JRA1 progress
PSC07 Meeting, Žabljak, 22-23 January 2010
The SEE-GRID-SCI initiative is co-funded by the European Commission under the FP7 Research Infrastructures contract no. 211338
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 2
Deliverables
Three JRA1 deliverables produced DJRA1.1 - Grid application requirements and commonalities
assessment M06, 7 PM, UoB-RCUB, Editor: B.M.
DJRA1.2 - Application-specific monitoring and control tools design
M08, 12 PM, IPP, Editor: E.A. DJRA1.3 - Application services design report
M12, 10 PM, UoB-RCUB, Editor: B.M. DJRA1.4 - Application services implementation and
deployment report M22, 30 PM, UoB-RCUB, Editor: B.M.
DJRA1.5 - Assessment of operational tools developed M23, JRA1 28,5 PM, ICI, Editor: A.S.
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 3
Milestones
MJRA1.1 - Baseline analysis of operational tools M03, IPP: wiki, informal report
MJRA1.2 - Application commonalities assessed and areas of development identified M06, UoB-RCUB: DJRA1.1
MJRA1.3 - Operational tools implemented and running M16, IPP: wiki, informal report 5 in production, Logwatch-G and AMS in beta
MJRA1.4 - Selected application services implemented and deployed M24 Demonstration at review
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 4
Ongoing Developments and Metrics (PSC06 -> PSC07)
11 AS (7 major, 3 pre-existing as prototypes, 1 small effort with some initial interest) Described in DJRA1.1, DJRA1.3 and DJRA1.4
7 OT Described in DJRA1.2 and DJRA1.5
Black: As in DoWGreen: Achieved
M0 M12 M16 M19 M22 M24
MTJRA1.1AS developed
0/3 preexisting
2/4 production + 4 alpha/beta
6+5 7+4 8+3->1 α
6
MTJRA1.2OT developed
0/0 2/4 production + 2 alpha
5+2 6+1 7+0 4
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 5
Application Services(PSC06 -> PSC07)
Name Status Availability datePartners
SEE-GRID File Management Java API Production/stable Available UOBData Management Web Portal Production/stable Available UOBEvent Logger Production/stable October 08 UOB
Work BinderProduction/live -> Production/stable
October 08 UOB
SDS (Seismic Data Server) Applications Service
Beta -> Production/live
January 09
ULAKBIM TUBITAK
User Level Monitoring Tool Beta
Since beginning of 09Production version in second half of 09
UKIM
Common Workflow Repository Extension of P-GRADE Portal
Production/live -> Production/stable
May 09 SZTAKI
Environment oriented Satellite Data Processing Platform
Production/live1. October 09 (Phase 1)30. March 10 (Final)
UTCN
Mathematical Expressions Web Service Production/live June 09 ETFBG
Rendering Application Service M-PSC06Alpha ->Beta
July 09 FGA
Advanced-Workflow Development Tool and Orchestration Service
Alpha September 09 UKIM
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 6
Operational Tools(PSC06 -> PSC07)
Name Status Availability date Partners
JTS, Job Track ServiceM-PSC06, M-PSC07
Production/live February 09 IPP-BAS/UKIM
BBmSAM ExtensionsM-PSC06
Production/live March 09 UoBL
Grid Site Software Vulnerability Analyzer
Production/live-> Stable
March 09 SZTAKI
No Mercy Trouble Ticketing System M-PSC06
Production/live May 09 ICI
User/application specific grid infrastructure monitoring extension
Production/live-> Stable
OperationalRelease in July 09
SZTAKI
Logwatch Plug-ins for Grid Services M-PSC06
Beta ->Prod/stable
September 09 RBI
Alert Messaging ServiceBeta ->Production/live
September 09 UoB, IPP/UoBL/ICI
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 7
Status (OT + AS)
Status
M16
M16
M16
M16
M19
M19
M19
M19
M22
M22
M22
M22
0
2
4
6
8
10
12
Alpha Beta Production/live Production/stable
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 8
Internal JRA1 MetricsMeasure and compare the progress of AS & OT
Current status (only one of offered values, maximum is 8 points): 1 - Planning - Conceptual description, possibly with initial functional specification, or architectural
description 3 - Development - in progress, no working version available 5 - Alpha - working version exists, available only to developers 6 - Beta - working version exists, available to users 7 - Production/live - released, open to adding new features and bug-fixes 8 - Production/stable - released, developers still work on bug-fixes but it is closed for new features 7 - Production/closed - final version released, development closed NaN - Abandoned/Inactive - project abandoned before being released to production
Usage (additive for each named usage, up to 6 points): 2 – per each application currently using an application service (AS only) 1 - per each site having tool deployed (if applicable, OT only) or 1 - per each user (e.g. grid site administrator) using it in last 3 months (for OT only)
Presentation (only one of offered values, maximum is 6 points): 0 - No presentation or outdated presentation 2 - Up-to-date brief presentation (based on JRA1 presentation template) available (not more than 3 months
old) 4 - Up-to-date detailed presentation available (not more than 3 months old) 6 - Detailed presentation available with usage or performance analysis and live or recorded demo
Publications (additive 0.5 for each, up to 6 points)Visibility towards wider community (additive for each fulfilled indicator, but up to maximally 8 points)
1 - Software license defined and declared 1 - Introductory web site or Wiki with basic data and functional overview 2 - Architectural description available, online or within the corresponding JRA1-related project deliverable 2 – User documentation available (preferably online) fully covering typical usage, including deployment, if
applicable 1 - Source code available publicly or to all eligible users (in accordance with license), e.g. via download. 1 - Source code repository with version control available publicly or to eligible users
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 9
Visibility towards wider community
Visibility
0
2
4
6
8
10
12
14
16
18
Licensedefined and
declared
Basic site orWiki
Architecturaldescription
Userdocumentation
available
Source codeavailable
Source coderepository
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 10
JRA Metrics Reporting
Did not respond by the start of PSC06 BBmSAMeX (Mihajlo) JTS (Emanouil/Dimitar) Logwatch-G (Valentin) NMTT (Alex) RAS (Davor/Mirsad)
AWT added in an APExpected to provide an overview report at PSC07!
JRA1 Wiki has been greatly improved – also visible in metrics 51 edit since PSC06
JTS was late in reporting for PSC07 (again)50 conference and publication references reportedIn 2 cases there is a slight regression due to outdated presentations
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 12
Access to JRA1 Developments
http://wiki.egee-see.org/index.php/JRA1_CommonalitiesSignificant progress since PSC06: 51 editsMissing summary BBmSAMeX JTS NMTT ESIP-P MEWS
Issues persist Missing summaries Resource links Missing publications Collaborations (applications etc.)
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 14
Per-application conclussions
In good standing AMS, DM-Web, Event Logger, FM-J-API, Work Binder, CWRE,
USGIME, GSSVA, SDSAS, BBmSAMeX, ESIP Platform, Logwatch-G, JTS
Need to improve metrics RAS, MEWS, NMTT, AWT, ULMON
Need to improve usage AMS, USGIME
Need to improve presentation (PPT and Web/Wiki) Event Logger, FM-J-API, Work Binder, SDSAS, ESIP Platform,
Logwatch-GOK, but should improve visibility towards wider community GSSVA, JTS
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 18
Dissemination and Plans
EGEE UF5 JRA1 umbrella presentation at EGEE UF5 in Uppsala, Sweden, April 12-
15 by Anastas Mišev
Possible external verification: should advertise our software and collaborate with other related projects and user communities Information exchange (and possible collaboration) with Grid
Observatory – more details at EGEE UF5 Work Binder and ESIP-P made submissions to RESPECT program
Focus on (unchanged bullets!) Improvement of existing documentation, installation and user
documentation Making both code and packaged (installable) software available Start promotion of developments when they reach adequate level of
maturity
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 23
Source code availability and repository usage
Source and download 11Source only 2Download 2In metrics, 9 confirmed usage of a repositoryNo source or download links for BBmSAM, JTS, RAS
Should provide at least source code, if OK with licensingEGEE-SEE/SEE-GRID-SCI SVN-Trac Repository is available, anonymous R/O access also worksDownload of binaries is a nice commodity
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 24
Ongoing issues
Final push for usage by applications AMS - NMTT? BBmSAM – applications? Alignment with application commitments
Usage of sites/admins od OTs E.g.Logwatch-G looks rather handy, Valentin is a bit shy in
promotionMissing user documentation RAS, GSSVA, AWT, JTS
AWT still alpha!
Address reviewer OT recommendations in DJRA1.5 (there is also an analogy for AS in DJRA1.4)
SEE-GRID-SCI PSC07 Meeting, Žabljak, 22-23 January 2010 25
Actions to be Taken
One slide each AS/OT for EGEE UF Contributions to DJRA1.5Wiki, wiki wiki DJRA1.4 helped AS DJRA1.5 for OT User documentation (4 missing) At least basic installation instructions, as done for RESPECT
Make at least source code available
Final metrics report at M24