Transportation PlanningSystem Context

Page 2: transportation planning system context.ppt

Transportation Planning (objectives)

• Understand how decisions to build transportation facilities are made

• Understand basic elements of the transportation planning process

• Understand basic elements of travel forecasting

Page 3: transportation planning system context.ppt

The transportation planning process

It has become “institutionalized,” meaning federal guide guidelines, regulations, and requirements for local planning are often driving forces behind existing planning methods. Have you heard of MPOs (metropolitan planning organizations) like the Mountain Land of Governments or the Wasatch Front Regional Council? Or, have you heard of Envision Utah?

It is intended to furnish unbiased information about the effects that the proposed transportation project will have on the community and on its expected users.

It is intended to give the appropriate information to those who will be responsible for deciding whether the transportation project should go forward.

Page 4: transportation planning system context.ppt

Basic elements of transportation planning

Situation definition Inventory transportation facilities, Measure travel patterns, Review prior studies

Problem definition Define objectives (e.g., Reduce travel time), Establish criteria (e.g., Average delay time), Define constraints, Establish design standards

Search for solutions

Consider options (e.g., locations and types, structure needs, environmental considerations)

Analysis of performance

For each option, determine cost, traffic flow, impacts

Evaluation of alternatives

Determine values for the criteria set for evaluation (e.g., benefits vs. cost, cost-effectiveness, etc)

Choice of project Consider factors involved (e.g., goal attainability, political judgment, environmental impact, etc.)

Specification and construction

Once an alternative is chosen, design necessary elements of the facility and create construction plans

Page 5: transportation planning system context.ppt

Example : Planning the relocation of a rural road

Step 1: Situation definition:

to understand the situation that gave rise to the perceived need for a transportation improvement

Page 6: transportation planning system context.ppt

Step 2: Problem definition

Purpose of the step: Describe the problem in terms of the objectives to be accomplished and translate those objectives into criteria.

Example:

Objective = Statements of purpose: Reduce traffic congestion, Improve safety, Maximize net highway-user benefits, etc.

Criteria = Measures of effectiveness: Travel time, accident rate, delays (interested in reductions in these MOEs)

Page 7: transportation planning system context.ppt

Step 3: Search for solutions

Brainstorm options at this stage.

Page 8: transportation planning system context.ppt

Step 4: Analysis of performance Estimate how each of the proposed alternatives would perform under present and future conditions.

Page 9: transportation planning system context.ppt

Step 4: Ranking of alternatives (in terms of MOE)

Page 10: transportation planning system context.ppt

Step 5: Evaluation of alternatives

This is a multi-objective evaluation problem.

Determine how well each alternative will achieve the objectives of the project as defined by the criteria.

Cost-wise best

Improvement-wise superior

Improves this way

Improves this way

Page 11: transportation planning system context.ppt

Step 6: Choice of project Based on the alternative evaluation in Step 5, we will choose the best alternative for design and eventual construction. The best choice may not be built because of opposition by the people of the community that is affected.

Step 7: Specification and construction

Once the project has been chosen, a detailed design phase is begun, in which each of the components of the facility is specified.

Page 12: transportation planning system context.ppt

Urban transportation (demand) forecasting process

This task is a technical effort to analyze the performance of various alternatives. We must define the study area first. Then further subdivide the area into traffic (analysis) zone, TAZ, for data tabulation and analysis.

Homogeneous socioeconomic characteristics: e.g., high-income residential

Minimum intra-zonal trips

Use of physical, political, and historical boundaries, where possible

Zones, once created, should not be subdivided into smaller zones during analysis

Zones generating and attracting approximately equal trips, households, population, or area

Use of census tract boundaries, where possible (easier to collect data from the Census Bureau’s publications)

Page 13: transportation planning system context.ppt

Travel demand model flowchart

Page 14: transportation planning system context.ppt

Four basic elements of the urban transportation forecasting process

Data collection (population, land use, etc.)

Economic activity (employment, sales volume, income, etc.), land use (type, intensity), travel characteristics (trip and traveler profile), and transportation facilities (capacity, travel speed, etc.), population and demography, Origin-destination trip data.

Analysis of existing conditions and calibration

Analyze the data collected in the data collection stage. You may build mathematical models describe the existing conditions and then use the relationships you have found in the existing parameters to forecast future values.

Forecast of future travel demand

4-step transportation demand forecasting process

Analysis of the results

Analyze what you get from the 4-stop demand forecasting process

Page 15: transportation planning system context.ppt

Analysis zones for transportation study (TAZ)

Page 16: transportation planning system context.ppt

Link-node map for highway system

Link-node maps are the starting point for the 4-step transportation demand forecasting process

Page 17: transportation planning system context.ppt

4-step transportation demand forecasting process• Preparation: population and economic

analysis and land use analysis

Trip generation Determines how many trips each activity (center) (residential area, commercial area, etc) will produce or attract

Trip distribution Determines the origin or destination of trips that are generated at a given activity

Modal split Determines which mode of transportation will be used to make the trip

Traffic assignment

Determines which route on the transportation network will be used when making the trip

Page 18: transportation planning system context.ppt

Graphical way of understanding the 4-step demand forecasting process

1000 trips generated

1000 trips attracted

200 trips from zone 46 to zone 29

Auto total: 95% Public transit: 5%70% this route

25% this route