the spanish electricity system. preliminary report 2018 · 2019-03-04 · the spanish electricity...
TRANSCRIPT
The Spanish Electricity System
P R E L I M I N A R Y R E P O R T
2018
C O M M I T T E D
I N T E L L I G E N T
E N E R G Y
T O
1 2 3 4
Page 4
ELECTRICITYBALANCE,INSTALLEDPOWERCAPACITY AND TRANSMISSIONGRID
Page 10 Page 24
PENINSULARSYSTEM
NON-PENINSULARSYSTEMS
Page 32
GLOSSARY OF TERMS
This preliminary report presents the provisional statistical data regarding the behaviour of the Spanish electricity system during 2018. Information prepared using data as at 16 January 2019.
C O N T E N T S
T A B L E
O F
1E L E C T R I C I T Y
B A L A N C E
I N S T A L L E D
P O W E R
C A P A C I T Y
A N D
T R A N S M I S S I O N
G R I D
E l e c t r i c i t y d e m a n d i n S p a i n i n 2 0 1 8 g r e w f o r t h e f o u r t h c o n s e c u t i v e y e a r , a l t h o u g h s h o w i n g a l o w e r g r o w t h r a t e t h a n t h a t r e g i s t e r e d i n t h e p r e v i o u s y e a r .
5
2 6 8 , 8 0 8 G W h
N AT I O N A L D E M A N D
2 0 1 8
+ 0 . 4 %C O M PA R E D T O
2 0 17
Electricity balance, installed power capacity and transmission grid 6
Electricity demand by autonomous communities and its variation with respect to the previous year
(GWh and %)
ANDALUSIA0.2 %
40,237 GWh
EXTREMADURA0.6 %
5,055 GWh
MURCIA2.5 %
9,613 GWh
COMMUNITY OF VALENCIA
2.0 %27,500 GWh
MADRID0.1 %
28,624 GWh
CASTILLA - LA MANCHA
0.3 %11,748 GWh
CASTILLA Y LEÓN1.5 %
14,288 GWh
GALICIA0.1 %
19,913 GWh
ASTURIAS0.4 %
10,639 GWh
CANTABRIA-2.2 %
4,275 GWh
BASQUE COUNTRY
1.1 %16,711 GWh
ARAGÓN 0.6 %
10,731 GWh
CATALONIA-1.0 %
47,323 GWh
BALEARIC ISLANDS
0.6 %6,052 GWh
MELILLA1.2 %
213 GWh
≤-1%
>-1 % a ≤0.2 %
>0.2 % a ≤1.3 %
>1.3%
LA RIOJA0.5 %
1,713 GWh
NAVARRA1.4 %
5,126 GWh
CANARY ISLANDS
-1.0 %8,840 GWh
CEUTA2.2 %
207 GWh
Demand for electricity in Spain has consolidated its positive trend begun in 2015, after registering falls in previous years due to the economic crisis. Specifi cally, demand in 2018 reached 268,808 GWh, 0.4% up on
the previous year.On the other hand, generation registered a fall of 0.5% with respect to 2017, affecting mainly coal-fi red and combined-cycle generating stations, whose production
decreased by 17.2% and 18.9% respectively. In terms of international exchanges, imports exceeded exports by 11,102 GWh.
7The Spanish Electricity System l Preliminary Report 2018
Installed Power Capacity by Autonomous Communities (MW)
ANDALUSIA15,485 MW
EXTREMADURA5,762 MW
MURCIA4,368 MW
COMMUNITY OF VALENCIA
8,224 MW
MADRID458 MW
CASTILLA - LA MANCHA8,204 MW
CASTILLA Y LEÓN
13,586 MW
GALICIA10,988 MW
ASTURIAS4,512 MW
CANTABRIA815 MW BASQUE
COUNTRY2,905 MW
ARAGÓN 7,183 MW
CATALONIA11,873 MW
BALEARIC ISLANDS
2,285 MW
MELILLA78 MW
≤1,000
> 1,000 a ≤ 4,000
> 10,000
LA RIOJA1,398 MW
NAVARRA2,832 MW
CANARY ISLANDS
3,006 MW
CEUTA91 MW
> 4,000 a ≤ 10,000
In 2018, installed power capacity in the complete set of generating facilities in Spain fell for the third consecutive year, ending the year with 104,053 MW, 0.1% less than the previous year, mainly due to the defi nitive
closure of the Tarragona Combined Cycle Power Station.Wind power has increased by 1.5%. The rest of the electricity generation technologies showed minimal or insignifi cant variations.
According to provisional data, the development of the electricity transmission grid in Spain during 2018 registered an increase of 277 km of new circuit and 2,592 MVA of new transformer capacity that bolsters the reliability
Electricity balance, installed power capacity and transmission grid 8
25,000
20,000
15,000
10,000
5,000
0
2014 2015 2016 2017 2018(1)
Evolution of the electricity transmission grid in Spain (km de circuito)
Provisional data pending audit (currently in progress). (1) Cumulative figures regarding kilometres of circuit as at 31 December of each year. Includes the transmission grid assets of those utility companies whose electricity distribution facilities are considered as an integral part of the overall transmission grid infrastructure nationwide.
42,713
Peninsula 400 kV Peninsula ≤220 kV Balearic Islands ≤220 kV
Canary Islands ≤220 kV
43,130 43,786 43,930 44,207
Electricity transmission grid facilities in Spain
Provisional data pending audit (currently in progress).Cumulative figures regarding kilometres of circuit and transformer capacity as at 31 December 2018. Includes the transmission grid assets of those utility companies whose electricity distribution facilities are considered as an integral part of the overall transmission grid infrastructure nationwide.
400 kV ≤ 220 kV
Peninsula Peninsula Balearic Islands
Canariy Islands Total
Total circuit (km) 21,730 19,133 1,854 1,491 44,207
Overhead lines (km) 21,613 18,343 1,133 1,187 42,276
Submarine cable (km) 29 236 540 30 835
Underground cable (km) 88 553 181 273 1,096
Transformer capacity (MVA) 81,490 613 3,433 3,310 88,846
T R A N S M I S S I O N G R I D
2 7 7 K M O F N E W
C I R C U I T C O M M I S S I O N E D
I N 2 0 1 8
of the transmission grid and the degree of grid meshing in order to guarantee security of supply.
2P E N I N S U L A R
S Y S T E M
E l e c t r i c i t y d e m a n d o n t h e S p a n i s h P e n i n s u l a m a i n t a i n s t h e p o s i t i v e t r e n d s h o w n o v e r t h e l a s t f o u r y e a r s . N o t e w o r t h y i s t h a t i n 2 0 1 8 o v e r 4 0 % o f t o t a l g e n e r a t i o n h a s b e e n o b t a i n e d u s i n g r e n e w a b l e e n e r g y t e c h n o l o g i e s .
2 5 3 , 4 9 5 G W h
P E N I N S U L A R D E M A N D
2 0 1 8
+ 4 0 %O F D E M A N D
C OV E R E D BY R E N E WA B L E
G E N E R AT I O N
Peninsular System12
3
2
1
0
-1
-2
-3
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
2014 2015 2016 2017 2018
Annual variation in peninsular electricity demand. Rolling year (%)
Adjusted Non-adjusted
Evolution of electricity demand on the spanish peninsula
Demand (measured at power station busbars) Components (%)
GWh D Annual (%) Working days Temperature Adjusted
2014 243,174 -1.1 0.0 -1.0 -0.1
2015 247,970 2.0 -0.1 0.4 1.7
2016 249,680 0.7 0.6 0.1 0.0
2017 252,506 1.1 -0.3 -0.2 1.6
2018 253,495 0.4 -0.1 0.2 0.3
Monthly variation in peninsular electricity demand. 2018 (%)
J F M A M J J A S O N D
Monthly -2.1 6.6 4.6 5.1 -0.6 -6.3 -1.1 1.0 2.9 0.6 0.1 -4.4
Cumulative -2.1 1.9 2.8 3.3 2.5 1.0 0.7 0.7 1.0 0.9 0.9 0.4
Variation with respect to the same month the previous year.
13
Peninsular electricity demand, according to provisional data, closed 2018 at 253,495 GWh, up 0.4% on the previous year. After factoring in the influence of seasonal patterns and working days, the annual variation rate of the demand is estimated at 0.3%.
The Spanish Electricity System l Preliminary Report 2018
8
6
4
2
0
-2
-4
-6
-8
J F M A M J J A S O N D
Components of the monthly variation in peninsular electricity demand. 2018 (%)
Working days Temperature Adjusted demand Variation in demand
2 5 3 , 4 9 5 G W h
P E N I N S U L A R D E M A N D
2 0 1 8
+ 0 . 4 %C O M PA R E D T O
2 0 17
T e m p e r a t u r e s h a v e h a d a n i m p a c t o f 0 . 2 % o n t h e e v o l u t i o n o f c o n s u m p t i o n
Peninsular System14
6
4
2
0
-2
-4
-6
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
2014 2015 2016 2017 2018
Monthly evolution of the adjusted IRE. Rolling year (%)
General Services Industrial
The Red Eléctrica Index (IRE) is an electricity consumption indicator that includes preliminary data that shows the evolution of the monthly demand of large power consumers. In 2018, the composition of the working calendar had a positive impact of 0.1 percentage points on the evolution
of the IRE. Temperature levels, on the contrary, higher than those of the previous year, reduced the evolution of the IRE by 0.6%. After having factored in both effects, the general index decreased by 1.3% year-on-year, a figure which represents the first negative variation of the index since 2013.
IRE: VARIATION BREAKDOWN IN 2018 (%)
Gross Working days Temperature Adjusted
General -1.8 0.1 -0.6 -1.3
Industrial -2.6 0.0 -0.1 -2.5
Services -0.8 0.0 -1.4 0.6
Other 0.9 0.1 -2.3 3.1
-1 . 3 %I R E
(d e m a n d o f l a r g e p o w e r c o n s u m e r s)
By sector, the industrial sector has shown a downward trend month-on-month, closing the year with a percentage of -2.5%, compared to the adjusted growth of 2.2% in 2017, while the services sector showed an/a adjusted variation of 0.6%, compared to -0.7% in 2017.
The Spanish Electricity System l Preliminary Report 2018
MAXIMUM ANNUAL PENINSULAR DEMAND VALUES
2018
2017
2016
2015
2014
40,000 30,000 20,000 10,000 0 0 200 400 600 800
40,611 836806
844814
783
798756
817
817822
8 February (8:00-9:00 p.m) 8 February
19 January
18 February
6 February
11 February
18 January (8:00-9:00 p.m)
17 February (8:00-9:00 p.m)
4 February (8:00-9:00 p.m)
4 February (8:00-9:00 p.m)
3 August (1:00-2:00 p.m) 3 August
13 July
6 September
7 July
3 September
13 July (1:00-2:00 p.m)
6 September (1:00-2:00 p.m)
7 July (1:00-2:00 p.m)
17 July (1:00-2:00 p.m)
39,685
40,96139,302
38,08640,044
40,21840,146
38,74636,929
Winter (January-May/October-December) Summer (June-September)
Hourly demand (MWh) Daily demand (GWh)
15
4 0 , 9 4 7M W
M A X I M U M I N S TA N TA N E O U S
P O W E R
8 F E B R U A R Y
8 : 2 4 P. M .
- 9 . 9 %C O M PA R E D T O T H E A L L-T I M E H I G H S E T I N
2 0 0 7
The maximum instantaneous power, at the time of drafting this report, was recorded on 8 February at 8:24 p.m. when it reached 40,947 MW, a value 1% lower than the previous year’s maximum recorded in January, but still far
from the all-time record of 45,450 MW set in December 2007. The maximum hourly demand was also registered on 8 February between 8:00 and 9:00 p.m., when it reached 40,611 MWh, a value 0.9% lower than the maximum for 2017.
Peninsular System16
Regarding demand coverage, noteworthy was the increase in the contribution of hydro (13.2% compared to 7.2% the previous year), which has led to a decrease
(1) Pure pumped storage + estimated mixed pumped storage.
in the contribution of coal (13.5% compared to 16.5% in 2017). As for the technologies that have contributed most to demand coverage, nuclear has again ranked first with
Installed power capacity on the peninsula as at 31 december 2018 (%)
Electricity demand coverage on the peninsula. 2018 (%)
Electricity demand coverage. Maximum hourly demand coverage on the Peninsula. 2018 (%)
Nuclear 7.2% Wind 23.4%
Coal 9.7% Hydro 17.3%
Combined cycle 24.9% Solar photovoltaic 4.5%
Cogeneration 5.8% Solar thermal 2.3%
Non-renewable waste 0.5% Other renewables 0.9%
Pumped-storage 3.4% Renewable waste 0.1%
Nuclear 20.6% Wind 19.0%
Coal 13.5% Hydro 13.2%
Combined cycle 10.2% Solar photovoltaic 2.9%
Cogeneration 11.2% Solar thermal 1.7%
Non-renewable waste 0.9% Other renewables 1.4%
Pumped-storage (1) 0.8% Renewable waste 0.3%
Import balance of international exchanges
4.3%
Nuclear 17.4% Wind 11.7%
Coal 18.5% Hydro 14.6%
Combined cycle 22.6% Solar thermal 0.5%
Cogeneration 8.7% Other renewables 1.1%
Non-renewable waste 0.8% Renewable waste 0.2%
Pumped-storage (1) 2.1% Import balance of international exchanges
1.8%
a contribution of 20.6%, followed by wind with 19%. It should also be noted that close to 4.3% of the demand was covered by energy imported from other countries.
98,593 MW
253,495 GWh
40,611 MW8 February(8:00-9:00
p.m.)
The Spanish Electricity System l Preliminary Report 2018 17
4 0 . 1 %S H A R E O F
R E N E WA B L E S I N T H E T O TA L
E L E C T R I C I T Y G E N E R AT I O N
Renewable energy increased its share to 40.1% in the overall annual electricity generation, compared to 33.7% the previous year, this was helped mainly by an increase of 84.8% in
hydroelectric generation compared to 2017. Similarly, wind energy grew 2.9%, maintaining its ranking as the second source of electricity generation in 2018.
2018
2017
2016
2015
2014
0 10 20 30 40 50 60 70 80 90 100
Evolution of renewable and non-renewable peninsular electricity generation (%)
40.1
33.7
40.5
36.7
42.3
59.9
66.3
59.5
63.3
57.7
Renewable: hydro, wind, solar photovoltaic, solar thermal, other renewables and renewable waste. Non-renewable: pumped storage, nuclear, coal, fuel/gas, combined cycle, cogeneration and non-renewable waste.
Hydro Wind Solar photovoltaic Solar thermal Other renewables Renewable waste
2018
2017
2016
2015
2014
0 20,000 40,000 60,000 80,000 100,000 120,000
Evolution of renewable electricity generation on the peninsula (GWh)
Peninsular System18
Pumped-storage (1) Nuclear Coal Combined cycle Cogeneration Non-renewable waste
2018
2017
2016
2015
2014
0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000 180,000
Evolution of non-renewable electricity generation on the peninsula (GWh)
(1) Pure pumped storage + estimated mixed pumped storage,
Coal Combined cycle Cogeneration Non-renewable waste
2018
2017
2016
2015
2014
0 10 20 30 40 50 60 70 80
Evolution of CO2 emissions associated with electricity generation on the peninsula (Million, tCO2)
D e c r e a s e i n C O 2 e m i s s i o n s f r o m e l e c t r i c i t y g e n e r a t i o n t h a n k s t o t h e g r e a t e r c o n t r i b u t i o n o f r e n e w a b l e e n e r g y
The Spanish Electricity System l Preliminary Report 2018
Evolution of non-renewable electricity generation on the peninsula (GWh)
19
According to provisional data, producible hydroelectric registered the highest value of the last four years, 37,386 GWh, a value 28% higher than the historical average value and 134% higher
than that registered in 2017. Hydroelectric reserves of the complete set of reservoirs closed 2018 with a fi ll level of 44.1% of their total capacity.
Producible hydroelectric energy on the peninsula
GWh Index Probability of being exceeded (%)
2014 40,271 1.3 14.6
2015 25,141 0.8 79.0
2016 34,667 1.1 37.3
2017 15,972 0.5 99.3
2018 37,386 1.3 17.2
500
400
300
200
100
0
J F M A M J J A S O N D
Daily producible hydroelectric energy on the peninsula in 2018 compared with the historical
average producible (GWh)
Wet Dry Historical average producible Producible 2018
Evolution of CO2 emissions associated with electricity generation on the peninsula (Million, tCO2)
125 122
123 125
107 6428 17 23 46
80 102
P r o d u c i b l e h y d r o e l e c t r i c h a s r e g i s t e r e d l e v e l s 2 8 % a b o v e t h e h i s t o r i c a l a v e r a g e v a l u e
Peninsular System20
Peninsular hydroelectric reserves as at 31 december 2018
2017 2018
Capacity GWh % Fill level GWh % Fill level
Annual management regime 8,967 2,617 29.2 4,717 52.6
Hyper-annual management regime 9,571 2,267 23.7 3,456 36.1
Total 18,538 4,883 26.3 8,172 44.1
Evolution of peninsular hydroelectric reserves (GWh)
19,000
17,000
15,000
13,000
11,000
9,000
7,000
5,000
3,000
2014 2015 2016 2017 2018
Statistical maximum
Statistical average Maximum capacity Real
Statistical maximum and minimum: average of the maximum and minimum values of the last 20 years.,
HYDROELECTRIC RESERVES
44.1 %
Statistical minimum
The Spanish Electricity System l Preliminary Report 2018
19,000
17,000
15,000
13,000
11,000
9,000
7,000
5,000
3,000
2014 2015 2016 2017 2018
21
S t r e n g t h e n i n g o f t h e t r a n s m i s s i o n g r i d w i t h t h e c o m m i s s i o n i n g o f n e w k i l o m e t r e s o f e l e c t r i c i t y l i n e t o e n s u r e a s a f e a n d e f f i c i e n t s u p p l y
According to provisional data, the peninsular electricity transmission grid registered an increase of 96 km of circuit during 2018 (2 km of 400 kV
and 94 km of 220 kV), bringing the total km of circuit in the peninsular transmission grid at year-end to 40,863 km.
2018 (1)
2017
2016
2015
2014
16,000 17,000 18,000 19,000 20,000 21,000 22,000
Evolution of the peninsular transmission grid (km of circuit)
(1) Provisional data pending audit (currently in progress).Cumulative fi gures regarding kilometres of circuit as at 31 December of each year. Includes the transmission grid assets of those utility companies whose electricity distribution facilities are considered as an integral part of the overall transmission grid infrastructure nationwide,
40,863
40,767
40,632
40,109
39,878
400 kV ≤220 kV
Evolution of the electricity transmission grid on the peninsula
2014 2015 2016 2017 2018 (1)
Circuit 400 kV (km) 21,094 21,184 21,619 21,728 21,730
Circuit ≤ 220 kV (km) 18,785 18,925 19,013 19,039 19,133
Transformer capacity (MVA) 79,271 79,271 79,871 80,421 82,103
(1) Provisional data pending audit (currently in progress).Cumulative fi gures regarding kilometres of circuit and transformer capacity as at 31 December of each year. Includes the transmission grid assets of those utility companies whose electricity distribution facilities are considered as an integral part of the overall transmission grid infrastructure nationwide.
Peninsular System22
Balance of international physical electrical energy exchanges (GWh)
International physical electrical energy exchanges. 2018 (GWh)
France Portugal Andorra Morocco Total
2014 3,567 -903 -235 -5,836 -3,406
2015 7,324 -2,266 -264 -4,927 -133
2016 7,802 5,086 -278 -4,951 7,658
2017 12,465 2,685 -233 -5,748 9,169
2018 12,047 2,655 -210 -3,389 11,102
Positive value: importer balance; Negative value: exporter balance
SAN
TA L
LOGA
IA32
0 KV
BAIX
AS1,
078
6,10
7
VIC
400
KVBA
IXAS
310
2,78
6
ADRA
LL11
0 KV
MAR
GIN
EDA
( AN
DOR
RA)
210
0
BEN
ÓS15
0 kV
LAC
D’O
O0
2
BIES
CAS
220
KVPR
AGN
ÉRES
347
710
HER
NAN
I40
0 KV
ARGI
A1,
284
5,41
9
ARKA
LE22
0 KV
ARGI
A44
649
0
IRÚ
N13
2 KV
ERRO
ND
ENIA
1
0
CONCHAS132 kV
LINDOSO
0
0
P, CRUZ 400 KV
MELLOUSSA (MOROCCO)
3,56
918
0
ALDEADÁVILA 400 KV
LAGOAÇA 2,511407
ALDEADÁVILA 220 KV
POCINHO 2 226224
ALDEADÁVILA 220 KV
POCINHO 1 199223
SAUCELLE 220 KV
POCINHO 159319
CEDILLO 400 KV
FALAGUEIRA 1,749291
BADAJOZ 66 KV
ALCÁÇOVAS 00
ROSAL DE LA FRONTERA 15 KV
V, FICALHO 00
BROVALES 400 KV
ALQUEVA 1,704281
PUEBLA DE GUZMÁN 400 KV
TAVIRA 1,40963
CARTELLE400 kV
LINDOSO
368
3,86
2
3N O N - P E N I N S U L A R
S Y S T E M S
25
E l e c t r i c i t y d e m a n d g r e w i n m o s t n o n - p e n i n s u l a r s y s t e m s , e x c e p t i n t h e C a n a r y I s l a n d s . O f n o t e i s t h a t r e n e w a b l e e n e r g y c o v e r e d m o r e t h a n 1 0 % o f d e m a n d i n t h e C a n a r y I s l a n d s , a s i g n i f i c a n t v a l u e f o r a n i s o l a t e d e l e c t r i c i t y s y s t e m .
1 5 , 3 1 3 G W h
E L E C T R I C I T Y D E M A N D I N N O N -
P E N I N S U L A R SYS T E M S
2 0 1 8
- 0 . 3 %C O M PA R E D T O
2 0 17
4
2
0
-2
-4
-6
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
2014 2015 2016 2017 2018
Annual variation of electricity demand. Balearic islands. Rolling year (%)
Non-Peninsular System26
Adjusted Non-adjusted
Adjusted Non-adjusted
2
0
-2
-4
-6
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
2014 2015 2016 2017 2018
Annual variation of electricity demand. Canary islands. Rolling year (%)
Evolution of non-peninsular electricity demand
Balearic Islands Canariy Islands Ceuta Melilla
GWh D Anual (%) GWh D Anual (%) GWh D Anual (%) GWh D Anual (%)
2014 5,577 -1.6 8,495 -0.1 212 5.1 210 0.1
2015 5,788 3.8 8,633 1.6 204 -3.9 213 1.6
2016 5,823 0.6 8,744 1.3 211 3.3 208 -2.3
2017 6,016 3.3 8,931 2.1 203 -3.7 210 1.0
2018 6,052 0.6 8,840 -1.0 207 2.2 213 1.2
The Spanish Electricity System l Preliminary Report 2018
M o r e t h a n 2 0 % o f t h e d e m a n d o f t h e B a l e a r i c I s l a n d s w a s c o v e r e d b y e n e r g y t r a n s f e r r e d f r o m t h e S p a n i s h P e n i n s u l a
Electricity demand on the Balearic Islands closed 2018 at 6,052 GWh, representing a growth of 0.6% compared
to 2017. After factoring in the influence of seasonal patterns and working days, the demand growth was 0.2%.
6 , 0 5 2 G W h
D E M A N D O N T H E BA L E A R I C
I S L A N D S 2 0 1 8
+ 0 . 6 %C O M PA R E D T O
2 0 17
20
15
10
5
0
-5
-10
J F M A M J J A S O N D
Components of the variation in monthly electricity demand. Balearic islands (%)
Working days Temperature Adjusted demand Variation in demand
27
Non-Peninsular System28
Electricity demand on the Canary Islands closed 2018 at 8,840 GWh, representing a decrease of 1% with respect to
2017. After factoring in the influence of seasonal patterns and working days, a negative 1% variation in demand is also estimated.
8 , 8 4 0 G W h
D E M A N D O N T H E C A N A RY
I S L A N D S 2 0 1 8
-1 . 0 %C O M PA R E D T O
2 0 17
3
2
1
0
-1
-2
-3
-4
J F M A M J J A S O N D
Components of the variation in monthly electricity demand. Canary islands. 2018 (%)
Working days Temperature Adjusted demand Variation in demand
The Spanish Electricity System l Preliminary Report 2018
The maximum hourly demand on the Balearic Islands occurred on 6 August, between 1:00 and 2:00 p.m., when it reached 1,315 MWh, a value 2.2% lower than the 2017 maximum recorded on 3 August, between 1:00 and
2:00 p.m. The maximum hourly demand in the Canary Islands was recorded on 8 February, between 8:00 and 9:00 p.m., with 1,404 MWh, a value 0.2% higher than the maximum of 2017 registered on 17 October, between 8:00 and 9:00 p.m.
29
Monthly variation of non-peninsular electricity demand. 2018 (%)
Balearic Islands Canariy Islands Ceuta Melilla
January -8.6 1.3 0.0 -2.1
February 15.7 2.6 8.7 9.1
March 12.9 -0.9 7.5 1.4
April 2.8 -0.3 9.2 5.1
May -1.3 -1.8 -1.0 0.3
June -7.7 -3.1 -6.9 -5.5
July 1.1 -1.4 -2.4 -2.9
August -0.4 -3.1 -5.1 3.1
September 7.6 0.8 5.2 9.0
October 0.1 -1.4 11.8 1.1
November -1.8 -3.1 6.2 1.3
December -8.2 -1.2 -3.2 -3.5
Variation with respect to the same period of the previous year,
Maximum annual demand values (non-peninsular systems)
Balearic Islands
Canariy Islands
Ceuta
Melilla
1,049 18,78026,412
26,70327,224
693657
763715
27 February (8:00-9:00 p.m.) 27 February
10 February
8 febrero
6 February
8 February (8:00-9:00 p.m.)
7 February (8:00-9:00 p.m.)
6 February (8:00-9:00 p.m.)
6 August (13-14h) 6 August
13 September
25 September
8 August
24 September (1:00-2:00 p.m.)
25 September (1:00-2:00 p.m.)
8 August (1:00-2:00 p.m.)
1,315
1,4041,375
3835
4140
Winter (January-May/October-December) Summer (June-September)
Hourly demand (MWh) Daily demand (MWh)
Non-Peninsular System30
Installed power capacity of non-peninsular systems remained stable in all systems, except in the Canary Islands, which registered an increase of 7.7%, due to an increase of 103.8% in installed wind power capacity. In terms of demand coverage, the most significant difference compared to the previous
year is the lower share of coal-fired generation in the Balearic Islands (nearly four percentage points less than in 2017). Of note is that renewable energy covered more than 10% of the demand in the Canary Islands, a significant value for an isolated electricity system.
Installed power capacity as at 31 december 2018. Balearic islands (%)
Electricity demand coverage. Balearic Islands. 2018 (%)
Coal 20.5% Non-renewable waste 1.6%
Diesel generators 8.0% Renewable waste 1.6%
Gas turbine 26.5% Wind 0.2%
Combined cycle 37.5% Solar photovoltaic 3.5%
Cogeneration 0.5% Other renewables 0.1%
Coal 39.5% Non-renewable waste 2.2%
Diesel generators 10.5% Renewable waste 2.2%
Gas turbine 12.6% Wind 0.1%
Combined cycle 9.8% Solar photovoltaic 1.9%
Auxiliary generation 0.2% Spanish Peninsula-Balearic Islands link
20.4%
Cogeneration 0.6%
2,285 MW
6,052 GWh
The Spanish Electricity System l Preliminary Report 2018 31
Installed power capacity as at 31 december 2018. Canary Islands (%)
Electricity demand coverage. Canary islands. 2018 (%)
Diesel generators 16.5% HidroWind 0.4%
Gas turbine 18.5% Wind 14.0%
Steam turbine 16.1% Solar photovoltaic 5.6%
Combined cycle 28.7% Other renewables 0.1%
Hydro 0.1%
Diesel generators 24.0% HidroWind 0.3%
Gas turbine 3.2% Wind 7.0%
Turbina de vapor 27.8% Solar photovoltaic 3.1%
Combined cycle 34.5% Other renewables 0.1%
Evolution of the non-peninsular electricity transmission grid
2014 2015 2016 2017 2018 (1)
Circuit 220 kV (km)
Balearic Islands 431 431 432 432 432
Canariy Islands 163 216 220 220 238
Total 594 647 652 652 670
Circuit 132 kV (km)
Balearic Islands 220 346 472 472 517
Canariy Islands - - - - 69
Total 220 346 472 472 586
Circuit ≤ 132 kV (km)
Balearic Islands 894 896 896 905 905
Canariy Islands 1,126 1,131 1,134 1,135 1,184
Total 2,019 2,027 2,030 2,039 2,088
Transformer capacity (MVA)
Balearic Islands 2,793 3,273 3,273 3,273 3,433
Canariy Islands 1,875 2,000 2,000 2,560 3,310
Total 4,668 5,273 5,273 5,833 6,743
(1) Provisional data pending audit (currently in progress).Cumulative figures regarding kilometres of circuit and transformer capacity as at 31 December 2018. Includes the transmission grid assets assets of those utility companies whose electricity distribution facilities are considered as an integral part of the overall transmission grid infrastructure nationwide.
3,006 MW
8,840 GWh
4G L O S S A R Y
O F
T E R M S
PUMPED STORAGE CONSUMPTION
Energy that pumped storage hydroelectric power stations use to elevate water from a lower reservoir to the upper one in order to be subsequently used to generate hydroelectric energy.
RENEWABLE ENERGY
Includes hydro, hydro-wind, wind, solar photovoltaic, solar thermal, biogas, biomass, marine energy, geothermal and renewable waste.
NON-RENEWABLE ENERGIES
Includes pumped-storage, nuclear, coal, fuel/gas, combined cycle, cogeneration and non-renewable waste.
PRODUCIBLE HYDROELECTRIC ENERGY
Maximum quantity of electricity that theoretically could be produced considering the water supplies registered during a specific period of time, and once the supplies used for irrigation or uses other than the generation of electricity have been subtracted.
PRODUCIBLE HYDROELECTRIC INDEX
Quotient between the producible energy and the average producible energy, both related to the same period and to the same hydroelectric system.
INTERNATIONAL PHYSICAL ELECTRICITY EXCHANGES
The movements of energy which have taken place via international interconnection lines during a given period of time. It includes the loop flow of energy as a consequence of the grid design.
INSTANTANEOUS POWER
Instantaneous power is the energy absorbed by the demand at any given moment of time.
33
Glossary34
TRANSMISSION GRID
The complete set of lines, switchyards/facilities, transformers and other electrical elements with voltages greater than or equal to 220 kV, and those other facilities, regardless of their power, which fulfil power transmission functions, international/cross- border interconnections and the interconnections with the Spanish non-peninsular electricity systems.
HYDROELECTRIC RESERVES OF A RESERVOIR
The hydroelectric reserve of a reservoir is the quantity of electricity that could be produced in its own power station and in all the power stations situated downstream, with the total drainage of its current useable water reserves and providing that drainage occurs without natural contributions.
The annual management regime reservoirs are those in which complete drainage would take place in less than one year. Hyper-annual management regime reservoirs are those in which the total drainage time takes more than one year.
Published byRED ELÉCTRICA DE ESPAÑAPaseo del Conde de los Gaitanes. 17728109 Alcobendas (Madrid)Tel, 91 650 85 00Fax, 91 640 45 42www,ree,es
Co-ordination of the publicationCorporate Image and Brand Department
Technical co-ordinationDepartment of Access to Information on the Electricity
Design and layout
Other data regarding this publicationPublication date: January 2019
English translation by Wayman English International www.waymanenglish.com
This English version is a translation of the original and authentic Spanish text found in the ‘EL SISTEMA ELÉCTRICO ESPAÑOL – AVANCE 2018’ report, originally issued in Spanish. In the event of any discrepancy, the Spanish-language version shall prevail.
Red Eléctrica works on selecting the most legible typographical font for their publications.The typographical font Geogrotesque has been used for the texts and graphics in this report.
www,ree,es
Paseo del Condede los Gaitanes. 17728109 Alcobendas (Madrid)www,ree,es