twenty-five years of performance - a …docs.trb.org/prp/13-1036.pdf · has validated idot’s...
TRANSCRIPT
TWENTY-FIVE YEARS OF PERFORMANCE - A VALIDATION OF ILLINOIS’
MECHANISTIC-EMPIRICAL PAVEMENT DESIGN ON US 20 AND US 50
Juan David Pava
Word Count = 7,207
Springfield, Illinois
August 1, 2012
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava i
ABSTRACT
In the summer of 1986, the Illinois Department of Transportation (IDOT) built four demonstration
sections to validate the proposed mechanistically-based pavement design procedures under development
by the University of Illinois. Multiple variables were taken into consideration in order to determine a
valid correlation between pavement design inputs and pavement performance.
After 25 years of service, these sections have provided great value to IDOT in the development of
pavement design procedures, policies and standards, and in general a better understanding of the
mechanics of pavement performance. The knowledge acquired from the four sections supports IDOT’s
practice in the use of performance graded binders, joint spacing in jointed concrete pavements, jointed
concrete and full-depth hot-mix asphalt pavement thickness design, and subgrade selection. This study
has validated IDOT’s mechanistic pavement design procedure, proving that the theory behind the 1986
design was correct. Since then, these sections and extensive laboratory testing and investigation have
allowed IDOT to further refine the mechanistic pavement design procedure to include more accurate
material properties.
In addition to improving design procedures, having 25 years of data and observing the
deterioration and rehabilitation of certain sections have allowed IDOT to fine tune the maintenance
models used for pavement type selection between flexible and rigid alternatives.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava ii
ACKNOWLEDGEMENTS
The author gratefully thanks the contribution of the following people without whose help and support this
paper would have not been possible: David Lippert, Amy Schutzbach, and LaDonna Rowden for their
help with the scope of the project Michael Brownlee, Joe Vespa, Charles Wienrank, and David Lass, for
their assistance in data collection, analysis and for providing historical information; and Amy Schutzbach
and LaDonna Rowden for their guidance and assistance in this paper.
DISCLAIMER
The contents of this paper reflect the views of the author, who is responsible for the facts and accuracy of
the data represented in this paper. The contents do not necessarily reflect the official views or policies of
IDOT. This paper does not constitute a standard, specification, or regulation at IDOT.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava iii
Table of Contents
ABSTRACT ................................................................................................................................................... i
ACKNOWLEDGEMENTS .......................................................................................................................... ii
DISCLAIMER .............................................................................................................................................. ii
INTRODUCTION AND HISTORICAL PERSPECTIVE ........................................................................... 1
ORIGINAL CONSTRUCTION DETAILS .................................................................................................. 1
Project 1 .................................................................................................................................................... 1
Project 2 .................................................................................................................................................... 1
Project 3 .................................................................................................................................................... 3
Project 4 .................................................................................................................................................... 3
Instrumentation ......................................................................................................................................... 6
Quality Control ......................................................................................................................................... 6
Objectives ................................................................................................................................................. 7
PERFORMANCE MONITORING .............................................................................................................. 8
Early age study .......................................................................................................................................... 8
Continuous Monitoring ............................................................................................................................. 9
Traffic Consumption ............................................................................................................................... 15
CONCLUSION ........................................................................................................................................... 16
BIBLIOGRAPHY ....................................................................................................................................... 17
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 1
TWENTY-FIVE YEARS OF PERFORMANCE - A VALIDATION OF ILLINOIS’
MECHANISTIC-EMPIRICAL PAVEMENT DESIGN ON US 20 AND US 50
INTRODUCTION AND HISTORICAL PERSPECTIVE
For several decades the Illinois Department of Transportation (IDOT) used the empirically-based design
procedure developed from the American Association of State Highway Officials (AASHO) Road Test
conducted in Illinois in 1959 and 1960. Limitations of these empirical design procedures became apparent
with the development of new and improved materials, cross sections, and construction technologies not
used in the AASHO Road Test (Thompson & Gomez, 1983). In order to progress to the next generation
of pavement design, IDOT decided to build four demonstration sections to validate a proposed
mechanistically-based design procedure under development by the University of Illinois (Thompson &
Cation, 1986) (Zollinger & Barenberg, 1989).
The construction of the four sections began in the summer of 1986. Projects 1 and 2 are sections
of US 20, northeast of Freeport, Illinois, in Stephenson County. Projects 3 and 4 are part of US 50,
between Lebanon and Carlyle, Illinois, in St. Clair and Clinton Counties. Figure 1 shows the location of
all four projects. Multiple variables were taken into consideration in order to determine a valid correlation
between pavement design inputs and pavement performance. The demonstration projects were established
in an experimental feature work plan entitled “Evaluating Pavement Design Procedures.”
This paper presents a compendium of technical data about the four projects built, major
reconstruction and maintenance events, their significance to the state, and an analysis of their behavior
throughout time based on field surveys, instrumentation data, and site and laboratory testing.
ORIGINAL CONSTRUCTION DETAILS
Project 1
This project is located on US 20, originally known as FA 401, northeast of Freeport, Illinois in
Stephenson County. Project 1 was built under contract 40463; this contract consisted of 3.8 miles of full-
depth hot-mix asphalt (HMA) pavement. The cross section was a 13-inch HMA pavement containing two
different types of asphalt binder; Section A, beginning at Henderson Road and extending 1.65 miles west,
was constructed with AC-10, which is similar to Performance Graded (PG) 58-22 asphalt binder; Section
B, beginning at Henderson Road and extending 2.15 miles east, was constructed with AC-20, which is
similar to PG 64-22. The main objective of this Project was to evaluate the influence of asphalt binder
viscosity on pavement performance.
Project 2
This project is adjacent to Project 1 on US 20. This project was built under contract 40455 and consisted
of 2.8 miles of Portland cement concrete (PCC) pavement. The cross section is a 10-inch PCC slab on
top of a 4-inch Cement Aggregate Mixture (CAM) II stabilized subbase. This section includes four
different designs as follows:
1. 40-foot jointed reinforced concrete pavement (Sections D and G4)
2. 20-foot jointed plain concrete pavement with dowels (Sections C and F)
3. 15-foot jointed plain concrete pavement with dowels (Sections E and H)
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 2
FIGURE 1 Location of projects 1 through 4.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 3
4. Hinge-jointed concrete pavement with three different hinge-joint designs (A1, A2, and B).
a. Design A1 consists of 20-foot joints with alternating tie bars and dowels (Section G1).
b. Design A2 has the same configuration as Design A1, but it includes full-width pavement
fabric for reinforcement (Section G2).
c. Design B consists of 13.3-foot joints with the pattern of a doweled joint followed by two
tied joints (Section G3).
Figure 2 shows the layout of Project 2. Figure 3 shows the three different hinge-joint
configurations.
FIGURE 2 Project 2 layout.
Note 1: three 400-ft hinge-jointed sections. G1 = Design A1; G2 =Design A2; G3 =Design B.
Project 3
This project is located on US 50, between Lebanon, Illinois, and the Sugar Creek Bridge, in St. Clair and
Clinton Counties. This project was built under contracts 40448 (St. Clair County) and 40315 (Clinton
County). These contracts consisted of 7.5 miles of full-depth HMA pavement with cross section
thicknesses of 9.5, 11, and 12.5 inches to evaluate the effects of pavement thickness on performance. The
primary cross section design for this project is an 11-inch full-depth HMA pavement over a lime-
modified subgrade with underdrains. Sections were also built with and without lime-modified subgrade
and with and without underdrains to evaluate the significance of each component in the design. Figure 4
shows the layout of this project.
Project 4
This project is located on US 50 from St. Rose Road to IL 127. Project 4 consisted of 9.7 miles of PCC
pavement on a 4-inch thick CAM II stabilized subbase and was built under two contracts. Contract 40317
consisted of 4.0 miles of continuously reinforced concrete pavement (CRCP) with thicknesses of 7.5, 8.5,
and 9.5 inches to evaluate the effects of concrete pavement thickness on performance. Contract 40456
consisted of 5.7 miles of jointed PCC pavement which includes 4 different designs:
1. 40-foot jointed reinforced concrete pavement.
2. 20-foot jointed plain concrete pavement with dowels.
3. 15-foot jointed plain concrete pavement with dowels.
4. Hinge-jointed concrete pavement with the same designs used in Project 2.
All jointed pavement designs were constructed with thicknesses of 7, 8, or 9 inches. Figure 5 shows
the layout of this project.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 4
FIGURE 3 Hinge-joint panel designs.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 5
FIGURE 4 Project 3 layout.
FIGURE 5 Project 4 layout.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 6
Instrumentation
Several types of gauges were installed throughout all four projects in order to evaluate the response of the
pavement to loading, freeze-thaw, and other weather events. Strain gauges were installed in the concrete
sections to verify theoretical strains due to wheel loads. Detailed information regarding the
instrumentation of the four projects is available in IDOT Physical Research Report (PRR) No. 112 (Reed
& Schutzbach, 1993) (Reed & Schutzbach, 1993).
Quality Control
Prior to construction, a thorough soil investigation was conducted to determine the Illinois Bearing Ratio
(IBR; similar to California Bearing Ratio) of each section. Subgrade stability measurements were
acquired using nuclear density gauges. Mix designs for the flexible and rigid sections were designed
according to the IDOT specifications. Since these two projects were part of the first full-depth, full-
quality sections constructed in the state, both full-depth HMA projects complied with IDOT’s Special
Provision for Bituminous Concrete Overlay on Interstate Highways (Illinois Department of
Transportation, 1985) (Illinois Department of Transportation, 1985). Mixture designs for Projects 1 and 3
are shown in Table 1.
TABLE 1 Hot-Mix Asphalt Design Data
Test Surface Binder
Specification Project 1 Project 3 Specification Project 1 Project 3
Gradation, %
passing
1” -- 100 100 100
3/4” 100 100 100 82-100 98 92
1/2” 90-100 99 100 50-82 73 68
3/8” 66-100 89 99 -- 56 56
#4 24-65 53 58 24-50 40 38
#8 16-48 33 36 16-36 30 30
#16 10-32 26 26 10-25 23 23
#30 -- 21 18 -- 18 15
#50 4-15 13 11 4-12 11 8
#100 3-10 8 7 3-9 7 5
#200 2-6 4.9 5.5 2-6 4.0 3.5
Asphalt, % of
total mix 3-9 5.7 7.1 3-9 4.7 5.3
Air Voids % 3-5 4.0 5.0 3-5 5.0 4.8
Voids in the
mineral
aggregate, %
15 Min 14.6 16.0 14 Min 14.0 14.9
Marshall
stability, lbs. 2000 Min 2425 2345 2000 Min 2630 2140
Marshall Flow,
1/100” 8-16 7.2 8.2 8-16 8.2 8.8
Tensile
Strength Ratio -- 0.50 -- 0.76 0.73
-- Denotes No Specification
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 7
All of the mix designs were developed using the Marshall Design Procedure (The Asphalt
Institute, 1979, March) (The Asphalt Institute, 1979, March). The only production results that were not
within the specified design parameters were the air voids in the surface mix using AC-20 binder in Project
1. The average air void content for production was 2.3 percent, compared to the specified 4.0 percent.
This problem was not identified until after production was completed. Cores taken during production of
Project 1 showed the air voids were within the acceptable range. All other production test results
complied with the specifications.
There were two PCC designs for the rigid sections, one for Project 2 and one for Project 4.
Table 2 shows the breakdown of each concrete mix design.
TABLE 2 Concrete Design Data
Ingredient Quantity, Pounds
Project 2 Project 4
Cement 455 575
Fly Ash 120 --
CA – 07 1967 1890
FA – 01 1036 1123
Water 259 249.9
Total 3837 3837.9
Flexural strength measurements were determined for these mixes at 3-, 7-, 14-, 28-, and 90-days.
In addition to this, slump and air content were taken during production. Although some individual
measurements did not meet the specifications, the average values were well within the specified ranges.
Project 2 mix average/specified values were: slump of 2.2/3.0 inches, air content of 6.87/5-8%, and 14-
day flexural strength of 826/620 psi. The average/specified values for Project 4 were: slump of 2.83/3.0
inches, air content of 6.41/5-8%, and 14-day flexural strength of 827/650 psi. Detailed testing information
was also published in IDOT PRR No. 112 (Reed & Schutzbach, 1993) (Reed & Schutzbach, 1993).
Objectives
There were four main objectives in the original work plan.
1. Validate the early stage performance of the mechanistically-based design for asphalt pavement
developed by the University of Illinois by comparing Falling Weight Deflectometer (FWD)
deflections, and assess the benefits of different pavement thicknesses, use of underdrains, and use of
lime-modified subgrade.
2. Measure strains and deflections on the PCC sections; compare results to the predicted values from the
mechanistically-based design procedure; and assess the benefits of underdrains, slab thicknesses, and
joint sealing on pavement performance.
3. Evaluate the effect of different asphalt cement viscosity, AC-10 and AC-20.
4. Evaluate the effect of joint configuration in jointed PCC pavement. Three different joint spacings
were to be evaluated, 40-, 20-, and 15-feet, as well as three hinge-joint designs.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 8
PERFORMANCE MONITORING
As part of this study, the four projects have been monitored throughout their life to capture pavement
performance. Various types of monitoring have taken place including: video images, ride quality
(smoothness and rutting), condition rating surveys (CRS), and manual distress surveys. The CRS is a
factor in highway program development. This value presents an opportunity to review the highway
network, provides overall condition of the state highway system, gives input into the legislative/budgeting
processes, and allows calculation of pavement needs. CRS ratings range from 1 (complete failure) to 9
(new pavement), and a value between 5.5 and 6 generally triggers rehabilitation.
Early age study
IDOT published a five-year performance evaluation in 1993 based on surveys collected in 1990 and 1992
(Reed & Schutzbach, 1993) (Reed & Schutzbach, 1993). The findings of the five-year evaluation are
summarized as follows.
Full-depth HMA Pavements
Early studies of the sections showed the expected behavior of increased structural
performance with increased thickness. Pavement thicknesses of 9.5, 11, and 12.5 inches
were studied.
Generally higher deflections were observed in thinner pavement.
There was no clear correlation between the asphalt viscosity rating and rut or thermal
crack susceptibility at that point in time. IDOT has since transitioned from viscosity-
graded binders to performance-graded binders. AC-10 and AC-20 are comparable to
PG 58-22 and PG 64-22, respectively.
Lime modification of the soil yielded higher modulus values, providing a better
construction platform and better life of the pavement. Two of the three sections requiring
early age patching and a large percentage of the 9.5-inch pavement did not have a lime-
modified subgrade. Because of this, some of the poorer structural performance could be
attributed to the untreated subgrades.
The use of underdrains did not show a direct correlation to the distresses found in the
early studies. The conclusion was that underdrains did not have a measurable effect in
pavement performance. General performance trends at IDOT have shown the importance
of proper drainage, therefore now most pavement cross sections include underdrains.
PCC Pavement Sections
The CRC sections performed equally for the first five years for all thicknesses (7, 8, and
9 inches) that were evaluated.
In the jointed sections, the shorter panels showed better performance, but thinner slabs
also exhibited more distresses. The strain gauges also confirmed that thicker slabs
experienced lower strains.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 9
The value of underdrains was not tangible in the early stage evaluation.
Sealed longitudinal joints did help to lower the moisture levels of the subgrade.
It was clear that joint spacing played an important role in the performance of pavements.
Within the first five years of service for Project 2, neither the 15- or 20-foot sections
exhibited any distresses, while all of the 40-foot jointed panels had at least one crack. The
hinge-jointed panels also showed good performance on these rural sections. However,
long-term monitoring in Illinois showed cracking in hinge-jointed pavements in urban
areas due to the increased presence of discontinuities; median nosing, cut-outs, side
streets, etc. In Project 4, only 5% of the 20-foot jointed slabs had cracked, while every
40-foot jointed slab was cracked. For this reason, the use of hinge-jointed design was
dropped, and in the early 1990’s IDOT’s pavement design shifted to use only jointed
plain concrete pavement with doweled 15-foot joint spacing.
Continuous Monitoring
CRS values for Projects 1 and 2 were collected every even year from 1986 until 1994 and every
odd year from 1995 until 2011. Manual field surveys were collected in 1990, 1992, 1993, 1995, 1997, and
2010. Figure 6 shows the CRS values for Projects 1 and 2 versus year. This figure shows the functional
performance of the sections throughout time. The effect of rehabilitation events is evident in the sections.
CRS rating sections are selected arbitrarily based on performance observed, pavement surface or critical
points. Consecutive sections with the same CRS values were grouped together in the following figures.
FIGURE 6 CRS values for Projects 1 and 2 versus year.
Sections A and B are HMA sections, Sections C though H are PCC sections.
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
1980 1985 1990 1995 2000 2005 2010 2015
CR
S
Year
CRS vs Year US 20
A
B
C - H
Sections
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 10
Project 1 was overlaid in 2007 under contract 64577. The overlay consisted of 0.75 inch of
leveling binder and 1.5 inches of Superpave HMA surface. Both the CRS and most recent field survey in
2010 showed a better performance of Section A compared to Section B due to the more flexible binder
(AC-10 vs. AC 20). For Project 2, part of Section C and the first 400 feet of Section D were reconstructed
in 2007 under contract 64577 as 15-foot jointed plain concrete with doweled joints as part of the
realignment and addition of westbound lanes. The reconstructed section did not show any distresses. The
remaining portion of Section D, 40-foot joints, showed low and medium severity cracks in every slab and
extensive patching. Sections E through G3 did not show many distresses. Section G4, 40-foot joints,
presented cracks in every slab mostly of medium severity and some high severity and a significant
percentage of the area was patched. A summary of the latest condition survey for each project is shown in
Table 3.
TABLE 3 Summary of the latest condition for Projects 1 and 2
Project Section Pavement Type Status of Pavement Condition in 2010
1
A Full-depth HMA,
AC-10,13 inches
Overlaid in 2007 with
0.75 inch leveling binder
and 1.5 inch HMA surface
19 low severity transverse
cracks
B Full-depth HMA,
AC-20, 13 inches
Overlaid in 2007 with
0.75 inch leveling binder
and 1.5 inch HMA surface
65 low severity transverse
cracks
2
C 20-foot Jointed
PCC, 10 inches
First 300 feet – Original 1 patch, 1 low severity crack
Remainder –
Reconstructed in 2007* No distress
D 40-foot Jointed
PCC, 10 Inches
First 400 feet –
Reconstructed in 2007* No distress
Remainder – Original
All 72 slabs cracked, 75% low
severity, 25% medium severity,
3% of section patched, typically
mid-panel
E 15-foot Jointed
PCC, 10 inches Original
1 low severity corner break,
4 low severity spalls
F 20-foot Jointed
PCC, 10 inches Original
10 low severity cracks,
6 medium severity cracks
G1 Hinge-joint design
A1, 10 inches Original
3 low severity cracks,
1 medium severity crack
G2 Hinge-joint design
A2, 10 inches Original 1 low severity crack
G3 Hinge-joint design
B, 10 inches Original
2 low severity cracks,
1 medium severity crack, some
spalls at hinge-joints
G4 40-foot Jointed
PCC, 10 inches Original
Cracks in every panel, mostly
medium severity, some low
severity, and 2% patching
H 15-foot Jointed
PCC, 10 inches Original
30 feet of longitudinal cracking
eastbound,1 corner break and
7 low severity transverse cracks
* Reconstruction unrelated to performance and due to facility improvement.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 11
CRS values for Projects 3 and 4 were collected every even year from 1986 until 2010. Complete
manual field surveys were collected in 1990, 1992, 1993, and 2010, and partial surveys were collected in
1995, 1997, and 1999. Figure 7 shows the CRS values for Projects 3 and 4 by year. This figure shows the
functional performance of the sections throughout time. The effect of rehabilitation events in the sections
is apparent in this figure.
FIGURE 7 CRS values for Projects 3 and 4.
4.0
5.0
6.0
7.0
8.0
9.0
10.0
1984 1989 1994 1999 2004 2009
CR
S
Year
CRS vs Year - Project 3 - HMA
A-B
C , D , E, H
I
J, K, L
M, MI
N
O, P
4.0
5.0
6.0
7.0
8.0
9.0
10.0
1984 1989 1994 1999 2004 2009
CR
S
Year
CRS vs. Year - Project 4 - PCC
R - Z
AA
BA - FA
GA
HA - MA
NA
OA - RA
Sections
Sections
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 12
Project 3 has received partial overlays throughout its life. In 1994, Sections A, B, J, K, L, M, and
M1 were overlaid. All of these sections were originally 9.5 inches thick. Sections A and B’s overlays
were triggered by rutting. These sections were originally constructed with AC-10 and were overlaid with
2.25 inches of recycled HMA with AC-20 binder. Sections J and K also exhibited rutting and were
overlaid with 3 inches of HMA. Sections K, M, and M1 required extensive patching prior to being
overlaid. Sections K and M were the only two sections with untreated subgrade and Sections M and M1
did not have underdrains. These sections exhibited severe stripping and were overlaid with 2.25 to 3
inches of HMA. Sections N, O, and P were overlaid in 2007 under contract 76A79. These sections
showed high occurrences of alligator cracking, raveling, block cracking, and centerline cracking in the
1999 distress survey. The CRS values ranged in the low 5’s in 2006. These sections were milled and
filled with 2.25 inches of Superpave HMA.
Sections GA through RA from Project 4 received an overlay in 2008. These sections were
overlaid under contract number 76B12. The last manual survey recorded before the overlay of these
sections dates back to 1997. In this survey, it was observed that the 40-foot jointed sections exhibited a
high number of medium- and low-severity panel cracks. Some patching was also noticed in this survey.
The 20-foot jointed and hinge-jointed sections did not show many distresses. All sections were overlaid
with 2.25 inches of HMA binder and 1.5 inches of HMA surface. The CRS values for these sections
ranged between 6.0 and 6.5 in 2006; whereas in 2008, CRS values ranged between 8.0 and 9.0. The latest
visual inspection of Project 4 took place in 2010. This survey showed a high number of medium- and
low-severity transverse cracks along the bare sections and a few low- and medium-severity transverse
cracks on the overlaid sections. These distresses were observed mainly in the 40-foot jointed sections. A
summary of the most recent condition survey for Projects 3 and 4 is summarized in Table 4 and Table 5,
respectively.
Detailed survey data was published by IDOT in PRR No. 159, Performance Monitoring of
Mechanistically Designed Pavements 2010 Data Collection (Pava, 2011, March ) (Pava, 2011, March ).
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 13
TABLE 4 Latest condition of Project 3
Project Section Thickness,
Inches Binder Subgrade Underdrains Status of Pavement Condition in 2010
3
A 9.5 AC-10 LM Yes Overlaid in 1994 with 2.25 inches of HMA due
to rutting
Centerline deterioration, raveling and weathering,
and some longitudinal cracks noticed.
B 9.5 AC-10 LM Overlaid in 1994 with 2.25 inches of HMA due
to rutting
Centerline deterioration, and raveling and
weathering noticed.
C 12.5 AC-10 LM Original Low block cracking, centerline deterioration, and
raveling and weathering noticed.
D 12.5 AC-10 LM Yes Original Low block cracking, centerline deterioration, and
raveling and weathering noticed.
E 12.5 AC-20 LM Yes Original Low block cracking, centerline deterioration, and
raveling and weathering noticed.
H 12.5 AC-20 LM Original Low block cracking, centerline deterioration, and
raveling and weathering noticed.
I 9.5 AC-20 LM Yes Original Low block cracking, centerline deterioration, and
raveling and weathering noticed.
J 9.5 AC-20 LM Yes Overlaid in 1994 with 3 inches of HMA due to
rutting.
Centerline deterioration and raveling and
weathering noticed.
K 9.5 AC-20 Overlaid in 1994 with 3 inches of HMA due to
rutting. Patching was required prior to overlay.
Centerline deterioration and raveling and
weathering noticed.
L 9.5 AC-20 LM Yes Overlaid in 1994 with 3 inches of HMA due to
rutting. Patching was required prior to overlay.
Block cracking, centerline and center of lane
deterioration, raveling and weathering noticed.
M 9.5 AC-20 LM
Overlaid in 1994 with 2.25 to 3 inches of HMA
due to stripping. Patching was required prior to
overlay.
Block cracking, centerline deterioration and
raveling and weathering noticed.
M1 9.5 AC-20
Overlaid in 1994 with 2.25 to 3 inches of HMA
due to stripping. Patching was required prior to
overlay.
Block cracking, centerline deterioration and
raveling and weathering noticed.
N 9.5 AC-20 LM Yes Milled and Filled with 2.25 inches of HMA
overlay in 2007.
Block cracking, centerline deterioration and
raveling and weathering noticed.
O 9.5 AC-20 LM Milled and Filled with 2.25 inches of HMA
overlay in 2007.
Block cracking, centerline deterioration and
raveling and weathering noticed.
P 11 AC-20 LM Yes Milled and Filled with 2.25 inches of HMA
overlay in 2007.
Block cracking, centerline deterioration and
raveling and weathering noticed.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 14
TABLE 5 Latest condition of Project 4
Project Section Thickness,
Inches
Joint
Spacing,
Feet
Under-
drains
Sealed
Joint Status of Pavement Condition in 2010
4
R 9.0
CRC
Yes Original 228 square feet of patching.
S 8.0 Yes Original 42 square feet of patching.
T 8.0 Yes Yes Original
U 8.0 Yes Original
V 8.0 Original
W 7.0 Original 792 square feet of isolated HMA Patch/OL and 2 punchouts.
X 7.0 Yes Original 2 medium severity punchouts.
Y 7.0 Yes Yes Original
Z 7.0 Yes Original
AA 9.5 20 Yes
Overlaid in 2011
with 3.75 inches of
HMA.
11 feet of low severity longitudinal cracks.
BA 9.5 40 Yes All panels showed mid-panel cracks mostly of high severity.
CA 8.5 40 Yes Yes All panels cracked, some more than once, most cracks of medium severity.
DA 8.5
HJ Yes On average 38 low severity cracks per lane were found. DB 8.5
DC 8.5
EA 8.5 40 Yes All panels cracked, some more than once, most cracks of medium severity.
FA 8.5 40 Yes Yes 76% of panels cracked, most cracks of medium severity.
GA 8.5 40
Overlaid in 2008
with 3.75 inches of
HMA.
Weathering and raveling throughout section. Few low severity transverse
cracks were recorded.
HA 8.5 40 Yes
IA 8.5 20 Yes
JA 8.5 20 Yes
KA 8.5 20 Yes Yes
Weathering and raveling throughout section. LA 8.5 20 Yes
MA 7.5 20 Yes Yes
NA 7.5 20 Yes
Weathering and raveling throughout section. Few low severity transverse
cracks were recorded.
OA 7.5 40
PA 7.5 40 Yes
QA 7.5 40 Yes Yes
RA 7.5 40 Yes
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 15
Traffic Consumption
One of the subjects of interest for IDOT was the correlation between traffic consumption and pavement
performance. Design Equivalent Single Axle Loads (ESALs) were determined for each of the test
sections, assuming poor subgrade and a 20-year design life. These values were compared to actual
cumulative ESALs values for each section when the section received an overlay. Table 6 shows the actual
cumulative ESALs of each section at the time of each overlay or as of December 31, 2011 if the section
was still bare. Percent consumption is defined as the ratio of actual cumulative ESALs to 20-year design
ESALs. For the HMA sections, these data show that the fatigue algorithm used in IDOT’s original design
procedure was conservative. Later fatigue work on Illinois specific mixes (Carpenter, 2006) (Carpenter,
2006) led to adoption of a less conservative fatigue algorithm in IDOT’s current design policy (Bureau of
Materials and Physical Reseach, 2011). Pavement performance monitoring in Illinois’ network has
showed that overlay timing is predicated by environmental factors, aging, and material issues rather than
traffic consumption. These data support IDOT’s practice that there is no direct correlation between
overlay timing and traffic consumption of the section since overlays were applied at consumption levels
ranging between 60% and 500%.
TABLE 6 Consumption of sections at time of major rehabilitation.
Project Section Pvmnt
Type
Thickness,
Inches
Design
ESALs1
1st Rehab Future
Rehab
Dec 2011
Year ESALs1 % Cons
2 ESALs
1 % Cons
2
1 A AC-10 13 3.5 2007 3.58 102% 4.59 131%
1 B AC-20 13 5.5 2007 3.58 65% 4.59 83%
2 C,D,F,G1,G2,G4 Jointed 10 11.7 5.96 51%
2 E,G3,H Jointed 10 18 5.96 33%
3 A,B AC-10 9.5 0.5 1994 0.64 128% FY 2012 3.14 628%
3 C,D AC-10 12.5 1.9 FY 2012 3.14 165%
3 E,H,I AC-20 12.5 2.6 FY 2012 3.14 121%
3 J,K AC-20 9.5 0.7 1994 0.64 91% FY 2012 3.14 449%
3 L,M,MI AC-20 9.5 0.7 1994 0.64 91% FY 2012 3.14 449%
3 N,O AC-20 9.5 0.7 2007 2.67 381% 3.25 464%
3 P AC-20 11 1.4 2007 2.67 191% 3.25 232%
4 AA,BA Jointed 9.5 2.6 2011 3.81 147% 3.81 147%
4 CA - FA Jointed 8.5 1.5 2011 3.73 249% 3.73 249%
4 DA, DB, DC Hinged 8.5 1.9 2011 3.73 249% 3.73 196%
4 GA - LA Jointed 8.5 1.5 2008 3.25 217% 3.7 247%
4 MA - RA Jointed 7.5 0.64 2008 3.25 508% 3.7 578%
4 R CRC 9 9.4 4.3 46%
4 S,T,U,V CRC 8 4.3 4.2 98%
4 W,X,Y,Z CRC 7 1.8 4.2 233%
1 ESALs in millions
2 Percent consumption = (Actual ESALs / Design ESALs) x 100
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 16
CONCLUSION
After 25 years of service, US 20 and US 50 have provided great value to IDOT in the development of
new pavement design procedures, policies, standards, and in general, a better understanding of the
mechanics of pavement performance. The knowledge acquired from the four sections supports IDOT’s
practice in multiple ways. Project 1 demonstrated the influence of asphalt binder in full-depth HMA
pavements. IDOT assumes use of a PG 64-22 for pavement design purposes and selects performance
graded binders for surface and top lift of binder depending on the traffic and the location of the project.
Projects 2 and 4 illustrated the importance of joint spacing in jointed concrete pavement performance.
Based on performance history, IDOT now constructs 15-foot dowel jointed slabs. Project 3 is evidence of
the value of correct pavement thickness and the influence of the subgrade in pavement performance.
IDOT currently requires 12 inches of improved subgrade (modified soil or aggregate) under all new
construction. This study validated IDOT’s mechanistic pavement design procedure, proving that the
theory behind the 1986 design was correct. These sections and extensive laboratory testing and
investigation have allowed IDOT to further refine the mechanistic pavement design procedure in order to
include more accurate material properties.
Additionally, having 25 years of data and observations on the deterioration and rehabilitation of
certain sections have allowed IDOT to fine tune maintenance models to improve pavement type selection
procedures.
The four projects have served IDOT as a life-sized laboratory on pavement performance. These
sections will continue to bring knowledge to IDOT in years to come by providing further understanding
of pavement performance and enhancing pavement design procedures.
TRB 2013 Annual Meeting Paper revised from original submittal.
Juan D. Pava 17
BIBLIOGRAPHY
Bureau of Materials and Physical Reseach. (2011). PAVEMENT DESIGN. In IDOT, Bureau of Design
and Environment Manual (pp. 54-1.1 - 54-9.12). Springfield: Illinois Department of
Transportation.
Carpenter, S. H. (2006). Fatigue Performance of IDOT Mixtures. Urbana: Illinois Center for
Transportation.
Heckel, L. (2000, September). Performance Monitoring og Mechanistically Designed Pavements.
Springfield, Illinois: Unpublished internal report, Illinois Department of Transportation.
Illinois Department of Transportation. (1985). Contract Documents for Contract Number 40448. St. Clair
County, Illinois: Illinois Department of Transportation.
Illinois Department of Transportation. (1997, April). Performance Monitoring of Mechanistically
Designed Pavements. Springfield, Illinois: Unpublished internal document, Illinois Department of
Transportation.
Illinois Department of Transportation. (Adopted October 1, 1983). Standard Specifications for Road and
Bridge Construction. Springfield, Illinois: Illinois Department of Transportation.
Illlinois Department of Transportation. (2012, May). Pavement Distress Manual. Springfield, Illinois:
Unpublished internal manual, Illinois Department of Transportation.
Pava, J. D. (2011, March ). Performance Monitoring of Mechanistically-Designed Pavements 2010 Data
Collection. Springfield, Illinois: Illinois Department of Transportation.
Reed, C. M., & Schutzbach, A. M. (1993). Evaluating Pavement Design Features. Five Year
Performance Evaluation of FA 401 and FA 409. Springfield, Illinois: Illinois Department of
Transportation.
The Asphalt Institute. (1979, March). Mix Design Methods for Asphalt Concrete and Other Hot-Mix
Types (MS-2). College Park, MD: The Asphalt Institute.
Thompson, M. R., & Cation, K. (1986). A Proposed Full-Depth Asphalt Concrete Thickness Design
Procedure. Urbana-Chamapign: University of Illinois.
Thompson, M. R., & Gomez, M. (1983). Structural Coefficients and Thickness Equivalency Ratios.
Urbana-Champaign: University of Illinois.
Wienrank, C. (2007, April). Traffic Update for Eight Structural Performance Sections. Illinois
Department of Transportation. Springfield, Illinois: Unpublished internal document.
Zollinger, D. G., & Barenberg, E. J. (1989). Proposed Mechanistic Based Design Procedure for Jointed
Concrete Pavements. Urbana-Champaign: University of Illinois.
TRB 2013 Annual Meeting Paper revised from original submittal.