wp 8 life cycle assessment of cost, sustainability, safety and aesthetics
DESCRIPTION
WP 8 Life cycle assessment of cost, sustainability, safety and aesthetics. Participants: CTU | DTI | ELC | PD | SUP | GS | DTP| DRA | UNC | GR . WP8: Life cycle assesment of cost, sustainability, safety and aesthetics. Research Partners : DTI, CTU - PowerPoint PPT PresentationTRANSCRIPT
WP 8Life cycle assessment of cost,
sustainability, safety and aesthetics
Participants: CTU | DTI | ELC | PD | SUP | GS | DTP| DRA | UNC | GR
WP8: Life cycle assesment of cost, sustainability, safety and aesthetics
Research Partners: DTI, CTU
Industrial Partners: PD, SUP, GS, DTP, GR, DRA, UNC, ELC
Workpackage Objective: To assess the TailorCrete concept in the life cycle regarding cost, sustainability, safety and aesthetics. The main objective is to compare TailorCrete to the traditional concept.
Tasks
Task 8.1: Life cycle costing DRA 60% Task 8.2: Life cycle environmental impacts DTI 60% Task 8.3: Safety in the life cycle CTU 75% Task 8.4: Aesthetics UNI 50% Task 8.5: Overall assessment CTU 20%
Deliverables
D8.1: Results of life cycle cost analysis M42 Not Complete D8.2: Results of life cycle screening regarding sustainabilityM42 Not Complete D8.3: Results of assessment of safety M42 Not Complete D8.4: Results of aesthetic assessment M45 Not Complete D8.5: Summary report on life cycle assessment M48 Not Complete
WP8 Structure and Progress Update
Life‐Cycle phases
– Pre‐construction phase – design– Raw material production– Construction– Operation and use, maintenance– Demolition
WP8: Life cycle assesment of cost, sustainability, safety and aesthetics
Construction
Form
wor
k
WP8: Life cycle assesment of cost, sustainability, safety and aesthetics
• Such evaluation is a very complex task– Some tasks need not to be analyzed, as their
impacts/costs are approximately the same in both approaches (design, demolition)
– The focus is on differences between traditional and TailorCrete approaches
WP8: Life cycle assesment of cost, sustainability, safety and aesthetics
Task objective: To compare costs between the traditional process and the TC for a specific construction project.
Representative structure (ML 8.1)Benidorm Wall Particular section Extrapolated drawings
T8.1 Life Cycle Cost
• Traditional and TC processes: construction phase decomposition • Identification of partners to provide data.• Continuous process to gather information of the construction process in
terms of costs, resources, etc. • Identification of tasks which do not need cost analyzed since they cost the
same (or with negligible differences) both in the traditional process or in the TC process.
T8.1 Life Cycle Cost
Resources needed for a 50m section of the wall
Nº OPERATIONS Unit measured
Unit number
Minimum work team
min.crane/unit
min.man/ unit
Total min.cran
e
Total min.ma
n
1
DEM
OLD
ING
Remove shoring and tirants tirants 340 2 2,6 898
2 Remove formwork blocking systemsunion 160 1 2,0 320
3 Remove compensations module 40 2 24,0 960
4 Modules separation module 40 2 20,0 40,0 800 1.600
5 Negatives recovery negative 0 2 24,0 0
6Cleaning and release agent application on formworks m2 450 1 1,0 432
7
FORM
WO
RK
PLAC
EMEN
T Modules layout def inition module 40 2 28,0 1.120
8Placement of outer side of formwork (i/shoring) module 20 3 40,0 120,0 800 2.400
9Layout def inition, negatives placement negative 0 2 60,0 0
10
REIN
FORC
EMEN
T PL
ACEM
ENT Supply and placement of
reinforcement panels panel 110 3 8,0 24,0 880 2.640
11Assembly of reinforcement panels and overlappings panel 110 1 1,5 165
12
FORM
WO
RK P
LACE
MEN
T AN
D CA
STIN
G
Placement of formwork inner side module 20 3 35,0 105,0 700 2.100
13 Compensation pieces placement module 40 2 20,0 800
14 Tirants placing and assembly tirants 340 2 3,0 1.020
15 Tirants adjustment tirants 340 2 2,0 680
16 Modules exact placing and levelling module 40 3 75,0 3.000
17 Concrete level marking module 40 2 20,0 800
18 Supplies ( miscellaneous) viajes 10 3 1,5 4,5 15 45
19 Casting (40,5 m3) m3 41 5 15,0 608
20 Topographyc check module 40 3 45,0 1.800Total formwork 1.515 18.582Total reinforcement 800 2.805
TOTAL GENERAL 2.315 21.387
T8.1 Life Cycle Cost
• Traditional and TC processes: construction phase decomposition • Identification of partners to provide data.• Continuous process to gather information of the construction process in
terms of costs, resources, etc. • Identification of tasks which do not need cost analyzed since they cost the
same (or with negligible differences) both in the traditional process or in the TC process.
Task objective: To asses sustainability of TailorCrete concept, evaluate product’s energy use, and environmental carbon , water, and waste footprints.
• The same representative considered: Section of Benidorm wall • Prepared extensive LCA data sheet for the partners to fill out.• Continuous process to gather information of the construction process of the Benidorm
Wall (CAD files, Costs, Materials, Resources and construction processes followed).• GaBi software evaluated, facilitating investigation and comparison of environmental
impacts of a process, material or building work. • LCA Database with the cost, energy and environmental impact data
T8.2 Life Cycle Analysis
Task objective: To make sure that TC concept will not worsen existing safety concerns. Existing safety issues should be improved, if possible.
• Developed material data sheets and safety questionnaire• The open literature and project materials reviewed (DLs, Reports)• Currently data analysis under progress to identify possible safety issues and
to propose possible solutions.
T8.3 Safety in the life cycle
• Material data sheet• Document with information on the potential hazards (health, fire,
reactivity, and environmental) of any material• Including description on composition, handling , and work safety of the
product
• Example: Wax• Not a new material, but its processing requires melting -> possible
risk for workers -> protective gear recommended.
The electronic version of this questionnaire can be downloaded from http://mech.fsv.cvut.cz/TC
T8.3 Safety in the life cycle
• Safety questionnaire– Structured according to individual life cycle phases – Focused on identification of new safety issues during individual phases. – Recommendations to how possible or existing safety problems can be eliminated.– Collected results (6 partners contributed)
Example: Fibers – Service life: -> improvement of safety (improved ductility - earthquakes, polypropylene fibers
- spalling prevention)– Production: need for quality control (dosage) -> solved for steel fibers, still open for
polypropylene
T8.3 Safety in the life cycle
The electronic version of this questionnaire can be downloaded from http://mech.fsv.cvut.cz/TC
Task objective: To assess the aesthetic factors (smoothness, texture, surface deterioration) using accelerated tests• Accelerated testing allows to simulate in a short period time the expected performance
of cement specimens exposed to different environmental conditions.• 11 samples for accelerated aesthetic evaluation have been received from project
partners• Concrete tiles of eleven different conventional or SCC recipes have been casted
following the same procedure in different laboratories with similar hydration time• Carried out colour measurements during a preliminary conditioning period
T8.4 Aesthetic evaluation
Due to delays in delivery of some samples, the completion of the accelerated ageing tests will have been postponed 2 months
• A draft of DL8.4 will be prepared for 31st of January 2013 with the preliminary results and conclusions from the accelerated ageing tests.
• The final DL8.4 will be submitted by 1st of April 2013 and uploaded to ECAS.
T8.4 Accelerated testing
WP8 Future Planning
Tasks 8.1 and 8.2: (LCA+LCC)
1. Considered postponement of DL8.1 and DL8.2 to perform LCA and LCC directly on demonstrator project.
1. Higher impact to project2. Results more valuable and solid
Task 8.3: (Safety)• Final communication with partners to propose solution on how to improve
identified issues• DL 8.3 will be on time.
Task 8.4: (Aesthetics evaluation)• Accelerated testing of received samples and their evaluation in progress.