why hvdc - r2 - usaid sari/energy integration · why hvdc? page 1 23.08.2011 et ... conventional ac...
TRANSCRIPT
Why HVDC? y
Page 1 23.08.2011 ET-PS Energy Transmission
World Power ScenarioWorld Power Scenario
• World wide electrical power consumption projected to increase by >70% by2030 investments in power generation
• Tendency to a global energy market need of national and internationalgrid interconnectionsgrid interconnections
• Generation and consumption centers separated by long distances Needto transfer power over long distances
Page 2 23.08.2011 ET-PS Energy Transmission
Issues concerning Transmission SystemsIssues concerning Transmission SystemsIssues concerning Transmission Systems Issues concerning Transmission Systems
Utilization of existing resources and systems to the maximum extent
Transmission of bulk power over long distances efficiently
Severe Right of Way constraints
Uncertainty in Generation Uncertainty in Generation
Control of flow of power
Stability Stability
Page 3 23.08.2011 ET-PS Energy Transmission
Wh t’ d d?Wh t’ d d?What’s needed?What’s needed?
Option of up-gradation / allow implementation in stages
Transfer of allocated power / long-term contractual requirement
Should have margin for transfer of operational surplus in addition to committed powerp
Meet system requirements – active and reactive power following variations in load demand and contingencies
High Availability & Reliability
Low cost to consumers
Page 4 23.08.2011 ET-PS Energy Transmission
SMART Transmission – Siemens WaySMART Transmission – Siemens Way
Conventional AC Transmission HVDC Transmission
Siemens InnovationPresent scenario
For Bulk Power transfer over long distances – AC not an efficient solution
• Reliable means of bulk power transfer
• Lower transmission losses 5% 2 000 k
Bhiwadi
RajasthanBalliaMohindergarh
• Degradation of capacity in AC lines with increasing lengths
- 5% over 2,000 km
• Flexibility to enhance the transfer capacity
• Fewer lines with lesser
Talchar
(Orissa)
UP
Mundra
Gujarat
Haryana
• Reactive power management & Losses - a major issue
Right-of-Way
• “SMART GRID” performance features
• More economical
Kolar
Karnataka
Hi h i t f l d & Ri ht f
One of the Worlds largest link
• More economical
2500MW,1400 km-long HVDC link from Talchar to Kolar –Executed by Siemens 3 months ahead of schedule
• Higher requirement of land & Right-of-Way
• Several parallel lines to be used to transfer high power
Page 5 23.08.2011 ET-PS Energy Transmission 800kV AC
85m
ahead of schedule
Other 2x 2500MW HVDC projects–Under execution by Siemens
Technology OptionsTechnology Options
Use of Compact Lines / Multi-Circuit lines Use of Compact Lines / Multi Circuit lines.
Use of HVDC/multi-terminal HVDC systems to build ysystems in phases.
Use of Voltage Source Converter systems.
Re conductoring of existing lines without outages Re-conductoring of existing lines without outages.
Page 6 23.08.2011 ET-PS Energy Transmission
HVDC Applications HVDC is the unique solution to interconnect asynchronous systems, e.g. different
grid frequencies.Solution: HVDC Back-to-Back
HVDC Applications
Up to 1000 MW
Back-to-Back Station
AC AC50 Hz 60 Hz
HVDC represents the most economical solution for distances greater than approx. 600 km / 400milesSolution: HVDC Long Distance
Up to 3000 MW
Long Distance Transmission
AC ACDC line
HVDC is an alternative for submarine transmission. Economical even for shorter distances such as a few 10 km / milesSolution: HVDC Cable
Page 7 23.08.2011 ET-PS Energy Transmission
Up to 800 MW
Long Submarine Transmission
AC ACDC cable
Benefits: HVDCBenefits: HVDCBenefits
DC line has lower construction costs than an AC lineFor equivalent transmission capacity
A double HVAC 3-Ø circuit with 6 conductors required to get reliability of a 2-pole DC link
DC losses are less compared to ACFor the same conductor
DC link is asynchronousDC link is asynchronousCan be used to interconnect grids with different frequencies
HVDC systems are more reliableCannot be overloaded by outage of parallel AC linesy g p
Right of way for DC line is 41% lowerCompared to AC Line designed to carry 2,000 MW
C S C
Page 8 23.08.2011 ET-PS Energy Transmission
HVDC systems do not add to Short Circuit Power requirements Beneficial, if the installed HV equipments are at / close to their limit Short Circuit capability
Benefits: HVDC (contd )Benefits: HVDC (contd..)
Benefits
DC systems are modularDC systems are modularcan be built in stages if the generation is being added over a longer period
HVDC system along with the existing AC system would enhance grid security and system stabilitysecurity and system stability
Overload and power modulation features of HVDC could be used to cater to grid emergencies in case of outage of AC lines
Page 9 23.08.2011 ET-PS Energy Transmission
AC vs. DC: Loss EvaluationAC vs. DC: Loss Evaluation
Line Length – 970 Km Load: 2500 MW Avg. Loading Factor: 90%
AC System: 1 no. 400 kV D/C Quad Moose Configuration + 1 no. 400 kV S/C Quad Moose
ConfigurationDC System: ±500kV HVDC
Resistance of quad moose conductor: 0 056/4 = Resistance of quad bersimis conductor: 0 042/4 =Resistance of quad moose conductor: 0.056/4 0.014 Ω/km at 20°C
Resistance of quad bersimis conductor: 0.042/4 0.011 Ω/km at 20°C
Resistance at 75°C and for line length of 970 Km: 16.57 Ω
Resistance at 75°C and for line length of 970 Km: 10.67 Ω
Power in each circuit: 2250/3= 750 MW Power = 2250 MW
Current per phase: 750/1.732x400x0.9 = 1203 A Current per pole: 2250/2x500 = 2250 A
Losses for AC configuration: 3x3x12032 x16.57=216 MW
Losses for DC line configuration: 2x22502 x10.67=108 MW + Losses at HVDC terminals: 27.4 MW
(from guaranteed loss figure)
Page 10 23.08.2011 ET-PS Energy Transmission
Total losses for AC configuration: 216 MW Total losses for DC configuration: 135.4 MW
Saving of 80.6 MW
Right of Way Comparisons
Typical tower structures and rights-of-way. Capacity: 2000 MWTypical tower structures and rights-of-way. Capacity: 2000 MW
Right of Way Comparisons
yp g y p yyp g y p y
± 500 KV DC 800 KV AC 2 X 500 KV AC
Page 11 23.08.2011 ET-PS Energy Transmission
50 m 85 m 100 m
Cost comparison of AC and DC transmission
Cost of AC Line
Cost comparison of AC and DC transmission
CostBreak even distance Cost of DC Line
Cost of DC terminal
Cost of AC terminal
Distance in km 500 – 700 km
Page 12 23.08.2011 ET-PS Energy Transmission