6). UnacceptableWaste,...,..,,...,...........

6.02. Emergency Con|acts.............

SectionT.0 EmployeeTrainingProgram........

Operaling PlanRevised 711012014

DES.SW-SP-12-OO1

..... 12

.....12

.....13

'.,'''''.','.....,''.''.' 13

......................... 13

........................ 1 3

1¿

...................,.... 14

........................ 1 4

1t

................., ...... 1 5

3of2A

Page 4: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River, VT 05154

7.01. Facil¡ty Staff¡ng ...

7. 02. Supervísory and Operating Personnel Tra inin7 ...................

7.03. Documentation of Tra¡ning

Appendix A - Site Plan.......

Appendix B - Registratron of Nondomeslc Wastewater Holding Tank

Appendix C - Disposal Commitments... ..

Appendix D - Emergency Contacts............

Operating PlanRevised 7/10/2014

DES-SW-SP-12-001

''.'...'','','.,,..,.....''.,,'.''', 21

........................,........... 21

''.'' ''' ''' '.' '.,'.,'.,'..,',,' ',,'. 22

Section 8.0 Recordkeep¡ng and Reporting .................22

8.01. lnformation Compilation.........

8,02. Recordkeep¡ngRequ¡rements

......................... 22

...................... 22

26

27

28

Page 5: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River, VT 05154

Section 1.0 Facility lnformation

1.01. Facility Contact lnformaiton

Name:

Location:

Mailing Address:

Operating PlanRevised 711012014

The Facility name, location, mailing address and property owner are asfollows:

RUGGIERO PROCESSING FACILITY

lndustrial Park Road, Walpole, NH

Ruggiero Processing Facility, LLCP.O. Box 434Saxtons River, VT 05157

1.02. Facility Type

RUGGIERO PROCESSING FACILITY (hereafter RPF) is categorized by theState of New Hampshire Department of Environmental Services WasteManagement Division (NHDES-WMD) as a commercial facility for thecollection, storage and transfer of solid waste as defined by Env-Sw 102.35.The term includes "transfer station" as defined by Env-SW 104.54 and"recycling facility" as defined by Env-Sw 104.20. Storage of recyclables willoccur either inside the building or outside in covered containers.

1.03. Facility Capacity

The Capacity of the facility is not subject to a fixed daily maximumthroughput. Facility processing and storage capacity is restricted so that the"average weekly tonnage received at the facility (during the quarter in whichthe most tonnage is anticipated and received), shall not exceed 200 tons."The waste storage capacity of the facility will not exceed 90 tons. Maximumquantity of processed recyclable material in storage at any one time is 33tons. Maximum quantity of municipal solid waste in storage waiting to betrucked off site for proper disposal at any one time is 30 tons.

1.04. Facility Service Type

The facility is a collection, storage and transfer facility, operated on acommercial basis and includes the recycling and transfer of material hauledby:

. Local Waste Haulers

. Occasional residents, whose load consists of construction anddemolition debris.

. Local contractors

5o128

Page 6: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Facil¡ty Operating planP.O Box 434 Revised 7/10/2014Saxtons River, W 05154 DES-SW-SP-12-OO1

RPF accepts non-recyclable mater¡als and various recyclable materials thatare appropriate for recovery and re-use. All recyclable and non-recyclablematerials are transported off site to facilities authorized to accept therespective materials.

l\lurrici¡ral Solid Waste , MSW, is also âccepted orrly for transfer from snrallbulk container to larger bulk containers wlrich then haul tlre repackagedMSW to approved final disposal sites ât a losser truck¡ng cost,

1.05. Facility Service Area

The facility service area includes southwestern and central western NewHampshire and spot markets with an unlimited service area as defined byEnv-Sw 102.37 . RPF services commercial, municipal and occasionalresidential loads.

1.06. Facility Permittee, Operator, and Property Owner lnformation

Permittee and Operator:

Ruggiero Processing Facility, LLCP.O. Box 434Saxtons River, VT 05157

Property Owner:

same

Section 2.0 Authorized and Prohibited Materials

2.01. Authorized Waste

. Recyclable materials including glass, aluminum, steel cans,paper, high density polyethylene (HDPE) and polyethyleneterephthalate (PET) plastics, and metal, as defined by Env-Sw104.19; and

o Construction/Demolition debris as defined by Env-Sw 102.42.

e Municipal Solid waste, MSW, as defined lty Env-Sw '103.46.

2.02. Prohibited Waste

o Hazardous waste;

. Sludge or septage waste;

o Asbestos waste;

6of28

Page 7: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Facility Operating PlanP.O. Box 434 Revised 7110/2014Saxtons River, VT 05154 DES-SW-SP-12-001

. lnfectious waste;

. Contained gaseous waste;

. Universal waste batteries (except for incidental lead-acidbatteries);

. 55-gal drums or other liquid containers (except for five gallon orless empty containers incidental to the load);

. Explosives;

. Ash;

* Mercury contain¡ng devices;

. Liquid waste; and

. Other wastes not otherwise authorized by condition 6 of thepermit.

Section 3.0 Routine Operations Plan

3.01 Hours of Operation

The facility is open to receive recyclables, non-recyclables, and IVSW sixdays per week within the following hours:

Monday through Friday: 7am to SpmSaturdays 7am to noon

Hours of operation, which may be less extensive than those allowed by itsDES permit, are prominently displayed on the facility entrance sign.

3.02. Access Control and On-site Traffíc Patterns

Appendix A provides a site plan for the facility, which, in addition to generalsite features and layout, shows the location of the following: entrance,access road, turn-around area, hot load area, recyclables storage,u nload ing/recycling building, and container storage areas.

The following site security measures are provided to minimize the potentialfor unauthorized access to the facility in accordance with Env-Sw 1103.03(as a result, locking gates are not necessary).

. On site facilities are locked during non-operating hours.

. Weather resistant signs, which indicate that access is restricted,are posted around the perimeter.

7of28

Page 8: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River. VT 05'154

Operaling PlanRevised 711012014

DES-SW-SP-'12-001

. Vehicular entrances are gated and locked during non-operatinghours.

The off site administrative office provides record keep¡ng and filing space.The recycling facility consists of a 50' x 100' steel building with a concretetipping floor. Areas are designated for material discharge, storage and atrailer loading area. Access inside is maintained at all times for fireprotection via a lockbox located at the main gate.

3.02(f ). lncoming Traffic - Loading

lncoming collection vehicles enter the facility from lndustrial ParkRoad, off Route 12 via a gravel entrance. Vehicles back up intothe recycling building onto the concrete tipping floor where theydischarge their loads. After discharge vehicles leave the buildingthrough the same door and exit the site back to lndustrial Drive.

3.02(21. Outbou nd Traffic

3.02(2)(a).Non-recyclables

Empty open-top transfer trailers enter the site via the mainentrance. The driver backs up to the loading tunnel (lowerslab of building), where the roll off dumpster is loaded. Theythen proceed to the facility entrance/exit onto lndustrial Driveand back onto Route 12.

On occasion, it may be necessary to temporarily store aloaded trailer in the staging area or loading tunnel beforebeing transported off site. While unusual, storage may beover night, but in no instance will the staging period exceedone week.

3.02(2Xb). Recvclables

Empty roll off containers are generally filled with recyclablemater¡al and covered before being transported to end usersor secondary material markets.

3.02(2)(c). Municipal Solid Waste

Fully enclosed waste hauling transfer vehìcles will enter thesile via the main entrance and proceed to the building, Thedrìver bacl<s up to tlre tipping floor and dunrps thcir Ioad,They tlren ¡rroceed to the facility entrance/exit <-¡nto lndusirialDriver and back onto Routc '12.

On occasion, it rïay be necessary to lenrporarily store aìoaded trailer ìn ihe stag¡nç] arca or loading tunnel beforebeirrc lrans¡:orte-'d off site. While unusual, storaqe may be

Bof28

Page 9: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Facilily Operating PlanP.O. Box 434 Revised 711012014Saxtons River, VT 05154 DÊS-SW-SP-12-001

over the weekenci, but ìn r¡o instance will the stagirrg periodexceed 72 hours.

3.03. Materials Acceptance, lnspection and rejection procedures

Each customer is required to provide information regarding the type andsource of recyclables, non-recyclables, and MSW brought to the facility. Asign posted at the entrance to the facility lists prohibited waste.

Upon arrival at the siie, the information is collected per section 3.4 below bythe attendant. Should any wastes arrive from out of State, the attendantdetermines whether there are public benefits as defined by section405.04(1) below. Finally, he categorizes the type of materials into either:non-accepted materials, construction/demolition debris, recycfables, orI\ISW,

Once information has been taken, the vehicles are turned and backed intothe building where the load ís tipped onto the concrete floor. The material isvisually inspected; metal, concrete, wood and other recyclable/re-usablematerials that are appropriate for recovery are separated by hand and/or byuse of wheefed heavy operating equipment, such as a Bobcat or front endloader (herein after, a WFL).

The non-recyclables are pushed to the rear of the building by a WFL to clearthe floor for the next load. An opentop transfer trailer is positioned in theloading tunnel to receive non-recyclable materials as it accumulates. Thetrailer is top loaded and material compacted as necessary by a WFL. Whenthe trailer is full, it is secured and removed from the tunnel for transfer per3.02(2)(a) above.

Facility operators have been trained to identify and properly managematerials not meeting facility acceptance requirements. The process used tomanage unauthorized material is described in Section 6.1.6.

3.04. lncoming Materials Quantity and Source Determination

The facility uses cubic yard measure to determine all incoming vehicleshauling either recyclables, non-recyclables, or MSW. The following isrecorded for each load: cubic yards, generator name and address, haulername and address, truck number or license number, type of recyclable ornon-recyclable material, date and time.

The attendant logs this information into the facility's tracking and billingsystem and prints a ticket for the load, which in turn, is signed by the vehicledriver. The driver retains the signed original; the facility retains a copy for itsrecords in accordance with section 8.

9of28

Page 10: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processinq FacilityP.O. Box 434Saxtons River. Vï 05154

Operating PlânRe\/ised 7110/2014

DES-SW-SP-12-001

3.05 Outgoing materials - Quantity and Destination Recording Procedures

Similar to the incoming vehicle procedures, all outbound materials aremeasured in cubic yards before exiting. Prior to leaving the site, the truck isstopped and data is collected and entered into the tracking and billingsystem. A ticket is printed that indicates the cubic yards and type of materialbeing transported off site. For recyclable loads, the type and cubic yards ofthe recovered material and information regarding the secondary materialmarket is also recorded.

The RPF facility sends recyclables to authorized facilities for re-use;disposal of recyclable materials in a landfill is avoided. The operatormaintains accurate records of all material transported to authorized disposalfacilities or secondary mater¡als markets located in New Hampshire, or outof state. ïhese records are maintained in accordance with requirementsdescribed in section B and are identified in the DES annual facility reporlwhich RPF prepares and submits for the previous year's operation.

3.06 Storage Time and Capacity Limits and Monitoring Procedures

All incoming materials are actively managed in a manner that minimizes thequantity of non-recyclable material stored on site at any one time to amaximum of 45 tons.

Recoverable materials are separated and temporarily stored either insidethe 5,000 square foot recycling building or outside in roll off containers.Maximum quantity of the processed recyclables material ¡n storage at anyone time is 33 tons.

Pursuant to Env-Sw 405.03(a) and (b), material will not be stored for aperiod of time which results in adverse affects to the environment, publichealth or safety. Furthermore, materials are stored in a manner to permitlocal fire fighting response capabilities in accordance with Env-Sw404.05(d).

Any/all putrescible and other non-recyclables will be loaded into open toptransfer trailers throughout the day and will normally be transported to apermitted disposal facility on the day that it is received a the facility.

When it is not possible to transport the materials to the disposal facilitywithin that facility's daily operating hours, it may be temporarily stored onthe recycling building tipping floor or in a transfer trailer and transferred offsite before producing noticeable odor. ln no case shall the waste be storedgreater that one week of its receipt.

10 of 2A

Page 11: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River, VT 05154

Operating PlanRev¡sed 7hOl2O14

DES-SW-SP-12"00'1

3.07 Collection, Processing, Storage, Transfer and Off-site Disposal

Material will be inspected as it is being deposited on the tipping floor. Theoperations staff will visually inspect the material during the process ofspreading and removing recyclable material to ensure that unacceptablematerials as defined in section 2.2 are not present.

Any unacceptable wastes encountered will be managed in accordance withSection 6.1.6 Contingency plan. All other materials are managed as follows:

3.07(1). Recyclables

Recyclables are segregated and managed according to thefollowing procedures to preserve value. All reasonablemeasures are taken to segregate recyclables form non-recyclables to ensure that they are diverted from landfilldisposal in accordance with Env-Sw 405.04(2).

Recyclables will be stored temporarily (working storage)inside the recycling building (see C-1 Site Plan, subject tominor changes); the materials are ultimately transferredoutside to their respective roll-off containers for storagepr¡or to transport off site.

3.07(2). Masonry & Concrete Products

3.07(3). Metal

Brick, masonry products and concrete are stored in roll offcontainers located outside but near the recycling building.(See Appendix A - Site Plan).

Ferrous and non ferrous metal and wire are separated andstored outside in a roll off container and transported to ametal reclamation facility when the container is full.

Aluminum is segregated and may be processed through thehorizontal baler prior to its transport off site to thereclamation facility. The aluminum is temporarily storedoutside in a roll off container.

Clean wood is stored outside in a roll off container.

3.07(4) Wood

3.07(5) Non-Recyclables

As described in section 3.04, once the recyclable materialsare removed, the remaining materials are handled as non-

Page 12: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing f-âcility Operating PlanP.O. Box 434 Revised 7l10l2O1ASaxtons River, VT 05154 DES-SW-SP-12,001

recyclables and temporar¡ly stored in open top transfertrailers, which are covered and secured when properly filledto capacity.

3.07(6) Municipal Solid Waste

MSW will be trucked to the site, durnped on the tippingfloor, and recyclables will be removed. The remainingMSW will then be put into larger dumpsters and hauledto an approved disposal facility.

Section 4.0 Residuals Management Plan

4.01. Type and Quantity of Residuals

RPF generates the following residual materials requiring specialma nagement:

¡ Moisture that may drain out of materials deposited on the tippingfloor.

. Liquids from the trailer loading tunnel. Quantity of liquidsaccumulated will vary depending on the mix of incomingmaterials.

. Non-recyclable materials. Volume will vary depending onincoming materials and respective market opportunities.

4.02. Residuals Management Procedures

The following is a brief description of the methods and procedures used byRPF to address each of the respect¡ve residual streams:

4.02(l ) Moisture from waste

Moisture entrained in the materials is normally absorbed asthe material is spread, separated and compacted on thetipping floor.

On inclement days with significant prec¡pitation, some liquidfrom the material may accumulate on the tipping floor. lf thisoccurs and the volume exceeds that which can be absorbedin the spreading and compacting process, sawdust or otherabsorbent material is spread and used to absorb the liquid.This material is then mixed with the non-recyclable materialand shipped off site for disposal.

12 of 28

Page 13: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River, VT 05154

4.02(21. Liquids from the trailer loading tunnel

Operating PlanRevised 7/10/2014

DES-SW-SP-12-001

The recycling building is equipped with a floor drain and a'1000 gallon liquid holding tank to collect liquids from thetrailer loading tunnel.

The holding tank meets the design criteria of Env-Wm 402of the Permit and Registration Rules, and will be registeredwith NHDES Groundwater Discharge Drinking andGroundwater Bureau. (See Appendix B) lt is equipped withvisual and audio signal alarms, which are activated oncethe level reaches the maximum water depth.

The liquids are emptied on a regular basis and transportedoff site to a local municipal wastewater treatment facility fortreatment and disposal.

4.02(31. Non-recyclable Material

The non-recyclable materials are segregated from theincoming materials and managed as described in Section3.07

4.02(41. General Shop waste

All internally generated waste and/or recyclable material are¡ncorporated into the respective management proceduresoutlines above.

4.03 Waste Disposal

ln accordance with Env-Sw 1105.10, the facility will maintain access to aminimum of two authorized disposal locations (See Appendix C) which arepermitted to dispose of the expected quantity of non-recyclable materials:

o Site One: Keene, NH

. Site Two: Bellows Falls, VT

. Other permitted and authorized facilities, as necessary, to ensurethat non-recyclable material is efficiently processed ihough thefacility.

Similarly, agreements (See attachmenf C) will be maintained at a minimumof two locations for disposal of the liquids from the liquids holding tank:Keene WWTP & Bellows Falls WWTP.

13 of 28

Page 14: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Process¡ng FacilityP.O. Bo¡ 434Saxtons River, VT 05154

Operating PlanRevised 7/10/2014

DES-SW-SP- 12-001

4.04. Quality Assurance/Quality Control Provisions

RPF and authorized disposal facilities regularly communicate regardingacceptable and prohibited materials. Facility operating staff are tra¡ned inidentification of prohibited materíals; these procedures are followed by allfacility operating staff .

Section 5.0 Facility Maintenance, lnspection and Monitoring Plan

Facility operating and supervisory staff are trained pursuant to Section 7.0. Duringfacility operation, staff are alert to potential situations that may require their immediateattention and to ensure safe operating conditions and prevent adverse situations asnoted in the following sections:

5.01. Spontaneous Combustion

The possibility of spontaneous combustion is limited since incomingmaterials are actively managed and do not include volatile materials. lnaddition, the materials are generally transported off site daily as describedin Section 3.07. Finally, the building is metal framed with a concrete floorand steel siding, designed and constructed to limit the potential of fire.

An automatic fire detector will be installed inside the recycling building,should a fire occur during operat¡ng hours, the owner is immediatelycontacted, and if no answer is detected, the Walpole Fire department isautomatically called to ensure immediate response.

ln the unlikely event of a fire, procedures as outlined in Section 6.01(2) willbe followed.

5.02. Other Fire Hazards

Although unlikely that a "hot" load would be delivered to the facility, alldrivers are encouraged to take immediate action in the event of a fire orother safety concern. All drivers are instructed to immediately contact theRPF office and building attendant so assistance can be provided.

RPF personnel will be prepared for the arrival and manage the load once itarrives. Procedures as outlined in Section 6.01(3) will be followed.

Once controlled, an assessment will be made prior to discharging the loadto determine the immediate need to notify and request assistance from theWalpole Fire Department.

Should a fire occur inside the building, the procedures described in Section6.01(2) will be followed.

14 of 28

Page 15: Created Date: 7/29/2014 8:57:54 AM

Ruggaero Processing FacilítyP.O. Box 434Sâxtons River, VT 05'154

Operating PlanRevised 7l1Ol2O14

DES-SW-SP-12-001

5.03. Vector Control

The facility is operated to minimize the potential for vectors. Recycling andtransfer operations occur within the enclosed building. Other than duringinspection and processing on the tipping floor, all non-recyclable materialsare containerized into open top transfer trailers and covered by a tarp uponbeing filled to capacity. Materials are actively removed so that the potentialfor vectors is minimized.

RPF staff will regularly inspect the facility for vectors and will retain theservices of a licensed pest control company to ensure that vectors do notbecome a problem.

5.04. Methane, Hazardous and/or Explosive Gas Generation

Any putrescible material will be removed from the facility before anaerobicdecomposition can generate methane, hazardous or explosive gases.

Hazardous and/or explosive gases are not accepted or managed by thefacility; liquids and gaseous wastes are proh¡bited.

5.05. Odors

The facility operations are conducted inside an enclosed building. lnaccordance with the operating permit, storage capacity and times are limitedas presented in Section 3.07. Since non-recyclable material and MSW aretypically transported off site daily, the potential for odor generation will beminimized. Recyclables are transferred off site as containers are filled.Adherence to the facility operating procedures generally prevents and/orcontrols odor issues.

The facility is located on approxímately 6 acres and operated in a mannerconsistent with applicable NH Solid waste Regulations. Although odorgeneration is minimized, RPF will investigate the potential source in theevent off site odors are detected and, if facility related, adjust operationsaccordingly. (e.9., apply odor neutralizing agents, arrange faster transfer,and check proper load tarping).

5.06. Dust

The majority of on-s¡te travel surfaces are gravel. The areas potentiallycontributing to dust generation are the access road and turn around areas.

The site is located in an isolated area in a part of a former sand and gravelpit. The location provides that impact of dust off site will be minimal.

Page 16: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River, W 05'154

Operating PlanRevised 7/ 10/2O14

DES-SW-SP-12-001

5.07. Windblown Litter

Material transfer operations occur within the building.

Most vehicles using the facility will be self contained packers and roll offtrucks. Drivers are instructed to keep loads covered until they reach the turnaround area to reduce the potential for litter generation.

To ensure that liiter is properly managed, facility operational staff willinspect the site daily and collect litter or debris found. This material will beplaced with other incoming material in the recycling building and processedaccordingly.

5.08. Leachate

Section 4.0 Residual Waste management, describes procedures that areused to manage any liquids collected from materials that are processed atthe facility.

5.09. Spill Management

Spills are managed in accordance with Section 6.01(5) Contingency Plan.

5.10. Storm Water Management

Storm water is generally managed as sheet flow from gravel surfaces andultimately infiltrates into vegetated areas.

Storm water from slabs in building will be collected with floor drains andpiped into the holding tank.

Section 6.0 Contingency Plan

The following contingency plan for Ruggiero Processing Facility discusses thepotent¡al emergency conditions, respective likelihood for occurrence andappropriate response to be taken by staff in an event.

Because of the no-toxic, non-hazardous nature of materials received at the RPF,emergencies of any kind are unlikely. Notwithstanding, several precautions andprocedures are in place to assure appropr¡ate responses in the event of a releaseor accident. RPF has designated an Emergency Coordinator and AlternateEmergency Coordinator who assist in managing response activities should any ofthe following emergency situations occur at the facility.

ln addition, RPF has posted emergency phone numbers ¡n the recycling buildingand on the lock box at the main gate.

16 of28

Page 17: Created Date: 7/29/2014 8:57:54 AM

Rugg¡ero Processing Facili(y Operating PlanP.O. Box 434 Revised 7/10/2014Saxtons River. VT 05154 DÊS-SW-SP-12-001

6.01 EmergencyPlanning

This plan describes the actions to be undertaken in response to thefollowing:

o Severe storm

. Fire/Explosion

. Hot Loads

. Medical emergency

. Chemical spills

. Unacceptable waste

6.01(1). Severe Storm

The operations staff evaluate whether early closure of the facility iswarranted. If the daily operation cannot be completed in time, thebuilding and all vehicles will be shut down and secured untiloperations are safe to resume.

6.01(2). Fire/Explosion

The facility does not store any petroleum or other combustibleproducts; therefore the likelihood of a fire or explosion is low.However, to assure full preparedness, hand-held fire extinguishersare located neat the entry to the recycling building.

The materials unloaded inside the recycling building are managed inaccordance with Env-Sw 404.05(d) (3). Access is maintained at alltimes in the event fire services are necessary.

Water supply in the event of a fire is off site via emergency vehicles.

Site personnel are trained to notify the fire department in the event ofa fire and to use the appropriate fire extinguishers until the firedepartment arrives. A lock box system is provided to ensure that thefire department can always access the building.

Finally, an automatic fire detector alarm will be installed in therecycling building; should a fire occur during non-operating hours, theowner and Walpole fire department are automatically called.

6.01(3). Hot Loads

Hot loads which inadvertently arrive at the entry are managedimmediately by on site personnel with assistance from the WalpoleFire Department (911) if needed. Upon arrival, drivers are instructed

Page 18: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons Rrver, Vl 05154

Operating P¡ênRevised 7/'10/2014

DES-SW-SP-12-001

to immediately contact the RPF office. An assessment will be madeto determine the immediate need to notify and request assistancefrom the Walpole Fire Department.

After appropriate response actions are taken (as determined on aload specific basis) and the load is determined safe, it is unloadedoutside the south side of the building in the truck turn-around area.The area is gravel, so should there be any smoldering or burningmaterial discharged, it will be extinguished using fire extinguishersand/or on site soil. lf necessary, small amounts of water will also beused to assist in extinguishing any fire or smoldering materials. Oncefully extinguished, facility operators will move the material into thebuilding where it will be loaded into a transfer trailer using standardoperating procedures. The area impacted by a hot load will also becleaned to ensure that no residual material, contaminated soil orwater is left in the area.

6.01(4). Medical Emergency/Personal lnjury

ln the event of minor personal injury at the facility, firsi aid kits will beavailable at the scale/office and inside the recycling building. Sitepersonnel will be instructed to call 91'l .

First aid and CPR training will be provided to site employees to assistin the immediate care of burns, needle sticks, RMW exposure,chemical exposure and physical injuries.

For non-emergencies, transportation is provided to the DartmouthHitchcock Medical Center in Keene, New Hampshire. The contactinformation and routing to the hospital wilf be posted at the facility.

For more seríous injuries, Mutual Aid Ambulance service will becontacted (91 1) for immediate instruction and treatment, includingtransport to the nearest hospital or to another medical treatmentfacility, if necessary.

Annual training is provided to facility employees regard¡ng proceduresfor notifrcation of injuries, fires and other emergencies.

6.01(5) Major Spills

6.01(sXa). General Site

Although a major spill of any kind is unlikely, a thirdparty spill response contractor will be called to thefacility to manage the clean-up, should one occur. Thetypes of spills that may occur include:

18 ol 28

Page 19: Created Date: 7/29/2014 8:57:54 AM

Ruggjero Processing Facjljty Operât¡ng plânP.O. Box 434 Revised 7t1Ol2O14Saxtons River, W 05154 DES-SW-SP- 12-OOl

I Petroleum from a piece of operating equipment or anyother vehicle on site.

ln the event that a petroleum-based liquid is accidentlyspilled from operating equ¡pment or vehicles using thefacility, it will be immediately contained, absorbentapplied and cleaned up by fac¡lity operating personnel.

For spills greater than 25 gallons (or less than 25gallons if for any reason site personnel are unable toimmediately contain) the fire department will becontacted. Personnel will be isolated from the area.Trained personnel will be asses and determine cleanup required. NHDES will be notified.

ii Unknown subsfance from an incoming load

Facility personnel wifl immediately secure the area andcontact the appropriate local and state personnel andagencies for assistance in determining appropr¡eateprocedures for managing the spill.

6.01(5Xb) Unloading/Loading Area - Recycling BuildingThe RPF recycling building is designed and consiructedto fully contain all spills.

There are floor drains in the tipping floor so that any spillsand/or any accumulation of liquids are contained in theholding tank. These liquids are co-mingled with the non-recyclable materials and/or absorbents. Spill kits, whichinclude speedy dry, other absorbent material, andabsorbent booms are kept inside the building. Theholding tank shall be cleaned and containment sent to adisposal center.

The trailer tunnel floor drain is connected to anunderground storage tank for collection and temporarystorage of liquid. lt is equipped with visual and audiosignal alarms, which are activated once the water levelreaches the maximum water depth.

Accumulated liquid is monitored and periodically pumpedout and transported to a waste treatment facility permittedto treat such liquids.

6.01(6). Unacceptable Waste

lf any unacceptable material is encountered, it is separated and removedfrom the facility by the original hauler. When such material is

19 of 28

Page 20: Created Date: 7/29/2014 8:57:54 AM

Rugg¡ero Processínq FacilityP.O. Box 434Saxtons River, Vf 05154

Operating PlanRevised 7/10/2014

DES-SW-SP-12-OO1

encountered, RPF will inform the hauler of other potentially availablefacilities for its management. lf the original hauler is no longer at thefacility or cannot be identified, RPF will assume responsibifity for theproper disposal of the material as required by solid waste and/orhazardous waste rules.

While unlikely, should asbestos-contain ing material be inadvertentlytransported to the facility with C&D debris (e.9., asbestos shingles) it willbe segregated and isolated from ongoing activities. RPF will contactoutside contractors listed in Section 6.02 to manage the material.

Similarly, outside contractors will be contacted to manage any materialthat is suspected hazardous or otherwise requires special handling (anysmall containers of ihese flammable materials will be temporarily storedin a steel fireproof cabinet per the fire department).

Should lead-acid batteries be encountered, they will be managedpursuant to the universal Waste Rule (Env-Hw 1 100) using proceduresdescribed in WMD-HW-lB and WMD-SW-4. They will be managed asfollows:

. Stored on pallets so that their electrodes do not comeinto contact with electrodes of other batteries or metalobjects;

. lf stored in containers, covers will be loose fitting;

. Stored and kept dry;

. Stored away from sources of sparks or flames; and

. Stored so leaking batteries are separated form nonleaking batteries.

These will be periodically transported to authorized battery recyclers orhandlers in compliance with DOï requirements.

Should mercury containing devices (e.9., thermometers, thermostats,switches, relays, etc) be encountered, they will be removed and placedin a small container for temporary storage until transfer off site to anauthorized outside contractor.

All facility operating personnel will receive initial and periodic refreshertraining, which covers at a minimum:

. Acceptable recyclable and non recyclable materials

. Prohibited materials

. The facilities procedures to ensure that identifiedunacceptable material is managed properly.

20 of 28

Page 21: Created Date: 7/29/2014 8:57:54 AM

RLrggiero Processing Facif ilyP.O. Box 434Saxtons River, VT 05154

6.02. EmergencyContacts

Operating PlanRevised 711012014

DES-SW-SP-12-001

A list of emergency contacts and phone numbers will be posted at thescale house and the recycling building. The contact list will be reviewedat least annually and updated as necessary to ensure it is current. Acurrent list (November 2010) that will be replaced periodically, is foundin Appendix D.

Section 7.0 Employee Training Program

This section provides a summary of training procedures for RPF supervisoryand operations staff. This training is based on requirements of:

. Job position, associated responsibilities and comp[any procedures

. Regulatory-based training requirements.

7.01. Facility Staffing

Facility operating personnel have obtained certification or interim certificationin accordance with Env-Sw 1600. At least one management/supervisor will becertified as a level lV operator for every one to five operators.

During hours of operation, at least fifty (50) percent of on site operatingpersonnel directly involved with the management of recyclable and non-recyclable material is certified by the DES as solid waste facility operatorspursuant to Env-Sw 1005.07(bX1) and (3).

7.02. Supervisory and Operating Personnel Training

Operating staff have completed the Solid Waste Facility Operator Training andCertification Program conducted by the New Hampshire Deparfment ofEnvironmental Services.

The facility provides periodic refresher haining to facility operations personneland requires that employees holding Solid Waste Operator Certificationsmaintain their certification by participating in annual continuing educationworkshops offered by DES. These workshops cover a variety of topicsassociated with solid waste facility operations.

New employees complete initial Employee Orientation throughout their 30 dayprobationary period while working under the direct and immediate supervisionof an experienced member of the facility operational staff. Emplovees shall becertified durinq probationarv period.

The haining program at RPF will focus on key elements of safe facilityoperating practices, such as:

. Facility layout and operating equipment

21 of 28

Page 22: Created Date: 7/29/2014 8:57:54 AM

Operating PlanRevised 7/'1012014

DES.SW"SP,12.OO1

. Work rules and procedures

c Facility permit and operating plan, including:- Materials inspection and identification procedures

- Acceptable and prohibited materials- Contingency plan

. Equipment operating procedures and maintenancesrequirements

. New Hampshire Solid Waste Rules applicable to collection,storage and transfer facilities.

New employees shall register and obtain interim ceft¡fication as a Solid WasteFacility Operator, (Level I to Level lV) under the New Hampshire Departmentof Environmental Services Solid Waste Operator Training and CertificationProgram. The employees retain their interim certification until they havesuccessfully completed the next scheduled NHDES Solid Waste FacilityOperator Training Program.

7.03. Documentation of Training

Documentation of operator training is maintained and posted at theadministrative office, including copies of Solid Waste Operator Certificatesissued by the New Hampshire Department of Environmental Services forfacility staff.

Section 8.0 Recordkeeping and Reporting

8.01. lnformation Compilation

The facility owner will compile and maintain information documenting keyaspects of facility operations. Recyclable and non-recyclable quantityinformation will be obtained as described in section 3.0. While out-of-Statewaste is expected to be minimal, an evaluation will be performed to verify thatthe total quantity of waste received annually from New Hampshire generatorsdoes not exceed the total quantity of waste transferred to New Hampshirelandfills. Should waste receipts approach its limit, out of-state loads will bescheduled accordingly and the scale operator notified.

All other informatíon compiled will meet the requirements of Env-SW 405.04(Public benefit) and 1105.06 (Facility Operating Records). The records will bemaintained at the facility and will be readily available for NHDES inspection.

8.02. Recordkeeping Requirements

The permittee will compile and maintain records, which document facilityoperations including:

Ruggiero Processing FacilityP.O. Box 434Sâxtons River. VT 05154

22 of 28

Page 23: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Fâcility Operat¡ng PlânP.O. Box 434 Revised 7/10/20'14Saxtons River, W 05154 DÊS-SW-SP-12-001

(1) Facility ldentification by name, street address, municipalityand permit number.

(2) Permittee name, address and telephone number

(3) ldentification of all facility operato(s) by name, address,NHDES Operator certificate number, and dates ofemployment at the facility.

(4) Quantity, type, sources and destination of non-recyclables,recyclables, and MSW received at the facility. ln accordancewith Env-Sw 405.05, the following information specifically willbe tracked and recorded:

o Totaf quant¡ty of waste that the facility transfersannually to New Hampshire landfills or incinerators.

. Total quantity the facility receives annually from NewHampshire generators.

(5) Quantity, type and destination of the materials generated bythe facility, including residuals which are not recycled.

(6) Quantity, type and destination of all certified waste derivedproducts produced by the facility, if any,

(7) Records of inspections, maintenance and repairs.

(B) Records of accidents, fires violations, remedial andemergency event response actions

(9) lncident reports and record of complaints in accordance w¡thEnv-SW 1005.09

('1 0) Data for all environmental monitor¡ng performed at or for thefacility, whether required by the solid waste rules or thepermit is undertaken voluntarily.

(1 I ) Documentation of all contact with the waste managementdistrict(s) served by the facility as required by Env-Sw1105.12

(12)Other recordkeeping information and documentation requiredby Env-Sw 400 (Collection, storage, and Transfer FacilityRequ irements)

(13)Other information and documentation required by the termsand conditions of the permit and solid waste rules.

RPF wifl maintain the operating records identified above during the active lifeof the facility, unless approval is granted or a Type V permit modificationpursuant to Env-Sw 315 (g) to relocate or destroy the records. Operatingrecords shall be made available for DES inspection and copies provided to theDepartment pursuant to Env-Sw 2000 (lnspections)

23 of 28

Page 24: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Facllity Operating PlanP.O. Box 434 Revised 7/'10/2014Saxtons River, VÎ 05154 DES-SW-SP-'12-001

Following closure of the facility, the operating records will be maintained at alocation approved by DES in the Closure Plan, unless desiruction of therecords is approved pursuant to the provisions of a Type V permit.

8.03. Facility reporting requirements

The permittee will ensure that the reporting requirements of Env-Sw 405.04(3)and 1105.07 (Reporting Requirements) are met and that the annual report forthe facility is submitted by March 31 for the prior calendar year. All reportingwill be in conformance with Env-Sw 303.03 (Basic Filing Requirements) andEnv-Sw 303.04 (Signature Requirements).

Finally, RPF will send a copy of the annual report to the Town of Walpole,Board of Selectmen (as representative for the Walpole Solid WasteManagement Dp:\project\k1 998 ruggíero rubbish removal\docs\permitapps\solid waste\section 7 2014-07-07 k1998 operatingplan.docp:\project\kl99B ruggiero rubbish removal\docs\permit apps\solidwaste\sect¡on 7 2014-07-07 k1998 operating plan.docistrict) in accordancewith Env-Sw 1105.12. A cover letter will accompany which explains how RPFmet its obligations for providing a substantial public benefit (per Env-Sw405.04) during the preceding year and which requests the Town/Districtrepresentatives to identify specific needs which the facility may be able toass¡st in meeting.

24 ot 28

Page 25: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Fac¡lítyP.O. Box 434Saxtons River, VT 05154

Operat¡ng PfânRevised 7ll0l2j14

DES-SW-SP-12-00'1

Appendix A:

Site Plan

25 of 28

Page 26: Created Date: 7/29/2014 8:57:54 AM

RLrggrero Processiog FacilityP.O. Box 434Saxtons River, W 05154

Operating PlanRevised 7/10/2014

DES-SW-SP-'12-001

Appendix B:

Registration of Nondomestic Wastewater Holding tank

Page 27: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Facility Operating PlanP.O. Box 434 Revrsed 7/10/2014Saxtons River. VT 05154 DES-SW-SP- 12-001

Appendix G:

Disposal Commitments

27 ol 28

Page 28: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons Rive¡. VT 05154

Operating PlanRevised 711012014

DES-SW-SP.12-OO1

Appendix D:

Emergency Contacts

RPF Jeff Ruggiero (802) 123-4567

Level lV OperatoÍs Jeff Ruggiero.loe Rr rooiero

Environmental Coordinator

Alternate Environmental Coordinator

Ambulance/Fire Police Emergency 911

Walpole Fire Departmenl Non-Emergency (603) 756-3ô21

Walpole Police Departmenl Non-Emergency (603) 455-2058

County Sherriff Emergency Cheshire County (603) 352-4238

Local Hospital Cheshire Medical Center/DartmouthHitchcock Clinic

(603) 354-5400

Poison Control Center Hanover Poison Center 1-800-562-8236

Spill Response Contractor

Spill Response Contractor - Alt,

Asbestos Contractor

State Police (Headquarters) Emergency (003) 271-3636

Emergency - Toll free (800) 525-5555

Non-Emergency, Troop C (603) 358-3333

Hazardous materials/Petroleum spills (800) 346,4009

Department of Environmental ServicesINHDES) Emergency Response (Daytime) (603) 27r -3899

Solid Waste Management Divis¡on (603) 27 1-2925

Hazardous Materials Spills (603)271-3899

Department of Health & Human Serv¡ces (603) 357-3s10

Homeland Security and Emergency Managemenl (603) 271-2231

U.S. Environmental Protection Agency/Ra<tnn\ Non-Emergency (888\ 372-7341

Emergency (800) 424-8802

National Response Center

Fed eiä Æ m *s. "õt

M ã iì aôe m-e ntBoston

!90013!v02(617) e56-7506

2P, of 2A

Page 29: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Facility

Section Vlll

Glosure Plan

Permit No. DES-SW-SP-12-001

Prepared for:

Ruggiero Processing Facility, LLC

P.O. Box 434

Saxtons River, VT 05154

November 2010

Revised thru July 10,2014

p:\proiect\k 1998 ruqgrero nlbbish removal\docs\peÍìrit apps\solid waste\section B 2014-07-10 k 1998 closure plan.doc

Page 30: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River, VT 05154

Closure P¡anRevised 7/'10/2014

DES-SW-SP-12-001

3.1. AuthorizedMaterial

5.1 . Recyclable, Non Recyclables, antl MSW ITemoval,

5.2. Equ¡pment Removal and Decomm¡ssion¡n7............... ........................6

5.3. Fac¡lity Cleanup.. ........................6

Section 6.0 Post-Glosure Requirements ..,.................... 7

Section 7.0 Recordkeeping and Reporting ................... 7

7.1. Closure Reporting

..................................... 4

7.2. Recordkeep¡ng ... ...................7

Section 8.0 Other Closure Permits............... .................. I

Section 9.0 Glosure Cost Estimate............. .................... IAppendix A: Financial Assurance Plan and Closure Gost Estimate.,,..,.,..,...................,.....9

2ol9

Page 31: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FaolityP.o. Box 434Sextons R¡ver. VI05154

Cìosure PlanRevised 7/10/2014

DES-SW-SP-12-001

Section 1.0 Facility lnformatíon

The Facility name, location, mailing address and property owner are asfollows:

Name: RUGGIERO PROCESSING FACILITY

Location: lndustrial Park Road, Walpole, NH

Mailing Address: Ruggiero Processing Facility, LLCP.O. Box 434Saxtons River, VT 05157

Section 2.0 Closure Schedule

This Schedule is based on the RUGGIERO PROCESSING FACILITY'soperation as a commercial C&D and recycling facility. With regularmaintenance and refurbishment of operating equipment, RFP expects tocontinue operations indefinitely. However, closure procedures will beinitíated when one or more of the conditions of Env-Sw 1006.01 exist.These include:

. RUGGIERO PROCESSING FACILITY's operating permit isexpired or revoked.

. RUGGIERO PROCESSING FACILITY ceases operations forany reason.

. Facility sustains irreparable damage.

. Environmental conditions exist that threaten human life orsafety or threaten the environment in a way that cannot beremed iated.

. Facility is issued an administrative or judicial order to ceaseoperations.

Closure will be completed within sixty (60) days of cessation ofoperations. The closure will occur according to the followingschedule:

Page 32: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River, VT 05154

Closure PfanRevised 7/10/2014

DES"SW-SP-12-OO1

30 days prior to Day 1:

. File a Notice to C/ose with the New Hampshire Departmentof Environmental Services (NHDES), Waste ManaqementDivision.

. File notice with NHDES Drinkinq Water and GroundwaterBureau regarding decommissioning of the Holding ïank.

Day 1 to day 20:

Empty and rinse/clean liquid holding tank. Transfer allrccyclables, non-recyclable, ancJ MSW materials to anauthorized disposal facility.

Day 21 to day 55

Decommission and remove facility equipment (i.e.:dumpsters, vehicles, etc) so that it can be used at anotherfacility or sold. Clean the building, sweep concrete surfacesand clean surrounding gravel parking and adjacent areas.

Day 56 to day 60

Prepare and submit the notification to the New HampshireDepartment of Environmental Services that the closure iscom plete.

Section 3.0 Waste ldentification

Section 2 of the Ruggiero Processing Facility Operating Plan describesthe materials authorized and prohibited for management at the facility.These lnclude:

3.1. Authorized Waste. Recyclable materials including glass, aluminum, steel cans,

paper, high density polyethylene (HDPE) and polyethyleneterephthalate (PET) plastics, and metal, as defined by Env-Sw 104.19; and

. Construction/Demolition debrìs as defined by Env-Sw102.42.

4ofg

Page 33: Created Date: 7/29/2014 8:57:54 AM

Ruggiero P¡ocessing FacilityP.O. Box 434Saxtons River. VT 05154

* Municipal Solid Waste, MSW, as defined by Ënv-Sw 103.46

3.2. ProhibitedMaterials. Hazardous waste;

. Sludge or septage waste;

. Asbestos waste;

. lnfectious waste;

. Contained gaseous waste;

. Universal waste batteries (except for incidental lead-acidbatteries);

. 55-gal drums or other liquid containers (except for five gallon orless empty containers incidental to the load);

. Explosives;

. Ash;

. Mercury containing devices;

. Liquid waste; and

. Other wastes not authorized by condition 6 of the Permit.

SectÍon 4.0 Notifications

At least 30 days prior to the cessation of facility operations, theRUGGIERO PROCESSING FACILITY will provide written notification,including notice of the planned date of facility closure, to the following inaccordance with the New Hampshire Solid Waste Rules:

. All users of the facility

o Town of Walpole

. NHDES - Waste Management Division

. NHDES - Drinking Water and Groundwater Bureau

The notice will be posted at the scale office and will include a final date forthe receipt of recyclables, non-recyclables, and IVSW at the facility.

Closure PfanRevised 7/10/2014

DES-SW-SP-12-001

5of9

Page 34: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons Rivêr. VT 05154

Closure PlanRevised 7/1012014

DES-SW-SP-12-001

Section 5.0 Closure Requirements

Cfosure will be in conformance with this facility closure plan, Env-Sw 406,Env-Sw 1006 and Env-Sw 1 1 06.

At the Specified closure date, receipt of recyclables, non-recyclables, andMSW will cease. At that time, the three activities described in sections 5.1,5.2 and 5.3 of this closure plan will commence. Upon completion of theactivities, the facility will be closed.

5.1. Recyclable, Non Recyclables and MSW RemovalWithin 20 days following the last day of facility operations, allrecyclables and non-recyclable material on site will be removed(see seclion 2.0 - Closure Schedule).

. All recyclables will be transported to authorized reclamationfacilities and/or secondary markets.

. All remaining non-recyclable/residual material and MSW willbe transported to authorized disposal facilities in accordancewith New Hampshire Solid Waste Rules.

. The liquids holding tank will be emptied and rinsed;wastewater will be transported off site to a local authorizedwastewater treatment facility.

No revenue from the sale of any recyclables stored on site at thetime of closure have been assumed nor considered in the closurecost estimate prepared for this plan.

5.2. Equipment Removal and DecommissioningUpon completion of recycling activities at the facility, all operatingequipment (i.e., heavy operating equipment, excavators, baler) willbe removed, sold or reallocated (in a commercial businessseparate from the recycling operation). The scale and liquidsholding tank will be cleaned and left on site for subsequent use by anew owner/operator.

No salvage value has been assumed nor considered in the closurecost estimate prepared for this plan.

5.3. Facility CleanupFollowing the removal of materials from the facility, the building willbe cleaned and any contaminat¡on to its approximate original

6ofg

Page 35: Created Date: 7/29/2014 8:57:54 AM

R0ggrero Processrng FacililyP.O. Box 434Saxlons River, VT 05154

Closure PlanRevised 7/10/2014

DES-SW-SP-12-001

condition of cleanliness. Facility signage will be removed. Anywater which is stored in the holding tank and utilized in this cleaningeffort will be absorbed by absorbent materials and/or collected anddisposed of at a permitted wastewater treatment facility.

Section6.0 Post-ClosureRequirements

The RUGGIERO PROCESSING FACÍ LITY will process and recoverrecyclables and manage recyclables, non-recyclables, and MSW bytransfer to authorized facilities during its operating life.

When facility operations cease, the closure plan activities described inSection 5 of this closure plan will assure that the facility will not adverselyaffect the environment, public health or safety. As a result, post closuremonitoring, testing, inspection and maintenance of the facility followingcompletion of facility closure will not be performed and post closurereporting will not take place, (uniess required by local, state or federalregulations).

Section 7.0 Recordkeeping and Reporting

7 .1. Closure ReportingFollowing completíon of closure activities described in Section 5 ofthis closure plan, RUGGIERO PROCESSING FACILITY willprovide wr¡tten not¡ce to the Town of Walpole and NHDFS - WasteManagement Division that closure has been completed.

RUGGIERO PROCESSING FACILITY will submit a final annualfacility report to the NHDES Waste Managemeni Division by March31 of the year following closure, pursuant to reporting requirementsdescribed in Env-Sw 1105.07(b).

7 .2. RecordkeepingFollowing closure of the facility, all records regarding the facilityoperation and closure will be retained at the RUGGIEROPROCESSING FACILITY's principal place of business at lndustrialRoad in Walpole, NH or as otherwise specified in the facility closurereport.

Page 36: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing Facility Closure PlanP.O. Box 434 Revised 7/10/20'14Saxtons River. W 05154 DES-SW-SP-12-001

Section 8.0 Other Closure Permits

No other permits or compliance related activities are required toimplement facility closure.

SectÍon 9.0 Closure Cost Estimate

A closure cost estimate for the RUGGIERO PROCESSING FACILITY wasprepared in accordance with this closure plan and criteria in Env-Sw1403.O2 and included as a part of the closure plan. The following criteriawere used when preparing the estimate.

. An assumption that maximum combined volume of non-recyclableand MSW materials in storage is 45 tons.

. An assumption of a maximum of 100 gallons of liquids are stored inthe liquid holding tank and an additional 500 gallons of rinse waterto clean.

. The liquid holding tank will be left on site.

. Current market rates for having third party per{orm all closureactivities.

o The estimate considers a point in the facilities active life when theextent and manner of operations and compliance with applicablelaws and rules make closure the most expensive.

. The value of on site recyclables was not considered or used toreduce the cost estimate of closure.

. Salvage value from the sale of facility structures, equipment orother assets associated with the facility were not used to reduce thecost estimate of closure.

o A contingency in the amount of 10% of the total itemized costs wasincluded.

The financial assurance plan will include a letter of credit and standby trustagreement in a form previously accepted by the NHDES. Followingapproval of the proposed permit application, the closure cost estimate willbe updated on an annual basis, consistent with current New HampshireSolid Waste Rules.

Sofg

Page 37: Created Date: 7/29/2014 8:57:54 AM

Ruggiero Processing FacilityP.O. Box 434Saxtons River. VT 05154

Closure PlanRevised 711012014

DES-SW-SP-12-001

Appendix A to this closure plan presents the Standby Trust Agreementand closure cost estimate prepared for the RUGGIERO PROCESSINGFACILITY.

Appendix A: Financial Assurance Plan and Closure Cost Estimate

Page 38: Created Date: 7/29/2014 8:57:54 AM

Cost Estimate Form for Closure of Sol¡d Wa )ollection/Storage/Transfer Fac¡l¡tyStaie of New Hampshire

Facil¡ty Name: Ruggìero Processing Fac¡l¡ty, LLC Departrnent oi Environmental SewìcesAddress: PO Box 434 Waste Management Dìvision

Saxtons River, vT 05157 29 Hazen Drive, pO Box 95 Concord, NH 03302_OO9S(603)271_2925 FM (603) 271-2456

DES Perm¡t #:

' Note: The combioed Quantity of SPR and Non-SPR must equal the maximum permitted storage cãpacity allowed .

acceptance by a market that will use the materialfor the produciion of certìfìed waste derived products.

Date: May 19 2011. revÌsed July 10,2014

P:\pròject\K1998 Ruggiero Rubbish Removal\Docs\closu.ecostest.l407.xls