use of numerical modelling for management of canal irrigation water
TRANSCRIPT
USE OF NUMERICAL MODELLING FOR MANAGEMENT OF CANALIRRIGATION WATERy
ABDUL RAZZAQ GHUMMAN,1* MUHAMMAD ZUBAIR KHAN2
AND MUHAMMAD JAMAL KHAN2
1Faculty of Civil Engineering, University of Engineering and Technology, Taxila, Pakistan2Department of Water Management, NWFP Agricultural University Peshawar, Pakistan
ABSTRACT
Flow regulation and distribution structures play an important role in the overall management of irrigation
canals. In this paper the solution of one-dimensional Saint Venant equations of continuity and momentum was
applied to a secondary canal in the Abazai Branch of the Upper Swat Canal Irrigation System, North West
Frontier Province of Pakistan. The system has been changed from supply based to crop based. The aim of the
study was to firstly evaluate the performance of canal outlets under different discharge conditions. The second
aim was to assess the response of any modifications in the dimensions of the canal outlets on water distribution
under different discharges. Five cases of 100, 80, 70 and 50% of design discharge were tested. The additional
operational option of opening and closure of the canal was also evaluated. It was found that under the existing
configuration of the canal, the majority of the canal outlets were not drawing discharges according to their
allocations for all the four discharge levels. Modifications in outlet dimensions improved the outlet
performance. The best performance of canal outlets was obtained under 100 and 80% of the design canal
discharge after modifications. In the periods of low irrigation demand, the study recommends opening and
closure of the canal instead of operation at lower than 80% of design discharge. Copyright # 2006 John Wiley
& Sons, Ltd.
key words: canal performance; irrigation management; models, outlets; water distribution
Received 28 October 2005; Revised 25 February 2006; Accepted 10 April 2006
RESUME
Les ouvrages de controle et de repartition des debits jouent un role important dans la gestion d’ensemble des
canaux d’irrigation. Dans cet article la resolution d’equations unidimensionnelles de Saint Venant de continuite
et impulsion a ete appliquee a un canal secondaire de la branche Abazai du Upper Swat Canal System dans le
Nord-Ouest du Pakistan. La gestion du systeme par la ressource est passee a une gestion par la demande (des
cultures). Le but de l’etude etait d’abord d’evaluer la performance des emissaires sous differentes conditions de
debit. Le deuxieme objectif etait d’evaluer l’effet de modifications dans les dimensions des emissaires sur la
distribution de l’eau en faisant varier le debit. Cinq cas de debit d’equipement (100%, 80%, 70% et 50%) ont ete
testes. L’option supplementaire d’ouverture et de fermeture du canal a egalement ete evaluee. Il a ete trouve que
dans la configuration existante du canal la majorite des emissaires ne transitaient pas le debit prevu pour les
quatre niveaux de debit etudies. Des modifications apportees a leurs dimensions ont ameliore leurs perform-
ances. La meilleure performance des emissaires a ete obtenue pour 100% et 80% du debit d’equipement du
canal apres modifications. Dans les periodes de moindre demande d’irrigation, l’etude recommande l’ouverture et la
IRRIGATION AND DRAINAGE
Irrig. and Drain. 55: 445–458 (2006)
Published online in Wiley InterScience (www.interscience.wiley.com). DOI: 10.1002/ird.265
*Correspondence to: A. R. Ghumman, Faculty of Civil Engineering, University of Engineering and Technology, Taxila, Pakistan.E-mail: [email protected] de modeles numeriques pour la gestion d’un canal d’irrigation.
Copyright # 2006 John Wiley & Sons, Ltd.
fermeture du canal plutot que son fonctionnement a des debits inferieurs a 80% du debit d’equipement.
Copyright # 2006 John Wiley & Sons, Ltd.
mots cles: distribution d’eau; emissaires; gestion d’irrigation; modeles; performance de canal
INTRODUCTION
The design of canals and irrigation outlets in many developing countries has remained a challenging job for
engineers and researchers. The most important design objective of a canal is the ability of the outlets along the
canal to draw their design discharges. For equitable water distribution in secondary canals of gravity irrigation
systems with very few flow control structures, the dimensions of the outlets need critical studies. These outlets
draw water from the canal in response to the water level in the canal. Performance evaluation studies for different
canals have been carried out in the past. Babar (2000), Shah (2000), Murray-Rust and Halsema (1998), Khan
et al. (2000) and Halsema (2002) found that the performance of secondary canals was generally not good as
far as equitable water distribution was concerned, due to underperformance of the design of the outlets.
Shahrokhnia and Javan (2005) applied HEC-RAS to evaluate the gate opening rules used to control the
offtakes. These rules control discharge reductions of offtakes due to discharge reductions at the system source.
These studies have, however, been restricted to the assessment of performance of the canals only. Due to limited
water regulation structures in such canals, modifications in the dimensions of the outlets offer the most feasible
option for improvement in performance. The present study aims at suggesting improvements in the design
dimensions of irrigation outlets to achieve equitable water distribution under varying irrigation demand. The
model provides a cost-effective way to assess the impact of different modifications on performance of the
canal. The canal management model CANALMAN, developed by the Utah State University, USA (Merkley,
1997) was applied to a secondary canal of the Upper Swat Canal (USC) Irrigation System in the North West
Frontier Province (NWFP) of Pakistan. The package was developed for performing hydraulic simulations
of unsteady flow in branching canal networks. The model is designed for use in design, analysis and operational
of irrigation canals.
Pakistan is a developing country and depends heavily on irrigated agriculture. With the rapid increase in the
demand for higher production per unit area in Pakistan as in many other developing countries in general and in the
NWFP in particular, there have been a number of efforts to change the basis of irrigation from supply-driven
protective systems to crop-based irrigation operations. One of the major systems in Pakistan to undergo this type of
transformation is the USC, situated in the NWFP. The system was redesigned to increase its water allowance from
3.5 to 6 mm d�1.
Assessment of the hydraulic performance of canals with crop-based water allowances, is important due to
varying irrigation demand. The crop-based canals, therefore, require to be operated at different discharges.
The aim of this study was to determine the performance of the canal at different discharges, to recommend
improvements in the design dimensions of the canal outlets and recommend operation strategies for the canal under
varying irrigation demand.
THE RESEARCH SITE
The model was applied to the Shingrai Minor located on the Abazai Branch of the USC, which receives water
from the Swat River at the Amandara Headworks. It was originally designed for a discharge of 68.6 cumecs
(2420 cusecs) to irrigate an area of 127 500 ha (315 000 acres) of the Charsaddah–Mardan–Swabi Plain. The canal,
after traversing the narrow ridge of the Malakand hills through the unlined Benton Tunnel, eventually bifurcates at
Dargai into the two branches of Machai and Abazai (Figure 1).
The Abazai Branch is 26 km long. It has 9 minors and 5 distributaries (Table I). The design discharge of Abazai
branch is 17.3 cumecs. There are additionally 36 direct outlets from the canal. It does not have any radial gate cross
regulators for flow control. The only points of flow control on the Abazai Branch are the intake, the secondary
offtakes and an escape structure located in the tail of Abazai Branch.
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
446 A. R. GHUMMAN ET AL.
Shingrai Minor takes off from the left side of the Abazai Branch of the USC at Reduced Distance (RD) 12 599 m
and is the first major secondary canal (Figure 2). It has a length of 5289 m and design discharge of 0.84 cumecs. It
has 13 outlets of which 11 are short-crested crump weirs (Bos, 1976), and two are open flumes. One of the open
flumes was designed as an Adjustable Orifice Semi Module (AOSM) but was constructed as an open flume. All the
outlets are fixed structures with no adjustable parts and the discharge through these outlets is entirely dependent on
the water depth above their sills. It has a culturable command area of 1170 ha. Most of the canal is lined, with
trapezoidal shape and a longitudinal slope of 0.0005. Shingrai Minor is representative of the medium-sized
Table I. Secondary canals of Abazai Branch
Name of canal Offtake RD (m) Length (m) Design discharge (m3 s�1) Outlets
Mehrdi Minor Abazai (7287) 1829 0.14 5Shingrai Minor Abazai (12599) 5289 0.84 13Pir Sadu Disty Abazai (14207) 9868 2.77 19Qutab Garh Minor Pir Sadu (2145) 5259 0.83 15Ghanu Minor Pir Sadu (7195) 3152 0.43 4Harichand Disty Abazai (17378) 8274 1.44 16Sharif Dheri Minor Harichand (2605) 4780 0.4 9Bariband Disty Abazai (23933) 26962 5.38 52Bahram Dheri Disty Abazai (22085) 14276 2.58 25Nasrat Zai Minor Bahram Dheri (11402) 6183 1.16 14Barazai Minor Bahram Dheri (10274) 3963 0.40 5Amir Abad Disty Abazai (26220) 12302 2.89 23Bajor Minor Amir Abad (1509) 2591 0.59 7Kiramat Minor Amir Abad (3460) 2754 0.54 11
Figure 1. Map of the Upper Swat Canal
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
NUMERICAL MODELLING FOR MANAGEMENT OF CANAL IRRIGATION 447
secondary canals of the Abazai Branch, in design, water allowance and discharge. It was designed for cropping
intensities of more than 180%. The water allowance of Shingrai Minor is 0.7 l s�1 ha�1 (6 mm d�1), which is
sufficient to meet the peak irrigation requirements in the months of May and June. The irrigation demand varies
throughout the year from a maximum in May/June to the lowest in winter months.
OPERATIONAL PRINCIPLES
According to the operational principles of the Irrigation Department, 70% of the design discharge represents the
winter demand and 55% of the design discharge is the minimum threshold discharge (Government of NWFP, 1992).
A comparison of the gross irrigation requirements (Swabi SCARP Consultants, 1991) for cropping intensity of
180%, shows that the demand frequently drops below 70% of design discharge (Figure 3). The supply and demand
are both considered zero in the month of January due to the annual canal closure period and the demand in January
is added to the demand in December. Throughout the year the variation in irrigation requirements indicates the need
for operation of the canal at discharges below 70% of design discharge.
Actual operation of the canal was monitored for five months on a daily basis from August till December (Shah,
2000). During this period the canal was supplied close to its design discharge but the demand varied between 5 and
1.6 mm d�1. The interference from the Irrigation Department was minimal, except that four rotations of one week
each were introduced in November and December.
DESIGN OF CANAL OUTLETS
The discharge through a fixed weir outlet depends on the water level (head) in the canal. The discharge through an
orifice outlet depends on the difference of head in the canal and in the watercourse downstream of the outlet (Bos,
1976). So for weir-type outlets to draw the design discharge the width, crest height of the outlet and the water level
in the canal are important. Similarly for the orifice, the area of outlets opening and the upstream head are important
factors.
A comparison of the design and actual dimensions of the outlets indicated that nine outlets were constructed
according to their design. One outlet was designed as an AOSM but actually constructed as an Open Flume (Ali,
1993) having no roof block.
A number of errors can result in the poor performance of canal outlets. These can be due to design, construction,
and interference by stakeholders. These errors require rectification for the canal to be able to supply discharges to
all its outlets in a fair manner. In this study mainly design and construction errors were observed.
Figure 2. Schematic map of Shingrai Minor
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
448 A. R. GHUMMAN ET AL.
DATA COLLECTION
Data from field measurements taken in 1999 were used. The data involved measurement of water levels in the canal
along all the outlets and the head regulator of the canal. The head regulator and all the outlets were calibrated
through regular flow measurements, and the discharge coefficients were computed. All the canal design data were
collected from the Irrigation Department and verified through field measurements. The period of data collection
was from August till December. All the geometric and hydraulic data were reconfirmed in December 2004 through
survey and measurements.
CANALMAN MODEL
CANALMAN software implicitly solves the Saint-Venant equations of continuity and motion (Strelkoff, 1969)
for one-dimensional unsteady open-channel flow in a branching canal system. Computational nodes are used
internally by the model, and they are automatically inserted along the length of a canal reach, between the system
layout nodes (Merkley, 1997). CANALMAN was evaluated by the ASCE Task Committee on Hydraulic Models
along USM, MODIS, DUFLOW and CARIMA, and found to be reasonably accurate (Dinshaw and Schuurmans,
1993).
MODEL CALIBRATION AND VALIDATION
The model was calibrated using simulated and measured water levels in the canal reaches at full supply (846 l s�1).
Optimal values of the Manning’s roughness coefficient (n) and outlet discharge coefficients (Cd), were determined
so that simulated values become close to the measured values. The head regulator and outlets were calibrated by
Figure 3. Supply and irrigation requirements for Shingrai Minor
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
NUMERICAL MODELLING FOR MANAGEMENT OF CANAL IRRIGATION 449
development of head–discharge relationships between water levels in the canal above the crest of the outlets and
discharges through the outlets. Another data set collected at 750 l s�1 was used for validation of the model for
Shingrai Minor.
Model accuracy for the calibration and validation was determined by calculating the model efficiency (ME) as
follows:
ME ¼ ðST� SEÞ=STwhere
ST ¼X
ððSimulatedDepth� ðX
ðMeasuredDepthÞ=nÞ2Þ
SE ¼X
ðSimulatedDepth�MeasuredDepthÞ2
The results of model calibration are presented in Figure 4. The Manning n values used in the calibration were
between 0.016 and 0.018 for lined reaches and 0.023 for unlined reaches. A model efficiency of 92% was obtained.
For validation of the model the model efficiency was 95%. Figure 5 shows the measured and simulated outlet
discharges. The differences between the simulated and measured outlet discharges were less than 5 l s�1.
SIMULATION OF OPERATIONAL SCENARIOS
Five different operational modes were assessed in order to determine the performance levels. The operational
modes assessed for Shingrai Minor were as follows:
1. Design full supply.
2. 80% of the design discharge.
3. 70% of the design discharge, which is considered to be close to the winter demand.
0
0.2
0.4
0.6
0.8
1
1.2
1.4
6000500040003000200010000
RD (m)
Dep
th (
m)
Measured
Simulated
Figure 4. Calibration of model with measured and simulated water levels at 846 l s�1
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
450 A. R. GHUMMAN ET AL.
4. 50% of the design discharge; to assess if the canal could be operated at low discharge when the requirements are
low.
5. Closure of the canal at night; to assess if night closure of the canal was a feasible option in the periods of low
requirement.
PERFORMANCE ASSESSMENT
Performance of canal outlets was evaluated under the existing outlet configuration and the modified configuration,
at four operational levels. Delivery performance ratio (DPR) was used as the performance indicator, which is an
expression of the actual discharge divided by the target discharge at any location in an irrigation system (Murray-
Rust and Snellen, 1993).
Performance of outlets was considered good if it remained within �10% of the target discharge for the outlet,
which is the criterion used by the Irrigation Department (Government of NWFP, 1992). An additional performance
level of �30% was used (Murray-Rust and Halsema, 1998). Below this the performance of an outlet was
considered unacceptable.
PERFORMANCE WITH THE EXISTING OUTLET DIMENSIONS
At 100% discharge, 7 outlets were drawing within �10% of their design (Figure 6). At 80 and 70% discharges 5
outlets could receive within �10% of their revised target discharges. At 50% discharge only 3 outlets had
satisfactory performance. Using a performance level of �30%, 8 outlets could draw satisfactory discharges under
100, 80 and 70%.While at 50% 7 outlets could draw within 30% of the modified discharges. Performance of outlets
0
20
40
60
80
100
120
6000500040003000200010000
RD (m)
Dis
char
ge (l
/s)
Measured
Simulated
Figure 5. Calibration of model with measured and simulated outlet discharges
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
NUMERICAL MODELLING FOR MANAGEMENT OF CANAL IRRIGATION 451
1, 3 and 4 was unsatisfactory even at �30% performance level under most of the discharges. These outlets were
overdrawing. On the other hand outlets 5, 8 and 13 could draw less than their allocation.
The overall performance of canal was not high even under full supply level. From an operational point of view it
was feasible to operate the system at 70% of the full supply. At this discharge it was possible for all the outlets to at
least draw discharges with which farmers could irrigate, i.e. more than 15 l s�1. At 50% discharge three outlets drew
less than 15 l s�1. At such low discharges interference by the farmers has been observed. In this situation they
usually place temporary stone weirs across the canal to raise the water level and get more water into the outlet. This
type of interference represents the desire of farmers to irrigate their fields quickly rather than to stay for a long time
in the field irrigating.
PERFORMANCE WITH MODIFIED OUTLET DIMENSIONS
Outlet dimensions were modified to achieve a better match between the observed discharge through the outlet and
the target discharge. This was done by running the CANALMAN model for several iterations. Those modified
dimensions were selected at which the simulated discharges became equal to the design discharges. Two outlets
were provided with roof blocks to convert them from weirs to orifices. This reduced their sensitivity and thus
became less sensitive to fluctuations in water levels in the canal. For the rest of the outlets the widths were modified
(Table II).
At a performance level of �10%, all the outlets had good performance with DPR close to 1 at 100% of design
discharge (Figure 7). Performance of 5 outlets was good at all the discharges, while 9 outlets performed well above
50% discharge. With a performance level of �30%, all the outlets showed good performance with only 4 outlets
showing low performance at only 50% canal flow.
Under the existing configuration, outlet 4 was highly sensitive to low discharges in the canal. The reason was its
construction as an open flume, although it was designed as an AOSM. It can be seen that the performance of outlet 4
did show improvement after modification; its DPR was still higher at low discharge in the canal.
0.00
0.50
1.00
1.50
2.00
2.50
1R 2R 3L 4L 5R 6R 7R 8R 9L 10L
11R
12T
L
13T
F
Outlet
DP
R (
%)
100% Discharge
80% Discharge
70% Discharge
50% Discharge
Figure 6. Delivery performance ratio at different discharges with existing outlet configuration
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
452 A. R. GHUMMAN ET AL.
OUTLET DISCHARGES WITH ACTUAL AND MODIFIED OUTLET DIMENSIONS
Discharges of the outlets were compared under actual and modified dimensions for our different operational levels
(Figures 8–11). The ideal water allowances are represented by the horizontal lines. The results indicated an overall
improvement in the discharges of the outlets. However, at 50% discharge due to lowwater level in the canal, outlet 4
behaves like a weir and draws more water. Outlets 6 and 8 cannot get their allocated discharges at 50% discharge
due to low downstream slopes in the watercourses.
Table II. Actual and modified outlet dimensions
Outlet Type Design Actual Modified
RD (m) No Design Actual(existing)
Modified Width(cm)
Height(cm)
Width(cm)
Height(cm)
Width(cm)
Height(cm)
18 1R1 Crump Weir Crump Weir AOSM 21.6 – 21.0 – 17.0 15.01253 2R Crump Weir Crump Weir Crump Weir 21.0 – 30.0 – 26.0 –1254 3L2 Crump Weir Crump Weir Crump Weir 23.5 – 23.50 – 16.0 –1882 4L AOSM Open Flume AOSM 8.54 – 8.65 – 8.5 22.01886 5R Open Flume Open Flume Open Flume 8.23 – 8.23 – 11.0 –2907 6R Crump Weir Crump Weir Crump Weir 60.7 – 62.0 – 62.0 –2908 7R Crump Weir Crump Weir Crump Weir 20.7 – 21.0 – 16.0 –2910 8R Crump Weir Crump Weir Crump Weir – – 25.50 – 27.0 –3550 9L Crump Weir Crump Weir Crump Weir – – 18.0 – 18.0 –3554 10L Crump Weir Crump Weir Crump Weir – – 15.0 – 12.5 –5288 11R Crump Weir Crump Weir Crump Weir – – 45.0 – 30.0 –5290 12TL Crump Weir Crump Weir Crump Weir – – 18.0 – 14.0 –
1R¼ right outlet.2L¼ left outlet.
0.00
0.50
1.00
1.50
2.00
2.50
1R 2R 3L 4L 5R 6R 7R 8R 9L 10L
11R
12T
L
13T
F
Outlet
DP
R (
%)
100% Discharge
80% Discharge
70% Discharge
50% Discharge
Figure 7. Delivery performance ratio at different discharges with modified outlet configuration
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
NUMERICAL MODELLING FOR MANAGEMENT OF CANAL IRRIGATION 453
The main errors in the outlets which caused underperformance were either in design or construction. Outlet 1R
was designed as a Crump Weir, although it should have been designed as an AOSM outlet. Outlet 2 R contained a
design as well as a construction error. Outlets 3, 5, 11 and 12 had design errors while outlet 4 was a construction
error.
OPENING AND CLOSURE OF CANAL
From the previous sections it is evident that there is a need to operate the canal at discharges lower than 80%
of the design discharge. But on the other hand the performance of canal at discharges below 80% is not
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1R 2R 3L L4 5R R6 7R 8R L9 10L 11
R LT21 1FT3
Outlets
l/s/h
a
Allocation
Actual
Modified
Figure 9. Allocated, actual and modified discharge at 80% of design discharge at 677 l s�1
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1R 2R L3 L4 5R 6R 7R 8R L9 10L 11
R21
LT1
FT3Outlets
l/s/h
a
Allocation
Actual
Modified
Figure 8. Allocated, actual and modified discharge at design discharge of 846 l s�1
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
454 A. R. GHUMMAN ET AL.
satisfactory. An additional operational option of opening and closing of the canal was explored using
hydraulic modelling. The response of the canal was studied with the discharge in the canal initially zero and
then it was increased to full supply. This is the situation of opening a closed canal and bringing it to full
supply. The whole canal was able to attain steady state in 3.5 h. After this time all the outlets of the canal were
drawing the maximum discharge and were in steady state (Figure 12). The simulation of canal closure
indicates that for the tail outlets of the canal, flow would be available for up to 3 h after closure of the Shingrai
Minor (Figure 13).
Field observations have shown that in periods of low demand farmers who have their irrigation turn at night
start to skip their night turns and instead irrigate in the day-time. Because farmers do not irrigate at night in
periods of low demand irrigation water is potentially wasted during the night in most of the secondary canals
and the shorter lag times involved in filling medium and small secondary canals. An additional strategy is
0.00
0.20
0.40
0.60
0.80
1.00
1.20
R1 R2 3L L4 R5 6R 7R R8 9L L01 1R1
1LT2
FT31Outlets
l/s/h
a
Allocation
Actual
Modified
Figure 10. Allocated, actual and modified discharge at 70% of design discharge at 592 l s�1
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
R1 R2 L3 L4 5R R6 R7 R8 9L 01L
1R1
12LT 31
FTOutlets
l/s/h
a
Allocation
Actual
Modified
Figure 11. Allocated, actual and modified discharge at 50% of design discharge at 423 l s�1
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
NUMERICAL MODELLING FOR MANAGEMENT OF CANAL IRRIGATION 455
0
20
40
60
80
100
120
300250200150100500
Elapsed Time (min)
Flo
w R
ate
(l/s
)1R
2R
3L
4L
5R
6R
7R
8R
9L
10L
11R
12TL
Figure 12. Outlet hydrographs after opening empty canal at full supply
0
20
40
60
80
100
120
300250200150100500
Elapsed Time (min)
Flo
w R
ate
(l/s
)
1R
2R
3L
4L
5R
6R
7R
8R
9L
10L
11R
12TL
Figure 13. Outlet hydrographs after closing the steady state canal at full supply
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
456 A. R. GHUMMAN ET AL.
proposed under which all the medium and small secondary canals of the system in the head and middle
reaches can be closed at night and reopened during the day, in November and December. This will ensure
water saving at night.
CONCLUSIONS
The study demonstrates the usefulness of hydrodynamic models in understanding the behaviour of a canal. The
one-dimensional hydrodynamic model CANALMAN was applied to a secondary canal in the Upper Swat Canal
Irrigation System in the North West Frontier Province of Pakistan.
The model was calibrated on the maximum design discharge of 846 l s�1. After calibration of the model,
the influence of modification in outlet dimensions was evaluated at 100, 80, 70 and 50% of design discharge.
The modifications in outlet dimensions did improve the overall performance of the canal. However, the best results
were obtained at full supply and 80%. Operation of the canal at discharges below 80% of the design supply cannot
be recommended. An additional operational option of opening and closing the canal during the day and night
respectively has been recommended at a time when the demand is low as an alternative to operation of the canal at
discharges below 80% of the design discharge.
The following main conclusions can be drawn from the study:
1. CANALMAN is a suitable model for evaluation of secondary canals.
2. Modifications in outlet dimensions improved the performance of the canal.
3. Operation of the canal at discharges below 80% of the full supply is not recommended in such canals even after
outlet modification.
4. Opening and closure of the canal provides an alternative for operation of the canal at lower than 80% discharges.
ACKNOWLEDGEMENTS
We would like to thank the Biological and Irrigation Department, Utah State University, Utah Logan, USA, for
making the CANALMAN software freely available which was used in this study. We also appreciate the excellent
data collected by Mr Muslim Shah during his MSc study at the Department of Water Management, NWFP
Agricultural University Peshawar. The cooperation of the Irrigation Department is also greatly appreciated in
providing the design data and drawings of the Shingrai Minor. Special thanks go to the International Water
Management Institute Pakistan for providing the digitized map of the Upper Swat Canal Irrigation System.
REFERENCES
Ali I. 1993. Irrigation and Hydraulic Structures. Institute of Environmental Engineering and Research, NED University of Engineering and
Technology: Karachi, Pakistan.
Babar KS. 2000. Hydraulic Performance Evaluation of Pabbi Minor of Warsak Gravity Canal. Unpublished MSc thesis, Department of Water
Management, NWFP Agricultural University, Peshawar, Pakistan.
Bos MG. 1976. Discharge Measurement Structures. ILRI Publication No. 20 (Third revised edition 1989). International Institute for Land
Reclamation and Improvement: Wageningen, The Netherlands.
Dinshaw NC, Schuurmans W. 1993. Informed usage and potential pitfalls of canal models. Journal of Irrigation and Drainage Engineering,
ASCE 119(4).
Government of NWFP. 1992. Manual of Operation and Maintenance of Irrigation Systems. NWFP Government Printer: Peshawar.
Halsema G, van. 2002. Trial & re-trial; the evolution of irrigation modernization in NWFP, Pakistan. PhD dissertation, Wageningen University,
The Netherlands.
Khan MJ, Khan MZ, Ahmad S, Asrar M. 2000. Hydraulic performance evaluation of Surezai Minor of Warsak Gravity Canal Irrigation System.
Sarhad Journal of Agriculture 16(4).
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
NUMERICAL MODELLING FOR MANAGEMENT OF CANAL IRRIGATION 457
Merkley GP. 1997. CanalMan: A Hydraulic Simulation Model for Unsteady Flow in Branching Canal Networks, User’s Guide, Dept. of
Biological and Irrigation Engineering, Utah State University.
Murray-Rust DH, Halsema G, van. 1998. Effects of construction defects on hydraulic performance of Kalpani distributary, NWFP, Pakistan.
Irrigation and Drainage Systems 12(4): 323–339.
Murray-Rust DH, Snellen WB. 1993. Irrigation System Performance Assessment and Diagnosis. International Irrigation Management Institute:
Colombo.
Shah M. 2000. Hydraulic performance evaluation of Shingrai Minor of Upper Swat Canal Irrigation System. MSc thesis, Department of Water
Management, NWFP Agricultural University, Peshawar, Pakistan.
Shahrokhnia MA, Javan M. 2005. Performance assessment of Doroodzan irrigation network by steady state hydraulic modeling. Irrigation and
Drainage Systems 19(4).
Strelkoff T. 1969. One-dimensional equations of open-channel flow. J. Hydraulics Div., ASCE 95(HY3): 861–876.
Swabi SCARP. 1991. Irrigation water requirements, Working Paper No. 3. Swabi Salinity Control and Reclamation Project Consultants,
Peshawar, Pakistan.
Copyright # 2006 John Wiley & Sons, Ltd. Irrig. and Drain. 55: 445–458 (2006)
DOI: 10.1002/ird
458 A. R. GHUMMAN ET AL.