traffic signal management and synchronization project · pdf filetraffic signal management and...
TRANSCRIPT
Traffic Signal Management and Synchronization Project
City of Salt Lake City
September, 2011
Prepared for: City of Salt Lake City
349 South 200 East, Suite 450 Salt Lake City, Utah 84114
Prepared by:
1120 W. La Veta Avenue, Suite 660 Orange, CA 92868
(714) 573-0317
Project No.: JA93152
Traffic Signal Management and Synchronization Project for Salt Lake City
i
Table of Contents
EXECUTIVE SUMMARY .......................................................................................................... 1
1. INTRODUCTION................................................................................................................ 6
2. ASSESSMENT OF EXISTING CONDITIONS ......................................................................... 7
2.1 Roadway Network ................................................................................................................................7
2.2 Traffic Signal Operation........................................................................................................................7
2.3 Queuing Observation ...........................................................................................................................8
2.4 Traffic Volume ........................................................................................................................................8
2.5 Transit ......................................................................................................................................................9
2.6 Bicycles.....................................................................................................................................................9
2.7 Uneven Lane Distribution....................................................................................................................9
2.8 Light Rail Operation........................................................................................................................... 10
3. SIGNAL TIMING OPTIMIZATION .....................................................................................11
3.1 Cycle Length Selection ...................................................................................................................... 12
3.2 Fine-Tuning of Proposed Timing Plans........................................................................................... 12
4. SYSTEM WIDE IMPROVEMENT ........................................................................................13
4.1 Corridor-Based Measures of Effectiveness (MOEs).................................................................... 13
4.2 Network-Wide Measures of Effectiveness Improvements........................................................ 21
4.3 Fuel Consumption and Pollutant Emission.................................................................................... 21
4.4 Economic Analysis .............................................................................................................................. 23
5. RECOMMENDATIONS FOR A THREE TO FIVE YEARS RE-TIMING EFFORT........................25
5.1 Agency Survey ..................................................................................................................................... 25
5.2 Staffing Needs ...................................................................................................................................... 26
5.3 Traffic Signal System Improvements ............................................................................................... 27
6. PERFORMANCE COMPARISONS WITH THREE OTHER CITIES..........................................30
7. CONCLUSIONS ...............................................................................................................32
Traffic Signal Management and Synchronization Project for Salt Lake City
ii
List of Tables
TABLE 1 – LIST OF AFTER STUDY CORRIDORS.............................................................................................. 14
TABLE 2 – TRAVEL TIME AND DELAY STUDY, AM PEAK ............................................................................. 15
TABLE 3 – TRAVEL TIME AND DELAY STUDY, MIDDAY PEAK ...................................................................... 17
TABLE 4 – TRAVEL TIME AND DELAY STUDY, PM PEAK............................................................................... 19
TABLE 5 – NETWORK-WIDE MEASURES OF EFFECTIVENESS IMPROVEMENTS ............................................. 21
TABLE 6 – PEAK HOUR FUEL CONSUMPTION AND POLLUTANT EMISSION COMPARISON....................... 21
TABLE 7 – ANNUAL FUEL CONSUMPTION REDUCTION .............................................................................. 22
TABLE 8 – MOTORIST COST SAVINGS ASSOCIATED WITH DECREASED DELAY AND STOPS .................... 23
TABLE 9– BENEFIT-TO-COST RATIO ANALYSIS............................................................................................. 24
TABLE 10 – SELECTED CITIES FOR TRAFFIC SIGNAL OPERATION SURVEY .................................................. 25
TABLE 11 – SUMMARY OF STAFFING NEEDS .................................................................................................. 26
TABLE 12 – RECOMMENDED STAFF RESOURCE FOR TRAFFIC CONTROL CENTER.................................... 27
TABLE 13 – MEASURES OF EFFECTIVENESS (MOE’S) OF FOUR CITIES ......................................................... 30
Appendices
APPENDIX A – EXISTING CYCLE LENGTH
APPENDIX B – EXISTING TRAFFIC VOLUME COUNTS
APPENDIX C – PROPOSED CYCLE LENGTH
APPENDIX D – TRAVEL TIME AND DELAY BEFORE AND AFTER STUDY REPORTS
APPENDIX E – SUMMARY OF TRAFFIC SIGNAL OPERATION SURVEY
Traffic Signal Management and Synchronization Project for Salt Lake City
1
Executive Summary
KOA Corporation (KOA) was retained by Salt Lake City as the consultant to conduct a traffic signal coordination study for 164 intersections1 within the greater Central Business District (CBD) area of Salt Lake City, Utah. The signals within the study area are under the control of Salt Lake City and the Utah Department of Transportation (UDOT). The goal of the study was to develop traffic signal management and synchronization recommendations to reduce traffic delays, pollutant emissions, and petroleum fuel consumption. Other goals included determining the optimal frequency of retiming the signals and resources needed to do so and comparing the performance of the traffic signal operation in Salt Lake City to other cities with similar characteristics. KOA completed the following tasks during this study:
• Conducted detailed field reviews of the project site • Updated the City’s original Synchro2 network with new count volumes and timing parameters • Used Synchro’s volume balancing tool to fill in the gaps at locations with no volume counts
available • Conducted field calibrations using the SimTraffic tool from Synchro • Optimized traffic signal coordination timing plans using Synchro • Fine-tuned and field-reviewed the City-installed timing plans
• Conducted the “After Study” travel time runs and compared with the “Before Study” runs • Conducted signal performance comparisons with three other cities • Researched and conducted interviews with other cities to identify the signal timing staffing needs
Traffic Signal Management Improvements Cycle Length For the AM and PM peak periods, KOA proposed to retain one uniform 120-second cycle length with the exception of those light rail intersections along Main Street that are currently running free. UDOT intersections are already operating on a 120-second cycle length. For the midday period, the cycle length was reduced at some of the city-maintained intersections to an 81-second cycle. The unusual cycle was selected to harmonize with the existing 108-second cycle length currently set for the State and some major City intersections. Intersections with the two different cycle lengths will reach a common base point every four cycles. Minimal changes are recommended to arterial corridors with light rail operation. The signalized intersections with light rail tracks in the median were previously calibrated and were optimized for the light rail operation by UDOT. Those signals also provide priority to the light rail operation. 1 – Salt Lake City has a total of 173 intersections in its system network 2 – A software application tool used in optimizing traffic signal timing
Traffic Signal Management and Synchronization Project for Salt Lake City
2
Signal Synchronization Measures of Effectiveness Improvements A travel time and delay “after” study was conducted along 16 corridors during the weekday AM, midday, and PM peak periods, which were compared to the results of “before” studies conducted by the City for each corridor. The corridor-based measures of effectiveness (MOE’s) performance consisted of average travel time, average speed, number of stops, and total delay. During the AM peak period, the optimized timing plans improved traffic operation by decreasing average travel time of 16 corridors by 8%, increasing average speed by 8%, decreasing number of stops by 17%, and decreasing total delay of each run by 14%. During the midday period, the comparison shows a 6% reduction in average travel time of 16 runs, with the average number of stops decreasing by 3% and total delay decreasing by 12%. The average speed increased by 3%. During the PM peak period, the comparison reports 8% reduction in the travel time, 14% reduction in number of stops and 11% reduction in total delay, the average speed increased by 5%.
In terms of network-wide improvement, with the optimized timing plans, total delay within the downtown area was reduced by 14% for AM Peak, 10% for Midday Period, and 7% for PM Peak. The number of total stops was reduced by 8% for AM Peak, 7% for Midday Period, and 8% for PM Peak. Fuel Consumption and Pollutant Emission Based on KOA’s recommendation, the Measure of Effectiveness (MOE) from Synchro shows improvements in all three time periods that result in 337,000 gallons of fuel savings per year. The results significantly exceed the target goal of 32,000 gallons for this project by a factor of ten. The daily and annual reduction in pollutant emissions are presented in the table below.
Peak Hour Network MOE Existing Optimized Reduction Fuel Consumed (gal) 4715 4437 278 (5.9%) CO Emissions (lbs) 728 683 42 (5.8%)
NOx Emissions (lbs) 141 132 9 (6.3%) AM
VOC Emissions (lbs) 168 159 11 (6.6%) Fuel Consumed (gal) 4189 4013 176 (4.2%) CO Emissions (lbs) 646 617 26 (4.1%)
NOx Emissions (lbs) 126 121 4 (3.5%) Midday
VOC Emissions (lbs) 150 143 7 (4.4%) Fuel Consumed (gal) 5279 5059 220 (4.2%) CO Emissions (lbs) 814 780 33 (4.1%)
NOx Emissions (lbs) 159 152 7 (4.2%) PM
VOC Emissions (lbs) 190 181 9 (4.7%)
Daily Reduction Annual Reduction Fuel Savings (gal) 1348 337,000
CO Emissions Reductions (lbs) 203 50,700
NOx Emissions Reductions (lbs) 40 10,000
VOC Emissions Reductions (lbs) 53 13,200
Traffic Signal Management and Synchronization Project for Salt Lake City
3
Staffing Resources for Signal Retiming The City recently lost one staff position in its Traffic Control Center (TCC) due to budgetary constraints. Based on our survey of four other cities (Tallahassee, Amarillo, Knoxville, and Little Rock), we believe that the staffing level in the TCC, currently consisting of two staff members, is inadequate to effectively operate and maintain the signal system while performing other vital daily tasks. Maintaining communication linkage between the TCC and more than 180 signals in the field and various closed circuit television (CCTV) cameras requires substantial effort on a daily basis. Additionally, the City should budget adequate resources to conduct the retiming of the entire signal system on three-year intervals. The primary factors for needing to retime the signals are:
• Land use changes • Population growth or shifts • Change in flow profiles (volume and classification) • Compliance to changes in Federal or state standards for pedestrian clearance and other intervals
Currently, the City maintains a database of the traffic signals, including controller type and history of updates. However, the City does not have enough resource to maintain a Performance Measure of Effectiveness (MOE) database to track the operational performance within the City’s roadway network. We recommend that the City assign adequate staff resource to conduct performance survey of MOE once every other year. Performance MOE surveys will also help in identifying areas where signal retiming efforts should be initiated. As a result, it is recommended that the City budget resources to hire three additional staff – two engineers and one operator. Duties of additional staff include, but not be limited, to the following:
Resolving traffic operational issues, in particular signal timing related issues, based on citizens’ complaints.
Analyzing and assessing the City’s communication infrastructure needs for improvements necessary for the safe and efficient utilization of the roadway network.
Ensuring coverage by manning in the communication console at all times during the normal business hours in the TCC.
Coordinating and staffing major/special events requiring changes in timing plans in the TCC. Maintaining a Performance Measure of Effectiveness (MOE) database to track the operational
performance within the City’s roadway network. Determining, evaluating and recommending solutions at intersections with high accident rates. Completing the retiming of signals on every three-year intervals.
With the additional staffing, the TCC should consist of one Director, two traffic signal engineers, and two operators. Signal retiming and traffic count stations are eligible to be funded through State and Federal sources. While the Federal Congestion Mitigation and Air Quality (CMAQ) program is one of
Traffic Signal Management and Synchronization Project for Salt Lake City
4
the primary sources of funds for signal retiming projects, other sources of funds are needed to maintain the traffic count stations.
Comparison of Performance with Three Other Cities There are several features that are unique to Salt Lake City that cannot be found in other cities in the U.S. The most significant feature, perhaps, is the overall size of an average intersection. The downtown streets are unusually wide, resulting in long crosswalks and corresponding long pedestrian clearance times. Outside of the downtown area, many intersections have no pedestrian push buttons. These features result in the need to use a relatively long traffic signal cycle that, in turn, necessitates longer waits at the intersections. Furthermore, the light rail operation that runs on Main Street and 400 South and cuts through the downtown area features traffic signal controllers that provide priority to minimize delays for the light rail operation, possibly at the expense of motor vehicular and pedestrian traffic. Downtown networks of three other cities were selected for comparison. They are the City of Honolulu, Hawaii, City of Louisville, Kentucky and City of Santa Monica, California. The table summarizes the network-based measures of effectiveness (MOE's) performance for all four cities.
City Period No. of I/S
in the Network
Average Speed (mph)
Delay/Int (sec) Stops/Int
AM 173 17 9.3 833 Salt Lake City
PM 173 16 11.3 939 AM 74 12 10.7 997
Honolulu PM 74 10 15.4 1117 AM 60 14 6.4 733
Santa Monica PM 60 12 11.4 1123 AM 220 20 10.5 n/a
Louisville * PM 220 19.5 13.6 n/a
Note: *Based on a report prepared by Entran, PLC, submitted to the City on October 2009. Despite its relative large intersection sizes and having a light rail operation running through the downtown area, Salt Lake City fares well in comparison with other cities. It has the second highest average speeds for both peak periods. Salt Lake City has the lowest average delay and number of stops during the evening rush hours. Newer Central Traffic Management Software
Siemens i2 Central Traffic Management Software (TMS) has been used to manage 755 traffic signals in the Salt Lake Metropolitan area, encompassing three counties, for the past 12 years. In the near future, this software will no longer be supported by the manufacturer and will need to be replaced. Newer generations of central traffic management software are available that are easier to use; could detect,
Traffic Signal Management and Synchronization Project for Salt Lake City
5
quickly diagnose and correct system problems; and, provide more robust reporting. In general, they operate in more effective and efficient manners. The newer software also provides a more secured interface and supports features such as emergency and/or incident response, transit signal priority and full set of customizable features to fit individual needs of the City. A comprehensive search is needed to review these software packages in order to determine which of them best suits the needs of the Salt Lake City area’s traffic signal system. In our review of the existing Salt Lake City’s traffic signal timing, we found the City is demonstrating “good practice” strategies and philosophies while providing balanced levels of service to all modes of travel in its approach to traffic signal operations. The strategies and philosophies, that the City is using, are in line with traffic signal timing industry standards provided by the Institute of Transportation Engineers (ITE).
Traffic Signal Management and Synchronization Project for Salt Lake City
6
1. Introduction
KOA Corporation was retained by the Transportation Division, Salt Lake City to develop traffic signal management and synchronization recommendations to reduce traffic delays, pollutant emissions and petroleum fuel consumption. The project is in keeping with the general guideline, established by the Institute of Transportation Engineers (ITE), an international educational and scientific association of transportation professional organization, to retime signal networks on a 3 to 5 year interval. The most recent timing update for the network had been conducted by UDOT and the City in the Fall of 2009. The goal of the 2009 effort was to optimize the coordination progress and decrease the delay on the State highways while maintaining coordination with the City streets. Salt Lake City is the central city to 1.8 million inhabitants residing in four counties that make up the Wasatch Front and that are within an hour’s drive from downtown. The majority of Utah’s 2.4 million people live in the Wasatch Front urban corridor, and 20 percent of the state’s total work force commutes to jobs located in the city limits. A significant portion of pollutants from nitrous oxides, volatile organic compounds, carbon monoxide, and small particulate matter in the Salt Lake Valley are produced by on-road vehicles.
As an idle reduction and fuel conservation strategy, this study optimized the city-wide traffic signal operation with a long-term effect of reducing fossil fuel emissions and improving air quality along the Wasatch Front.
It was hoped per the funding application that updating traffic signal timing could save an estimated 32,000 gallons or more of petroleum fuel each year by reducing traffic signal delays and reducing vehicle idling. Community residents will save in gasoline costs due to reduced starting and stopping, and idling. In addition to greenhouse gas emissions reductions, the project is anticipated to reduce volatile organic compounds emissions by more than 300 pounds per year and nitrous oxides emissions by over 400 pounds per year, resulting in air quality improvements. This report summarizes the existing signal operation analysis at the study intersections, development of updated coordination timing plans for each peak period of the day, travel time and delay before and after studies, and other findings.
Traffic Signal Management and Synchronization Project for Salt Lake City
7
2. Assessment of Existing Conditions
2.1 Roadway Network The study includes a total of 164 signalized intersections in Salt Lake City, east and west between 500 West and 1300 East and north and south between 600 North and 900 South. The signals within the study area are under the jurisdictions of Salt Lake City and the Utah Department of Transportation (UDOT). The major study corridors are listed below.
• N Temple • 400 West • S Temple • 300 West • 200 South • West Temple • 300 South • Main • 400 South • State • 500 South • 200 East • 600 South • 300 East • 700 South • 500 East • 800 South • 600 East • 900 South • 700 East • 600 North • 1300 East
Salt Lake City’s street network in downtown CBD is primarily a grid network. The signal spacing varies between 700 feet and 900 feet. Light rail runs on 400 South, the major east-west arterial connecting the downtown CBD to the University of Utah campus.
2.2 Traffic Signal Operation
In 2009 the signals in downtown area were re-timed in a joint effort between the City and UDOT to run 164 traffic signals on the same cycle length and time-of-day schedule. A cycle length of 120 seconds was used for the AM and PM peak periods and a cycle length of 108 seconds was used during the off-peak periods. Some virtual one-way couplets were provided to favor certain directions during the peak hours such as 800 South favors westbound and 900 South favors eastbound. The existing cycle length of study intersections is shown in Appendix A. Opinions about the effectiveness of the re-timing efforts conducted in 2009 have been mixed. Some people have perceived great improvements, while others have expected better performance from the system. As a result, KOA Corporation was hired to, among other tasks, conduct field reviews of the downtown system to analyze whether significant benefits might accrue from further re-timing. The most significant feature of Salt Lake City’s downtown street system, perhaps, is the overall size of an average intersection. The downtown streets are unusually wide, resulting in long crosswalks and accompanying long pedestrian clearance times. Many intersections in the downtown area have simple
Traffic Signal Management and Synchronization Project for Salt Lake City
8
two phase operation, but some locations provide left turn phases. Some of these provide more efficient protected/permitted left turn phasing, while others provide fully protected left turn phases. These features, coupled with frequent pedestrian crossing usage, result in the need to use relatively long traffic signal cycles at the larger intersections. The intersection that appears to require the longest natural cycle length is State Street at 400 South. This intersection provides six lanes on each street, left turn phasing on all approaches and a light rail line in the median. This intersection and similarly large locations probably have dictated the use of the 108-second off peak cycle and the 120-second peak cycle length used throughout the downtown area.
2.3 Queuing Observation During the off peak period, overall traffic conditions appear orderly and uncongested. A detailed study of traffic volumes and alternative signal operation were conducted to determine whether significant improvements can be derived. Different cycle length combinations were tested along some of the less important streets that do not provide frequent left turn phases. The travel time and delay after study was conducted to evaluate whether the faster local operation will compensate for loss of coordinated movement between smaller and larger intersections. During peak periods, there is considerably more visible traffic congestion. The existing system-wide 120-second cycle results in relatively long queues of vehicles on heavily used through movements Optimization of signal timing will not likely improve this condition substantially, but minor improvements may be achievable. The network appears to have excessive stops that can be potentially reduced through timing adjustments. Queues were observed during the PM peak hours along 500 South, a wide one-way street traveling from downtown toward a major freeway interchange. These queues were of the type that can occur when the design coordination speed is higher than the travel speed. Initially slow moving cars were “clipped” by the yellow signal and required to stop until the next cycle. Over the peak period, these vehicles built up queues that were standing at the end of the green phase. During a typical cycle, 10 to 15 vehicles per lane could be stopped at the end of the green phase. These stopped vehicles created longer queues due to approaching vehicles in the next cycle stopping behind them. This further aggravated the travel speed and resulted in more queued vehicles at the end of the cycle. This type of congestion could often be alleviated through minor adjustments in the signal timing, either by slowing down the platoon speed if there is sufficient capacity for the approaching phase, or modifying the timing plan to expect that vehicles will be stopped.
2.4 Traffic Volume The City counted AM, midday, and PM traffic turning movement volumes at 27 study intersections in June 2010. For other locations, the City provided historical traffic counts and estimated volumes for AM, PM, and off-peak periods. KOA conducted field reviews and identified inconsistencies between peak hour traffic volumes in the field and historical data/estimated volumes. KOA manually balanced the
Traffic Signal Management and Synchronization Project for Salt Lake City
9
traffic volumes at critical locations using Synchro 7 models. The adjusted volumes were reviewed and approved by the City staff as shown in Appendix B.
2.5 Transit Existing light rail and bus run through the following corridors in downtown areas:
• South Temple • 200 South • 400 South • 700 South • 200 West • 400 West • 600 West • Main Street
The Siemens NextPhase traffic signal control program was customized to provide TRAX priority over the local signal operation. As agreed with the City and UDOT, signal timings were held at light rail intersections with minor split or offset adjustments. Six intersections on South Temple, twelve intersections on Main Street, ten intersections on 400 South, and seven light rail intersections fall in this category. During all periods, light rail priority generates negative impacts on signal synchronization along north-south streets, especially for State Street, 700 East, and 1300 East, as well as on the light rail corridors themselves, especially 400 South.
2.6 Bicycles Salt Lake City is recognized as a silver-level Bicycle Friendly Community by the League of American Bicyclists’ Bicycle Friendly Community program. The City continues to take steps to improve bicycle facilities, education, and encouragement. Within the project network, bike lanes are provided on the following streets:
• 200 South • 800 South • 200 West • 300 East • 1300 East
A green shared lane is provided on parts of Main Street, South Temple, and 200 South.
2.7 Uneven Lane Utilization Uneven lane distribution (when one lane is used significantly more than an adjacent lane or lanes) is usually observed at intersections where there are multiple turn lanes and a downstream traffic generator that requires traffic to use one lane more often than the other. During the PM peak hours, a great amount of traffic on 500 S tends to use the first three through lanes on the left to access the freeway. The designed through phase seems not long enough to release arrival traffic. During the peak
Traffic Signal Management and Synchronization Project for Salt Lake City
10
hours, the yellow signal cuts the last portion of the platoon.
2.8 Light Rail Operation In Salt Lake City, light rail travels through the core part of downtown signal system. At the intersection of Main Street and 400 South, the light rail line splits into two routes – one line heads toward University of Utah and the other trains towards the south of the study area, 13 miles south of downtown Salt Lake City. This intersection is the major bottleneck affecting traffic operations on 400 South between 200 W and State Street, and State Street between 300 S and 500 S. Passage of a light rail train may force signals to cut a traffic platoon affecting operations of auto transportation. At times during peak hours, the stopped vehicles may not be served before the next platoon arrives. The accumulated stopped vehicles can easily queue back to the upstream intersection. This makes traffic signal operation look inefficient and sluggish. The light rail intersections run on a customized controller program that provides priority to the mobility of trains. Frequent passage of rail cars may cause light rail intersections to change order of phases from normal phasing sequence or prematurely truncate the phase duration, allowing rail cars to pass through the intersection with minimal delays. When that happens, the signals take several cycles to transition back to normal operation, interrupting progression for cars. Motorists may experience more stops or delays when they try to cross light rail lines.
Traffic Signal Management and Synchronization Project for Salt Lake City
11
3. Signal Timing Optimization
The development of new timing plans began with an evaluation of the existing traffic conditions within the project network. The cycle lengths for the intersections along state highways and the light rail were not changed, although minor adjustments to the split or offset were provided as needed. The optimization process was performed by using the Synchro 7.0 software. The Synchro models were further adjusted to improve the Measures of Effectiveness (MOE) performance, based on the knowledge of the traffic characteristics of the network and traffic flow pattern during the different time periods of the day. The evaluation of the existing operation conditions identified several unique features of Salt Lake City downtown network that create challenges to signal coordination: large size intersections resulting in long crosswalks and accompanying long pedestrian clearance interval; light rail traveling through the core part of downtown system and forcing intersections to change order of normal phasing sequence, and protected left turn phases provided at some downtown intersections. 500 South and 600 South carry very heavy traffic during the AM and PM peak hours with the offsets set to favor these two state highways. With the light rail going through most part of 400 South, offset optimizations are limited along north-south city streets. State Street is another state street heavily used by the peak hour commuters. With the light rail crossing at 400 South, it is difficult to achieve stable coordination progression along Main Street. The following items were reviewed during the signal timing optimization:
• Existing queuing conditions • Cross arterial coordination • Queuing conditions of left turn phases • Movements with uneven lane distribution • Potential oversaturated movements • Location of high volume unsignalized intersections • Potential impacts from pedestrians, bicyclists, and transit • Bus stops locations and usage
The signal coordination analysis and development of optimized timing plans consist of the following tasks:
• Review and balance the traffic turning movement volumes • Update and calibrate the existing Synchro models • Evaluate signal grouping and free operation • Evaluate and select cycle lengths • Agency review • Review the split • Optimize the offset • Evaluate the final timing plans
Traffic Signal Management and Synchronization Project for Salt Lake City
12
3.1 Cycle Length Selection Cycle length selection is a critical step in the developing signal coordination plans. A longer cycle length may provide better progression along the corridors, but may most likely increase side street delay and queuing. On the other hand, decreasing the cycle length to reduce the side street delay may increase the overall delay and number of total stops. For the Salt Lake City downtown area, most intersections operate below saturated conditions. Pedestrian phases generally determine the minimum cycle length at most two-phase intersections. However, accommodating light rail operation requires increase of the cycle length along corridors. For the AM and PM peak periods, KOA concurs in using 120-second cycle length. UDOT intersections are already operating on a 120-second cycle length. Some free-running light rail intersection on Main Street and 400 South are kept as actuated-uncoordinated operation. The uniformity of cycle length would provide for better progression with minimal stops for the entire network. KOA also reviewed the flow profiles of critical intersections to identify the appropriate setting for different time of day operations. The review did not necessitate changes to any time of day operations. For the midday period, the cycle length was reduced at 48 city-maintained intersections to an 81-second cycle. The unusual cycle was selected to harmonize with the existing 108-second cycle length currently set for the State and some major City intersections. It is also close to the natural cycle length of the 48 city-maintained intersections. Intersections with the two different cycle lengths (81 seconds versus 108 seconds) would reach a common base point every four cycles (324 seconds). Further reduction below 81 seconds cycle is not feasible at most of the City intersections while accommodating pedestrian crossing times. Multiple-phase intersections were verified to operate at the lower cycle length without violating the minimum green time for any of the phases. The cycle length for each peak period is shown in Appendix C. At the City’s request, the following signal timing parameters were maintained:
• Yellow and All Red intervals • Pedestrian Walk and Flashing Don’t Walk (FDW) intervals • Vehicle Extension • Time-of-Day Schedule
3.2 Fine-Tuning of Proposed Timing Plans KOA engineers reviewed the signal system operation in the field to insure that all timing plans were inputted properly during all timing periods, as the volumes of many interior intersections in the network were based on estimation of the upstream flows and might not accurately reflect the actual flows. Furthermore, the timing plans generated by any computer model must be fine-tuned by engineers to best accommodate real-world conditions. During the implementation and fine-tuning, KOA engineers also identified some intersections that were not running according to the timing plans and some were in transition from time to time. Discrepancies could be due to the aging traffic signal system. Observed issues were reported to the City staff.
Traffic Signal Management and Synchronization Project for Salt Lake City
13
4. System Wide Improvement
The City conducted a travel time and delay “before” study along 46 corridors in 2008 and 2009. KOA summarized and tabulated the field data. KOA then selected 16 corridors to conduct a GPS-based floating car travel time and delay after study in May 2011. Tru-Traffic software was used to collect and process the survey data. A total of three runs were conducted for each direction of the corridor for each peak time period. The corridor-based measures of effectiveness (MOE’s) performance were summarized as:
• Average Travel Time (seconds): the total elapsed time spent driving along the study corridor from the first intersection to the last intersection. This study reports the average travel time of three runs.
• Average Speed (miles per hour): the average distance a vehicle travels within the measured amount of time.
• Number of Stops: the average number of stops during three survey runs. • Total Delay (seconds): the time difference between actual travel time and desired travel time.
The network-wide fuel consumption savings and emission decrease are reported by Synchro models using the following measures:
• Fuel Consumption (Pounds) • Carbon Monoxide Emission (Pounds) • Oxides of Nitrogen Emission (Pounds) • Volatile Organic Compounds Emission (Pounds)
The detailed travel time and delay after study reports are included in Appendix D.
4.1 Corridor-Based Measures of Effectiveness (MOEs) As show in Table 1, 16 corridors were surveyed during the weekday AM, midday, and PM peak periods. Tables 2 through 4 compared the results of before and after studies for each corridor. Optimized timing plans improved average MOE’s by approximately 8% to 17% during the peak periods.
• During the AM peak period, the optimized timing plans improved traffic operation by decreasing average travel time of 16 corridors by 8%, increasing average speed by 8%, decreasing number of stops by 17%, and decreasing total delay of each run by 14%.
• During the midday period, the comparison shows 6% reduction in average travel time of 16 runs, with the average number of stops decreasing by 3% and total delay decreasing by 12%. The average speed increased by 3%.
• During the PM peak period, the comparison reports 8% reduction in the travel time, 14% reduction in number of stops, and 11% reduction in total delay, with average speed increasing by 5%.
Traffic Signal Management and Synchronization Project for Salt Lake City
14
Table 1 – List of After Study Corridors
No. Corridor From To
1 South Temple 200 West 1200 East
2 100 South Main St 1300 East
3 200 South 450 West 700 East
4 300 South 300 West 700 East
5 800 South 300 West 1300 East
6 900 South 300 West 1300 East
7 400 West 600 South 900 North
8 300 West 800 South 600 North
9 200 West 900 South North Temple
10 West Temple 800 South North Temple
11 State Street 900 South North Temple
12 200 East 900 South South Temple
13 300 East 900 South South Temple
14 400 East 900 South South Temple
15 700 East 900 South South Temple
16 900 East 800 South 100 South
• It should be noted that three corridors were under construction during the travel time and delay “after” runs: State Street between 300 South and 500 South, 400 West north of North Temple, and 200 East between 400 South and 500 South. As these on-going constructions slowed down traffic flow and caused extra stops, traffic platoons could not follow the designed progression through multiple sets of intersections. The worst case was observed on State Street northbound between 300 South and 500 South during the AM and Midday peak periods. Northbound drivers had to make hasty lane changes before 400 South to avoid the closed curb lane. The northbound through phases could not serve all arriving traffic after the lane drop The last part of platoon was cut off and queued up between 400 South and 500 South. Vehicles often needed to wait more than one cycle to go through this segment. This explained why the after runs reported worse performance on those corridors.
• During the fine-tuning and implementation process, KOA also identified offsets that were
drifting at some intersections on State Street and 700 East during the peak hours. This worsened the after run results on these two corridors.
Traffic Signal Management and Synchronization Project for Salt Lake City
15
Table 2 – Travel Time and Delay Study, AM Peak
Travel Time (sec) Average Speed (mph) Number of Stops Total Delay (sec) Corridor
Before After Change Before After Change Before After Change Before After Change
EB 508 395 -22% 15.5 19.4 25% 5.2 4.3 -17% 205 139 -32% South Temple WB 419 420 0% 18.5 19.1 3% 6 5.3 -12% 133 147 11%
EB 388 414 7% 18.9 17.4 -8% 3.6 4.3 19% 132 157 19% 100 South
WB 457 488 7% 15.5 14.6 -6% 5.2 6.3 21% 179 225 26% EB 508 470 -7% 12.4 13.5 9% 7.4 4.7 -36% 256 210 -18%
200 South WB 399 401 1% 16.4 15.7 -4% 3.6 5 39% 158 156 -1% EB 405 336 -17% 13.4 16.5 23% 4.8 3.3 -31% 178 110 -38%
300 South WB 428 389 -9% 12.7 14.8 17% 6.3 4.7 -25% 197 166 -16% EB 557 541 -3% 15.7 16.2 3% 6.8 5.7 -16% 240 229 -5%
800 South WB 578 516 -11% 15 17 13% 7.4 5 -32% 260 230 -12% EB 563 537 -5% 15.5 16.3 5% 6.8 7.3 7% 235 209 -11%
900 South WB 564 459 -19% 15.6 19.3 24% 6.2 4.7 -24% 231 156 -32% NB 401 586 46% 20.3 14 -31% 5.2 5.7 10% 119 276 132%
400 West SB 483 463 -4% 17 17.8 5% 5.6 4.3 -23% 206 165 -20% NB 434 452 4% 18.2 21.5 18% 5.4 4 -26% 180 160 -11%
300 West SB 395 404 2% 19.6 23.7 21% 4.8 3.3 -31% 147 120 -18%
Traffic Signal Management and Synchronization Project for Salt Lake City
16
Table 2 – Travel Time and Delay Study, AM Peak (Continued)
Travel Time (sec) Average Speed (mph) Number of Stops Total Delay (sec) Corridor
Before After Change Before After Change Before After Change Before After Change
NB 427 331 -22% 12.8 17.7 38% 6.4 4 -38% 191 122 -36% 200 West
SB 542 478 -12% 10 11.6 16% 7 6.3 -10% 323 280 -13% NB 482 379 -21% 9.7 12.5 29% 7.2 4.7 -35% 278 182 -35%
West Temple SB 379 351 -7% 12.5 13.3 6% 5.4 4.7 -13% 185 176 -5%
NB 403 408 1% 14.8 14.9 1% 3.8 6 58% 195 198 2% State Street
SB 318 226 -29% 17.7 25.5 44% 3.6 2 -44% 94 47 -50%
NB 259 230 -11% 19.2 17.6 -8% 3 3.3 10% 77 91 18% 200 East
SB 283 252 -11% 17.5 17 -3% 3 3 0% 103 108 5% NB 521 419 -20% 9.3 11.2 20% 6.8 5 -26% 313 228 -27%
300 East SB 272 280 3% 18.4 17 -8% 3.6 3 -17% 86 107 24% NB 469 320 -32% 10.7 15.7 47% 6.2 3.7 -40% 282 134 -52%
400 East SB 438 352 -20% 11.2 14.2 27% 6.2 5 -19% 245 151 -38% NB 242 264 9% 20.9 19.1 -9% 3 3 0% 69 73 6%
700 East SB 225 246 9% 22.7 19.7 -13% 2.6 3 15% 63 72 14% NB 281 180 -36% 18.2 23 26% 2.6 0.5 -81% 97 42 -57%
900 East SB 260 193 -26% 19.3 21.1 9% 3 1.5 -50% 75 63 -16%
Average 415 381 -8% 16 17 8% 5 4 -17% 179 154 -14%
Traffic Signal Management and Synchronization Project for Salt Lake City
17
Table 3 – Travel Time and Delay Study, Midday Peak
Travel Time (sec) Average Speed (mph) Number of Stops Total Delay (sec) Corridor
Before After Change Before After Change Before After Change Before After Change
EB 480 425 -11% 15.9 18 13% 6 5 -17% 200 145 -28% South Temple
WB 443 447 1% 17.5 17.1 -2% 5.2 7 35% 165 150 -9% EB 375 316 -16% 19.7 23.7 20% 3.8 3.3 -13% 107 64 -40%
100 South WB 422 461 9% 17.7 16 -10% 4.4 6.3 43% 143 187 31% EB 602 503 -16% 12.2 14.7 20% 8 6.7 -16% 308 209 -32%
200 South WB 405 516 27% 18.4 14.4 -22% 3.4 6.7 97% 139 238 71% EB 470 424 -10% 14 15.4 10% 7.2 5.7 -21% 199 139 -30%
300 South WB 564 472 -16% 11.5 13.9 21% 7.2 6 -17% 291 188 -35% EB 431 476 10% 18.8 16.8 -11% 4.4 5.8 32% 141 187 33%
800 South WB 439 373 -15% 18.2 21.7 19% 5 3.5 -30% 156 94 -40% EB 431 352 -18% 16.7 20.2 21% 5.4 4 -26% 159 92 -42%
900 South WB 428 384 -10% 16.9 19.4 15% 5 4 -20% 154 139 -10% NB 337 389 15% 17.8 15.4 -13% 3.6 3.7 3% 108 165 53%
400 West SB 325 350 8% 18.6 17.4 -6% 4.6 3.3 -28% 96 119 24% NB 447 439 -2% 17.1 17.3 1% 5.8 5 -14% 188 171 -9%
300 West SB 300 327 9% 26.3 23.2 -12% 1.6 3 88% 56 71 27%
Traffic Signal Management and Synchronization Project for Salt Lake City
18
Table 3 – Travel Time and Delay Study, Midday Peak (Continued)
Travel Time (sec) Average Speed (mph) Number of Stops Total Delay (sec) Corridor
Before After Change Before After Change Before After Change Before After Change
NB 460 429 -7% 12.2 12.8 5% 7 6 -14% 241 222 -8% 200 West
SB 460 390 -15% 12.2 14 15% 6.6 6.8 3% 239 166 -31% NB 366 390 7% 13.7 11.9 -13% 4.8 5.7 19% 157 200 27%
West Temple SB 480 395 -18% 10.2 12 18% 6.2 5 -19% 272 210 -23%
NB 343 367 7% 16 15.3 -4% 3.4 5 47% 132 172 30% State Street
SB 265 246 -7% 22.3 22.5 1% 2.8 3 7% 62 58 -6%
NB 252 314 25% 17.5 13 -26% 3.4 5 47% 83 147 77% 200 East
SB 301 263 -13% 14.4 15.5 8% 4 4.3 8% 141 99 -30% NB 412 352 -15% 12.1 13.8 14% 5.6 5 -11% 200 134 -33%
300 East SB 349 289 -17% 14.2 18.4 30% 4.4 3.3 -25% 142 103 -27% NB 408 355 -13% 12 14.2 18% 6.6 5 -24% 220 162 -26%
400 East SB 371 272 -27% 13.3 17.9 35% 5.8 3.7 -36% 181 86 -52% NB 279 248 -11% 18.4 19.6 7% 3.4 2.7 -21% 112 72 -36%
700 East SB 232 228 -2% 21.3 21.9 3% 2.8 3 7% 71 63 -11% NB 202 199 -1% 18.7 19.1 2% 2.6 1.7 -35% 58 58 0%
900 East SB 200 206 3% 19.9 18.5 -7% 1.8 3 67% 55 64 16%
Average 384 362 -6% 16 17 4% 5 5 -3% 156 137 -12%
Traffic Signal Management and Synchronization Project for Salt Lake City
19
Table 4 – Travel Time and Delay Study, PM Peak
Travel Time (sec) Average Speed (mph) Number of Stops Total Delay (sec) Corridor
Before After Change Before After Change Before After Change Before After Change
EB 377 377 0% 20.7 20.8 0% 4.2 4 -5% 95 117 23% South Temple
WB 458 384 -16% 16.6 19.8 19% 5.8 5.3 -9% 154 104 -32% EB 272 309 14% 21.1 18.5 -12% 1.2 3.3 175% 68 100 47%
100 South WB 404 364 -10% 14 15.8 13% 4.4 3.7 -16% 190 155 -18% EB 519 438 -16% 13.1 15.6 19% 6 5 -17% 217 185 -15%
200 South WB 464 464 0% 14.9 15.2 2% 6 5 -17% 200 207 4% EB 390 404 4% 15.3 14.9 -3% 3.2 4.7 47% 150 159 6%
300 South WB 616 576 -6% 9.7 10.5 8% 7.6 7.7 1% 316 301 -5% EB 548 570 4% 16.1 15.4 -4% 6.2 5 -19% 219 262 20%
800 South WB 502 488 -3% 17.3 17.8 3% 5.8 4.3 -26% 179 191 7% EB 547 580 6% 16.1 14.9 -7% 6.2 6.7 8% 209 252 21%
900 South WB 548 564 3% 16.1 16.2 1% 7.4 6 -19% 206 245 19% NB 418 295 -29% 14.2 11.3 -20% 4.4 2.3 -48% 191 142 -26%
400 West SB 316 293 -7% 19.2 20.9 9% 3.6 2.7 -25% 83 79 -5% NB 493 454 -8% 19.5 21 8% 4.8 3.5 -27% 198 155 -22%
300 West SB 466 396 -15% 20.6 24.2 17% 4.4 2.3 -48% 165 110 -33%
Traffic Signal Management and Synchronization Project for Salt Lake City
20
Table 4 – Travel Time and Delay Study, PM Peak (Continued)
Travel Time (sec) Average Speed (mph) Number of Stops Total Delay (sec) Corridor
Before After Change Before After Change Before After Change Before After Change
NB 452 540 19% 12.1 10.1 -17% 5.6 6.7 20% 238 324 36% 200 West
SB 532 362 -32% 10.2 15.3 50% 6.8 5.3 -22% 317 141 -56% NB 445 440 -1% 11.5 11 -4% 6.3 6.7 6% 210 245 17%
West Temple SB 765 398 -48% 7 12.4 77% 8.2 4.7 -43% 556 208 -63%
NB 367 265 -28% 15.2 21.1 39% 4.4 2.7 -39% 148 67 -55% State Street
SB 264 404 53% 20.5 13.5 -34% 2.4 4.7 96% 67 193 188%
NB 284 340 20% 15.2 12.2 -20% 4.2 3.7 -12% 112 185 65% 200 East
SB 337 195 -42% 12.9 21.2 64% 4.5 2 -56% 156 45 -71% NB 354 309 -13% 14.3 15.7 10% 5 4 -20% 152 109 -28%
300 East SB 414 315 -24% 12.1 15.7 30% 5.6 3.7 -34% 208 116 -44% NB 467 414 -11% 10.9 11.8 8% 6 5 -17% 275 224 -19%
400 East SB 357 302 -15% 14 16.8 20% 4.2 3.3 -21% 179 129 -28% NB 240 167 -30% 20.7 23 11% 2.8 1 -64% 64 51 -20%
700 East SB 241 229 -5% 20.5 17.2 -16% 2.2 2.7 23% 80 96 20% NB 207 223 8% 18.7 17.7 -5% 2.8 1.7 -39% 63 69 10%
900 East SB 230 310 35% 16.6 12.3 -26% 3.2 3.7 16% 80 166 108%
Average 415 380 -8% 16 16 5% 5 4 -14% 180 160 -11%
Traffic Signal Management and Synchronization Project for Salt Lake City
21
4.2 Network-Wide Measures of Effectiveness Improvements The tables in the previous subsection show improvements for the average run, without adjusting for the different traffic volumes on each street. Network-wide total delay and total stops improvements are reported by the Synchro Models and compared in Table 5 with each street weighted according to their current traffic volumes. With the optimized timing plans, total delay within downtown area was reduced by 14% for AM Peak, 10% for Midday Period, and 7% for PM Peak. The number of total stops was reduced by 8% for AM Peak, 7% for Midday Period, and 8% for PM Peak.
Table 5 – Network-Wide Measures of Effectiveness Improvements Total Delay (hr) Total Stops (#)
Time Period Before After Percent
Change Before After Percent Change
AM 1876 1616 -14% 155799 144101 -8%
Midday 1467 1319 -10% 151841 140711 -7%
PM 2154 1995 -7% 176230 162467 -8%
4.3 Fuel Consumption and Pollutant Emission Minimizing fuel consumption and related pollutant emissions are prime goals of this project. Fuel consumption is closely related to traveling distance, delay and stop/idle time at each intersection. For a vehicle trip of a given length, the number of stops, acceleration and deceleration cycles, and speed changes can affect Carbon Monoxide (CO), Oxides of Nitrogen (NOx), and Volatile Organic Compounds (VOC) Emissions. Signal timing plans were optimized to reduce fuel consumption and pollutant emissions by minimizing system-wide delay and number of stops, and providing higher and steadier cruise speeds along study corridors. Table 6 presents the fuel consumption savings and emissions decrease achieved by optimizing traffic signal operation for each peak period.
Table 6 – Peak Hour Fuel Consumption and Pollutant Emission Comparison
Peak Hour Network MOE Existing Optimized Reduction Fuel Consumed (gal) 4715 4437 278 (5.9%) CO Emissions (lbs) 728 683 42 (5.8%)
NOx Emissions (lbs) 141 132 9 (6.3%) AM
VOC Emissions (lbs) 168 159 11 (6.6%) Fuel Consumed (gal) 4189 4013 176 (4.2%) CO Emissions (lbs) 646 617 26 (4.1%)
NOx Emissions (lbs) 126 121 4 (3.5%) Midday
VOC Emissions (lbs) 150 143 7 (4.4%) Fuel Consumed (gal) 5279 5059 220 (4.2%) CO Emissions (lbs) 814 780 33 (4.1%)
NOx Emissions (lbs) 159 152 7 (4.2%) PM
VOC Emissions (lbs) 190 181 9 (4.7%)
Traffic Signal Management and Synchronization Project for Salt Lake City
22
Based on a literature review, which included the document titled Methodology for the 2009 Urban Mobility Report, David Schrank, 2009, KOA used the following methodology to calculate the difference in the annual fuel consumption due to the traffic signal optimization for the downtown area:
• Difference in the fuel consumption should be based on the change in fuel consumption during AM, Mid-day and PM peak hours only. The other times of the day will remain unaffected by the recommended traffic signal coordination plans.
• The hourly gasoline consumption rate for the corresponding peak hours (AM, Mid-day, and PM) was extracted from Synchro model output.
• The number of hours that should be considered in the fuel consumption calculations are as follows:
− AM Peak Hour: 2.0 hours − Mid-day Peak Hour: 2.0 hours − PM Peak Hour: 2.0 hours
• Annual fuel consumption calculations are based on 250 weekdays and 115 weekend days. • Normally, the weekend traffic volumes are lower than weekday traffic. Therefore, the weekend
fuel consumption calculations should be based on the reduced fuel consumption rate, if the coordination plan is desired to be implemented.
Table 7 – Annual Fuel Consumption Reduction Daily Reduction Annual Reduction
Fuel Savings (gal) 1348 337,000
CO Emissions Reductions (lbs) 203 50,700
NOx Emissions Reductions (lbs) 40 10,000
VOC Emissions Reductions (lbs) 53 13,200 Table 7 presents the annual fuel consumption and emissions reduction as reported by Synchro models. The calculation only includes weekdays and assumes two hours for each peak period and 250 weekdays a year. With the traffic signal timing operation, fuel consumption is reduced by 337,000 gallons per year within the downtown area, which exceeded the reduction target of 32,000 gallon per year by a factor of ten. The daily and annual reduction in pollutant emissions also greatly exceeded their respective reduction targets.
Traffic Signal Management and Synchronization Project for Salt Lake City
23
4.4 Economic Analysis The motorist annual cost savings associated with signal timing optimization efforts within the study network were estimated using the following assumptions:
• Vehicle delay cost is $10.00 per vehicle hour. • Vehicle stop saving is $0.014 per vehicle stop Fuel cost is $3.00 per gallon
Based on the network-wide measure of effectiveness improvements identified in Table 5, the savings associated with decrease of total delay and total stops are presented in Table 8. A total of $3,091,137 will be saved per year by decreasing total delay and total stops within the study network through signal optimization efforts.
Table 8 – Motorist Cost Savings Associated with Decreased Delay and Stops
Peak Hour Before After Decrease
Peak Hour (hr)
Daily Decrease
Annual Savings
Total
Total Delay
AM 1876 1616 260 2
Midday 1467 1319 148 2
PM 2154 1995 159 2
1134 $2,835,000
Total Stops
AM 155799 144101 11698 2
Midday 151841 140711 11130 2
PM 176230 162467 13763 2
73182 $256,137
$3,091,137
By including the results of fuel consumption analysis, the total economic savings were calculated in Table 9. A conservative value of $3 per gallon of fuel was used for this analysis. Motorists will save $1,011,000-worth of fuel per year. As shown in Table 9, the total annual savings is $4,102,137. The cost of this project is $200,000. This yielded a one-year benefit-to-cost ratio of 21:1. Traffic signal retiming efforts are recommended by ITE to be conducted at least every three years. The three-year benefit is $12,306,411, while the project cost remains $200,000. This yields a three-year benefit-to-cost ratio of 62:1. It is assumed that the signals are properly maintained and monitored at all times, Given the tremendous benefits to cost ratio, it is important that the City allocate sufficient resources to maintain the city’s traffic signal system.
Traffic Signal Management and Synchronization Project for Salt Lake City
24
Table 9– Benefit-to-Cost Ratio Analysis Annual Fuel Consumption Reduction (gallon) 337,000
Dollar Value per Gallon $3.00
One-Year Benefit $1,011,000
Savings by Decrease of Delay and Stops $3,091,137
Total Annual Savings $4,102,137
Project Cost $200,000
Benefit-to-Cost Ratio 21:1
Three-Year Benefit $12,306,411
Three-Year Benefit-to-Cost Ratio 62:1
Traffic Signal Management and Synchronization Project for Salt Lake City
25
5. Recommendations for a Three to Five Years Re-Timing Effort
A traffic signal timing update every three year provides significant direct benefits for the traveling public. Many factors contribute to the need for updates. The major factors are listed below:
• Land use changes • Population growth • Change in flow profiles (volume and classification) • New MUTCD requirements related to signal timing • Increases in the rate of crashes along major corridors • Traffic signal equipment changes, including a new signal system
Optimal timed signals along major corridors minimize the diversion of traffic to local and residential streets, improving safety and traffic conditions. They also lead to reduced fuel consumption, reduced emissions, and improved air quality. Currently, the City maintains a database of the traffic signals, including controller type and history of updates. However, the City does not have enough resource to maintain a Performance Measure of Effectiveness (MOE) database to track the operational performance within the City’s roadway network. We recommend that the City budget adequate staff resource to conduct survey of performance MOE once every other year. The survey of performance MOE will also help in identifying areas where signal retiming efforts should be initiated. Based on the NCHRP 409 Traffic Signal Retiming Practices in the U.S. on average, 26 person hours are required to conduct signal retiming per intersection. A staffing level of five in the City’s TCC is needed to maintain operational and safety performance of the City’s roadway network and retiming of signals in three-year intervals.
5.1 Agency Survey
Many cities throughout the country are benefiting from efficient traffic signal operation within their communities and across jurisdictional boundaries. Listed in Table 10 are four other cities which are considered “comparable” to Salt Lake City in terms of population and population density. A summary of the Traffic Signal Operation Survey is presented in Appendix E.
Table 10 – Selected Cities for Traffic Signal Operation Survey
TCC City State Population
Pop Density (Per Sq.
Mile)
Signals Total Staffing
I/S Per Staffing
Yes Salt Lake City Utah 186,440 1,678 184(1) 7(2) 27 Yes Tallahassee Florida 181,376 1,809 350 13 27 No Amarillo Texas 190,695 1,917 293 14 21 Yes Knoxville Tenn 178,874 1,816 393 19 21 No Little Rock Ark 193,524 1,624 350 10 35
Note: (1) Number of the City intersections including non-system signals (2) Two in TCC and Five in Traffic Signal Maintenance
Traffic Signal Management and Synchronization Project for Salt Lake City
26
Four comparable cities were phone interviewed in June 2011 by KOA staff to answer 10 questions as summarized in Appendix E. The number of traffic signals operated in those four cities range from 293 to 393. Tallahassee, Amarillo and Knoxville have full control of traffic signals within the city boundary. Little Rock does not maintain County’s or State’s traffic signals, but provides timing plans for traffic signals within the city boundaries. Out of the four surveyed cities, Little Rock is the only city that has a light rail operation. However, its operation is far smaller in distance covered and patrons served compared to the light rail operation in Salt Lake City.
5.2 Staffing Needs Staffing needs for traffic signal system operations are discussed in several literature documents. As shown in the Table 11, FHWA Traffic Signal Timing Manual provides general guidelines on staffing needs for a traffic signal system as it relates to signal retiming.
Table 11 – Summary of Staffing Needs*
Position 1 to 50 Traffic Signals
51 to 100
Traffic Signals
101 to 200
Traffic Signals
201 to 500
Traffic Signals
501 to 1000
Traffic Signals
Traffic Signal Engineer 0 to 1 1 1 to 2 2 to 5 5 to 10 Traffic Signal Analyst/Technician 0 to 1 0 to 1 1 1 to 3 3 to 5 ITS Engineer - - 0 to 1 1 1 to 3 Traffic Signal Maintenance Technician 1 to 2 2 to 4 4 to 7 7 to 17 17 to 33 Electronic Specialists 1 1 1 to 2 2 to 4 4 to 9 TMC Operators - - 2 2 to 4 4 to 9 Public Relations Coordinator 0 to 1 0 to 1 1 1 2
Note: * FHWA Traffic Signal Timing Manual The ITE “Traffic Control System Operations” manual suggests that a traffic signal system should have one traffic engineer per 75 to 100 traffic signals and one signal technician per 40 to 50 traffic signals or other field devices. An NCHRP report (Synthesis 245) also suggests 38 to 43 signals per technician. The manual also provides staffing guidelines for a continuously operated TMC which includes one center manager, two supervisors, and five system operators. The unique physical and operational characteristics of Salt Lake City’s signal system may require more resources than that of a typical city with similar number of signals. The recommended staff resource for the Traffic Control Center of Salt Lake City is summarized in Table 12. To have adequate resources to handle daily operations, special events and retiming of signals on a scheduled interval, two new engineers and one additional operator are recommended to operate the 184-intersection signal system. The
Traffic Signal Management and Synchronization Project for Salt Lake City
27
additional operator would replace a position lost due to budget constraints. If the recommendation is followed, the TCC would have a total of 5 people, including the Director.
Table 12 – Recommended Staff Resource for Traffic Control Center
Staff Resource Traffic Signal
Engineer
ITS Engineer
TCC Operators Total
Per FHWA Guidelines 1 to 2 0 to 1 2 3 to 5
Existing 0 0 1 1
Recommended Additional Staff 2 0 1 3
Total 2 0 2 4
5.3 Traffic Signal System Improvements KOA recommends the following measures to improve the traffic signal system performance:
5.3.1 Trouble-Shoot Signal Transition Problems
The review of current signal system operations identified that some city intersections running with customized pedestrian logic may cause signal yield point drift when a controller loses the detection on minor streets. The City staff is working with Econolite engineers toward solving this problem. A few of the UDOT intersections were found to behave differently in the field to what is shown on the central i2 system. UDOT staff may need to check the controller status in the field. Routine review and troubleshooting of signal operations are recommended to keep the signal system efficiently working as designed. 5.3.2 Consistent Pedestrian Crossing Operation
Pedestrian push buttons are provided at most signals in the core CBD area, while at most intersections outside the CBD area, pedestrian push buttons are not installed. Although the pedestrian volumes are low at these intersections outside CBD, the signals are timed to accommodate pedestrian crossing. Due to the size of the intersections, a long cycle length has to be maintained, which create seemingly long delays, especially during off-peak hours. It is recommended that the City allocate funds to install pedestrian push buttons at these intersections so that the current cycle lengths can be reduced with the benefits of reducing delays for motorists.
Traffic Signal Management and Synchronization Project for Salt Lake City
28
5.3.3 Traffic Data Collection
Traffic volume data is important to network-wide signal operation optimization efforts. However, the data collection can be costly and time intensive. This project estimated traffic turning volumes at a great number of intersections in Synchro models. For the future operation efforts, the survey of performance MOE can help in identifying areas where traffic data needs to be updated to justify and support signal re-timing efforts. Field fine-tuning efforts identified inconsistencies between real-time traffic and estimation at some intersections. For future signal re-timing efforts, traffic count stations need to be installed to collect data to track changes of the flow profiles at major corridors. Three categories of traffic data should be considered during the data collection:
• 24-Hour tube counts can be used to evaluate the number of timing plans used during the weekdays and weekend, to decide when to transition from one timing plan to the next, and to develop adjustment factors for some timing periods without conducting other turning movement counts. Tube counts should be collected at critical locations on, but not limited to, the following corridors: − State − 700 East − 1300 East − North Temple − 400 South − 500 South − 600 South − 900 South
• Turning movement counts are typically collected at each of the study intersections in consideration of re-timing. Depending on the traffic patterns along the streets, turning movement counts are often conducted during peak periods: the weekday morning, midday, and afternoon peak hours. Tube counts should be used to identify each peak period for collecting the counts, as well as for developing adjustment factors for the weekend volume. Traffic volumes may be higher or more critical during the weekend at some locations, although that has not been observed to be the case in the Salt Lake City downtown area.
• Travel time and delay runs can be used to review the signal operation performance before and after the new timing plans are implemented. The travel time and delay runs can be collected by driving along the study corridors and recording the delay, running time, and stops using GPS-based equipment. Travel time and delay can be reported to elected officials and the public when doing signal timing optimization. The runs are also good to monitor traffic to determine the quality of existing signal operations and the need for retiming efforts. Salt Lake City is maintaining a comprehensive travel time delay runs database within the downtown area.
Traffic Signal Management and Synchronization Project for Salt Lake City
29
This project conducted after runs for 16 corridors: three runs for each direction each peak period.
5.3.4 Cross-jurisdictional Traffic Signal Re-Timing
The joint efforts from the City and UDOT have been contributing to the improvements of system-wide signal operations in the downtown area. For the future signal re-timing efforts, the City, UDOT and UTA should jointly discuss operational improvements at intersections with light rail operations. 5.3.5 Newer Central Traffic Management Software
Siemens i2 Central Traffic Management Software (TMS) has been used to manage 755 traffic signals in the Salt Lake Metropolitan area, encompassing three counties, for the past 12 years. In the near future, this software will no longer be supported by the manufacturer and will need to be replaced. Newer generations of central traffic management software are available that are easier to use; could detect, quickly diagnose and correct system problems; and, provide more robust reporting. In general, they operate in more effective and efficient manners. The newer software also provides a more secured interface and supports features such as emergency and/or incident response, transit signal priority and full set of customizable features to fit individual needs of the City. A comprehensive search is needed to review these software packages in order to determine which of them best suits the needs of the Salt Lake City area’s traffic signal system.
Traffic Signal Management and Synchronization Project for Salt Lake City
30
6. Performance Comparisons with Three Other Cities
There are several features that are unique to Salt Lake City that could not be found in other cities in the U.S. The most significant feature, perhaps, is the overall size of the average intersection. The downtown streets are unusually wide, resulting in long crosswalks and accompanying long pedestrian clearance times. Many intersections in the core and peripheral downtown area have simple two-phase operation, but some locations provide left turn phases. Some of these provide more efficient protected/permitted left-turn operation, while other left turn phases are fully protected. Outside of the core downtown area, many large intersections have no pedestrian push buttons. These features result in the need to use relatively a long traffic signal cycle which, in turn, necessitates longer waits at the intersections. Furthermore, the light rail operation that runs on Main Street and 400 South and cuts through the downtown area features traffic signal controllers that provide priority to minimize delays for the light rail operation, possibly at the expense of motor vehicular and pedestrian traffic. All these features constrain traffic signal operation and re-timing efforts within Salt Lake City downtown area. Downtown networks of three other cities were selected for comparison. They are the City of Honolulu, Hawaii, City of Louisville, Kentucky and City of Santa Monica, California. Like Salt Lake City, the three cities have traffic management centers that allow for monitoring and instant timing updates from its respective center. The average size of their intersections is smaller than that of Salt Lake City, better representing what one finds in other U.S cities. Pedestrian traffic in the cities of Santa Monica and Honolulu is significantly higher than Salt Lake City. There are significantly more one-way streets in downtown Louisville than the other three cities. Within Louisville’s project study area, there are 26 corridors, of which 18 of them are either one-way or partial one-way streets. One-way streets are more efficient movers of traffic and provide for higher travel speeds than two-way streets. Table 13 below summarizes the Measures of Effectiveness (MOE’s) of the four cities.
Table 13 – Measures of Effectiveness (MOE’s) of Four Cities
City State No. of I/S in the Network
Average Speed (mph) Delay/Int Stops/Int
AM 173 17 9.3 833 Salt Lake City
PM 173 16 11.3 939 AM 74 12 10.7 997
Honolulu PM 74 10 15.4 1117 AM 60 14 6.4 733
Santa Monica PM 60 12 11.4 1123 AM 220 20 10.5 n/a
Louisville* PM 220 19.5 13.6 n/a
Note: *Based on a report prepared by Entran, PLC, submitted to the City on October 2009.
Traffic Signal Management and Synchronization Project for Salt Lake City
31
Despite its relative large intersection size and having light rail operation running through the downtown area, Salt Lake City fares well in comparison with other cities. It has the second highest average speeds for both peak periods. Salt Lake City has the lowest average delay and number of stops during the evening rush hours.
Traffic Signal Management and Synchronization Project for Salt Lake City
32
7. Conclusions
This report documented the existing traffic signal operation analysis, optimized timing plan development, field fine-tuning and implementation, performance improvement, and fuel consumption savings associated with the signal retiming efforts within the greater CBD area in Salt Lake City. This report also surveyed and compared traffic signal system operation and management of other agencies, and provided the recommendations for the next 3 to 5-year signal retiming efforts. KOA completed the following tasks during this study:
• Attended kick off meeting and collected traffic volume and existing timing plans. KOA manually balanced the traffic volumes at critical locations using Synchro 7 models. The adjusted volumes were reviewed and approved by the City staff.
• Reviewed and updated Synchro networks for AM, midday, and PM peak periods with existing timing plans and balanced turning volumes. Existing downtown signal operation was reviewed in August 2010. Based on the field review, KOA calibrated the existing Synchro networks for three time periods.
• Optimized three signal timing plans for the weekday AM, midday, and PM periods, using calibrated Synchro networks. Different cycle lengths have been tested with the MOE comparison. KOA concurs in using 120-second cycle length for AM and PM peak periods, and proposed partially harmonic cycle lengths of 108 seconds and 81 seconds during the midday period. Minimal changes are recommended to arterial corridors with light rail operation. Splits and offsets are optimized at other intersections accordingly.
• The optimized timing plans were implemented and fine-tuned in May 2011.
• Sixteen corridors were selected to conduct after studies. A total of three runs were conducted for each direction of the corridor for each peak time period.
The conclusions and findings of the study are provided below:
• The physical and operational characteristics of Salt Lake City’s signal system require more staff resources to be adequate for signal system operation maintaining operational and safety performance of the City’s roadway network and retiming of signals in three-year intervals. As a result, KOA recommends hiring two new engineers and one additional operator are recommended to operate the 184-intersection signal system.
• The current Siemens i2 Central Traffic Management Software (TMS), which has been used to
manage traffic signals in the Salt Lake Metropolitan area for the past 12 years, needs to be replaced. In the near future, this software will no longer be supported by the manufacturer.
Traffic Signal Management and Synchronization Project for Salt Lake City
33
The City, together with UDOT and other users of the software, should begin a comprehensive search for a new software package that best suits the needs of the Salt Lake Metropolitan area’s traffic signal system.
• The corridor-based measures of effectiveness (MOE’s) performance collected were average travel time, average speed, number of stops, and total delay. The optimized timing plans improved average MOE’s by approximately 8% to 17% during the peak periods. The after study showed that the optimized timing plans balanced the Salt Lake City downtown roadway system with other travel modes, such as light rail. The signal coordination favors major corridors with heavy traffic volumes such as Sate Street, 500 South, and 600 South. Meanwhile, the optimized timing plans limit the number of stops and delay on the cross streets and provide better progression along the City corridors.
• In terms of network-wide improvement with the optimized timing plans, total delay within the downtown area was reduced by 14% for AM Peak, 10% for Midday Period, and 7% for PM Peak. The number of total stops was reduced by 8% for AM Peak, 7% for Midday Period, and 8% for PM Peak.
• The Synchro models estimated network-wide fuel consumption, carbon monoxide emission, oxides of nitrogen emission, and volatile Organic compounds emission decreases. With the traffic signal retiming efforts, fuel consumption is reduced by 337,000 gallon per year within the study area, exceeding the reduction target of 32,000 gallon per year by a factor of 10.
• Based on the fuel consumption decrease and MOE improvements, an economic evaluation was conducted to identify a three-year benefit-to-cost ratio of 62:1 achieved by this project.
• KOA recommends the following measures to improve traffic signal system performance: routine review and troubleshooting of signal operations, updating the traffic volume database, cross-jurisdictional traffic signal retiming, and updating to a newer generation of central traffic management system.
Considering the overall size of the intersections, light rail operation and absence of pedestrian push buttons at many intersections in the surrounding downtown area, the current traffic system with optimized cycle length, splits and offsets is operating as well as it possibly can using “good practice” strategy and a philosophy of providing transit priority and balanced service to other travel modes.
Traffic Signal Management and Synchronization Project for Salt Lake City
APPENDIX A
EXISTING CYCLE LENGTH
Appendix A ExistingCycle Length Timing Plan: AM
E S
tree
t
500
W
550 S
850 S
100 S
900
E90
0 E
900
E90
0 E
300 S300 S300 S300 S 30 E
300 S
200 S 200 S 200 S 200 S 200 S 200 S 200 S
600 S600 S600 S600 S600 S
W-T
empl
eW
-Tem
ple
W-T
empl
eW
-Tem
p le
Uni
vers
ity S
tU
nive
rsity
St
Mai
n M
ain
1300
E13
00 E
1300
E
900 S900 S900 S900 S900 S
700
E70
0 E
700
E
600
E60
0 E
450 S
N-Temple N-Temple N-Temple
400
W4 0
0 W
400
W50 N
S-TempleS-TempleS-TempleS-TempleS-TempleS-Temple
800
E
500 S500 S500 S500 S500 S
South Campus Dr400 S 400 S 400 S 400 S 400 S
700 S
200
W2 0
0 W
200
W
450 S
700 S700 S
300
E30
0 E
300
E30
0 E
300
E
350 S
400
E40
0 E
Sta
teS
tate
Sta
te
500
E50
0 E
500
E50
0 E
400
E40
0 E
400
E
50 W
800
E80
0 E
1100
E11
00 E
150
W
50 S50 E
150 S
250 S
Mai
n
800 S 800 S 800 S 800 S 800 S 800 S
300
W30
0 W
300
W3 0
0 W
300
W
100 S
100 S100 S100 S100 S100 S
200
E20
0 E
2 00
200
E
500 S500 SUni
vers
ity B
lvd
U
120120
120
120
120
106
94A
120
120
120
120
120
120
77A
60
120
120
120
120
112A
71A
120
71A
120
72A
120
120
120
120
71A 120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
84
70A
120
120
120
60
120
120
120
120
120
120A
120
120
120
120
120
107A
71A
113A
120
73A
120
112A
87A
120
102A
120
94A
120 120 120 120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120 120 125A 120 120 120 120 120 120 120
120 120 120
120 120
120
120
120
120
120
120
Appendix A ExistingCycle Length Timing Plan: AM
E S
tree
t
Bec
k S
t
600 N
Victory Rd
200 N
900 N
N-Temple N-Temple N-Temple
400
W4 0
0 W
400
W
50 N
500 N
50 W
300 N
Mai
n
300
W30
0 W
75A
120
60
120 120 120 120
65A
120
120
120
120 120
120
120
Appendix A ExistingCycle Length Timing Plan: Midday
E S
tree
t
500
W
550 S
850 S
900
E90
0 E
900
E90
0 E
300 S300 S300300 S 30 E
300 S
200 S 200 S 200 S 200 S 200 S 200 S
600 S600 S600 S600 S
W-T
empl
eW
-Tem
ple
W-T
empl
eW
-Tem
ple
Uni
vers
ity S
tU
nive
rsity
St
Mai
n M
ain
1300
E13
00 E
900 S900 S900 S900 S900 S
700
E70
0 E
700
E
600
E6 0
0 E
450 S
N-Temple N-Temple
400
W4 0
0 W
50 N
100 S
S-Temple #1S-TempleS-Temple
800
E
500 S500 S500 S500 S
South Campus Dr
400 S 400 S 400 S
700 S
200
W20
0 W
2 00
450 S
700 S 700 S
300
E30
0 E
300
E
350 S
400
E40
0 E
Sta
teS
tate
St a
t e
500
E50
0 E
500
E
400
E40
0 E
50 W
8 00
E80
0 E
1100
E11
00 E
150
W
50 S50 E
150 S
250 S
Mai
n
800 S 800 S 800 S 800 S 800 S
S-TempleS-Temple
300
W30
0 W
300
W30
0 W
100 S
100 S100 S100 S
200
E20
0 E
2 00
E
500 SUni
vers
ity B
lvd
U
108108
108
132A
108
108
108
108
108
108
108
108
108
77A
47
108
108
108
108
112A
71A
108
71A
108
72A
108
108
108
108
71A 108
108
108
108
108
108
80
80
80
108
108
120
80
108
108
80
80
108
108
108
108
80
80
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
70A
108
94
108
108
108
108
108
108
108
120A
120
108
108
108
108
107A
71A
113A
108
73A
108
112A
87A
64A
102A
108
94A
108 108 108 108
191A
80
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
135A
108 108 110A 108 108 108 108 108 108 108
108 108 108
108 108
108
108
108
108
108
108
Appendix A ExistingCycle Length Timing Plan: Midday
E S
tre e
t
900
E
Beck S
t
Beck S
t
Bec
k S
t
600 N
Victory Rd
200 S 200 S 200 S 200 S 200 S
W-T
empl
e
200 N
900 N
700
E
600
E
N-Temple N-Temple
400
W40
0 W
400
W
50 N
100 S
S-Temple #1S-TempleS-Temple
800
E
500 N
200
W
Sta
t e
50 W
300 N
150
W
50 S50 E
150 S
Mai
n
S-TempleS-Temple
300
W30
0 W
100 S100 S100 S
108
75A
108
108
108
132A
108
108
108
47
108
108
108
112A
71A
108
71A
108
71A 108
108
108
108
108
120
108
108
108
108
108
108
108
108
108
108
108
108108
108
112A
108
108 108 108 108
90A
65A
108
108
108
108
108
108
108
108
108
108
108
108
108
Appendix A ExistingCycle Length Timing Plan: PM
E S
tree
t
500
W
550 S
850 S
900
E90
0 E
900
E90
0 E
300 S300 S300 S300 S
30 E
300 S
200 S 200 S 200 S 200 S 200 S 200 S 200 S
600 S600 S600 S600600 S
W-T
empl
eW
-Tem
ple
W-T
empl
eW
-Tem
p le
Uni
vers
ity S
tU
nive
rsity
St
Mai
n M
ain
1300
E13
00 E
1300
E
900 S900 S900 S900 S900 S
700
E70
0 E
700
E
600
E60
0 E
450 S
N-Temple N-Temple N-Temple
400
W4 0
0 W
400
W50 N
100 S
S-Temple #1S-TempleS-Temple #1S-Temple
800
E
500 S500 S500 S500 S500 S
South Campus Dr400 S 400 S 400 S 400 S 400 S
700 S
200
W2 0
0 W
200
W
450 S
700 S700 S
300
E30
0 E
300
E30
0 E
300
E
350 S
400
E40
0 E
Sta
teS
tate
Sta
te
500
E50
0 E
500
E50
0 E
400
E40
0 E
400
E
50 W
800
E80
0 E
1100
E11
00 E
150
W
50 S50 E
150 S
250 S
Mai
n
800 S 800 S 800 S 800 S 800 S 800 S
S-TempleS-Temple
300
W30
0 W
300
W3 0
0 W
300
W
100 S
100 S100 S100 S100 S100 S
200
E20
0 E
2 00
200
E
500 S500 SUni
vers
ity B
lvd
U
120120
120
120
120
120
94A
120
120
120
120
120
120
77A
120
120
120
120
120
112A
71A
120
71A
120
72A
120
120
120
120
71A 120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
84
120
84
70A
120
120
120
60
120
120
120
120
120
120A
120
120
120
120
120
107A
71A
113A
120
73A
120
112A
87A
120
102A
120
120
120 120 120 120
191A
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120 120 125A 120 120 120 120 120 120 120
120 120 120
120 120
120
120
120
120
120
120
Appendix A ExistingCycle Length Timing Plan: PM
E S
tree
t
900
E
Beck S
t
Bec
k S
t
600 N
Victory Rd
Victory
200 N
900 N
700
E
N-Temple N-Temple N-Temple
400
W4 0
0 W
400
W
50 N
S-TempleS-Temple #1S-Temple
800
E
500 N
2 00
W
300
E
Sta
te
400
E
50 W
300 N15
0 W
50 S50 E
Mai
n
S-TempleS-Temple
300
W30
0 W
120
75A
120
120 120
120
120 112A
71A
71A 120 120 120 120 120120 120120
120 120 120 120
120
60
120
120
120
120
120
120
120
120
120
Traffic Signal Management and Synchronization Project for Salt Lake City
APPENDIX B
EXISTING TRAFFIC VOLUME COUNTS
Appendix A ExistingCycle Length Timing Plan: AM
E S
tree
t
500
W
550 S
850 S
900
E90
0 E
900
E
300 S300 S
30 E
300 S
200 S 200 S 200 S
600 S600 S
W-T
empl
eW
-Tem
ple
Uni
vers
ity S
tU
nive
rsity
St
Mai
n
1300
E
900 S900 S900
700
E70
0 E
6 00
E
450 S
N-Temple N-Temple400
W4 0
0 W
50 N
S-TempleS-Temple
500 S500 S
South Campus Dr
700 S
2 00
200
200
W
450 S
700 700 S
300
E30
0 E
350 S
400
E40
0 E
St a
t e
500
E
400
E
50 W
800
E80
0 E
1100
E11
00 E
150
W
50 S
50 E
150 S
250 S
Mai
n
800 S 800 S 800 S
300
W
100 S
100 S
200
E
500 SUni
vers
ity B
lvd
50
50
6076060
1002070
139 91
822107
86773
192
100
250633523
3
50 3 00
50
5020050
2010050
100
150
150
141
350 64
3210633
249017
3 59 43 8
1 00
5 00 50
204020
304030
308030
50 300 50
50150
50
5050150
5 02 00
5 0
50 200 50
150250
50
50200150
50200
100
50 200 50
5015050
5010050
50200
50
5 0 300 5 050
25050
8040050299613
50 250125
50125
505050
1 50
5 0
41 2 50 75
1453955
2423960
37200
18
50 3 00 50
4025040
5010050
50150
5 0
200 16
9288
204540
22150
24
150 50
5025050
5035050
200
50
1 70
160
46 134
150
35046
40027299826
3 23
63
243918
6
60 350
25050
50050
15025050
5 01 50
5 0
50 700
15050
350100
5010050
100
400
50
50 50
50050
50450
100
50
100
100100
10
60204010
60
50
38 61
17769
41
940217
3826
100
90
69 78
12524
24
25155235834
24 100 27
238614
74034
5921
50 100 50
5050050
50400100
107010
120
100 20
6052060
3037020
20100
10
600
500
200
100
700150
100500
50 200 50
5045050
3015030
50100
50
50 300 50
50600
50
5040050
50100
50
50 4 00 80
5030060
5035050
50100
50
200
300
70105070
100
20
2 00
77
2901954
49
2289
27 242 2724
4633
145221
41 05
1 8
80 200 50
5040050
5040050
20100
50
100
200 50
100300100
5025050
50100
50
29 70
75034
135627
50 200 50
5040050
3012030
20100
20
50 270 50
5050050
5040050
50100
50
48 244 59
4225064
3934247
14168
38
100
300
80105050
140
80
50 50
3501500
1505050
50 200 50
5035050
50400150
50100
50
100
150 50
5030050
5020050
50100
50
30 120 30
4036040
2014020
1 01 00
1 0
50 150 30
5035050
5045050
50100
50
50 150 50
3020050
5035050
50100
50
100
260
60100050
9 09 0
15 46 18
24330
9
757615
73514
50 50 50
5030050
8025040
203020
102588
649264
258
168
50 2 50
1 0020
30020
5030050
50100
50
54 381 43
3521023
3447234
1 71 71
2 3
50 400 50
5020040
4035050
50200
50
67 632 30
1491132
1295151
400 50
300800100
50100
20 350 5050
5050
505050
50100
50
60 250 50
5030050
5040050
50100
50
29 252 38
3327733
3126114
157428
150 50 50
103020
80700100
30100
100
450300
38050350500
100450505025
050
200
1100 10050
50250
15010050
50800
50
250
1400 50
4020030
4018040
60900
60
248
1674 85
2411743
6915012
35922
47
100
100 50
50450100
40400405010
050
50 260 50
5015050
50200504014
040
65 272 31
2315743
361789
0186
14
50 360 40
4015050
5015040
40180
50
30 350 5050
35050
505050
50150
20
50 2 50 50
5045050
5040050
50100
50
50 250 50
50150
50
5030050
5 01 00
5 0
50 50 10
40180
40
2017020
301030
239
93
377291
115175
150
300 50
20180
20
505010
20370
20
73 4 84
1 10
2010452
424061540
29
70 600 50
5050
100
5020505 03 5
01 5
0
7 5 250
25050
2050
1005050
50350
100
25 50 50
1015050
5010050
255025
505020
1010050
303060
108 17
2521162
21
1647
1 00
50
75070
50700
50 1 00 50
5015050
503505
505050
50 150 50
5022030
5035050
505050
50 50 50
100500100
5050050
50100
50
100 50
5015050
5010050
300
50
150
109020
020
0 0
0100
0
350
500
300
100
40 40 70
5010050
5020050
100
50100
24 69 9014337
1020024
83 92
50
15 0 50
5045050
5040050505050
450150
150450
7550
200
350
100 10 10050
25050
5030050
5 05 05 0
1 0 400
1010
110
30
100
250 75
401000
40
5060050
50200
50
29 79 65
18295077
37600110845119
1100
700
40 10401000
110
40650190
360
24
100
700
150
100450100
503501007030
020
59 766 55
6413819
3011569
11309
28
100
310
220100
350100
200450150
561
825
10
40 500 60
20010
50300100
601030
40
50 6 00 50
60200100
503020
100
900
50
50 600
15040
17040
5010050
2 00
5 00
5 0
30 707 85
946
7
223624
79478
14
47 641
591370142
275
146
20 800
100150
1300100
2035070
50280
5
172
911
40128872
150
157
650
200
4502750150
50150
150
750 50
15050
405040
50150
50
145
868
291
1723047
19127053
469015
1349 534
315641
19117125
357
22
368
294 53
16600839
425006929
368
52 7
50 500 50
5045050
70400170
400
900
100
1 7 519
16446
13230
824941
259
563
15
150
600
10080
700100
50400505 06 0
05 0
245
1078 210
23130
63
5828126
67502
82
110
1283 86
11799552
6433847
104
434
26
212
1373
46979217
317
279
1300 50
3002250150
100
300
5012
00 30
507030
305030
40250
60
38 793 42
11141830
5141081
32235
33
72 717 31
13542528
3230354
15295
37
1 56
1680 1 3
96669762
90380647886
744
400
1950 10020
10020
7030050
1 00
7 50
1 00
5820
30 57
363360107
331941
19740
25
5020
00 20050
30050
1003001005075
010
0
5021
00 50
50150150
15020050
50800
50
85 6 01
1 98
13497740
38411190
2 02
2 81
2 3
40 600
150100
160050
5030090
100
300
100
27 231 75
1511501102
2734925
2 51 26
2 9
15 102
122
441340
50
46217254826
21 366 25
1201004
24
479812011
76 4
100
200 50
10090050
6045060
50150
70
22 1 87
19
3789140
1552025
12123
21
100
400
10070
80050
5040050
50250
50
50 100 50
5080050
500505 05 05 0
50 10 40
30850
30
150350100105050
65 441
46
95941
944523
47188
29
130
250
1501350100
200
100
50 150
501300150
5050
50 50 1001000
0
4045040
502050
200
100200
325050
50200
63 47
1402690
20
2138
136
567 67
471680
29
1940648
2 99 22 0
117
663
18162560
4496
1 00
1 00
5003750100
2060
50 100 50
501550100
5050050
906030
20 30
50180050
100
200
2 44
41
4653426
44
103
203
Appendix A ExistingCycle Length Timing Plan: AM
E S
tree
t
Bec
k S
t
600 N
Victory Rd
W-T
empl
e200 N
900 N
N-Temple N-Temple
400
W40
0 W
400
W
50 N
500 N
St a
te
50 W
Mai
n
300
W
50 400 0
105010
10100045
00
50 200 50
10020020
10010015015
025
015
0
16010
025
0 7540
100040
5060050
50200
50
29 79 65
182950
77
37600110
845119
1100
700
40 10401000
110
40650190
360
24
30350400
0
450
150
250 50
2010
250
150300100
201100
20
50 300
10050
10050
00010
012
5015
0
50 350 50
50200
50
505050
501300
50
100
310
220100
350100
200450150
561
825
10
368
294 53
16600839
425006929
368
527
550
1400
90 300 50
200200200
5035050
7 03 00
5 0
Appendix A ExistingCycle Length Timing Plan: Midday
E S
tree
t
500
W
550 S
850 S
900
E90
0 E
900
900
E
300 S300300300 S
30 E
300 S
200 S 200 200 200 200 S 200 S
600 S600600600
W-T
empl
eW
-Tem
ple
Uni
vers
ity S
tU
nive
rsity
St
Mai
n
1300
E
900 S900 S900900900 S
700
E70
070
0 E
600
6 00
E
450 S
N-Temple N-Temple400
W40
04 0
0 W
50 N
100
S-Temple #1S-Temple #1
800
500 S500500500
South Campus Dr400 400 400
700 S
200
200
200
W
450 S
700 700
300
E30
0 E
300
350 S
400
E40
0 E
St a
t e
500
E50
050
0
400
E40
0
50 W
800
E80
0 E
1100
E11
00 E
150
W
50 S
50 E
150 S
250 S
Mai
n
800 S 800 800 800 S 800 S
300
W30
030
030
0
100 S
100 S100100
200
E20
02 0
0
500 SUni
vers
ity B
lvd
20 20
150750100
2008040
152 96
591126
90679
219 69
85806439
5
6 0 380 6 0
5020050
7018050
80390
80
204
299 75
6719476
4427167
5 83 07
8 2
5 0 500
5 0
5010050
5015050
50400
50
50 300 50
50150
50
5050150
1 00
3 00
5 0
40 180 40
100700
50
100700100
50280
100
50 200 50
5025050
5020050
50200
50
98 1 3 231
13021
42179453012
923
100
12020
1040
150
4 0
6 8 113 6 4
1543663
5339747
68180
44
5 0 150
10050
15050
5015050
100
1 50
5 0
53 10
128411
219946
274746
200 50
50700
50
50850100
8040
240
130
30 150 59
18260
18496
18125
32
308
7 9
405121
4
50 250
15050
40050
5040090
4 02 00
4 0
50 400
10050
25050
4015040
100
300
50
70 50
25050
80250
0
0
100 50
10050
702010
030
190
150
113 72
40496
52
4653638
9041
110
190
118
111
10263
42
5828949
108
38
35 129 23
139349
2310422
124
9
50 100 50
50600100
5085050
40120
40
50 300 50
5035050
5040050
50150
50
350
400
150
100
470130
130580
40 200 40
5020050
4020040
40190
40
50 250 50
5040050
5045050
50250
50
5 0 250 5 0
5035050
5020050
50300
50
100
200
50115050
140
70
132
3 8
1431193
75
67142
28 145 16
249061
3310721
81 38
4 8
30 170 30
6032060
5046050
40150
40
100
200 50
5036050
5035050
50150
50
58 108
53241
129642
50 200 80
5020050
5020050
40150
40
40 250 40
4037040
4041040
40150
40
29 190 58
7027790
6022579
33226
38
100
200
501050100
250
100
150 50
1501050100
170
50
50 100 50
5029050
5040050
50100
50
80 100 50
4035040
5030050
40100
40
50 150 40
5025050
5025050
1 01 10
1 0
40 160 40
5034050
5037050
40150
40
50 210 40
5027080
5027050
40240
40
20 210
50100060
1 20
1 70
9 51 12
1929916
1044616
167833
50 50 50
5035050
5025020
505030
116515
583251
230
107
8 0 220
8 0
4020070
10025050
30180
40
65 374 50
2435368
4232325
3 73 33
4 7
40 380 30
5035050
5029060
50350
50
68 347 26
2679757
23189
241
300 50
15090050
50170
40 300 4040
2040
402040
30150
30
50 150 30
8020050
50400150
100
100
40
27 147 46
4625050
3522019
45111
25
40 40 10
105010
50700100
3050150
250200
100
50550140
12045050
50300
50
120
470
10050
150200
10020040
50500
50
160
700 60
50150250
4018040
50700
50
148
832 92
56218183
6316528
461083
78
120
100 50
058050
50350503010
070
40 180 40
5030050
50200405010
050
32 214 32
4217748
3419911
4206
14
40 210 40
60200100
10020050
30230
30
40 200 30
9015050
302030
60300
30
5 0 160
5 0
5045050
5045050
50280
50
40 150 50
50200
80
4020040
5 02 50
5 0
40 40 10
5030050
4020040
501050
171
104224
223
107231
50 300
10025
250100
5020010
50350
25
86
4 71
1 2721
87113
8859122142
410
50 600 50
504080
404040
50520
30
5 0 570 5 050
5050
2005050
50550
50
20 50 50
1035050
4020040
505020
5010010
1010040
4040100
86 20
1501058
12
38117
150 6 0
60050
80650
5 0 100 5 0
5040050
5030050
30100
30
50 100 50
5035050
5029050
404040
50 50 50
4059040
5050050
50100
50
200
100
5025050
5020050
100
50
200
80
100
10
10 280 10
100
100
10
250
240
240
120
50 50 50
5025050
4020040
100
2080
16 58 33
018640
12021181
438913
3 0 6 0 3 0
2045020
5045050
306030
150380
230100
1010
280
170
100 50 10050
25050
5025050
4 04 04 0
1 0 250
3020
250
25
50 50 50
5067050
5060050
50100
50
73 61 80
72607
42
4159258
435232
730
600
100 50140
450100
50450200
360
30
80 450
100
50400100
6045070
70490
20
57 534 52
457133
367041
22572
45
540
511
64350100
275150316
295
422
11
50 450 50
15050
5010040
50700
50
5 0 500
5 0
5020050
4010040
40700
40
50 550 50
5030050
5040050
5 06 50
5 0
58 545 71
316224
6711764
50613
39
90 541
1221609150
430
174
50 400 50
8080080
5076050
50300
50
123
414
56144185
248
224
600
150
2001750150
50350
50 760 50
25050
5020050
50500
50
173
656
263
33608105
393726130
138
372
64
488
2416
18173
20624944
417
26
448
437
10232
155389
5418435
131
3 84
2 8
40 560 50
10025050
200250280
260
400
120
1 8 502 8 7
266945
9635113
91566
15
50 750 50100
40070
50500504 06 4
07 0
72 713
151
51209124
8320962
69622
56
84 613
18098
83672
19163186
112
685
45
170
921
1081002211
689
415
750 30
3001300200
100
700
50 680 80
2010020
3013030
60850
60
116
641 57
10133277
10240552
55772
111
104
720 68
8231372
7933055
72867
86
212
740
131182
612189
13178757
156
996
147
270
1000 50
204020
5040050
7 01 00 0
2 00
88 956 25
300228202
252545
131031
65
5085
015
0
5025050
50450508011
0080
50 850 50
5025050
12015050
601200
70
8 2 366
100
109767
74
99711190
1 98
4 24
8 1
100
550 60
5090050
5070050
70550
100
37 174 26
6785967
6368957
3 52 12
1 6
25 131 84
3486829
80951628832
31 182 90
59950
44
8651077223
31 1
0
100
150 50
5090050
5090050
50250
50
3 0 153
5 8
5487130
5191089
94216
55
50 330 40
6085060
60100060
50350
50
100 50 50
5085050
10001006 01 0
04 0
20 20 20
5080050
2095020202020
71 257 30
68974
5083131
62274
89
120
430
601620100
230
120
70 200
50150040
100
20
0 80 120780
30
5080050
50200
50
300 50250
1900100
70200
149 56
1661699
69
3487
90 441 63
5982118
47843102
1 14
2 74
7 9
92 475
22203365
122
252
300
100
2502250
50
80150
100
100 50
10080050
5090050
40200
40
50 100
50230050
100
250
420
7 4
2542028
31
131
365
Appendix A ExistingCycle Length Timing Plan: Midday
E S
tree
t
Beck S
tB
eck
St
600 N
Victory Rd
W-T
empl
e200 N
900 N
600
E
N-Temple N-Temple
400
W40
0 W
400
W
50 N
S-Temple #1
500 N
St a
te
50 W
50 S
Mai
n
300
152 96
591126
90679
50 4 00 2050
5050
0500
50400
50
25 250 25
2510050
2020025
50350
25
219 69
85806439
5
98 1 3 231
13021
42179453012
923
240
130
30 150 59
18260
18496
18125
32
70 50
25050
80250
0
350
400
150
100470
130
130580
58 108
53241
129642
116515
583251
230
107
1 50 60
60050
80650
250
240
50 50 50
50670
50
5060050
50100
50
73 61 807260742
4159258
435232
730
600
100 50140
450100
50450200
360
30
0 7504000
775400
150
650
5 050100100
5020050
25700
50
25 700 5020
1030
501020
50700
50
25 700 2525
2550
1002525
25700
25
540
511
64350100
275150316
295
422
11
50 450 50
15050
5010040
50700
50
448
437
10232
155389
5418435
131
384
2 8
40 560 50
10025050
200250280
260
400
120
750
750
50 200 50
200200200
5030050
25350
50
Appendix B ExistingTraffic Volume Timing Plan: PM
E S
tree
t
500
W
550 S
850 S
900
E90
0 E
900
E90
0 E
300 S300 S300 S300 S
30 E
300 S
200 S 200 S 200 S 200 S 200 S 200 S 200 S
600 S600 S600 S600 S
W-T
empl
eW
-Tem
ple
Uni
vers
ity S
tU
nive
rsity
St
Mai
n M
ain
1300
E13
00 E
1300
900 S900 S900 S900 S900 S
700
E70
0 E
700
E
600
E60
0 E
450 S
N-Temple N-Temple
400
W4 0
0 W
400
W50 N
100 S
S-Temple #1S-Temple #1
800
E
500 S500 S500 S500 S500 S
South Campus Dr400 S 400 S 400 S 400 S 400 S
700 S
200
W2 0
0 W
200
W
450 S
700 S 700 S
300
E30
0 E
300
E30
0 E
300
E
350 S
400
E40
0 E
Sta
teS
tate
Sta
te
500
E50
0 E
500
E50
0 E
400
E40
0 E
400
E
50 W
800
E80
0 E
1100
E11
00 E
150
W 50 S
50 E
150 S
250 S
Mai
n
800 S 800 S 800 S 800 S 800 S 800 S
300
W30
0 W
300
W3 0
0 W
100 S
100 S100 S100 S100 S100 S
200
E20
0 E
200
E20
0 E
500 S500 SUni
vers
ity B
lvd
30 20
201400
20
1206 02 0
202 82
667109
101857
352 65
110138
60362
5 0 350 5 0
5020050
1005050
40450
50
187
322 53
6423745
8030173
8 54 39
7 1
5 0 450
5 0
50100100
10010050
50500
50
50 400 50
5015050
5010050
5 04 00
1 00
40 380 30
100450
50
5040050
40380
60
50 200 50
5030050
5020050
50320
70
2 714
6 3 85211634
5324162
20158
52
50 150100
20100
200
4 0
9 7 110 4 5
1839170
7967457
46241
42
5 0 300 5 0
5020050
10025050
50300
5 0
100 60
1712114
1310146
54150
46
150
10050
40050
5045030
200
50
240
170
39 166 48
15539
234103
24149
29
304
150
11082
543
20 350 50
4045040
15065050
5 06 00
5 0
40 350 40
50200100
15030050
50450
50
100
200200
50
100320
180
200
100 40150
40
15040
160
40
150
0
78 52
17536
56
4781331
7137
150
180
102 72
1922355
9541953
131
38
37 114 30
189840
3312121
128
29
50 150 50
3050030
5080050
30150
30
50 150 50
10040050
5055050
5050150
500
400
200 50
600100
50850
50 100 50
4025040
5035050
30300
40
50 100 50
40450100
5060040
40500
100
5 0 160 5 0
5035050
5030050
50550
50
50 200
50155020
280
230
120
3 1
1231499
72
62230
38 117 2129
12960
141176
1 32 33
8 3
30 110 30
4038040
2063020
50250
50
40 150 40
5035050
3045020
40180
100
58 110591
30
110859
150
100 40
4022040
5030050
20150
20
40 250 50
4045060
6045040
50250
50
24 201 69
5936077
4224770
35344
61
50 200
50125050
150
300
70 70
1001500
207070
70 20 50
2042030
3058020
202020
50 30 30
5033050
3040020
203030
40 140 50
3022080
4039030
6 01 20
2 0
40 200 40
5045050
4034040
20300
20
30 160 30
5040050
5025050
50350
50
40 200
40105050
2 00
2 00
16 58 11
2144525
1458417
24112
40
40 50 20
4030050
3035020
20120
30
117542
78528528
510
5
5 0 250
5 0
3030030
5030050
50250
50
58 262 58
3444071
2733230
3 13 90
4 1
50 300 50
5040050
5025050
50400
50
68 347 26
2679757
23189
241
290 30
1001400
50
50150
40 200
30401030
302040
10200
10
40 160 20
3042030
3055020
50200
50
26 153 40
5029559
6329618
20221
57
20 60 20
105010
3085050
4040100
250200
10050300350
20065050
50300
50
100
500 50
50150150
15022030
20800
20
150
600 50
50150250
10020025
501000
50
114
836
10766
255249
7314619
351503
55
100
100 50
030070
5055055010
050
40 200 30
4020040
4018040
20200
40
43 257 27
2317158
561827
6258
14
100
250 5050
200150
5015050
30350
30
20 150 50200
150200
403040
60500
50
3 0 150
4 0
4040040
5055060
50600
100
50 100 50
50250
50
4025040
1 00
5 50
5 0
50 30 10
3019030
1017010
401040
279
103167
229
113312
50 360 70
10100100
7010020
50300
50
75
4 31
70
1671
107
666210
18485
15
50 550 50
5030
150
5020504055
040
5 0 600
15040
4040
2205050
30700
30
30 20 10
108080
5010050
252525
5020010
2022030
3030100
81 22
1471484
25
38224
100 5 0
62080
70870
5 0 100 5 0
5045050
3025040
60100
40
50 100 50
50350100
5030050
50100
50
100
100 50
10300100
2065040
5080100
200 50
5030050
5020050
300
50
12050
260
10
10 220 10
10180
10
250
350
230
180
40 150 40
3020030
4020050
508050
41 82 33
016459
19826870
45202
10
20 10 20
3045030
3053030
201020
25350
400
60100
250
350
100 10 10050
28050
20300205 05 05 0
1 022
0
3030
520
20
50 300 50
15065050
5095050
50200
50
88 88 7750644
66
3788983
769054
790
1000
100 0 70
40590100
40780190
100
50
60 500 60
7045080
13055080
100
700
70
45 428 38
609252
10512334
29834
66
26 764
15050
400200
335200547
313
432
50
50 850 50
15040
5015050
40700
40
5 0 850
5 0
5020050
308030
50750
50
50 800 50
5030050
150400200
5 08 50
5 0
81 746 76
176722
96105105
68823
16
69 585
1102763181
487
504
40 350 40
40800150
50128050
50650
50
93 393
136224761
539
420
400 50
502100
50
80650
30 370 50
20040
4013040
30690
30
84 348
17221
349108
38147972
85673
34
540
35313
193174
56828732
1195
29
660
920
11832
277422
38274148
165
335
49
50 900
100
10040050
150300600
100
600
100
2 1 734 9 659
10749
113115233
138
784
20
70 700 5050
50050
10070050
8 08 00
8 0
74 659
12961
203193
10523678
651058
43
93 618
112138
698134
23589899
149
1201
105
170
768
981562155
1035
425
650 50
2001700170
100
1150
40 700 40
2010020
3017030
201300
20
90 659 74
71387100
9862449
651195
237
75 670 6677
37533
8045167
641035
181
182
906 9 3
151543259
18975375
117
1780
83
250
1150 50
206020
4040040
4 01 95 0
2 50
5910
29 66
378469360
483251
281897
54
3010
50 30
5040050
5050050
602200
100
5010
00 50
6025040
5025050
502150
60
9 6 417 8 1
7857852
114857275
2 67
6 27
7 1
50 800 50
4085040
50130050
50850
100
54 199 16
5985754
95121880
3 83 95
3 4
28 75 81
2293527
127238
49157
79
36 139 64
34980
26
1100666652
91 7
4
100
150 50
10080050
50105050
50350
50
3 6 145
5 8
4877434
5299635
53333
39
50 300 50
5078030
5095050
50350
50
30 100 30
3083030
940804 01 1
04 0
50 30 50
2065020
50100050
302020
91 292 31
60477
11088835
75501
92
100
250
50270050
350
200
50 180
50220050
150
50
010
010
065050
3095050
50150
50
200 50
1002200
50
100
250
123 53
1372063
63
45122
112
365 34
4777355
57140479
8 95 74
8 4
126
491
5351053
144
575
100
100500
2300100
100
100
50 50 50
5080050
70145070
50350
50
50 100
100405050
100
350
458
6 3
2042268
49
150
479
Appendix B ExistingTraffic Volume Timing Plan: PM
E S
tree
t
Beck S
t
Bec
k S
t
600 N
Victory Rd
Victory
W-T
empl
e
200 N
900 N
N-Temple N-Temple
400
W4 0
0 W
400
W
50 N
S-Temple #1
500 N
50 W
300 N
Mai
n
300
300
W
202 82
667109
101857
505 0
0 10201020
000
10500
20
25 450 25
2510050
2510050
50350
25
352 65
110138
60362
27
146
3852
116
5324162
20158
52
240
170
39 166 48
15539
234103
24149
29
100
200200
50
100320
500
400
200 50
600100
50850
58 110591
30
110859
117542
78528528
510
5
50300
300
50
1 00 50
62080
70870
250
350
50 300 50
15065050
5095050
50200
50
88 88 7750644
66
3788983
769054
790
1000
100 0 70
40590100
40780190
100
50
1600
0 11005500
775500
200
1 10 0 5 050
50150
5010025
50700
25
2513
50 50
25100
50
5010025
50700
25
2513
50 5025125
50
2510025
50700
25
26 764
15050
400200
335200547
313
432
50
50 850 50
15040
5015050
40700
40
660
920
11832
277422
38274148
165
335
49
50 900
100
10040050
150300600
100
600
100
1400
750
150
350 25
200200100
2530020
25350
150
Traffic Signal Management and Synchronization Project for Salt Lake City
APPENDIX C
PROPOSED CYCLE LENGTH
Appendix C OptimizedPROPOSED CYCLE LENGTH Timing Plan: AM
KOA Corporation
E S
tree
t
500
W
550 S
850 S
100 S
900
E90
0 E
900
E90
0 E
300 S300 S300 S300 S
30 E
300 S
200 S 200 S 200 S 200 S 200 S 200 S 200 S
600 S600 S600 S600600 S
W-T
empl
eW
-Tem
ple
W-T
empl
eW
- Tem
p le
Uni
vers
ity S
tU
nive
rsity
St
Mai
n M
ain
1300
E13
00 E
1300
E
900 S900 S900 S900 S900 S
700
E70
0 E
700
E
600
E60
0 E
450 S
N-Temple N-Temple N-Temple
4 00
W40
0 W
50 N
S-TempleS-TempleS-TempleS-TempleS-TempleS-Temple
800
E
500 S500 S500 S500 S500 S
South Campus Dr400 S 400 S 400 S 400 S 400 S
700 S
200
W2 0
0 W
200
W
450 S
700 S700 S
300
E30
0 E
300
E30
0 E
300
E
350 S
400
E40
0 E
Sta
teS
tate
Sta
te
500
E50
0 E
500
E50
0 E
400
E40
0 E
400
E
50 W
800
E80
0 E
1100
E11
00 E
150
W
50 S50 E
150 S
250 S
Mai
n
800 S 800 S 800 S 800 S 800 S 800 S
300
W30
0 W
300
W3 0
0 W
100 S
100 S100 S100 S100 S100 S
200
E20
0 E
2 00
200
E
500 S500 SUni
vers
ity B
lvd
U
120120
120
120
120
120
120
120
120
120
120
120
120
77A
120
120
120
120
120
112A
71A
120
71A
120
72A
120
120
120
120
71A 120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120A
120
120
120
120
120
107A
71A
113A
120
73A
120
112A
120
120
102A
120
94A
120 120 120 120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120 120 125A 120 120 120 120 120 120 120
120 120 120
120 120
120
120
120
120
120
120
Appendix C OptimizedPROPOSED CYCLE LENGTH Timing Plan: AM
KOA Corporation
E S
tree
t
900
E
Beck S
t
Bec
k S
t
600 N
Victory Rd
Victory
200 N
900 N
700
E
N-Temple N-Temple N-Temple
400
W4 0
0 W
400
W
50 N
S-TempleS-TempleS-TempleS-TempleS-Temple
800
E
500 N
2 00
W
300
E
Sta
te
400
E
50 W
300 N15
0 W
50 S50 E
Mai
n
300
W30
0 W
120
75A
120
120 120
120
120 112A
71A
71A 120 120 120 120 120120 120120
120 120 120 120
65A
120
120
120
120
120
120
120
120
120
Appendix C OptimizedPROPOSED CYCLE LENGTH Timing Plan: Midday
KOA Corporation
E S
tree
t
500
W
550 S
850 S
900
E90
0 E
900
E90
0 E
300 S300 S300 S300 S
30 E
300 S
200 S 200 S 200 S 200 S 200 S 200 S 200 S
600 S600 S600 S600600 S
W-T
empl
eW
-Tem
ple
W-T
empl
eW
- Tem
p le
Uni
vers
ity S
tU
nive
rsity
St
Mai
n M
ain
1300
E13
00 E
1300
E
900 S900 S900 S900 S900 S
700
E70
0 E
700
E
600
E60
0 E
450 S
N-Temple N-Temple N-Temple
400
W4 0
0 W
400
W50 N
100 S
S-Temple #1S-TempleS-Temple #1S-Temple
800
E
500 S500 S500 S500 S500 S
South Campus Dr400 S 400 S 400 S 400 S 400 S
700 S
200
W2 0
0 W
200
W
450 S
700 S700 S
300
E30
0 E
300
E30
0 E
300
E
350 S
400
E40
0 E
Sta
teS
tate
Sta
te
500
E50
0 E
500
E50
0 E
400
E40
0 E
400
E
50 W
800
E80
0 E
1100
E11
00 E
150
W
50 S50 E
150 S
250 S
Mai
n
800 S 800 S 800 S 800 S 800 S 800 S
S-TempleS-Temple
300
W30
0 W
300
W3 0
0 W
300
W
100 S
100 S100 S100 S100 S100 S
200
E20
0 E
2 00
200
E
500 S500 SUni
vers
ity B
lvd
U
81108
108
132A
108
108
108
108
108
108
108
108
108
77A
47
108
108
108
108
112A
71A
108
71A
108
72A
108
108
108
108
71A 81
81
81
81
108
108
81
81
81
81
81
81
81
108
108
81
81
81
81
81
108
81
81
81
81
81
81
108
108
81
81
81
108
108
108
108
108
81
81
81
81
81
81
81
81
81
81
81
81
81
81
120A
108
81
81
81
81
107A
71A
113A
108
73A
81
112A
87A
64A
102A
81
94A
108 108 108 108
81
81
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
108
135A
108 108 110A 108 108 108 108 108 108 108
108 108 108
108 108
108
108
108
108
108
108
Appendix C OptimizedPROPOSED CYCLE LENGTH Timing Plan: Midday
KOA Corporation
E S
tree
t
900
E
Beck S
t
Bec
k S
t
600 N
Victory Rd
Victory
200 N
900 N
700
E
N-Temple N-Temple N-Temple
400
W4 0
0 W
400
W
50 N
S-TempleS-Temple #1S-Temple
800
E
500 N
2 00
W
300
E
Sta
te
400
E
50 W
300 N15
0 W
50 S50 E
Mai
n
S-TempleS-Temple
300
W30
0 W
81
75A
108
108 108
47
108 112A
71A
71A 81 81 81 108 8181 81108
108 108 108 108
65A
108
108
108
108
108
108
108
108
108
Appendix C OptimizedPROPOSED CYCLE LENGTH Timing Plan: PM
KOA Corporation
E S
tree
t
500
W
550 S
850 S
900
E90
0 E
900
E90
0 E
300 S300 S300 S300 S
30 E
300 S
200 S 200 S 200 S 200 S 200 S 200 S 200 S
600 S600 S600 S600 S
W-T
empl
eW
-Tem
ple
W-T
empl
eW
- Tem
p le
Uni
vers
ity S
tU
nive
rsity
St
Mai
n M
ain
1300
E13
00 E
1300
E
900 S900 S900 S900 S900 S
700
E70
0 E
700
E
600
E60
0 E
450 S
N-Temple N-Temple
4 00
W40
0 W
50 N
100 S
S-Temple #1S-TempleS-Temple
800
E
500 S500 S500 S500 S500 S
South Campus Dr400 S 400 S 400 S 400 S
700 S
200
W20
0 W
200
W
450 S
700 S 700 S
300
E30
0 E
300
E30
0 E
300
E
350 S
400
E40
0 ESta
teS
tate
St a
t e
500
E50
0 E
500
E5 0
0 E
400
E40
0 E
4 00
E
50 W
800
E80
0 E
1100
E11
00 E
150
W
50 S50 E
150 S
250 S
Mai
n
800 S 800 S 800 S 800 S 800 S 800 S
S-TempleS-Temple
300
W30
0 W
300
W3 0
0 W 100 S
100 S100 S100 S100 S
200
E20
0 E
2 00
E20
0 E
500 S500 SUni
vers
ity B
lvd
U
120120
120
120
120
120
120
120
120
120
120
120
120
77A
120
120
120
120
120
112A
71A
120
71A
120
72A
120
120
120
120
71A 120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120A
120
120
120
120
120
107A
71A
113A
120
73A
120
112A
120
120
102A
120
120
120 120 120 120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120
120 120 125A 120 120 120 120 120 120 120
120 120 120
120 120
120
120
120
120
120
120
Appendix C OptimizedPROPOSED CYCLE LENGTH Timing Plan: PM
KOA Corporation
E S
tree
t
900
E
Beck S
t
Bec
k S
t
600 N
Victory Rd
200 N
900 N
700
E
N-Temple N-Temple
400
W4 0
0 W
400
W
50 N
S-TempleS-Temple
800
E
500 N
2 00
W
300
E
4 00
E
50 W
300 N15
0 W
50 S50 E
Mai
n
S-TempleS-Temple
300
W30
0 W
200
E
120
75A
120
120 120
120
120 112A
71A
71A 120 120 120 120 120120 120120
120 120 120 120
60
120
120
120
120
120
120
120
120
120
Traffic Signal Management and Synchronization Project for Salt Lake City
APPENDIX D
TRAVEL TIME AND DELAY BEFORE AND AFTER STUDY REPORTS
Travel Time Delay After Study Summary, AM
Corridor Length (feet) Length (mi) Direction From To Actual From Actual To Travel Time (sec) Speed (mph) No. of Stops Total Delay (sec)
11127 2.11 EB 300 West 1300 East 200 West 1200 East 395 19.4 4.3 13911127 2.11 WB 1300 East 300 West 1200 East 200 West 420 18.2 4.3 14810361 1.96 EB West Temple University Street Main St 1300 East 414 17.4 4.3 15710361 1.96 WB University Street West Temple 1300 East Main St 488 14.6 6.3 2259255 1.75 EB 500 West 900 East 450 West 700 East 470 13.5 4.7 2109255 1.75 WB 900 East 500 West 700 East 450 West 401 15.7 5 1567934 1.50 EB 400 West 1300 East 300 West 700 East 336 16.5 3.3 1107934 1.50 WB 1300 East 400 West 700 East 300 West 389 14.8 4.7 16612687 2.40 EB 300 West 1300 East 300 West 1300 East 541 16.2 5.7 229
South Temple
100 South
200 South
300 South
12687 2.40 EB 300 West 1300 East 300 West 1300 East 541 16.2 5.7 22912687 2.40 WB 1300 East 300 West 1300 East 300 West 516 17 5 23012686 2.40 EB 300 West 1300 East 300 West 1300 East 537 16.3 7.3 20912686 2.40 WB 1300 East 300 West 1300 East 300 West 459 19.3 4.7 15611884 2.25 NB 600 South 900 North 600 South 900 North 586 14 5.7 27611884 2.25 SB 900 North 600 South 900 North 600 South 463 17.8 4.3 16511092 2.10 NB 900 South Victory Road 800 South 600 North 452 21.5 4 16011092 2.10 SB Victory Road 900 South 600 North 800 South 404 23.7 3.3 1207927 1.50 NB 900 South North Temple 900 South North Temple 331 17.7 4 1227927 1.50 SB North Temple 900 South North Temple 900 South 478 11.6 6.3 2807130 1.35 NB 900 South North Temple 800 South North Temple 379 12.5 4.7 1827130 1.35 SB North Temple 900 South North Temple 800 South 351 13.3 4.7 1767933 1.50 NB 900 South North Temple 900 South North Temple 408 14.9 6 198
200 West
800 South
900 South
400 West
300 West
West Temple
State Street7933 1.50 SB North Temple 900 South North Temple 900 South 226 25.5 2 47
7144 1.35 NB 900 South South Temple 800 South South Temple 230 18.1 3 72
7144 1.35 SB South Temple 900 South South Temple 800 South 252 17 3 108
7127 1.35 NB 900 South South Temple 900 South South Temple 419 11.2 5 2287127 1.35 SB South Temple 900 South South Temple 900 South 280 16.9 3 1077129 1.35 NB 900 South South Temple 900 South South Temple 320 15.7 3.7 1347129 1.35 SB South Temple 900 South South Temple 900 South 352 14.2 5 1517132 1.35 NB 900 South South Temple 900 South South Temple 264 19.1 3 737132 1.35 SB South Temple 900 South South Temple 900 South 246 19.7 3 727127 1.35 NB 900 South South Temple 800 South 100 South 180 23 0.5 427127 1.35 SB South Temple 900 South 100 South 800 South 193 21.1 1.5 63
900 East
State Street
200 East
300 East
400 East
700 East
Travel Time Delay After Study Summary, Midday
Corridor Data Year Length (feet) Length (mi) Direction From To Actual From Actual To Travel Time (sec) Speed (mph) No. of Stops Total Delay (sec)
11127 2.11 EB 300 West 1300 East 200W 1200 East 425 18 5 14511127 2.11 WB 1300 East 300 West 1200 East 200 West 447 17.1 7 15010799 2.05 EB West Temple University Street Main St University Street 316 23.7 3.3 6410799 2.05 WB University Street West Temple University Main St 461 16 6.3 18710842 2.05 EB 500 West 900 East 450 East 900 East 503 14.7 6.7 20910842 2.05 WB 900 East 500 West 900 East 450 West 516 14.4 6.7 2389522 1.80 EB 400 West 1300 East 300 West 900 East 424 15.4 5.7 1399522 1.80 WB 1300 East 400 West 900 East 300 West 472 13.9 6 18812687 2.40 EB 300 West 1300 East 200 West 1250 East 476 16.8 5.8 18712687 2.40 WB 1300 East 300 West 1250 East 200 West 373 21.7 3.5 94
2009
2009
2009
2009
2008
South Temple
100 South
200 South
300 South
800 South12687 2.40 WB 1300 East 300 West 1250 East 200 West 373 21.7 3.5 9410340 1.96 EB 300 West 1300 East 200 West 1100 East 352 20.2 4 9210340 1.96 WB 1300 East 300 West 1100 East 200 West 384 19.4 4 1398706 1.65 NB 600 South 900 North 500 South 600 North 389 15.4 3.7 1658706 1.65 SB 900 North 600 South 600 North 500 South 350 17.4 3.3 11911092 2.10 NB 900 South Victory Road 800 South 600 North 439 17.3 5 17111092 2.10 SB Victory Road 900 South 600 North 800 South 327 23.2 3 717927 1.50 NB 900 South North Temple 900 South North Temple 429 12.8 6 2227927 1.50 SB North Temple 900 South North Temple 900 South 390 14 6.8 1667130 1.35 NB 900 South North Temple 800 South 50 North 390 11.9 5.7 2007130 1.35 SB North Temple 900 South 50 North 800 South 395 12 5 2107933 1.50 NB 900 South North Temple 900 South North Temple 367 15.3 5 1727933 1.50 SB North Temple 900 South North Temple 900 South 246 22.5 3 586350 1.20 NB 900 South South Temple 800 South North Temple 314 13 5 1476350 1.20 SB South Temple 900 South North Temple 800 South 263 15.5 4.3 99
2008
2009
2009
2009
2009
2008
2009
200 East
200 West
900 South
400 West
300 West
West Temple
State Street
6350 1.20 SB South Temple 900 South North Temple 800 South 263 15.5 4.3 997127 1.35 NB 900 South South Temple 900 South 50 South 352 13.8 5 1347127 1.35 SB South Temple 900 South South Temple 900 South 289 18.4 3.3 1037129 1.35 NB 900 South South Temple 900 South South Temple 355 14.2 5 1627129 1.35 SB South Temple 900 South South Temple 900 South 272 17.9 3.7 867132 1.35 NB 900 South South Temple 900 South South Temple 248 19.6 2.7 727132 1.35 SB South Temple 900 South South Temple 900 South 228 21.9 3 637127 1.35 NB 900 South South Temple 800 South 100 South 199 19.1 1.7 587127 1.35 SB South Temple 900 South 100 South 800 South 206 18.5 3 64
900 East
2009
2009
2008
2008
300 East
400 East
700 East
Travel Time Delay After Study Summary, PM
Corridor Data Year Length (feet) Length (mi) Direction From To Actual From Actual To Travel Time (sec) Speed (mph) No. of Stops Total Delay (sec)
11127 2.11 EB 300 West 1300 East 200W 1200 East 377 20.8 4 11711127 2.11 WB 1300 East 300 West 1200 East 200 West 384 19.8 5.3 1048374 1.59 EB West Temple University Street Main St 1040 East 309 18.5 3.3 1008374 1.59 WB University Street West Temple 1040 East Main St 364 15.8 3.7 15510054 1.90 EB 500 West 900 East 450 East 800 East 438 15.6 5 18510054 1.90 WB 900 East 500 West 800 East 450 West 464 15.2 5 2078733 1.65 EB 400 West 1300 East 300 West 800 East 404 14.9 4.7 1598733 1.65 WB 1300 East 400 West 800 East 300 West 576 10.5 7.7 30112687 2.40 EB 300 West 1300 East 300 West 1300 East 570 15.4 5 26212687 2.40 WB 1300 East 300 West 1300 East 300 West 488 17.8 4.3 191
2009
2009
2009
2008
2009
South Temple
100 South
200 South
300 South
800 South12687 2.40 WB 1300 East 300 West 1300 East 300 West 488 17.8 4.3 19112689 2.40 EB 300 West 1300 East 300 West 1300 East 580 14.9 6.7 25212689 2.40 WB 1300 East 300 West 1300 East 300 West 564 16.2 6 2458706 1.65 NB 600 South 900 North 500 South 100 North 295 11.3 2.3 1428706 1.65 SB 900 North 600 South 600 North 500 South 293 20.9 2.7 7913925 2.64 NB 900 South Victory Road 800 South 400 West 454 21 3.5 15513925 2.64 SB Victory Road 900 South 400 West 800 South 396 24.2 2.3 1107927 1.50 NB 900 South North Temple 900 South North Temple 540 10.1 6.7 3247927 1.50 SB North Temple 900 South North Temple 900 South 362 15.3 5.3 1417130 1.35 NB 900 South North Temple 800 South North Temple 440 11 6.7 2457130 1.35 SB North Temple 900 South North Temple 800 South 398 12.4 4.7 2087933 1.50 NB 900 South North Temple 900 South North Temple 265 21.1 2.7 677933 1.50 SB North Temple 900 South North Temple 900 South 404 13.5 4.7 1936350 1.20 NB 900 South South Temple 800 South 40 South 340 12.2 3.7 1856350 1.20 SB South Temple 900 South 40 South 800 South 195 21.2 2 45
2008
2009
2008
2009
2009
2009
2009
West Temple
State Street
200 East
200 West
900 South
400 West
300 West
6350 1.20 SB South Temple 900 South 40 South 800 South 195 21.2 2 457127 1.35 NB 900 South South Temple 900 South 50 South 309 15.7 4 1097127 1.35 SB South Temple 900 South South Temple 900 South 315 15.7 3.7 1167129 1.35 NB 900 South South Temple 900 South South Temple 414 11.8 5 2247129 1.35 SB South Temple 900 South South Temple 900 South 302 16.8 3.3 1295546 1.05 NB 900 South South Temple 800 South 100 South 167 23 1 515546 1.05 SB South Temple 900 South 100 South 800 South 229 17.2 2.7 967127 1.35 NB 900 South South Temple 800 South 100 South 223 17.7 1.7 697127 1.35 SB South Temple 900 South 100 South 800 South 310 12.3 3.7 166
900 East
2009
2009
2008
2008
300 East
400 East
700 East
Traffic Signal Management and Synchronization Project for Salt Lake City
APPENDIX E
SUMMARY OF TRAFFIC SIGNAL OPERATION SURVEY
Survey Questions Tallahassee Amarillo Knoxville Little Rock
1) How many signals does the City operate? 350 293 393 350
2) Do you have light rail in the City? No No No No
3) Do you have State controlled streets in downtown CBD area?
City operates all
signals within city
boundary
City operates all
signals within
city boundary
City operates all
signals within
city boundary
City operates all
signals within city
boundary
4) How many staff does the City have for signal operations and
complaints?4 7 10 4
5) Do you maintain you own signals? Yes Yes Yes Yes
6) Under what division (same as the traffic division?), approx how
many technicians9 7 9 6
7) Do you have a TMC? If no, Skip questions 8 through 10. Yes No No Yes
8) How many people work in the TMC – Supervisor, Operator,
Engineer, Technician?4 n/a n/a 8
9) Do they also take care of communication problems, signal 9) Do they also take care of communication problems, signal
timing complaintsYes n/a n/a Yes
10) Hours of Operation – M to F or including weekends Monday to Friday n/a n/a Monday to Friday