weekly progress summary

Upload: kumaarrr

Post on 08-Mar-2016

4 views

Category:

Documents


0 download

DESCRIPTION

Work Progress

TRANSCRIPT

  • TASK

    Page 1

    WEEKLY PROGRESS SUMMARY FOR MECHANICAL WORKS AS ON 21/05/2014Project : LULU BOWSHER PHASE II

    Activity ID Activity Name (*)Start (*)Finish

    BASEMENT FLOOR

    FBZA1090 INSTALLATION AND TESTING OF FIRE FIGHTING PIPES 4/16/20129/17/2012

    FBZA1130 INSTALLATION OF UPRIGHT SPRINKLERS IN PARKING AREA 11/24/2013 12/7/2013 FBZA1120 FIRE HOSE REEL CABINET INSTALLATION WORKS 5/16/2013 8/24/2013

    FBMR1040 INSTALLATION AND TESTING OF FIRE FIGHTING PIPES IN BASEMENT MECHANICAL ROOM 10/12/2012 22/10/2012

    FBMR1050 FIXING OF FIRE FIGHTING VALVES AND ACCESSORIES IN BASEMENT MECHANICAL ROOM 10/23/2013 11/3/2013

    FBMR1060 INSTALLATION OF FIRE GRP WATER TANKS IN BASEMENT MECHANICAL ROOM 9/30/2013 10/22/2013

    FBMR1070 FIXING OF PUMPS IN BASEMENT MECHANICAL ROOM 10/6/2013 10/22/2013 HBZA1130 FIXING OF HVAC VALVES & ACCESSORIES IN BASEMENT 5/20/2013 9/16/2013 HBZA1120 HVAC PIPE INSULATION WORKS IN BASEMENT 5/7/2013 7/22/2013 HBZA1140 FIXING OF FANS & FAN COIL UNITS IN BASEMENT 10/22/2013 11/18/2013 HBZA1150 FIXING OF AIR OUTLETS IN BASEMENT 9/17/2013 10/21/2013 HBZA1006 PRE INSULATED DUCT INSTALLATION WORKS IN BASEMENT 8/15/2012 9/23/2012HBZA1016 FIXING OF HVAC DUCT ACCESSORIES(DAMPERS) IN BASEMENT 10/1/2013 10/8/2013 HBZA1050 FIXING OF FANS IN BASEMENT BETWEEN GRIDS B3/14 - 18/19 11/19/2013 12/5/2013 HBZA1060 FIXING OF FANS IN BASEMENT BETWEEN GRIDS B3/14 - 18/29 11/19/2013 12/5/2013

    PBMR1040 LAYING OF EXPOSED WATER SUPPLY PIPES IN BASEMENT MECHANICAL ROOM 5/14/201210/31/2012

    PBMR1060 INSTALLATION OF BOOSTER PUMPS IN BASEMENT MECHANICAL ROOM 10/23/2013 10/30/2013 PBMR1050 INSTALLATION OF COLD WATER TANKS IN BASEMENT MECHANICAL ROOM 9/30/2013 10/22/2013

  • TASK

    Page 2

    GROUND FLOOR FGZA1070 FIXING OF PENDENT SPRINKLERS IN GROUND FLOOR 12/15/2013 1/28/2014 FGZA1080 FIRE HOSE REEL CABINET FIXING WORKS IN GROUND FLOOR 6/6/2013 9/2/2013 FGZA1090 INSTALLATION OF FM-200 SYSTEMS IN GROUND FLOOR 1/29/2014 2/11/2014 HGZA1210 FIXING OF FANS & FAN COIL UNITS IN GROUND FLOOR 11/19/2013 1/2/2013 HGZA1190 FIXING OF AIR OUTLETS IN GROUND FLOOR 10/1/2013 11/4/2013

    PGZA1130 INSTALLATION OF DRAINAGE SUNDRIES & SANITARY FIXTURES IN GROUND FLOOR 7/18/2013 9/5/2013

    FIRST FLOORFFZA1070 FIXING OF PENDENT SPRINKLERS IN FIRST FLOOR 6/23/2013 9/18/2013 FFZA1080 FIRE HOSE REEL CABINET FIXING WORKS IN FIRST FLOOR 7/1/2013 7/24/2013 HFZA1120 PRE INSULATED DUCT WORKS IN FIRST FLOOR 11/6/2012 1/3/2013 HFZA1160 FIXING DUCT ACCESSORIES(DAMPERS) IN FIRST FLOOR 4/24/2013 5/25/2013 HFZA1210 FIXING OF FANS AND FAN COIL UNITS IN FIRST FLOOR 7/29/2013 9/8/2013 HFZA1200 FIXING OF AIR OUTLETS IN FIRST FLOOR 7/29/2013 9/8/2013 PFZA1100 WATER SUPPLY PIPES INSULATION WORKS IN FIRST FLOOR 6/13/2013 7/3/2013

    PFZA1130 INSTALLATION OF DRAINAGE SUNDRIES & SANITARY FIXTURES IN FIRST FLOOR 8/8/2013 9/4/2013

    SECOND FLOORSFZD1090 FIXING OF PENDENT SPRINKLERS IN SECOND FLOOR 10/9/2013 11/23/2013 SFZD1070 FIRE HOSE REEL CABINET FIXING WORKS IN SECOND FLOOR 7/25/2013 9/21/2013 HSZB1160 FIXING HVAC VALVES & ACCESSORIES IN SECOND FLOOR 6/30/2013 10/3/2013 HSZB1120 PRE INSULATED DUCT INSTALLATION WORKS IN SECOND FLOOR 3/24/2013 8/11/2013 HSZB1130 FIXING DUCT ACCESSORIES(DAMPERS) IN SECOND FLOOR 6/10/2013 9/22/2013 HSZB1190 FIXING FANS AND FAN COIL UNITS IN SECOND FLOOR 11/19/2013 1/6/2014HSZB1180 FIXING AIR OUTLETS IN SECOND FLOOR 10/29/2013 11/21/2013 HSTT1000 LAYING OF HVAC PIPES IN 2ND FLOOR TECHNICAL TERRACE 10/19/2013 11/10/2013 HSTT1010 FIXING OF HVAC VALVES & ACCESSORIES IN 2ND FLOOR TECHNICAL TERRACE 11/11/2013 11/27/2013

  • TASK

    Page 3

    HSTT1020 HVAC PIPE INSULATION WORKS IN 2ND FLOOR TECHNICAL TERRACE 10/29/2013 11/20/2013 HSTT1030 LAYING OF CONDENSATE DRAIN PIPES IN 2ND FLOOR TECHNICAL TERRACE 8/6/2013 8/12/2013

    HSTT1040 CONDENSATE DRAIN PIPE INSULATION WORKS IN 2ND FLOOR TECHNICAL TERRACE 10/26/2013 10/28/2013

    HSTT1050 GI DUCT WORKS IN 2ND FLOOR TECHNICAL TERRACE 10/19/2013 11/10/2013 HSTT1060 FIXING DUCT ACCESSORIES IN 2ND FLOOR TECHNICAL TERRACE 11/11/2013 11/19/2013 HSTT1080 FIXING FAN COIL UNITS IN 2ND FLOOR TECHNICAL TERRACE 10/22/2013 10/28/2013 HSTT1090 FIXING AIR HANDLING UNITS IN 2ND FLOOR TECHNICAL TERRACE 10/22/2013 11/7/2013 HSTT1100 FIXING FANS IN 2ND FLOOR TECHNICAL TERRACE 10/29/2013 11/14/2013

    PSZA1130 INSTALLATION OF DRAINAGE SUNDRIES & SANITARY FIXTURES IN SECOND FLOOR 7/1/2013 11/17/2013

    THIRD FLOOR FTZB1050 FIXING OF PENDENT SPRINKLERS IN THIRD FLOOR 10/13/2013 11/18/2013 FTZB1080 FIRE HOSE REEL CABINET FIXING WORKS IN THIRD FLOOR 8/12/2013 8/8/2013 HTZB1070 PRE INSULATED DUCT INSTALLATION WORKS IN THIRD FLOOR 5/13/2013 9/3/2013 HTZB1100 FIXING DUCT ACCESSORIES(DAMPERS) IN THIRD FLOOR 7/24/2013 10/8/2013 HTZB1160 FIXING FANS & FAN COIL UNITS IN THIRD FLOOR 11/19/2013 1/6/2014 HTZB1170 FIXING AIR OUTLETS IN THIRD FLOOR 10/29/2013 11/26/2013 PTZA1060 LAYING OF EXPOSED WATER SUPPLY PIPES IN THIRD FLOOR 5/12/2013 8/12/2013PTZA1070 WATER SUPPLY PIPES INSULATION WORKS IN THIRD FLOOR 7/24/2013 8/28/2013 PTZA1080 FIXING OF PLUMBING VALVES AND ACCESSORIES IN THIRD FLOOR 7/15/2013 9/1/2013 PTZA1090 INSTALLATION OF DRAINAGE SUNDRIES & SANITARY FIXTURES IN THIRD FLOOR 7/1/2013 11/24/2013

    Roof FloorHTRF1000 LAYING OF HVAC PIPES IN ROOF FLOOR 9/25/2013 10/17/2013 HTRF1010 FIXING HVAC VALVES & ACCESSORIES IN ROOF FLOOR 11/12/2013 11/28/2013 HTRF1020 HVAC PIPE INSULATION WORKS IN ROOF FLOOR 10/19/2013 10/26/2013 HTRF1030 LAYING OF CONDENSATE DRAIN PIPES IN ROOF FLOOR 11/5/2013 11/14/2013 HTRF1040 CONDENSATE DRAIN PIPE INSULATION WORKS IN ROOF FLOOR 11/12/2013 11/14/2013

  • TASK

    Page 4

    HTRF1050 PRE INSULATED WORKS IN ROOF FLOOR 9/22/2013 10/15/2013 HTRF1060 FIXING DUCT ACCESSORIES IN ROOF FLOOR 10/16/2013 10/26/2013 HTRF1080 FIXING FAN COIL UNITS IN ROOF FLOOR 10/22/2013 10/28/2013 HTRF1090 FIXING AIR HANDLING UNITS IN ROOF FLOOR 10/29/2013 11/9/2013 HTRF1100 FIXING FANS IN ROOF FLOOR 10/29/2013 11/14/2013 PRFA1000 LAYING OF EXPOSED DRAINAGE & VENT PIPES IN ROOF FLOOR 11/5/2013 11/11/2013 PRFA1010 LAYING OF EXPOSED WATER SUPPLY PIPES IN ROOF FLOOR 11/12/2013 11/18/2013 PRFA1020 WATER SUPPLY PIPES INSULATION WORKS IN ROOF FLOOR 11/19/2013 11/25/2013 PRFA1030 FIXING OF PLUMBING VALVES & ACCESSORIES IN ROOF FLOOR 11/26/2013 12/2/2013 PRFA1040 INSTALLATION OF DRAINAGE SUNDRIES IN ROOF FLOOR 12/3/2013 12/9/2013

  • TASK

    Page 5

    REMARKS

    100% 97%

    100.00% 95%100% 85%

    100% 0% Suction and delivery headersWill be shifted from stage I pump room

    100% 0%

    100.00% 50%

    100.00% 0% Has to be shifted from stage 100% 100%

    100.00% 95%100.00% 96.00%100.00% 0%

    100% 95%100% 100%

    100.00% 80%100.00% 75%

    100% 95% testing balance

    100% 95% Pumps installed at site.100.00% 100%

    Planned Progress

    Actual Progress

    Lulu materials area and temperory pump room area balance.Lulu materials has to be removed

  • TASK

    Page 6

    100.00% 10% Toilet sprinklers completed.False ceiling work on hold100% 60% Fire Cabinet Recess block work balance0.00% 20%

    100.00% 99%100% 0%

    100% 75% EWC installation finished.

    100.00% 40% Waitig for ceiling confirmation from LULU .100.00% 95%

    100% 99%100% 99%

    100.00% 70%100.00% 0%

    100% 100%

    100% 70%

    100.00% 15% toilets completed100.00% 100%100.00% 100%

    100% 94% Only branches balance100% 75% volume dampers balance

    100.00% 92%100.00% 0%100.00% 97% Ahu Connection and flushing progress100.00% 97%

    Sanitary Fixtures balance.After completion of all other works inside toilet to avoid material damage.

  • TASK

    Page 7

    100.00% 94%100.00% 0%

    100.00% 0%0.125

    100.00% 45%100% 38%

    100.00% 70%100.00% 99%100.00% 0%

    100.00% 70%

    100.00% 25%100.00% 99%

    100% 93.5%100.00% 75% volume dampers balance100.00% 38%100.00% 0%100.00% 100%100.00% 100%100.00% 100%100.00% 65%

    100% 93% Rerouting and rework for AHU shifting progress100.00% 92%

    100% 91%100% 0%

    100.00% 0%

  • TASK

    Page 8

    100% 0%100% 0%100% 0%100% 100%

    100.00% 25%100% 96%

    100.00% 0%100.00% 0%100.00% 0%100.00% 0%