tutorial mrp
TRANSCRIPT
![Page 1: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/1.jpg)
Material Requirement Planning
Basic term
Prepared by; Muhammad Fahmi Md Idris
![Page 2: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/2.jpg)
Product Structure TreeAli producing Bicycle for Amen-Bshop and he expected to deliver 10 units of bicycles in week 1 to Amen-Bshop. The basic components used to assemble a set of bicycle are 1 unit of handle bars and 1 unit of frame, assemble with 2 units of wheels.
![Page 3: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/3.jpg)
Bill of Material
Component Unit Quantity Total Q’tty (Week 1)
Bicycle (B) 1 1 10
Handle Bars (H) 1 1 10
Frame Assembly (FA) 1 1 10
Frame (F) 1 1 10
Wheels (W) 2 2 20
Prepare a BoM of each component for each order of Bicycle component
![Page 4: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/4.jpg)
Time-phase assembly chart
Refer lead time to draw time-phase assembly chart
1)
ComponentLead Times(Minutes)
Bicycle (B) 1
Handle Bars (H) 1
Frame Assembly (FA) 2
Frame (F) 2
Wheels (W) 3
![Page 5: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/5.jpg)
Time-phase assembly chart
Start = Right Left 2)
ComponentLead Times(Minutes)
Bicycle (B) 1
Handle Bars (H) 1
Frame Assembly (FA) 2
Frame (F) 2
Wheels (W) 3
![Page 6: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/6.jpg)
Time-phase assembly chart
Draw the line 3)
B
ComponentLead Times(Minutes)
Bicycle (B) 1
Handle Bars (H) 1
Frame Assembly (FA) 2
Frame (F) 2
Wheels (W) 3
![Page 7: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/7.jpg)
Time-phase assembly chart
B
H
FA
ComponentLead Times(Minutes)
Bicycle (B) 1
Handle Bars (H) 1
Frame Assembly (FA) 2
Frame (F) 2
Wheels (W) 3
1 min
2 min
1 min
![Page 8: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/8.jpg)
Time-phase assembly chart
1 2 3 4 5 6Component
Lead Times(Minutes)
Bicycle (B) 1
Handle Bars (H) 1
Frame Assembly (FA) 2
Frame (F) 2
Wheels (W) 3
B
H
FA
W
F
Time-Phased Assembly Chart for BWith 6-Minutes Time Horizon
![Page 9: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/9.jpg)
Item : X Duration
Duration (Days/weeks/months)
1 2 3 4 5 6
Gross Requirement
Scheduled Receipts
On-Hand Inventory
Net Requirement
Planned-Order Receipt
Planned-Order Release
Planned-Order ReceiptThe quantity expected to be received by the beginning of the period
Planned-Order ReleasePlanned amount to order in each time period
Net requirementThe actual amount needed in each time period
Gross requirementTotal expected amount of material/component during each time period
Scheduled ReceiptOpen orders scheduled to arrive from vendors/suppliers
On-Hand InventoryThe expected amount of inventory that will be on hand
MRP Schedules
![Page 10: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/10.jpg)
Tutorial MRPNO. 3
In the MRP planning schedule for steel reinforcement shown in Table 1 below, indicate the correct net requirement, planned order receipts and planned order releases to meet the shown gross requirements.Lead time = 1 weeks
Item : Steel Reinforcement Week
Week No. 1 2 3 4 5 6
Gross Requirement 75 50 60
Scheduled Receipts 40
On-Hand Inventory
Net Requirement
Planned-Order Receipt
Planned-Order Release
![Page 11: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/11.jpg)
Item : Steel Reinforcement Week
Week No. 1 2 3 4 5 6
Gross Requirement 75 50 70
On-Hand Inventory 40
Net Requirement
Planned-Order Receipt
Planned-Order Release
Tutorial MRPNO. 3
Lead time = 1 weeks
![Page 12: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/12.jpg)
Item : Steel Reinforcement Week
Week No. 1 2 3 4 5 6
Gross Requirement 75 50 70
On-Hand Inventory 40 - - - - -
Net Requirement 75
Planned-Order Receipt
Planned-Order Release
Tutorial MRPNO. 3
Lead time = 1 weeks
![Page 13: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/13.jpg)
Item : Steel Reinforcement Week
Week No. 1 2 3 4 5 6
Gross Requirement 75 50 70
On-Hand Inventory 40 - - - - -
Net Requirement 75
Planned-Order Receipt 35
Planned-Order Release
Tutorial MRPNO. 3
Lead time = 1 weeks
![Page 14: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/14.jpg)
Item : Steel Reinforcement Week
Week No. 1 2 3 4 5 6
Gross Requirement 75 50 70
On-Hand Inventory 40 - - - - -
Net Requirement 75
Planned-Order Receipt 35
Planned-Order Release 35
Tutorial MRPNO. 3
Lead time = 1 weeks
![Page 15: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/15.jpg)
Item : Steel Reinforcement Week
Week No. 1 2 3 4 5 6
Gross Requirement 75 50 70
On-Hand Inventory 40 - - - - -
Net Requirement 75 50
Planned-Order Receipt 35
Planned-Order Release 35
Tutorial MRPNO. 3
Lead time = 1 weeks
![Page 16: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/16.jpg)
Item : Steel Reinforcement Week
Week No. 1 2 3 4 5 6
Gross Requirement 75 50 70
On-Hand Inventory 40 - - - - -
Net Requirement 75 50
Planned-Order Receipt 35 50
Planned-Order Release 35
Tutorial MRPNO. 3
Lead time = 1 weeks
![Page 17: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/17.jpg)
Item : Steel Reinforcement Week
Week No. 1 2 3 4 5 6
Gross Requirement 75 50 70
On-Hand Inventory 40 - - - - -
Net Requirement 75 50
Planned-Order Receipt 35 50
Planned-Order Release 35 50
Tutorial MRPNO. 3
Lead time = 1 weeks
![Page 18: Tutorial MRP](https://reader036.vdocuments.site/reader036/viewer/2022082623/547ad47bb479596d098b4c02/html5/thumbnails/18.jpg)
Item : Steel Reinforcement Week
Week No. 1 2 3 4 5 6
Gross Requirement 75 50 70
On-Hand Inventory 40
Net Requirement 75 50 70
Planned-Order Receipt 35 50 70
Planned-Order Release 35 50 70
Lead time = 1 weeks
Tutorial MRPNO. 3