transbay corridor core capacity program · 2017. 8. 22. · capacity program. 0. air quality...

29
Transbay Corridor Core Capacity Program 0 Air Quality Conformity Task Force August 24, 2017 Planning, Development and Construction Transbay Corridor Core Capacity

Upload: others

Post on 03-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • Transbay Corridor Core Capacity Program

    0

    Air Quality Conformity Task ForceAugust 24, 2017

    Planning, Development and Construction

    Transbay Corridor Core Capacity

  • BART Department responsible for this report goes here 1

  • BART Department responsible for this report goes here 2

  • BART’s Peak Hour Transbay Market Share

    3

  • BART Transbay Corridor Peak Loads

    4

    2012 2013 2014

    20,000

    15,000

    17,500

    22,500• 107 pax / vehicle• 21,870 per hour

    • 113 pax / vehicle• 23,052 per hour

    22,900

    20,30021,500

    May 2015

    24,500

    Sept. 2015

    26,50025,000

    27,500

    National standard (5.4 S.F. per passenger)

    BART standard

    • ~140 pax / vehicle• 28,610 per hourHighest Loads On Trains Today

    Transbay AM Peak Hour/Direction

  • 5

    Project Corridor Definition was Driven by Square Feet per Passenger

    June 2017

    5

  • 6

    Project Overview

    • Project Need: Current trains are overloaded beyond BART and FTA’s standards.

    • Project Purpose: To provide additional capacity through the operation of more frequent, longer trains.

    • Project Objective: Increase capacity from 24 to 30 TPH, and make all peak trains 10-car trains.

    Transbay Corridor Core Capacity

    6

    306 New Vehicles Hayward Maintenance Complex Car Storage

    Communication-Based Train Control Traction Power

    Transbay Core Capacity Project

  • 7

    7

    Project Scope• New CBTC train

    control systemwide• 306 railcars• New railcar storage

    yard at Hayward Yard

    • 5 new traction power substations

    Note: Corridor limit shown is for FTA CIG Program eligibility purposes only.

  • Project Delivery Schedule

    8

    July 2017

    RTP Adoption

    Complete PD, Entry into

    Engineering

    Aug 2017

    LONP

    Jan 2018

    FFGA

    Q1 2019

    Q1 2019

    Award CBTC Contract

    2026

    Last of the 306

    Vehicles Delivered

    Q1 2026

    CBTC Complete

    thru Transbay Tube –

    increased frequencies

    possible

    Q1 2023

    HMC Ph 2 & TPSS

    Operable

    2028

    CBTC Complete

    System-wide

  • 1 – Hayward Test Track 2 – South SF

    3 – Downtown SF Core

    4 – Transbay Tube and

    Oakland Wye

    5 –Fremont

    6 –Richmond

    7 –Pittsburg / Bay Point

    8 – Dublin / Pleasanton

    9 – WSX+SVBX

    Phased Migration

    99

    Train Control Modernization -CBTC

  • The Case for CBTC

    30,000

    25,000

    20,000

    15,000

    10,000

    5,000

    2012

    2014

    2016

    2018

    2020

    2022

    2024

    2026

    2028

    2030

    2032

    2034

    2036

    2038

    2040

    2042

    2044

    2046

    2048

    2050

    Capacity vs. Peak Demand – Transbay Tube

    Demand

    Current TrackCircuits

    Refurbished Track Circuit System

    CBTC

    Refurbished Track Circuit System

    2025: CBTC provides Surplus Capacity

    (breathing room)

    2036: Demand

    overtakes CBTC

    capacity (overcrowding resumes)

    Second TBT Crossing Needed

    2017: Overcrowding

    Pas

    seng

    ers

    per H

    our

    10

  • 11

    How Does CBTC Work?

    11

  • 12

    How Does CBTC Work?

    12

  • 13

    Core Capacity Program306 New Car Procurement

    13

    13

    13

  • 14

    1081 Cars (306 New) Needed to Operate 30 Ten-Car Trains per hour thru Tube

    Contract Tranche No. of CarsRunning

    Total

    Bombardier (funded) Replace Current Fleet 669 669

    Capacity – train length 13 682

    WSX (opens 2016) 33 715

    SVBX (opens 2017) 60 775

    Funded but not part of Bombardier contract Capacity – train length 75 850

    Capacity – more frequent service 231* 1081

    *Includes additional cars for Orange Line

    14

  • Hayward Maintenance Complex (HMC) Phase 2 (Hayward Yard East)

  • Flyover at HMC Phase 2(Looking north from Whipple Rd.)

    16

  • 17

    21

    3

    4,5

    Why more substations?1. Increased power draw from:

    • 23 TPH 30 TPH• 8/9/10 car trains all 10 car

    trains• Higher performance new cars

    2. Address low voltage segments of system.

    3. TPSS 4 and 5 needed to allow for closure and rehabilitation of existing TPSS equipment at Powell.

    30 TPH Service Requires 5 New Traction Power Substations (TPSS)

  • Typical TPSS within Existing Station

  • Typical At-Grade AC Switchgear House

  • 20

    Air Quality Conformity Status

    • Project has plan-level conformity - full project is included in Plan Bay Area 2040 adopted by MTC, and so is included in a conforming regional plan.

    • Project-level conformityo HMC Phase 2 has existing CE under 23 CFR 771 and is thus

    exempt per 40 CFR 93.126.o Train control modernization (CBTC) and traction power

    improvements are exempt from conformity per 40 CFR 93.126.o Acquisition of 306 new rail vehicles is not considered to be a minor

    expansion, and therefore is not exempt. Project-level conformity determination is needed for this element.

    20

  • Is this a project of air quality concern?

    Not a Project of Air Quality Concerno Not a new or expanded highway project.o No effect on intersections (no changes to parking).o No changes to rail or bus terminals or transfer points are

    included in project, and none are anticipated.o No modifications to bus operations are part of the

    project, and none are anticipated. o No effect on PM emissions.

    All BART vehicles are electrically-powered. Slight reduction of VMTs possible.

  • 22

    Connecting Buses

    22

    No changes to bus network are included in project (BART does not operate buses).

    Bus changes generally happen as part of large bus network restructuring projectso Concentrate service on frequent, high density corridors.o Reduce low-frequency coverage service in low-density areas.o SFMTA (Muni Forward), AC Transit (ACgo), VTA (Next Network).o Reaction to changing ridership patterns, different housing patterns,

    and competition from TNCs.o Subject to independent environmental review and AQ findings.

    Bus Technologyo Evolving to low/zero-emission – hybrids, hydrogen.

  • BART Access Trends 2008-2016

    Note – This reduction is from approx45,000 daily trips down to approx32,000 daily trips.

  • BART Access Trends 2008-2016

  • BART Access Trends 2008-2016

    Home Origin Percentages• Walking and biking have increased significantly.• Transit and drive-alone have decreased.Non-Home Origin Percentages• Walking, biking and transit are 92% of non-home

    access.

  • 26

    Access Trends

    26

    0.00

    200,000.00

    400,000.00

    600,000.00

    800,000.00

    1,000,000.00

    1,200,000.00

    1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

    Ride

    rs p

    er a

    vera

    ge w

    eekd

    ay

    Bus Ridership Trends - 5 Largest Connecting Operators

    AC Transit Muni (Bus) SamTrans VTA (Bus) CCCTA Total

    Muni (Bus)

    Total

    AC Transit

    VTASamTrans

    CCCTA

  • 27

    Conclusion

    27

    • BART’s Transbay Corridor Core Capacity Project will implement much needed capacity relief on the BART system. As an electrically-powered rail system, BART’s operation has no detrimental effects on air quality.

    • Expansion of the fleet by 306 rail vehicles is a critical component of expanding the system’s capacity.

    • Requesting a finding that BART’s Transbay Corridor Core Capacity Project is not a project of air quality concern.

    • Questions?

  • 28

    Thank You

    BART Department responsible for this report goes here

    28

    Transbay Corridor Core Capacity ProgramSlide Number 2Slide Number 3Slide Number 4BART Transbay Corridor Peak LoadsProject Corridor Definition was Driven by Square Feet per Passenger Project OverviewSlide Number 8Project Delivery ScheduleSlide Number 10Slide Number 11How Does CBTC Work?How Does CBTC Work?Core Capacity Program�306 New Car Procurement�1081 Cars (306 New) Needed to Operate �30 Ten-Car Trains per hour thru TubeHayward Maintenance Complex (HMC) Phase 2 (Hayward Yard East)Flyover at HMC Phase 2�(Looking north from Whipple Rd.) 30 TPH Service Requires 5 New Traction Power Substations (TPSS)Typical TPSS within Existing StationTypical At-Grade AC Switchgear HouseAir Quality Conformity StatusIs this a project of air quality concern?Connecting BusesBART Access Trends 2008-2016BART Access Trends 2008-2016BART Access Trends 2008-2016Access TrendsConclusionThank You