the scottish renewable resource assessment and implications … · the scottish renewable resource...

33
Page 1 EPRG seminar: The Scottish renewable resource assessment and implications for the grid 16 May 2008 The Scottish renewable resource assessment and implications for the grid Thomas Boehme, Jamie Taylor, Robin Wallace, and Janusz Bialek Institute for Energy Systems The University of Edinburgh, UK

Upload: vuduong

Post on 06-Sep-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

The Scottish renewable resourceassessment and implications for

the grid

Thomas Boehme, Jamie Taylor, Robin

Wallace, and Janusz Bialek

Institute for Energy Systems

The University of Edinburgh, UK

Page 2

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Background

• Scottish renewable target: 40% by 2020, recently upgraded to 50%, interim milestone of 31% by 2011

• In 2004, the (then) Scottish Executive commissioned a report to appraise of the extent to which Scotland could meet the 40% target

• The aim: realistic assessment of Scotland’s renewable potential (wind on- and off-shore, tidal and wave resource)

• The Scottish target is now 50% but the assessment of the resource still stands

Page 3

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

• Temporal resolution: one-hour for wind and 3 hours for wave

• Spatial resolution: 1 km2

• Physical modelling using WAsP and WindFarmer: calculate wind at turbine height (80 m agl.) in each 1 km2 cell from met station data, elevation data and surface roughness description

• Eliminate no-go areas and take limits into account

• Rank sites according to costs• Full report available from:

http://www.scotland.gov.uk/Publications/2006/04/24110728/0

What’s unique?

Page 4

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

The Challenge

Network

Demand

Time

Supply

Time

MEC Load

Page 5

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Constraints GIS Mapped

Resourcetime series

Long-termresource

Generatorlocations

Converter

Constraints

Macro

Renewable

generation

GIS

Projectcosts

Selectioncriteria

Macro

Scenarios

Demand

Contents

Net

work

Keyfigures

Results

Page 6

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

StudyArea

N = 500 kmE = 0 km

N = 500 kmE = 500 km

500 km

750 km

Source: Ordnance Survey

• Spatial resolution: 1 km2

• Use of British National Grid coordinates

N = 1250 kmE = 500 km

Page 7

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Political

• International limit (200 nmi, 12 nmi)

• National limit

• Fishing limit (6 nmi)

• Planning authorities

• Local regulations

Sources: OS, UKHO

Page 8

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Physical

• Water depth

• Slope

• Lakes

• Rivers

• etc.

Sources: OS, BGS, BODC, SRTM

Example:

Average slope > 15% in

a 1 km by 1 km square.

Page 9

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

• Recreation interests (high sensitivity)

• Biodiversity interests (high sensitivity)

• Medium sensitivity areas

Sources: OS, SNH, SEGIS

National Scenic Area

National Park

Regional park

AGLV, LNR, ...

Natura 2000, SSSI, ...

Environment

Page 10

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Aviation Interests

• Civil radars

• Military radars

• Met Office radars

• Low Flying System

Sources: OS, DTI, CAA, BWEA

15 km exclusion zone

30 km consultation zone

NATS high impact

NATS lower impact

Tactical Training Area

Page 11

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

• Urban areas

• Navigational risk

• Seismological measurements

• Ammunition dumping

• Distances, etc.

Sources: OS, DTI, CAA, BWEA

Cities, towns, villages

Eskdalemuir

Further Constraints

very high

medium

very low

Page 12

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Long-Term Resource

Resourcetime series

Long-termresource

Generatorlocations

Converter

Constraints

Macro

Renewable

generation

GIS

Projectcosts

Selectioncriteria

Macro

Scenarios

Demand

Contents

Net

work

Keyfigures

Results

Page 13

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Average wind speed

in each 1 km2 cell at

80 m height agl.

calculated from met

station data using

WAsP and

WindFarmer

10 years data (1994-

2003)

Kirkwall

Wick

Lerwick

Sella Ness

Dyce

Leuchars

Charterhall

Eskdalemuir

West Freugh

Tiree Airport

Port Ellen

South Uist

Stornoway

Dundrennan

Machrihanish

Altnaharra

AvSk

StD

Sa

Au

K

T

OnshoreWindResource

Meteorological

station (21 + 3)

4 10 16 m/s

Sources: OS, Met Office

Page 14

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Average wind speed

at 80 m height asl.

OffshoreWindResource

4 10 16 m/s

Sources: OS, DTI, Met Office

Met Office

Simulation Point

(11)

Water depth, 5 km

offshore

0 ... 30 m

30 ... 40 m

40 ... 50 m

Page 15

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Wave power per

metre crest length

WaveResource

5 30 55 kW/m

Sources: OS, DTI, Met Office

Met Office

Simulation Point

(84 + 11)

Water depth, 5 km

offshore

50 ... 100 m

3 hour data: March

2000 – Nov 2004

Page 16

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Tidal CurrentResource

Sources: OS, DTI, Robert Gordon Univ.

Average spring tide

velocity (surface)

0.5 1.5 2.5 m/s

Water depth

30 ... 50 m

South-West

Orkney

Islands

Pentland Firth

Shetland

Mull of Galloway

Variable but

deterministic

Page 17

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Future Generator Locations

Resourcetime series

Long-termresource

Generatorlocations

Converter

Constraints

Macro

Renewable

generation

GIS

Projectcosts

Selectioncriteria

Macro

Scenarios

Demand

Contents

Net

work

Keyfigures

Results

Page 18

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Cost Calculation

Step Remark

Remove “no go” cells

500 x 750

Check capacity limit in

consultation areas

Select cells

Calculate annual energy output

Calculate (initial) levelisedproject cost (LPC) per cell

Remove “expensive” cells

Calculate (final) LPC per cell

Cluster to projects (for cost sharing)

Excluding grid

connection costs

e.g. by 100 km2 area,

remove more cells

e.g. > 10 p/kWh

e.g. cities, NSAs

neighbouring cells,

total capacity limit

Including grid

connection costs

per area; capacity or

cost limit

Page 19

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Estimated onshore

wind project costs

excluding connection

to existing network

low cost

medium cost

high cost

Example:

“no go” zone

• 3 x 2.5 MW per km2

• 80 m hub height• 20 years, 8 % discount rate

Assumptions:

including

Project Costs

Page 20

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Creating Power Time Series

Resourcetime series

Long-termresource

Generatorlocations

Converter

Constraints

Macro

Renewable

generation

GIS

Projectcosts

Selectioncriteria

Macro

Scenarios

Demand

Contents

Net

work

Keyfigures

Results

Page 21

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Energy Converters

On/Offshore Wind Waves Tidal Currents

Source: Nordex, OPD, MCT

• 3-bladed horizontal axis turbine with pitchableblades

• 80 / 120 m diameter

• 2.5 / 5 MW

• 80 m hub height

• Offshore: < 40 m water depth

• Semi-submerged articulated structure

• 180 m long

• 1.5 MW

• 50 ... 150 m water depth

• Twin-rotor horizontal axis turbine with pitchable blades

• 20 m rotor diameter

• 2 x 500 kW

• 30 ... 50 m water depth

Poweroutput

Wind speed

cut-outcut-in

nominal

Page 22

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Generation vs. Demand

Resourcetime series

Long-termresource

Generatorlocations

Converter

Constraints

Macro

Renewable

generation

GIS

Projectcosts

Selectioncriteria

Macro

Scenarios

Demand

Contents

Net

work

Keyfigures

Results

Page 23

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

0

1,000

2,000

3,000

4,000

5,000

0 h 4 h 8 h 12 h 16 h 20 h 0 h

Demand - DailyS

yste

m D

em

an

d (

MW

)

Time

ScottishPower

Scottishand

SouthernEnergy

max.

min.

avg.

Source: SP and SSE 2003 Seven Year Statements

24 h

Example:2002/03

Page 24

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

0

1,000

2,000

3,000

4,000

5,000

Demand - AnnualS

yste

m D

em

an

d (

MW

)

Time

ScottishPower

weekly max.

weekly min.

weekly avg.

Source: SP 2002 and 2003 Seven Year Statements

J F M A M J J A S O N D

Example:2002

Page 25

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 20080

40

80

120

Jul-21 Jul-22 Jul-23 Jul-24 Jul-25 Jul-26 Jul-27 Jul-28

0

40

80

120

Jan-20 Jan-21 Jan-22 Jan-23 Jan-24 Jan-25 Jan-26 Jan-27

Sample Area

Demand Matching January, July 2003

(MW)

(MW)

Offshore windOnshore wind

(a) Orkney(b) Mainland

Tidal currents

Waves

40

%,

100

% d

em

an

d

Page 26

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Key Figures and Results

Resourcetime series

Long-termresource

Generatorlocations

Converter

Constraints

Macro

Renewable

generation

GIS

Projectcosts

Selectioncriteria

Macro

Scenarios

Demand

Contents

Net

work

Keyfigures

Results

Page 27

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Results

After application of geographical constraints

it could be possible to develop at least

– 6 GW of onshore wind

– 3 GW of offshore wind

– 3 GW of wave and

– 1 GW for tidal current

or any combination of these technologies.

Page 28

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Results

Annual plant capacity factors derived from production time-series all exceed 30% – They reduce as the

capacity increases by adding less energetic higher cost sites.

– Seasonal values for wind and wave power are significantly higher in winter than in summer.

60%

30%

0 6 GW

Winter

Summer

Page 29

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Results

Onshore wind or the mixed technology

portfolio of 6 GW

would on average meet at least 40% of

the electricity demand in 2020

Potential to increase the penetration to

50% or more

60%

40%

0 6 GW

Winter

Summer20%

Page 30

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Results

Coincident hours best describe ongoing hourly match as a histogram

There is about 29 hours/ year when the demand > 90% of the peak while on-shore wind provides less than 10% of its capacity

Diversification by using a portfolio of renewable generation reduces that number to 20 hours/year

Coincident hours for demand > 90% and

production < 10% (h/year)

3 GW 6 GW

Onshore-wind

75-10-10-5% mix

Tidal-current (750 MW)

Wave

Offshore-wind

29

-(22)

-19

-14

29

2018

Demand

Gen

erat

ion

Page 31

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Network Access

Generally weak network in Scotland

Competition for network access

Full development of the more remote onshore and most of the offshore resource would require completion of planned network upgrades in northern and western Scotland.

Page 32

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Need for network upgrades

Current developments: review of GB Security and Quality of Supply Standard (SQSS) and

Transmission Access Review (TAR)

Controversy regarding scaling factor for wind for

network planning purposes (currently 60%)

Need for upgrades could be reduced if control schemes were more widely used (quad

boosters, intertrips)

Page 33

EPRG seminar:

The Scottish renewable resource

assessment and

implications for the grid

16 May 2008

Summary

The study has refined understanding of characteristics and availability of renewable resource in Scotland through detailed physical modelling using geographical and surface roughness data

Realistic assessment by eliminating no-go areas and including limits tp renewable generation

Diversification of renewable energy sources helps to manage variability of renewable input but a strong interconnected transmission system is required

SuperGen FlexNet projects will extend the study to the whole GB although in less detail