Page 1
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 1IDM UID: Q75AVH v1.1
Tokamak Cooling Water Systems (TCWS) Design and Centralized
Procurement for ITER Piping
14:00 / 16:30 : Conference Part 2
Page 2
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 2IDM UID: Q75AVH v1.1
Info Day Agenda10:00 / 13:00 : Conference Part 1
1 - Introduction and general presentation
2 - General presentation of Tokamak Cooling Water Systems
3 - General presentation of other systems in centralized procurement
14:00 / 16:30 : Conference Part 2
4 - Quality Assurance requirements –14:00 / 14:10
5 - TCWS Procurement general strategy / program – 14:10 / 14:40
6 - Focus on Design contracts – 14:40 / 15:00
7 - Focus on Procurement contracts - 15:00/ 15:15
8 - US DA Procurement program - 15:15 / 15:30
9 - Questions / Answers - 15:30 / 16:00
10 - Conclusion – 16:00 / 16:15
16:30 / 17:30 : Site visit
Page 3
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 3IDM UID: Q75AVH v1.1
Info Day Agenda10:00 / 13:00 : Conference Part 1
1 - Introduction and general presentation
2 - General presentation of Tokamak Cooling Water Systems
3 - General presentation of other systems in centralized procurement
14:00 / 16:30 : Conference Part 2
4 - Quality Assurance requirements –14:00 / 14:10
5 - TCWS Procurement general strategy / program – 14:10 / 14:40
6 - Focus on Design contracts – 14:40 / 15:00
7 - Focus on Procurement contracts - 15:00/ 15:15
8 - US DA Procurement program - 15:15 / 15:30
9 - Questions / Answers - 15:30 / 16:00
10 - Conclusion – 16:00 / 16:15
16:30 / 17:30 : Site visit
Page 4
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 4IDM UID: Q75AVH v1.1
Tokamak Cooling Water Systems (TCWS) Design and Centralized
Procurement for ITER Piping
4 – Quality Assurance requirements
Mark Gardner - IO/SQS/QAD Quality Assurance Engineer
Page 5
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 5IDM UID: Q75AVH v1.1
� ITER QA Program
• Quality Plan• Manufacturing and Inspection Plan• Deviations and Non Conformances• Release Notes• Welding Requirements
� Quality Classification Determination
� Specific requirements from ESP and ESPN French regulations
Outlines :
4 - Quality Assurance requirements
Page 6
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 6IDM UID: Q75AVH v1.1
Quality Plan (reference ITER_D_22MFMW)
� Each Supplier or Subcontractor providing equipment or servicesto the ITER Organization must provide a dedicated Quality Plan.
� A Quality Plan covers the whole scope of the contract anddescribes the operational quality system (based on ISO 9001 orequivalent) to ensure that:� Contract requirements will be met� Evidence of such compliance is maintained
� Work shall not start until the relevant Quality Plan has beenaccepted by ITER.
4 - Quality Assurance requirements
Page 7
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 7IDM UID: Q75AVH v1.1
Quality Plan (reference ITER_D_22MFMW)
� The Quality Plan is contract specific and shall identify:
• the specific allocation of resources, duties, responsibilities andauthority;
• details of all suppliers/subcontractors and how interfaces will bemanaged;
• the specific procedures, methods and work instructions to beapplied;
• the specific methods of communication, both formal and informal,to be established between working groups.
� Much of the generic documentation needed to prepare the Quality Planwill normally already exist as part of the Supplier/Subcontractor’squality management system and supporting procedures. The QualityPlan need only refers to this documentation and shows how it is to beapplied to the particular contract.
4 - Quality Assurance requirements
Page 8
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 8IDM UID: Q75AVH v1.1
Manufacturing and Inspection Plan (reference ITER_D_22MDZD)
� Each Supplier and sub-contractor shall supply the DA with a MIPlisting the sequence of manufacturing operations encompassing thewhole scope of the contract (review of drawings, verification ofmaterials, manufacture, inspection and test to delivery…).
� MIP allows supplier, DA and IO to mention control points (NP, HP,WP…).
4 - Quality Assurance requirements
Page 9
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 9IDM UID: Q75AVH v1.1
Manufacturing and Inspection Plan
4 - Quality Assurance requirements
Page 10
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 10IDM UID: Q75AVH v1.1
Deviations and Non Conformances (reference ITER_D_22F53X)
� Deviation: A planned alternative to a specified requirement.
When a deviation to IO specifications is anticipated theSupplier/Contractor shall discuss it with the IO/DA responsible officer asappropriate for that ITER work activity. If the proposal is consideredbeneficial, the Deviation Request shall be sent to IO for approval.
� Non-Conformance: Any condition, which does not comply with a
specified requirement.
When a non-conformance is identified the Supplier/Contractor shall:• Identify, and segregate when practical, the non-conforming item• stop any further work on the item until a decision is made• record and report the occurrence by raising a Non-conformance
Report• Minor Non-conformances are sent to IO for information• Major Non-conformances are sent to IO for approval
4 - Quality Assurance requirements
Page 11
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 11IDM UID: Q75AVH v1.1
Release Notes (reference ITER_D_22F52F)
� The release note must be signed before equipment is deliveredto the ITER site.
� It specifies what equipment/components are being delivered.
� It lists the documents supplied with the equipment.
4 - Quality Assurance requirements
Page 12
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 12IDM UID: Q75AVH v1.1
� Systems, structures and components are classified into one of the fourquality classes and the following shall be noted:
• All SIC-1 systems and component parts shall be Quality Class 1
• SIC-2 systems and component parts can be Quality Class 1 or 2
• Commercial Grade or Proprietary Items that are purchased using a
manufacturer’s catalogue or other commercially available
documentation that have been assessed as Quality Class 1, 2 or 3,
need only be supplied with a manufacturer’s “Certificate of
Conformity”.
• Modified commercial or proprietary items shall conform to ITER
Procurement Quality Requirements (ITER_D_22MFG4) .
Quality Classification Determination
4 - Quality Assurance requirements
Page 13
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 13IDM UID: Q75AVH v1.1
Welding Requirements
� Weld Plan
• Before fabrication can commence the supplier shall prepare for
approval a weld plan.
• The weld plan is a drawing which cross references each welded
joint to a supporting Welding Procedure Specification (WPS).
� Welder and Operator Qualification
• Welder qualification shall be in accordance with EN 287-1, ISO
9606 or equivalent standards agreed in advance. For welding
operators ISO 1418 shall be used.
• Other standards may be approved by ITER on submission of
documentation detailing the equivalence between the proposed
standards and the standards quoted herein.
4 - Quality Assurance requirements
Page 14
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 14IDM UID: Q75AVH v1.1
� Welding Procedure Qualification Record:
• The Welding Procedure Qualification Record (WPQR) is used to
record all the relevant data from the welding of test pieces in WPS
qualification.
• The WPQR is the qualification of the WPS and provides proof that
the defined welding process will achieve a weld of acceptable
quality. The welding and testing of this must be witnessed by an
ITER recognised Independent Inspection Authority.
• All welding data and results from the required non-destructive and
destructive testing shall be documented using a WPQR endorsed
by the witnessing Independent Inspection Authority.
� Inspections• All Quality Class 1 welds will require 100 percent Visual, Surface,
and Volumetric inspections.
Welding Requirements
4 - Quality Assurance requirements
Page 15
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 15IDM UID: Q75AVH v1.1
Info Day Agenda10:00 / 13:00 : Conference Part 1
1 - Introduction and general presentation
2 - General presentation of Tokamak Cooling Water Systems
3 - General presentation of other systems in centralized procurement
14:00 / 16:30 : Conference Part 2
4 - Quality Assurance requirements –14:00 / 14:10
5 - TCWS Procurement general strategy / program – 14:10 / 14:40
6 - Focus on Design contracts – 14:40 / 15:00
7 - Focus on Procurement contracts - 15:00/ 15:15
8 - US DA Procurement program - 15:15 / 15:30
9 - Questions / Answers - 15:30 / 16:00
10 - Conclusion – 16:00 / 16:15
16:30 / 17:30 : Site visit
Page 16
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 16IDM UID: Q75AVH v1.1
Tokamak Cooling Water Systems (TCWS) Design and Centralized
Procurement for ITER Piping
5 – TCWS Procurement general strategy
/ program
Antoine CALMES –IO/ADM/GEA/PCD/IPS – TCWS Procurement Officer
Page 17
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 17IDM UID: Q75AVH v1.1
5 - TCWS&CP Procurement general strategy/program
Outlines :
� 5.1 - IO In-Cash Procurement rules
� 5.2 - TCWS General Contractual Strategy
� 5.3 - TCWS Contractual Strategy for Design
� 5.4 - TCWS Contractual Strategy for Procurement
� 5.5 - Centralized Piping Opportunity for Procurement
� 5.6 - TCWS Contractual Strategy for Notified Body
� 5.7 - TCWS Contracts Mapping and Conflict of Interest
� 5.8 - TCWS and Centralized Piping Contracting Program Overview
Page 18
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 18IDM UID: Q75AVH v1.1
5.1 - IO In-Cash Procurement rules :
� Principles :
• IO recognizes the basic principles of competition, fair andequal treatment of Tenderers
• These principles shall ensure that the IO can obtain the bestvalue for money by soliciting participation of a number ofqualified firms.
� Procurement and Contracts Division (PCD) :
• PCD primary objective and responsibility is to protect the IO’sinterest while procuring supplies, services, and works to meetits organizational requirements.
• PCD in charge of the management of tendering processesand then administrating the contracts
5 - TCWS&CP Procurement general strategy/program
Page 19
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 19IDM UID: Q75AVH v1.1
� Two methods for the award criteria are implemented:
• Lowest-price technically compliant
� The contract is awarded to the tenderer meeting all requirements and offering the lowest price.
� Technical compliancy usually evaluated based on a Compliance Matrix to be filled-in by the Tenderers
• Best value for money
� The contract is awarded to the tender with the best price-quality, taking into account criteria justified by the scope of the contract.
5 - TCWS&CP Procurement general strategy/program
5.1 - IO In-Cash Procurement rules :
Page 20
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 20IDM UID: Q75AVH v1.1
5.1 - IO In-Cash Procurement rules :
� Call for tender process ⇒ A 3 phased process
• Stage 1 - Call for Nomination (minimum 1 month) :
� IO formally invites the DAs to nominate potential suppliers.
• Stage 2 - Pre-Qualification (PQ) (minimum 1.5 months) :
� Ensure that offers are sought only from suppliers who have thefinancial capabilities as well as requested skills, equipmentand experience to perform works or services as described inthe technical summary (and later in the technicalspecifications).
� The PQ form includes :• Questionnaire with Pre-Qualification criteria (pass/ fail)• Technical Summary of the scope • Administrative forms
5 - TCWS&CP Procurement general strategy/program
Page 21
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 21IDM UID: Q75AVH v1.1
5.1 - IO In-Cash Procurement rules :
� Stage 3 - Call for Tender (CFT) (minimum 3 months) :
• The Call for Tender is used to obtain proposals from identified pre-qualified
suppliers.
• Call for Tender content : � Cover letter with the deadline for submission of offers � Annex 1: Instructions To Tenderers
� Annex 2: Technical Specifications (including Quality, Management, etc.)
� Annex 3: Draft Contract
• Instructions To Tenderers content :
� Schedule of the CFT
� Formal forms required to be filled-in (ex. Compliance Matrix)� Tender required content : Technical, Management and Financial parts
� Award method
� Evaluation criteria
5 - TCWS&CP Procurement general strategy/program
IMPORTANT: Clarifications are always possible until a few weeks
before the due date of the offers.
Page 22
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 22IDM UID: Q75AVH v1.1
5.1 - IO In-Cash Procurement rules :
� Evaluation process
• Evaluation Committee is composed of :
� IO Representatives from Technical Directorates and PCD� Experts if needed
All members have declared a non-conflict of interest and confidentiality commitment
• Evaluation principles :
� Confidentiality and fair competition� Two-step approach :
1 –Technical evaluation 2 – Financial evaluation
5 - TCWS&CP Procurement general strategy/program
Page 23
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 23IDM UID: Q75AVH v1.1
5.1 - IO In-Cash Procurement rules :
� Main types of contract (1/2):
• Standard Service or Supply contracts :
� Deliverables-based (versus efforts-based)
� Fixed Price (or Lump-sum) for each Deliverable and/or Work Package
� Possibility to implement Works Instructions process when Work Packages
� Baseline, optional and conditional Work Packages
• Framework Service or Supply contracts :
� A contract that establishes terms and conditions under which subsequent
Task Orders will be placed
� Could be awarded to one or several contractors to enable min-
competition for each Task Order
� A Task Order can be :
• composed of quantities and applicable unit prices • based on IO technical specification and Contractor’s proposal
5 - TCWS&CP Procurement general strategy/program
Page 24
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 24IDM UID: Q75AVH v1.1
5.1 - IO In-Cash Procurement rules :
� Main types of contract (2/2):
• Strategic Agreement (catalogue of products):
� Contractual document signed between the IO and Supplier(s)which sets the terms and conditions under which anyDomestic Agency or their contractors may procure identifiedsupplies
� Concluded and signed by the IO to ensure standardization ofsupplies for the ITER Project
5 - TCWS&CP Procurement general strategy/program
Page 25
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 25IDM UID: Q75AVH v1.1
• IO will handle his responsibilities as:
� Designer for all TCWS scope � Manufacturer for Piping Procurement (with regards to the French
Order Feb.2012)
• Hence the IO will : � Lead the design activities and perform “in-house” part of the
design� Lead and coordinate the manufacturing and pre-assembly
operations
• IO will place Services and Supply contracts as follows:
� 7 Engineering Support Service Contracts for Design� 7 Manufacturing and Pre-Assembly Supply Contracts for Piping
Procurement� 2 Notified Body Services Contracts for Design and
Procurement
5 - TCWS&CP Procurement general strategy/program
5.2 - TCWS General Contractual Strategy
Page 26
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 26IDM UID: Q75AVH v1.1
� Contemplated selection process in most of the cases:
� Call for Tender with Call For Nomination and Pre-Qualification
� Award criteria based on Lowest Price Technically Compliant approach where the Technical Compliancy for each Requirement is to be justified in the Tender.
5 - TCWS&CP Procurement general strategy/program
5.2 - TCWS General Contractual Strategy (cont’)
Page 27
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 27IDM UID: Q75AVH v1.1
5.3 - TCWS Contractual Strategy for Design
No Scope of Work CFT Ref.
TCWS/FD/1Contract for Thermo-Hydraulic Analyses and Calculations for Process and System Engineering of TCWS
IO/14/CFN/9561A/TKA -TCWS/FD/1
PQ under final assessment
TCWS/FD/2Contract for Mechanical Analyses and Calculations of TCWS piping
IO/14/CFN/9561A/TKA -TCWS/FD/1
PQ under final assessment
TCWS/FD/3Contract for Analyses and Calculations for Mechanical Engineering of Equipment Design
Cancelled
TCWS/FD/4 Contract for Feasibility Studies CFN not issued
TCWS/FD/5 Optional : Contract for 2D-3D drawings CFN not issued
TCWS/FD/6 Contract I&C Engineering CFN not issued
TCWS/FD/7Contract for Agreed Notified Body Services during Final Design
Cancelled
TCWS/FD/8 Final Design for TCWS: 1st plasma equipment CFN not issued
TCWS/FD/9 Final Design for TCWS: 2nd plasma equipment CFN not issued
� “Deliverables-based” contracts (versus “effort-based”)
� For most of them, Contract Type will be :
�Contract with Fixed Price Work Packages and Works Instruction, or
�Framework Contracts with “mini-competition” and Tasks Orders.
5 - TCWS&CP Procurement general strategy/program
Page 28
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 28IDM UID: Q75AVH v1.1
� Each Contract will cover the needs of TCWS and potentially other ITER
Systems needs => Centralized Piping Procurement approach – See next slide
� For most of them, Contract Type will be : • Framework Contract or Strategic Agreement with Materials / Works
Catalogue and Unit Prices, with commitment on minimum quantities if possible
No Scope of Work CFT Ref.
TCWS/CP/1 Contract for procurement of piping and fittingsIO/14/CFT/9560/ACS
CFN to be closed by the 20/10/14
TCWS/CP/2 Contract for procurement of commercial supportsCFN not issued
TCWS/CP/3Contract for procurement of manual, motorized, safety and control valves & valve actuators
CFN not issued
TCWS/CP/4 Contract for procurement of instruments CFN not issued
TCWS/CP/5 Contract for procurement of miscellaneous CFN not issued
TCWS/CP/6 Contract for pre-assembly of piping CFN not issued
TCWS/CP/7 Contract for insulation of piping system and equipment CFN not issued
5 - TCWS&CP Procurement general strategy/program
5.4 - TCWS Contractual Strategy for Procurement
Page 29
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 29IDM UID: Q75AVH v1.1
� Specific Provisions : IO aims at making as wider as possible the range of
companies participating to the call for tender processes with regards to the
Contracts to be placed.
• Resulting Provision #1 : Capability versus proven experience in the
nuclear industry
⇒ A proven experience in the nuclear industry will not be required at the
Pre-Qualification stage but a capability to comply with some particular
requirements will be preferred. Also, to justify this capability,
subcontracting strategies will be accepted at the PQ and subcontractors will have to be declared at the CFT stage.
• Resulting Provision #2 : Transcribing French regulations into Requirements
⇒ IO is responsible as “Manufacturer” and will clearly specify in the technical
specifications for the Tenderers the particular technical and quality requirements involved by the application of the French applicable
regulations (French Order Feb 2012, ESP, ESPN)
5 - TCWS&CP Procurement general strategy/program
5.4 TCWS Contractual Strategy for Procurement
Page 30
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 30IDM UID: Q75AVH v1.1
5.5 - Centralized Piping opportunity for Procurement� Approach :
� Seven Framework Contracts will be placed for TCWS needs and are opened for other ITER Systems needs (from IO or DAs)
� Expected benefits for TCWS and other ITER Systems :
� Volume discount and cost savings � Optimizing contract management
� Simplification of final assembly by pre-assembled spools in timely
manner
� Standardization of technical specifications and final piping materials
� Other IO Systems already identified :
� Vacuum
� Atmosphere Detritiation System (ADS)� Part of CCWS and CHWS
� Tentative volume for piping :
TCWS Other PBSs Total Variation
30 45 75 x 2.5Piping needs in km
� Test Blanket Modules (TBM)
� Diagnostic Systems (DS)� Type A Radwaste System
5 - TCWS&CP Procurement general strategy/program
Page 31
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 31IDM UID: Q75AVH v1.1
� Regulatory requirement to have two separate contracts, but could be awarded to one single Contractor
� Each Contract will cover the needs of TCWS and potentially ITER Systems needs with regards to the Centralized Piping Procurement approach
� For these two contracts : �Contract Type should be Framework Contract with Tasks Orders. �Selection process should be Restricted Solicitation to companies
agreed Notified Body by ASN (French Nuclear Safety Authority)
No Scope of Work
TCWS/NB/1 Contract for Technical assistance in the field of Pressure Equipment and Nuclear Pressure Equipment.
TCWS/NB/2Contract for mission of Notified Body and Agreed Notified Body for the manufacture of several Pressure and Nuclear Pressure Equipment
5 - TCWS&CP Procurement general strategy/program
5.6 - TCWS Contractual Strategy for Notified Body
Page 32
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 32IDM UID: Q75AVH v1.1
No Scope of Work
TCWS/CP/1Contract for procurement of piping and
fittings
TCWS/CP/2Contract for procurement of commercial
supports
TCWS/CP/3
Contract for procurement of manual,
motorized, safety and control valves &
valve actuators
TCWS/CP/4 Contract for procurement of instruments
TCWS/CP/5Contract for procurement of
miscellaneous
TCWS/CP/6 Contract for pre-assembly of piping
TCWS/CP/7Contract for insulation of piping system
and equipment
TCWS Final Design Centralized Procurement and Pre-
Assembly of Pipes
NO
NO
Conflict of
interest with CP
YES
TCWS/NB/2
Contract for mission of Notified Body and Agreed Notified
Body for the manufacture of several Pressure and Nuclear
Pressure Equipment
NO
Nota : � No conflict of interest between CP contracts stated in CP/1 CFN (issued)� No conflict of interest between FD contracts stated in FD/1 and 2 CFN
(issued)
No Scope of Work
TCWS/FD/1
Contract for Thermo-Hydraulic Analyses and
Calculations for Process and System
Engineering of TCWS
TCWS/FD/2Contract for Mechanical Analyses and
Calculations of TCWS piping
TCWS/FD/3Contract for Analyses and Calculations for
Mechanical Engineering of Equipment Design
TCWS/FD/4 Contract for Feasibility Studies
TCWS/FD/6 Contract I&C Engineering
TCWS/FD/7Contract for Agreed Notified Body Services during
Final Design
TCWS/FD/8 Final Design for TCWS: 1st plasma equipment
TCWS/FD/9 Final Design for TCWS: 2nd plasma equipment
YES
YES*
YES*
TCWS/FD/5 Optional : Contract for 2D-3D drawings
TCWS/NB/1Contract for Technical assistance in the field of Pressure
Equipment and Nuclear Pressure Equipment.
5.7 - TCWS Contracts Mapping and Conflict of Interest
YES* Conflict with only one CP/X contract
[FD/4 with CP/6 and FD/6 with CP/4]
TCWS Notified Body
NO
5 - TCWS&CP Procurement general strategy/program
Page 33
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 33IDM UID: Q75AVH v1.1
5.7 - TCWS Contracts mapping and Conflict of Interest
5 - TCWS&CP Procurement general strategy/program
� In summary:
• No conflict between:
� Design Contracts
� Procurement Contracts
� Notified Body Contracts
� FD/1, FD/5, FD/8, FD/9 and Procurement Contracts
• Conflict between :
� FD/2 (Piping mechanical analysis) and all Procurement Contracts
� FD/4 (Feasibility studies) and CP/6 (Piping pre-assembly)
� FD/6 (I&C engineering) and CP/4 (Instruments procurement)
� Notified Body Contracts and all Procurement Contracts
Page 34
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 34IDM UID: Q75AVH v1.1
5 - TCWS&CP Procurement general strategy/program
5.8 - TCWS & Centralized Piping Contracting Program
� Design contracts
S1 S2 S1 S2 S1 S2
CFT
CFT
CFT
CFT
CFT
CFT
2014 2015 2016
CFT
TCWS/FD/4
Thermo-Hydraulic Analyses and
Calculations for Process and System
Engineering of TCWS
Mechanical Analyses and Calculations
of TCWS piping TCWS/FD/2
No Scope of Work
Feasibility Studies
TCWS/FD/6
Optional 2D-3D drawingsTCWS/FD/5
TCWS/FD/1
I&C Engineering
TCWS/FD/9
TCWS/FD/8
Final Design for TCWS: 2nd
plasma
equipment
Final Design for TCWS: 1st plasma
equipment
Page 35
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 35IDM UID: Q75AVH v1.1
5 - TCWS&CP Procurement general strategy/program
� Procurement contracts
5.8 - TCWS & Centralized Piping Contracting Program
S1 S2 S1 S2 S1 S2
CFT
CFT
CFT
CFT
CFT
CFT
2014 2015 2016
CFT
Contract for insulation of piping
system and equipment TCWS/CP/7
TCWS/CP/5
TCWS/CP/6
Contract for procurement of manual,
motorized, safety and control valves &
valve actuators
TCWS/CP/3
Contract for procurement of
instrumentsTCWS/CP/4
No Scope of Work
Contract for procurement of
commercial supports
Contract for procurement of
miscellaneous
Pre-assembly of TCWS piping
TCWS/CP/2
Contract for procurement of piping and
fittingsTCWS/CP/1
Page 36
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 36IDM UID: Q75AVH v1.1
5 - TCWS&CP Procurement general strategy/program
� ANB contracts
5.8 - TCWS & Centralized Piping Contracting Program
S1 S2 S1 S2 S1 S2
CFTTCWS/NB/2
Contract for mission of Notified Body
and Agreed Notified Body for the
manufacture of several Pressure and
Nuclear Pressure Equipment
CFT
No Scope of Work2014 2015 2016
TCWS/NB/1
Contract for Agreed Notified Body
services during procurement and
construction
Page 37
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 37IDM UID: Q75AVH v1.1
Info Day Agenda10:00 / 13:00 : Conference Part 1
1 - Introduction and general presentation
2 - General presentation of Tokamak Cooling Water Systems
3 - General presentation of other systems in centralized procurement
14:00 / 16:30 : Conference Part 2
4 - Quality Assurance requirements –14:00 / 14:10
5 - TCWS Procurement general strategy / program – 14:10 / 14:40
6 - Focus on Design contracts – 14:40 / 15:00
7 - Focus on Procurement contracts - 15:00/ 15:15
8 - US DA Procurement program - 15:15 / 15:30
9 - Questions / Answers - 15:30 / 16:00
10 - Conclusion – 16:00 / 16:15
16:30 / 17:30 : Site visit
Page 38
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 38IDM UID: Q75AVH v1.1
Tokamak Cooling Water Systems (TCWS) Design and Centralized
Procurement for ITER Piping
6 – Focus on Design contracts
Prashant SINGH –IO/DIP/PSE/PED – TCWS Project Engineer
Page 39
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 39IDM UID: Q75AVH v1.1
6 – Focus on Design contracts FD/1 : Contract for Thermo-Hydraulic Analyses and Calculations for Process and System Engineering of TCWS
Subject : Thermo-Hydraulic Analyses and Calculations for Process and System Engineering of TCWS
Main tasks / activities :
� Task 1: Thermo-hydraulic steady state analyses
� Task 2 : Thermo-hydraulic transient analyses
� Task 3 : Components sizing calculations
� Task 4 : Water Hammer analyses
� Task 5 : Design of overpressure protection systems
� Task 6 : Listing needed modifications to PFD and P&IDs
Particular skills:
� Experience in thermal-hydraulic design of nuclear systems or complex processing plants cooled by pressurised water.
� Computational analyses performed with Fathom and Arrow (or similar codes) for steady state analyses and Relap5 code for transient analyses. Experience in water hammer analyses.
� Experience in the design of overpressure protection systems.
� Knowledge of the requirements included in ESP/ESPN regulations.
Contract type : Fixed Prices Contract with Work Packages or Framework Contract
Duration forecast : 3 years
Key sizing figures :
� Thermo-hydraulic analyses and components sizing (Task1-2-3) for 5 TCWS sub-systems (excluding IBED and VV PHTS).
� Water hammer analyses and over pressure protection system design for 7 TCWS sub-systems (including IBED and VV PHTS).
� 115 reports to be produced.
Conflict : No
Page 40
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 40IDM UID: Q75AVH v1.1
6 – Focus on Design contracts FD/2 : Contract for Mechanical Analyses and Calculations of TCWS piping
Subject : Mechanical Analyses and Calculations of TCWS piping
Main tasks / activities :
� Static and Dynamic stress analysis for Nuclear and Non – Nuclear class piping
� Postulation of Double End Guillotine Breaks for High Energy Lines, analysis of consequences and implementation of mitigating measures to cope with jet and whipping effect
� Detailed Design of Pipes and component supports and structures
� Thermal stratification studies and thermal fatigue analyses
Particular skills:
� Strong experience in the thermo mechanical analyses of nuclear piping
� Good knowledge of ASME B31.3 code and additional requirements of ESPN regulation
� Good knowledge of the Double End Guillotine Break problem and the associated effects
� Strong capacity to design a large amount of nuclear qualified supports and associated reports and drawings within a tight schedule
� Knowledge of Nuclear supports design codes, in particular AISC N690 / ASME III NF
� Proven capability to analyze the thermal stratification problem in piping systems
Contract type : Fixed Prices Contract with Work Packages or Framework Contract
Duration forecast : 3 years
Key sizing figures :
� 3400 process lines grouped in 150 Engineering Problems for Stress analyses
� 6500 individual supports to be designed and 6500 drawings to be produced
� 1200 potential rupture DEGB locations
� 3 pressurizer lines and potentially several more lines to be address for thermal fatigue
� 100 Reports to be produced, 300 Deliverables (including software files) ;30 Work Packages
Conflict : With all Piping Procurement Contracts
Page 41
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 41IDM UID: Q75AVH v1.1
6 – Focus on Design contracts
FD/4 : Contract for Feasibility Studies
Subject : Feasibility Studies
Main tasks / activities :
� General assessment of the present TCWS design solutions namely for the piping supporting systems and penetrations
� Study of design solutions for TCWS piping modularity and relevant prefabrication and assembly sequences
� Detailed Engineering analysis of the feasibility of the complex piping modules/skids in term of weldability, inspectability and maintenability
� Assessment of specific fabrication processes for double wall pipes’ spools
� FMECA analysis relevant to specific welded piping modules
Particular skills:
� Good knowledge of Nuclear piping manufacturing procedures
� Proven experience in prefabrication and modularization of Nuclear piping
� Extensive knowledge of Welding and NDE techniques
� Experience in FMECA analyses
Contract type : Fixed Prices Contract with Work Packages or Framework Contract
Duration forecast : 7-9 months
Key sizing figures :
� 7 different types of penetration configuration (In total 188 grouped penetrations)
� 43 potential pipe modules to be analyzed
� Approximately 1000 meters of double wall pipes
� 3500 Process lines
Conflict : With CP/6 pre-assembly of TCWS piping
Page 42
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 42IDM UID: Q75AVH v1.1
6 – Focus on Design contracts
FD/5 : Contract for 2D-3D drawings
Subject : Preparation of 2D Drawings – 3D models
Main tasks / activities :
� Convert Catia ® models to AVEVA PDMS ® models and vice versa
� Generation of Piping lay outs and GA drawings
� Generation of isometric drawings for piping construction
� Preparation of 3D models files for other contractors
Particular skills: � CAD – 2D/3D drawings
Contract type : Fixed Prices Contract with Work Packages or Framework Contract
Duration forecast : 6 -9 months
Key sizing figures :
� 3400 isometrics
� 150 3D models
� Approximately 150 – 200 2D Drawings
Conflict : No
OPTIONAL AS PER FUTURE IO NEEDS
Page 43
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 43IDM UID: Q75AVH v1.1
6 – Focus on Design contracts
FD/6 : Contract I&C Engineering
Subject : Instrumentation, Control & Electrical contract for Tokamak Cooling Water System of ITER
Main tasks / activities :
� Instrumentation engineering documents including function analysis, control logic, Instrument list, Instrument specification, etc…
� I&C architectural documents, Controllers configuration, Control Network configuration and so on
� Instrumentation installation drawings of control system to including instrument hook-up drawing,
Instrument loop drawings, cabling (electrical & Pneumatic) diagrams, and cubicle fabrication drawings
� Interface engineering for Instrument and Electrical systems
� Control Software Philosophy
� Electrical power engineering documents including load list revisions, single-line diagrams, power distribution equipment lists and specifications, etc….
� Electrical power distribution installation drawings including cable specification and diagrams, motor control centre (MCC/VFD) fabrication drawings, etc….
Particular skills: Instrumentation engineering for industrial plants, preferably water treatment systems or chemical plants. Experience in instrumentation installed in ionizing radiation and magnetic field, nuclear domain will be an added advantage
Contract type : Fixed Prices Contract with Work Packages or Framework Contract
Duration forecast : 1 – 1,5 year
Key sizing figures :
� > 3000 components
� > 10.000 Inputs/outputs
� > 50 MW
Conflict : With CP/4 : Contract for procurement of instruments
Page 44
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 44IDM UID: Q75AVH v1.1
6 – Focus on Design contracts
FD/8 : Final Design for TCWS: 1st plasma equipment
Subject : Final Design for TCWS: 1st plasma equipment
Main tasks / activities :
� Perform equipment associated calculations to support USDA and IO in the preparation of the component detailed design (Pressure Vessels, Heat Exchangers, Filters, Cyclones, Heaters, etc)
� Providing support to the USDA and IO during the preparation of the system’s 1st Plasma main component Technical Specification
� Providing expert support to the USDA and IO during the elaboration of the system’s 1st Plasma main components data sheets
� Providing support to the USDA and IO during the selection of 1st Plasma component supplier by giving expert advice on relevant technical issues
Particular skills: Systems engineering
Contract type : Framework Contract
Duration forecast : 9-11 months
Key sizing figures :
� 3 Compressors and 11 pumps
� 10 Heat exchangers and 4 electrical heaters
� 6 Pressure vessels and 3 separators
� 4 cartridge filters
Conflict : Potential conflict with the contracts for Supply of components under USDA scope
Page 45
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 45IDM UID: Q75AVH v1.1
6 – Focus on Design contracts
FD/9 : Final Design for TCWS: 2nd plasma equipment
Subject : Final Design for TCWS: D - T plasma phase equipment
Main tasks / activities :
� Perform equipment associated calculations to support USDA and IO in the preparation of the component detailed design (Pressure Vessels, Heat Exchangers, Filters, Cyclones, Heaters, etc)
� Providing support to the USDA and IO during the preparation of the system’s D -T phase main component Technical Specification
� Providing expert support to the USDA and IO during the elaboration of the system’s D -T phase main components data sheets
� Providing support to the USDA and IO during the selection of D -T phase component supplier by giving expert advice on relevant technical issues
Particular skills: Systems engineering
Contract type : Framework Contract
Duration forecast : 10-12 months
Key sizing figures :
� 20 pumps.
� 22 Heat exchangers and 3 electrical heaters.
� 17 Pressure vessels
� 14 cartridge filters and 4 mixed bed filters
Conflict : Potential conflict with the contracts for Supply of components under USDA scope
Page 46
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 46IDM UID: Q75AVH v1.1
Info Day Agenda10:00 / 13:00 : Conference Part 1
1 - Introduction and general presentation
2 - General presentation of Tokamak Cooling Water Systems
3 - General presentation of other systems in centralized procurement
14:00 / 16:30 : Conference Part 2
4 - Quality Assurance requirements –14:00 / 14:10
5 - TCWS Procurement general strategy / program – 14:10 / 14:40
6 - Focus on Design contracts – 14:40 / 15:00
7 - Focus on Procurement contracts - 15:00/ 15:15
8 - US DA Procurement program - 15:15 / 15:30
9 - Questions / Answers - 15:30 / 16:00
10 - Conclusion – 16:00 / 16:15
16:30 / 17:30 : Site visit
Page 47
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 47IDM UID: Q75AVH v1.1
Tokamak Cooling Water Systems (TCWS) Design and Centralized
Procurement for ITER Piping
7 – Focus on Procurement contracts
Moustafa MOTELEB –IO/DIP/PSE/PED – TCWS Project Manager
Page 48
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 48IDM UID: Q75AVH v1.1
7 – Focus on Procurement contracts
CP/1 : Contract for Procurement of Piping and Fittings
Subject : Manufacturing and procurement of Piping and Fittings for TCWS and other systems of ITER machine
Materials:
� Seamless Stainless Pipes
� Welded Stainless Pipes
� Welded Carbon Pipes
� Seamless and welded austenitic stainless steel butt welding fittings
� Austenitic stainless steel integrally reinforced forged branch outlet fittings
Particular Requirements : Applicable standards: ASTM for all, ESP and ESPN partially
Contract Type : Framework Contract or Strategic Agreement with Materials / Works Catalogue and Unit Prices
Duration forecast : 5 years
Key Sizing Figures :
� Stainless pipes : 60 ≤ X ≤ 100 km
� Carbon Pipe : X ≤ 5 km
� Fittings : 30 000 +/- 20% units
� Size (DN): 15 to 500
Page 49
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 49IDM UID: Q75AVH v1.1
7 – Focus on Procurement contracts
CP/1 : Contract for Procurement of Piping and Fittings
� Selection process progress status :
• CFN extended until October 20th following clarification sent to the DAs on the 29.09
• PQ should be launched by the end of October - CFT should be launched by December
� Pre-Qualification criteria will be based on the following approach :
• Proven experience in :
� manufacturing or procuring Seamless Stainless Pipes in conformity with ASTM A312 standard
• Capacity in :
� manufacturing or procuring other materials (Welded Stainless Pipes, Stainless Fittings, ….)
in compliance with relevant ASTM standards
� manufacturing or procuring Pipes and Fittings in compliance with some particular technical
requirements on chemical composition and mechanical properties (mainly involved by ESP/ESPN)
� Quality Assurance Management in compliance with particular quality requirements (mainly
involved by IO Quality System, ESP/ESP and French Order Feb. 2012)
� Supply Chain Management on large equipment manufacturing and procurement contracts
⇒ The demonstration can be based on subcontracting strategy. In such case, name(s) and capabilities of identified subcontractor(s) are required.
Page 50
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 50IDM UID: Q75AVH v1.1
7 – Focus on Procurement contracts
Subject : Commercial off the shelf (COTS) pipe supports
Materials:
� Springs (Variable, Constant, and Angulating)
� Rigid Sway Strut
� Snubbers (Hydraulic and Mechanical)
� Energy Absorber
� Pipe Clamp (Restraint, Dynamic, Two bolt, Three bolt)
� Riser Clamp
� Pipe Saddle
� Insulated Pipe Shoes
� Pipe Slides
� Pipe Whip Restraint
� Hanger Rod
� Turnbuckle
� U-Bolt
Particular requirements :� Applicable design standards: ASME B31.3 and MSS-SP-58
� Nuclear Qualification documentation and Design Record Sheets required
Contract type : Framework Contract or Strategic Agreement with Materials / Works Catalogue and Unit Prices
Duration forecast : 4 years
Key sizing figures :
� Size (DN): 15 to 500
� Carbon Steel supports: approx. 5900 Supporting units
� Stainless steel supports: approx. 530 Supporting units
CP/2 : Contract for procurement of commercial supports
Page 51
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 51IDM UID: Q75AVH v1.1
7 – Focus on Procurement contracts
Subject : Manual, motorized, safety and control valves & valve actuators
Materials:
� Manual valves with ratings ranging from 150# to 900 #
� Pneumatic Actuators and Electric Motor including required accessories, spare parts and documentation to the IO
� Control valves including required accessories, spare parts and documentation to the IO
� Pilot operated relief valves and Spring operated relief valves
Particular requirements :
� Applicable Standards: ASME B16.34 (Valve Body), ASTM for all, ESP and ESPN partially, Machinery Directive (Control Valves and Actuators), and EMC Directive (Control Valves and Actuators)
� Seismic qualification required for most of the valves
� Most valves with rigorous leak tightness requirements
� Some valves with particularly low seat leakage requirements
Contract type : Framework Contract or Strategic Agreement with Materials / Works Catalogue and Unit Prices
Duration forecast : 4 years
Key sizing figures :
� Valve Size (DN): 15 to 500
� Approximately 2700 valves (Manual, operated), 100 Relief Valves, 100 Control Valves, 2200 actuators (Pneumatic and Motor operated)
CP/3 : Contract for procurement of manual, motorized, safety and control valves & valve actuators
Page 52
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 52IDM UID: Q75AVH v1.1
7 – Focus on Procurement contracts
Subject : Piping instruments
Materials:
� Instrumentation relative to standard process variables (transmitters, indicators switches): Pressure / Temperature / Level / Flow
� Water analysis and monitoring : pH / Dissolved Oxygen / Dew point / Hydrogen sensors
� Radiation monitoring
� Signal/command processing : Signal conditioners /Pre-actuator (solenoid valves) / IO Remote Device
� Valves accessories : Positioners (modulating valves) /Position Switches
Particular requirements : Technical Specifications pending Final Design
Contract type : Framework Contract or Strategic Agreement with Materials / Works Catalogue and Unit Prices
Duration forecast : 4 years
Key sizing figures : TBD pending Final Design
CP/4 : Contract for procurement of instruments
Page 53
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 53IDM UID: Q75AVH v1.1
7 – Focus on Procurement contracts
Subject : Various Piping materials
Materials:
� Orifices
� Bellows
� Flanges
� Feed-throughs (for piping)
Particular requirements :
� For orifices and bellows a proper customization is needed to meet the TCWS needs and is described in the technical specification
� Applicable Standards: ASME B16.36 (Orifice Flange), ASME B31.3 (Bellows), ASME B16.5 (Flanges), and ASME B16.47 (Flanges)
Contract type : Framework Contract or Strategic Agreement with Materials / Works Catalogue and Unit Prices
Duration forecast : 4 years
Key sizing figures :
� Size (DN): 15 to 500
� Approximately 120 cylindrical bellows and 18 big oblong bellows
� 400 orifice plates
� 300 flanges
CP/5 : Contract for procurement of miscellaneous
Page 54
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 54IDM UID: Q75AVH v1.1
7 – Focus on Procurement contracts
Subject : Pre-assembly and pre-testing of piping spools
Technical works : � Pre-fabrication and pre-testing of TCWS piping spools and skids
(Modular Units)
Particular requirements :
� Proximity of workshop to ITER site
� Capacity to manufacture modular skids weighing up to 20 tons
� Previous experience
� Financial capacity
� Bonding capacity
Contract type : Framework Contract or Strategic Agreement with Materials / Works Catalogue and Unit Prices
Duration forecast : 4 years
Key sizing figures : Size (DN): 15 to 500
CP/6 : Construction of TCWS piping
Page 55
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 55IDM UID: Q75AVH v1.1
7 – Focus on Procurement contracts
Subject : Insulation of piping system and equipment
Technical works : � Mineral wool (outside Cryostat) .
� Microtherm Super G or similar super-insulation (inside Cryostat)
Particular requirements :
� Lifetime: 20 years minimum (without maintenance)
� Chemical composition : - No halogens - S and F (%weight) = 0.025% maximum of each
Contract type : Framework Contract or Strategic Agreement with Materials / Works Catalogue and Unit Prices
Duration forecast : 3 years
Key sizing figures : Size (DN): 15 to 500
CP/7 : Contract for insulation of piping system and equipment
Page 56
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 56IDM UID: Q75AVH v1.1
Info Day Agenda10:00 / 13:00 : Conference Part 1
1 - Introduction and general presentation
2 - General presentation of Tokamak Cooling Water Systems
3 - General presentation of other systems in centralized procurement
14:00 / 16:30 : Conference Part 2
4 - Quality Assurance requirements –14:00 / 14:10
5 - TCWS Procurement general strategy / program – 14:10 / 14:40
6 - Focus on Design contracts – 14:40 / 15:00
7 - Focus on Procurement contracts - 15:00/ 15:15
8 - US DA Procurement program - 15:15 / 15:30
9 - Questions / Answers - 15:30 / 16:00
10 - Conclusion – 16:00 / 16:15
16:30 / 17:30 : Site visit
Page 57
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 57IDM UID: Q75AVH v1.1
Tokamak Cooling Water Systems (TCWS) Design and Centralized
Procurement for ITER Piping
8 - US DA Procurement program
Kirby Wilcher, TCWS Engineer, US ITER
Page 58
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 58IDM UID: Q75AVH v1.1
Subject : Total TCWS Procurement Scope is shared between ITER IO (France) and US ITER (USA) US ITER Procurement originating from organization in USA:
• Pumps • Demineralizers • Compressors• Heat Exchangers • Dryers • Associated Electrical and I&C items• Tanks & Vessels • Filters
• Pressurizers • Degasifiers
8 - US DA Procurement Program
Page 59
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 59IDM UID: Q75AVH v1.1
Subject : Manufacturing and Procurement of Rotating Equipment for
TCWS
Equipment:
� Main Cooling Water Pumps
� Transfer Pumps
� Chemical Injection Pumps & Skids
� Nitrogen Charging Compressor
� Drying Primary Compressor
Particular
Requirements :Applicable standards: Machinery Directive, API, ASME
Contract Type : Individual Fixed Unit Prices
Schedule : Contract Launch: 1st Procurement Cycle beginning 2016
Contract Duration: TBD for 1st and 2nd Procurement Cycles
Key Sizing Figures :
Quantity: Over (30) Major Equipment Tag Numbers
Stainless pumps: Size (DN): 60 to 500
Ranging from Small Transfer Pumps to
6 MW Main Pumps with flow rate: 1.2 m3/s (over 1,000 kg/s),
3.77 MPa Head
8 - US DA Procurement Program
Page 60
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 60IDM UID: Q75AVH v1.1
Subject : Manufacturing and Procurement of Passive Equipment for TCWS
Equipment:
� Pressurizers
� Pressure Relief Tanks� Main Cooling Water Heat Exchangers� Decay Heat Exchanger
� Volume Control, Letdown and Regenerative Heat Exchangers
� Auxiliary & Waste Drain Tank, Volume Control Tanks
� Demineralizers, Condensers
� Filters, Degasifiers, and Moisture SeparatorsParticular Requirements :
Applicable standards: ESPN, PED, ASME
Contract Type : Individual Fixed Unit Prices
Schedule : Contract Launch: 1st Procurement Cycle beginning 2016
Contract Duration: TBD for 1st and 2nd Procurement Cycles
Key Sizing Figures : Quantity: Approximately (100) Major Equipment Tag Numbers Stainless steel pressure vessels: volume ranges from low
volume filter housings, to pressurizer over 50 cubic meter
Page 60
8 - US DA Procurement Program
Page 61
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 61IDM UID: Q75AVH v1.1
TCWS Procurement Schedule: Captive Piping / 1st Plasma Equipment
8 - US DA Procurement Program
Page 62
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 62IDM UID: Q75AVH v1.1
TCWS Procurement Schedule: 2nd Plasma Equipment
8 - US DA Procurement Program
Page 63
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 63IDM UID: Q75AVH v1.1
Subject : Point of Contacts (POC) for Manufacturing and Procurement of
Equipment for TCWS
CAMs: May be contacted now for participation in budgetary engineering
cost estimates.
� Fabrication Manager: Jay Brizendine [email protected](all items)
� Draining: Juan Ferrada [email protected]
� VV PHTS: Andrei Petrov [email protected]
� Drying: Juan Ferrada [email protected]
� CVCS: Andrei Petrov [email protected]
� IBED PHTS: Kirby Wilcher [email protected]
� NBI PHTS: Andrei Petrov [email protected]
Page 63
8 - US DA Procurement Program
Page 64
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 64IDM UID: Q75AVH v1.1
Info Day Agenda10:00 / 13:00 : Conference Part 1
1 - Introduction and general presentation
2 - General presentation of Tokamak Cooling Water Systems
3 - General presentation of other systems in centralized procurement
14:00 / 16:30 : Conference Part 2
4 - Quality Assurance requirements –14:00 / 14:10
5 - TCWS Procurement general strategy / program – 14:10 / 14:40
6 - Focus on Design contracts – 14:40 / 15:00
7 - Focus on Procurement contracts - 15:00/ 15:15
8 - US DA Procurement program - 15:15 / 15:30
9 - Questions / Answers - 15:30 / 16:00
10 - Conclusion – 16:00 / 16:15
16:30 / 17:30 : Site visit
Page 65
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 65IDM UID: Q75AVH v1.1
Tokamak Cooling Water Systems (TCWS) Design and Centralized
Procurement for ITER Piping
9 – Questions / Answers
Page 66
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 66IDM UID: Q75AVH v1.1
9 - Questions / Answers
Page 67
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 67IDM UID: Q75AVH v1.1
Info Day Agenda10:00 / 13:00 : Conference Part 1
1 - Introduction and general presentation
2 - General presentation of Tokamak Cooling Water Systems
3 - General presentation of other systems in centralized procurement
14:00 / 16:30 : Conference Part 2
4 - Quality Assurance requirements –14:00 / 14:10
5 - TCWS Procurement general strategy / program – 14:10 / 14:40
6 - Focus on Design contracts – 14:40 / 15:00
7 - Focus on Procurement contracts - 15:00/ 15:15
8 - US DA Procurement program - 15:15 / 15:30
9 - Questions / Answers - 15:30 / 16:00
10 - Conclusion – 16:00 / 16:15
16:30 / 17:30 : Site visit
Page 68
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 68IDM UID: Q75AVH v1.1
Tokamak Cooling Water Systems
(TCWS) Design and Centralized Procurement for ITER Piping
10 – Conclusion
Sergio ORLANDI – IO/DIP/Director of Directorate for Plant System Engineering (PSE) and Chief Executive Engineer
Page 69
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 69IDM UID: Q75AVH v1.1
� IO is looking for suppliers or consortia who can
comply with Tokamak Cooling Water Systems
(TCWS) Design and Centralized Procurement for
ITER Piping specifications, including:
• Technical requirements,
• Schedule requirements,
• Quality/Safety requirements,
• Conflict of interest/unfair technical advantage requirements.
10 – Conclusion
Page 70
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 70IDM UID: Q75AVH v1.1
� Successful Tenderers will demonstrate:
10 – Conclusion
• A thorough understanding of what is being asked
• A well-thought out technical solution
• A high degree of confidence that the requirements will be met
• A high level of professionalism in QA matters
• An adequate level of resources to achieve on time
• A reasonable/competitive price
Page 71
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 71IDM UID: Q75AVH v1.1
� ITER Organization is looking for a collaborative
approach in the forthcoming contracts:
• IO needs to work with “Suppliers” or “Performers” who will
take responsibility in the contract execution with a shared
approach with the IO, of the identified risks;
• IO is determined to use “Suppliers” or “Performers” who
have the capacity to identify in advance difficulties or
uncertainties in order to smoothly address them in a
collaborative manner.
10 – Conclusion
Page 72
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 72IDM UID: Q75AVH v1.1
Industry Feedback
� All attendees are kindly invited:
• to fill-in the Questionnaire available from today onthe ITER PCD web portal :
http://www.iter.org/org/team/adm/proc/overview
• to send it back to the following e-mail address no laterthan October 21st 2014, at :
10 – Conclusion
� Read more on the IO Procurement Web Site:
http://www.iter.org/org/team/adm/proc/generalinfo
� TCWS Procurement officer :
Page 73
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 73IDM UID: Q75AVH v1.1
Page 74
TCWS Design and Centralized procurement for ITER Piping Information Day
ITER Headquarters, October 7th 2014
© 2014, ITER Organization
Page 74IDM UID: Q75AVH v1.1
Tokamak Cooling Water Systems
(TCWS) Design and Centralized Procurement for ITER Piping
Site Visit
16:30 – 17:30