Transmission Gully Proposal Certificates
Published by the Board of Inquiry into the Transmission Gully Proposal
Publication No: EPA 0175
ISBN: 978-0-478-34877-4 (print) 978-0-478-34878-1 (electronic)
978-0-478-34879-8 (CD)
June 2012
Table of Contents
NOR 1 – Notice of Requirement confirmed in the jurisdiction of the Kapiti Coast District Council .................................................................................................................... 5
NOR 2 – Notice of Requirement confirmed in the jurisdiction of the Upper Hutt City Council................................................................................................................................ 10
NOR 3 – Notice of Requirement confirmed in the jurisdiction of the Porirua City Council................................................................................................................................ 14
NOR 4 – Notice of Requirement confirmed in the jurisdiction of the Wellington City Council................................................................................................................................ 18
NOR 5 – Notice of Requirement confirmed in the jurisdiction of the Porirua City Council................................................................................................................................ 22
NOR 6 – Notice of Requirement confirmed in the jurisdiction of the Wellington City Council................................................................................................................................ 26
RC 1 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 31
RC 2 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 35
RC 3 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 39
RC 4 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 43
RC 5 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 47
RC 6 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 51
RC 7 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 55
RC 8 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 59
RC 9 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 63
RC 10 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 67
4 |Certificates | June 2012
RC 11 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 71
RC 12 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 75
RC 13 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 79
RC 14 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 83
RC 15 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 87
RC 16 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 89
NOR 7 – Notice of Requirement confirmed in the jurisdiction of the Porirua City Council................................................................................................................................ 91
NOR 8 – Notice of Requirement confirmed in the jurisdiction of the Porirua City Council................................................................................................................................ 95
RC 17 – Resource Consent granted in the jurisdiction of the Wellington Regional Council................................................................................................................................ 98
RC 18 – Resource Consent granted in the jurisdiction of the Wellington Regional Council.............................................................................................................................. 101
RC 19 – Resource Consent granted in the jurisdiction of the Wellington Regional Council.............................................................................................................................. 104
RC 20 – Resource Consent granted in the jurisdiction of the Wellington Regional Council.............................................................................................................................. 107
RC 21 – Resource Consent granted in the jurisdiction of the Kapiti Coast District Council.............................................................................................................................. 110
RC 22 – Resource Consent granted in the jurisdiction of the Porirua City Council .... 112
6 |Certificates | June 2012
Definitions – NOR 1
AEE Transmission Gully Project Assessment of Effects on the Environment Volumes 1 to 5 dated August 2011
CEMP Construction Environmental Management Plan
Commencement of Works means the time when the works that are the subject of these designations commence
Council means the Kapiti Coast District Council (KCDC)
District means the Kapiti Coast District
District Plan means the Kapiti Coast District Plan
Existing network utilities all network utilities existing at 15 August 2011. Network utility has the same meaning as in section 166 of the RMA
The Manager means the regulatory / consents manager of the Council
Outline Plan (OP) means an Outline Plan prepared in accordance with section 176A of the RMA
Project means the construction, maintenance and operation of the Transmission Gully Main Alignment
Requiring Authority means the New Zealand Transport Agency (NZTA)
RMA or “the Act‟ Resource Management Act 1991
Road Asset Manager
means the KCDC‟s road asset manager
SSEMP means a Site Specific Environmental Management Plan required under the provisions of regional consent conditions
Stage
7 |Certificates | June 2012
means a stage of the Project as nominated by the Requiring Authority
Work means any activity or activities undertaken in relation to the Project
WRC Wellington Regional Council
8 |Certificates | June 2012
Conditions
Conditions attached to NOR 1 Conditions not attached to NOR 1
General Conditions and Administration
NZTA.1 – NZTA.3A NZTA.3B
Outline Plans and Management Plans
NZTA.4 – NZTA.11
Communications and Public Liaison - Construction
NZTA.12 – NZTA.13 NZTA.14 – NZTA.14A
Complaints - Construction
NZTA.15
Archaeology and Heritage
Advice Note NZTA.16 (excluding 16(c), 16(f), 16(g)) NZTA.18 – NZTA.19
16(c), 16(f), 16(g) of NZTA.16 NZTA.17
Construction Environmental Management Plan
Advice Note NZTA.20 – NZTA.21
Traffic Management and Roading - Construction
NZTA.22 – NZTA.23 NZTA.26 – NZTA.30 NZTA.31 – NZTA.34
NZTA.24 – NZTA.25 NZTA. 30A
Construction Noise and Vibration Management
NZTA.35 – NZTA.36
NZTA.37 – NZTA.38
Construction Air Quality (including Dust) Management
NZTA.39 – NZTA.40 NZTA.41 (excluding the words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park.”)
The words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park.” of NZTA.41
Construction Lighting
NZTA.41A
Landscape and Urban Design
NZTA.42 (excluding bullet points 2, 3, 5 and 6 and 42(a)) NZTA.43 – NZTA.45 NZTA.46 (excluding 46(d)(ix) bullet point 3, 46(e),
Bullet points 2, 3, 5 and 6 and 42(a) of NZTA.42 46(d)(ix) bullet point 3, 46(e), 46(f), 46(g), 46(h) of NZTA.46
9 |Certificates | June 2012
46(f), 46(g), 46(h)) NZTA.49 NZTA.50 (excluding the words “Except as specified in Condition NZTA.50A,”)
NZTA.47A – NZTA.48 The words “Except as specified in Condition NZTA.50A,” of NZTA.50 NZTA.50A
Ecology
NZTA.51 (excluding 51(b)(xi) – (xvii)) NZTA.52 – NZTA.56
51(b)(xi) – (xvii) of NZTA.51
Existing Network Utilities
NZTA.57 – NZTA.61 NZTA.63 – NZTA.64
NZTA.62
Transpower Specific Conditions
NZTA.65 – NZTA.70
Operational Noise
NZTA.71 – NZTA.81B
Permanent Lighting
NZTA.82
Traffic Safety Audit
NZTA.83
11 |Certificates | June 2012
Definitions – NOR 2
AEE Transmission Gully Project Assessment of Effects on the Environment Volumes 1 to 5 dated August 2011
CEMP Construction Environmental Management Plan
Commencement of Works means the time when the works that are the subject of these designations commence
Council means the Upper Hutt City Council (UHCC)
District means the Upper Hutt City District
District Plan means the Upper Hutt City District Plan
Existing network utilities all network utilities existing at 15 August 2011. Network utility has the same meaning as in section 166 of the RMA
The Manager means the regulatory / consents manager of the Council
Outline Plan (OP) means an Outline Plan prepared in accordance with section 176A of the RMA
Project means the construction, maintenance and operation of the Transmission Gully Main Alignment
Requiring Authority means the New Zealand Transport Agency (NZTA)
RMA or “the Act‟ Resource Management Act 1991
Road Asset Manager
means the UHCC‟s road asset manager
SSEMP means a Site Specific Environmental Management Plan required under the provisions of regional consent conditions
Stage means a stage of the Project as nominated by the Requiring Authority
Work means any activity or activities undertaken in relation to the Project
WRC Wellington Regional Council
12 |Certificates | June 2012
Conditions
Conditions attached to NOR 2 Conditions not attached to NOR 2
General Conditions and Administration
NZTA.1 – NZTA.3A NZTA.3B
Outline Plans and Management Plans
NZTA.4 – NZTA.11
Communications and Public Liaison - Construction
NZTA.12 – NZTA.13 NZTA.14 – NZTA.14A
Complaints - Construction
NZTA.15
Archaeology and Heritage
Advice Note NZTA.16 (excluding 16(b), 16(c), 16(e) 16(f), 16(g)) NZTA.19
16(b), 16(c), 16(e) 16(f), 16(g) of NZTA.16 NZTA.17 – NZTA.18
Construction Environmental Management Plan
Advice Note NZTA.20 – NZTA.21
Traffic Management and Roading - Construction
NZTA.22 – NZTA.23 NZTA.26 – NZTA.30 NZTA.31 – NZTA.34
NZTA.24 – NZTA.25 NZTA. 30A
Construction Noise and Vibration Management
NZTA.35 – NZTA.36 NZTA.37 – NZTA.38
Construction Air Quality (including Dust) Management
NZTA.39 – NZTA.40
NZTA.41 (excluding the words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park.”)
The words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park.” of NZTA.41
Construction Lighting
NZTA.41A
Landscape and Urban Design
NZTA.42 (excluding bullet points 2, 3, 5 and 6 and 42(a)) NZTA.43 – NZTA.45 NZTA.46 (excluding: 46(d)(ix) bullet point 3, 46(e), 46(f), 46(g), 46(h)) NZTA.49 – NZTA.50 (excluding the words “Except
Bullet points 2, 3, 5 and 6 and 42(a) of NZTA.42 46(d)(ix) bullet point 3, 46(e), 46(f), 46(g), 46(h) of NZTA.46 NZTA.47A – NZTA.48 The words “Except as specified in
13 |Certificates | June 2012
as specified in Condition NZTA.50A”) Condition NZTA.50A” of NZTA.50 NZTA.50A
Ecology
NZTA.51 (excluding 51(b)(vii) – (ix) and 51(b)(xi) – (xvii)) NZTA.52 – NZTA.56
51(b)(vii) – (ix) and 51(b)(xi) – (xvii) of NZTA.51
Existing Network Utilities
NZTA.57 – NZTA.61 NZTA.64
NZTA.62 - NZTA.63
Transpower Specific Conditions
NZTA.65 – NZTA.70
Operational Noise
NZTA.71 – NZTA.81B
Permanent Lighting
NZTA.82
Traffic Safety Audit
NZTA.83
15 |Certificates | June 2012
Definitions NOR - 3
AEE Transmission Gully Project Assessment of Effects on the Environment Volumes 1 to 5 dated August 2011
CEMP Construction Environmental Management Plan
Commencement of Works means the time when the works that are the subject of these designations commence
Council means the Porirua City Council (PCC)
District means the Porirua City District
District Plan means the Porirua City District Plan
Existing network utilities all network utilities existing at 15 August 2011. Network utility has the same meaning as in section 166 of the RMA
The Manager means the regulatory / consents manager of the Council
Outline Plan (OP) means an Outline Plan prepared in accordance with section 176A of the RMA
Project means the construction, maintenance and operation of the Transmission Gully Main Alignment
Requiring Authority means the New Zealand Transport Agency (NZTA)
RMA or „the Act‟ Resource Management Act 1991
Road Asset Manager
means the PCC‟s road asset manager
SSEMP means a Site Specific Environmental Management Plan required under the provisions of regional consent conditions
Stage means a stage of the Project as nominated by the Requiring Authority
Work means any activity or activities undertaken in relation to the Project
WRC Wellington Regional Council
16 |Certificates | June 2012
Conditions
Conditions attached to NOR 3 Conditions not attached to NOR 3
General Conditions and Administration
NZTA.1 – NZTA.3B
Outline Plans and Management Plans
NZTA.4 – NZTA.11
Communications and Public Liaison - Construction
NZTA.12 – NZTA.13
NZTA.14A
NZTA.14
Complaints - Construction
NZTA.15
Archaeology and Heritage
Advice Note
NZTA.16 (excluding 16(b), 16(e))
NZTA.17
NZTA.19
16(b), 16(e) of NZTA.16 NZTA.18
Construction Environmental Management Plan
Advice Note
NZTA.20 – NZTA.21
Traffic Management and Roading - Construction
NZTA.22 – NZTA.23
NZTA.26 – NZTA.34
NZTA.24 – NZTA.25
Construction Noise and Vibration Management
NZTA.35 – NZTA.36 NZTA.37 – NZTA.38
Construction Air Quality (including Dust) Management
NZTA.39 – NZTA.41
17 |Certificates | June 2012
Construction Lighting
NZTA.41A
Landscape and Urban Design
NZTA.42 – NZTA.46 (excluding 46(e), 46(g), 46(h))
NZTA.47A – NZTA.47 (excluding bullet points 1 – 7 of NZTA.47).
NZTA.49 – NZTA.50A (excluding 50A(a))
46(e), 46(g), 46(h) of NZTA.46 Bullet points 1 – 7 of NZTA.47 NZTA.48 50A(a) of NZTA.50A
Ecology
NZTA.51 (excluding 51(b)(vii) – (ix))
NZTA.52 – NZTA.56
51(b)(vii) – (ix) of NZTA.51
Existing Network Utilities
NZTA.57 – NZTA.62 (excluding 62 bullet points 2 – 4)
NZTA.64
Bullet points 2 – 4 of NZTA.62 NZTA.63
Transpower Specific Conditions
NZTA.65 – NZTA.70
Operational Noise
NZTA.71 – NZTA.81B
Permanent Lighting
NZTA.82
Traffic Safety Audit
NZTA.83
19 |Certificates | June 2012
Definitions – NOR 4
AEE Transmission Gully Project Assessment of Effects on the Environment Volumes 1 to 5 dated August 2011
CEMP Construction Environmental Management Plan
Commencement of Works means the time when the works that are the subject of these designations commence
Council means the Wellington City Council (WCC)
District means the Wellington City District
District Plan means the Wellington City District Plan
Existing network utilities all network utilities existing at 15 August 2011. Network utility has the same meaning as in section 166 of the RMA
The Manager means the regulatory / consents manager of the Council
Outline Plan (OP) means an Outline Plan prepared in accordance with section 176A of the RMA
Project means the construction, maintenance and operation of the Transmission Gully Main Alignment
Requiring Authority means the New Zealand Transport Agency (NZTA)
RMA or „the Act‟ Resource Management Act 1991
Road Asset Manager
means the WCC‟s road asset manager
SSEMP means a Site Specific Environmental Management Plan required under the provisions of regional consent conditions
Stage means a stage of the Project as nominated by the Requiring Authority
Work means any activity or activities undertaken in relation to the Project
WRC Wellington Regional Council
20 |Certificates | June 2012
Conditions
Conditions attached to NOR 4 Conditions not attached to NOR 4
General Conditions and Administration
NZTA.1 – NZTA.3A NZTA.3B
Outline Plans and Management Plans
NZTA.4 – NZTA.11
Communications and Public Liaison - Construction
NZTA.12 – NZTA.14 NZTA.14A
Complaints - Construction
NZTA.15
Archaeology and Heritage
Advice Note NZTA.16 (excluding 16(b), 16(c), 16(e), 16(f), 16(g)) NZTA.19
16(b), 16(c), 16(e), 16(f), 16(g) of NZTA.16 NZTA.17 - NZTA.18
Construction Environmental Management Plan
Advice Note NZTA.20 – NZTA.21
Traffic Management and Roading - Construction
NZTA.22 – NZTA.30 NZTA.31 – NZTA.34
NZTA.30A
Construction Noise and Vibration Management
NZTA.35 – NZTA.38
Construction Air Quality (including Dust) Management
NZTA.39 – NZTA.40 NZTA.41 (excluding the words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park.”)
The words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park.” of NZTA.41
Construction Lighting
NZTA.41A
Landscape and Urban Design
NZTA.42 (excluding bullet points 2, 3, 5 and 42(a) NZTA.43 - NZTA.46 (excluding 46(d)(ix) bullet point 3, 46(f),) NZTA.47A – NZTA.47 (excluding bullet points 8 - 9). NZTA.48 - NZTA.50A (excluding 50A(b))
Bullet points 2, 3, 5 and 42(a) of NZTA.42 46(d)(ix), bullet point 3, 46(f), of NZTA.46 Bullet points 8 - 9 of NZTA.47 50A(b) of NZTA.50A
Ecology
21 |Certificates | June 2012
NZTA.51 (excluding 51(b)) NZTA.52 – NZTA.56
51(b) of NZTA.51
Existing Network Utilities
NZTA.57 – NZTA.62 (excluding 62 bullet points 1 – 2) NZTA.64
Bullet points 1 – 2 of NZTA.62 NZTA.63
Transpower Specific Conditions
NZTA.65 – NZTA.70
Operational Noise
NZTA.71 – NZTA.81B
Permanent Lighting
NZTA.82
Traffic Safety Audit
NZTA.83
23 |Certificates | June 2012
Definitions – NOR 5
AEE Transmission Gully Project Assessment of Effects on the Environment Volumes 1 to 5 dated August 2011
CEMP Construction Environmental Management Plan
Commencement of Works means the time when the works that are the subject of these designations commence
Council means the Porirua City Council (PCC)
District means the Porirua City District
District Plan means the Porirua City District Plan
Existing network utilities all network utilities existing at 15 August 2011. Network utility has the same meaning as in section 166 of the RMA
The Manager means the regulatory / consents manager of the Council
Outline Plan (OP) means an Outline Plan prepared in accordance with section 176A of the RMA
Project means the construction, maintenance and operation of the Transmission Gully Main Alignment and/or the Kenepuru Link Road
Requiring Authority means the New Zealand Transport Agency (NZTA)
RMA or “the Act‟ Resource Management Act 1991
Road Asset Manager
means the PCC‟s road asset manager
SSEMP means a Site Specific Environmental Management Plan required under the provisions of regional consent conditions
Stage means a stage of the Project as nominated by the Requiring Authority
Work means any activity or activities undertaken in relation to the Project
WRC Wellington Regional Council
24 |Certificates | June 2012
Conditions
Conditions attached to NOR 5 Conditions not attached to NOR 5
General Conditions and Administration
NZTA.1 – NZTA.3A NZTA.3B
Outline Plans and Management Plans
NZTA.4 – NZTA.11
Communications and Public Liaison - Construction
NZTA.12 – NZTA.13 NZTA.14 – NZTA.14A
Complaints - Construction
NZTA.15
Archaeology and Heritage
Advice Note NZTA.16 (excluding 16(b), 16(c), 16(e), 16(f), 16(g)) NZTA.19
16(b), 16(c), 16(e), 16(f), 16(g) of NZTA.16 NZTA.17 - NZTA.18
Construction Environmental Management Plan
Advice Note NZTA.20 – NZTA.21
Traffic Management and Roading - Construction
NZTA.22 – NZTA.23 NZTA.26 – NZTA.30 NZTA.31 – NZTA.34
NZTA.24 – NZTA.25 NZTA. 30A
Construction Noise and Vibration Management
NZTA.35 – NZTA.36 NZTA.37 – NZTA.38
Construction Air Quality (including Dust) Management
NZTA.39 – 40 NZTA.41 (excluding the words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park.”)
The words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park.” of NZTA.41
Construction Lighting
NZTA.41A
Landscape and Urban Design
NZTA.42 (excluding bullet points 2, 3, 5 and 42(a)) NZTA.43 – NZTA.46 (excluding 46(d)(ix) bullet point 3, 46(e), 46(f) 46(g), 46(h)) NZTA.49 – NZTA.50 (excluding the words “Except as specified in Condition NZTA.50A”)
Bullet points 2, 3, 5 and 42(a) of NZTA.42 46(d)(ix) bullet point 3, 46(e), 46(f) 46(g), 46(h) of NZTA.46 NZTA.47A - NZTA.48 The words “Except as specified in Condition NZTA.50A” of NZTA.50
25 |Certificates | June 2012
NZTA.50A
Ecology
NZTA.51 (excluding 51(b)) NZTA.52 – NZTA.56
51(b) of NZTA.51
Existing Network Utilities
NZTA.57 – NZTA.62 (excluding bullet points 1,3, 4 of NZTA.62) NZTA.64
Bullet points 1,3, 4 of NZTA.62 NZTA.63
Transpower Specific Conditions
NZTA.65 – NZTA.70
Operational Noise
NZTA.71 – NZTA.81B
Permanent Lighting
NZTA.82
Traffic Safety Audit
NZTA.83
27 |Certificates | June 2012
Definitions – NOR 6
AEE
Transmission Gully Project Assessment of Effects on the Environment Volumes 1 to 5 dated August 2011
CEMP
Construction Environmental Management Plan
Commencement of Works
means the time when the works that are the subject of these designations commence
Council
means the Wellington City Council (WCC)
District
means the Wellington City District
District Plan
means the Wellington City District Plan
Existing network utilities
all network utilities existing at 15 August 2011. Network utility has the same meaning as in section 166 of the RMA
The Manager
means the regulatory / consents manager of the Council
Outline Plan (OP)
means an Outline Plan prepared in accordance with section 176A of the RMA
Project
means the construction, maintenance and operation of the Transmission Gully Main Alignment and/or the Kenepuru Link Road
Requiring Authority
means the New Zealand Transport Agency (NZTA)
RMA or “the Act‟
28 |Certificates | June 2012
Resource Management Act 1991
Road Asset Manager
means the WCC‟s road asset manager
SSEMP
means a Site Specific Environmental Management Plan required under the provisions of regional consent conditions
Stage
means a stage of the Project as nominated by the Requiring Authority
Work
means any activity or activities undertaken in relation to the Project
WRC
Wellington Regional Council
29 |Certificates | June 2012
Conditions
Conditions attached to NOR 6 Conditions not attached to NOR 6
General Conditions and Administration
NZTA.1 – NZTA.3A NZTA.3B
Outline Plans and Management Plans
NZTA.4 – NZTA.11
Communications and Public Liaison - Construction
NZTA.12 – NZTA.13 NZTA.14 – NZTA.14A
Complaints - Construction
NZTA.15
Archaeology and Heritage
Advice Note NZTA.16 (excluding 16(b), 16(c), 16(e), 16(f), 16(g)) NZTA.19
16(b), 16(c), 16(e), 16(f), 16(g) of NZTA.16 NZTA.17 - NZTA.18
Construction Environmental Management Plan
Advice Note NZTA.20 – NZTA.21
Traffic Management and Roading - Construction
NZTA.22 – NZTA.23 NZTA.26 – NZTA.30 NZTA.31 – NZTA.34
NZTA.24 – NZTA.25 NZTA. 30A
Construction Noise and Vibration Management
NZTA.35 – NZTA.36 NZTA.37 – NZTA.38
Construction Air Quality (including Dust) Management
NZTA.39 – NZTA.40 NZTA.41 (excluding the words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park”)
The words “; and Battle Hill Eventing where works are being undertaken within Battle Hill Farm Forest Park” of NZTA.41
Construction Lighting
NZTA.41A
Landscape and Urban Design
NZTA.42 (excluding bullet points 2, 3, 5 and 42(a)) NZTA.43 – NZTA.46 (excluding 46(d)(ix) bullet point 3, 46(e), 46(f) 46(g), 46(h)) NZTA.49 – NZTA.50 (excluding the words “Except as specified in Condition NZTA.50A”)
Bullet points 2, 3, 5 and 42(a) of NZTA.42 46(d)(ix) bullet point 3, 46(e), 46(f) 46(g), 46(h) of NZTA.46 NZTA.47A - NZTA.48 The words “Except as specified in Condition NZTA.50A” of NZTA.50
30 |Certificates | June 2012
NZTA.50A
Ecology
NZTA.51 (excluding 51(b)) NZTA.52 – NZTA.56
51(b) of NZTA.51
Existing Network Utilities
NZTA.57 – NZTA.61 NZTA.64
NZTA.62 – NZTA.63
Transpower Specific Conditions
NZTA.65 – NZTA.70
Operational Noise
NZTA.71 – NZTA.81B
Permanent Lighting
NZTA.82
Traffic Safety Audit
NZTA.83
32 |Certificates | June 2012
Dated:
Conditions attached to RC1 Conditions not attached to RC1
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5 G.6
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
Construction Environmental Management Plan
33 |Certificates | June 2012
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Earthworks area limit conditions
E.1 – E.2
Erosion and Sediment Control Peer Review Panel
Advice Note
E.6
Erosion and Sediment Control Objectives, Standards and Design Criteria
E.7 – E.10
Erosion and Sediment Control Plan
E.11 – E.22
Progressive Stabilisation Trials
E.23
Chemical Treatment (Flocculation) Plan
E.24 – E.26
Forestry Harvesting Management Plan
E.27
Fill Standards
E.28
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
34 |Certificates | June 2012
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
G.39 – G.39A
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
36 |Certificates | June 2012
Conditions attached to RC2
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5 - G.6
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
Construction Environmental Management Plan
37 |Certificates | June 2012
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Earthworks area limit conditions
E.1 – E.2
Erosion and Sediment Control Peer Review Panel
Advice Note
E.6
Erosion and Sediment Control Objectives, Standards and Design Criteria
E.7 – E.10
Erosion and Sediment Control Plan
E.11 – E.22
Progressive Stabilisation Trials
E.23
Chemical Treatment (Flocculation) Plan
E.24 – E.26
Forestry Harvesting Management Plan
E.27
Fill Standards
E.28
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
38 |Certificates | June 2012
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
G.39 – G.39A
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
40 |Certificates | June 2012
Conditions attached to RC3
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5 - G.6
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
Construction Environmental Management Plan
41 |Certificates | June 2012
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Earthworks area limit conditions
E.1 – E.2
Erosion and Sediment Control Peer Review Panel
Advice Note
E.6
Erosion and Sediment Control Objectives, Standards and Design Criteria
E.7 – E.10
Erosion and Sediment Control Plan
E.11 – E.22
Progressive Stabilisation Trials
E.23
Chemical Treatment (Flocculation) Plan
E.24 – E.26
Forestry Harvesting Management Plan
E.27
Fill Standards
E.28
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
42 |Certificates | June 2012
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
G.39 – G.39A
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
44 |Certificates | June 2012
Conditions attached to RC4 Conditions not attached to RC4
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5
G.6 (except in relation to the reclamation aspects of the consent)
G.6 (for the reclamation aspects of the consent)
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
45 |Certificates | June 2012
Construction Environmental Management Plan
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
46 |Certificates | June 2012
G.39 – G.39A
Baseline
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Streamworks conditions
WS.1 – WS.3
WS.7 – WS.8
WS.4 – WS.6
WS.9
48 |Certificates | June 2012
Conditions attached to RC5 Conditions not attached to RC5
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5
G.6 (except in relation to the reclamation aspects of the consent)
G.6 (for the reclamation aspects of the consent)
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
Construction Environmental Management Plan
49 |Certificates | June 2012
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
G.39 – G.39A
50 |Certificates | June 2012
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Streamworks conditions
WS.1 – WS.3
WS.7 – WS.9
WS.4 – WS.6
52 |Certificates | June 2012
Conditions attached to RC6 Conditions not attached to RC6
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5 G.6 (except in relation to the reclamation aspects of the consent)
G.6 (for the reclamation aspects of the consent)
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
Construction Environmental Management Plan
53 |Certificates | June 2012
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
G.39 – G.39A
54 |Certificates | June 2012
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Streamworks conditions
WS.1 – WS.3 WS.7 – WS.8
WS.4 – WS.6
WS.9
56 |Certificates | June 2012
Conditions attached to RC7 Conditions not attached to RC7
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5
G.6 (except in relation to the reclamation aspects of the consent)
G.6 (for the reclamation aspects of the consent)
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
57 |Certificates | June 2012
Construction Environmental Management Plan
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
58 |Certificates | June 2012
G.39 – G.39A
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Streamworks conditions
WS.1 – WS.3
WS.7 – WS.8
WS.4 – WS.6
WS.9
60 |Certificates | June 2012
Conditions attached to RC8 Conditions not attached to RC8
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5 - G.6
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
Construction Environmental Management Plan
61 |Certificates | June 2012
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
G.39 – G.39A
62 |Certificates | June 2012
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Streamworks conditions
WS.1 – WS.3
WS.7 – WS.8
WS.4 – WS.6
WS.9
64 |Certificates | June 2012
Conditions attached to RC9 Conditions not attached to RC9
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5
G.6 (except in relation to the reclamation aspects of the consent)
G.6 (for the reclamation aspects of the consent)
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
65 |Certificates | June 2012
Construction Environmental Management Plan
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
66 |Certificates | June 2012
G.39 – G.39A
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Streamworks conditions
WS.1 – WS.3
WS.7 – WS.8
WS.4 – WS.6
WS.9
68 |Certificates | June 2012
Conditions attached to RC10 Conditions not attached to RC10
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5
G.6 (except in relation to the reclamation aspects of the consent)
G.6 (for the reclamation aspects of the consent)
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
69 |Certificates | June 2012
Construction Environmental Management Plan
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
70 |Certificates | June 2012
G.39 – G.39A
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Streamworks conditions
WS.1 – WS.3
WS.6 – WS.8
WS.4 – WS.5
WS.9
72 |Certificates | June 2012
Conditions attached to RC11 Conditions not attached to RC11
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5
G.6 (except in relation to the reclamation aspects of the consent)
G.6 (for the reclamation aspects of the consent)
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
73 |Certificates | June 2012
Construction Environmental Management Plan
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
74 |Certificates | June 2012
G.39 – G.39A
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Streamworks conditions
WS.1 – WS.4
WS.7 – WS.8
WS.5 – WS.6
WS.9
76 |Certificates | June 2012
Conditions attached to RC12 Conditions not attached to RC12
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5
G.6 (except in relation to the reclamation aspects of the consent)
G.6 (for the reclamation aspects of the consent)
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
77 |Certificates | June 2012
Construction Environmental Management Plan
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
78 |Certificates | June 2012
G.39 – G.39A
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Streamworks conditions
WS.1 – WS.3
WS.5
WS.7 – WS.8
WS.4
WS.6
WS.9
80 |Certificates | June 2012
Conditions attached to RC13
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5 - G.6
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
Construction Environmental Management Plan
81 |Certificates | June 2012
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
G.39 – G.39A
82 |Certificates | June 2012
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Duck Creek Conditions
Duck.1
84 |Certificates | June 2012
Conditions attached to RC14
G.1 – G.2
Pre-construction Administration Conditions
G.3 – G.4
Consent Lapse and Expiry
G.5 – G.6
Review Condition
G.7
Archaeology
G.8
Complaints
G.9
Incidents
G.10 – G.10A
Staff Training
G.11
Staging and Programme Conditions
G.12 – G.13
Annual Reporting
G.14
Management Plans - General
G.15 – G.18
Construction Environmental Management Plan
85 |Certificates | June 2012
Advice Note
G.19A – G.19
Contaminated Land Management Plan
G.20
Ecological Management and Monitoring Plan
G.21 – G.25
Site Specific Environmental Management Plans (SSEMPs)
G.26 – G.30
Land Protection – Specific Requirements
G.31 – G.31B
Replacement of Existing Culverts – Specific Requirements
G.32 – G.33
Ecological Monitoring - General
G.34
Ecological Outcome Monitoring
G.35
Revegetation Monitoring
G.36
Lizard Translocation Monitoring and Management
G.37
Bat Monitoring
G.38
Erosion and Sediment Control Monitoring - General
Advice Note
G.39 – G.39A
86 |Certificates | June 2012
Baseline Sediment Monitoring – Pre-construction
G.40
Erosion and Sediment Control Monitoring – During Construction
G.41 – G.43
Marine Conditions
G.44A – G.49
Freshwater Conditions
G.50 – G.57
Temporary Culvert Conditions
S.1 – S.4
88 |Certificates | June 2012
Conditions attached to RC15
Administration
CBP.1
Expiry
CBP.2
Review Condition
CBP.3
Complaints
CBP.4
Incidents
CBP.5 – CBP.9
Limit Conditions
CBP.10 – CBP.12
Operation and Process Conditions
CBP.13 – CBP.20
Monitoring and Site Management Conditions
CBP.21 – CBP.26
Monitoring and Reporting Conditions
CBP.27 – CBP.29
90 |Certificates | June 2012
Conditions attached to RC16 Conditions not attached to RC16
Administration
CBP.1
Expiry
CBP.2 (excluding the words “to air”) The words “to air” from CBP.2
Review Condition
CBP.3
Complaints
CBP.4
Incidents
CBP.5 – CBP.9
Limit Conditions
CBP.10 – CBP.12
Operation and Process Conditions
CBP.13 – CBP.20
Monitoring and Site Management Conditions
CBP.21 – CBP.26
Monitoring and Reporting Conditions
CBP.27 – CBP.29
92 |Certificates | June 2012
Definitions – NOR 7
AEE Transmission Gully Project Assessment of Effects on the Environment Volumes 1 to 5 dated August 2011
CEMP Construction Environmental Management Plan
Commencement of Works means the time when the works that are the subject of these designations commence
Council means the Porirua City Council (PCC)
District means the Porirua City District
District Plan means the Porirua City District Plan
Existing network utilities all network utilities existing at 15 August 2011. Network utility has the same meaning as in section 166 of the RMA
The Manager means the regulatory / consents manager of the Council
Outline Plan (OP) means an Outline Plan prepared in accordance with section 176A of the RMA
Project means the construction, maintenance and operation of the Whitby Link Road
Requiring Authority means the Porirua City Council
RMA or “the Act‟ Resource Management Act 1991
Road Asset Manager
means the PCC‟s road asset manager
SSEMP means a Site Specific Environmental Management Plan required under the provisions of regional consent conditions
Stage means a stage of the Project as nominated by the Requiring Authority
Work means any activity or activities undertaken in relation to the Project
WRC Wellington Regional Council
93 |Certificates | June 2012
Conditions
Conditions attached to NOR 7 Conditions not attached to NOR 7
General Conditions and Administration
PCC.1 – PCC.3A
Outline Plans and Management Plans
PCC.4 – PCC.10
Communications and Public Liaison - Construction
PCC.11 – PCC.12
Complaints - Construction
PCC.13
Archaeology and Heritage
PCC.14
Construction Environmental Management Plan
Advice Note
PCC.15 – PCC.16
Traffic Management and Roading - Construction
PCC.17 - PCC.22
Construction Noise and Vibration Management
PCC.23
Construction Air Quality (including Dust) Management
PCC.24 - PCC.25
Construction Lighting
PCC.25A
Landscape and Urban Design
94 |Certificates | June 2012
PCC.26 (excluding “-15” from PCC.26(a)) PCC.27 - PCC.29 (excluding the words “Waitangirua Community Park Design Team, Cannons‟ Creek Residents‟ and Ratepayers Association,” and “Maraeroa Marae Executive, and Tokelauan Christian Church” in PCC.29 and 29(c)(xvi) - (xvii)) PCC.30 – PCC.31
“-15” from NZTA.26(a)
The words “Waitangirua Community Park Design Team, Cannons‟ Creek Residents‟ and Ratepayers Association,” and “Maraeroa Marae Executive, and Tokelauan Christian Church” and 29(c)(xvi) - (xvii) of PCC.29
Ecology
PCC.32
Existing Network Utilities
PCC.33 – PCC.37 PCC.39
PCC.38
Transpower Specific Conditions
PCC.40 – PCC.44
Permanent Lighting
PCC.45
96 |Certificates | June 2012
Definitions – NOR 8
AEE Transmission Gully Project Assessment of Effects on the Environment Volumes 1 to 5 dated August 2011
CEMP Construction Environmental Management Plan
Commencement of Works means the time when the works that are the subject of these designations commence
Council means the Porirua City Council (PCC)
District means the Porirua City District
District Plan means the Porirua City District Plan
Existing network utilities all network utilities existing at 15 August 2011. Network utility has the same meaning as in section 166 of the RMA
The Manager means the regulatory / consents manager of the Council
Outline Plan (OP) means an Outline Plan prepared in accordance with section 176A of the RMA
Project means the construction, maintenance and operation of the Waitangirua Link Road
Requiring Authority means the Porirua City Council
RMA or “the Act‟ Resource Management Act 1991
Road Asset Manager
means the PCC‟s road asset manager
SSEMP means a Site Specific Environmental Management Plan required under the provisions of regional consent conditions
Stage means a stage of the Project as nominated by the Requiring Authority
Work means any activity or activities undertaken in relation to the Project
WRC Wellington Regional Council
97 |Certificates | June 2012
Conditions
Conditions attached to NOR 8 Conditions not attached to NOR 8
General Conditions and Administration
PCC.1 – PCC.3A
Outline Plans and Management Plans
PCC.4 – PCC.10
Communications and Public Liaison - Construction
PCC.11 – PCC.12
Complaints - Construction
PCC.13
Archaeology and Heritage
PCC.14
Construction Environmental Management Plan
Advice Note PCC.15 – PCC.16
Traffic Management and Roading - Construction
PCC.17 - PCC.22
Construction Noise and Vibration Management
PCC.23
Construction Air Quality (including Dust) Management
PCC.24 - PCC.25
Construction Lighting
PCC.25A
Landscape and Urban Design
PCC.26 – PCC.29 (excluding the words “Whitby Residents‟ Association” in PCC.29) PCC.30 – PCC.31
The words “Whitby Residents‟ Association” of PCC.29
Ecology
PCC.32 (excluding 32(a), 32(b), 32(c) and the preceding words “This includes:”)
32(a), 32(b), 32(c) and the preceding words “This includes:” of PCC.32
Existing Network Utilities
PCC.33 – PCC.39
Transpower Specific Conditions
PCC.40 – PCC.44
Permanent Lighting
PCC.45
99 |Certificates | June 2012
Conditions
Conditions attached to RC17 Conditions not attached to RC17
PCC.E.1 - PCC.E.2
Pre-construction and Administration Conditions
PCC.E.3 – PCC.E.4
Consent Lapse and Expiry
PCC.E.5 PCC.E.6
Review Condition
PCC.E.7
Archaeology
PCC.E.8
Complaints
PCC.E.9
Incidents
PCC.E.10 - PCC.E.10A
Staff Training
PCC.E.11
Staging and Programme Conditions
PCC.E.12 – PCC.E.13
Management Plans - General
PCC.E.14 – PCC.E.17
Construction Environmental Management Plan
Advice Note, PCC.E.18A - PCC.E.18
Erosion and Sediment Control Plan
PCC.E.19 – PCC.E.20
Earthworks Limit Conditions
PCC.E.21
Erosion and Sediment Control Objectives and Design Criteria
PCC.E.23 – PCC.E.31
Chemical Treatment (Flocculation)
PCC.E.32 – PCC.E.34
Fill Standards
PCC.E.35
Ecological Management and Monitoring Plan
PCC.E.36 – PCC.E.38
100 |Certificates | June 2012
Site Specific Environmental Management Plans (SSEMPs)
PCC.E.39 – PCC.E.40
Erosion and Sediment Control Monitoring
Advice Note, PCC.E.41 - PCC.E.44
Contaminated Land Management Plan
PCC.E.46
102 |Certificates | June 2012
Conditions
Conditions attached to RC18 Conditions not attached to RC18
PCC.E.1 - PCC.E.2
Pre-construction and Administration Conditions
PCC.E.3 – PCC.E.4
Consent Lapse and Expiry
PCC.E.5 – PCC.E.6
Review Condition
PCC.E.7
Archaeology
PCC.E.8
Complaints
PCC.E.9
Incidents
PCC.E.10 -PCC.E.10A
Staff Training
PCC.E.11
Staging and Programme Conditions
PCC.E.12 – PCC.E.13
Management Plans - General
PCC.E.14 – PCC.E.17
Construction Environmental Management Plan
Advice Note PCC.E.18A - PCC.E.18
Erosion and Sediment Control Plan
PCC.E.19 – PCC.E.20
Earthworks Limit Condition
PCC.E.21
Erosion and Sediment Control Objectives and Design Criteria
PCC.E.23 – PCC.E.31
Chemical Treatment (Flocculation)
PCC.E.32 – PCC.E.34
Fill Standards
PCC.E.35
Ecological Management and Monitoring Plan
PCC.E.36 – PCC.E.38
103 |Certificates | June 2012
Site Specific Environmental Management Plans (SSEMPs)
PCC.E.39 – PCC.E.40
Erosion and Sediment Control Monitoring
Advice Note, PCC.E.41 - PCC.E.44
Contaminated Land Management Plan
PCC.E.46
105 |Certificates | June 2012
Conditions
Conditions attached to RC19
PCC.E.1 - PCC.E.2
Pre-construction and Administration Conditions
PCC.E.3 – PCC.E.4
Consent Lapse and Expiry
PCC.E.5 – PCC.E.6
Review Condition
PCC.E.7
Archaeology
PCC.E.8
Complaints
PCC.E.9
Incidents
PCC.E.10 - PCC.E.10A
Staff Training
PCC.E.11
Staging and Programme Conditions
PCC.E.12 – PCC.E.13
Management Plans - General
PCC.E.14 – PCC.E.17
Construction Environmental Management Plan
Advice Note, PCC.E.18A - PCC.E.18
Erosion and Sediment Control Plan
PCC.E.19 – PCC.E.20
Earthworks Limit Condition
PCC.E.21
Erosion and Sediment Control Objectives and Design Criteria
PCC.E.23 – PCC.E.31
Chemical Treatment (Flocculation)
PCC.E.32 – PCC.E.34
Fill Standards
PCC.E.35
Ecological Management and Monitoring Plan
PCC.E.36 – PCC.E.38
106 |Certificates | June 2012
Site Specific Environmental Management Plans (SSEMPs)
PCC.E.39 – PCC.E.40
Erosion and Sediment Control Monitoring
Advice Note, PCC.E.41 - PCC.E.44
Contaminated Land Management Plan
PCC.E.46
108 |Certificates | June 2012
Conditions
Conditions attached to RC20 Conditions not attached to RC20
PCC.E.1 - PCC.E.2
Pre-construction and Administration Conditions
PCC.E.3 – PCC.E.4
Consent Lapse and Expiry
PCC.E.5 – PCC.E.6
Review Condition
PCC.E.7
Archaeology
PCC.E.8
Complaints
PCC.E.9
Incidents
PCC.E.10 -PCC.E.10A
Staff Training
PCC.E.11
Staging and Programme Conditions
PCC.E.12 – PCC.E.13
Management Plans - General
PCC.E.14 – PCC.E.17
Construction Environmental Management Plan
Advice Note, PCC.E.18A - PCC.E.18
Erosion and Sediment Control Plan
109 |Certificates | June 2012
PCC.E.19 – PCC.E.20
Earthworks Limit Condition
PCC.E.21
Erosion and Sediment Control Objectives and Design Criteria
PCC.E.23 – PCC.E.31
Chemical Treatment (Flocculation)
PCC.E.32 – PCC.E.34
Fill Standards
PCC.E.35
Ecological Management and Monitoring Plan
PCC.E.37 – PCC.E.38 PCC.E.36
Site Specific Environmental Management Plans (SSEMPs)
PCC.E.39 – PCC.E.40
Erosion and Sediment Control Monitoring
Advice Note, PCC.E.41 - PCC.E.43 PCC.E.44
Stream Works Conditions
PCC.WS.0 – PCC.WS.3
Contaminated Land Management Plan
PCC.E.46
111 |Certificates | June 2012
Conditions attached to RC21:
Note
These conditions relate to works located within both the Kapiti Coast and Porirua Districts. Towers 1 – 11 fall within the jurisdiction of the Kapiti Coast District Council and Towers 12 – 49A fall within the jurisdiction of the Porirua City Council. Where conditions are specific to particular towers, the Council with jurisdiction in that area is responsible for any required approval or certification required under these consents.
General
TL1 – TL5
Tower and Access Track Design
TL6 – TL7
Location and Height of the Transmission Line Support Structures
TL8 – TL12A
Ecological
TL13
Historic Heritage
TL14 – TL15B
Construction Environmental Management Plan
TL16 – TL21
Noise and Vibration
TL22 – TL24
Clearance of Trees and Vegetation
TL25 – TL26
Erosion and Sediment Control
TL27 – TL29
Restoration of the Land
TL30
Electric and Magnetic Fields (EMF)
TL31
113 |Certificates | June 2012
Conditions attached to RC22:
Note
These conditions relate to works located within both the Kapiti Coast and Porirua Districts. Towers 1 – 11 fall within the jurisdiction of the Kapiti Coast District Council and Towers 12 – 49A fall within the jurisdiction of the Porirua City Council. Where conditions are specific to particular towers, the Council with jurisdiction in that area is responsible for any required approval or certification required under these consents.
General
TL1 – TL5
Tower and Access Track Design
TL6 – TL7
Location and Height of the Transmission Line Support Structures
TL8 – TL12A
Ecological
TL13
Historic Heritage
TL14 – TL15B
Construction Environmental Management Plan
TL16 – TL21
Noise and Vibration
TL22 – TL24
Clearance of Trees and Vegetation
TL25 – TL26
Erosion and Sediment Control
TL27 – TL29
Restoration of the Land
TL30
Electric and Magnetic Fields (EMF)
TL31