vocational training project

Upload: vikalp321

Post on 30-Oct-2015

70 views

Category:

Documents


2 download

TRANSCRIPT

  • NTPC - FGUTPP

    MAY-JUNE

    2011

    Vocational Training Report

  • ii

    ACKNOWLEDGMENT

    I am very grateful and thankful to all those who were a

    part of this project and helped me towards its smooth

    and efficient completion. I feel especially thankful to Mr.Munish Jauhari,

    Mr.A.K.Sharma, Mr.M.Z.A.Siddique,Mr. Umashankar, Mr.Rakesh Kumar, Mr.

    Sameer Kashyap,Mr.Ranjeet, Mr. J.K. Sahu, Mr. K.M. Gupta, Mr. D.D. Singh,

    Mr. K.K. Singh and Mr. Sanjeet to name a few for their helpful contribution

    and knowledge without which my project would not be a reality.

  • iii

    INDEX

    Acknowledgement.ii

    List of figuresvi

    List of tablesvii

    I. About the company.............1

    A. Corporate Vision..1

    B. Core Values..1

    C. Evolution of NTPC..3

    D. NTPC Group4

    II. Introduction to FGUTPP5

    A. Location5

    B. Major Milestones..5

    C. Installed capacity..5

    D. Production Inputs.5

    E. Requirements6

    F. Cost of Generation6

    G. Environmental aspects6

    H. Layout..6

    I. Various Cycles in the plant.7

    i. Coal cycle...7

    ii. Water cycle.8

    iii. Steam cycle8

    III. Switchyard..9

    A. Circuit Breaker...9

    B. Lightening Arrester...11

    C. Earthing Switch12

    D. Bus Bar.13

    E. Capacitor Voltage Transformer13

    F. Wave Trap.14

    G. PLCC.14

  • iv

    H. Current Transformer.14

    I. Isolator..14

    J. Bay15

    IV. Generator..18

    A. Main Components..18

    B. Excitation system19

    C. Generator protection..19

    D. Generator cooling system..20

    E. Coolong specifications of turbogenerators21

    V. Transformers.22

    A. Transformer accessories.22

    B. Cooling of transformers.23

    C. Main transformers..25

    i. Generator transformers25

    ii. Station transformers.25

    iii. Unit auxiliary transformers..25

    iv. Neutral Grounding Transformer..25

    VI. DC system27

    A. Requirement of DC system27

    B. Description of battery.27

    C. Battery Charger..27

    D. Capacity test of battery..28

    VII. Switchgear..29

    A. L.T. switchgear..29

    B. H.T. switchgear...30

    VIII. Boiler..32

    IX. Electrostatic Precipitator (ESP)...34

    A. Working principle..34

    B. Description.34

    C. Parts of ESP34

    D. Electrical scheme of ESP36

    E. Variable frequency drive.36

    X. Coal Handling Plant.39

  • v

    A. Introduction39

    B. Properties of coal...39

    C. Coal Analysis.39

    D. Different methods of unloading the coal.39

    E. Various equipments used in CHP.40

    i. Marshalling Yard.40

    ii. Wagon Tripler.40

    iii. Paddle Feeder...41

    iv. Vibrating feeder41

    v. Transfer points.41

    vi. Flap gate42

    vii. Conveyors.42

    viii. Belt protection42

    ix. Primary crusher43

    x. Secondary crusher43

    xi. Cross belt magnetic separator..43

    xii. Metal detector..43

    xiii. Stacker reclaimer44

    xiv. Transfer towers..45

    xv. Tipper45

    xvi. Bunker.45

    F. Some Special motors of CHP.45

    G. Power and Distribution Diagram of CHP.46

    XI. Conclusion...47

    LIST OF FIGURES Pg No.

    Figure 1 NTPC generation growth 1

  • vi

    Figure 2 NTPC in power sector 2

    Figure 3 NTPC group 4

    Figure 4 Unit overview 7

    Figure 5 Steam flow 8

    Figure 6 SF6 Circuit Breaker 10

    Figure 7 Lightening Arrester 12

    Figure 8 Capacitor Voltage Transformer 13

    Figure 9 Single line diagram of switchyard 17

    Figure 10 Electrical System layout of stage III 31

    Figure 11 Water tube Boiler Schematic Layout 33

    Figure 12 Schematic Diagram of ESP 35

    Figure 13 Electrical scheme of VFD 37

    Figure 14 Two channel arrangement of synchronous motor 37

    Figure 15 Forward Conveyor 42

    Figure 16 Return Conveyor 42

    Figure 17 Power distribution diagram of CHP in stage I 46

    Figure 18 - Power distribution diagram of CHP in stage II 47

    LIST OF TABLES Pg No.

    Table I Specifications of Circuit Breakers 11

    Table II Specifications of earthing switch 12

    Table III Specifications of Turbo generators 19

    Table IV Specifications of GTs 25

    Table V Specifications of STs 26

    Table VI Specifications of UATs 26

    Table VII Specification of NGT 26

    Table VIII Specification of Synchronous Motor 38

  • 1

    I. ABOUT THE COMPANY

    A. Corporate Vision:

    A world class integrated power major, powering Indias growth, with increasing global

    presence

    B. Core Values:

    B-Business Ethics

    C-Customer Focus

    O-Organizational & Professional pride

    M-Mutual Respect and Trust

    I- Innovation & Speed

    T-Total quality for Excellence

    NTPC Limited is the largest thermal power generating company of India. A public sector

    company, it was incorporated in the year 1975 to accelerate power development in the

    country as a wholly owned company of the Government of India. At present,

    Government of India holds 89.5% of the total equity shares of the company and the

    balance 10.5% is held by FIIs, Domestic Banks, Public and others. Within a span of 31

    years, NTPC has emerged as a truly national power company, with power generating

    facilities in all the major regions of the country.

    Figure 1. NTPC generation growth

  • 2

    NTPCs core business is engineering, construction and operation of power

    generating plants. It also provides consultancy in the area of power plant constructions

    and power generation to companies in India and abroad. As on date the installed capacity

    of NTPC is 27,904 MW through its 15 coal based (22,895 MW), 7 gas based (3,955

    MW) and 4 Joint Venture Projects (1,054 MW). NTPC acquired 50% equity of the SAIL

    Power Supply Corporation Ltd. (SPSCL). This JV company operates the captive power

    plants of Durgapur (120 MW), Rourkela (120 MW) and Bhilai (74 MW). NTPC also has

    28.33% stake in Ratnagiri Gas & Power Private Limited (RGPPL) a joint venture

    company between NTPC, GAIL, Indian Financial Institutions and Maharashtra SEB

    Holding Co. Ltd.

    NTPCs share on 31 Mar 2007 in the total installed capacity of the country was

    20.18% and it contributed 28.50% of the total power generation of the country during

    2006-07.

    Figure 2. NTPC in power sector

  • 3

    C. Evolution of NTPC

    NTPC was set up in 1975 with 100% ownership by the

    Government of India. In the last 30 years, NTPC has grown

    into the largest power utility in India.

    In 1997, Government of India granted NTPC status of

    Navratna being one of the nine jewels of India, enhancing the

    powers to the Board of Directors.

    NTPC became a listed company with majority Government

    ownership of 89.5%. NTPC becomes third largest by Market

    Capitalisation of listed companies

    The company rechristened as NTPC Limited in line with its

    changing business portfolio and transform itself from a thermal

    power utility to an integrated power utility.

    NTPC Ltd. Has granted of Maharatna status by Govt. of India.

    NTPC Ltd. Has been ranked 7th

    great place to work in India by

    The great places to work institute INDIA and The Economic

    times.

    1975

    1997

    2005 TABLE IV

    Specificat

    ions of

    Turbo

    Generator

    s of stage

    I. (gen1,

    gen2)

    KVA Pf Stator

    Voltage

    (V)

    Stator

    Current

    (A)

    Rotor

    Voltage

    (V)

    Rotor

    Current

    (A)

    Rpm Hz Phase Coolant

    247000 0.85 15750 9050 310 2600 3000 50 3 Water

    (stator)&

    hydrogen

    (rotor)

    2004

    2010 TABLE IV

    Specificat

    ions of

    Turbo

    Generator

    s of stage

    I. (gen1,

    gen2)

    KVA Pf Stator

    Voltage

    (V)

    Stator

    Current

    (A)

    Rotor

    Voltage

    (V)

    Rotor

    Current

    (A)

    Rpm Hz Phase Coolant

    247000 0.85 15750 9050 310 2600 3000 50 3 Water

    (stator)&

    hydrogen

  • 4

    D. NTPC Group

    NTPC Limited

    Subsidiaries

    Joint Ventures

    Figure 3. NTPC Group

    NTPC Vidyut

    Vyapar

    Nigam Limited

    100%

    NTPC Electric

    Supply

    Co. Limited

    100%

    Kanti Bijlee

    Utpadan

    Nigam Limited

    64.57%

    NTPC Hydro

    Limited

    100%

    Nabinagar

    Power

    Generating

    Company

    Pvt.

    Limited/

    BF-NTPC

    Energy

    Systems

    Limited

    NTPC-Alstom

    Power

    Services Pvt.

    Limited/

    Utility

    Powertech

    Ltd. (UPL)

    50%

    TELK/ICV

    PL, NPEL

    44.7%

    NTPC-SAIL

    Power

    Company

    Pvt.

    Limited

    50%

    NTPC-SAIL

    Power

    Company

    Pvt.

    Limited

    50

    Ratnagiri

    Gas &

    Power

    Private Ltd

    29.65%

    Meja Urja

    Nigam

    Private

    Limited

    50%

    NTPC

    Tamilnadu

    Energy Co.

    Limited

    50%

    Aravali

    Power Co.

    Pvt. Ltd.

    50%

    NTPC-

    BHEL

    Power

    Projects

    Pvt.

    Limited/

    PTC India

    Limited

    8%

  • 5

    II. INTRODUCTION TO NTPC FEROZ GANDHI UNCHAHAR

    THERMAL POWER PROJECT (FGUTPP)

    A. Location

    Located on Lucknow Allahabad state highway

    35 Km from Raebareli

    80 Km from Allahabad

    120 Km from Lucknow

    B. Major Milestones

    Our late Prime Minister Smt. Indira Gandhi laid down the foundation stone on

    27TH

    June 1981.

    First two units of 210MW were commissioned on 21stNovember, 1988 and

    22nd

    March, 1989 by U.P. Rajya Vidyut Utpadan Nigam.

    Unchahar project was taken over by NTPC from UPSEB on 13th Feb,1992

    After take over of FGUTPP from UPRVUN to NTPC, unit-3 & unit-4 were

    commissioned on 27th

    January, 1999 and 22nd

    October, 1999

    Now third stage (unit-5) is of 1X 210 MW.

    C. Installed Capacity

    Stage I = 2 X 210 MW

    Stage II = 2 X 210 MW

    Stage III = 210 MW

    D. Production Inputs

    a. Coal Source

    Central Coal fields Ltd. ( CCL)

    Bharat Cooking Coal Ltd. (BCCL)

    b. Water Source

    Sharada Sahayak Canal (main)

    Dalmau Pump Canal ( from river Ganga)

  • 6

    E. Requirements

    Coal 140 tonnes / hr / unit

    Water 700 tonnes/ hr / unit

    F. Cost of Generation

    Rs. 2.40 / Kwh

    G. Environmental Aspects

    Water Polluton- Effluents from thermal discharges from condenser,wastes

    from coal handling plant, service areas,oil , DM plant, sanitary waste and

    effluents from ash pond will be neutralized before being discharged.

    Air Pollution- Particulate emission will be limited to 150 mg/Nm3 by

    installing high efficiency ESPs.

    H. Layout

    The main project consist of following areas :

    Main plant area consisting of chimney,ESP,Boiler, Control room, turbine,

    generator, transformers and switchyard

    Ash handling plant consisting of ash handling pump house, ash handling

    compressor house, control room, pipeline corridor and ash ponds

    Coal handling Plant consisting of track hopper,primary coal yard, primary

    crusher, secondary crusher, secondary coal yard, stacker reclaimer, wagon

    trippler and connected conveyors.

    Circulating water system consisting of CW pumps,associated pipelines and

    cooling towers.

    Water treatment plant consisting of chlorination plant, pre-treatment plant and

    De-mineralized water treatment plant.

  • 7

    Figure 4. Unit overview

    I. Various Cycles In The Thermal Plant

    i. Coal Cycle

    C.H.P Plant Bunker R.C Feeder pulverize mill Boiler section

    R.C. Feeder -It is induction motor driven device, which determine the Quantity of coal

    enter in to pulverize mill.

    Pulverize mill - Pulverization means exposing large surface area to the action of oxygen.

    Two types of mill are used in the plant.

    Ball mill - A ball mill operates normally under suction. A large drum partly filled

    with steel balls, is used in this mill. The drum is rotated slowly while coal is fed in to

    it. The ball pulverizes the coal by crushing. This type of mill is used in stage -1.

    Contact mill - This mill uses impact principle. All the grinding elements and the

    primary air fan is mounted on a single shaft. The flow of air carries coal to the

    primary stage where it is reduced to a fine granular state by impact with a series of

    hammers. This type of mill is used in stage-2.

  • 8

    ii. Water Cycle

    D.M. Plant Hot Well C.E.P. Pump Low Pressure heater 1,2,3Derater

    Boiler Feed pump High pressure Heater 5,6 Feed Regulating station Economizer

    Boiler Drum.

    Derater - Feed storage tank of water. To produce sufficient pressure before

    feeding to B.F.P. Filter the harmful chemicals.

    Feed Regulating Station - Control the quantity of water in to boiler drum.

    Economiser - Flue gases coming out of the boilers carry lot of heat. An

    economizer extracts a part of this heat from the flue gases and uses it for heat

    the feed water.

    Drafts System- In forced draft system the fan is installed near the base of the

    boiler furnace. This fan forces air through the furnace, economizer, air preheater

    and chimney.In an induced draft system, the fan is installed near the base of

    Chimney.

    iii. Steam Cycle

    Boiler drums Ring Header Boiler Drum (Steam chamber) Super Heater H.P.

    Turbine Reheater I. P. Turbine L.P. Turbine

    Boiler Drum - Boiler drum consist two chamber water chambers, steam

    chamber.Before entering in super heater the steam is going in to boiler drum,

    where the boiler drum filtered the moisture and stored in to water chamber.

    Super Heater - The function of super heater is to remove the last traces of

    moisture from the saturated steam leaving the water tube boiler. The temperature

    is approx 530C.

    Turbine -Steam turbine converts the heat energy in to mechanical energy and

    drives on initial and final heat content of the steam. Turbine having number of

    stage in which the pressure drops takes place.

    Figure 5. Steam flow

  • 9

    III. SWITCHYARD

    The switch yard is the places from where the electricity is send outside. We know that

    electrical energy cant be stored like cells, so what we generate should be consumed

    instantaneously. But as the load is not constants therefore we generate electricity

    according to need i.e. the generation depends upon load. It has both outdoor and indoor

    equipments.

    1. Outdoor Equipments

    Bus Bar

    Lightening Arrester

    Wave Trap

    Breaker

    Capacitor Voltage Transformer

    Earthing Rod

    Current Transformer

    Potential Transformer

    Isolators

    PLCC

    2. Indoor Equipments

    Relays

    Control Panels

    A. Circuit Breaker:

    The code for circuit breaker is 52. An electric power system needs some form of

    switchgear in order to operate it safely & efficiently under both normal and abnormal

    conditions.

    Circuit breaker is an arrangement by which we can break the circuit or flow of

    current. A circuit breaker in station serves the same purpose as switch but it has many

  • 10

    added and complex features. The basic construction of any circuit breaker requires the

    separation of contact in an insulating fluid that servers two functions:

    It extinguishes the arc drawn between the contacts when circuit breaker opens.

    It provides adequate insulation between the contacts and from each contact to

    earth.

    The insulating fluids commonly used in circuit breakers are:

    Compressed air

    Oil which produces hydrogen for arc excitation.

    Vacuum

    Sulphur hexafluorides (SF6 )

    There are two makes of Circuit Breakers used at NTPC Unchahar switchyard :

    i. SF6 Circuit Breaker manufactured by ALSTOM

    ii. Gas Circuit Breaker manufactured by CGL

    Figure 6. SF6 Circuit Breaker

  • 11

    TABLE I

    The specifications of the circuit breakers

    Specifications ALSTOM Circuit

    Breaker

    CGL Circuit

    Breaker

    Type

    Rated Voltage

    Rated Frequency

    Rated Normal Current

    Rated Closing Voltage

    Rated Opening Voltage

    Rated Gas Pressure

    Total weight with gas

    Gas Weight

    Rated Duration of short circuit current

    First pole to clear factor

    Rated operating pressure

    Rated Short-Circuit breaking current

    Rated Lightning impulse withstand

    voltage

    GL 314

    245 kV

    50 Hz

    1600/2500 A

    220 V DC

    220 V DC

    0.85 MPa (abs)

    3000 Kg

    23.5 Kg

    40 kA 3 secs

    1.3

    15 kg/cm2-g

    40 kA

    1050 kV (peak)

    200-SFM-40A

    245 kV

    50 Hz

    3150 A

    220 V DC

    220 V DC

    6 Kg/cm2-g(20 C)

    3900 Kg

    21 Kg

    40 kA 3 secs

    5

    15 kg/cm2-g

    40 kA

    1050 KV (peak)

    B. Lightening Arrester

    These are provided to combat the effect of over voltages and surges caused due to

    lighting strokes on the transmission lines. These are generally provided at the end near

    the instrument which we want to protect. The lightening arrestors provide an easy path to

    the surge current to the ground thereby not letting the equipments to fail.

    It saves the transformer and reactor from over voltage and over currents. We have

    to use the lightning arrester both in primary and secondary of transformer and in reactors.

    It has a round metal cap type structure on the top called CORONA RING, meant

    for providing corona losses.

  • 12

    A meter is provided which indicates the surface leakage and internal grading current

    of arrester.

    Green arrester is healthy

    Red arrester is defective.

    In case of red we first de-energize the arrester and then do the operation.

    Figure 7. Lightening Arrester

    C. Air Break Earthing Switch

    These are used to ground the circuit and to discharge the CB when CB is in off

    condition.

    The code of earthling switch is 5, 6, 7.The work of this equipment comes into picture

    when we want to shut down the supply for maintenance purpose. This help to neutralize

    the system from induced voltage from extra high voltage. This induced power is up to

    2KV in case of 400 KV lines.

    TABLE II

    The specification of earthing switch

    Make Type Voltage Current Motor volt

    (ac)

    Control volt

    (dc)

    S & S

    power

    Madras 245 kv 10 kA 415 volts 220 volts

  • 13

    D. Bus Bar

    There are three buses viz. two main buses ( bus 1 and bus 2 ) and one transfer bus. The

    two main buses are further divided into two sections thus giving us a total of five buses.

    Bus bars generally are of high conductive aluminum conforming to IS-5082 or

    copper of adequate cross section .Bus bar located in air insulated enclosures &

    segregated from all other components .Bus bar is preferably cover with polyurethane.

    E. Capacitor Voltage Transformer (CVT)

    It is used for three purposes :

    Metering

    Protection

    PLCC

    The carrier current equipment can be connected via the capacitor of CVT. Thereby

    there is no need of separate coupling capacitor. The reactor connected in series with the

    burden is adjusted to such a value that at supply frequency it resonates with the sum of

    two capacitors. This eliminates the error. CVT is attached at end of each transmission,

    line and buses.

    The cvt is used for line voltage measurements on loaded conditions. The basic

    construction of a cvt is as follows. Each CVT consists of a coupling capacitor (CC)

    which acts as a voltage driver and an Electro Magnetic Unit (EMU) which transforms the

    high voltage to standard low voltage. Depending on the system voltage the CC can be a

    single or a multi stack unit. 245 kV & 420kV CVTs no normally comprise of 2 units.

    The CC and the EMU are individually hermetically sealed to ensure accurate

    performance and high reliability.

    Figure 8. Capacitor Voltage Transformer

  • 14

    The main points of difference between a cvt and a potential transformer is that in

    a PT full line voltage is impressed upon the transformer while in cvt line voltage after

    standard reduction is applied to the transformer.

    F. Wave Trap

    It is used in PLCC system to trap frequency higher than 50 Hz. It is lightly inductive

    having very less resistance. It is attached at each end of transmission line. It is of

    cylindrical shape mounted on top of the transmission line.

    G. PLCC ( Power Line Carrier Communication)

    In addition to power supply transfer, transmission line is also used for communication

    purpose. This is done by PLCC system. Here line conductors itself are used as channel

    for carrying information between two end of line.

    The PLCC system is used to trap the frequency higher than 50 Hz through high

    inductance and low resistance along with a coupling capacitor. The main components of

    PLCC are :-

    Wave trap

    Co-axial cable

    CVT

    PLCC cabinet

    LMU ( Line matching Unit)

    H. Current Transformer (CT)

    These are used for stepping down AC current from higher value to lower value for

    measurement, protection and control. Here N2 gas is used to prevent oil from moisture.

    Its secondary winding has 5 cores.

    Terminal 1,2,4,5 protection

    3 - metering

    Turns ratio - 800/1

    I. Isolator

    The isolators can be thought of switches that can either make or break the circuit at the

    operators wish. The difference of an isolator from a circuit breaker can be realized from

  • 15

    the fact that a circuit breakers making or breaking of a circuit depends upon certain

    predefined conditions while that of the isolator dictates no condition.

    It is used as off line line circuit breaker. It is normally used for purpose of isolating a

    certain portion when required for maintenance. It operates at 2000 A . In switchyard

    there are 3 types of isolators :

    Line isolator

    Transfer bus isolator

    Bus isolator

    Sequence of operation while opening / closing a circuit :

    While opening : open circuit breaker open isolator close earthing switch (if any )

    While closing : ensure ciruit breaker is open close isolator open earthing switch

    close circuit breaker.

    J. Bay

    System componenets connected in a sequence constitute a bay.

    The total number of bays is 22. Out of which 3 are spare bays.

    Bay 1 250 MVA 15.75/242 kV Generator transformer 1

    Bay 2 Spare 40 MVA 220/7.1 kV Station Transformer- 3

    Bay 3 40 MVA 220/7.1 KV Station Transformer - 1

    Bay 4 40 MVA 220/7.1 KV Station Transformer - 2

    Bay 6 250 MVA 15.75/242 KV Generator Transformer -2

    Bay 7 220 Kv (Chin hut) Luck now Feeder - 1

    Bay 8 220 KV Luck now Feeder -2

    Bay 9 Bus couplets 220 KV

    Bay 10 220 KV Fateful Feeder - 1

    Bay 11 220 KV Fateful Feeder - 2

    Bay 12 220 KV by Pass Breaker

    Bay 13 210 MW Generators -3

    Bay 14 40 MVA 220/6.9 KV Station Transformer - 3

    Bay 16 210 Mw Generators - 3

    Bay 17 220 KV Transfer Bus Coupler- 2

  • 16

    Bay 19 220 KV Kanpur Feeders - 1

    Bay 20 220 KV Kanpur Feeders - 2

    Bay 21 220 KV Kanpur Feeders - 3

    Bay 22 220 KV Kanpur Feeders - 4

  • 17

    Figure 9. Single line diagram of Switchyard

  • 18

    IV. GENERATOR

    The transformation of mechanical energy into electrical energy is carried out by the

    generator. The generator also called the alternator is based upon the principle of

    electromagnetic induction. The stator houses the armature windings and the rotor houses

    the field windings. The alternator is a doubly excited system and the field is excited from

    dc supply whereas the output received from the alternator is ac. When the rotor is

    energised the flux lines emitted by it are cut by the stator windings which induces an emf

    in them given by

    E = 4.44 f N

    Where f frequency in Hz

    field strength in webers/m2

    N speed of rotor in rpm

    Turbo generators run at a very high speed hence the no. of poles are generally two or

    four and have a cylindrical rotor construction with small diameter and long axial length.

    A. Main components

    The main components of a generator are the rotor and stator.

    Rotor

    The electrical rotor is the most difficult part of the generator to design. It is an

    electromagnet and to give it the required strength of magnetic field a large current is

    required to flow through it. The rotor is a cast steel ingot and is further forged and

    machined.

    Rotor winding:Silver bearing copper is used for the winding with mica as the insulation

    between conductors. A mechanically strong insulator such as micanite is used for lining

    the slots. Rotor has hollow conductors with slots to provide for circulation of the cooling

    gas.

    Rotor balancing:The rotor must then be completely tested for mechanical balance which

    eans that a check is made to see if it will run upto normal speed without vibration.

    Stator

    Stator frame: It is the heaviest load to be transported. The major part is the stator core.

    This comprises an inner frame and an outer frame. The outer frame is a rigid fabricated

    structure of welded steel plate. In large generator the outer casing is done in two parts.

  • 19

    Stator core: it is the heaviest part and is built from a large no. of thin steel plates or

    punchings.

    Stator windings:It is of lap type and employs direct water cooled bar type winding. The

    stator winding bar is made from glass lapped elementary conductor and hollow

    conductors. The main insulation is applied by means of mica tape which is wrapped and

    is compounded with the help of a silicon epoxy compound.

    TABLE III

    Specifications of Turbo Generators

    KVA Pf Stator

    Voltage

    (V)

    Stator

    Current

    (A)

    Rotor

    Voltage

    (V)

    Rotor

    Current

    (A)

    Rpm Hz Phase Coolant

    247000 0.85 15750 9050 310 2600 3000 50 3 Water

    (stator)&

    hydrogen

    (rotor)

    B. Excitation System

    Static Excitation System-The generators in stage -1(u-1&u-2) have this

    excitation system. Static excitation system has slip ring and carbon brush

    arrangement. It consists of step down transformer, converter and AVR (automatic

    voltage regulator).

    Brushless Excitation System The generators in stage -2(U-3, U-4& &U- 5)

    have this excitation system. It has two exciters, one is main exciter and other is

    pilot exciter.

    C. Generator Protection

    Stator Protection- The neutral of star connected winding is connected to primary

    of neutral grounding transformer, so that earth fault current is limited by over

    voltage relay.

    Differential Protection- In case of phase-to-phase fault generator is protected by

    longitudinal differential relay.

  • 20

    Rotor Protection-Rotor winding may be damaged by earth faults or open circuits.

    The field is biased by a dc voltage, which causes current to flow through the relay

    for an earth fault anywhere on the field system.

    Over Speed Protection Mechanically over speed device that is usually in the

    form of centrifugally operated rings mounted on the rotor shaft, which fly out and

    close the stop valves if the speed of the set increase more than 10%.

    Over Voltage Protection It is provided with an over voltage relay. The relay is

    usually induction pattern. The relay open the main circuit break and the field

    switch if the over voltage persists.

    Seal Oil System Hydrogen in the generator is under very high pressure. There is

    a possibility of this hydrogen to come out of gaps, which is very hazardous. So,

    seal oil is used to seal the gaps so that hydrogen doesnt come out.

    Lubrication Oil System Turbine lubrication-oil system seeks to provide proper

    lubrication of turbo generator bearings and operation of barring gear. Pumps are

    used to circulate lubrication-oil inside the generator. The oil of the lubrication

    and the governing system is cooled in the oil coolers. The cooling medium for

    these coolers is circulating water.

    D. Generator Cooling System

    Turbogenerator is provided with an efficient cooling system to avoid excessive

    heating and consequent wear and tear of its main components during operation. The

    two main systems employed for cooling are water cooling system and hydrogen

    cooling system.

    Hydrogen cooling system: Hydrogen is used as a cooling medium in large capacity

    generator in view of the following feature of hydrogen. When hydrogen is used as a

    coolant the temperature gradient between the surface to be cooled and the coolant is

    greatly reduced. This is because of the high coefficient of heat transfer of hydrogen.

    The thermal conductivity of hydrogen is 7 times that of air and hence good heat

    conduction is possible. While using hydrogen it eliminates oxygen in the chamber

    and hence prevents the formation corrosive acids therefore lengthens the life of

    insulation. As hydrogen is a non-supporter of combustion hence risk of fire is

  • 21

    eliminated. The density of hydrogen is 1/14th times of air hence circulation is also

    easier.

    The cooling system mainly comprises of a gas control stand, a driver, hydrogen

    control panel, gas purity measuring instrument and an indicating instrument, valves

    and the sealing system. A great care should be taken so that no oxygen enters the

    cooling system because hydrogen forms an explosive mixture with air. The purity of

    hydrogen be maintained as high as 98%.to produce hydrogen in such large quantities

    a separate plant called the hydrogen plant is also maintained.

    Water cooling system: Turbogenerators require water cooling arrangement. The

    stator winding is cooled by circulation of demineralised water through hollow

    conductors. The system is designed to maintain a constant rate of cooling water flow

    to the stator winding at a nominal temperature of 40 deg Celsius.

    E. Cooling Specifications Of Turbogenerators At FGUTPP

    Stage-I:

    Water as well as hydrogen cooling is present in stage-I turbo generators with

    following specifications:

    Rotor cooling: Hydrogen gas pressure: 3.5 Kg/cm2, Purity: 98%

    Stator cooling: Water pressure: 3.5 Kg/cm2 , Rate of flow of water: 130 m

    3/hr

    Stage-II & III:

    Only hydrogen cooling is used for both stator and rotor cooling.

    Rotor cooling: Hydrogen gas pressure: 3.5 Kg/cm2, Purity: 98%

    Stator cooling: Hydrogen gas pressure: 2.0 Kg/cm2, Purity: 98%

  • 22

    V. TRANSFORMERS

    The transformer is a device that transfers electrical energy from one electrical circuit to

    another through the medium of magnetic field and without the change of frequency. It is

    an electromagnetic energy conversion device, since the energy received by the primary is

    first converted to magnetic and is then reconverted to electrical energy in the secondary.

    Thus these windings are not connected electrically but coupled magnetically. Its

    efficiency is in the range of 97 to 98 %.

    A. Transformer accessories

    Conservator: with the variation of temperature there is a corresponding variation

    in the volume of oil due to expansion and contraction of oil caused by the

    temperature change. To account for this, an expansion vessel called the

    conservator is connected to the outside atmosphere through a dehydrating

    breather to keep the air in the conservator dry. An oil gauge shows the level of oil

    in the conservator.

    Breather: it is provided to prevent the contamination of oil in the conservator by

    the moisture present in the outside air entering the conservator. The outside air is

    drawn into the conservator everytime the transformer cools down which results in

    the contraction of the volume occupied by the oil in the conservator. The

    breather contains a desiccator usually Silica gel which has the property of

    absorbing moisture from the air. After sometime silica gel gets saturated and then

    it changes it colour from purple to pink indicating that it has become saturated

    and hence needs to be replaced or regenerated.

    Relief vent: In case of severe internal fault in the transformer, the pressure may

    be built to a very high level which may result in the explosion in the tank. Hence

    to avoid such condition a relief vent is provided with a bakelite diaphgram which

    breaks beyond certain pressure and releases the pressure.

    Bushings: they consist of concentric porcelain discs which are used for insulation

    and bringing out the terminals of the windings from the tank.

    Buchcholtz relay: this is a protection scheme for the transformer to protect of

    against anticipated faults. It is applicable to the oil immersed transformer and

    depends on the fact that transformer breakdowns are always preceded by violent

  • 23

    generation of gas which might occur due to sparking or arcing. It consist of two

    mercury relayed switches one for a danger alarm and the second for tripping the

    transformer.

    Temperature indicators: transformers are provided with two temperature

    indicators that indicate the temperature of the winding and that of the oil in the

    transformer for an oil filled transformer. The temperature indicators are also

    protective in nature whereby the first create an alarm and then tripp the respective

    transformer in case the temperature of the respective parts rises beyond a certain

    value.

    Tap changers: these are also provided and are mounted on the transformer. In

    case some kind of load fluctuations the taps can be changed or adjusted as per the

    need. There are two types of tap changers On load tap changer and Off load tap

    changer.

    B. Cooling Of Transformers

    Heat is produced in the transformers due to the current flowing in the conductors of the

    windings and on account of the eddy current in the core and also because of the hyterisis

    loss. In small dry type transformers the heat is directly dissipated to the atmosphere. In

    oil immersed systems oil serves as the medium for transferring the heat produced.

    Because of the difference in the temperatures of the parts of the transformers circulating

    currents are set. On account of these circulating currents hot oil is moved to the cooler

    region namely the heat exchanger and the cooler oil is forced towards the hot region. The

    heat exchangers generally consist of radiators with fins which might be provided with

    forced or natural type air circulation for removal of heat.

    The oil in oil immersed transformers may also be of forced or natural circulation

    type. The oil used for cooling is silicone oil or a mixture of naphthalene and paraffin.

    When forced oil circulation is used then pumps are used for the circulation of the oil. The

    oil forced air forced type cooling is used in large transformers of very high KVA rating.

    i. Simple Cooling

    AN: Natural cooling by atmospheric circulation, without any special devices. The

    transformer core and coils are open all round to the air. This method is confined to very

    small units at a few kV at low voltages.

  • 24

    AB: In this case the cooling is improved by an air blast, directed by suitable trunking and

    produced

    by a fan.

    ON: The great majority of transformers are oil-immersed with natural cooling, i.e. the

    heat developed

    in the cores and coils is passed to the oil and thence to the tank walls, from which it is

    dissipated.

    The advantages over air-cooling include freedom from the possibility of dust clogging

    the cooling

    ducts, or of moisture affecting the insulation, and the design for higher voltages is greatly

    improved.

    OB: In this method the cooling of an ON-type transformer is improved by air blast over

    the

    outside of the tank.

    OFN: The oil is circulated by pump to natural air coolers.

    OFB: For large transformers artificial cooling may be used. The OFB method comprises

    a forced

    circulation of the oil to a refrigerator, where it is cooled by air-blast.

    OW: An oil-immersed transformer of this type is cooled by the circulation of water in

    cooling

    tubes situated at the top of the tank but below oil-level.

    OFW: Similar to OFB, except that the refrigerator employs water instead of air blast for

    cooling

    the oil, which is circulated by pump from the transformer to the cooler.

    ii. Mixed Cooling

    ON/OB: As ON, but with alternative additional air-blast cooling. ON/OFN, ON/OFB,

    ON/OFW,

    ON/OB/OFB, ON/OW/OFW: Alternative cooling conditions in accordance with the

    methods indicated.

    A transformer may have two or three ratings when more than one method of cooling is

    provided. For an ON/OB arrangement these ratings are approximately in the ratio 1/1.5;

    for ON/OB/OFB in the ratio 1/1.5/2.

  • 25

    C. Main Transformers

    i. Genrator Transformer: -- This is a step up transformer. This supply gets its

    primary supply from generator and its secondary supplies the switchyard from

    where it is transmitted to grid. This transformer is oil cooled. The primary of this

    transformer is connected in star. The secondary is connected in delta. These are

    five in number.

    ii. Station Transformer: --This transformer has almost the same rating as the

    generator transformer. Its primary is connected in delta and secondary in star. It is

    a step down transformer. These are 4 in number.

    iii. Unit Auxiliary Transformer: -- This is a step down transformer. The primary

    receives from generator and secondary supplies a 6.6 KV bus. This is oil cooled.

    These are 10 in number.

    iv. Neutral Grounded Transformer: --This transformer is connected with supply

    coming out of UAT in stage-2. This is used to ground the excess voltage if occurs

    in the secondary of UAT in spite of rated voltage.

    TABLE IV

    Specifications of GTs

    TA

  • 26

    TABLE V

    Specifications of STs

    TABLE VI Specifications UATs

    TABLE VII

    Neural grounded transformer (NGT)

    KVA Phase Hz Type of

    cooling

    No

    load

    voltage

    (volts)

    No

    load

    voltage

    LV

    (volts)

    Line

    current

    HV (A)

    Line

    Current

    LV (A)

    Temp

    Rise

    of Oil

    (C)

    Temp

    rise

    Winding

    1150 3 50 ONAF/ONAN 6600 250 105.9 2655.8 50 55

  • 27

    VI. D.C SYSTEM

    A. Requirement Of Dc System

    There are some auxiliaries which need to run even when the ac supply fails such as seal

    oil pumps, the scanner system, valve control,lights,etc. So we require the DC system.

    All the circuit breakers in the power plant operate on DC. The DC system

    comprises of batteries, chargers, control circuit to maintain a continuous supply for the

    DC feeders.

    There are five units in unchahar power plant and in each unit separate battery

    rooms are made from which we have 220V as well as 24V DC supply

    B. Description of battery:

    Capacity = 220 V (1400 AH) / 24 V (400 AH)

    Per unit cell = 2.2 V

    Battery plate:

    Positive terminal = PbO2

    Negative terminal = Pb

    Electrolyte = H2SO4

    Reactions occuring in the battery :

    1. At the time of charging:

    At positive plate

    PbSO4 + SO4 + 2H2O -> PbO2 + 2H2O

    At negative plate

    PbSO4 + H2 -> Pb + H2S

    2. At the time of Discharging:

    At positive plate

    PbO2 + H2 + H2SO4 -> PbSO4 + 2 H2O

    At negative plate

    Pb + SO4 -> PbSO4

    C. Battery charger

    Battery charger normally operates in two modes.

  • 28

    Float charging: It is constant voltage mode and works as a trickle charger.

    Boost charging: It is constant current mode and works as a quick charger.

    Trickle Charger It operates at 220V. It is used for continuous charging of the battery.

    Full time battery is charged by the trickle charger and remains in float condition.

    Quick charger It is also known as Boost Charger. This is used at the time of

    overhauling. It operates in two modes

    i. Constant current (CC)

    ii. Constant Voltage (CV)

    D. Capacity test of battery:

    In order to maintain the condition of battery we do a capacity test. For 220V we first

    discharge the battery at the rate of 140 A for 10 hrs. through a resistance boxes. We keep

    on monitoring the

    Specific gravity of electrolyte

    Temperature

    Voltage

    of each cell. If the voltage level goes below 1.85V, it indicates that the cell is defective

    and needs replacement.

    For recharging these batteries we charge them in constant current (CC) mode at

    the rate of 6% for 1-2 days. During charging the battery gives a total of 270-280 V. In

    order to maintain 220 V level we bypass some batteries till the supply is maintained.

    Basic operation of charger:

    In the charger there are two incomers and at a time only one switch in on. This supply

    goes to the contactor which is tapped through the coils according to the voltage levels.

    The diodes rectify ac to dc but since it is not ripple free so we apply the LC filter circuit

    which lowers the ripple factor and gives us the DC same is the case with 24 V Charger.

    From the charger one supply goes to the DCDB (Direct Coupled Digital Board)

    and the other to the battery for charging.

  • 29

    VII. SWITCHGEAR

    Switchgear is an electrical functional switch used for starting any drive and provide

    protection to the drive during on load condition. It is of two types :-

    Low tension switchgear (below 1000 V)

    High tension switchgear (above 1000 V)

    A. L.T Switchgear

    OPERATING VOLTAGE- 415VOLT

    The main components are :

    Relays

    Contactors

    Isolators

    Fuses

    Relays: the purpose of protective relaying system is to operate the circuit breaker so as to

    disconnect only the faulty equipment from the system as quickly as possible thus

    minimizing the trouble and damage caused by faults when they do occur. The general

    relay used is BMR ( Bi-Metallic Relay). It trips due to thermal overloading when

    overcurrent passes through the bimetallic strips causes different expansions in different

    parts as a result the BMR strip is bent.

    Contactors: these are used on-loadoperations under normal conditions. Contactor is a

    mechanical switching device capable of making carrying and breaking electric current

    under normal circuit conditions including operating overload conditions

    Isolators: These are disconnecting switches used for off-load operations. These are

    operated manually. Before operation power is switched off. Isolators are kept in closed

    position when the system components are in operation. During any maintenance work

    isolators are kept open.

    Fuses: It is a device used in circuit for protecting electrical equipments against overload

    or short circuit. The fuse wire melts when an excessive current flows in the circuit and

    thus isolates the faulty device from the supply circuit.

  • 30

    B. H.T. Switchgear

    OPERATIONG VOLTAGE - 6.6KV

    For low voltage circuits fuses may be used to isolate the faulty circuit. For voltage higher

    than 3.3 kV isolation is achieved by circuit breaker.

    Requirement of circuit breaker:

    After occurrence of fault the switchgears must isolate the faulty circuit as quickly

    as possible i.e. keeping the delay to minimum.

    It should not operate when an over current flows under healthy condition.

    Basic principal of operation of circuit breaker:

    Circuit breaker consists of a fix contact and sliding contact into which moves a moving

    contact. The end of moving contact it attached to a handle that can be manually operated

    or may operate automatically with the help of mechanism that has a trip coil energized

    by secondary of CT. Under normal condition the secondary of CT is not energized

    sufficiently to trip the coil but under false condition the coil is energized fully to operate

    the trip coil and the circuit breaker is operated.

    MOCB (Minimum oil circuit breaker)

    SF6 (Sulphur hexafluoride circuit breaker)

    Here oil and SF6 are used to quench the arc.

    Bus ducts:

    These serve as interconnection between transformer and switchgear and are non-

    segregated phase type. These are natural air cooled.

    Bus coupler:

    It acts as interconnection between the two bus. If the supply of one bus fails then the bus

    coupler connects the two buses and charges the bus from the other bus.

    Different relays used:

    Motor protection system

    Earth fault relay

    Over load relay

    Lock out relay

    Check synchronizing relay

  • 31

    Differential protection relay

    Auxiliary relay

    Figure 10. Electical system layout of stage III

  • 32

    VIII. BOILER

    Furnace is placed at the bottom of the most important part of the thermal plant where

    steam is generated. The boiler used at FGUTPP is the water tube boiler type in which,

    water circulates in tubes surrounded by fire. Hence it takes up heat and gets converted

    into steam. The steam then rises up and gets collected inside the boiler drum. The boiler

    is made up of carbon steel. The temperature of steam that comes out of the boiler is

    around 530 deg Celsius and its pressure is 120kg/cm2. The type of boiler can be further

    elaborated as natural circulation, dry bottom, and tangential fired, radiant heat type with

    direct fired pulverised coal system.

    Once the steam is produced in the boiler, it gets collected inside the boiler drum.

    Boiler drum is a special type of cylindrical drum like structure which contains a mixture

    of water and steam. Steam being lighter gets collected at the top portion and beneath it

    we have the water. It is very important to maintain a safe level of water in the drum since

    we have two main types of constraints in this regard. If the steam produced and collected

    is more then it can lead to a blast in the boiler drum else tiny droplets of water can enter

    the turbine. Hence in order to keep a check we measure the level by hydrastep.

    Hydrastep is a phenomenon based on the difference in the conductivities of water and

    steam.

    Since there is great pressure and temperature at the boiler great care should be

    taken while going to the site and maintenance.

    Since coal is burning in the furnace and then we have water tubes of the boiler

    inside hence constant burning of coal produces ash which gets collected on the water

    tubes and the start working as insulation, hence its necessary to blow this soot hence for

    this purpose we use Soot Blowers.

    Soot blowers are basically pipe like structures that go inside the furnace and the

    boiler for efficient onload cleaning. Cleaning is done by the superheated steam which is

    tapped from the superheater for the purpose of soot blowing. The pressure is reduced to

    31kg/cm2

    at 330 deg Celsius by means of reducing valve. We mainly have three types of

    soot blowers:

    1. long retraceable soot blower

    2. wall blower

    3. air reheater

  • 33

    Before sending this steam to the turbine, the steam is again superheated and then its

    temperature is around 580deg Celsius. This increases the efficiency since the

    temperature is the measure of energy hence higher temperature higher is the energy.

    Hence, during the phenomenon of superheating the steam which is dry and saturated, is

    being heated and hence the temperature of steam again rises.

    First the steam from boiler drum enters the low temperature super heater (LTSH).

    After LTSH steam enters the platen superheater and then finally to a high temperature

    superheater. The steam which is now produced goes to the HP turbine.

    Figure 11. Water tube Boiler Schematic Layout

  • 34

    IX. ELECTROSTATIC PRECIPITATOR (ESP)

    The ash content in the Indian coal is of the order of 30 to 40 %. When coal is fired in the

    boiler, ashes are liberated and about 80% of ash is carried along with the flue gases. If

    this ash is allowed to flow in the atmosphere, it will cause air pollution and lead to health

    troubles. Therefore it is necessary to precipitate the dust from the flue gases and this

    work is done by the electrostatic precipitator.

    A. Working principle

    The principle upon which an electrostatic precipitator works is that dust laden gases are

    passed into a chamber where the individual particles of dust are given an electric charge

    by absorption of free ions from a high voltage DC ionising field. Electric forces cause a

    stream of ions to pass from the discharge electrodes (emitting) to the collecting

    electrodes and the particles of ash in the gas are deflected out of the gas stream into the

    collecting surfaces where they are retained by electrical attraction. They are removed by

    an intermittent blow usually referred to as RAPPING. This causes the ash to drop into

    hoppers situated below the electrodes. There are 4 steps that are involved:

    1. Ionisation of gases and charging of particles.

    2. Migration of particles to respective electrodes.

    3. Deposition of particles on the electrodes.

    4. Dislodging of particles from the electrodes.

    B. Description

    The ESP consist of two sets of electrodes, one in the form of helical thin wires called

    emitting electrode which is connected to -70KV DC and the collecting electrode in

    grounded.

    C. Parts of ESP

    1. Basing-: the precipitator casing is robustly designed and has an all welded steel

    construction.

    2. Hoppers-: the hoppers are of pyramidical shape. The angle between hopper corner

    and the horizontal is never less than 55 deg and often more to ensure easy dust flow.

  • 35

    To ensure free flow dry ash into disposal system the lower portion of hopper are

    provided with electrical heaters.

    3. Collecting system-: the collecting system consists of electrodes which are based on

    the concept of dimensional stability. They have a flat uniform surface for uniform

    charge distribution. These electrodes have larger area and are grounded, hence have

    zero potential.

    4. Emitting system-: the emitting system consist of emitting or discharging electrodes

    that are in the front of the helical wires for a non-uniform distribution to enhance the

    rate of charging since a non-uniform field is created.

    5. Rapping mechanism-: the Rapping mechanism is a process which is employed to

    hammer out the ash particles which get precipitated on the respective plates. Hence

    in order to hammer out those particles rapping motors are employed which hammer

    at the rate of 2 to 3 cycles per minute. Various motors are employed and are called

    collecting rapping motor and emitting rapping motor.

    6. Insulators-: these are also employed for support since ESP is hung with the help of

    these insulators.

    7. Transformer Rectifier-: a transformer rectifier is employed which steps up the

    voltage to 70KV and then it is rectified to -70 KV and is given to the emitting

    electrode

    Figure 12. Schematic Diagram of ESP

  • 36

    D. Electrical scheme of ESP

    The following mechanism takes place electrically:

    Emitter electrode (E) creates a strong electric field near the surface and corona

    discharge takes place.

    Positive and negative ions are formed by this discharge.

    The positive ions move towards anti positive charge line electrodes called

    emitting electrodes and the negative ions towards collecting electrodes.

    During this passage ions collide with ash particles and adhere to them.

    These charged particles stick on the collector curtain which is the dislodged by

    the rapping motors which is collected by the hoppers.

    For optimum functional efficiency of the precipitator the supply voltage should

    be maintained near above the flash over level between electrodes. This is achieved by the

    electronic control. The efficiency of ESP is about 99.95%. The ESP is divided into 4

    passes called A, B, C, D and has various fields per pass.

    In stage-I we have 7 fields per pass and hence the total no. of fields is 28 whereas in

    stage-II & III we have have 8 fields per pass and hence the total no. of fields is 32.

    E. Variable frequency drive

    From the electrostatic precipitator, the flue gases are sucked. It is a type of fan and is

    called Induced draft fan. It sucks the flue gases from the ESP and then transfers them to

    the chimney. In stage-I an IM is employed for this purpose but the speed control of that

    motor is not possible. Sometimes the amount of flue gases coming out is small and other

    times it is large but since no speed control is possible hence the flow of flue gases

    become a tedious task. However in stage-II the speed control is possible since here we

    have variable frequency drive. The motor which is employed here are synchronous

    motor.

    Using variable frequency drive voltage is compensated at low frequencies, the

    torque at low speeds is improved. To obtain the voltage boost, we require a controlled

    converter as well as a controlled inverter.

    The panel in Figure 11 is a variable frequency drive panel. First the three phase

    supply from transformer is fed to the controlled rectifier which the ac to dc. The

    advantage of using a controlled rectifier is that the average value of the output can be

  • 37

    controlled by varying the firing angle. Then its output is fed to the inverter which is a

    type of load commutated inverter. Before passing it to the inverter a reactor is also

    employed in between this reduces the ripples. The inverter then converts dc to ac and the

    ac is fed to the synchronous motor. The speed of synchronous motor is fixed and is given

    by 120 f / p. since the only thing variable in the expression is the frequency which is

    directly proportional to the speed. Hence the inverter varies the frequency and hence

    controls the speed of the motor. The controlled rectifier in the circuit is used for voltage

    control while the load commutated inverter is used for frequency variation

    Figure 13. Electrical scheme of VFD

    Two channel arrangement for synchronous motor

    The stator of the synchronous motor is given supply using two channels. Normally the

    motor works on both channels but under some faulty conditions on any one of the

    channels the other channel can continue working since the motor is required for

    continuous operation

    Figure 14. Two channel arrangement of synchronous motor

  • 38

    Hence the frequency is varied from 0.5 Hz to 47.5Hz. When both channels

    operate the motor moves at 575rpm and when one channel is in operation the maximum

    speed is 475rpm. The power and current ratings in case of both the channels is 1414KW

    & 420Amp. In case only one channel is working then the power is 635KW and current is

    380Amp.

    TABLE VIII

    Specification of Synchronous Motor

    KW

    rating

    KVA

    rating

    P.F. Speed

    (rpm)

    Stator

    voltage

    Excitation

    voltage

    Insulation

    class

    Wt.

    (Kg)

    1414KW 1646 0.9

    (lead)

    575 2X1200

    V

    170 V dc F

    19,000

    Advantages of Variable Frequency Drive

    1. Speed control is fine as the frequency is varied from 0.5Hz to 47.5 Hz.

    2. Very low starting current as motor starts on reduced voltage.

    3. Power consumption is low.

    4. Motor life is improved

  • 39

    X. COAL HANDLING PLANT

    A. Introduction

    NTPC Unchahar gets its coal supply mainly from Bihar. Now coal is also coming from

    Australia, as coal produced in India is of low grade and ash content is more. The coal

    being filled in the wagons of the rail reaches plant. The purpose of this plant is to convey

    the coal to the bunker in the size not larger than 20mm.It handles and transports the coal

    to the bunker from the wagons by passing through various conveyors, transfer points,

    crusher houses, etc.

    BCCL costs Rs.4/kg

    CCI cost Rs.6/kg

    B. Properties of Coal

    1. Calorific value: the heat evolved when unit amount of coal is burned.

    2. Gross calorific value: the heat evolved when all the products of combustion are

    cooled to the atmospheric temperature.

    3. Net calorific value: it is the value obtained when GCV is subtracted by sensible

    and latent heat of water in the products of combustion.

    4. Grindablity: it is the ease with which the coal can be ground to fine sizes. It is

    measured on the hard grove scale. Coal used here has a Grindablity index of 55.

    C. Coal analysis

    It is done in two ways:

    1. Proximate analysis: it gives the behaviour of coal when heated.

    2. Ultimate analysis: it tells the elementary composition of coal . it is useful in

    determining the air required for combustion and in finding the weight of

    combustion products.

    D. Different methods of unloading the coal

    1. Manual Unloading: - Previously, manpower was used for unloading the wagons.

    But it was very time consuming and more workers were required for the job to be

    done.

  • 40

    2. Box in (using wagon tippler for unloading): - This method is still used in stage-1

    of NTPC Unchahar. For this method, Indian Railway grants 10 hours for

    unloading the 58 wagons. In this method, Wagons are separated and tippled by using

    wagon tippler. The Beetle Feeder is used to move the wagon on wagon tippler. The

    coal from the wagons gets accumulated in The Track Hopper. At this time; the size

    of the coal is approximately 300mm.

    3. BOBR: - This method is used in used in stage -2 and stage-3 of NTPC

    Unchahar. Indian Railway grants only 2.5 hours for Unloading 58 BOBR wagons.

    This is an advanced technology in which we use the compressor system. In Bottom

    Open Bottom Release (BOBR) technology the wagons are opened from side.

    Pressure is applied by the compressor to open the bottom gates of the wagon so that

    the coal gets released over the track hopper and wagon get unloaded quickly.

    E. Various equipment used in CHP

    i. Marshalling Yard: it consist of railway tracks provided to receive the

    loaded trains, to unload them and to put them back in formation without

    interference between loaded and empty racks.

    ii. Wagon Tripler: The wagon Tripler is a most important device in thermal power

    project. The Wagon Tripler turns back the wagon at 135-degree angle and the

    structure of the wagon tippler is to be very heavy. Upper side of the wagon is

    fixed with the many angles for supporting the wagon. When the wagon is fixed

    on the Platform then whole platform is turned back and the coal fall down in the

    wagon tippler hopper. The unloading time of the Rack is 6hours. Here the type of

    the rack is Box C / Box N type.

    Wagon Tripler Hopper: - The Wagon Tripler Hopper is a part of the wagon

    tippler where the coal is stored from the wagon tripler. The size of the coal

    here is less than 300mm.

    Vibrating Feeder: - The vibrating feeder is used for falling the coal on the

    conveyer through Wagon tippler Hoper. Before Wagon tippler Hoper and

    Vibrating Feeder the gate is providing to control the flow of the coal.

  • 41

    Beetle Charger: - The Beetle charger is a traveling device that is used to

    carry the wagon on the wagon tippler platform.

    Dust Suppuration: - Dust Suppuration is a useful device. When the wagon

    are tippling then the dust is mixed in the air and that area becomes very dusty

    then Dust Suppuration operates and water flows through its points and the

    dust settles down. It is an automatic device.

    iii. Paddle Feeder: - They have been installed on conveyors below the manual

    unloading track hopper. There are 6 nos. of paddle feeders, 3 on each conveyer. 3

    Paddle Feeders of each conveyer move to and fro within a limiting range. The

    rotating part of the paddle feeder is called as plough wheel. Plough wheel has 6

    blades. By the rotation of the plough wheel, the coal of the track hopper gets

    accumulated between the blades and is discharged on the conveyor below it. The

    main components of paddle feeder are:

    Plough wheel - It is the rotating part consists of 6 blades. It is attached with

    the rotor of 3-phase slip ring induction motor.

    Reduction gear box - It is installed to control the speed of plough wheel.

    End limit switch (left or right) - It provides the limiting motion of the

    paddle feeders.

    Anti-collision switch - It provides the prevention from collision between two

    paddle feeders.

    Interlock system - It is provided for safety purpose. By this, the conveyor

    belt moves first then paddle feeder starts.

    iv. Vibrating Feeder: - They have been installed below the track hoppers of wagon

    tippler. The coal is accumulated over the vibrating feeder so by giving vibrations

    to the vibrating feeder we discharge the coal from track hopper to the conveyors.

    Their main purpose is to provide uniform feeding on the conveyors. The vibrating

    feeders consist of a tray to which vibrator body is fixed on the rear end.

    v. Transfer Points: - Transfer Point is provided with flap gate and Conveyer. In

    transfer Point the coal is transferred from one conveyer to other conveyer.

  • 42

    vi. Flap Gate: - The flap Gate is a two-way device. It consists of two gates. Both

    gates cannot operate together. By help of the flap Gate, we change the way of

    coal that fall down on the conveyer.

    vii. Conveyers: - The Conveyer Belt is a moving device. It travels on its platforms.

    The shape of the conveyer belt is to be flat but on the platforms it is to be in curve

    shape. The coal falls down the conveyer and goes to the primary Crusher House

    Platforms. The capacity of conveyer in Stage I is 800MT/ hr. & in Stage II is

    1200MT / hr.

    Figure 15. Forward Conveyor Figure 16. Return Conveyor

    viii. Protecting devices provided to the Conveyer

    Zero Speed Switch: - The Zero Speed Switch prevents the Conveyer from

    over load run. When the conveyer is over loaded, the speed of the conveyer is

    reduced and Zero Speed Switch is operated and stops the conveyer. This

    device is provided at Head End of the Conveyer. The Zero Speed Switch is a

    Centrifugal Switch.

    Pull cord Switch: - This is a manual protecting device. When the Worker

    sees any mistake like big stone or any dangerous fault, pulls this cord. The

    Pull Cord Switch is to be operated, and the Conveyer stops.

    Belt Sway Switch: - The Belt Sway Switch also protects the conveyer. This

    device is provided on both side of the conveyer. When the conveyer leaves its

    way the switch is operated and the conveyer stops. This is also an automatic

    protecting device.

    Linear heat sensing cable: - This protection is for any type of heat related

    procedures. If by any means the temperature of the conveyor belt increases

    beyond a certain limit then this protection comes into action. In this

  • 43

    protection a special temperature sensing type wire runs through the periphery

    of the conveyor structure.

    ix. Primary crusher (rotary breaker): - In Primary Crusher House, the coal breaks

    in Rotary Breaker. Here the coal comes from the Transfer point; breaks here and

    the stone fall down to a separate place. Coal is converted from 300mm to 150mm

    size.

    Parts of the Primary Crusher House

    Rotary Breaker: - The Rotary Breaker has a rotating mechanism. It is

    rotated on the shaft. The coal come from the conveyer through the Flap Gate

    falls down into the rotary breaker. The rotary breaker is to be rotated and coal

    moves up and down and collides and hence breaks. The Rotary Breaker is

    H.T. 170KW 6.6KV Motor.

    Belt Feeder: - The Belt Feeder is a small size of the conveyer. It is used

    for feeding the coal to the conveyer through Flap Gate.

    x. Secondary Crusher (Ring Granulator): - In Secondary crusher House first the

    magnetic part separate from the coal and then feed to the Secondary Crusher.

    This Crusher breaks the coal in 20mm size and coal is sent to the Flap Gate and

    then feeded to the conveyer. The Secondary crusher is hammer type. H.T. motor

    are used for breaking of the coal. Specifications are 700KW 6.6KVMotor.

    xi. Cross Belt Magnetic Seprators: - They will remove the ferrous particles, which

    passes along with the coal. It consists of electromagnet around which a belt is

    moving. It is suspended from top, perpendicular to the conveyor belt at certain

    height. Whenever any iron particle passes below the CBMS, it is attracted by the

    magnet and stick to the cross belt below it. The CBMS capacity is of 50kg.

    xii. Metal Detector: - The purpose of installation is to detect any metallic piece

    passing through the conveyor. Whenever the pieces pass below the search coil of

    the metal detector, it gives the trip command to the conveyor. Simultaneously,

    sand bag marker will fall on the conveyor belt so that the metal can be searched

    easily and removed.

  • 44

    xiii. Stacker/Reclaimer: - It is a very important device. The whole Structure of

    it is called Super Structure. It stacks the excessive coal and reclaims the coal on

    its requirement. It is a two-way device. It consists of following main parts:

    Stacker: - The Stack is a position (1). When the rack comes, the

    excessive coal is send to the stacker through the conveyer from Secondary

    Crusher house. The coals are stacked at the Secondary Crusher Coal Heap. The

    coal falls down from the stacker through Boom Conveyer.

    Reclaimer: - The Reclaimer is position (2). When the rack is not coming

    and there is a shortage of coal, then reclaiming is to be started and the coal is

    lifted from the Secondary Crush Coal Heap and fed to the bunker.

    Boom Conveyer: - The Boom conveyer is a Bi-directional conveyer. It

    moves clockwise & anticlockwise direction. In stacking position, it is moving in

    clockwise direction and in the reclaiming position its moving in anticlockwise

    direction. They are provided with Center Chute and End Chute on the both end.

    Boom hoist: - The Boom hoist is a link of the Super Structure. The hoist

    is moved up and down. For controlling the up & down position, limit switch is

    provided.

    Slew drive: - The Slew Drive moves at 180-degree. When the coal is

    stored on both the side of the track of travel, then the Slew Drive moves and lifts

    or fall the coal from Boom Conveyer. For control the rotation of Slew Drive, the

    limit switch is provided.

    Bucket wheel: - The Bucket Wheel is used when there is a requirement of

    the coal. It is a rotary device. It is always rotated in anticlockwise. In the

    Reclaiming position, the Center Chute is to be up and End Chute of the Boom

    Conveyer is fixed on the conveyer. The Bucket Wheel rotates; when the Bucket

    of the wheel is full with coal and the wheel is rotated the coal fall down on the

    Boom conveyer and the coal is send to the Super Structure.

    Travel: - It is a slip ring induction motor driven system. The Super

    Structure moves on it. The normal speed of the Travel is 10 meter / minute. It

    moves on its track from one end to other end.

    The stacker reclaimer does the following three functions:

    1. travelling (movement in forward and reverse direction)#

    2. luffing (up and down movement)

  • 45

    3. slewing (left and right movement)

    The stacker reclaimer also has two cable reeling drums in which the reeling action is

    done by electrical medium and the unreeling is done mechanically. Great care has to be

    taken during this operation since any loop hole can lead to accidental results. During the

    stocking operation the coal from the crusher house is diverted towards the stockyard

    conveyor at a transfer point. The above conveyor discharges coal to the boom conveyor

    through a discharge chute. The boom conveyor running in the forward direction creates

    coal stacks.

    During reclaiming, coal from the stockyard falls on the boom conveyor with the help

    of bucket wheel and the boom conveyor during this period rotates in the reverse

    direction. The coal from the central chute falls on the conveyor belts used for transferring

    the coal from the stockyard.

    Advantages:

    1. It can operate at full load capacity in bad weather.

    2. It is productive at all times as no return journey is to be performed.

    The only drawback is that it is expensive.

    xiv. Transfer Tower: - Here the coal is send to the Tipper. Transfer Tower is

    provided with a coal sampler.

    xv. Tipper: - The Tipper is a three-way device to feed the coal in Bunker. It is

    moveable device. It is move on its track.

    xvi. Bunker: - Here the coal is collected from the tipper and stored. The capacity of

    the bunker for Stage-I is 4800MT & Stage-II is 8700MT.

    F. Some Special Motors Of CHP

    1. Secondary Crusher house motor :-

    450 kW P.F. = 0.77

    Supply 6.6 kV 746 rpm

    2. Primary Crusher house motor:-

    700 kW P.F. = 0.78

    Supply 6.6 kV 742 rpm

    3. Stacker Reclaimer:-

  • 46

    5.5 kW P.F. = 0.70

    Supply 6.6 kV 965 rpm

    4. Wagon Trippler motor:-

    175 kW

    Supply 415 V

    5. Rotary Breaker motor:-

    175 kW P.F. = 0.8

    Supply 6.6 kV 1485 rpm

    6. Vibrating Feeder motor:-

    40 kW 1470 rpm

    Supply 415 V efficiency = 93 %

    G. Power and Distribution Diagrams

    Stage-I

    Figure 17. Power distribution diagram of CHP in stage I

  • 47

    Stage-II

    Figure 18. Power distribution diagram of CHP in stage II

    XI. CONCLUSION

    On completion of my vocational training at NTPC Feroze Gandhi Unchahar Thermal

    Power Project, I have come to know about how the very necessity of our lives nowadays

    i.e how electricity is generated. What all processes are needed to generate and run the

    plant on a 24x7 basis.

    NTPC Unchahar is one the plants in India to be under highest load factor for the

    maximum duration of time and that to operating at highest plant efficiencies. This plant

    is an example in terms of working efficiency and management of resources to all other

    thermal plants in our country. The operating plf of the NTPC as compared to the rest of

    country is the highest with 87.54% the highest since its inception.

    The training gave me an opportunity to clear my concepts from practical point of

    view with the availability of machinery of diverse ratings.