the islamic university · the islamic university of gaza ... thanks to the staff and the deans of...
TRANSCRIPT
The Islamic University – Gaza
Faculty of Engineering
Higher Education Deanship
Construction project management
زةـــغ –ة ــيــلامــــة الاســـعـــامــجــل ا
ةــــدســنــهــل ة اــيــلــك
اـــيـــلـــعــل ات اـــــدراســادة الــمــع
ةــيـــــسهــنـــدالوعــات رــــشــمالدارة إ
Master Dissertation in Construction Management
The success factors that affecting public construction projects
and their relation to key performance indicators
عوامل النجاح التي تؤثر على مشاريع الإنشاءات العامة وعلاقتها بالأداء
Prepared by:
Sirin K. Elbohisi
Supervised by:
Prof. Adnan Enshassi
Professor of Construction Engineering and Management
A thesis is submitted in partial fulfillment of the requirement for
Degree of Master of Science in Civil Engineering – Construction Management
The Islamic University of Gaza
January, 2016
II
والله مكم الله ويعله بكله شيء عليم واتقوا الله
282سورة البقرة،
III
Dedication
This research is dedicated to all people who inspired, supported and encouraged me.
"To my parents, thank you for your endless love, support, and encouragement."
"To my brothers and sisters: Khadiga, Arwa, Hamzah, Muath, Salam, Abed Elrzaq,
Iman, Sufyan, Asma, Shima, Ahamed and Iqbal, thanks for making my life special and
have never left my side".
To my great teachers, thanks for all the things you have done for me. To my friends who
encourage and support me. Last but not least, deepest thanks go to all people who took
part in making this thesis real. All the people in my life who touch my heart.
IV
Acknowledgement These acknowledgements presented to sincerely thank people who supported, guided, and
encouraged me along the way to complete this research. Without their assistance,
encouragement, suggestions and commitment, this dissertation would not have been a
reality. From the depth of my heart I would like to express sincere gratitude and
appreciation to my supervisor Professor Adnan Enshassi who worked hard with me
throughout the route. Due to his continued support, generous academic advice,
discussions, suggestions, and his incredible understanding and capability to initiate
guidelines, I would like to pass him special thanks. Furthermore, I highly appreciate the
efforts of Dr. Jawad Alagh, Abed Elrhaman Ayyash and my brother Sufyan Elbohisi for
their support and big efforts in helping me in this research.
As well, I would like to thank all experts especially Dr. Yousef Elgaraiz, Dr. Khalid
Alhalaq and Dr. Ibrahim Madi for their contribution and valuable opinion. Also my
thanks to the staff and the deans of the faculty of Engineering at University of Palestine
for their most welcoming support and friendly environment.
A special thanks to consultants and engineers in Gaza Strip and West Bank for their
enormous help in collecting the surveys and their participated in the questionnaire. I am
grateful to Eng. Wasem Elkhaldi for helping in designing Electronic questionnaire and
Mr. Mohammed Elhawajre for helping in distributing and collecting the questionnaire
and Eng. Bassam Shallan for his big support in collecting data from West Bank. Finally,
to my family, very special thanks for all their sacrifices, patience, love and support
throughout my research studies.
Eng. Sirin K. Elbohisi
V
Abstract
Purpose: Construction industry is characterized by complexity nature; being challenged
by high cost pressure, and increasing competition. The aim of this research was to
investigate the success factors that affecting public construction projects and their
relation to key performance indicators in Palestine. This has been achieved throw three
main objectives which were 1) identifying and evaluating the key performance indicators
(KPIs) of public construction projects, 2) investigating the critical success factors CSFs
affecting the public construction projects and 3) evaluating the relationship between KPIs
and CSFs in the public construction projects.
Design/methodology/approach: Intensive literature review was done and a quantitative
survey was designed and used in the research. Two main steps were used to reach the
final amendment of the questionnaire: (1) Experts consultation by presenting the
questionnaire to 6 experts in construction projects from Palestine to evaluate
questionnaire clarity, comprehensivness and readability. (2) Pilot study was conducted by
distributing 20 copies of the questionnaire to respondents from the target group which
include engineering professionals (civil or architectural engineers who works as project
managers, field supervisors and designers) and analyzing them for testing statistical
validity and reliability. Three hundred and eighty four copies of the questionnaire were
distributed and two hundred and seventy four copies were received from the respondents
with a response rate = 71.35%. To draw meaningful results, the collected data have been
analyzed by using the quantitative data analysis techniques (which include Relative
important index RII, Factor analysis, Pearson correlation analysis, and others) through the
Statistical Package for Social Science (SPSS) IBM version 22.
Findings: From literature review and pilot study 13 KPIs were determined in this study.
Factor analysis was used to reduce and group the 13 KPIs. As a result of factoring 11
KPIs were remaining and grouped into three groups namely: 1) project quality and
environment impact, 2) satisfaction and reputation of project parties and 3) overall cost
and time. Descriptive statistics used to rank the 13 KPI and results revealed that the top
three most important KPIs were 1) project conformity to quality and technical
specifications standards, 2) actual project costs compared with planned budget and 3)
actual project duration compared with planned duration. Also results indicated that
Palestinian construction projects suffer from cost and time overrun and the quantity and
costs of variation orders are high.
Also from literature review and pilot study 81 CSFs were obtained. They were classified
according to project life cycle into four phases. By using factor analysis the number were
reduced to 52 CSFs and grouped into 14 component. Results also showed that all 81
CSFs were important since the least RII was above 75.51%. The top five most important
CSFs from the respondents view were 1) project feasibility and priority for the society, 2)
coordinating with related formal parties such as (municipalities, electricity companies,
ministries,… etc.), 3) document the preparation meetings in details, 4) project manager
VI
commitment to meet cost quality and time of project and 5) the client follows project
implementation regularly. Also results showed that there were significant relationship
between CSFs and KPIs which means that project KPIs affected by CSFs.
Theoretical and practical implications of the research: The research unravels about an
important concept and paves the path for future research in this particular area. It is
concerned with construction professionals working in governmental and non-
governmental organizations and consultant firms. The questionnaire survey did not
include all collected factors from literature review, since it was generalized that adopted
to Palestine. Recommendations were made for clients, consultants and contractors
respectively in order to optimize the their construction projects success. It is hoped that
the obtained KPIs and CSFs in this study can be applied and examines practically in
construction projects.
Originality/ value: This research will add to the current body of knowledge about KPIs
and CSFs all over the world. Rarely studies have examined the relationship between KPIs
and CSFs according to projects life cycle. This research is considered as one of these
limited studies which link between KPIs and CSFs according to projects life cycle. It is
the first study that contributes significantly to consider KPIs and CSFs in Palestine. This
study can provide a documentation of reference for the researcher who interested in the
field of the study.
Keywords: key performance indicators KPIs, critical success factors CSFs, life cycle,
public construction projects.
VII
Abstract (Arabic)
ملخص البحث
تحديات ارتفاع التكاليف والمنافسة. بناء على ذلك : تمتاز صناعة الإنشاءات بأنها ذات طبيعة معقدة وتواجه الغرضكان الغرض من هذا البحث دراسة عوامل النجاح وعلاقتها بالأداء في مشاريع الإنشاءات العامة. وقد تم تحقيق هذا
( تحديد وتقييم مؤشرات الأداء المفتاحية لمشاريع 1الغرض عن طريق ثلاثة أهداف من خلال البحث وهي: ( تقييم العلاقة بين 3( دراسة عوامل النجاح الحرجة التي تؤثر على مشاريع الإنشاءات العامة و 2لعامة، الإنشاءات ا
مؤشرات الأداء المفتاحية للمشاريع وعوامل النجاح الحرجة.وفق منهج استبانةومن خلالها تم تصميم الدراسة مجال المتعلقة ب: تم دراسات الأبحاث السابقة منهجية البحث
6( تحكيمه من خلال 1عن طريق الاستبانةاس الكمي في هذا البحث. وقد تم الوصول للنسخة النهائية من القي ةانوضوح وسهولة فهم وشمولية الاستب خبراء في صناعة الإنشاءات بفلسطين حيث استعين بهم لتنقيح وقياس مدى
فئة المستهدفة المتمثلة بمهندسين محترفين نسخة منه لل 20من خلال توزيع عدد للاستبانة( عمل دراسة تجريبية 2المعماري والذين يعملون كمدراء للمشاريع أو مصممين أو مشرفين ميدانيين وبناء عليه تم من تخصصات المدني أو
وتم استعادة مئتان وأربعة استبانةتحليل صدق وثبات الاستبانة. ومن ثم تم توزيع عدد ثلاثمائة واربعة وثمانون %. ومن أجل الخروج بنتائج ذات قيمة تم عمل تحليل للبيانات 71.35ها بنسبة استجابة بلغت قرابة وسبعون من
المحصلة بطرق التحليل الكمي مثل الوزن النسبي والتحليل العاملي ومعامل بيرسون وغيرها وذلك باستخدام برنامج .SPSS22التحليل الإحصائي
مؤشر أداء مفتاحي للمشاريع في هذه الدراسة. وقد تم استخدام التحليل 13تم تجميع وتنقيح عدد نتائج البحث:مؤشر اداء مفتاحي موزعة على ثلاث 11العاملي لتقليل عددها ووضعها ضمن مجموعات. وكنتيجة لذلك بقي عدد
( التكلفة والوقت الإجماليين 3روع و ( رضا وسمعة أطراف المش2( جودة المشروع وتأثيراته البيئية، 1مجموعات وهي مؤشر وكانت النتيجة أن أهم ثلاثة مؤشرات مفتاحية 13للمشروع. كما تم استخدام الإحصاء الوصفي لترتيب ال
( التكلفة الفعلية للمشروع مقارنة بموازنته المخططة و 2( مطابقة المشروع لمعايير ومواصفات الجودة، 1للأداء هي للمشروع مقارنة بالمقدرة. كما وأظهرت النتائج أن صناعة الإنشاءات في فلسطين تعاني من زيادة في ( المدة الفعلية3
التغيرية.الأوامر عدد وتكلفة التكلفة والمدة عن ما هو مخطط وارتفاع فيزيعها وفقا عامل نجاح حرج للمشروع. وقد تم تو 81كما أنه ومن خلال الدراسات السابقة وتحكيم الاستبيان تم تجميع
عامل نجاح حرج 52لدورة حياة المشروع لأربع مراحل. وقد تم استخدام التحليل العاملي الذي قلص عددها إلى هامة ومتوسط الوزن 81مجموعة. كما وأظهرت النتائج أن جميع عوامل النجاح الحرجة وعددها 14مقسمة على ظهر النتائج أن أهم خمس عوامل نجاح حرجة للمشروع هي %. وكنتيجة لترتيبها وفق الأهمية ت75.51النسبي لها
( التنسيق مع الجهات الرسمية من وزارات وبلديات وشركات... 2( دراسة جدوى المشروع وأولويته بالنسبة للمجتمع، 1الك ( متابع ةالم5( التزام مدير المشروع بتكلفة ووقت المشروع و 4( توثيق اللقاءات التحضيرية للعطاءات، 3إلخ،
للمشروع بشكل مستمر. كما وتظهر النتائج وجود علاقة دالة إحصائيا بين مؤشرات قياس الأداء المفتاحية وعوامل النجاح الحرجة للمشروع.
VIII
الدراسة تبحث في عنوان ومفاهيم تفتح الآفاق للبحث المستقبلي في هذا الجزء التطبيقات النظرية والعملية للبحث:محترفي قطاع الإنشاءات الذين يعملون في المؤسسات الحكومية وغير مدت على أراء إن الدراسة اعتالهام.
نما تم تعديل الحكومية. لم يتم وضع جميع ما تم جمعه من الدراسات السابقة في الاستبيان الذي هو أداة الدراسة وا موجهة للمالكين والاستشاريين وتنقيح المؤشرات وعوامل النجاح بما يتناسب مع فلسطين. والتوصيات الخاصة بالبحث
والمقاولين لتساعدهم على تحسين نجاح المشاريع. ويأمل الباحث أن يتم الاستفادة من مؤشرات قياس الأداء المفتاحية وعوامل النجاح الحرجة التي تم الخلوص لها بهذه الدراسة في تطوير مشاريع الإنشاءات بصفة عامة.
بحث إلى الجسم المعرفي حول مؤشرات قياس المشاريع المفتاحية وعوامل النجاح يضيف هذا ال قيمة واهمية البحث:الحرجة. حيث أن يكاد لا يوجد دراسات سابقة تبحث في علاقة مؤشرات قياس الأداء المفتاحية وعوامل النجاح
ال. كما أن هذه الحرجة على أساس دورة حياة المشروع. وتعد هذه الدراسة الأولى من نوعها في فلسطين بهذا المج الدراسة يمكن أن تعتبر مرجعا للباحثين في مجال الدراسة.
IX
Table of contents
The success factors that affecting public construction projects and their relation to key
performance indicators ............................................................................................................... I Dedication ..................................................................................................................................... III
Acknowledgement ......................................................................................................................... IV
Abstract ........................................................................................................................................... V
Abstract (Arabic) .......................................................................................................................... VII
Table of contents ........................................................................................................................... IX
List of abbreviations ..................................................................................................................... XII
List of Tables ............................................................................................................................... XIII
List of Figures .............................................................................................................................. XV
Chapter1: Introduction .................................................................................................................... 1
1.1 Background.......................................................................................................................... 1 1.2 The current status of the construction industry in Palestine ............................................... 1 1.3 Statement of the problem ..................................................................................................... 3 1.4 Research objectives and questions ...................................................................................... 4 1.4.1 Research objectives ............................................................................................................. 4 1.4.2 Research questions .............................................................................................................. 4 1.5 Limitations of the research .................................................................................................. 6 1.6 Research layout ................................................................................................................... 6
Chapter 2: Literature Review .......................................................................................................... 9
2.1 Countries classification ....................................................................................................... 9 2.2 Key performance indicators (KPI) .................................................................................... 10 2.2.1.1 Time and Cost ............................................................................................................. 11 2.2.1.2 Health and Safety ....................................................................................................... 12 2.2.1.3 Value and Profitability ............................................................................................... 12 2.2.1.4 Quality ........................................................................................................................ 12 2.2.1.5 Functionality .............................................................................................................. 13 2.2.1.6 Productivity ................................................................................................................ 13 2.2.1.7 Benchmarks ................................................................................................................ 14 2.2.1.8 Satisfaction ................................................................................................................. 14 2.2.1.9 Environmental sustainability ...................................................................................... 14 2.2.2 KPI on developing countries studies ................................................................................. 15 2.2.3 KPI on developed countries studies................................................................................... 17 2.3 Critical success factors ...................................................................................................... 22 2.3.1 Background........................................................................................................................ 22 2.3.2 CSFs in developing countries studies ................................................................................ 23
X
2.3.3 CSFs in developed countries studies ................................................................................. 32 2.4 Relationship between KPIs and CSFs ............................................................................... 47 2.4.1 KPIs and CSFs relationship on developing countries studies ........................................... 47 2.4.2 KPIs and CSFs relationship on developed countries studies ............................................ 51 2.5 Summary ............................................................................................................................ 52
3. Chapter3: Research Methodology ......................................................................................... 54
3.1 Research framework .......................................................................................................... 54 3.2 Research period ................................................................................................................. 57 3.3 Rationale of use quantative approach ............................................................................... 57 3.4 Research location .............................................................................................................. 58 3.5 Research population and sample ....................................................................................... 59 3.5.1 Research sample elements ................................................................................................. 59 3.5.2 Research population categories ........................................................................................ 59 3.5.3 Sample size ........................................................................................................................ 60 3.5.4 Sampling procedure ........................................................................................................... 62 3.6 Questionnaire Design ........................................................................................................ 63 3.6.1 General information .......................................................................................................... 64 3.6.2 Key performance indicators .............................................................................................. 64 3.6.3 Critical success factors ...................................................................................................... 65 3.7 Pilot study .......................................................................................................................... 67 3.7.1 Experts consultation .......................................................................................................... 67 3.7.2 Distributing questionnaire to limited group ...................................................................... 71 3.7.3 Statistical results of pilot study .......................................................................................... 71 3.7.3.1 Criterion and structural validity of the questionnaire ................................................ 71 3.7.3.2 Half Split Coefficient for reliability of the questionnaire ........................................... 71 3.7.3.3 Cronbach’s Alpha Coefficient for reliability of the questionnaire ............................. 72 3.8 Main questionnaire distribution ........................................................................................ 72 3.9 Quantitative data analysis using SPSS .............................................................................. 74 3.9.1 Reliability statistics ........................................................................................................... 74 3.9.1.1 Alpha-Cronbach coefficient........................................................................................ 75 3.9.1.2 Half Split Method ....................................................................................................... 75 3.9.2 Validity statistics ............................................................................................................... 76 3.9.2.1 Pearson correlation coefficients for criterion related validity ................................... 76 3.9.2.2 Pearson correlation coefficients for structure validity ............................................... 76 3.9.3 Kolmogorov-Smirnov Test of Normality ............................................................................ 76 3.9.4 Relative Importance Index (RII) ........................................................................................ 77 3.9.5 Parametric tests: ............................................................................................................... 78 3.9.5.1 One sample t test. ....................................................................................................... 78 3.9.5.2 One way ANOVA. ....................................................................................................... 78 3.9.6 Factor analysis .................................................................................................................. 78 3.9.6.1 Types of factor analysis .............................................................................................. 79 3.9.6.2 Methods of factoring .................................................................................................. 79 3.9.6.3 The distribution of data .............................................................................................. 79 3.9.6.4 Validity of sample size ................................................................................................ 80 3.9.6.5 Validity of correlation matrix (correlations between variables) ................................ 80 3.9.6.6 Kaiser-Meyer-Olkin (KMO) and Bartlett's Test as a measure of appropriateness of
Factor Analysis .......................................................................................................................... 80 3.9.6.7 Determining the number of factors ............................................................................. 81 3.9.6.8 Mathematical validity of factor analysis .................................................................... 81 3.1 Summary ............................................................................................................................ 82
XI
4. Chapter 4: Results and discussion ......................................................................................... 84
4.1 Scope of chapter ................................................................................................................ 84 4.2 Demographic survey of respondents ................................................................................. 85 4.3 Key performance indicators .............................................................................................. 86 4.3.1 Factor analysis results for KPIs ........................................................................................ 86 4.3.1.1 Appropriateness of factor analysis ............................................................................. 86 4.3.1.2 The extracted components .......................................................................................... 95 4.3.2 Ranking of KPIs of construction projects .......................................................................... 99 4.3.3 Public construction projects KPIs evaluation (actual versus planned performance) ..... 103 4.4 Critical success factors CSFs .......................................................................................... 106 4.4.1 Factor analysis results for CSFs ..................................................................................... 106 4.4.1.1 CSFs related to conceptualizing and preparation phase ......................................... 106 4.4.1.1.1 Appropriateness of factor analysis ....................................................................... 106 4.4.2 The extracted components ............................................................................................... 115 4.4.2.1 CSFs related to planning and designing phase ........................................................ 119 4.4.2.1.1 Appropriateness of factor analysis ....................................................................... 119 4.4.2.1.2 The extracted components .................................................................................... 131 4.4.2.2 CSFs related to tendering and contracting phase .................................................... 135 4.4.2.2.1 Appropriateness of factor analysis ....................................................................... 135 4.4.2.2.2 The extracted components .................................................................................... 146 4.4.2.3 CSFs related to implementation phase ..................................................................... 150 4.4.2.3.1 Appropriateness of factor analysis ....................................................................... 150 4.4.2.3.2 The extracted components .................................................................................... 162 4.4.2.4 Summary of factor analysis for CSFs ....................................................................... 168 4.4.3 Ranking of CSFs which affect public construction projects ............................................ 169 4.5 KPIs and CSFs relationship ............................................................................................ 173 4.6 Differences among respondents toward the analysis of CSFs and KPIs on Palestine .... 175 4.7 Summary of results .......................................................................................................... 180
5. Chapter 5: Conclusions and recommendations ................................................................... 183
References ................................................................................................................................... 190
Appendix I: Literature reviews summary tables .......................................................................... 201
Appendix II: Questionnaire (English) ......................................................................................... 237
Appendix III: Questionnaire (Arabic) ......................................................................................... 245
Appendix IV: Criterion and structural validity of the questionnaire ........................................... 253
Appendix V: Summary of selected and omitted KPIs and CSFs ................................................ 257
Appendix VI: RII, means, SD and rank of CSFs......................................................................... 284
XII
List of abbreviations
Abbreviation The Interpretation Of Abbreviation
GDP Gross Domestic Product
PCBS Palestinian Central Bureau Of Statistics
KPIs Key Performance Indicators
CSFs Critical Success Factors
UN United Nations
NPV Net Present Value
PSI Project Success Index
MHBPs Mass House Building Projects
SEM Structural Equation Model
UK United Kingdom
PPP Public Private Partnership
CPMSF Critical Project Management Success Factors
COMs Comprehension, Competence, Commitment, And Communication
AHP Analytical Hierarchical Method
USA United States Of America
SPSS Statistical Package For Social Science
NGOs Non-Governmental Organizations
MPWH Ministry Of Public Works And Housing
MOHE Ministry Of Education
MOLG Ministry Of Local Government
UNRWA United Nations Relief And Works Agency Of Palestinian Refugees
UNDP United Nations Development Programme
IUG Islamic University Of Gaza
Cα Cronbach’s Coefficient Alpha
RII Relative Important Index ()
ANOVA Analysis Of Variance One Way
r Pearson Correlation Coefficient
EFA Exploratory Factor Analysis
CFA Confirmatory Factor Analysis
PCA Principal Component Analysis
KMO Kaiser-Meyer-Olkin
N Sample Size
DF Degree Of Freedom
XIII
List of Tables
Table 2. 1: Developed and developing countries classification ...................................................... 9
Table 2. 2: Summary of literature review KPIs ............................................................................. 19
Table 2. 3: Summary of CSFs ....................................................................................................... 37
Table 3. 1: Research methods for previous studies ....................................................................... 58
Table 3. 2: Sample size for each of the research population categories ....................................... 63
Table 3. 3: Detailed information for the consulted experts ........................................................... 69
Table 3. 4: Questionnaire review notes gathered from experts .................................................... 69
Table3. 5: Split-Half Coefficient method ....................................................................................... 72
Table 3. 6: Reliability Cronbach's Alpha method ......................................................................... 72
Table 3. 7: Summary of factors and indicators selected and omitted ........................................... 73
Table 3. 8: Kolmogorov-Smirnov test of normality ....................................................................... 77
Table 4. 1: Demographic survey of respondents ........................................................................... 85
Table 4. 2: KMO and Bartlett's Test for KPIs ............................................................................... 88
Table 4. 3:Correlations between items of KPIs ............................................................................. 89
Table 4. 4: Communalities of KPIs ............................................................................................... 90
Table 4. 5: Total variance Explained of KPIs ............................................................................... 91
Table 4. 6: Factor loadings for a three-component model of key performance indicators KPI's . 94
Table 4. 7: Means and test values for “key performance indicators KPI's of projects”- Degree of
importance ................................................................................................................................... 100
Table 4. 8: Means and test values for “key performance indicators KPI's of projects”-
performance evaluation of organization projects ....................................................................... 105
Table 4. 9: KMO and Bartlett's Test for CSFs of conceptualizing and preparation phase .......... 108
Table 4. 10: Correlations between items of CSFs of conceptualizing and preparation phase ... 109
Table 4. 11: Communalities of CSFs of conceptualizing and preparation phase ....................... 110
Table 4. 12: Total variance Explained of CSFs of conceptualizing and preparation phase ....... 111
Table 4. 13: Summary of remaining and removed CSFs in conceptualizing and preparation phase
as a result of factor analysis runs................................................................................................ 113
Table 4. 14: Factor loadings for a three-component model CSFs of conceptualizing and
preparation phase ........................................................................................................................ 115
Table 4. 15: KMO and Bartlett's Test for CSFs of planning and designing phase ..................... 121
Table 4. 16: Correlations between items of CSFs of planning and designing phase .................. 123
XIV
Table 4. 17: Communalities of CSFs of planning and designing phase of first and final runs ... 124
Table 4. 18: Total variance Explained of CSFs of planning and designing phase ..................... 126
Table 4. 19: Summary of remaining and removed CSFs in planning and designing phase as a
result of factor analysis runs ....................................................................................................... 128
Table 4. 20: Factor loadings for a three-component model CSFs of planning and designing phase
..................................................................................................................................................... 130
Table 4. 21: KMO and Bartlett's Test for CSFs of tendering and contracting phase ................. 137
Table 4. 22: Correlations between items of CSFs of tendering and contracting phase .............. 138
Table 4. 23: Communalities of CSFs of tendering and contracting phase of first and final runs 139
Table 4. 24: Total variance Explained of CSFs of tendering and contracting phase ................. 141
Table 4. 25: Summary of remaining and removed CSFs in tendering and contracting phase as a
result of factor analysis runs ....................................................................................................... 143
Table 4. 26: Factor loadings for a three-component model CSFs of planning and designing phase
..................................................................................................................................................... 145
Table 4. 27: KMO and Bartlett's Test for CSFs of implementation phase .................................. 152
Table 4. 28: Correlations between items of CSFs of implementation phase ............................... 153
Table 4.29: Communalities of CSFs of implementation phase of first and final runs ................. 155
Table 4. 30: Total variance Explained of CSFs of implementation phase .................................. 158
Table 4. 31: Factor loadings for a five-component model CSFs of implementation phase ........ 161
Table 4. 32: Factor analysis summary of CSFs .......................................................................... 168
Table 4. 33: Correlation coefficient between CSFs and the degree of importance of KPIs ....... 175
Table 4. 34: Independent Samples T-test of the fields and their p-values for Place of resident . 176
Table 4. 35: ANOVA test of the fields and their p-values for organization type ......................... 177
Table 4. 36: ANOVA test of the fields and their p-values for projects size ................................. 179
Table 4. 37: ANOVA test of the fields and their p-values for years of experience in the
construction industry ................................................................................................................... 180
Table A 1: Summary of KPIs researches ..................................................................................... 202
Table A 2: Summary of CSFs researches .................................................................................... 209
Table A 3: Summary of KPIs and CSFs relationship researches ................................................ 227
Table A 4: Internal validity of the questionnaire ........................................................................ 254
Table A 5: Summary of selected KPIs ......................................................................................... 258
Table A 6: Summary of selected and modified CSFs ................................................................... 263
Table A 7: RII, means, SD and ranks of CSFs ............................................................................ 285
XV
List of Figures
Figure 3. 1: Framework of the research methodology ................................................................... 56 Figure 4. 1: The outline of data analysis and discussion chapter ................................................. 84
Figure 4. 2: Scree Plot for key performance indicators KPI's of projects .................................... 92
Figure 4. 3: Final components extracted from factor analysis for KPIs....................................... 93
Figure 4. 4: RII of KPI's (KPI 1 to KPI 13) ................................................................................ 101
Figure 4. 5: Scree Plot for CSFs of conceptualizing and preparation phase ............................. 112
Figure 4. 6: Final components extracted from factor analysis for CSFs in conceptualizing and
preparation phase ........................................................................................................................ 114
Figure 4. 7: Scree Plot for CSFs of planning and designing phase ............................................ 127
Figure 4. 8: Final components extracted from factor analysis for CSFs in planning and designing
phase ............................................................................................................................................ 129
Figure 4. 9: Scree Plot for CSFs of tendering and contracting phase ........................................ 142
Figure 4. 10: Final components extracted from factor analysis for CSFs in tendering and
contracting phase ........................................................................................................................ 144
Figure 4. 11: Scree Plot for CSFs of implementation phase ....................................................... 159
Figure 4. 12: Final components extracted from factor analysis for CSFs in phase 4................. 160
Figure 4. 17: The RII of the importance KPIs as evaluated by respondents ............................... 181
Figure 4. 18: The RII of the importance CSFs as evaluated by respondents .............................. 181
1
Chapter 1
Introduction
1
Chapter1: Introduction
This chapter presents a general introduction to the research which introduce background about
the construction industry in developing countries in general and especially in Palestine. It also
provide problem statement, research objectives, research questions and hypothesis, research
limitations and an overview of chapters.
1.1 Background
Construction makes a significant contribution to national economy, it creates employment
(especially for the least skilled members of society), it plays a role in the development and
transfer of technology, it creates many opportunities for enterprises, and it contributes directly to
improving quality of life of users of its products (Bourne et al, 2002). Additionally, construction
projects are growing larger and more complicated (Toor and Ogunlana 2008). Construction is
considered to be one of the most human actions that consumes resources and affects the
environment, not only through the construction process but also during lifetime of structures and
buildings (Salameh,2012).
Most construction projects in developing countries are public projects which directed by
government. Public sector projects involve a multitude of stakeholders ranging from the local
municipality to the affected community and even political parties with divergent interests
(Garbharran et al, 2012). In developed countries construction industry faces many challenges.
These challenges including increased competition, more exacting quality standards,
globalization, rapid development of new technologies and increased various risks (Chen and
Chen ,2007).
1.2 The current status of the construction industry in Palestine
Local construction industry is one of the main economic engine sectors, supporting the
Palestinian national economy (Enshassi et al, 2009a). It provides significant improvement in the
overall Gross domestic product GDP of the local economy, and contributes to the improvement
of the quality of life by providing the required infrastructure such as schools, hospitals, roads and
other basic facilities. Therefore, stability, development and growth of the construction industry
2
are critical for the local economy (Enshassi and Ayyash, 2014). Building construction is one of
the pioneer sectors that has achieved high growth rates during late 1994s and early 2015s and has
played a crucial role in absorbing gradual injections into the Palestinian labour force (Enshassi et
al, 2009b). As per the Palestinian Central Bureau of Statistics (PCBS), 15.3% of the employed
persons in the West Bank and Gaza Strip work in the construction industry in 2014. Also, the
construction industry contributed 10.1% of the Palestinians GDP (PCBS, 2015a). There were
8,023 individuals employed in this sector in 2014. The value of output of enterprises in the
construction sector was USD 596.3 million; intermediate consumption totaled USD 285.7
million; and the value added was USD 310.6 million in 2014 (PCBS, 2015b).
There are many challenges affect local construction industry like lack of funding, the dependence
on funding and implementation of aid from donor countries, weak infrastructure, lack of
management, security issues related to political and economic instability in Palestine (Najmi,
2011). The main challenge is that Palestinian construction sector depends on Israel for energy,
communications, raw materials and exports so the closure of border crossings imposed by Israel
has left grave impacts on this sector (Enshassi and Ayyash, 2014).
Palestinian construction sector suffers from cost problems. Cost problems Dealing with
unforeseen costs is usually a problem for construction project parties and is the basic reason of
the failure of many projects. Risks and uncertainty are the main causes of unforeseen costs in
construction projects because these may cause cost overrun and losses for construction parties
(Enshassi and Ayyash, 2014).
Safety and quality are not widely recognized as inherent characteristic of success for Palestinian
construction projects (Enshassi et al, 2009c). The key players in the Palestinian construction
industry do not adopt safe working practices for several reasons including that: employers and
employees are unwilling to spend or invest in safety measures, equipment or practices; hazards
are considered a necessary part and consequence of construction; employees cannot afford to
purchase their own safety equipment (Enshassi et al, 2008). Accidents are happening on
construction projects in Palestine with contributing factors varying between falls, shocks, and
others particularly due to the increase in the number of projects implemented accompanied with
carelessness for safety (Enshassi et al, 2009c).
Variation orders also consider as basic problem in Palestinian construction industry. The
frequent and continuous closure of borders crossing leads to severe shortage of construction
3
materials. Many projects are either on hold or subjected to major variations due to shortage of
construction materials (Enshassi et al, 2007). Also many projects experience extensive delays
and thereby exceed initial time and cost estimates. This problem is more evident in the traditional
or adversarial type of contracts in which the contract is awarded to the lowest bidder which is the
strategy in the majority of public projects in developing countries including Palestine.
1.3 Statement of the problem
Every construction project is unique and comprises of unique complexities and risks across
many issues throughout the construction process (Adnan et al, 2011). A construction project
proceed through stages of concept, scheme design, bidding, contracting, construction, service
and maintenance. The main participants and stakeholders differ among stages, as does the related
professional know-how, technologies and experience (Meng, 2012). Increasing complexity in
design and involvement of multitude of stakeholders in modern construction projects, add further
challenges to deliver the project successfully (Adnan et al, 2011).
In practice poor performance , such as time delays and cost overruns, are common in
construction projects and the reasons behind these problems have attracted the attention of
construction practitioners and researchers (Meng, 2012). In palestine, many local construction
projects reported poor performance due to many evidential project-specific factors such as:
unavailability of materials; excessive amendments of design and drawings; poor
coordination among participants, ineffective monitoring and feedback, lack of project
leadership skills and political situation (Enshassi et al, 2009b).The importance of specifying the
factors which affect the performance needed to improve the performance of the construction
industry has now been recognized in several countries at various levels. Underlying relationships
among the factors that contribute to project success can provide important insights for success
(Cserháti and Szabó, 2014). Also Identification of success factors can help in selection of project
team members, identification of their development needs, forecast of performance level of a
project before it commences and help the firms to decide their strategic standing on the project
(Toor and Ogunlana, 2008). Therefore, this research will be conducted to start paying more
attention to the success factors and their relation to key performance indicators.
4
1.4 Research objectives and questions
The basic research aim is to investigate the success factors that affecting public construction
projects and their relation to key performance indicators in Palestine. The research will thus
explore the present situation of construction projects performance and identify the critical
success factors which affect these projects.
1.4.1 Research objectives
This study was conducted to accomplish the following objectives:
1. To identify and evaluate the key performance indicators (KPIs) of public construction
projects.
2. To investigate the critical success factors CSFs affecting the public construction projects.
3. To evaluate the relationship between CSFs and KPIs in the public construction projects.
1.4.2 Research questions
Question 1: What is the ranking of KPIs according to their degree of importance, and the
evaluation of actual KPIs versus planned?
Question 2: What is the ranking of CSFs according to their degree of importance?
To answer this question, a structured questionnaire is conducted to investigate the suggestions
and expectations of the relevant parties.
Question 3: Is there a significant relationship between CSFs and the degree of importance of
KPIs on Palestine?
Question 4: Are their differences among respondents toward the analysis of CSFs and KPIs due
to place of resident, organization type, projects size and years of experience in the public
construction industry of Palestine?
The questions will be answered using a structured questionnaire and by analyzing the collected
data and by testing the following hypothesis:
5
Hypothesis 1 "H0": Null hypothesis: There is no significant statistical relationship at level (α>=
0.05) in respondents evaluations for CSFs affected public construction projects and the degree of
importance of KPIs in Palestine.
Hypothesis 1 "H1": Alternative hypothesis: There is significant statistical relationship at level
(α>= 0.05) in respondents evaluations for CSFs affected public construction projects and the
degree of importance of KPIs in Palestine.
Hypothesis 2 "H0": Null hypothesis: There is no significant statistical relationship at level (α>=
0.05) in respondents evaluations for CSFs affected public construction projects and the degree of
importance of KPIs in Gaza Strip.
Hypothesis 2 "H1": Alternative hypothesis: There is significant statistical relationship at level
(α>= 0.05) in respondents evaluations for CSFs affected public construction projects and the
degree of importance of KPIs in Gaza Strip.
Hypothesis 3 "H0": Null hypothesis: There is no significant statistical relationship at level (α>=
0.05) in respondents evaluations for CSFs affected public construction projects and the degree of
importance of KPIs in West Bank.
Hypothesis 3 "H1": alternative hypothesis: There is significant statistical relationship at level
(α>= 0.05) in respondents evaluations for CSFs affected public construction projects and the
degree of importance of KPIs in West Bank.
The question will be answered using a structured questionnaire and by testing the following
hypothesis:
Hypothesis 4 "H0": Null hypothesis: There is no differences at level (α>= 0.05) in respondents
evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to place of resident.
Hypothesis 4 "H1": Alternative hypothesis: There is differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to place of
resident.
Hypothesis 5 "H0": Null hypothesis: There is no differences at level (α>= 0.05) in respondents
evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to respondents
organizations type.
6
Hypothesis 5 "H1": Alternative hypothesis: There is differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
respondents organizations type.
Hypothesis 6 "H0": Null hypothesis: There is no differences at level (α>= 0.05) in respondents
evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to respondents
organizations project size.
Hypothesis 6 "H1": Alternative hypothesis: There is differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
respondents organizations project size.
1.5 Limitations of the research
1. The research is limited to the public construction projects of Palestine.
2. The research is based on quantitative analysis including questionnaire only.
3. The research sample targeted the construction experts working in governmental
organizations, nongovernmental organizations and consultant offices.
1.6 Research layout
The thesis consists of five chapters as follows:
Chapter 1: Introduction: This chapter contains a general introduction to the subject of
the thesis. It describes research background, statement of the problem, research aim and
objectives, research limitations and research layout.
Chapter 2: Literature review: This chapter discusses general concepts of success criteria
which considered as key performance indicators and critical success factors and also
mentioned the previous studies in this field.
Chapter 3: Methodology: This chapter defines the process of the methodology that will
be applied through the research.
Chapter 4: Results and Discussion: This chapter presents the results of the research and
discusses them in details.
Chapter 5: Conclusions and Recommendations: This chapter states the conclusions and
recommendations for the research.
References.
7
Appendices.
Chapter 2
Literature Review
9
Chapter 2: Literature Review
This chapter composed of four sections. The first section described general concepts of
key performance indicators and also reported the previous studies in this field. The
second section described previous studies about the critical success factors in
construction of both developing and non-developing countries and their categorization.
The third section stated studies which described the relationship between KPIs and the
success factors. The forth section summarized the literature review chapter.
2.1 Countries classification
The classification of developing and developed countries followed in this research
according to United Nations classification which published on their site in 2013 (UN,
2013). Table 2.1 indicated the developed countries and the developing countries.
Table 2. 1: Developed and developing countries classification
Developed countries Developing countries
Austria
Belgium
Denmark
Finland
France
Germany
Greece
Ireland
Italy
Luxembourg
Netherlands
Portugal
Spain
Sweden
United Kingdom
Bulgaria
Cyprus
Czech Republic
Estonia
Hungary
Latvia
Lithuania
Malta
Poland
Algeria
Egypt
Libya
Morocco
Tunisia
Cameroon
Central African Republic
Chad
Congo
Equatorial Guinea
Gabon
Sao Tome and Prinicipe
Burundi
Comoros
Democratic Republic of the Congo
Djibouti
Eritrea
Ethiopia
Kenya
Madagascar
Rwanda
Somalia
Sudan
Uganda
Ghana
Guinea
Guinea-Bissau
Liberia
Mali
Mauritania
Niger
Nigeria
Senegal
Sierra Leone
Togo
Barbados
China
Hong Kong SAR
Indonesia
Malaysia
Myanmar
Papua New Guinea
Philippines
Republic of Korea
Singapore
Taiwan Province of
China
Thailand
Turkey
United Arab
Emirates
Yemen
Cuba
Dominican Republic
Guyana
Haiti
Jamaica
Trinidad and Tobago
Costa Rica
El Salvador
Guatemala
Honduras
Mexico
Nicaragua
Panama
Argentina
Bolivia
(Plurinational State)
Brazil
Chile
Colombia
Ecuador
10
Table 2. 1: Developed and developing countries classification
Developed countries Developing countries
Romania
Slovakia
Slovenia
Iceland
Norway
Switzerland
Australia
Canada
Japan
New Zealand
Canada
Japan
France
Germany
Italy
United Kingdom
United States
United Republic of Tanzania
Angola
Botswana
Lesotho
Malawi
Mauritius
Mozambique
Namibia
South Africa
Zambia
Zimbabwe
Brunei Darussalam
Benin
Burkina Faso
Cape Verde
Côte d’Ivoire
Gambia
Viet Nam
Bangladesh
India
Iran (Islamic Republic
of )
Nepal
Pakistan
Sri Lanka
Bahrain
Iraq
Jordan
Kuwait
Lebanon
Oman
Qatar
Saudi Arabia
Syrian Arab
Paraguay
Peru
Uruguay
Venezuela
(Bolivarian
Republic)
2.2 Key performance indicators (KPI)
This section provides a background through pre studies about KPIs. key performance
indicators are measurable indicators that demonstrate the level of achievement in a
project. KPIs provide information to the decision makers to measure performance and to
compare them with the intended outputs, outcomes, goals, and objectives, and were
chosen to reflect the success criteria of a project (Omran and Mamat, 2011). The purpose
of the KPIs is to enable measurement of project and organizational performance. The
process of developing KPIs involved the following issues (Chan and Chan, 2004)
1. KPIs are general indicators of performance that focus on critical aspects of
outputs or outcomes.
2. Only a limited, manageable number of KPIs is maintainable for regular use.
Having too many (and too complex) KPIs can be time- and resource-consuming.
3. The systematic use of KPIs is essential as the value of KPIs is almost completely
derived from their consistent use over a number of projects.
4. Data collection must be made as simple as possible.
5. A large sample size is required to reduce the impact of project specific variables.
Therefore, KPIs should be designed to be used on every building project.
11
6. For performance measurement to be effective, measures or indicators must be
accepted, understood and owned across the organization.
7. KPIs will need to evolve and it is likely that a set of KPIs will be subject to
change and refinement.
8. Graphic displays of KPIs need to be simple in design, easy to update and
accessible
Different key performance indicators used by different researchers and each indicator
describes project performance on different way. The following indicators were the most
common KPIs had been used in previous literature studies:
2.2.1.1 Time and Cost
Time performance is as important to all construction parties as cost performance
(Meeampol and Ogunlana, 2006). Completing a project in a predictable manner, on time,
within schedule is an important KPI ( LI et al, 2012). Time is defined as the degree to
which the general conditions promote the completion of a project within the allocated
duration (Chan et al, 2002; Lam et al, 2007). It can be measured by time overrun,
construction time, and speed of construction (Chan et al, 2002). Cost is defined as the
degree to which the general conditions promote the completion of a project within the
estimated budget (Chan et al, 2002; Omran and Mamat, 2011; Lam et al, 2007). It can be
measured by cost overrun and unit cost (Chan et al, 2002). Specifically in terms of unit
cost, percentage of net variation over the final cost (Chan and Chan, 2004). Chou et al
(2013) considered the cost refers to the budget.
Cost performance is the most important indicator of project success used by all parties
(LI et al, 2012). It presents firm’s profitability, productivity and is always used to
measure project performance against the estimated target (Meeampol and Ogunlana,
2006; Memon et al, 2013). Time and cost are measured in pre-construction and
construction phases because for design/build projects, price and time certainty are
essential to success, which should be evaluated early at the pre-tendering phase. They
should also be closely monitored during construction to avoid subsequent delays (Chan et
al, 2002). construction time usually interrelates and functions with the actual cost because
12
increasing construction time always results in additional cost to the whole project
(Meeampol and Ogunlana, 2006; Ahsan and Gunawan, 2010).
2.2.1.2 Health and Safety
Health and safety are defined as the degree to which the general conditions promote the
completion of a project without major accidents of injuries (Chan et al, 2002). It is well
known that construction projects have many work-related accidents and injuries and a
successful safety program can be measured in terms of no injury to people, no damage to
equipment, machines and tools, no damage to environment, no loss of market
competition, no damage to company image or brand-name, and increased productivities
(Aksorn and Hadikusumo, 2008). The measurement of safety is mainly focused on the
construction period as most accidents occur during this stage (Alzahrani and Emsley,
2013).With the increasing complexity of construction projects and the rapid increase of
construction activities, construction safety has become a big concern because workers
injuries cause tremendous losses (Ali et al, 2013).
2.2.1.3 Value and Profitability
profitability is also considered as one of the most important key performance indicators
(Ali et al, 2013). Profitability measures financial success of the project. Nowadays,
competition is increasing and firms are aware that the project must be properly managed
to be profitable (Chan et al, 2002). Value is evaluating satisfaction of owner’s needs in a
global sense. It includes the realization for the owner of quantity produced, operational
and maintenance costs, and flexibility. It can be considered as “business benefit” derived
from the completed project (Chan and Chan, 2004). According to Chan and Chan (2004)
The most common measure of financial achievement is net present value (NPV).
2.2.1.4 Quality
Quality is to be assessed in both preconstruction and construction phases as it forms the
‘‘iron triangle’’ with time and cost that is fundamental KPI of the project (Chan et al,
2002). Final product quality and process quality that meet and exceed owner
requirements are an important part of project success ( LI et al, 2012). Sanvido et al
(1992) defined the quality defined as the totality of features, attributes, and characteristics
13
of a facility, product, process, component, service, or workmanship that bear on its ability
to satisfy a given need: fitness for purpose. Chan et al (2002) defined quality as the
degree to which the general conditions promote meeting of the project’s established
requirements of materials and workmanship. Another close definition of quality used by
Lam et al (2007) and Ling and Bui (2010) was that quality is the output quality of the
service rendered or work done from the technical and workmanship aspects. Chou et al
(2013) considered the quality as performance outcome.
2.2.1.5 Functionality
This criterion correlates with expectations of project participant and can best be measured
by the degree of conformance to all technical performance specifications. Both financial
and technical aspects implemented to technical specifications should be considered, to
achieve the ‘‘fitness for purpose’’ objective (Chan et al, 2002). Quality, technical
performance, and functionality are closely related and are considered as important KPIs
to the owner, designer, and contractor (Chan and Chan, 2004). The requirements of
technical performance are normally established in specifications and its performance is
best measured by the degree of variations from those listed in specifications (Lam et al,
2007).
2.2.1.6 Productivity
Productivity is universally accepted as KPI and it is the main key to the cost-effectiveness
of projects. It refers to the amount of resource input to complete a given task and it is
usually assessed on a ranked basis (Chan et al, 2002). Shehata and El-Gohary (2012)
considered that proper management of resources in construction projects can yield
substantial savings in time and cost. In order to improve project performance, they
suggested that variability in labor productivity should be reduced with regard to available
workload and capacity (work hours). These variations that affects labor productivity and
is defined as the time difference between what was planned and what occurred in terms
of task starting times and duration.
14
2.2.1.7 Benchmarks
Benchmarking is currently considered as one of the most effective approaches to help a
company to improve its performance and they considered as the search for “best practice”
(Lam et al, 2007). Benchmarking can be defined as a process of continuously measuring
and comparing an organization’s business process against business leaders anywhere in
the world to gain information which will help the organization to take action to improve
its performance (Shehata and El-Gohary, 2012). Another definition of bench marking
was “A systematic process of measuring one’s performance against results from
recognized leaders for the purpose of determining best practices that lead to superior
performance when adapted and implemented” Ali et al, 2013). Construction companies
can benchmark their performance to enable them to identify strengths and weaknesses
and improve their performance (Lam et al, 2007).
2.2.1.8 Satisfaction
Satisfaction describes level of ‘‘happiness’’ of people affected by a project. Such people
include key project participants, namely the client, architect, contractor, various
subcontractors, surveyors and engineers, end-users, and third parties (Chan et al, 2002;
Lam et al, 2007). Chan and Chan (2004) divided satisfaction to (1) user expectation and
satisfaction and (2) Participants’ satisfaction. user satisfaction describes the level of
achievement of the expectations in a project ( LI et al, 2012). Success for a given project
participant is defined as the degree to which project goals and expectations are met, these
goals and expectations may include technical, financial, educational, social, and
professional aspects (Sanvido et al, 1992). Satisfaction as KPI have been found to be
better than purely financial criteria that can be turned into corrective managerial decisions
and actions (Lehtiranta et al, 2012)
2.2.1.9 Environmental sustainability
Impacts of a construction project on the environment are notoriously negative (Chan et
al, 2002). The generation of construction waste is one of the major negative impacts from
a construction project on the environment, which can be measured by the difference
15
between the amount of the total delivery of materials to the site and the amount of work
completed (Lam et al, 2007).
2.2.2 KPI on developing countries studies
Shenhar et al (2001) conducted study to develop a multidimensional framework for
assessing project KPIs. Shenhar et al (2001) grouped KPIs into: (1) project efficiency, (2)
impact on the customer, (3) direct business and organizational success, and (4) preparing
for the future. They suggested these dimensions should be addressed during the project’s
definition, planning, and execution phases. They also concerned with customer needs,
competitive advantage, and future market success, and rather than sticking to the initial
plan, they keep making adjustments that will create better business outcomes.
In Hong Kong done by Chan et al (2002) aimed to establish criteria for project success
for a design/build project in construction. They conducted a comprehensive review of the
literature over 10 years in order to make framework for success criteria. They classified
KPIs into objective measures which were time, cost, profitability, health and safety and
subjective measures which were quality, productivity, satisfaction, functionality,
technical performance and environmental sustainability.
Another studies in Hong Kong held by Chan and Chan (2004) aimed to develop a set of
key performance indicators (KPIs) for measuring construction success. They measured a
set of key performance indicators (KPIs), both objectively and subjectively through a
comprehensive literature review. Their study showed that the cost quality and time are in
general good indicators of the performance of construction projects and other measures,
such as safety, functionality and satisfaction, etc., were important too. They also
furnished to project managers, clients and other project stakeholders useful information to
implement a project successfully.
In Taiwan Ko and Cheng (2007) endeavored to dynamically predict project success. They
proposed an evolutionary project success prediction model. Their model is developed
based on a hybrid approach that fuses genetic algorithms, fuzzy logic, and neural
networks. They used KPIs which were actual design complete, actual owner
expenditures, cost of contractor project commitments, cost of owner project
16
commitments, actual owner effort hours, recordable incident rate by period, actual
overtime work, cost of change orders, quantity of change orders and days lost to weather
gross working days.
In Hong Kong Lam et al (2007) aimed to develop a project success index (PSI) to
benchmark the performance of design-build projects from a number KPIs. They claimed
that a construction project is mostly initiated by the needs of the client. In order to satisfy
the client’s requirements in terms of time, cost and quality, various procurement methods
are used to increase the chance of success for the complex sequence of activities one of
them is design build strategy. They formulated an equation to benchmark project success
and their findings showed that time, cost, quality and functionality should be the
principal success criteria for design and built projects.
In Ghana Ahadzie et al (2008) conducted a research to address what constitutes the
determinants of success in mass house building projects (MHBPs). They used A
questionnaire survey and they classified the KPIs into four main clusters, namely
environmental impact, customer’s satisfaction, quality and cost, and time .
In Republic of Korea Cho et al (2009) conducted study to analyze the overall relationship
between project performance and a project’s characteristics. They employed factor
analysis method and a structural equation model (SEM) on quantitative data from actual
case studies to analyze relations. They concluded that the quantitative KPIs measured
construction were cost (i.e., award rate, unit cost, cost growth, etc.) and construction time
(i.e., construction speed, delivery speed, schedule growth, etc.), while the qualitative
KPIs evaluated the quality (i.e., turnover quality, system quality, etc.), and the owner’s
satisfaction.
In Vietnam Ling and Bui (2010) examined the factors that lead to successful outcomes in
construction projects. They used case studies technique and they used the following KPIs
as a sign of successful outcomes:
1. Project delivery which determined by the budget performance, schedule
performance, and quality which defined on the research as “The output quality of
the service rendered or work done from the technical and workmanship aspects”.
17
2. Organizational level competency which determined by owner satisfaction.
3. Profitability.
Another study in Malaysia by Al-Tmeemy et al (2011) aimed to propose a framework to
categorize project success for building projects in Malaysia from the contractors'
perspective. They divided the KPIs into three dimensions which were project
management success, product success and market success. These dimensions included
thirteen KPIs which were cost, time, quality, safety, achieving scope, customer
satisfaction, technical specifications, functional requirements, market share, competitive
advantage, reputation, revenue and profits , and benefit to stakeholder.
In Saudi Arabia Ali et al (2013) conducted study to explore the most important KPIs for
measuring company performance as perceived by large building contractors working in
Saudi Arabia. They used A survey on a randomly selected sample of large construction
firms. They Figured out the most significant KPIs are profitability, quality of service and
work, growth, financial stability, cash flow, external customer satisfaction, safety,
business efficiency, market share, and effective-ness of planning.
2.2.3 KPI on developed countries studies
In the United Kingdom Atkinson (1999) investigated how to determine KPIs. He was the
first one who concluded that iron triangle (time, cost and quality) was not enough to
investigate project success. On his study he focused on project management KPIs. And
he found there were other criteria in addition to iron triangle criteria can be used to
evaluate project performance like information system, organization benefits and
stakeholder and community benefits.
In Annapolis Hughes et al (2004) investigated how experienced construction project
management personnel perceive KPIs, both objectively and subjectively. On their article
they developed a construction project success survey instrument to identify important
KPIs before the start of a project, and to evaluate the level of success achieved at project
completion. The measuring metrics include the objective such as, cost, schedule,
performance, and safety and subjective considerations. They suggest a method of
measuring subjective project success attributes that can ultimately lead to a successful
18
outcome of a project regardless of the values associated with the traditional objective
success attributes.
In UK also Bryde and Robinson (2005) aimed to report client versus contractor
perspectives on project KPIs. Their results showed that contractors put more emphasis on
minimizing project cost and duration, whilst clients put more emphasis on satisfying the
needs of other stakeholders. Also they found clients project management practice showed
no stronger focus on meeting stakeholder needs than contractor organizations.
Another study in United Kingdom by Ojiako et al (2008) aimed to develop a different
understanding of KPIs rather than time, cost and quality. Their data collection and
analysis was rooted in grounded theory (Glaser and Strauss, 1969; Strauss and Corbin,
1990). They conducted semi structured interviews and the study revealed that that it was
impossible to generate a universal checklist of criteria suitable for all projects. KPIs will
differ from project to project depending on a number of variables including size,
uniqueness, industry, complexity and the stakeholders involved. The authors suggested
that it is not enough to assume that time cost and quality are the correct project
deliverables but they must be discovered and quantified with an overall establishment of
a number of complex and inter-related project measurement criteria which the authors
would called “project performance”.
In Australia Yeung et al (2009) conducted an empirical study using Delphi survey
technique to formulate a model to assess the success of relationship-based construction
projects in terms of KPI. They conducted four rounds of Delphi survey questionnaires
and selected eight KPIs to evaluate the success of relationship-based projects which were
client’s satisfaction; cost performance; quality performance; time performance; effective
communications; safety performance; aesthetics (trust and respect); and innovation and
improvement.
The researcher derived 31 KPIs from the previous studies. Table 2.2 summarized KPIs
according to their references.
19
Table 2. 2: Summary of literature review KPIs
NO
. Key performance
indicators
Resources
Shen
har
et
al
(2001)
Chan
et
al
(2002)
Dvir
et
al
(2003)
Fri
mpong e
t al
(2003)
Dvir
and L
echle
r (2
004)
Chan
and C
han
(2004)
Chan
et
al
(2004a)
Hughes
et
al
(2004)
Bry
de
andR
obin
son (
2005)
Wan
g a
nd H
uan
g (
2006)
Sam
bas
ivan
and S
oon (
2007)
Ko a
nd C
hen
g (
2007)
Chen
and C
hen
(2007)
Lam
et
al
(2007)
Ahad
zie
et a
l (2
008)
Ensh
assi
et
al
(2009a)
Yeu
ng e
t al
(2009)
Cho e
t al
(2009)
Lin
g a
nd B
ui
(2010)
Ahsa
n a
nd G
unaw
an (
2010)
Yan
g e
t al
(2011)
Al-
Tm
eem
y e
t al.
(2011)
Sheh
ata
and E
l-G
ohar
y (
2012)
Men
g (
2012)
Ng e
t al
(2012)
LI
et a
l (2
012)
Chou e
t al
(2013)
Hw
ang e
t al
(2013)
Ali
et
al
(2013)
Alz
ahra
ni
and E
msl
ey (
2013)
Mir
and P
innin
gto
n (
2014)
Cse
rhát
i an
d S
zabó (
2014)
Ali
as e
t al
(2014)
Loca
tell
i et
al
(2014)
1 Schedule indicators
2 Cost indicators
3 Satisfying the
customers' needs
4 Meeting the technical
specification
5 Satisfying the needs of
stakeholders
(other than the
customer)
6 Quality of service and
work
7 Safety (accident rate)
8 Efficiency
9 Effectiveness of
planning
20
Table 2. 2: Summary of literature review KPIs
NO
. Key performance
indicators
Resources
Shen
har
et
al
(2001)
Chan
et
al
(2002)
Dvir
et
al
(2003)
Fri
mpong e
t al
(2003)
Dvir
and L
echle
r (2
004)
Chan
and C
han
(2004)
Chan
et
al
(2004a)
Hughes
et
al
(2004)
Bry
de
andR
obin
son (
2005)
Wan
g a
nd H
uan
g (
2006)
Sam
bas
ivan
and S
oon (
2007)
Ko a
nd C
hen
g (
2007)
Chen
and C
hen
(2007)
Lam
et
al
(2007)
Ahad
zie
et a
l (2
008)
Ensh
assi
et
al
(2009a)
Yeu
ng e
t al
(2009)
Cho e
t al
(2009)
Lin
g a
nd B
ui
(2010)
Ahsa
n a
nd G
unaw
an (
2010)
Yan
g e
t al
(2011)
Al-
Tm
eem
y e
t al.
(2011)
Sheh
ata
and E
l-G
ohar
y (
2012)
Men
g (
2012)
Ng e
t al
(2012)
LI
et a
l (2
012)
Chou e
t al
(2013)
Hw
ang e
t al
(2013)
Ali
et
al
(2013)
Alz
ahra
ni
and E
msl
ey (
2013)
Mir
and P
innin
gto
n (
2014)
Cse
rhát
i an
d S
zabó (
2014)
Ali
as e
t al
(2014)
Loca
tell
i et
al
(2014)
10 Profitability
11 Growth/ market share
12 Financial stability
13 Environmental impact
14 Disputes, arbitrations
and litigations
15 Impact on Long Term
Benefits
16 Functional
requirements
17 Reputation
“professional image”
18 Design team
satisfaction
19 Construction team’s
satisfaction
21
Table 2. 2: Summary of literature review KPIs
NO
. Key performance
indicators
Resources
Shen
har
et
al
(2001)
Chan
et
al
(2002)
Dvir
et
al
(2003)
Fri
mpong e
t al
(2003)
Dvir
and L
echle
r (2
004)
Chan
and C
han
(2004)
Chan
et
al
(2004a)
Hughes
et
al
(2004)
Bry
de
andR
obin
son (
2005)
Wan
g a
nd H
uan
g (
2006)
Sam
bas
ivan
and S
oon (
2007)
Ko a
nd C
hen
g (
2007)
Chen
and C
hen
(2007)
Lam
et
al
(2007)
Ahad
zie
et a
l (2
008)
Ensh
assi
et
al
(2009a)
Yeu
ng e
t al
(2009)
Cho e
t al
(2009)
Lin
g a
nd B
ui
(2010)
Ahsa
n a
nd G
unaw
an (
2010)
Yan
g e
t al
(2011)
Al-
Tm
eem
y e
t al.
(2011)
Sheh
ata
and E
l-G
ohar
y (
2012)
Men
g (
2012)
Ng e
t al
(2012)
LI
et a
l (2
012)
Chou e
t al
(2013)
Hw
ang e
t al
(2013)
Ali
et
al
(2013)
Alz
ahra
ni
and E
msl
ey (
2013)
Mir
and P
innin
gto
n (
2014)
Cse
rhát
i an
d S
zabó (
2014)
Ali
as e
t al
(2014)
Loca
tell
i et
al
(2014)
20 Productivity
21 Aesthetics
22 Risk
23 Human resources
24 communication
25 Procurement
26 Benchmarks
27 Cost of change orders
28 Quantity of change
orders
29 Pre-contract costs
30 Learning value
31 Overall performance
22
2.3 Critical success factors
2.3.1 Background
This section aimed to determine the critical success factors affecting construction
projects. Rubin and Seeling (1967) were the first ones who introduced the concept of
project success factors in and Rockart (1979) used the terminology critical success factors
(CSFs) for the first time (Toor, and Ogunlana, 2008; Yang et al., 2009 ). The factors that
predicate success were initially derived from the integrated building process model
developed at Penn State by Sanvido in 1990 (Sanvido et al, 1992). CSFs can be
defined as “areas, in which results, if they are satisfactory, will ensure successful
competitive performance for the organization” (Rockart, 1979 cited in Aksorn and
Hadikusumo 2008, p712). Another definition mentioned by Yang et al (2009) was “CSFs
those critical areas of managerial planning and action that must be practiced in order to
achieve effectiveness” or "CSFs are inputs to project management practice which can
lead directly or indirectly to project success and they encompasses many elements, which
have to be synchronized to ensure the project delivery on time" as described by Alias et
al (2014 p61).
Comprehensive success criteria must reflect different interests and views, which lead to a
multi-dimensional, multi-criteria approach (Dvir et al 2003). Successful to construction
project manager may or may not resonate the same way with the construction project
owner, project engineer, operator, or maintenance staff (Hughes et al 2004). From a
project management perspective, critical success factors (CSFs) are characteristics,
conditions, or variables that can have a significant impact on the success of the project
when properly sustained, maintained, or managed (Milosevic and Patanakul, 2005). An
architect may consider success in terms of aesthetic appearance, an engineer in terms of
technical competence, an accountant in terms of dollars spent under budget, a human
resources manager in terms of employee satisfaction and chief executive officers rate
their success in the stock market (Shenhar et al, 2001).
23
2.3.2 CSFs in developing countries studies
On this part the researcher will give general view for the previous studies which divided
into two kinds: 1) studies described CSFs and evaluated them and 2) studies categorized
CSFs.
Studies described CSFs and evaluated them
In Oman Hartman and Ashrafi (2004) conducted a study to develop the simple
measurable analytic realistic time bounded "SMART" project planning framework based
on research into causes of both project failure and success. They recognized that poor
project planning plays a major role as one of the significant causes of project failure.
They also concluded that good planning enabled creativity and supported both team
formulation and effectiveness. It brought out innovative ideas that led to cost or time
savings. They developed a framework presented a unified approach to project planning,
integrating both hard and soft aspects, enhancing current tools and techniques, and
improving the project planning process by providing internal validation.
In Hong Kong Chan et al (2004a) conducted a study to identify critical success factors
for partnering projects. In their study a set of 41 success factors was derived. The results
indicated that certain requirements must be met for partnering to succeed which were the
establishment and communication of a conflict resolution strategy, a willingness to share
resources among project participants, a clear definition of responsibilities, a commitment
to a win-win attitude, and regular monitoring of partnering process were believed to be
the significant underlying factors for partnering success.
In China Wang and Huang (2006) conducted a study to evaluate project success and to
what extent key project stakeholders performance correlates with project success. Their
results showed that the engineers use relation among the key stakeholders as the most
important criterion of project success, the stakeholder project performance positively
correlates with each other and project owners played the most important role in
determining project success.
24
In China Lu and Yuan et al (2010) conducted a study to identify the CSF’s in waste
management in construction projects of Shenzhen. They identified 18 CSFs and they
concluded that the most important CSF’s in Shenzhen were 7 factors namely (1)
regulations, (2) waste management system (3) awareness (4) building technologies, (5)
design changes, (6) research and development, and (7) vocational training.
In Malaysia Adnan et al (2011) aimed to determine the primary factors which support the
successful application of the design and build method. They found that client attributes
for the success of the Design and Built projects in public universities were the main
factors. These factors listed as developing a clear understanding of project scope, a clear
brief thorough assessment of the contractor’s proposal, a clear understanding of project
costs, fulfilling the end-user requirements, quality finish of the project, completion within
the time frame as well as the budget allocated.
In India Tabish and Jha (2011) studied success factors of public construction projects.
They claimed that achieving success in public construction projects is difficult because it
requires economy, efficiency, quality, fairness and transparency. They concluded that
identification of the success factors is considered the key to achieving success in these
projects. Authors identified 36 success attributes. Four success factors which were
‘awareness of and compliance with rules and regulations’, ‘effective partnering among
project participants’, ‘pre-project planning and clarity in scope’, and ‘external monitoring
and control’ were extracted by the application of factor analysis on 36 attributes
developed through a synthesis of empirical studies and opinions from industry
practitioners on public construction projects. The most important factor for overall
performance is found to be ‘awareness of and compliance with rules and regulations’.
Another study conducted in Malaysia by Abdul-Aziz and Kassim (2011) aimed to
examine the objectives, success and failure factors of housing public private partnership
PPP projects. They found that public agencies desired to fulfil an array of objectives
when adopting PPP, the most important factor was to enhance organizational reputation.
They also claimed that the most CSF that impact project success was action against errant
developers. And the factor which had the most influential on project which may lead to
project failure was absence of robust and clear agreement.
25
In South Korea also Yu and Kwon (2011) conducted a research to identify the critical
success factors (CSFs) for urban regeneration projects. They identified and confirmed 10
CSFs. They formulate a model and they concluded that the most CSF’s was minimization
of conflict between stakeholders.
In Taiwan Also Yang et al (2011) examined on their article the impact of teamwork on
project performance and they investigated the relationships among the project manager's
leadership style, teamwork, and project success. They concluded that increased in levels
of leadership may enhanced relationships among team members. The results also
indicated that teamwork exhibits statistically significant influence on project
performance.
In Taiwan Chen et al (2012) conducted a study to explore the success variables in
construction partnering and the relationships among these variables. Research results
showed that four successful factors (collaborative team culture, long-term quality
perspective, consistent objectives, and resource sharing) had a significant influence on
the success of construction partnering. Of the four factors, collaborative team culture and
consistent objectives had the highest correlation. Additionally, results indicated that good
cultural fit has the most influence on characterizing collaborative team culture,
commitment to continuous improvement had the highest influence in characterizing long-
term quality perspective, clear understanding had the highest influence in characterizing
consistent objectives, and availability of resource had the highest influence in
characterizing resource sharing.
Another research in Malaysia done by Ismail et al (2012) to study the management
factors contributing to successful implementation of industrialized building system IBS
projects from contractor point of view. They disclosed that good working collaboration,
effective communication channel and team member involvement during the design stage
are the top three most influential management -related factors towards the successful
implementation of IBS projects in Malaysia. The result reinforced that good coordination
between all parties play the main role towards successful implementation of IBS project.
26
In Nigeria Jagboro et al (2012) evaluated the contribution of construction professionals in
budgeting for infrastructure projects and its effect on the real cost of them. They
indicated that majority of projects budgeted for execution lack adequate technical
evaluation and cost assessment as a result of inadequate professional involvement and
this could be adduced to be a significant problem of success implementation of public
financed infrastructure projects in Nigeria.
In Taiwan Yang et al (2012) held a study to assess the impacts of information technology
on project success through knowledge management practice. They claimed that under the
pressure of globalization, the construction industry employs project teams to respond
quickly to the environmental changes and reach the enterprise goals so the use of
information technology to manage the information is vital. They concluded that
knowledge management is a key factor influencing project performance in terms of
schedule, cost, quality, and safety performance. Also they found that knowledge
management fully mediates the effects of information technology application on project
performance. Another result of the study showed that project success can be improved
when the project team seeks to enhance knowledge management and teams with worse
member relationship may achieve higher levels of project success when they experienced
high levels of knowledge management than those with better member relationships.
In Malaysia Memon et al (2013) studied the effect of resource related causes on the basic
criteria of project performance. They claimed that construction projects are highly
dependable on resources and construction cost is significantly affected by various
resource related factors. Their study results showed that approximately 47% of cost
overrun was influence with resource related factors. Also they concluded that finance
factors were the most critical factors so that an effective financial management can
significantly improve the project's success and help in reducing the cost overrun.
Another Study in Malaysia done by Yong and Mustaffa (2013) to assess the critical
success factors for Malaysian construction projects. They identified 75 CSFs for
construction projects in Malaysia. They revealed that there were a strong consistency
among the perception of project stakeholders in recognizing the significance of human-
related ‘soft’ factors. Also their study results ranked major factors as: (1) project
27
personnel; (2) commitment and communication; and (3) site management and
supervision.
In south Africa a study done by Windapo and Cattell (2013) to investigate the challenges
influencing the performance, development and growth of the construction industry. They
found the main challenges included the increasing costs of building materials, difficulties
on access to mortgage/credits, high interest rates and the high rate of failure of
contracting enterprises. Also they concluded that economic factors invariably introduce
additional uncertainty into the project.
Another study conducted in Nigeria by Ihuah et al (2014) to investigate and establish the
critical project management success factors (CPMSF) for the sustainable social (public)
housing estates. The study revealed that 22 critical project management success factors
are essential and they were related to: the project managers’ performance; the
organization that owns the development project; the characteristics of the team members;
and the external project environment. At the same time, the study revealed that these
were social, economic, and environmental factors that are associated with the triple
objectives of sustainable development. The critical success factors implementation in the
project management for sustainable social (public) housing estates’ delivery and
provision should be supported by government policies based on the people’s real needs
and not for selfish political and financial motives.
In Indonesia Wibowo and Alfen (2014) aimed on their research to investigate the macro-
environmental critical success factors (CSFs) and key areas for improvement for public-
private partnerships (PPP) in infrastructure development. They concluded that the most
important remedial actions should be concentrated to improve the PPP’s projects were:
commitments to policy continuity, financial transparency, and corruption eradication.
Also in Hong Kong Zou et al (2014) held a study to identifying the critical success
factors for relationship management in PPP projects. They considered that the ability to
actively create and develop collaborative relationships is an essential asset for managing
project networks. They identified three essential successful factors for effective
relationship management in PPP included commitment and participation of senior
28
executives; defining the objectives and project strategy; and integration of the divisions
of the organization.
Studies categorized CSFs
Dvir et al (2003) studied the relationship between project planning and project success.
They grouped CSF’s in three groups 1. Meeting planning goals (success at the project
manager level) 2. End-user benefits (success from the end-user point of view) 3.
Contractor benefits (success at the contractor’s level, and includes their last two criteria:
commercial success of the project and potential for future revenues). Their findings
revealed that project success is insensitive to the level of implementation of management
processes and procedures, which are readily supported by modern computerized tools and
project management training. On the other hand, project success is positively correlated
with the investment in requirements’ definition and development of technical
specifications.
In Vietnam by Nguyen et al (2004) held a study to identify project success factors and to
uncover the relationships between that factors. They used survey questionnaire to collect
the data. They categorized the CSFs into four groups namely comfort, commitment,
communication and competence. Study results showed that the most CSFs were
competent of project manager, adequate funding until project completion, competent
project team, commitment to project and availability of resources. Also they found out
the most CSFs are human related factors.
In Hong Kong Chan et al (2004b) held a research to develop a conceptual framework on
critical success factors CSFs. They grouped the variables affecting project success in five
major groups of independent variables, namely project-related factors, project
procedures, project management actions, human-related factors, and external
environment are identified as crucial to project success.
Also on Thailand Toor and Ogunlana (2008) conducted study to explore the
interrelationships between various critical success factors and group them. They
employed questionnaire and interview surveys with construction professionals and used
factor analysis to examine the underlying relationships which resulted in formulation of
29
four factor groupings which were together called critical COMs of success and were
labeled as comprehension, competence, commitment, and communication.
In Thailand Aksorn and Hadikusumo (2008) held a research to identify and quantitatively
prioritize the factors contribute to the successful implementation of construction safety
programs. They grouped 16 CSF’s influencing safety program performance into four
dimensions which were worker involvement, safety prevention and control system, safety
arrangement, and management commitment. They concluded that the most influential
factor is management support.
In Hong Kong Yang et al (2009) made a research to identify CSFs associated with
stakeholder management in construction projects, and explore their ranking and
underlying relationship. They grouped 15 CSFs into five dimensions related basically to
planning stage namely: precondition factor, stakeholder estimation, information inputs,
decision making, and sustainable support. Their results indicated that the top three ranked
CSFs were 1) managing stakeholders with social responsibilities, 2) assessing the
stakeholders' needs and constraints to the project, and 3) communicating with
stakeholders properly and frequently.
In South Korea Park (2009) conducted a research to identify the critical factors CFs and
to evaluate their relative importance to whole life performance assessment. He focused
on procurement stage and he investigated 188 individual factors. Then he grouped CFs
into eight critical categories namely: project scope, time, cost, quality,
contract/administration, human resource, risk, and health and safety. He revealed that
cost, quality, scope, and time are more important than contract/administration, risk,
human resource, and health and safety to all respondents over a project life cycle.
Another founding was that the most critical individual factors in each category were
clarity of contract; fixed construction period; precise project budget estimate; material
quality; mutual/trusting relationships; leadership/team management; and management of
work safety on site.
In Hong Kong also Ng et al (2009) studied the factors contributing to the success of
equipment intensive subcontractors in construction. They grouped 17 CSFs into six major
30
components namely: (i) market position; (ii) equipment-related factors; (iii) human
resources; (iv) earnings; (v) managerial ability to adapt to changes; and (vi) project
success related factors. The top five CSFs identified in the study were ‘‘timely
completion ” , ‘‘relationship with main contractor/client/consultant” , ‘‘profit” , ‘‘cash
flow” , and ‘‘adoption of new technologies/methodologies”.
In China Chan et al (2010) held a research to explore the critical success factors CSFs
necessary to conduct PPP projects. They grouped 18 CSFs into five groups: stable
macroeconomic environment; shared responsibility between public and private sectors;
transparent and efficient procurement process; stable political and social environment;
and judicious government control. They concluded that the most critical factor was
transparent and efficient procurement process.
Another study in Vietnam conducted by Ling and Bui (2010) to examine factors that lead
to successful outcomes in construction projects. They classified the factors into four
groups to 1) project related factors, 2) procurement related factors, 3) project
management related factors, 4) characteristics of owners, consultants, and contractors.
Their results showed that major enablers that lead to project success were foreign
experts’ involvement in the project, government officials inspecting the project, and very
close supervision when new construction techniques are employed. They found that the
factor which leads to poor performance was the lack of accurate data on soil, weather,
and traffic conditions.
In Saudi Arabia Alhaadir and Panuwatwanich (2011) held a research to identify CSFs for
safety program implementation. They grouped the factors into four categories namely: (1)
worker participation; (2) safety prevention and control system; (3) safety arrangement;
and (4) safety commitment. They used Pareto principle, and analytical hierarchical
method AHP and suggested seven critical factors that can account for 80% of the
successful implementation of safety programs in construction companies which were (1)
management support; (2) clear and reasonable objectives; (3) personal attitude; (4)
teamwork; (5) effective enforcement; (6) safety training; and (7) suitable supervision.
31
Also in Malaysia Zawawi et al (2011) conducted study to drive a conceptual framework
for describing CSF of building maintenance management. They claimed that the
implementing CSF concept would enhance the management process and work planning
which would result in a more economic use of resources, a corresponding reduction in
the total cost and create successful competitive performance organization. In this study,
critical success factors were categorized into five primary categories namely: 1.
leadership, 2. culture, 3. structure, roles, and responsibilities, 4. system infrastructure, and
5. measurement.
Another study in Malaysia held by Tan and Ghazali (2011) to determine the CSFs and
provide some guidance for contractors needed to operate overseas. They grouped CSF’s
under seven main categories: (1) project management factors; (2) procurement related
factors; (3) client-related factors; (4) design team-related factors; (5) contractor-related
factors; (6) project manager -related factors; and (7) business and work environment-
related factors. Study evidences showed that project management related factor is more
important than the other main factors in terms of ranking and contractor’s experience is
the most critical among all the sub-factors.
In Nigeria Famakin et al (2012) reported the factors affecting the performance of partners
in joint ventures construction projects. They grouped CSFs into five groups namely: 1)
establishment of joint venture partner’s loyalty, 2) commitment to joint venture
relationship, 3) maintaining of joint venture organization, 4) establishment of joint
venture interests and 5) conflict management. Their study revealed that at the formation
stage, compatibility of objectives, mutual understanding and agreement of the contract
are very much important to the success of joint venture construction projects. At the
implementation stage, the study also revealed that communication and management
control as very important factors at this stage.
Also in Hong Kong Ng et al (2012) held a research to explore the key successful
ingredients to be assessed at the initial stage of PPP projects. In their research they
described the dimensions of CSFs of public private projects as (i) technical factors; (ii)
financial and economic factors; (iii) social factors; (iv) political and legal; and (v)others
32
(staff issue and possible management actions). Study results indicated that the most
critical factors for evaluating PPP were cost effectiveness and financial attractiveness.
In Durban and South Africa Garbharran et al (2012) conducted study to assess the
perceptions of contractors and project managers on the critical success factors that lead to
project success in the construction industry. They used four groups (comfort,
competence, communication and commitment). They emerged that there were no
significant differences between project managers and contractors regarding the critical
success factors.
In China Zhao et al (2013) studied the factors influencing the success of build operate
transfer power plant projects. The results showed that there were 14 CSF’s at two levels,
i.e. macro level and micro level affect the success of these projects. Study results also
indicated that the main success factor of China’s built operate transfer electric power
projects was the existence of combined efforts from all related stakeholders.
2.3.3 CSFs in developed countries studies
On this part the researcher will give general view for the previous studies which divided
into two kinds: 1) studies described CSFs and evaluated them and 2) studies categorized
CSFs.
Studies described CSFs and evaluated them
In Pennsylvania Sanvido et al (1992) carried out a study considered as one of the first
studies on CSFs field. They aimed to define the critical factors that lead to project success
and provide a forecasting tool to enable parties to rapidly assess the possibility of a
successful project from their viewpoint. The research results revealed that four factors
were found to be critical: (1) a well-organized, cohesive facility team to manage, plan,
design, construct, and operate the facility team chemistry was typically developed by
common goals and activities. (2) A series of contracts that allows and encourages the
various specialists to behave as a team without conflicts of interest and differing goals.
these contracts must allocate risk and reward in the correct proportions. (3) Experience in
the management, planning, design, construction, and operations of similar facilities. and
33
(4) Timely, valuable optimization information from the owner, user, designer, contractor,
and operator in the planning and design phases of the facility. Authors also concluded
that if project participants can predict probability of success better, they can take steps
to: (1) avoid unsuccessful projects; (2) identify good projects worth pursuing; and (3)
identify problems on current projects and take corrective action.
In United Kingdom Bourne et al (2002) studied the major factors that impact the success
and failure of the implementation of a performance measurement system. They
considered four factors appeared to be significant on project success which were how the
introduction and launch was handled, who was involved in the project and project
management and procedure. They found that poor strategy and project vision could be
attributed to poor design process which affected implementation issues.
In United States of America (USA) Doerr et al (2004) investigated how the extent and
type of centrality shapes managers’ perceptions of the success or failure of
technologically innovative projects. They consider 6 CSFs which were (1) general
reflections on the “big picture” of project success; (2) social and cultural criteria, such as
reputation; (3) organizational factors, including support from upper level management;
(4) market concerns; (5) efficiencies, for example, in time and costs; and (6)
technological success. They concluded that managers asymmetrically discuss success
more than failure, and the type of centrality they have influences how they talk about
success and interpretive flexibility in the meaning of success occurs among more central
managers who have access to more information through their network ties.
In Germany Dvir and Lechler (2004) investigated on their study the interactions between
the planning variables and their influences on project success. They claimed that planning
is a process with many different activities that cover a variety of issues, using numerous
planning techniques and planning procedures such as analysis, design reviews, reports
and interpersonal communication. They also concluded that the positive total effect of the
quality of planning was almost completely overridden by the negative effect of goal
changes. Also they found out that combined effect of goal changes and plan-changes on
project success was considerably stronger than that of the quality of planning.
34
In Sweden Turner and Müller (2005) conducted a research to prove that the project
manager’s leadership style is a success factor on projects and to assess whether its impact
is different on different types of projects. They concluded that an appropriate leadership
style can lead to better performance.
In Finland Lehtiranta et al (2012) conducted a study to explore a new dimension of the
determinants for construction project success, i.e. relationship between success and multi-
firm project participants’ satisfaction with each other. The results of the study showed
that correlations can be found between certain project participants’ satisfaction with each
other’s performance and the owner’s perception of project success. More specifically,
satisfaction with performance factors within the relationships between the owner and any
other participant (i.e. the contractor, designer or project consultant), within the
relationship between project consultants and designers and within the relationship
between project consultants and contractors were reflected in the owner’s perception of
project success.
Also on UK Meng (2012) held a research to analyze the role of relationship management
as CSF in project performance. He used ten factors to describe the key aspects of a
supply chain relationship. He concluded that supply chain relationship has some
significant influences on project performance, so developing a good supply chain
relationship may help to improve project performance and deterioration of supply chain
relations hips is a major reason for the occurrence of poor performance.
In Finland, Netherlands and Switzerland Verburg et al (2013) conducted a study to
highlight the conditions that are important for successful task accomplishment. Their
results showed that important conditions for successful project execution in a dispersed
setting include rules of communication and its clarity; project management style and
goal-setting; and managers' competences and trust in a team.
Another study in USA held by Molenaar et al (2013) aimed to understand whether
project peer reviews could be an indicator of project success and to identify the questions
most correlated with the outcomes. The results of their research indicated that project
peer reviews should be conducted during the construction process and it can be used to
35
assess and predict final project performance. Additionally they found that there were
significant correlations between project success and questions regarding working
relationships, communication, timing, project controls, and relational approaches to
project participants. Molenaar et al (2013) suggested that companies and organizations
can strategically improve projects by conducting project peer reviews early in the
construction process.
In Italy Locatelli et al (2014) investigated the effect of project characteristics on the
success of megaprojects. Locatelli et al (2014) found out the megaprojects suffer from
very poor performance like over-budget and/or behind schedule and, once finished, they
deliver less benefits than planned. Study results determined main factors needs to be
considered in order to improve performance of megaprojects which were participation of
internal stakeholders in company and external stakeholders (like a governmental
authority), a proper designed project governance, and efficient project delivery chain and
project nature.
In Finland Skaates et al (2014) examined the relationships and project marketing success.
They concluded that project managers should focus their attention on the management of
project relationships before, during and after projects and relevant environmental factors
of project. Also they concluded that project managers are accountable for the successful
delivery of complete projects. Increasingly, success depends on project managers’
processing and utilizing skills and competencies.
In Slovenia Fink (2014) held a study to investigate the effect of customer focus
competence on construction project performance. He defined customer focus competence
as an “awareness of the construction project team members of the customer’s importance,
recognizing customer needs and increasing customer loyalty”. He founded positive
effects of the team average customer focus on examined project goals and it can
considered important factor projects success.
Studies categorized CSFs
In UK Fortune and White (2006) conducted theoretical study to frame a model of project
critical success factors. They used sets of critical success factors from 63 publications to
36
develop the model in order to distinguish between successful and unsuccessful projects.
They suggested to use it in the planning phase in order to provide a way of tackling the
human and organizational aspects of systems development projects. They grouped 27
CSFs into 11 main cluster which were 1) goals objectives, 2) performance monitoring, 3)
decision-makers, 4) transformations, 5) communication, 6) environment, 7) boundaries,
8) resources continuity, 9) viewpoints, 10) project champion, and 11) change agent.
In Lithuania Gudienė et al (2013) and Gudienė et al (2014) conducted study in order to
rank CSF’s in construction industry. They grouped CSF’s into seven groups which were
1) external factors, 2) institutional factors, 3) project related factors, 4) project
management/team related factors, 5) project manager related factors, 6) client related
factors, 7) contractor related factors. Their study revealed that clear and realistic project
goals, project planning, the project manager’s competence, relevant past experience of
the project management/team, the competence of the project management/team, clear and
precise goals/objectives of the client, the project’s value, the project’s complexity and
uniqueness, the project manager’s experience, and the client’s ability to make timely
decisions are the top ranking CSFs.
Another research in UK conducted by Alzahrani and Emsley (2013) to study the impact
of contractors’ attributes on project success from a post construction evaluation
perspective and to identify what critical success factors (CSFs) that greatly impact the
success of project. They used factor analysis and grouped the CSFs that greatly impact
the success of a project on nine clusters which were (i) safety and quality; (ii) past
performance; (iii) environment; (iv) management and technical aspects; (v) resource; (vi)
organization; (vii) experience; (viii) size/type of pervious projects; and (ix) finance. They
investigated that factors such as turnover history, quality policy, adequacy of labor and
plant resources, waste disposal, size of past projects completed, and company image are
the most significant factors affecting projects success.
Another research in Austria, Czech Republic, Germany, Hungary, Poland, Slovakia,
Slovenia and Switzerland done by Cserháti and Szabó (2014) aimed to investigate the
relationship between success criteria and success factors in organizational event projects.
They classify the success factors into two groups which were relationship orientation
37
factors and task focus factors. They concluded that relationship-oriented success factors,
such as communication, co-operation and project leadership, play a crucial role in
carrying out successful organizational event projects.
From the previous studies in both developed and developing countries the researcher
summarized 125 CSFs that may affect the project success. Table 2.3 presented the
summarized CSFs according to their references.
Table 2. 3: Summary of CSFs
No. Factor Resource
1. Accidents and hazards Park (2009); Gudienė et al (2013); Gudienė et al (2014); Marzouk and El-
Rasas (2014); Zavadskas et al (2014).
2. Client approvals and
Payment method
Frimpong et al (2003); Sambasivan and Soon (2007); Ng et al (2009);
Orangi et al (2011); LI et al (2012); Marzouk and El-Rasas (2014).
3. Change in goals plans
and orders
Davies (2002); Dvir and Lechler (2004); Hughes et al (2004); Fortune and
White (2006); Orangi et al (2011); Lehtiranta et al (2012); Yong and
Mustaffa (2013); Hwang et al (2013); Marzouk and El-Rasas (2014);
Wibowo and Alfen (2014); Yang et al (2015).
4. Commitment to
continuous improvement
Davies (2002); Chen and Chen (2007); Meng (2012); Cserháti and Szabó
(2014); Yang et al (2015)
5. Knowledge management Davies (2002); Yang et al (2012); Zou et al (2014).
6.
The project has effective
well established
information and
communication routines
Bourne et al (2002); Dvir et al (2003); Nguyen et al (2004); Chan et al
(2004); Meeampol and Ogunlana (2006); Wang and Huang (2006);
Fortune and White (2006); Iyer and Jha ( 2006); Chen and Chen (2007);
Sambasivan and Soon (2007); Lu et al (2008); Aksorn and Hadikusumo
(2008); Park (2009); Yang et al (2009); Chan et al (2010); Lu and Yuan et
al (2010); Alhaadir and Panuwatwanich (2011); Yang et al (2011); Tan
and Ghazali (2011); Omran and Mamat (2011); Yu and Kwon (2011);
Abdul-Aziz and Kassim (2011); Orangi et al (2011) ; Chen et al (2012);
Alias et al (2014); Gudienė et al (2014); Cho et al (2009); Famakin et al
(2012); Garbharran et al (2012); Ismail et al (2012); Meng (2012);
Lehtiranta et al. (2012); Molenaar et al (2013); Yong and Mustaffa (2013);
Gudienė et al (2013); Verburg et al (2013); Ihuah et al (2014); Cserháti
and Szabó (2014); Zou et al (2014).
7.
Performance
measurement
(Management for
successful outcome).
Davies (2002); Omran and Mamat (2011); Yu and Kwon (2011); Zawawi
et al (2011); Meng (2012); Mir and Pinnington (2014); Cserháti and
Szabó (2014); Yang et al (2015).
8. Control of subcontractor
works
Sambasivan and Soon (2007); Ling and Bui (2010); Orangi et al (2011);
LI et al (2012); Yong and Mustaffa (2013).
9. Effective and timely
conflict resolution
Chan et al (2004a); Chan et al (2004); Iyer and Jha ( 2006); Lu et al
(2008); Park (2009); Cho et al (2009); Yang et al (2009); Yu and Kwon
(2011); Famakin et al (2012); Gudienė et al (2013); Gudienė et al (2014).
10. The project has a clear
and well-planned agenda
of meetings for all
Dvir et al (2003); Nguyen et al (2004); Andersen et al (2006); Iyer and Jha
( 2006); Chen et al (2012); Garbharran et al (2012).
38
Table 2. 3: Summary of CSFs
No. Factor Resource
participants
11. Parties relationships and
coordination
Chan et al (2004); Meeampol and Ogunlana (2006); Wang and Huang
(2006); Iyer and Jha ( 2006); Lu et al (2008); Ng et al (2009); Park (2009);
Tan and Ghazali (2011); Omran and Mamat (2011); Yu and Kwon (2011);
Meng (2012); Hwang et al (2013); Molenaar et al (2013); Yong and
Mustaffa (2013); Cserháti and Szabó (2014); Yang et al (2015).
12. Team members number
and performance
Wang and Huang (2006); Zavadskas et al (2014); Ihuah et al (2014); Yang
et al (2015).
13. Project nature Chan et al (2004); Cho et al (2009); Yong and Mustaffa (2013); Shehu et
al (2014).
14.
Leadership, monitoring,
coordinating, organizing
manager skills for both
contractor PM and owner
Bourne et al (2002); Dvir et al (2003); Turner and Müller (2005); Iyer and
Jha ( 2006); Andersen et al (2006); Fortune and White (2006); Lu et al
(2008); Ng et al (2009); Park (2009); Tan and Ghazali (2011); Yang et al
(2011); Omran and Mamat (2011); Zawawi et al (2011); Lehtiranta et al
(2012); Ismail et al (2012); Alzahrani and Emsley (2013); Gudienė et al
(2013); Zhao et al (2013); Gudienė et al (2014); Alias et al (2014); Mir
and Pinnington (2014).
15. Decision-making
effectiveness
Frimpong et al (2003); Dvir et al (2003); Iyer and Jha ( 2006); Park
(2009); Tan and Ghazali (2011); Yu and Kwon (2011); Meng (2012);
Lehtiranta et al (2012); Gudienė et al (2013); Gudienė et al (2014); Ihuah
et al (2014).
16. Commitment of all
project participants
Bourne et al (2002); Chan et al (2004a); Nguyen et al (2004); Hughes et al
(2004); Iyer and Jha ( 2006); Wang and Huang (2006); Chen and Chen
(2007); Aksorn and Hadikusumo (2008); Chan et al (2010); Omran and
Mamat (2011); Tan and Ghazali (2011);Chen et al (2012); Garbharran et
al (2012); Lehtiranta et al. (2012); Ismail et al (2012); Ng et al (2012);
Yong and Mustaffa (2013); Cserháti and Szabó (2014); Alias et al (2014);
Zou et al (2014).
17. Environmental plan and
methods during
construction
Fortune and White (2006); Lu et al (2008); Ng et al (2009); Park (2009);
Lu and Yuan et al (2010); Ismail et al (2012); Alzahrani and Emsley
(2013); Son and Kim (2014); Wibowo and Alfen (2014); Zavadskas et al
(2014).
18. Safety issues
Chan et al (2004); Hughes et al (2004); Lu et al (2008); Aksorn and
Hadikusumo (2008); Ng et al (2009); Park (2009); Alhaadir and
Panuwatwanich (2011); Gudienė et al (2013); Yong and Mustaffa (2013);
Gudienė et al (2014); Son and Kim (2014).
19. Complexity and
uniqueness
Chan et al (2004); Hughes et al (2004); Meeampol and Ogunlana (2006);
Fortune and White (2006); Cho et al (2009); Park (2009); Tan and Ghazali
(2011); Yang et al (2011); LI et al (2012); Gudienė et al (2013); Yong and
Mustaffa (2013); Gudienė et al (2014).
20. Profitability
Ng et al (2009); Park (2009); Ng et al (2012); Famakin et al (2012);
Gudienė et al (2013); Zhao et al (2013); Gudienė et al (2014); Zavadskas
et al (2014).
21.
Contract management
and documentation
include penalties, bonds,
incentives, ..etc
Frimpong et al (2003); Dvir et al (2003); Nguyen et al (2004); Chan et al
(2004a); Hughes et al (2004); Wang and Huang (2006); Lu et al (2008);
Ng et al (2009); Park (2009); Tan and Ghazali (2011); Abdul-Aziz and
Kassim (2011); Chen et al (2012); LI et al (2012); Famakin et al (2012);
39
Table 2. 3: Summary of CSFs
No. Factor Resource
Ng et al (2012); Garbharran et al (2012); Lehtiranta et al (2012); Verburg
et al (2013); Gudienė et al (2013); Yong and Mustaffa (2013); Alzahrani
and Emsley (2013); Gudienė et al (2014); Marzouk and El-Rasas (2014).
22. Subcontractor and
contractor Involvement
Chan et al (2004); Ng et al (2009); Park (2009); Tan and Ghazali (2011);
LI et al (2012).
23. Project type
Chan et al (2004); Yang et al (2011); Cho et al (2009); Gudienė et al
(2013); Gudienė et al (2014); Locatelli et al (2014); Shehu et al (2014);
Yang et al (2015).
24. Reputation Ng et al (2009); Abdul-Aziz and Kassim (2011); Verburg et al (2013)
25. Transparent and efficient
procurement method
Frimpong et al (2003); Dvir et al (2003); Chan et al (2004); Wang and
Huang (2006); Lu et al (2008); Ng et al (2009); Chan et al (2010); Ling
and Bui (2010); Tan and Ghazali (2011); Garbharran et al (2012); Gudienė
et al (2013); Yong and Mustaffa (2013); Windapo and Cattell (2013);
Gudienė et al (2014); Shehu et al (2014); Son and Kim (2014); Wibowo
and Alfen (2014).
26. Risk identification
management and
allocation
Davies (2002); Dvir et al (2003); Chan et al (2004a); Fortune and White
(2006); Lu et al (2008); Park (2009); Chan et al (2010); Ismail et al
(2012); LI et al (2012); Lehtiranta et al (2012); Ng et al (2012); Meng
(2012); Yong and Mustaffa (2013); Gudienė et al (2013); Gudienė et al
(2014); Ihuah et al (2014); Son and Kim (2014); Zavadskas et al (2014).
27. Size
Chan et al (2004); Fortune and White (2006); Lu et al (2008); Cho et al
(2009); Ng et al (2012); Gudienė et al (2013); Gudienė et al (2014); Shehu
et al (2014); Yang et al (2015).
28. Legal environment
Lu et al (2008); Chan et al (2010); Yu and Kwon (2011); Ng et al (2012);
Gudienė et al (2013); Zhao et al (2013)Gudienė et al (2014); Wibowo and
Alfen (2014).
29. Design management
change and mistakes
Dvir et al (2003); Ahsan and Gunawan (2010); Lu and Yuan et al (2010);
Tan and Ghazali (2011); Orangi et al (2011); Lehtiranta et al (2012); LI et
al (2012); Yong and Mustaffa (2013); Son and Kim (2014); Marzouk and
El-Rasas (2014);
30.
Clear and realistic and
sharable multi-benefit
goals vision and mission
of projects
Bourne et al (2002); Dvir et al (2003); Nguyen et al (2004); ); Hughes et
al (2004); Chan et al (2004a); Iyer and Jha ( 2006); Fortune and White
(2006); Andersen et al (2006); Chen and Chen (2007); Aksorn and
Hadikusumo (2008); Lu et al (2008); Toor et al (2008); Yang et al (2009);
Ahsan and Gunawan (2010); Chan et al (2010); Alhaadir and
Panuwatwanich (2011); Tan and Ghazali (2011); Garbharran et al (2012);
Lehtiranta et al. (2012); Ng et al (2012); Famakin et al (2012); Gudienė et
al (2013); Molenaar et al (2013); Yong and Mustaffa (2013); Verburg et al
(2013); Gudienė et al (2014); Ihuah et al (2014); Son and Kim (2014);
Cserháti and Szabó (2014); Zou et al (2014).
31. Technical capability
(contractor and
managers)
Chan et al (2004); Iyer and Jha ( 2006); Wang and Huang (2006); Chen
and Chen (2007); Lu et al (2008); Ng et al (2009); Tan and Ghazali
(2011); Gudienė et al (2013); Alzahrani and Emsley (2013); Gudienė et al
(2014).
32. Quality standards and
criteria
Tan and Ghazali (2011); Gudienė et al (2013); Yong and Mustaffa (2013);
Gudienė et al (2014); Son and Kim (2014); Yang et al (2015).
33. Consultant recruitment Bourne et al (2002); Fortune and White (2006); Wang and Huang (2006);
40
Table 2. 3: Summary of CSFs
No. Factor Resource
and involvement in
budgeting and
supervision
Ahsan and Gunawan (2010); Jagboro et al. (2012); Molenaar et al (2013);
Yong and Mustaffa (2013).
34. Design completed before
work on site Park (2009).
35. Value
Dvir et al (2003); Dvir and Lechler (2004); Cho et al (2009); Ng et al
(2012); Gudienė et al (2013); Zhao et al (2013); Gudienė et al (2014); Son
and Kim (2014); Yang et al (2015).
36. Financial security and
stability (contractor,
owner)
Frimpong et al (2003); Nguyen et al (2004); Chan et al (2004); Chen and
Chen (2007); Lu et al (2008); Ng et al (2009); Park (2009); Chen et al
(2012); Famakin et al (2012); Ng et al (2012); Hwang et al (2013); Zhao
et al (2013); Gudienė et al (2013); Gudienė et al (2014); Marzouk and El-
Rasas (2014); Wibowo and Alfen (2014).
37. Project team leader
involvement and
authority
Chan et al (2004); Turner and Müller (2005); Andersen et al (2006); Iyer
and Jha ( 2006); Tan and Ghazali (2011); Yong and Mustaffa (2013);
Ihuah et al (2014).
38. Construction regulations
Chan et al (2004); Park (2009); Lu and Yuan et al (2010); Zhao et al
(2013); Gudienė et al (2013); Windapo and Cattell (2013); Gudienė et al
(2014); Ihuah et al (2014); Son and Kim (2014); Wibowo and Alfen
(2014).
39. Product and service
certification Gudienė et al (2013); Gudienė et al (2014).
40. Cultural issues
Bourne et al (2002); Chen and Chen (2007); Ahsan and Gunawan (2010);
Orangi et al (2011); Zawawi et al (2011); Chen et al (2012); Gudienė et al
(2013); Gudienė et al (2014); Ihuah et al (2014).
41. Adequate and clear
financial budget
Bourne et al (2002); Dvir et al (2003); Frimpong et al (2003); Wang and
Huang (2006); Fortune and White (2006); Andersen et al (2006);
Meeampol and Ogunlana (2006); Park (2009); Ahsan and Gunawan
(2010); Chan et al (2010); Tan and Ghazali (2011); Yang et al (2011);
Garbharran et al (2012); Chen et al (2012); Yong and Mustaffa (2013);
Alzahrani and Emsley (2013); Gudienė et al (2013); Alias et al (2014);
Gudienė et al (2014); Ihuah et al (2014); Locatelli et al (2014); Son and
Kim (2014); Zavadskas et al (2014);.
42. Community,
international and end
user involvement
Fortune and White (2006); Chen and Chen (2007); Orangi et al (2011);
Yang et al (2011); Garbharran et al (2012); Ng et al (2012); Ihuah et al
(2014).
43. Depreciation/devaluation
of local currency Hughes et al (2004); Ahsan and Gunawan (2010); Gudienė et al (2014).
44. Clear prioritization of
project goals by the client
Chan et al (2004); Toor et al (2008); Yang et al (2009); Ling and Bui
(2010); Yang et al (2011); Yong and Mustaffa (2013); Gudienė et al
(2013); Gudienė et al (2014).
45. Political influence
Chan et al (2004); Chan et al (2004a); Iyer and Jha ( 2006); Fortune and
White (2006); Ng et al (2009); Chan et al (2010); Abdul-Aziz and Kassim
(2011); Tan and Ghazali (2011); Garbharran et al (2012); Ng et al (2012);
Yong and Mustaffa (2013); Zhao et al (2013); Gudienė et al (2013);
Gudienė et al (2014).
46. Applicable Construction Bourne et al (2002); Meeampol and Ogunlana (2006); Park (2009); Chan
41
Table 2. 3: Summary of CSFs
No. Factor Resource
methods et al (2010); Lehtiranta et al (2012); Hwang et al (2013); Alzahrani and
Emsley (2013); Gudienė et al (2013); Gudienė et al (2014).
47. Natural calamities
Frimpong et al (2003); Iyer and Jha ( 2006); Ahsan and Gunawan (2010);
Orangi et al (2011); Gudienė et al (2013); Yong and Mustaffa (2013);
Gudienė et al (2014).
48. Effective control , such
as monitoring, updating
plans and feedback
Davies (2002); Frimpong et al (2003); Chan et al (2004b); Nguyen et al
(2004); Chan et al (2004a); Andersen et al (2006); Wang and Huang
(2006); Iyer and Jha ( 2006); Meeampol and Ogunlana (2006); Fortune
and White (2006); Toor et al (2008); Aksorn and Hadikusumo (2008);
Park (2009); Ahsan and Gunawan (2010); Abdul-Aziz and Kassim (2011);
Tan and Ghazali (2011); Omran and Mamat (2011); Chen et al (2012); Ng
et al (2012); Famakin et al (2012); Gudienė et al (2013); Yong and
Mustaffa (2013); Alias et al (2014); Gudienė et al (2014); Ihuah et al
(2014); Son and Kim (2014); Zavadskas et al (2014).
49. Mutual trust and
understanding
Gudienė et al (2014); Gudienė et al (2013); Chan et al (2004); Chan et al
(2004a); Chen et al (2012); Famakin et al (2012); Park (2009); Tan and
Ghazali (2011); Verburg et al (2013); Chen and Chen (2007); Yong and
Mustaffa (2013)
50. Collaborative team
culture
Chan et al (2004a); Iyer and Jha ( 2006); Aksorn and Hadikusumo (2008);
Lu et al (2008); Ng et al (2009); Park (2009); Yang et al (2009); Alhaadir
and Panuwatwanich (2011); Yang et al (2011); Chen et al (2012); Meng
(2012); Famakin et al (2012); Ismail et al (2012); Verburg et al (2013);
Yang et al (2015).
51. Management support
Bourne et al (2002); Chan et al (2004a); Nguyen et al (2004); Iyer and Jha
( 2006); Andersen et al (2006); Fortune and White (2006); Aksorn and
Hadikusumo (2008); Lu et al (2008); Alhaadir and Panuwatwanich (2011);
Garbharran et al (2012); Gudienė et al (2013); Yong and Mustaffa (2013);
Gudienė et al (2014); Alias et al (2014); Chen et al (2012); Ihuah et al
(2014); Cserháti and Szabó (2014); Zou et al (2014).
52. Training the human
resources in the skill
demanded by the project
Fortune and White (2006); Iyer and Jha (2006); Ng et al (2009); Lu and
Yuan et al (2010); Wibowo and Alfen (2014); Yang et al (2015).
53.
Project manager
commitment to meet cost
quality and time of
project
Dvir et al (2003); Chan et al (2004); Meeampol and Ogunlana (2006);
Chen and Chen (2007); Lu et al (2008); Park (2009); Omran and Mamat
(2011); Chen et al (2012); Gudienė et al (2013); Son and Kim (2014);
Cserháti and Szabó (2014).
54.
The project has a formal
organizational chart
covering the entire
project
Chan et al (2004); Andersen et al (2006); Lu et al (2008); Park (2009); Yu
and Kwon (2011); Zawawi et al (2011); Famakin et al (2012); Gudienė et
al (2013); Tan and Ghazali (2011); Gudienė et al (2014); Son and Kim
(2014); Cserháti and Szabó (2014);
55.
All key participants have
participated in the
detailed project planning
within their area of
expertise
Hughes et al (2004); Fortune and White (2006); Andersen et al (2006);
Famakin et al (2012); Lehtiranta et al (2012); Yong and Mustaffa (2013).
56. Strong /detailed and
updated integrated
Bourne et al (2002); Frimpong et al (2003); Dvir and Lechler (2004);
Nguyen et al (2004); Hughes et al (2004); Chan et al (2004); Chan et al
42
Table 2. 3: Summary of CSFs
No. Factor Resource
planning effort in
design and construction
(2004a); Andersen et al (2006); Sambasivan and Soon (2007); Fortune and
White (2006); Ng et al (2009); Cho et al (2009); Yu and Kwon (2011);
Garbharran et al (2012); Lehtiranta et al (2012); Ismail et al (2012); LI et
al (2012); Gudienė et al (2013); Hwang et al (2013); Alias et al (2014);
Gudienė et al (2014); Ihuah et al (2014); Locatelli et al (2014); Son and
Kim (2014); Cserháti and Szabó (2014); Marzouk and El-Rasas (2014).
57. Physical environment
(civil works, location,
weather, ..etc)
Frimpong et al (2003); Chan et al (2004); Lu et al (2008); Ahsan and
Gunawan (2010); Tan and Ghazali (2011); Zawawi et al (2011); Windapo
and Cattell (2013); Gudienė et al (2013); Gudienė et al (2014); Ihuah et al
(2014); Shehu et al (2014); Son and Kim (2014); Marzouk and El-Rasas
(2014); Wibowo and Alfen (2014).
58. Ability to Generate
Innovative Ideas
Chan et al (2004a); Lu et al (2008); Lu and Yuan et al (2010); Ng et al
(2012); Gudienė et al (2013); Gudienė et al (2014).
59. Parties relevant past
experience
Hughes et al (2004); Nguyen et al (2004); Dvir and Lechler (2004); Chan
et al (2004a); Fortune and White (2006); Sambasivan and Soon
(2007);Chen et al (2007); Lu et al (2008); Ng et al (2009); Park (2009);
Cho et al (2009); Ling and Bui (2010); Tan and Ghazali (2011); LI et al
(2012); Chen et al (2012); Famakin et al (2012); Garbharran et al (2012);
Ng et al (2012); Hwang et al (2013); Alzahrani and Emsley (2013); Yong
and Mustaffa (2013); Zhao et al (2013); Gudienė et al (2013); Gudienė et
al (2014); Marzouk and El-Rasas (2014).
60. Appropriate supervision
and site management
Bourne et al (2002); Meeampol and Ogunlana (2006); Iyer and Jha (
2006); Sambasivan and Soon (2007); Aksorn and Hadikusumo (2008); Lu
and Yuan et al (2010); Orangi et al (2011); Alhaadir and Panuwatwanich
(2011); Tan and Ghazali (2011); Hwang et al (2013); Yong and Mustaffa
(2013); Gudienė et al (2013); Gudienė et al (2014); Marzouk and El-Rasas
(2014).
61. Tendering/ bidding
strategy and management
Frimpong et al (2003); Nguyen et al (2004); Wang and Huang (2006); Lu
et al (2008); Toor et al (2008); Park (2009); Lu and Yuan et al (2010); Tan
and Ghazali (2011); Abdul-Aziz and Kassim (2011); Molenaar et al
(2013); Yong and Mustaffa (2013); Shehu et al (2014); Marzouk and El-
Rasas (2014).
62. Client contribution in
design and construction
Chan et al (2004); Chan et al (2004a); Nguyen et al (2004); Hughes et al
(2004); Andersen et al (2006); Iyer and Jha ( 2006); Toor et al (2008); Cho
et al (2009); Orangi et al (2011); LI et al (2012); Gudienė et al (2013);
Ihuah et al (2014).
63. Construction permits Tan and Ghazali (2011); Ng et al (2012); Gudienė et al (2013); Gudienė et
al (2014).
64. Personal motivation
Aksorn and Hadikusumo (2008); Lu et al (2008); Park (2009); Ahsan and
Gunawan (2010); Gudienė et al (2013); Alias et al (2014); Gudienė et al
(2014).
65. Bureaucracy Nguyen et al (2004); Ahsan and Gunawan (2010).
66.
The project is well
described and
coordinated with other
projects and activities
Bourne et al (2002); Dvir and Lechler (2004); Andersen et al (2006); Lu et
al (2008); Zou et al (2014).
67. Project ownership Davies (2002); Ihuah et al (2014).
43
Table 2. 3: Summary of CSFs
No. Factor Resource
68. One major contractor and
consortium Ng et al (2012); Locatelli et al (2014).
69. Project insurance Lu et al (2008); Ng et al (2009).
70. Responsiveness of
correspondence Molenaar et al (2013).
71. Commitment to
corruption eradication Abdul-Aziz and Kassim (2011); Wibowo and Alfen (2014).
72. An acceptable level of
tariff Ng et al (2012)
73. Access to affordable
mortgage/credit Windapo and Cattell (2013).
74. Critical global
issues/globalization Windapo and Cattell (2013).
75. Contingency funds Ahsan and Gunawan (2010)
76. Extent of subcontracting LI et al (2012); Gudienė et al (2013); Gudienė et al (2014).
77. Close supervision when
new construction
techniques are employed
Hughes et al (2004); Ling and Bui (2010).
78. Willingness to Eliminate
Non-value Added
Activities
Chan et al (2004); Park (2009).
79. Sustainable project
design and construction Park (2009); Ng et al (2012); Windapo and Cattell (2013).
80. Project is not susceptible
to fast-paced change (e.g.
Technological change)
Dvir and Lechler (2004); Ng et al (2012).
81. Customer focus
competence Fink (2014)
82. Fairness of new
conditions to employees Chen and Chen (2007); Ng et al (2012).
83. Knowledge transfer Toor et al (2008); Famakin et al (2012); Cserháti and Szabó (2014)
84.
All the organizations
involved in the project
effort have agreed to
provide the project with
sufficient resources
Chan et al (2004); Chen et al (2012); Famakin et al (2012); Garbharran et
al (2012); Alzahrani and Emsley (2013).
85.
Commitment to Win-
Win Attitude
(compatibility of
objectives)
Chan et al (2004); Abdul-Aziz and Kassim (2011); Yu and Kwon (2011);
Famakin et al (2012); Meng (2012).
86. Partnering was started at
the design stage
Chan et al (2004); Chen and Chen (2007); Park (2009); Chen et al
(2012); Ismail et al (2012).
87.
Open exchange and
consideration of ideas
were promoted during
the partnering process
Chan et al (2004a); Andersen et al (2006); Wang and Huang (2006); Yang
et al (2009); Chen et al (2012).
88. A list of partner selection Chan et al (2004); Famakin et al (2012); Verburg et al (2013).
44
Table 2. 3: Summary of CSFs
No. Factor Resource
criteria was developed
89. Strong and good private
consortium Chan et al (2010); Cserháti and Szabó (2014).
90. Public -sector capacity Ng et al (2012); Windapo and Cattell (2013).
91. Partnerships with local
and national stakeholders Ng et al (2012); Cserháti and Szabó (2014).
92. Profit-sharing Abdul-Aziz and Kassim (2011); Meng (2012).
93. Identifying stakeholders Yang et al (2009)
94. Social environment
Chan et al (2004); Iyer and Jha ( 2006); Park (2009); Yang et al (2009);
Chan et al (2010); Abdul-Aziz and Kassim (2011); Tan and Ghazali
(2011); Gudienė et al (2013); Yong and Mustaffa (2013); Gudienė et al
(2014).
95. Troubleshooting Gudienė et al (2013); Alias et al (2014); Gudienė et al (2014).
96. Project management was
systematic and
methodical
Davies (2002); Frimpong et al (2003); Nguyen et al (2004); Fortune and
White (2006); Wang and Huang (2006); Ng et al (2009); Park (2009); Yu
and Kwon (2011); Lehtiranta et al (2012); Son and Kim (2014).
97. Transaction cost
economics (preplanning) Park (2009); LI et al (2012); Son and Kim (2014).
98. Close relationship with
suppliers Orangi et al (2011); Ismail et al (2012).
99. Service quality can be
easily defined and
objectively measured
Ng et al (2012); Marzouk and El-Rasas (2014); Yang et al (2015).
100. Technological
environment
Bourne et al (2002); Davies (2002); Dvir and Lechler (2004); Nguyen et al
(2004); Chan et al (2004); Fortune and White (2006); Lu et al (2008);
Park (2009); Lu and Yuan et al (2010); Tan and Ghazali (2011); Omran
and Mamat (2011); Garbharran et al (2012); Gudienė et al (2013); Yong
and Mustaffa (2013); Zhao et al (2013); Verburg et al (2013); Windapo
and Cattell (2013); Alzahrani and Emsley (2013); Gudienė et al (2014);
Son and Kim (2014).
101. Skilled designers Aksorn and Hadikusumo (2008); Park (2009); Tan and Ghazali
(2011);Gudienė et al (2014); Locatelli et al (2014).
102. Staff qualification and
skills
Fortune and White (2006); Ng et al (2009); Park (2009); Tan and Ghazali
(2011); Chen et al (2012); Lehtiranta et al. (2012); LI et al (2012); Yong
and Mustaffa (2013); Alzahrani and Emsley (2013); Verburg et al (2013);
Windapo and Cattell (2013); Cserháti and Szabó (2014); Wibowo and
Alfen (2014).
103. Rework due to errors
during construction
Sambasivan and Soon (2007); Orangi et al (2011); Molenaar et al (2013);
Marzouk and El-Rasas (2014); Zavadskas et al (2014);
104. Litigation, disputes and
arbitrating tendency
Lu et al (2008); Park (2009); Molenaar et al (2013); Alzahrani and Emsley
(2013).
105.
The detailed project
plans are understood and
accepted by all project
team members
Andersen et al (2006); Iyer and Jha ( 2006); Chen and Chen (2007); Toor
et al (2008); Park (2009).
106. Foreign (external)
Experts’ Participation in Chan et al (2004a); Ling and Bui (2010); Chen et al (2012).
45
Table 2. 3: Summary of CSFs
No. Factor Resource
Projects
107. Having an explicit
competitive strategy Davies (2002); Lu et al (2008); Park (2009).
108. Competition
Hughes et al (2004); Park (2009); Ahsan and Gunawan (2010); Abdul-
Aziz and Kassim (2011); LI et al (2012); Ng et al (2012); Ihuah et al
(2014); Son and Kim (2014).
109. The costs of building
materials Frimpong et al (2003); Windapo and Cattell (2013).
110.
Delegation and allocation
of authority and
responsibility
Chan et al (2004a); Andersen et al (2006); ); Iyer and Jha ( 2006); Aksorn
and Hadikusumo (2008); Lu et al (2008); Park (2009); Chan et al (2010);
Alhaadir and Panuwatwanich (2011); Omran and Mamat (2011); Zawawi
et al (2011); Lehtiranta et al. (2012); Alzahrani and Emsley (2013);
Gudienė et al (2013); Verburg et al (2013); Gudienė et al (2014); Cserháti
and Szabó (2014); Zou et al (2014).
111. Sufficient resource
allocation
Chan et al (2004b); Fortune and White (2006); Aksorn and Hadikusumo
(2008); Park (2009); Alhaadir and Panuwatwanich (2011); Gudienė et al
(2014).
112. Waste management
system Lu and Yuan et al (2010); Son and Kim (2014);
113. Personal competency
Nguyen et al (2004); Fortune and White (2006); Toor et al (2008); Aksorn
and Hadikusumo (2008); Ahsan and Gunawan (2010); Omran and Mamat
(2011); Tan and Ghazali (2011); Garbharran et al (2012); Lehtiranta et al.
(2012); Gudienė et al (2013); Yong and Mustaffa (2013); Gudienė et al
(2014); Ihuah et al (2014); Cserháti and Szabó (2014).
114.
Selection of PM with
proven track record at an
early stage by top
management
Iyer and Jha ( 2006); Omran and Mamat (2011).
115. Personal attitude and
issues
Bourne et al (2002); Dvir and Lechler (2004); Iyer and Jha ( 2006);
Aksorn and Hadikusumo (2008); Alhaadir and Panuwatwanich (2011);
Omran and Mamat (2011); Gudienė et al (2013); Verburg et al
(2013);Gudienė et al (2014).
116. Good governance
(government policy)
Ng et al (2009); Chan et al (2010); Ng et al (2012); Wibowo and Alfen
(2014).
117.
The project is part of a
well-documented or
understood strategy
Davies (2002); Dvir et al (2003); Hughes et al (2004); Andersen et al
(2006); Toor et al (2008); Park (2009); Yu and Kwon (2011); Lehtiranta et
al (2012); Alzahrani and Emsley (2013); Ihuah et al (2014); Son and Kim
(2014); Mir and Pinnington (2014); Zavadskas et al (2014).
118. Research and
development
Davies (2002); Lu et al (2008); Ng et al (2009); Lu and Yuan et al (2010);
Chan et al (2010); Ismail et al (2012).
119.
A team leader or
champion was appointed
to ensure that partnering
principles did not slip out
of focus
Chan et al (2004a)
120. Government Officers’
Participation in Projects
Hughes et al (2004); Ling and Bui (2010); Chan et al (2010); Locatelli et
al (2014); Wibowo and Alfen (2014).
46
Table 2. 3: Summary of CSFs
No. Factor Resource
121.
Realistic time forecasting
and schedule
management
Bourne et al (2002); Dvir et al (2003); Fortune and White (2006);
Andersen et al (2006); Meeampol and Ogunlana (2006); Lu et al (2008);
Ng et al (2009); Park (2009); Abdul-Aziz and Kassim (2011); Famakin et
al (2012); Hwang et al (2013); Gudienė et al (2013); Molenaar et al
(2013); Gudienė et al (2014); Ihuah et al (2014); Marzouk and El-Rasas
(2014); Zavadskas et al (2014)
122. Economic viability
environment
Chan et al (2004); Iyer and Jha ( 2006); Enshassi et al (2009a); Chan et al
(2010); Ahsan and Gunawan (2010); Tan and Ghazali (2011); Ng et al
(2012); Windapo and Cattell (2013); Gudienė et al (2013); Yong and
Mustaffa (2013); Zhao et al (2013); Gudienė et al (2014); Son and Kim
(2014); Wibowo and Alfen (2014);
123. Adequacy and
management of resources
Frimpong et al (2003); Dvir et al (2003); Nguyen et al (2004); Hughes et
al (2004); Iyer and Jha ( 2006); Meeampol and Ogunlana (2006);
Sambasivan and Soon (2007); Chen and Chen (2007); Lu et al (2008); Ng
et al (2009); Lu and Yuan et al (2010); Omran and Mamat (2011); Orangi
et al (2011); Garbharran et al (2012); Ismail et al (2012); LI et al (2012);
Chen et al (2012); Lehtiranta et al (2012); Gudienė et al (2013); Alzahrani
and Emsley (2013); Yong and Mustaffa (2013); Verburg et al (2013);
Hwang et al (2013); Memon et al (2013); Gudienė et al (2014); Ihuah et al
(2014); Son and Kim (2014); Mir and Pinnington (2014); Marzouk and El-
Rasas (2014); Yang et al (2015).
124. Adaptability to changes,
management of Changes
Dvir et al (2003); Chan et al (2004); Andersen et al (2006); Fortune and
White (2006); Chen and Chen (2007); Cho et al (2009); Ng et al (2009);
Chen et al (2012); Gudienė et al (2013); Yong and Mustaffa (2013);
Gudienė et al (2014); Yang et al (2015).
125.
Client ability on brief,
define roles and make
decisions
Chan et al (2004); Iyer and Jha ( 2006); Cho et al (2009); Tan and Ghazali
(2011); Lehtiranta et al (2012); Gudienė et al (2013); Hwang et al (2013);
Gudienė et al (2014); Son and Kim (2014); Marzouk and El-Rasas (2014);
47
2.4 Relationship between KPIs and CSFs
2.4.1 KPIs and CSFs relationship on developing countries studies
In Ghana Frimpong et al (2003) conducted a research to investigate the CSFs affect the
KPIs time and cost in the construction of groundwater projects. They found the critical
factors which lead to delay and cost overrun in developing countries which were: poor
contractor management, monthly payment difficulties from agencies, material
procurement, poor technical performances, and escalation of material prices according to
their degree of influence.
In Thailand by Meeampol and Ogunlana (2006) aimed to study the factors affecting cost
and time performance on highway construction projects. On their investigation of CSF’s
they concluded that some factors, such as complexity, do not contribute significantly to
project success or failure. They also found that supervision and control, owner
involvement and design effectiveness, are not significant predictors of cost performance
on projects. However, better supervision and control and less owner interference can
reduce construction duration. They also indicated that the most important factors in
discriminating between success and failure on projects are managerial practices factors.
They indicated that change in goals, plans or priorities lead to variations in project stages
and performance.
Another study on India done by Iyer and Jha (2006) to figure out the CSFs affecting cost
KPI of Indian construction projects. They indicated that the factors which adversely
affecting the cost performances of projects were: conflict among project participants;
ignorance and lack of knowledge; presence of poor project specific attributes and non-
existence of cooperation; hostile socio economic and climatic condition; reluctance in
timely decision; aggressive competition at tender stage; and short bid preparation time.
Results showed that coordination among project participants was the most significant of
all the factors and had the maximum positive influence on cost performance.
In Malaysia Sambasivan and Soon (2007) conducted a study to identify the CSFs which
effects time KPI in Malaysian construction industry. They indicated ten critical factors
caused delay in Malaysian projects which were: (1) contractor’s improper planning, (2)
48
contractor’s poor site management, (3) inadequate contractor experience, (4) inadequate
client’s finance and payments for completed work, (5) problems with subcontractors, (6)
shortage in material, (7) labor supply, (8) equipment availability and failure, (9) lack of
communication between parties, and (10) mistakes during the construction stage. Also
they investigated six main effects of delay on project performance were: (1) time overrun,
(2) cost over-run, (3) disputes, (4) arbitration, (5) litigation, and (6) total abandonment.
In Taiwan Chen and Chen (2007) held a study to distinguish between CSFs based on
their degrees of importance in relation to KPI of PPP projects. They identified 19 CSFs
and divided them into four clusters. They concluded that the most important cluster being
collaborative team culture, followed by a long-term quality focus, consistent objectives,
and finally resource sharing.
In United Arabs of Emirates Mir and Pinnington (2014) tested the relationship between
project management PM performance as CSF and project KPIs. In their research, they
demonstrated that PM performance is correlated to project success. And they concluded
that by paying greater attention to this relationship, originations can enhance their
projects performance.
On China Lu et al (2008) conducted study to utilize the CSF approach to identify a few
manageable but vital factors contributing to the overall competiveness of a contractor as
KPI. They indicated that there were 35 success factors contributing to enhancing a
contractor’s competitiveness in the Chinese construction market. They used factor
analysis and generated eight clusters from the 35 CSFs which namely “project
management,” “organization structure,” “resources,” “competitive strategy,”
“relationship.” “bidding,” “marketing,” and “technology”. The most important factors as
the study revealed were “winning enough contracts by adopting successful bidding
strategy,” “having an explicit competitive strategy,” and “developing a good relationship
with the government".
In Korea Cho et al (2009) studied the relationship between project performance and a
project’s characteristics as CSF. They categorized the project characteristics as project
characteristics, owner characteristics, contractor characteristics, and environment
49
characteristics. Results of study showed that the project characteristics positively
influenced the cost growth and negatively influenced the award rate and ‘construction
speed. Also, the contractor characteristics positively influenced the unit cost, cost growth
and the schedule whereas the owner characteristics, negatively influenced the schedule
growth and positively influenced the ‘construction speed. Finally, the environmental
characteristics positively influenced the unit and negatively influenced the schedule
growth and construction speed.
In Gaza strip Enshassi et al (2009a) conducted study to identify the factors affecting the
performance of local construction projects. They found out the most important factors
affecting project performance are: delays because of borders/roads closure leading to
materials shortage; unavailability of resources; low level of project leadership skills;
escalation of material prices; unavailability of highly experienced and qualified
personnel; and poor quality of available equipment and raw materials.
In Malaysia Omran and Mamat (2011) studied cost performance as KPI of construction
projects in Kelantan state located in the east-coast part of Malaysia. The results of their
research indicated that the CSFs affecting the cost performances were identified as
project manager competence in works affecting cost performance. And they concluded
that commitment responsibilities of all participants and various teams to the project was
the top CSF while presence of poor project specific attributes and not existence of
cooperate and ignorance and lack of knowledge in operating, techniques and decision by
project manager were identified as the most important failure factors.
In Taiwan, Indonesia and Vietnam Chou et al (2013) conducted study to determine the
effects of project management body of knowledge techniques/ tools/ skills (TTSs) on
project success. They defined project objectives as success criteria that are quantifiable in
terms of time, cost, and quality. They used Structural equation modeling was used to
determine the effects of PMBOK techniques/tools/skills (TTSs) on project success. they
formulate a model and concluded that TTSs improve project success, enhancing project
performance, and improving the efficient use of management resources.
50
In Korea Son and Kim (2014) endeavored to develop a model to predict the cost and
schedule KPIs of green building projects based on the CSF "the level of definition during
the pre-project planning phase". They reported that the cost and schedule performance of
green projects is highly dependent on the quality of definition in the pre-project planning
phase. they proposed models that could be utilized to credibly assess the cost and
schedule performance based on the 64 factors derived from successful and unsuccessful
projects. They divided the factors into 11 categories, which in turn are grouped into three
sections: basis of project decision, basis of design, and execution approach.
In Malaysia Shehu et al (2014) explored the construction cost as KPI of projects in terms
of project characteristics as CSFs. They categorized project characteristics as project
sector (public or private), nature of project (new build or refurbishment), procurement
methods (traditional, design and build, and project management), nature of project
(residential, infrastructure, commercial, office, educational, and health), tendering
method (open, selected and negotiated), and project size (small, medium, large and very
large ). They established that more than half of Malaysian construction projects (55%)
experienced cost overruns. They also founded that public sector projects performed better
than private sector projects, also design and build projects was associated with reduced
cost overrun, and small and large projects performed better than medium and very large
projects.
Another study in Malaysia done by Alias et al (2014) to identify the extent of the
relationship between CSFs and project performance. They developed conceptual
framework and grouped 61 CSF’s for project success in five variables and they were
project management action, project procedures, human factors, external issues and
project related factors.
In Taiwan also Yang et al (2015) searched on their study the roles of the CSFs
interpersonal conflict, product advantage, and project type in the relationship between
requirement quality and stability in terms of project performance and market
performance. Their results showed that the positive association between requirement
quality and stability and project performance depends on number of groups, the
relationship is stronger for projects with fewer groups than it is for those with more
51
groups. Also they investigated that training and continuous improvement is critical to
requirement definition and management implementation.
2.4.2 KPIs and CSFs relationship on developed countries studies
In UK Andersen et al (2006) studied the relationship between project success factors and
actual KPIs. They found that the most important factors in improving managerial ability
to deliver results in time and at cost were strong project commitment, early stakeholder
influence, stakeholder endorsement of project plans and rich project communications.
In New Zealand Ahsan and Gunawan (2010) applied a study to investigate the major
causes of project delay. They studied 100 project in Asian countries. Their study results
revealed that the root causes of project delay and cost underrun together were long
duration of contract, procurement, civil works and land acquisition, and consultant
recruitment. And the critical causes of project delay were attributed to natural calamities
and host country bureaucracy. Finally they found the main reasons of cost under-run were
categorized as devaluation of local currency, competitive bidding price, lower then
estimated bid, and large contingency budgets.
In Australia and Victoria Orangi et al (2011) aimed to study specific cost overrun and
time overrun issues in the linear construction projects for utility services infrastructure.
They identified the factors which causes time and cost overrun as (i) design changes, (ii)
design errors (including ambiguities and discrepancies of details/ specifications), (iii)
design submission delays, (iv) lack of communication between designers and contractors,
(v) lack of communication between client and project team, (vi) customer/ end-user
related issues, (vii) inadequate geotechnical investigations, (viii) issues regarding client
approvals, (ix) issues regarding permissions/ approvals from other stakeholders, (x)
adverse weather conditions, (xi) delays by materials suppliers, (xii) poor site management
practices, (xiii) planning and scheduling errors, (xiv) construction rework, (xv) cultural
and heritage management issues, (xvi) subcontractor issues.
In Singapore, Hwang et al (2013) identified the critical factors affecting schedule
performance of public housing projects as site management, financing by contractors,
coordination among parties, preparation of schedule plans and updates, experience of
52
contractors, experience of consultants, construction methods, foundation conditions,
speed of decision making of owners, financing by owners during construction, design
changes by owners during construction, experience of owners, project duration set by
owners, availability of laborers on site, availability of staff to manage projects,
availability of equipment, availability of material, Availability of site.
In Lithuania Zavadskas et al (2014) applied a research to analyze common project
management problems and the success factors of construction projects by aggregating
performance indicators. They indicated ten performance indicators namely project
profitability, estimate of project expenditures, income for one executive, number of
accidents during project implementation, repetitive important non conformities in project
quality audits, delay of project close, budget compliance, management of documentation,
environmental project appraisal and personnel risk. They also indicated 13 management
problem. Results of Zavadskas et al (2014) study showed that by using the aggregated
indicators it was easy to compare the projects, the received impartial information was
useful for strategic planning, quality management, for solving the tasks of resource
allocation and motivational project evaluation.
2.5 Summary
The main objectives of this study are to identify and evaluate of the key performance
indicators (KPIs) as a success criteria, to investigate the critical success factors CSFs
affecting the public construction projects and to evaluate the relationship between KPIs
and CSFs in the public construction projects. First section of this chapter conducted
studies to identify briefly KPIs in both developing and developed countries studies. Table
(A 1) in Appendix I summarizes these studies. Second section reviewed studies
concerned about CSFs in developing and developed countries. Table (A 2) in Appendix I
summarizes these studies. In the third section studies about the relationship between
CSFs and KPIs were mentioned. Table (A 3) in Appendix I.
Chapter 3
Research Methodology
54
3. Chapter3: Research Methodology
This research was designed to investigate the success factors that affecting public
construction projects and their relation to key performance indicators; Palestine as case
study. This chapter discusses the methodology which was used in this research. The
research methodology was chosen to achieve the research aims and objectives that to
identify the key performance indicators (KPIs) as a success criteria, to investigate the
critical success factors CSFs affecting the public construction projects and to evaluate the
relationship between KPIs and CSFs.
3.1 Research framework
This study employed a quantitative data. The researcher designed the research by seven
main steps as described below and shown in Figure 3.1.
First step: Theme identification (Problem definition)
It was initiated to define the problem, set the objectives and develop the research plan.
Second step: Literature review
About one hundred published article were reviewed from 38 international journals. And
about 31 KPIs and 125 CSFs were derived.
Third step: Questionnaire development
The pilot study includes two parts. The first part was undertaken by consulting 5 experts
in construction; academic associated doctors, governmental and international
professionals to pre-test the survey and subsequently modified before a final version was
produced. After this, the second part was accomplished by making analysis trial using
some of the population sample for validation before the main survey. The questionnaire
was modified based on the results of the pilot study and the final list of questions was
adopted to be used for the study.
55
Fourth step: The main survey
In this step of the survey, a quantitative approach was utilized as the main statistical
component in the study, to obtain qualitative data using postal questionnaire. An
extensive sampling strategy will be used to ensure meaningful statistical analysis, which
included distributing the questionnaire to the target groups. In order to obtain reliable and
representative quantitative data, the questionnaires will be distributed to four categories
of community members in different positions and disciplines (i.e. NGOs representatives,
construction consultants, esteemed persons, governmental representatives). Moreover, the
targeted group will be from different education levels, ages and work experience years.
Fifth step: Results and discussion
Data collected will be analyzed using both descriptive and inferential tools of statistical
software Statistical Package for Social Science (SPSS 22).
Sixth step: Conclusion and recommendations
This phase of the research included the conclusions and recommendations.
Seventh step: documentation
The final phase of the research included editing the final text, formatting and spelling
and grammatical review.
56
Figure 3. 1: Framework of the research methodology
Stage 5:
Results and
discussions
Distributed 211 electronically
questionnaire in West Bank.
Distributed 173 electronically and paper
questionnaire in Gaza Strip.
Stage 6:
Conclusion and
recommendation
Results Summary with related objectives.
Identifying problem areas from results.
Proposing applicable solution.
Final List of
recommendations
Stage 7:
Documentation
Editing the final text.
Formatting.
Spelling and grammatical review etc.
Final thesis
Activities Stage Deliveries
Stage 1:
Problem definition
Extensive search on recent researches.
Conference topics.
Experts advice.
Setting specific
aim and
objectives
Stage 3:
Questionnaire
development
Interviews with
5 experts to
modify the
questionnaire.
Final modified
questionnaire
Stage 2:
Literature review
Review journals papers.
Review conferences papers
Review thesis.
Initial draft of
questionnaire
Main pilot study by
participating 20
construction experts
to pre-test the
survey.
Stage 4:
Main survey
274 filled
questionnaires
received back
SPSS to perform
quantitative data
Reliability and
validity tests.
Descriptive analysis,
Ranking (RII) and
non-parametric tests.
Factor analysis,
Correlation and
regression analysis.
Obtaining
proposed
objectives
Explaining,
comparing
results and
linking with
previous
studies
57
3.2 Research period
The study started on May 2014 after the proposal was approved. The literature review
was completed at the end of November 2014. The validity testing, piloting and
questionnaire distribution and collection completed at the beginning of August 2015. The
analysis, discussion, conclusion and recommendation were completed at the January
2016.
3.3 Rationale of use quantative approach
The related fieldwork data to this research were collected by using a structured
questionnaire survey which was considered the most widely used data collection
technique for conducting surveys since most of the literature mentioned studies as shown
in Table 3.1. Using postal questionnaire is mostly suited to surveys whose purpose and
objectives are clear enough to be explained in a few paragraphs which are carefully
chosen and guaranteed in this research. Moreover it offers relatively high validity of
results and a quick method of conducting the survey. Therefore the researcher adopted
this strategy.
By surveying the relevant studies mentioned in the literature review, it was obtained that
there were different methodologies and data collection approaches used in order to
achieve the required target, goals and objectives. The collection data methods include
postal quesrionnaire, case study appoach, interviews, focus groups, documents review,
and workshops. Table 3.1 showed the surveyed studies and the adopted corresponding
methodologies. In this study litratures reviews and postal questionaire were used to
collect data.
58
Table 3. 1: Research methods for previous studies
Research methods Research studies
Postal questionnaires
Bourne et al (2002); Dvir et al (2003); Frimpong et al (2003);
Nguyen et al (2004); Dvir and Lechler (2004); Chan et al (2004a);
Bryde and Robinson (2005); Wang and Huang (2006); Meeampol
and Ogunlana (2006); Andersen et al (2006); Iyer and Jha ( 2006);
Sambasivan and Soon (2007); Chen and Chen (2007); Lu et al
(2008); Aksorn and Hadikusumo (2008); Ahadzie et al (2008); Toor
and Ogunlana (2008); Enshassi et al (2009a); Omran and Mamat
(2011); Hwang et al (2013); Ali et al (2013); Ng et al (2009); Yang
et al (2009); Park (2009); Chan et al (2010); Lu and Yuan et al
(2010); Alhaadir and Panuwatwanich (2011); Adnan et al. (2011);
Abdul-Aziz and Kassim (2011); Yu and Kwon (2011); Yang et al
(2011); Al-Tmeemy et al (2011); LI et al (2012); Garbharran et al
(2012); Jagboro et al (2012); Yang et al (2012); Ismail et al (2012);
Lehtiranta et al. (2012); Meng (2012); Ng et al (2012); Chen et al
(2012); Famakin et al (2012); Chou et al (2013); Memon et al (2013);
Yong and Mustaffa (2013); Alzahrani and Emsley (2013); Windapo
and Cattell (2013); Lam et al (2007); Berssaneti and Carvalho (2014);
Gudienė et al (2014); Shehu et al (2014); Mir and Pinnington (2014);
Son and Kim (2014); Cserháti and Szabó (2014); Zou et al (2014);
Wibowo and Alfen (2014); Yang et al (2015).
Case study
Shenhar et al (2001); Bourne et al (2002); Chan and Chan (2004);
Hughes et al (2004); Fortune and White (2006); Aksorn and
Hadikusumo (2008); Cho et al (2009); Abdul-Aziz and Kassim
(2011); Zawawi et al (2011); Orangi et al (2011); Shehata and El-
Gohary (2012); Zavadskas et al (2014); Locatelli et al (2014); Fink
(2014).
Interviews
Bourne et al (2002); Dvir et al (2003); Chan et al (2004b); Hughes et
al (2004); Chan and Chan (2004); Ojiako et al (2008); Toor and
Ogunlana (2008); Lu and Yuan et al (2010); Orangi et al (2011);
Abdul-Aziz and Kassim (2011); Tan and Ghazali (2011); Ng et al
(2012); Windapo and Cattell (2013); Verburg et al (2013); Zhao et al
(2013); Alias et al (2014); Zou et al (2014).
Delphi survey and
brainstorming Yeung et al (2009); Yu and Kwon (2011); Locatelli et al (2014)
Secondary data Shenhar et al (2001); Ahsan and Gunawan (2010); Tan and Ghazali
(2011); Zhao et al (2013); Ihuah et al (2014).
Literatures reviews
Chan et al (2002); Chan and Chan (2004); Chan et al (2004b); Turner
and Müller (2005); Tan and Ghazali (2011); Gudienė et al (2013);
Molenaar et al (2013); Zhao et al (2013); Alias et al (2014).
3.4 Research location
The research was carried out in Palestine territory, in both Gaza Strip and West Bank.
59
3.5 Research population and sample
In this part sample elements, research population, research sample and sample procedure
will be determined.
3.5.1 Research sample elements
The research sample elements consists of construction professionals who can defined in
this study as "civil or architectural engineers who works as project managers, designers
or field supervisors and have more than five years experience in construction projects".
The questionnaire submitted only to those construction professionals.
3.5.2 Research population categories
The research population was mainly limited to three categories: (1) Governmental
organizations, (2) Non-governmental organizations (NGOs) and (3) Engineering
consultants offices. In which, the first category represents local government perspective
and the last two categories represent the local community perspective. In total, the
research population accounted for 1924 engineer.
First category; Governmental organizations: In Gaza Strip and West Bank, there were
several ministries which employed designers, field engineers and project managers that
the researcher targeted three ministries to fill out the questionnaire which were ministry
of public works and housing (MPWH), ministry of education (MOHE); ministry of local
government (MOLG). The selection of those ministries based on their important and
main role in supervising the construction public projects. The population of these
ministries is limited to construction professionals and there total were 226 engineers as
shown in Table 3.2.
Second category; Non-governmental organizations (NGOs): Several NGO's
supervised the public construction projects. But the main there were two associations
targeted only in this study namely united nations relief and works agency (UNRWA) of
Palestinian refugees and united nations development programme (UNDP). The researcher
targeted these agencies only because they are the most and the biggest NGO's which
60
responsible beside the government to supervise most of public construction projects in
Palestine. The population of these agencies is limited to construction professionals and
there total were 230 engineers as shown in Table 3.2.
Third category: Engineering consultants offices: The number of engineering
consultants offices registered in engineering associations on Gaza was 168 offices
(Engineering Association Gaza center, 2015) and in West Bank was 199 office
(Engineering Association Jerusalem center, 2015). The population of these offices is
limited to construction professionals and their number in each office nearly 4 engineers
(Engineering Association Gaza center, 2015), so the population is 1468 engineers for all
offices as shown in Table 3.2.
3.5.3 Sample size
Study sample is a subset of population selected to participate in a research study and its
size refers to the number of the elements to be included in a study, which can be
individuals, groups or organizations (Zikmund et al, 2009). The aim of determining an
adequate sample size is to estimate the population prevalence with a good precision
(Naing et al, 2006). It is extremely rarely possible to conduct full population surveys so
that, a sample can be chosen from the study population that is commonly referred to as
the ‘target population’ (Malhotra and Birks, 2006). The most advantage of using sample
is that it is less time and less costly than collecting data from all of the population.
Otherwise, the disadvantage of using sample is that the selected sample may not
adequately representative of the population and the results obtained from it cannot be
generalized (Marczyk et al, 2005). The principles of statistical sampling which guarantee
a representative sample are employed for economy and speed (Fellows and Liu, 2008).
Several factors can influence the size of the required sample for a study, including the
purpose of the study, population size, sample sizes used in similar studies, the risk of
selecting a “bad” sample, and the allowable sampling error and resource constraints
(Israel, 2013). A statistical calculation approach have been used in this study to calculate
the required sample size. Table 3.2 showed the sample size used on this research. The
61
following formulas was used to determine the sample size of unlimited population (Israel,
2013; Creative research system, 2015).
For infinity population 𝑆𝑆 =𝑍2×𝑃×(1−𝑃)
𝐶2 =1.962×0.5×(1−0.5)
0.052 = 384
Where:
SS: The sample size
Z: Z value (e.g. 1.96 for 95% confidence interval)
P: Percentage picking a choice, expressed as decimal, (0.50 used for sample size needed)
C: Confidence interval expressed as decimal (0.05)
Generally, the confidence interval is the plus or minus figure usually reported in
newspaper or television opinion poll results (Creative research system, 2015). The
general rule relative to acceptable margins of error (a precision ) in categorical data
research is 5% (Israel, 2013). In this study, the population was 1924, and the ratio
between the obtained sample size and the population equals to 0.2 (384/1924) which is
larger than 0.05, then corrected sample size for finite population can be used. For that ,
the sample size for this study was calculated as follows,
𝑆𝑆𝑁𝑒𝑤 =𝑆𝑆
1 +𝑆𝑆 − 1
𝑃𝑜𝑝
=384
1 +384 − 1
1924
= 320.24 = 321
Where: pop is the total population
The method of sampling followed in this research was stratified random sampling. The
population were divided into different sub-populations or categories in order to obtain a
sample that is representative of the population. The stratified sample was obtained by
taking samples from each category which calculated by the following equation (Creative
research system, 2015):
(𝑆𝑆)𝑖 =(𝑃𝑜𝑝)𝑖
𝑅𝑒𝑠𝑒𝑎𝑟𝑐ℎ 𝑃𝑜𝑝𝑢𝑙𝑎𝑡𝑖𝑜𝑛× 𝑅𝑒𝑠𝑒𝑎𝑐ℎ 𝑆𝑎𝑚𝑝𝑙𝑒 𝑠𝑖𝑧𝑒
Where:
(SS)i: The sample size of category i
(Pop)i: Population of category i
An example for MPWH in Gaza Strip, the sample size was calculated as following:
62
(𝑆𝑆)𝑀𝑃𝑊𝐻/𝐺𝑎𝑧𝑎 =47
1924× 321 = 7.8 ≈ 8
The sample size formulas used above provide the number of responses that need to be
obtained in study. Israel (2013) reported that, many researchers commonly increased the
sample size about 10% to 30% , to compensate for persons that the researcher is unable to
contact and for nonresponse. Thus, the number of distributed questionnaires can be
substantially larger than the number required for a desired level of confidence and
precision. So that, in this study, 384 questionnaires which was the sample before
correction to be distributed to the targeted sample which represented 17.2% of the sample
size after correction.
3.5.4 Sampling procedure
A sample design “sampling procedure” refers to the technique or the procedure the
researcher would adopt in selecting items for the sample (Kothari, 2004). In this study,
the population consisted of three groups which were the first, second and third groups,
then, more complicated sampling method should be adopted to select the questionnaire
respondents. Zikmund et al. (2009) pointed out that, in stratified random sampling, a
subsample is drawn using simple random sampling within each stratum. This method is
one of the random sampling techniques and yields precise estimation and more accurate
than those produced by simple random sampling; particularly, when the sampling frame
is available in the form of a list (Kothari, 2004). According to Love et al (2013) there are
two main benefits can be obtained from using stratified sampling method, which are:
1. Ensuring adequate and representative respondents in each category under study is
acquired.
2. Ensure that the respondents within the same category are homogeneous.
The discussion above forced the researcher in this study to adopt the stratified random
sampling method to select a representative for the study population. Table 3.2 describes
the sampling numbers and percentages used in this study. Also the number of the
returned questionnaires and percent are presented in this table. It was cleared that only
274 questionnaire were collected which was less than the sample size 321 due to several
63
reasons like using electronic questionnaire only in West Bank since the researcher can
not have permission to go there within study period. Also many of targeted elements
hadn't enough time to response. However the total returned percent is considered to be
acceptable since it is nearly 71.35%.
Table 3. 2: Sample size for each of the research population categories
Category
pla
ce o
f w
ork
Po
pu
lati
on
Sam
ple
siz
e
No
. o
f
dis
trib
ute
d
qu
esti
onn
aire
s
Ret
urn
ed
qu
esti
onn
aire
s
% R
etu
rned
qu
esti
onn
aire
s
Governmental
organizations
Gaza
Strip
MPWH 47 8 10 10 100%
MOLG 4 1 2 2 100%
MOHE 5 1 2 2 100%
West
Bank
MPWH 103 17 22 16 72.72%
MOLG 37 6 9 6 66.67%
MOHE 30 5 8 5 62.50%
NGOs Gaza
Strip
UNRWA 105 17 22 18 81.82
UNDP 17 3 4 3 75%
West
Bank
UNRWA 77 13 16 13 81.25%
UNDP 31 5 8 6 75%
Engineering
consultants
offices
Gaza Strip 672 113 112 99 74.44%
West Bank 796 133 133 94 63.51%
Total in Gaza Strip 850 142 173 134 77.46%
Total in West Bank 1074 179 211 140 66.35%
Total 1924 321 384 274* 71.35%
3.6 Questionnaire Design
The questionnaire design was extracted from previous studies in developing countries
and developed countries directly related to the subject of this research. After a long time
of searching, consulting, modifying and reviewing by the supervisor and experts the
questionnaire was established and ready for distribution. The questionnaire was designed
in both English and Arabic languages in order to facilitate the understanding of content
for the concerned population sample. The first page in the questionnaire was a covering
letter that explained the study purpose, aim and the information security.
The questionnaire consisted of close-ended (multiple choice) items. Close-ended
questions are more difficult to design than open-ended items, but they come up with
64
much more efficient data collection, processing and analysis (Bourque and Fielder,
2003). Bourque and Fielder (2003) said that “surveyors should avoid using open-ended
questions in mail and other self-administered questionnaires”. The questionnaire divided
into three main parts, which included (i) general information, (ii) key performance
indicators and (iii) the importance of critical success factors. The first questionnaire draft
was designed and reviewed by pilot study and based on the results, the questionnaire
framework was modified and refined (refer to Appendix II and Apendix III for the final
questionnaire design in English and Arabic respictively).
3.6.1 General information
The first part of the questionnaire consisted of general information. This part had two
segments, the first segment was for personal information of the respondent and the other
segment was about respondent's organization. The first segment included questions about
respondents jop title, working experience, proffesion, and their place of residant. The
second segment seeked some information about respondent organization such as; type,
working field and size of the organization.
3.6.2 Key performance indicators
The second part of the questionnaire consisted of three main fields which were:
1. KPIs degree of importance: The main objective of this field is to determine the
most important KPIs that should be measured to indicate the performance
situation of the project. Respondents asked to give their opinion about the
importance of 13 KPIs which derived from literature review and piloting study.
The items in this field of questionnaire were in statements format. Respondents in
this part were asked to rate each item on five-point likert item that required a
ranking from 1 to 5 according to that "1" not important, "2" low important, "3"
semi important, "4" important, and "5" very important". Where 1 represented
“lowest scale” and 5 represented “highest scale”. Wikipedia (2014) stated that a
Likert item is simply a statement that the respondent is asked to evaluate by
giving it a quantitative value on any kind of subjective or objective dimension,
with level of agreement/disagreement being the dimension most commonly used.
65
Well-designed Likert items exhibit "symmetry" in that they contain equal
numbers of positive and negative positions whose respective distances apart are
bilaterally symmetric about the "neutral"/zero value (whether or not that value is
presented as a candidate. A Likert scale is the sum of responses on several Likert
items.
2. Measuring practices for KPIs in Palestinian construction projects: The
objective of this field is to determine whether the 13 KPIs measured during the
project or not in order to test the effect of this practice on project success.
Respondents asked to give their opinion about the 13 KPIs. They asked wither
they measure them annually by five-point likert item which required a ranking
from 1 to 5 according to that "1" always, "2" Mostly, "3" sometimes, "4" rarely,
and "5" never. Where 1 represented “lowest scale” and 5 represented “highest
scale”.
3. Public construction projects KPIs evaluation: The main objective of this field is
to evaluate the situation of projects according to the KPIs. Respondents asked to
give their opinion about the 13 KPIs. They asked about their evaluation for the
actual KPIs in comparative to planned. The items in this part of questionnaire
were in statements format. Respondents in this part were asked to rate each item
on five-point likert item which required a ranking from 1 to 5 according to that
"1" much less, "2" less, "3" equal, "4" higher, and "5" very high". Where 1
represented “lowest scale” and 5 represented “highest scale”.
3.6.3 Critical success factors
Kerzner (2001) stated that the available life cycle phases of projects were Conceptual,
Planning, Testing, Implementation and Closure. Ng and Walker (2008) conducted a study
of project management leadership styles across life cycle stages of information
technology projects in Hong Kong. They divided projects life cycle into four phases
which were 1) project initiation & design, 2) development, 3) testing and production cut
over and 4) project acceptance. Another study conducted by Saad (2011) investigated the
factors impacting the project’s life cycle and he divided project life cycle into five phases
namely 1) conceptual planning and economics (feasibility study) Phase, 2) engineering
66
and functional design phase, 3) tender and award phase, 4) construction and completion
of the Project (implementation) phase and 5) operation and utilization phase. In this study
the researcher divided the collected CSFs divided into four phases which were:
1. CSFs related to project conceptualizing and preparation phase: this phase
contains 12 CSFs related to issues like project feasibility, type, size, priority and
so on which should be determined at the beginning of the project life cycle. Those
factors was collected from literature reviews such as Abdul-Aziz and Kassim
(2011); Yu and Kwon (2011) ; Yang et al (2011); Chen et al (2012); Ismail et al
(2012); Alzahrani and Emsley (2013); Hwang et al (2013) and Verburg et al
(2013) and from questionnaire piloting. The most important party in this phase is
client and most of the phase factors related to his behavior.
2. CSFs related to project planning and designing phase: this phase contains 19
CSFs related to plans, designs, codes, licenses, cost and time estimations,
consultants involvement and experience and so on. Those factors was collected
from literature reviews such as Lam et al. (2007); Windapo and Cattell (2013);
Chou et al (2013); Ihuah et al (2014); Wibowo and Alfen (2014); Zou et al
(2014); Mir and Pinnington (2014) and Locatelli et al (2014) and from
questionnaire piloting. The most important party in this phase is consultant and
most of the phase factors related to his behavior.
3. CSFs related to project tendering and contracting phase: this phase consists of
16 CSFs related to contracting management, criteria, experience, meetings and so
on. Those factors was collected from literature reviews such as Lam et al. (2007);
Molenaar et al (2013); Locatelli et al (2014); Mir and Pinnington (2014); Son and
Kim (2014); Shehu et al (2014); Alias et al (2014) and Yang et al (2015) and
from questionnaire piloting. The most important party in this phase is client and
most of the phase factors related to his behavior.
4. CSFs related to implementation phase: this phase contains 34 CSFs related to
project implementation monitoring, authorities, team commitment,
communications effectiveness and so on. Those factors was collected from
literature reviews such as Lam et al (2007); Famakin et al (2012); Ng et al
(2012); Garbharran et al (2012); Ali et al (2013); Alzahrani and Emsley (2013);
67
Hwang et al (2013); Verburg et al (2013); Molenaar et al (2013); Gudienė et al
(2014); Cserháti and Szabó (2014); Zavadskas et al (2014) and Mir and
Pinnington (2014) and from questionnaire piloting. The most important party in
this phase is contractor and most of the phase factors related to his behavior.
The items in this part of questionnaire were in statements format. Respondents in this part
were asked to rate each item on five-point likert item which required a ranking from 1 to
5 according to that "1" not important, "2" low important, "3" semi important, "4"
important, and "5" very important". Where 1 represented “lowest scale” and 5
represented “highest scale”.
3.7 Pilot study
In order to test the appropriateness, validity and reliability of the questionnaire before
committing to the complete sample population, a pilot study for the questionnaire was
conducted. It provides a trial run for the questionnaire, which involves testing the
wordings of question, identifying ambiguous questions, testing the techniques that used
to collect data, and measuring the effectiveness of standard invitation to respondents. The
pilot study was divided mainly in three stages which were:
The first stage: in this stage the questionnaire was consulted by experts who have more
than 15 years experience in construction projects and they have academic background in
questionnaires assessment.
The second stage: in this stage the questionnaire was conducted to limited group from
the targeted population by distributing the questionnaire conveniently to 20 respondents
selected randomly.
The third stage: in this stage the questionnaire analyzed using statistical tests in order to
check the questionnaire validity and reliability respectively.
3.7.1 Experts consultation
Before arbitrating the questionnaire from experts the researcher undertaken the following
steps:
Firstly the researcher summarize 125 CSFs from the literature and 31 KPIs and prepared
the first draft of the questionnaire.
68
Secondly: the supervisor review the questionnaire and he canceled the factors related to
PPP part which included 10 factors in order to limit the scope of the research and because
this type of projects not famous on Palestine.
Thirdly: the first draft of the questionnaire was prepared. First draft contained 13 KPIs
and 72 CSFs grouped in five groups namely: project related factors, stakeholders related
factors, external related factors, management practices related factors and relationships
and communications related factors.
Fourthly: Expert A got the first draft of the questionnaire and he suggested the following
general notes to be perform firstly before distribute the questionnaire to other experts:
1. The classification of the CSFs should change to fit project life cycle phases and this
modification was confirmed.
2. He suggest to take Palestine as case study not only Gaza Strip and this idea was
confirmed.
3. He also recommended to distribute the questionnaire electronically and hard copy
and this idea was also confirmed.
Fifthly: the second draft of the questionnaire was prepared and it contained 12 KPIs and
74 CSFs grouped in clusters according to projects life cycle. The questionnaire was
consulting 6 Palestinian experts who have more than 15 years experience in construction
projects to review the questionnaire and make adjustments that best fit the Palestinian
conditions. Table 3.3 showed some detailed information about the experts work and
their experience in construction projects. Each expert got a copy of the questionnaire for
revision, and after that the researcher discussed the notes with each expert. Each expert
developed his own notes for modification (see Table 3.4), and some notes were
confirmed by more than one expert. Each note were carefully considered in preparing
the final questionnaire. The changes undertaken by those experts and are summarized in
Table 3.6.
69
Table 3. 3: Detailed information for the consulted experts
No. Recent Work Related experience
Expert
A
Minister consultant for planning and
international cooperation. MPWH
Previous manager of tendering
department in MPWH.
Previous member in Khan Younis
municipality.
Ph.D. in civil engineering.
Expert
B
Associated Professor in civil
engineering. UCAS
Previous minister of public works and
housing ministry. Palestine.
Manager of engineering office at
UCAS university.
Expert
C
Consultant and expert in UNRWA, Gaza
and UNAMID, Sudan. 15 years' experience in the
international agencies.
Expert
D Assistant Professor in architecture. IUG
Previous minister of public works and
housing ministry. Palestine.
Former Dean of the Faculty of
Engineering at IUG.
Previous manager of engineering
office at IUG university.
Expert
E Assistant Professor in architecture. IUG
Renewable energy expert.
Expert
F
General manager of projects department.
MOLG Over 20 years' experience in the
municipal construction projects.
Table 3. 4: Questionnaire review notes gathered from experts
No. Notes
Expert
A
In general information part:
He suggested to cancel the question about the number of workers in respondent
organization. Confirmed.
In CSFs part:
He suggested to add the definition of CSF's at the beginning of the part.
Confirmed.
He modified several factors wordings.
He suggested to split the factor of "construction permits and detailed it".
He suggested to add 9 factors which were "Studying the level of acceptance of
local community to execute the project in their location", "Taking in consider
the operation and maintenance phase during project planning and designing
phase", "Documentation for all agreements of the preparation meetings in
details", "Visiting project location by all consultants and contractors before
filling out the bid form", " The client (his representative) interprets all project
requirements and location during the preparatory meeting of the bids ", " Giving
enough time for consultants and contractors to fill out the bid form", "
Continuous revision for the project shop drawings and approve them fast", "
Availability and execution of material handling plans" and " Involvement of the
consultant and the contractors in project operating and maintenance plan after
project execution" . All suggested factors confirmed to be added.
Expert
B
In general information part:
He suggested to use five likert scale for both periodically measure of indicator
and performance evaluation of organization projects. Confirmed.
70
Table 3. 4: Questionnaire review notes gathered from experts
No. Notes
He modified the indicator " Project conformity to sustainability and
environmental criteria" to be two indicators which were "Project conformity to
sustainability criteria" and "Project conformity to environment protection
standards during execution". Confirmed.
In CSFs part:
He modified several factors wordings.
He suggested to add two factors which were "Documentation for all agreements
of the preparation meetings in details" and " Documentation of project activities
clearly and through annual reports". The first added factor also confirmed with
expert A suggestion. The two factors were Confirmed to be added.
He suggested that the CSF's in the questioner should be ranked according to
their rationale weight. The researcher will take this suggestion into account in
data analysis phase.
Expert
C
In KPI part:
He suggested to modify the second indicator which was " Actual project time
comparing with scheduled" to be " Actual project execution time comparing
with scheduled". Confirmed.
He suggested to use five likert scale for both periodically measure of indicator
and performance evaluation of organization projects. Confirmed and it was the
same suggestion of Expert B.
He splited the indicator " Project conformity to sustainability and environmental
criteria" to be two indicators which were "Project conformity to sustainability
criteria" and "Project conformity to environment protection standards during
execution". Confirmed and it was the same suggestion of Expert B.
In CSFs part:
He modified several factors wordings.
He suggested to split the factor of "construction permits and detailed it".
He suggested to add two factors which were " Continuous revision for the
project shop drawings and approve them fast" and " Saving as built drawings of
the project". The first added factor also confirmed with expert A suggestion.
The two factors were Confirmed to be added.
Expert
D
The questionnaire is too long so that, in order to get real and valuable
information, participants should take enough time to fill it.
He suggested to split the questionnaire to three questionnaires for the project
owner, consultant and contractor. The researcher could not apply this
suggestion because it is will take a lot of effort and time and the questionnaire
in this targeted only experts and consultants.
Expert
E
In the front page of the questionnaire add the time required to fill the
questionnaire, do not write headings for the paragraphs, and write the researcher
email. Confirmed.
In General information part rearrange the questions related to the respondent
association together and the questions related to the respondent himself
together. Confirmed
She suggested to split the questionnaire according to engineers fields like
architectural, design, civil, ..etc.. The researcher could not apply this suggestion
because it is will take a lot of effort and time and the questionnaire in this
targeted only experts and consultants and they can answer all questions.
The questionnaire is too long so that, in order to get real and valuable
information, participants should take enough time to fill it.
71
Table 3. 4: Questionnaire review notes gathered from experts
No. Notes
Expert
F
He suggested to split the factor of "construction permits and detailed it".
The questionnaire is too long so that, in order to get real and valuable
information, participants should take enough time to fill it.
3.7.2 Distributing questionnaire to limited group
Many previous studies used less than 20 as the sample of pilot study such as (Enshassi,
2012; Ng et al, 2012; Mir and Pinnington, 2014). In this study the researcher distributed
the questionnaire to limited group consist of 20 person. The sample selected from the
population randomly in order to test the validity and reliability of the questionnaire.
3.7.3 Statistical results of pilot study
After the researcher collected the 20 questionnaire data analyzed using SPSS (22) in
order to test the internal validity and the reliability of the questionnaire. The validity
tested using Pearson correlation coefficient for both criterion and structural validity of the
questionnaire. The reliability tested using two types of tests the first was Half Split
Coefficient and the second was Cronbach’s Alpha Coefficient.
3.7.3.1 Criterion and structural validity of the questionnaire
The correlation coefficient for each domain items were significant at α = 0.01 or α = 0.05,
as shown in Table (A 4) in Appendix IV. It can be concluded that the paragraphs of the
questionnaire were consistent and valid to measure what it was set for.
3.7.3.2 Half Split Coefficient for reliability of the questionnaire
The normal range of corrected correlation coefficient is between 0.0 and + 1.0 As shown
in Table 3.5, all the corrected correlation coefficients values are between 0.835 and 0.879
and the general reliability for all items equal 0.907, and the significant (α ) is less than
0.05 so all the corrected correlation coefficients are significance at α = 0.05. It can be said
that according to the Half Split method, the dispute causes group are reliable.
72
Table3. 5: Split-Half Coefficient method
Field Half split coefficient
Key performance indicators KPI's 0.835
CSFs related to conceptualizing and preparation phase 0.864
CSFs related to planning and designing phase 0.859
CSFs related to tendering and contracting phase 0.851
CSFs related to implementation phase 0.879
Total 0.907
3.7.3.3 Cronbach’s Alpha Coefficient for reliability of the questionnaire
As shown in Table 3.6, The Cronbach’s coefficient alpha was calculated for the
questionnaire domains. The results were in the range from 0.847 and 0.912, and the
general reliability for all items equal 0.935. This range is considered high; the result
ensures the reliability of the questionnaire.
Table 3. 6: Reliability Cronbach's Alpha method
Field Cronbach's Alpha
Key performance indicators KPI's 0.85
Factors related to conceptualizing and preparation phase 0.89
Factors related to planning and designing phase 0.89
Factors related to tendering and contracting phase 0.86
Factors related to implementation phase 0.91
Total 0.94
3.8 Main questionnaire distribution
To sum up, 31 KPIs and 125 CSFs were identified from literature review. The final
questionnaire contain 13 KPIs and 81 CSFs after supervisor, researcher and experts
involved in the study participate in variety of comments include accepted, modifying,
adding, separating, merging and deleting some factors. The KPIs and CSFs are
summarized in Appendix V Tables (A 5) and Table (A 6). Table 3.7 summarized the
selected and omitted KPIs and CSFs and it was cleared all KPIs were modified in order to
fit Palestinian construction projects enviroment.
73
The researcher followed two methods to distribute the questionnaire which were
electronically and papers (by hand). The questionnaire were distributed only
electronically questionnaire in West Bank. The researcher had a list of telephones and
mobiles numbers of the targeted group and she phoned each one of them. The targeted
group sample as mentioned in section 3.5 was 384 questionnaire. In West Bank 211
questionnaire were distributed and 173 questionaire in Gaza Strip. From West Bank 140
person responded which represented 66.35% of total targeted group in West Bank. In
Gaza Strip 40 person responded electronically and 94 person responded on papers which
represented 77.46% of total targeted group in Gaza Strip. The total number of
respondents was 274 which represent 71.35% of the total targeted group.
Table 3. 7: Summary of factors and indicators selected and omitted
Comment types Remaining Factors Omitted Factors
KPIs
Selected 0
Modified 12
Added 1
Merged 9
Cancelled 10
Total used in the questionnaire 13
CSFs
Selected 13
Modified 46
Splitted 5
Added 9
Merged 31
Cancelled 29
Total used in the questionnaire 81
74
3.9 Quantitative data analysis using SPSS
A quantitative method was adopted in the current research, where quantitative methods of
data analysis can be of great value to the researcher who is attempting to draw
meaningful results from a large body of qualitative data. The main beneficial aspect is
that quantitative analytical approach provides the means to separate out the large number
of confounding factors that often obscure the main qualitative findings (Field, 2009).
SPSS 22 (Statistical Package for the Social Sciences) for Windows contains a broad
range of capabilities for the entire analytical process. The decision-making information
can quickly be generated by using powerful statistics, to understand and present the
results with tabular and graphical output, and share the results using a variety of reporting
methods. By using this software, the following tests were adopted in this study:
A. Descriptive Statistics:
1. Frequencies.
2. measures of central tendency (the mean)
3. Measurement of dispersion based on the mean (standard deviation)
4. Relative Important Index (RII)
5. Kolmogorov-Smirnov test of normality.
6. Factor analysis
B. The inferential statistics:
1. Pearson product-moment correlation coefficient/ Pearson's correlation coefficient
(a parametric test)
2. The sample independent t-test to find out whether there is a significant difference
in the mean between two groups (a parametric test).
3. Analysis of Variance One way ANOVA) test (a parametric test).
4. Cronbach's Alpha for Reliability Statistics.
5. Independent Samples T-test.
3.9.1 Reliability statistics
Reliability aimed to examine the quality of measurement. It was the "consistency" or
"repeatability" of the analysis. Polit and Hunger (1985) defined the reliability of an
instrument as "the degree of consistency which measures the attribute it was supposed to
75
be measuring". Reliability was typically assessed by one of two ways: (1) Internal
consistency - Precision and consistency of test scores on one administration of a test and
(2) Stability - Precision and consistency of test scores over time (test-retest).
The less variation an instrument produces in repeated measurements of an attribute, the
higher its reliability. Reliability can be equated with the stability, consistency, or
dependability of a measuring tool (Polit and Hunger, 1985). Period of two weeks to a
month is recommended between two tests. But, in this research, it was too difficult to ask
participants to respond to the questionnaire twice within short period since they were so
busy having full time works. In addition, it was hard for the researcher because it needs a
lot of time. Fortunately, statistician's stated that overcoming the distribution of the
questionnaire twice to measure the reliability could be achieved by using Cronbach Alpha
coefficient and Half Split method through the SPSS software.
3.9.1.1 Alpha-Cronbach coefficient
One of the most commonly used indicators of reliability analysis was Cronbach‟s alpha
coefficient. Its scale should be above 0.6 as stated by Hair et al and Pallant (cited in
Chan, 2008:77). This method was used to measure the reliability of the questionnaire
between each field and the mean of the whole fields of the questionnaire. The normal
range of Cronbach’s coefficient alpha value between 0.0 and + 1.0 (Field, 2009; Weiers,
2011), and the higher values reflects a higher degree of internal consistency. Its scale
should be above 0.7 as stated by Hair et al. and Pallant (cited in Chan, 2008:77). The
results of this test is shown in the pilot study section 3.7.
3.9.1.2 Half Split Method
This method depends on finding Pearson correlation coefficient between the means of
odd rank questions and even rank questions of each field of the questionnaire. Then,
correcting the Pearson correlation coefficients can be done by using Spearman Brown
correlation coefficient of correction. The corrected correlation coefficient (Consistency
coefficient) is computed according to the following equation:
𝐶𝑜𝑛𝑠𝑖𝑠𝑡𝑒𝑛𝑐𝑦 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 = 2𝑟
𝑟 + 1
Where: r is the Pearson correlation coefficient.
76
3.9.2 Validity statistics
Statistical validity of the questionnaire refers to the degree to which an instrument
measures what it is supposed to be measuring (Pilot and Hungler, 1985). Validity has a
number of different aspects and assessment approaches.
To insure the validity of the questionnaire, two statistical tests should be applied. The
first test is Criterion-related validity test (Pearson test) which measure the correlation
coefficient between each item in the field and the whole field. The second test is structure
validity test (Pearson test) that used to test the validity of the questionnaire structure by
testing the validity of each field and the validity of the whole questionnaire. It measures
the correlation coefficient between one filed and all the fields of the questionnaire that
have the same level of similar scale.
3.9.2.1 Pearson correlation coefficients for criterion related validity
Internal consistency of the questionnaire was measured by a scouting sample, which
consisted of 20 questionnaires, through measuring the correlation coefficients between
each paragraph in one field and the whole filed.
3.9.2.2 Pearson correlation coefficients for structure validity
Structure validity was the second statistical test that used to test the validity of the
questionnaire structure by testing the validity of each field and the validity of the whole
questionnaire. It measures the correlation coefficient between one filed and all the fields
of the questionnaire that have the same level of liker scale.
3.9.3 Kolmogorov-Smirnov Test of Normality
The One-Sample Kolmogorov-Smirnov test procedure compares the observed cumulative
distribution function for a variable with a specified theoretical distribution, which may be
normal, uniform, Poisson, or exponential. The Kolmogorov-Smirnov Z is computed from
the largest difference (in absolute value) between the observed and theoretical cumulative
distribution functions. This goodness-of-fit test tests whether the observations could
reasonably have come from the specified distribution. Many parametric tests require
77
normally distributed variables. The one-sample Kolmogorov-Smirnov test can be used to
test that a variable of interest is normally distributed (Henry and Thode, 2002).
Table 3.8 showed the results for Kolmogorov-Smirnov test of normality. From Table 3.8,
the p-value for each variable is greater than 0.05 level of significance, then the
distributions for these variables are normally distributed. Consequently, parametric tests
can be used to perform the statistical data analysis.
Table 3. 8: Kolmogorov-Smirnov test of normality
Field Kolmogorov-Smirnov
Statistic P-value
Key performance indicators KPI's of projects 0.951 0.327
CSFs related to conceptualizing and preparation phase 0.712 0.690
CSFs related to planning and designing phase 0.731 0.659
CSFs related to tendering and contracting phase 0.599 0.866
CSFs related to implementation phase 0.780 0.577
All paragraphs of the questionnaire 0.754 0.621
3.9.4 Relative Importance Index (RII)
In order to be able to select the appropriate method of analysis, the level of measurement
must be understood. For each type of measurement, there is/are an appropriate method/s
that can be applied and not others. In this research, ordinal scales were used. Ordinal
scale is a ranking or a rating data that normally uses integers in ascending or descending
order. The numbers assigned to the important (1,2,3,4,5) did not indicate that the interval
between scales are equal, nor do they indicated absolute quantities. They are merely
numerical labels. Based on Likert scale shown in questionnaire design section 3.6.
The relative importance index method (RII) was used to determine the ranks of all
factors. The relative importance index was computed as (Sambasivan and Soon, 2007;
AbuHamra, 2015):
𝑅𝐼𝐼 =∑ 𝑊
𝐴 × 𝑁
Where:
W = the weighting given to each factor by the respondents (ranging from 1 to 5)
A = the highest weight (i.e. 5 in this case)
N = the total number of respondents
78
The RII value had a range from 0 to 1 (0 not inclusive), the higher the value of RII, the
more impact of the attribute. However, RII doesn't reflect the relationship between the
various attributes.
3.9.5 Parametric tests:
Parametric test: a test that requires data from one of the large catalogue of distributions
that statisticians have described. Normally this term is used for parametric tests based on
the normal distribution, which require four basic assumptions that must be met for the
test to be accurate: a normally distributed sampling distribution (researcher can
approximate using a normal distribution after invoking the central limit theorem),
homogeneity of variance, interval or ratio data, and independence (Field, 2009).
3.9.5.1 One sample t test.
The t-test is a parametric test which is used to compare the difference between the mean
scores of two samples.
3.9.5.2 One way ANOVA.
If there are more than two independent groups being compared the one-way ANOVA is
used if the parametric assumptions are satisfied—that is, interval-scale variable
approximately normally distributed.
3.9.6 Factor analysis
Factor analysis is a generic term for a family of statistical techniques concerned with the
reduction of a set of observable variables in terms of a small number of latent factors. It
has been developed primarily for analyzing relationships among a number of measurable
entities (such as survey items or test scores). The underlying assumption of factor
analysis is that there exist a number of unobserved latent variables (or “factors”) that
account for the correlations among observed variables. In other words, the latent factors
determine the values of the observed variables (Doloi, 2009; Field, 2009). The main
applications of factor analytic techniques are:
1. Explore data for pattern.
79
2. Data reduction.
3. Confirm the hypothesis of data structure.
3.9.6.1 Types of factor analysis
1. Exploratory factor analysis (EFA), which is used to identify complex
interrelationships among items and group items that are part of unified concepts. The
researcher makes no “a priori” assumptions about relationships among factors.
2. Confirmatory factor analysis (CFA), which is a more complex approach that tests the
hypothesis that the items are associated with specific factors.
3.9.6.2 Methods of factoring
There are several methods for unearthing factors in data (Field, 2009):
1. Principal component analysis (PCA): is a widely used method for factor extraction,
which is the first phase of EFA. Factor weights are computed in order to extract the
maximum possible variance, with successive factoring continuing until there is no
further meaningful variance left. The factor model must then be rotated for analysis;
2. Canonical factor analysis, also called Rao's canonical factoring;
3. Image factoring;
4. Alpha factoring; and
5. Factor regression model
Principal component analysis (PCA) is the preferred method since it is usually result in
similar solution not like remaining methods which their conclusions are restricted to the
sample collected and generalization of the results can be achieved only if analysis using
different samples reveals the same factor structure. thus, Principal component analysis
(PCA) has been selected for factoring in this research to examine the underlying structure
or the structure of interrelationships among the variables.
3.9.6.3 The distribution of data
The assumption of normality is most important requirement to generalize the results of
factor analysis test beyond the sample collected (Field, 2009; Zaiontz, 2014).
80
3.9.6.4 Validity of sample size
The reliability of factor analysis is dependent on sample size. PCA can be conducted on a
sample that has fewer than 100 respondents, but more than 50 respondents. The common
rule is to suggest that sample size contains at least 10–15 respondents per item. In other
words, sample size should be at least 10 times the number of items and some even
recommend 20 times (Field, 2009; Zaiontz, 2014).
3.9.6.5 Validity of correlation matrix (correlations between variables)
It is simply a rectangular array of numbers which gives the correlation coefficients
between a single item and every other item in the investigation. The correlation
coefficient between a variable and itself is always 1; hence the principal diagonal of the
correlation matrix contains 1s. The correlation coefficients above and below the principal
diagonal are the same. PCA requires that there be some correlations greater than 0.30
between the items included in the analysis (Field, 2009; Zaiontz, 2014).
3.9.6.6 Kaiser-Meyer-Olkin (KMO) and Bartlett's Test as a measure of
appropriateness of Factor Analysis
The value of (KMO) can be calculated for individual and multiple items and represents
the ratio of squared correlation between items to the squared partial correlation between
items. It varies from 0 to 1. Interpretive adjectives for the Kaiser Meyer Olkin Measure of
Sampling Adequacy are: in the 0.90 as marvelous, in the 0.80's as meritorious, in the
0.70's as middling, in the 0.60's as mediocre, in the 0.50's as miserable, and below 0.50 as
unacceptable. A value close to 1 indicates that pattern of correlation is relatively compact
and hence factor analysis should give distinct and reliable results (Kaiser, 1974; Field,
2009; Zaiontz, 2014). Bartlett's test of sphericity tests the hypothesis that the correlation
matrix is an identify matrix; i.e. all diagonal elements are 1 and all off diagonal elements
are 0, implying that all of the items are uncorrelated. If the sig. value for this test is less
than alpha level, researcher must reject the null hypothesis that the correlation matrix is
an identity matrix (Field, 2009; Zaiontz, 2014).
81
3.9.6.7 Determining the number of factors
Determining the optimal number of factors to extract is not a straightforward task since
the decision is ultimately subjective. There are several criteria for the number of factors
to be extracted. The “eigenvalues greater than one” rule has been most commonly used
due to its simple nature and availability in various computer packages. The eigenvalue
(variance) criterion stated that each component explained at least one item's 's worth of
the variability, and therefore only components with eigenvalues greater than one should
be retained (Larose, 2006; Field, 2009).
After extraction of factors, Table of “communalities (common variances)” should be
examined to know how much of the variance in each of the original items is explained by
the extracted factors. If the communality for a variable is less than 50%, it is a candidate
for exclusion from the analysis because the factor solution contains less than half of the
variance in the original item, and the explanatory power of that variable might be better
represented by the individual item (Field, 2009; Zaiontz, 2014).
Components are then rotated via varimax rotation approach to assist in the process of
interpretation and to discover the best distribution of the better loading components in
terms of the meaning of the components. This does not change the underlying solution, or
the relationships among the items. Rather, it presents the pattern of loadings in a manner
that is easier to interpret factors/ components (Factor loading: the regression coefficient
of an item/ a variable for the linear model that describes a latent variable or factor in
factor analysis). On other hand, the pattern of factor loadings should be examined to
identify variables that have complex structure (complex structure occurs when one item
has high loadings or correlations (0.50 or greater) on more than one factor/ component).
If an item/ a variable has complex structure, it should be removed from the analysis
(Reinard, 2006; Field, 2009; Zaiontz, 2014).
3.9.6.8 Mathematical validity of factor analysis
Once factors have been extracted, it is necessary to cross check if factor analysis
measured what was intended to be measured by using Cronbach's alpha test (Cα). An
alpha of 0.60 or higher is the minimum acceptable level. Preferably, alpha will be 0.70 or
higher (Field, 2009; Weiers, 2011; Garson, 2013).
82
3.1 Summary
This chapter described the detailed adopted methodology of research. It included the
primary research framework for the study, details of research period, location,
population, and sample size. The questionnaire design was detailed including the initial
draft that was modified and refined through pilot study. Quantitative data analysis
techniques, which include factor analysis, reliability test, normality test and Pearson
correlation analysis, were designed to be applied by the instruments of SPSS. For the
purposes of testing the research validity, reliability, and adequacy of methods used in
analysis, different statistical tests were used and explained in details.
Chapter 4
Results and Discussion
84
4. Chapter 4: Results and discussion
4.1 Scope of chapter
This chapter included analysis and discussion of the results that have been collected from
field surveys. Data was analyzed using SPSS including descriptive and inferential
statistical tools. In this study, total of two hundred and seventy four questionnaires
respondents from the study sample were considered. This chapter included the personal
information and profile of the respondents, quantitative analysis of questionnaire field
survey, and finally the summary framework of the results.
Figure 4. 1: The outline of data analysis and discussion chapter
Data analysis outline
Demographic survey of
respondents
Identifying and
evaluation of the key
performance indicators (KPIs) as a
success criteria
Factor analysis
results for KPIs
Ranking and evaluation of
KPIs as a success criteria
Investigating the critical
success factors CSFs affecting the
public construction
projects.
Factor analysis
results for CSFs
CSFs related to conceptualizing and preparation
CSFs related to planning and
designing stage
CSFs related to tendering and
contracting
Factors related to implementation
Ranking of CSFs affect
construction projects Differences
among respondents toward the analysis of
CSFs and KPIs on Palestine
Summary of results
framework
85
4.2 Demographic survey of respondents
This section of questionnaire mainly designed to provide general information about the
respondents and their companies. Table 4.1 represents the characteristics of respondents.
Table 4. 1: Demographic survey of respondents
Category Place of resident Frequency Percent %
Place of respondents resident Gaza Strip 134 48.91
West Bank 140 51.09
Total respondents 274 100
Category Organization type Frequency Percent %
Respondents organization type
Governmental organization 41 14.96
Non-governmental organization 40 14.59
Consultation offices 193 70.45
Total respondents 274 100
Category Value Frequency Percent %
Respondents organization projects
size during the last five years (in
million dollar)
Less than 5 M$ 105 38.32
From 5 -10 M$ 40 14.6
From 11 - 20 M$ 40 14.6
More than 20 M$ 89 32.48
Total respondents 274 100
Category Job title Frequency Percent %
Respondents job title
Design consultant 93 33.94
Supervising consultant 116 42.34
project manager 65 23.72
Total respondents 274 100
Category Years interval Frequency Percent %
Respondents years of experience in
the construction industry
From 5 -10 years 175 63.87
From 11 -15 years 45 16.42
From 16 -20 years 32 11.68
More than 20 years 22 8.03
Total respondents 274 100
86
4.3 Key performance indicators
This part aims to accomplish the first objective of this study by identifying and evaluation
of the key performance indicators (KPIs) of public construction projects. For that, in the
second section of the study questionnaire, 13 common KPIs were identified. These KPIs
have a very important role to measure construction industry success. These KPIs were
subjected to different analysis processes and tests (descriptive, t-tests and factor analysis)
in order to formulate the basic conclusions related to the first objective of this study. The
following sections provide detailed descriptions of the analysis results related to these
KPIs analysis results.
4.3.1 Factor analysis results for KPIs
Factor analysis was employed to establish which variables could be measuring aspects of
the same underlying dimensions. Factor analysis is useful for identifying clusters of
related variables and thus ideal for reducing a large number of variables into a more
easily understood framework (Ahadzie et al, 2008). In other words, it identified subsets
of items that correlate highly with each other, which called factors or components. Factor
analysis was conducted for this study using the Principal Component Analysis (PCA).
4.3.1.1 Appropriateness of factor analysis
The data was first assessed for its suitability to the factor analysis application. According
to the following:
Data distribution
The assumption of normality is most important requirement to generalize the results of
factor analysis test beyond the sample collected (Field, 2009; Zaiontz, 2015). The one-
sample Kolmogorov-Smirnov test was used to test that a variable of interest is normally
distributed. Table 3.8 showed that the distributions of KPIs is normally distributed. So
The results had been satisfied with this requirement.
87
Validity of sample size
The validity of factor analysis is dependent on sample size. PCA can be conducted on a
sample that has fewer than 100 respondents, but more than 50 respondents, and the
sample size for this study was 274. On the other hand, the common rule is to suggest that
sample size contains at least 10:15 respondents per item. In other words, sample size
should be at least 10 times the number of items and some even recommend 20 times
(Field, 2009; Zaiontz, 2015). Fortunately, for KPIs, the condition was verified. This field
contains 13 items and the sample size was 274. With 274 respondents and 13 items KPIs,
the ratio of respondents to items are 21: 1, which exceeds the requirement ratio 10:15.
Measures of reliability for the whole items
Cronbach's alpha test was performed on the items in the field of KPIs. The value of
Cronbach’s alpha (Cα) could be anywhere in the range of 0 to 1, where a higher value
denotes the greater internal consistency and vice versa. An alpha of 0.60 or higher is the
minimum acceptable level. Preferably, alpha will be 0.70 or higher (Field, 2009). As
shown in Table 4.2, the value of calculated Cα for all items in the field of (KPIs) is 0.89
in the final run which is considered to be marvelous.
Kaiser-Meyer-Olkin (KMO) and Bartlett's test
The Kaiser-Meyer-Olkin (KMO) sampling adequacy test and Bartlett's test of Sphericity
were carried out. The results of these tests are reported in Table 4.2. The value of the
KMO measure of sampling adequacy was 0.84 for first run and 0.83 for the final run
(close to 1), and was considered acceptable and marvelous because it exceeds the
minimum requirement of 0.50 (‘superb’ according to Kaiser, 1974; Field, 2009; Zaiontz,
2015). Moreover, the Bartlett test of sphericity was another indication of the strength of
the relationship among items. The Bartlett test of sphericity was 1123.36 for the first run
and 999.40 for the final run and the associated significance level was 0.00. The
probability value (Sig.) associated with the Bartlett test is less than 0.01, which satisfies
the PCA requirement. This indicated that the correlation matrix was not an identity
matrix and all of the items are correlated (Field, 2009; Zaiontz, 2015). According to the
results of these two tests, the sample data of (KPIs) were appropriated for factor analysis.
88
Table 4. 2: KMO and Bartlett's Test for KPIs
Factor analysis run description
First run Final run
Number of included variables 13 11
Kaiser-Meyer-Olkin Measure of Sampling
Adequacy. 0.84 0.83
Bartlett's Test of Sphericity
Approx.
Chi-Square 1123.36 999.40
Df 78.00 55.00
P-value 0.00 0.00
Cronbach's Alpha 0.85 0.89
Validity of Correlation matrix (Correlations between items)
Table 4.3 illustrates the correlation matrix for the 13 KPIs. It is simply a rectangular array
of numbers which gives the correlation coefficients between a single item and every other
item in the investigation (Field, 2009; Zaiontz, 2015). As shown in Table 4.3, the
correlation coefficient between an item and itself is always 1; hence the principal
diagonal of the correlation matrix contains 1s. The correlation coefficients above and
below the principal diagonal are the same. PCA requires that there be some correlations
greater than 0.30 and less than 0.8 between the items included in the analysis. For this set
of items, that many of the correlations in the matrix are strong and greater than 0.30
(Field, 2009; Zaiontz, 2015). Correlations have been satisfied with this requirement so no
items was removed at this step.
89
Table 4. 3:Correlations between items of KPIs
KPI 1 KPI 2 KPI 3 KPI 4 KPI 5 KPI 6 KPI 7 KPI 8 KPI 9 KPI 10 KPI 11 KPI 12 KPI 13
KPI 1 1.00
KPI 2 0.39 1.00
KPI 3 0.12 0.19 1.00
KPI 4 0.30 0.20 0.26 1.00
KPI 5 0.22 0.18 0.20 0.02 1.00
KPI 6 0.12 0.16 0.15 0.12 0.53 1.00
KPI 7 0.16 0.26 0.19 0.12 0.53 0.69 1.00
KPI 8 0.17 0.35 0.17 0.16 0.44 0.51 0.55 1.00
KPI 9 0.15 0.21 0.21 0.15 0.17 0.21 0.25 0.40 1.00
KPI 10 0.12 0.15 0.25 0.26 0.20 0.23 0.33 0.40 0.52 1.00
KPI 11 0.16 0.22 0.33 0.24 0.34 0.28 0.39 0.41 0.36 0.49 1.00
KPI 12 0.13 0.21 0.34 0.18 0.27 0.35 0.40 0.40 0.37 0.42 0.57 1.00
KPI 13 0.15 0.26 0.38 0.16 0.45 0.37 0.42 0.42 0.21 0.37 0.47 0.57 1.00
90
Communalities (common variance)
Communalities represent the proportion of the variance in the original items that is
accounted for by the factor solution. The factor solution should explain at least half of
each original item's variance, so the communality value for each item should be 0.50 or
higher (Field, 2009; Zaiontz, 2015). Two factor analysis runs were held. On iteration 1 of
factor analysis test, the communality for the variable KPI 3 and KPI 4 were less than
0.50. Since they were less than 0.50, the items had to be removed and the PCA was
computed again (new iteration). Table 4.4 shows that all of the communalities for all
remaining items satisfy the minimum requirement of being larger than 0.50, so items
were not excluded any on the basis of low communalities and all of the remaining 11
items (from the original 13 items) of this field (KPIs) were used in this analysis.
Table 4. 4: Communalities of KPIs
No. KPIs First run
communalities
Final run
(second run)
communalities
KPI 1 Actual project costs compared with planned budget. 0.67 0.67
KPI 2 Actual project duration compared with planned
duration. 0.57 0.68
KPI 3 Financial ability for both owner and contractor to
cover project expenditures 0.39 Removed
KPI 4 Project profitability for contractor comparing with
other related projects 0.46 Removed
KPI 5 Project conformity to quality and technical
specifications standards. 0.61 0.76
KPI 6 Project conformity to sustainability criteria. 0.74 0.62
KPI 7 Project conformity to environment protection
standards during execution. 0.72 0.73
KPI 8 Accidents and injures number in the project. 0.56 0.56
KPI 9 Quantity and costs of variation orders. 0.51 0.52
KPI 10 Number and size of disputes, litigations. 0.57 0.52
KPI 11 Contractor and consultant reputation . 0.61 0.64
KPI 12 Project parties satisfaction. 0.61 0.59
KPI 13 Beneficiaries satisfaction on project functionality. 0.55 0.60
91
Total Variance Explained
Using the output from iteration 2, there were three eigenvalues greater than 1. The
eigenvalue criterion stated that each component explained at least one item's worth of the
variability and therefore only components with eigenvalues greater than one should be
retained (Larose, 2006; Field, 2009). The latent root criterion for number of components
to derive would indicate that there were 3 components to be extracted for these items.
Results were tabulated in Table 4.5. The three components solution explained a sum of
the variance with component 1 contributing 39.93%; component 2 contributing 11.62%;
and component 3 contributing 11.17%. All the remaining components are not significant.
The three components were then rotated via varimax (orthogonal) rotation approach. This
does not change the underlying solution, or the relationships among the items. Rather, it
presents the pattern of loadings in a manner that is easier to interpret factors
(components) (Reinard, 2006; Field, 2009; Zaiontz, 2014). The rotated solution revealed
that the three components solution explained a sum of the variance with component 1
contributing 24.92%; component 2 contributing 24.75%; and component 3 contributing
13.05%. These three components explained 62.72% of total variance for the varimax
rotation since it was more than 50%.
Table 4. 5: Total variance Explained of KPIs
Att
rib
ute
Initial Eigenvalues Extraction Sums of Squared
Loadings
Rotation Sums of Squared
Loadings
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
1 4.39 39.93 39.93 4.39 39.93 39.93 2.74 24.92 24.92
2 1.28 11.62 51.55 1.28 11.62 51.55 2.72 24.75 49.67
3 1.23 11.17 62.72 1.23 11.17 62.72 1.44 13.05 62.72
4 0.90 8.14 70.86
5 0.70 6.38 77.24
6 0.55 4.96 82.20
7 0.50 4.51 86.72
8 0.46 4.22 90.94
9 0.43 3.87 94.81
10 0.31 2.80 97.61
11 0.26 2.39 100.00
92
Scree Plot
The scree plot below in Figure 4.2 is a graph of the eigenvalues against all the
components. This graph can also be used to decide on number of components that can be
derived. Although scree plots are very useful, component selection should not be based
on this criterion alone (Field, 2009). The point of interest is where the curve starts to
flatten. It can be seen that the curve begins to flatten between component 3 and 4. Note
also that component 4 has an eigenvalue of less than 1, so only three components have
been retained to be extracted.
Figure 4. 2: Scree Plot for key performance indicators KPI's of projects
Rotated Component Matrix
Table 4.6 shows the factor loadings after rotation of 11 items (from the original 13 items)
on the three factors extracted and rotated. The pattern of factor loadings should be
examined to identify items that have complex structure (complex structure occurs when
one item has high loadings or correlations (0.50 or greater) on more than one
component). If an item has a complex structure, it should be removed from the analysis
(Reinard, 2006; Field, 2009; Zaiontz, 2014). As shown in Table 4.6, factor loading all
items were above 0.50 and all items had simple structure. The items are listed in the order
of size of their factor loadings.
0
1
2
3
4
5
0 1 2 3 4 5 6 7 8 9 10 11
Eig
en
valu
es
Component
93
Naming the components
Once an interpretable pattern of loadings is done, the components should be named
according to their substantive content or core. The components should have conceptually
distinct names and content. Items with higher loadings on a component should play a
more important role in naming the component. Also the common names for components
in previous studies were used in naming them. One of these studies was Ahadzie et al
(2008) study. They used factor analysis and derived four components and they named
them environmental impact, quality, customer satisfaction and overall cost and time. In
this study the three components were named as the following:
Component 1: “Project quality and environment impact” with items: KPI 5, KPI
6, KPI 7 and KPI 8.
Component 2: “Satisfaction and reputation of project parties” with items: KPI 9,
KPI 10, KPI 11, KPI 12 and KPI 13.
Component 3: “Overall cost and time” with items: KPI 1 and KPI 2.
The proposed naming of the extracted components were discussed with experts and
academics to validate the naming of the principal components. Figure 4.3 below
describes the final results of the components extracted, percent of total variance
explained and the eigenvalue of each component.
Figure 4. 3: Final components extracted from factor analysis for KPIs
Key performance indicators KPIs
Total variance: 62.72%
Component 3
Overall cost and time
Eigenvalue: 1.23
Component 2
Satisfaction and reputation of project parties
Eigenvalue: 1.28
Component 1
Project quality and environmental impact
Eigenvalue: 4.39
94
Measures of reliability for each component
Once components have been extracted and rotated, it was necessary to cross checking if
the items in each component formed collectively explain the same measure within target
dimensions (Doloi, 2009). If items truly form the identified component, it is understood
that they should reasonably correlate with one another, but not the perfect correlation
though. Cronbach's alpha (Cα) test was conducted for each component. The higher value
of Cα denotes the greater internal consistency and vice versa. An alpha of 0.60 or higher
is the minimum acceptable level. Preferably, alpha will be 0.70 or higher (Field, 2009).
According to results which were tabulated in Table 4.6, Cα for component 1 is 0.83; Cα
for component 2 is 0.79; and Cα for component 3 is 0.66. They are considered to be
acceptable.
Table 4. 6: Factor loadings for a three-component model of key performance indicators KPI's
Component and factor loading
Fac
tor
load
ing
Eig
enval
ues
Var
iance
%
expla
ined
Cro
nbac
h's
Alp
ha
(Cα
)
Component 1: Project quality and environmental impact
KPI 5 Project conformity to quality and technical
specifications standards.
0.86
4.39 24.92 0.83
KPI 7 Project conformity to environment
protection standards during execution.
0.81
KPI 6 Project conformity to sustainability criteria. 0.77
KPI 8 Accidents and injures number in the
project.
0.57
Component 2: Satisfaction and reputation of project parties
KPI 11 Contractor and consultant reputation . 0.80
1.28 24.75 0.79
KPI 13 Beneficiaries satisfaction on project
functionality.
0.73
KPI 12 Project parties satisfaction. 0.70
KPI 9 Quantity and costs of variation orders. 0.68
KPI 10 Number and size of disputes, litigations. 0.55
Component 3: Overall cost and time
KPI 1 Actual project costs compared with planned
budget.
0.86
1.23 13.05 0.66 KPI 2 Actual project duration compared with
planned duration.
0.81
Kaiser-Meyer-Olkin measure of sampling adequacy = 0.83
Bartlett's test of sphericity: x2= 999.40,df=55,p-value =0.00
Total variance explained (%) = 62.72 %
Total reliability Cornbach’s α = 0.89
Two insignificant factor loadings (< 0.5) are blanked
95
4.3.1.2 The extracted components
The next section will interpret and discuss each of the extracted components as follows:
Component 1: Project quality and environmental impact
First component named "Project quality and environment impact" explains 24.92 % of
the total variance and contains four items. The majority of items had relatively high
factor loadings (≥ 0.57). The four items are as follows:
1. Project conformity to quality and technical specifications standards KPI 5, with
factor loading=0.86
2. Project conformity to environment protection standards during execution KPI 7, with
factor loading=0.81
3. Project conformity to sustainability criteria KPI 6, with factor loading =0.77
4. Accidents and injures number in the project KPI 8, with factor loading=0.57
Results revealed that the four items that loaded on this component are related to quality
and environment issues. This grouping would appear to be logical and the component can
be termed “Project quality and environmental impact”. According to factor analysis
theory, the first component accounts for the largest part of total variance of the cases.
Hence, it implies that quality and environment impact considered as the most important
KPIs in construction companies in Palestine. Previous study in Gaza strip held by
Enshassi et al (2009c) indicated that quality and safety in construction industry still
suffers from ignorance and lack of supervision and accident rate on construction projects
is very high. In line with this study in Taiwan Yang et al (2011) found that quality was
the highest loaded component accounted variance. Also in Malaysia Al-Tmeemy (2011)
results showed that quality was the second high loaded component. In Ghana Ahadzie et
al (2008) reported that quality is the third high loaded component between four
components derived on their study.
Results also indicated that KPI “Accidents and injures number in the project” was the
lowest loading KPIs of this component with factor loading of 0.57. This result is not
strange since the culture of safety is still weak in Palestine. Recording injuries and
accidents and number in the project is KPIs not common in Palestinian construction
96
project. Same conclusion was indicated by Enshassi et al (2009c) who found that safety
and quality in Gaza Strip is not widely recognized as inherent characteristic of success for
construction projects. However, public construction projects contracts contain provisions
about safety practices but construction parties do not follow them in reality. Enshassi et
al (2008) found that in Palestine, the key players in the construction industry do not adopt
safe working practices for several reasons including that: employers and employees are
unwilling to spend or invest in safety measures, equipment or practices; employees
cannot afford to purchase their own safety equipment and fear they might be penalized if
they request personal protective equipment (PPE) from their employers. Additionally,
contractors are not aware of their legal responsibilities in relation to health and safety
issues. Hughes et al (2004) considered safety measurements was a major competitive
component. In contract to this study result in Ghana Ahadzie et al (2008) stated that
overall health and safety measures component loading was 0.76 and they consider
environmental-safety protection has now become a worldwide challenge facing the
construction industry. Also in contract to this study result Ali et al (2013) ranked safety
measurements as seventh important one among 47 performance indicators.
Component 2: Satisfaction and reputation of project parties
The second component, (Satisfaction of project parties), accounted for 24.75% of the
total variance and contained 5 items. Items had relatively high factor loadings (0.55).
The five items were:
1. Contractor and consultant reputation KPI 11, with factor loading=0.80.
2. Beneficiaries satisfaction on project functionality KPI 13, with factor loading=0.73
3. Project parties satisfaction KPI 12, with factor loading=0.70.
4. Quantity and costs of variation orders KPI 9, with factor loading=0.6.
5. Number and size of disputes, litigations KPI 10, with factor loading=0.55.
The second component was labelled as “Satisfaction and reputation of project parties”,
and comprise 5 items. This component is labelled in accordance with the characteristics
of the set of individual items loaded on it. Throughout this research, it is encouraging to
see that the respondents having a positive attitude towards satisfaction and reputation of
97
project parties KPIs and its related aspects. The importance of this component in
Palestine came from the main reason of implementing public construction projects. The
main reason was to serve people by construct housing buildings, governmental buildings,
roads, hospitals or schools. So parties satisfaction will be important KPIs for the success
of these projects. This result supported Ahadzie et al (2008) study in Ghana which
showed that satisfaction is the second component accounted variance between four
components of KPIs. They stated that Satisfied customers as the evidence suggests are
the backbone of the house building industry in Malaysia. Also in Saudi Arabia Ali et al
(2013) found that satisfaction is the 6th
important KPIs from 47 one. Ali et al (2013)
indicated that there was no doubt that construction organizations depend on their
customers, therefore they should understand and meet their needs and expectations. Also
they stated that satisfaction of customers and other interested parties is necessary for the
success of the project and organization. In other words, increasing the satisfaction of
customers and stakeholders through effective goal deployment, cost reduction,
productivity and process improvement has proved to be essential for organizations to stay
in operation.
Results as shown in Table 4.6 indicated that KPI “Contractor and consultant reputation”
was the highest factor loading item in component 2 with 0.80 factor loading. This item
indicated that the company's reputation can be impressiveness measure of project success
to contractors and consultants. Reputation depends on whether the consultant or
contractor deliver their projects on time, cost, within quality standards and with
satisfaction of project parties. In Palestine construction projects consultant or contractor
reputation is important and awarding of projects depend mostly on low bidding and then
on the good reputation of consultant and contractor. In line with this study in Malaysia
Al-Tmeemy (2011) found that reputation is the third component affect company success
and they found that there is a relationship between market share and reputation by
building up a strong reputation would help a company to gain market share. Also in line
with this study in Israel Dvir et al (2003) showed the that reputation was the second item
which affect contractor benefit.
98
Results also indicated that KPI “Number and size of disputes, litigations” was the lowest
item of factor loading of 0.55. Because of the discrepancy in goals and expectations,
conflicting issues are commonly observed among parties which lead to disputes during
the course of the project. Also conditions such as delay in the payments for completed
work, frequent owner interference, changing requirements, lack of communication
between the various parties, problems with neighbors, and unforeseen site conditions give
rise to disputes between the various parties. The disputes, if not resolved amicably, can
lead to arbitration or litigation. In Palestine disputes and litigations take a long time due
to the fog in laws and regulations since they are outdated, contradicted and uncompleted.
So project parties directed toward solving their disputes by themselves and this make this
KPI to be less important. In USA li et al (2012) found that high level of uncertainty in the
transaction environment file numerous claims, deal with substantial amounts of extra
work, and in general have antagonistic relationships with owners that sometimes end up
in disagreement, conflict and litigation. In contract to this result in Hong Kong Chan et al
(2004a) stated that establishment and communication of conflict resolution strategy was
the highest attribute accounted variance in the second component of his study.
Component 3: Overall cost and time
The third component, (Overall cost and time), accounted for 13.05% of the total variance
and contains two items. The two items had relatively high factor loadings (0.81). The
two items are as follows:
1. Actual project costs compared with planned budget KPI 1, with factor loading=0.86.
2. Actual project duration compared with planned duration KPI 2, with factor
loading=0.81.
The third component was labelled as “Overall cost and time”, and comprises 2 KPIs. This
component was labelled in accordance with the characteristics of the set of individual
items loaded on it. This component measures the efficiency of project execution and
ensures that the project is done right. The issue of shortening construction time, reducing
cost and improving production performance has engaged all project parties on Palestine.
Cost and time are very important KPIs on Palestinian public construction projects since
99
projects have limited budget from funders. However delays and cost overruns are still
major challenges founding in construction projects in Palestine. In Gaza Enshassi et al
(2009b) concluded that the main causes of time delays included strikes and border
closures, material-related factors, lack of materials in markets, and delays in materials
delivery to the site. Additionally, the main causes for cost overruns included price
fluctuations of construction materials, contractor delays in material and equipment
delivery, and inflation. In line with this study results in Annapolis Hughes et al (2004)
considered cost and schedule as very important measurements of project success in the
construction industry. In Ghana also Ahadzie et al (2008) results showed that overall cost
and time was the fourth high loaded component between four components derived on
their study with 0.827 factor loading for overall project costs KPI and 0.765 for overall
project duration. Also in Malaysia Al-Tmeemy (2011) found that overall cost KPI had the
highest factor loading of 0.777 and overall project time KPI had the third factor loading
of 0.701.
4.3.2 Ranking of KPIs of construction projects
In order to evaluate which the degree of importance of KPIs in Palestinian public
construction projects descriptive statistics was used. RII was calculated to weight each
KPI (from KPI 1 to KPI 13) according to the numerical scores obtained from the
questionnaire responses and results have been ranked from the highest degree (The most
important KPI) to the least degree (The most vulnerable KPI). Table 4.7 shows RIIs and
ranks of KPIs, respectively. The numbers in the “rank” column represent the sequential
ranking. It worth mentioning that ranking of KPIs was based on the highest mean, RII,
and the lowest SD. If some items have similar means as in the case of (KPI 1 and KPI 2)
ranking will be depended on RIIs and the lowest SD. More precisely, although KPI 1 and
KPI 2 have the same mean, but KPI 1 was ranked higher than KPI 2 because it has the
higher RII and the lower SD. Items were categorized with ratings from 89.01 % to 71.81
% (Figure 4.4).
100
Table 4. 7: Means and test values for “key performance indicators KPI's of projects”- Degree of
importance
No. KPI of projects Mean S.D RII Test
value
P-value
(Sig.)
Total
rank
KPI 1 Project conformity to quality and
technical specifications standards.
4.47 0.72 89.37 33.40 0.00* 1
KPI 2 Actual project costs compared with
planned budget.
4.45 0.63 89.05 38.25 0.00* 2
KPI 3 Actual project duration compared with
planned duration.
4.45 0.72 89.01 33.22 0.00* 3
KPI 4 Financial ability for both owner and
contractor to cover project expenditures
4.36 0.73 87.25 31.04 0.00* 4
KPI 5 Accidents and injures number in the
project.
4.21 0.84 84.25 23.99 0.00* 5
KPI 6 Beneficiaries satisfaction on project
functionality.
4.17 0.90 83.31 21.26 0.00* 6
KPI 7 Project conformity to sustainability
criteria.
4.12 0.84 82.35 21.89 0.00* 7
KPI 8 Project parties satisfaction. 4.09 0.90 81.78 19.97 0.00* 8
KPI 9 Contractor and consultant reputation. 4.05 0.92 80.97 18.66 0.00* 9
KPI 10 Quantity and costs of variation orders. 3.97 0.89 79.41 17.90 0.000* 10
KPI 11 Project conformity to environment
protection standards during execution.
3.90 0.98 78.09 15.18 0.00* 11
KPI 12 Project profitability for contractor
comparing with other related projects
3.61 0.87 72.18 11.57 0.00* 12
KPI 13 Number and size of disputes, litigations. 3.59 0.93 71.81 10.45 0.00* 13
Overall 4.11 0.50 82.17 36.84 0.00*
101
Figure 4. 4: RII of KPI's (KPI 1 to KPI 13)
The findings indicated that “Project conformity to quality and technical specifications
standards” was the highest important KPI in Palestinian public construction projects. It
has been ranked as the first position with mean = 4.47, RII = 89.37%, Test-value = 33.40
and P-value = 0.00 according to overall respondents. Quality can be defined as the degree
to which the general conditions promote meeting of the project’s established
requirements of materials and workmanship Lam et al (2007). Respondents agreed that
project conformity to quality and technical specifications standards KPI was more
important than cost and time. This result may due to the fact of that donors who fund the
public construction projects give high important to the quality more than any other
consideration. In line with this study in Saudi Arabia Ali et al (2013) found that quality
is the second highest important KPI with RII equal 85.8%. Also not far result in Australia
Yeung et al (2009) ranked quality as third important KPI. In Hong Kong Lam et al
(2007) found that there were four important KPI to determine the success of design and
built projects and quality was the third important KPI.
Results indicated that “Actual project costs compared with planned budget” (mean=4.45,
RII=89.05%, Test-value = 38.25, and P-value=0.000), ranked as the second important
KPI in Palestinian construction industry. Cost is defined as the degree to which the
general conditions promote the completion of a project within the estimated budget (Chan
89.37 89.05
89.01
87.25
84.25
83.31
82.35 81.78
80.97
79.41
78.09
72.18
71.81
0
20
40
60
80
100KPI 1
KPI 2
KPI 3
KPI 4
KPI 5
KPI 6
KPI 7 KPI 8
KPI 9
KPI 10
KPI 11
KPI 12
KPI 13
102
et al, 2002). Cost as KPI is still very important in Palestine due to the limited budget of
projects since most of them are funded by donors. This study result in line with Yeung et
al (2009) study in Australia which ranked cost as the second important KPI. Also it is the
same as in Hong Kong Lam et al (2007) found that there were four important KPI to
determine the success of design and built projects and cost was the most important one.
Results also revealed that “Actual project duration compared with planned duration”
(mean=4.45, RII= 89.01%, Test-value = 33.22, and P-value=0.000) was ranked as the
third important KPI. Time is defined as the degree to which the general conditions
promote the completion of a project within the allocated duration (Chan et al, 2002). In
Palestine most of public projects are funded by donors as mentioned earlier. The donors
give limited time to implement the projects due to the uncertainty of political conditions
in Palestine like annually wars. Although most of Palestinian construction projects
suffered from delays for many reasons such as referral bids to the lowest price, incorrect
bids pricing, lack of sufficient cash for project implementation and irregular owner cash
follow (Albatsh, 2015). Similar to this study results in Australia Yeung et al (2009)
ranked time as the 6th
important KPI. In line with this study in Hong Kong Lam et al
(2007) found that there were four important KPI to determine the success of design and
built projects and time was the second important KPI.
The results showed that the most important KPIs were quality, time and cost which
means that in Palestine construction industry the highest important KPIs were the
traditional basic ones. This result is in line with most previous studies such as in Hong
Kong ( Chan et al, 2002; Chan and Chan, 2004 and Chan and Chan 2004), Ghana
(Ahadzie et al, 2008), Republic of Korea (Cho et al, 2009), Malaysia (Al-Tmeemy et al,
2011) , Saudi Arabia (Ali et al 2013) and Brazil (Berssaneti and Carvalho, 2014) which
consider quality, time and cost as the most important KPIs. This result was different than
other studies which consider satisfaction as the highest important indicator followed by
the iron triangle indicators (cost, quality and time) such studies as in UK (Bryde and
Robinson, 2005), Hong Kong (Lam et al, 2007), and in Australia (Yeung et al, 2009). On
this study respondents gave satisfaction moderate important rank may be due to the bad
103
economic situation and siege which cause inflation and high rates of unemployment and
that give cost and time more attention than satisfaction.
4.3.3 Public construction projects KPIs evaluation (actual versus planned
performance)
The main objective of this field is to evaluate the situation of Palestinian public
construction projects according to the KPIs. Respondents asked to evaluate the actual
KPIs in comparative to planned. The analysis of this part will give general view for
Palestinian public construction projects performance. As a result the problems in
performance will be known. Descriptive analysis was used to obtain the results of this
part. From Table 4.8 the means of KPI "Actual project duration compared with planned
duration", “Actual project costs compared with planned budget” and "Quantity and costs
of variation orders" were 3.85, 3.67 and 3.51 respectively with P-value=0.000 which
were smaller than the level of significance 0.05. And the signs of the test were positive,
so the mean of those indicators was significantly greater than the hypothesized value 3.
Which means Palestinian construction projects suffer from cost overrun and delay and the
quantity and costs of variation orders are high. Since quantity and costs of variation
orders are high this may be the main cause of cost overrun and delay. Other possible
causes of cost overrun and delay were blockade, material shortage in types and quantities
and the limited budget for the Palestinian public construction projects which is basically
depend on grants on. Variation orders are high because of projects multiple owners who
have different interests. In Malaysia Shehu et al (2014) concluded that more than half of
Malaysian construction projects (55%) experienced cost overruns. Also in Malaysia
Young and Mustaffa (2012) indicated that delays, cost overruns and disputes are common
challenges faced by the industry.
Also from Table 4.8 the means of KPI "Beneficiaries satisfaction on project
functionality", "Project conformity to quality and technical specifications standards",
"Project parties satisfaction" and "Financial ability for both owner and contractor to
cover project expenditures" were 3.70, 3.64, 3.61 and 3.55 respectively with P-
value=0.000 which were smaller than the level of significance 0.05. And the signs of the
test were positive, so the mean of this indicators was significantly greater than the
104
hypothesized value 3. This means Palestinian construction projects have good evaluation
for projects quality, satisfaction and ability to cover project expenditures. The
explanation of this result was that public construction projects on Palestine raise based on
people's needs and there is a big shortage in types and numbers of these projects in
comparing with needs. So when the projects implemented parties will be satisfied
regardless the level of quality. Another justification is that mostly the owners of
Palestinian construction public projects are the government which funded these projects
from donors so the parties will be less worried on the ability to finance these projects and
will perceived positively according the evaluation.
Additionally from Table 4.8 the mean of KPI "Accidents and injures number in the
project" is 2.85 with P-value=0.000 which was smaller than the level of significance
0.05. And the signs of the test was negative, so the mean of this indicators was
significantly smaller than the hypothesized value 3. That means Palestinian construction
projects do not suffer from high number of injuries and accidents. In reality it seems to be
high evaluation and may be the basic reason of this evaluation was that there is poor
documentation for injuries and accidents since the safety culture level is still limited in
Palestine.
105
Table 4. 8: Means and test values for “key performance indicators KPI's of projects”-
performance evaluation of organization projects
No. KPI of projects Mean S.D RII Test
value
P-
value
(Sig.)
1 Financial ability for both owner and contractor to
cover project expenditures 3.55 0.87 70.94 10.19 0.000*
2 Project conformity to quality and technical
specifications standards. 3.64 0.92 72.88 11.32 0.000*
3 Project conformity to sustainability criteria. 3.43 0.98 68.57 7.15 0.000*
4 Project conformity to environment protection
standards during execution. 3.30 0.97 65.93 4.93 0.000*
5 Actual project costs compared with planned budget 3.67 0.80 73.36 13.73 0.000*
6 Actual project duration compared with planned
duration 3.85 0.78 77.01 17.77 0.000*
7 Accidents and injures number in the project. 2.85 1.23 57.09 -1.90 0.029*
8 Number and size of disputes, litigations. 3.02 1.13 60.45 0.33 0.745
9 Project profitability for contractor comparing with
other related projects 3.19 0.81 63.73 3.71 0.000*
10 Quantity and costs of variation orders. 3.51 0.91 70.11 9.00 0.000*
11 Contractor and consultant reputation. 3.34 1.05 66.74 5.21 0.000*
12 Project parties satisfaction. 3.61 0.81 72.21 12.17 0.000*
13 Beneficiaries satisfaction on project functionality. 3.70 0.92 73.96 12.40 0.000*
Overall 3.43 0.53 68.70 13.58 0.000*
* The mean is significantly different from 3
106
4.4 Critical success factors CSFs
This part aims to accomplish the second objective of this study by investigating the
critical success factors CSFs affecting the public construction projects. For that, in the
third section of the study questionnaire, 81 common CSFs were identified. These CSFs
were subjected to different analysis processes and tests (descriptive, t-tests and factor
analysis) in order to formulate the basic conclusions related to the second objective of
this study. The following sections provide detailed descriptions of the analysis results
related to these CSFs analysis results.
4.4.1 Factor analysis results for CSFs
This part aims to accomplish the second objective of this study by investigating the CSFs
affecting the public construction projects. The study of these factors gives good insight to
policy makers on how to improve their practices during project life cycle in order to
guarantee project success. For that, in this section of the study questionnaire, 81 common
CSFs were identified. These factors were subjected to different analysis processes and
tests (descriptive, t-tests and factor analysis) in order to formulate the basic conclusions
related to the second objective of this study. The following sections provide detailed
descriptions of the analysis results related to these CSFs analysis results.
4.4.1.1 CSFs related to conceptualizing and preparation phase
In this phase of data analysis process, factor analysis was employed to reduce a large
number of items (CSFs) to a smaller set of underlying components that summarize the
essential information contained in the items. Using SPSS 22, Principle Component
Analysis (PCA) with Varimax rotation were performed to set up which items could
capture the aspects of same dimension of the 12 CSFs and examine the underlying
structure or structure of interrelationships among the CSFs. In order to perform the factor
analysis for used items, all the appropriate checks and procedures were fulfilled.
4.4.1.1.1 Appropriateness of factor analysis
The data was first assessed for its suitability to the factor analysis application. According
to the following:
107
Data distribution
The assumption of normality is most important requirement to generalize the results of
factor analysis test beyond the sample collected (Field, 2009; Zaiontz, 2015). The one-
sample Kolmogorov-Smirnov test was used to test that a item of interest is normally
distributed. Table 3.8 showed that the distributions of CSFs which related to
conceptualizing and preparation phase is normally distributed. So the results had been
satisfied with this requirement.
Validity of sample size
The validity of factor analysis is dependent on sample size. PCA can be conducted on a
sample that has fewer than 100 respondents, but more than 50 respondents, and the
sample size for this study was 274. On the other hand, the common rule is to suggest that
sample size contains at least 10:15 respondents per item. In other words, sample size
should be at least 10 times the number of items and some even recommend 20 times
(Field, 2009; Zaiontz, 2015). Fortunately, for CSFs of conceptualizing and preparation
phase, the condition was verified. This field contains 12 items and the sample size was
274. With 274 respondents and 12 items CSFs, the ratio of respondents to items are 22.8:
1, which exceeds the requirement ratio 10:15.
Measures of reliability for the whole items
Cronbach's alpha test was performed on the items in CSFs field of conceptualizing and
preparation phase. The value of Cronbach’s alpha (Cα) could be anywhere in the range of
0 to 1, where a higher value denotes the greater internal consistency and vice versa. An
alpha of 0.60 or higher is the minimum acceptable level. Preferably, alpha will be 0.70 or
higher (Field, 2009). As shown in Table 4.9, the value of calculated Cα for all items in
the field CSFs of conceptualizing and preparation phase is 0.86 for the final run which
considered to be marvelous.
108
Kaiser-Meyer-Olkin (KMO) and Bartlett's test
The Kaiser-Meyer-Olkin (KMO) sampling adequacy test and Bartlett's test of Sphericity
were carried out. The results of these tests are reported in Table 4.9. The value of the
KMO measure of sampling adequacy was 0.79 for first run and 0.73 for the final run
(close to 1), and was considered acceptable and marvelous because it exceeds the
minimum requirement of 0.50 (‘superb’ according to Kaiser, 1974; Field, 2009; Zaiontz,
2015). Moreover, the Bartlett test of sphericity was another indication of the strength of
the relationship among items. The Bartlett test of sphericity was 822.96 for the first run
and 556.82 for the final run and the associated significance level was 0.00. The
probability value (Sig.) associated with the Bartlett test is less than 0.01, which satisfies
the PCA requirement. This indicated that the correlation matrix was not an identity
matrix and all of the items are correlated (Field, 2009; Zaiontz, 2015). According to the
results of these two tests, the sample data of (CSFs in conceptualizing and preparation
phase) were appropriated for factor analysis.
Table 4. 9: KMO and Bartlett's Test for CSFs of conceptualizing and preparation phase
Factor analysis run description
First run Second run
(Final run)
Number of included items 12 8
Kaiser-Meyer-Olkin Measure of
Sampling Adequacy. 0.79 0.73
Bartlett's Test of Sphericity
Approx. Chi-
Square 822.96 556.82
Df 66 28
P-value < 0.001 .00
Cronbach's Alpha 0.89 0.86
Validity of Correlation matrix (Correlations between items)
Table 4.10 illustrates the correlation matrix for the 12 CSFs. It is simply a rectangular
array of numbers which gives the correlation coefficients between a single item and every
other item in the investigation (Field, 2009; Zaiontz, 2015). As shown in Table 4.10, the
correlation coefficient between an item and itself is always 1; hence the principal
diagonal of the correlation matrix contains 1s. The correlation coefficients above and
below the principal diagonal are the same. PCA requires that there be some correlations
greater than 0.30 and less than 0.8 between the items included in the analysis. For this set
109
of items, that many of the correlations in the matrix are strong and greater than 0.30
(Field, 2009; Zaiontz, 2015). Correlations have been satisfied with this requirement.
Table 4. 10: Correlations between items of CSFs of conceptualizing and preparation phase
CSF
CSF
1
CSF
2
CSF
3
CSF
4
CSF
5
CSF
6
CSF
7
CSF
8
CSF
9
CSF
10
CSF
11
CSF
12
CSF 1 1.00
CSF 2 0.39 1.00
CSF 3 0.24 0.31 1.00
CSF 4 0.12 0.27 0.27 1.00
CSF 5 0.25 0.26 0.21 0.64 1.00
CSF 6 0.24 0.30 0.30 0.34 0.41 1.00
CSF 7 0.10 0.21 0.18 0.13 0.27 0.32 1.00
CSF 8 0.32 0.25 0.21 0.16 0.20 0.29 0.22 1.00
CSF 9 0.23 0.26 0.12 0.17 0.27 0.22 0.13 0.38 1.00
CSF 10 0.16 0.26 0.14 0.22 0.33 0.30 0.35 0.43 0.48 1.00
CSF 11 0.06 0.14 0.16 0.22 0.27 0.17 0.30 0.33 0.41 0.62 1.00
CSF 12 -0.01 0.18 0.06 0.22 0.23 0.23 0.21 0.28 0.29 0.50 0.43 1.00
110
Communalities (common variance)
Communalities represent the proportion of the variance in the original items that is
accounted for by the factor solution. The factor solution should explain at least half of
each original item's variance, so the communality value for each item should be 0.50 or
higher (Field, 2009; Zaiontz, 2015). On iteration 1 of factor analysis test, the
communality for the item CSF 3, CSF 6 and CSF 7 were less than 0.50. Since they were
less than 0.50, the items had to be removed and the PCA was computed again (new
iteration). Table 4.11 shows that all of the communalities for all remaining items satisfy
the minimum requirement of being larger than 0.50.
Table 4. 11: Communalities of CSFs of conceptualizing and preparation phase
Item. CSFs First run
communalities
Second run
(Final run)
communalities
CSF 1 Studying the feasibility, cost and priority of the
project for the society. 0.64 0.74
CSF 2 Formalizing deterministic, clear and realistic
objectives for the project and sharing project
relatives in.
0.50 0.59
CSF 3 Determining project size represented by its required
budget. 0.37 Removed
CSF 4 Specifying the project type whether it is new,
maintenance, completion for existing one or rubble
removal project)
0.71 0.84
CSF 5 Determining the construction project nature
(housing, infrastructure, public building, …) 0.69 0.78
CSF 6 Specifying the project designing and execution
complexity comparing with previous related
projects.
0.46 Removed
CSF 7 Endeavoring to decrease the political instability
effect on the project. 0.26 Removed
CSF 8 Studying the level of acceptance of local community
to execute the project in their location. 0.56 Removed
CSF 9 Studying project tendency to accidents and hazards. 0.50 0.55
CSF 10 Existence of experienced and understandable client
(his representative) on project nature and clear
priorities for project execution.
0.74 0.74
CSF 11 Giving suitable and enough time for planning and
designing phase. 0.67 0.69
CSF 12 Recruiting and involving consultant in all project
activities and phases. 0.52 0.56
111
Total Variance Explained
Using the output from iteration 2, there were three eigenvalues greater than 1. The
eigenvalue criterion stated that each component explained at least one item's worth of the
variability and therefore only components with eigenvalues greater than one should be
retained (Larose, 2006; Field, 2009). The latent root criterion for number of components
to derive would indicate that there were 3 components to be extracted for these items.
Results were tabulated in Table 4.12. The three components solution explained a sum of
the variance with component 1 contributing 37.62%; component 2 contributing 17.17%;
and component 3 contributing 13.79%. All the remaining components are not significant.
The three components were then rotated via varimax (orthogonal) rotation approach. This
does not change the underlying solution, or the relationships among the items. Rather, it
presents the pattern of loadings in a manner that is easier to interpret components (Field,
2009; Zaiontz, 2015). The rotated solution revealed that the three components solution
explained a sum of the variance with component 1 contributing 29.17%; component 2
contributing 20.50%; and component 3 contributing 18.91%. These three components
explained 68.58% of total variance for the varimax rotation which is acceptable since it
was more than 50%.
Table 4. 12: Total variance Explained of CSFs of conceptualizing and preparation phase
Att
rib
ute
Initial Eigenvalues Extraction Sums of Squared
Loadings
Rotation Sums of Squared
Loadings
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
1 3.01 37.62 37.62 3.01 37.62 37.62 2.33 29.17 29.17
2 1.37 17.17 54.79 1.37 17.17 54.79 1.64 20.50 49.67
3 1.10 13.79 68.58 1.10 13.79 68.58 1.51 18.91 68.58
4 0.71 8.87 77.45
5 0.58 7.30 84.75
6 0.52 6.51 91.26
7 0.37 4.64 95.90
8 0.33 4.10 100.00
112
Scree Plot
The scree plot below in Figure 4.5 is a graph of the eigenvalues against all the
components for final run of analysis. This graph can also be used to decide on number of
components that can be derived. Although scree plots are very useful, component
selection should not be based on this criterion alone (Field, 2009). The point of interest is
where the curve starts to flatten. It can be seen that the curve begins to flatten between
components 3 and 4. Note also that component 4 has an eigenvalue of less than 1, so only
three components have been retained to be extracted.
Figure 4. 5: Scree Plot for CSFs of conceptualizing and preparation phase
Rotated Component (Factor) Matrix
Table 4.14 shows the factor loadings after rotation of 8 items (from the original 12 items)
on the three factors extracted and rotated. The pattern of factor loadings should be
examined to identify items that have complex structure (complex structure occurs when
one item has high loadings or correlations (0.50 or greater) on more than one component.
If an item has a complex structure, it should be removed from the analysis (Reinard,
2006; Field, 2009; Zaiontz, 2015). According to that, it was necessary to remove item
CSF 8 because it demonstrated complex structure. It was loaded under two components
(component 1 and component 3) in the same time with a factor loading of 0.51 under
component 1 and a factor loading of 0.55 under component 3. As shown in Table 4.14,
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
0 1 2 3 4 5 6 7 8
Eig
en
valu
es
Component
113
for each remaining items factor loading were above 0.50 and all items had simple
structure. The items are listed in the order of size of their factor loadings.
As a conclusion of analysis 4 Items were removed and 8 items remaining as summarized
in Table 4.13.
Table 4. 13: Summary of remaining and removed CSFs in conceptualizing and preparation
phase as a result of factor analysis runs
Item. CSFs Result
CSF 1 Project feasibility and priority for the society. Remaining
CSF 2 Deterministic, clear, sharable and realistic project
objectives Remaining
CSF 3 Predetermining of project size and budget. Removed since
communalities less than 0.5
CSF 4 Project type (new, maintenance, completion for
existing one or rubble removal project). Remaining
CSF 5 Determining the construction project nature (housing,
infrastructure, public building, …) Remaining
CSF 6 Project complexity and uniqueness. Removed since
communalities less than 0.5
CSF 7 Recognizing political influence on the project. Removed since
communalities less than 0.5
CSF 8 Local community acceptance to execute the project in
their location.
Removed since it have
complex structure
CSF 9 Preparing safety and health plans. Remaining
CSF 10 Client understanding of project nature priorities and
needs Remaining
CSF 11 Granting suitable and enough time for project
planning and designing Remaining
CSF 12 Consultant recruitment and involvement in all project
activities. Remaining
Naming the Components
Once an interpretable pattern of loadings is done, the factors or components should be
named according to their substantive content or core. The components should have
conceptually distinct names and content. Items with higher loadings on a component
should play a more important role in naming the component. Also the common names for
114
components in previous studies were used in naming the components. In this study the
three components (factors) were named as the following:
Component 1: “Client actions and capabilities” with items: CSF 10, CSF 11,
CSF 12 and CSF 9.
Component 2: “Project characteristics” with items: CSF 4 and CSF 5.
Component 3: “Project feasibility and goals” with items: CSF 1 and CSF 2.
The proposed naming of the extracted components were discussed with experts and
academics to validate the naming of the principal components. Figure 4.6 below
describes the final results of the components extracted, percent of total explained
variance and eigenvalue of each component..
Figure 4. 6: Final components extracted from factor analysis for CSFs in conceptualizing and
preparation phase
Measures of reliability for each factor (component)
Once components have been extracted and rotated, it was necessary to cross checking if
the items in each component formed collectively explain the same measure within target
dimensions (Doloi, 2009). If items truly form the identified component, it is understood
that they should reasonably correlate with one another, but not the perfect correlation
Conceptualizing and preparation phase
Total variance: 68.58%
Component 3
Project feasibility and goals
Eigenvalue: 1.10
Component 2
Project characteristics
Eigenvalue: 1.37
Component 1
Client actions and capabilities
Eigenvalue: 3.01
115
though. Cronbach's alpha (Cα) test was conducted for each component. The higher value
of Cα denotes the greater internal consistency and vice versa. An alpha of 0.60 or higher
is the minimum acceptable level. Preferably, alpha will be 0.70 or higher (Field, 2009;
Weiers, 2011; Garson, 2013). According to results which were tabulated in Table 4.14,
Cα for component 1 is 0.77; Cα for component 2 is 0.76; and Cα for component 3 is 0.67.
They are considered to be acceptable.
Table 4. 14: Factor loadings for a three-component model CSFs of conceptualizing and
preparation phase
Component and factor loading
Fac
tor
load
ing
Eig
enval
ues
Var
ian
ce %
exp
lain
ed
Cro
nb
ach
's
Alp
ha
(Cα
)
Component 1: Client actions and capabilities
CSF 10 Client understanding of project nature
priorities and needs. 0.83
3.01 29.17 0.77 CSF 11 Granting suitable and enough time for
project planning and designing. 0.82
CSF 12 Consultant recruitment and involvement
in all project activities. 0.72
CSF 9 Preparing safety and health plans. 0.62
Component 2: Project characteristics
CSF 4 Project type (new, maintenance, completion
for existing one or rubble removal project). 0.91
1.37 20.50 0.76 CSF 5 Determining the construction project nature
(housing, infrastructure, public building,
…)
0.84
Component 3: Project feasibility and goals
CSF 1 Project feasibility and priority for the
society. 0.86
1.10 18.91 0.67 CSF 2 Deterministic, clear, sharable and realistic
project objectives 0.72
Kaiser-Meyer-Olkin measure of sampling adequacy = 0.73
Bartlett's test of sphericity: x2= 556.82,df=28,p-value =0.00
Total variance explained (%) = 68.58 %
Total reliability Cornbach’s α = 0.86
Four insignificant factor loadings (< 0.5) are blanked
4.4.2 The extracted components
The next section will interpret and discuss each of the extracted components as follows:
116
Component 1: Client actions and capabilities
First component named "Client actions and capabilities" explains 29.17 % of the total
variance and contains four items. The majority of items had relatively high factor
loadings (≥ 0.62). The four items are as follows:
1. Client understanding of project nature priorities and needs CSF 10, with factor
loading=0.83.
2. Granting Suitable and enough time for project planning and designing CSF 11, with
factor loading =0.82.
3. Recruiting and involving consultant in all project activities and phases CSF 12, with
factor loading=0.72.
4. Studying project tendency to accidents and hazards CSF 9, with factor loading=0.62.
Results from Table 4.14 indicated that CSF “Client understanding of project nature
priorities and needs” was the highest factor loading item of component 1 of CSFs in
conceptualizing and preparation phase with factor loading of 0.83. This CSF indicated
that in Palestine client plays an important role in the construction industry. When clients
understand what they need from the proposed project this will consultants and contractors
to understand the project. In addition client experience in similar in project nature is very
important because this will facilitate the management of the project and defining its
priorities easily. In Palestine the client usually governmental organization, UNRWA or
UNDP who's usually the one who write the proposal of the public construction project.
Those organizations mostly know what are they want from the proposed project and its
priorities since they have good experience in similar projects. Different studies results
considering this CSF as one of most important CSFs but not the most important one such
as in Thailand, where Toor et al (2008) stated that this CSF as one of important CSFs.
Also in Malaysia young et al (2014) ranked this CSF as very critical factor. Another
study also in Lithuania Gudienė et al (2013) indicated that the success of construction
projects depends on client’s experience as one of the most important CSFs.
117
The next CSF was “Granting Suitable and enough time for project planning and
designing” which had the second highest factor loading of 0.82. This CSF indicated that
when giving enough time to design and planning phase this will lead to success project in
terms of performance. Enough time giving more concentration for the team in their work
which can reduce variations, mistakes and costs. In Palestine this CSF is important since
it can be traced to the high level of uncertainty in the project environment and thus more
accurate planning is required. Also most public construction projects in Palestine have
multi clients such as government, donor, NGO's and each one have his ideas on designing
and planning so consultant should have enough time in order to satisfy all clients needs as
possible. Most previous studies did not mention this CSF directly. One of studies in
South Korea conducted by Park (2009) ranked this CSF as 10th
most important CSF from
client view point, 8th
from contractor viewpoint and 1st from subcontractor viewpoint.
Component 2: Project characteristics
Second component named "Project characteristics" explains 20.50% of the total variance
and contains two items. The items had relatively high factor loadings (≥ 0.84). The two
items are as follows:
1. Project type (new, maintenance, completion for existing one or rubble removal
project) CSF 4, with factor loading=0.91.
2. Determining the construction project nature (housing, infrastructure, public building,
…) CSF 5, with factor loading =0.84.
Results revealed that the CSF “Project type (new, maintenance, completion for existing
one or rubble removal project)” had high factor loading of 0.91. This CSF indicated that
determining project issues such as choosing project teams, defining the needed project
budget, time, design features, materials and quality levels depend on project type. In
Palestine each project type has his specific consultants, contractors and donors. Not all
donors fund maintenance projects or rubble removal projects also not all donors fund
roads project for examples due to political reasons. This give high important to specify
the type of project in the conceptualizing and preparation phase in order to submit the
project to donors and to hire consultants. In line with this study in Korea Cho et al (2009)
118
found that project type was very important project characteristics that affect the level of
project performance required by owner in the planning phase, and is thus expected to
help facilitate the decision making process in the early planning phase of a project. Also
in Taiwan Yang et al (2011) found that project type has a moderating effect on the
relationship between teamwork dimensions and overall project success. In Malaysia
Shehu et al (2014) observation indicated that project type affect cost variance and they
concluded that refurbishment projects tends to negative cost variance when compared to
new build.
Component 3: Project feasibility and goals
Third component named "Project feasibility and goals" explains 18.91% of the total
variance and contains two items. The items had relatively high factor loadings (≥ 0.72).
The two items are as follows:
1. Project feasibility and priority for the society CSF 1, with factor loading=0.86.
2. Deterministic, clear, sharable and realistic project objectives CSF 2, with factor
loading =0.72.
Results from Table 4.14 revealed that CSF “Project feasibility and priority for the
society” was the highest factor loading of this component with factor loading of 0.86.
This indicated this CSF is very important in public construction project and it should be
cleared in conceptualizing and preparation phase. In Palestine most of public construction
projects are funded by donors. So it is very important to study the feasibility of projects
and whether it can be executed especially in Gaza strip since it suffer from blockade and
shortage in construction materials and equipment's. Also cost is very important in
feasibility study since the budget of the project will be determined in this phase and the
grant amount will be limited to it and it is very hard to have big variation after the fund
approved. Donors and government also should take in consider to execute the top priority
projects that will benefit the society as much as possible. Some studies are in line with
this result like in Taiwan Ng et al (2012) indicated that the support of the community
should be considered as an important success factor. Also in China Zhao et al (2013)
indicated that public perception, awareness, attitude, behavior and acceptability should be
119
taken into consideration seriously at the feasibility phase. Zhao et al (2013) concluded
that since project funds confirmed basically on the feasibility study outputs so the project
developer and the potential investors have to go through the tedious procedure prior to
the final approval and confirmation of the project from donors.
The second CSF in this component is “Deterministic, clear, sharable and realistic project
objectives” and it has factor loading of 0.72. In Palestine commitment to project is
basically depends on commitment to clear and realistic objectives. Thus clear and
realistic objectives helps project team to focus on target and lead to eliminate the non-
value added activities. Respondents in this study give moderate importance this CSF. In
line to this study in Vietnam Nguyen et al (2004) ranked this CSF as the first attribute in
commitment component. Similar results in India Iyer and Jha (2006) indicated that
inadequate project formulation in the beginning was the most critical factor in owner
incompetence component which lead to project failure. And in Saudi Arabia Alhaadir and
Panuwatwanich (2011) found that clear and reasonable project objectives was the second
weighted CSF.
4.4.2.1 CSFs related to planning and designing phase
In this phase of data analysis process, factor analysis was employed to reduce a large
number of items (CSFs) to a smaller set of underlying components that summarize the
essential information contained in the items. Using SPSS 22, Principle Component
Analysis (PCA) with Varimax rotation were performed to set up which items could
capture the aspects of same dimension of the 19 CSFs and examine the underlying
structure or structure of interrelationships among the CSFs. In order to perform the factor
analysis for used items, all the appropriate checks and procedures were fulfilled.
4.4.2.1.1 Appropriateness of factor analysis
The data was first assessed for its suitability to the factor analysis application. According
to the following:
120
Data distribution
The assumption of normality is most important requirement to generalize the results of
factor analysis test beyond the sample collected (Field, 2009; Zaiontz, 2015). The one-
sample Kolmogorov-Smirnov test was used to test that a item of interest is normally
distributed. Table 3.8 showed that the distributions of CSFs which related to planning and
designing phase is normally distributed. So the results had been satisfied with this
requirement.
Validity of sample size
The validity of factor analysis is dependent on sample size. PCA can be conducted on a
sample that has fewer than 100 respondents, but more than 50 respondents, and the
sample size for this study was 274. On the other hand, the common rule is to suggest that
sample size contains at least 10:15 respondents per item. In other words, sample size
should be at least 10 times the number of items and some even recommend 20 times
(Field, 2009; Zaiontz, 2015). Fortunately, for CSFs of planning and designing phase, the
condition was verified. This field contains 19 items and the sample size was 274. With
274 respondents and 19 items CSFs, the ratio of respondents to items are 14.4:1, which
exceeds the requirement ratio 10:15.
Measures of reliability for the whole items
Cronbach's alpha test was performed on the items in CSFs of planning and designing
phase. The value of Cronbach’s alpha (Cα) could be anywhere in the range of 0 to 1,
where a higher value denotes the greater internal consistency and vice versa. An alpha of
0.60 or higher is the minimum acceptable level. Preferably, alpha will be 0.70 or higher
(Field, 2009). As shown in Table 4.15, the value of calculated Cα for all items in the field
CSFs of planning and designing phase for the final run was 0.89 which considered to be
marvelous.
121
Kaiser-Meyer-Olkin (KMO) and Bartlett's test
The Kaiser-Meyer-Olkin (KMO) sampling adequacy test and Bartlett's test of Sphericity
were carried out. The results of these tests are reported in Table 4.15. The value of the
KMO measure of sampling adequacy was 0.93 for first run and 0.90 for the final run
(close to 1), and was considered acceptable and marvelous because it exceeds the
minimum requirement of 0.50 (‘superb’ according to Kaiser, 1974; Field, 2009; Zaiontz,
2015). Moreover, the Bartlett test of sphericity was another indication of the strength of
the relationship among items. The Bartlett test of sphericity was 2179.29 for the first run
and 1461.18 for the final run and the associated significance level was 0.00. The
probability value (Sig.) associated with the Bartlett test is less than 0.01, which satisfies
the PCA requirement. This indicated that the correlation matrix was not an identity
matrix and all of the items are correlated (Field, 2009; Zaiontz, 2015). According to the
results of these two tests, the sample data of (CSFs in planning and designing phase) were
appropriated for factor analysis.
Table 4. 15: KMO and Bartlett's Test for CSFs of planning and designing phase
Factor analysis run
description
First run Fourth run
(Final run)
Number of included items 19 13
Kaiser-Meyer-Olkin Measure of
Sampling Adequacy. 0.93 0.90
Bartlett's Test of Sphericity
Approx. Chi-
Square 2179.29 1461.18
Df 171 78
P-value 0.00 0.00
Cronbach's Alpha 0.89 0.89
Validity of Correlation matrix (Correlations between items)
Table 4.16 illustrates the correlation matrix for the 19 CSFs. It is simply a rectangular
array of numbers which gives the correlation coefficients between a single item and every
other item in the investigation (Field, 2009; Zaiontz, 2015). As shown in Table 4, the
correlation coefficient between an item and itself is always 1; hence the principal
diagonal of the correlation matrix contains 1s. The correlation coefficients above and
below the principal diagonal are the same. PCA requires that there be some correlations
122
greater than 0.30 and less than 0.8 between the items included in the analysis. For this set
of items, that many of the correlations in the matrix are strong and greater than 0.30
(Field, 2009; Zaiontz, 2015). Correlations have been satisfied with this requirement so no
items was removed at this step.
123
Table 4. 16: Correlations between items of CSFs of planning and designing phase
CSF 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
13 1.00
14 0.41 1.00
15 0.32 0.20 1.00
16 0.24 0.41 0.32 1.00
17 0.27 0.25 0.41 0.34 1.00
18 0.29 0.31 0.34 0.35 0.68 1.00
19 0.30 0.23 0.55 0.35 0.50 0.51 1.00
20 0.25 0.15 0.35 0.21 0.44 0.42 0.53 1.00
21 0.29 0.27 0.24 0.27 0.43 0.43 0.48 0.40 1.00
22 0.28 0.34 0.25 0.34 0.45 0.44 0.42 0.36 0.53 1.00
23 0.22 0.28 0.27 0.32 0.45 0.41 0.47 0.37 0.44 0.36 1.00
24 0.24 0.23 0.15 0.26 0.33 0.37 0.31 0.32 0.29 0.35 0.39 1.00
25 0.33 0.33 0.23 0.36 0.43 0.40 0.40 0.37 0.44 0.42 0.44 0.42 1.00
26 0.25 0.28 0.32 0.34 0.46 0.47 0.50 0.44 0.40 0.39 0.50 0.32 0.42 1.00
27 0.25 0.28 0.29 0.40 0.42 0.47 0.54 0.41 0.51 0.38 0.46 0.27 0.39 0.52 1.00
28 0.23 0.21 0.37 0.31 0.45 0.43 0.47 0.35 0.40 0.45 0.35 0.28 0.29 0.41 0.48 1.00
29 0.19 0.24 0.33 0.42 0.55 0.49 0.45 0.43 0.43 0.36 0.45 0.32 0.42 0.39 0.58 0.58 1.00
30 0.22 0.25 0.28 0.34 0.34 0.41 0.48 0.30 0.43 0.46 0.34 0.26 0.39 0.52 0.52 0.49 0.48 1.00
31 0.22 0.33 0.22 0.36 0.42 0.52 0.36 0.25 0.45 0.44 0.34 0.28 0.42 0.43 0.50 0.41 0.50 0.54 1.00
124
Communalities (common variance)
Communalities represent the proportion of the variance in the original items that is
accounted for by the factor solution. The factor solution should explain at least half of
each original item's's variance, so the communality value for each item should be 0.50 or
higher (Field, 2009; Zaiontz, 2015). Four iterations of factor analysis were run. On third
iteration of factor analysis test, the communality for the item CSF 16, CSF 21, CSF 22,
CSF 23, CSF 24 and CSF 25 were less than 0.50. Since they were less than 0.50, the
items had to be removed and the PCA was computed again (new iteration). Table 4.17
shows that all of the communalities for all remaining items satisfy the minimum
requirement of being larger than 0.50.
Table 4. 17: Communalities of CSFs of planning and designing phase of first and final
runs
Item. CSFs First run
communalities
Fourth run
(Final run)
communalities
CSF 13 Coordinating with related formal parties
such as (municipalities, electricity
companies, ministries,… etc.).
0.63 0.72
CSF 14 Client contribution on project designing and
planning.
0.71 0.74
CSF 15 Past relevant experience of consultant on
designing similar project.
0.76 0.62
CSF 16 Ability of project parties to generate
innovative ideas.
0.50 Removed
CSF 17 Specific and measurable project quality
standards.
0.57 0.56
CSF 18 Approved, clear and updated codes,
specifications and regulations for
construction industry.
0.54 0.56
CSF 19 Efficient technical capability of consultant
for example existence of skilled team and
designers.
0.69 0.68
CSF 20 Designing project according to updated
codes and standards in order to eliminate
possible errors.
0.62 0.57
CSF 21 Considering operation and maintenance
requirements into project design.
0.50 Removed
125
Table 4. 17: Communalities of CSFs of planning and designing phase of first and final
runs
Item. CSFs First run
communalities
Fourth run
(Final run)
communalities
CSF 22 Social, cultural and environmental impacts
on project type, design and planning.
0.48 Removed
CSF 23 Project physical environment of project like
(location, soil works, availability of
surrounding infrastructure, etc.).
0.51 Removed
CSF 24 Ease of having permits, licenses and any
related approvals from governmental
institutions.
0.59 Removed
CSF 25 Availability of organized legal environment
i.e. (laws of industry encouragement,
conflict resolution, litigations, etc).
0.57 Removed
CSF 26 Strong, detailed and updated integrated
planning effort in design and construction.
0.50 0.50
CSF 27 All key participants have participate in the
detailed project planning within their area of
expertise.
0.60 0.61
CSF 28 Effective schedule management and realistic
forecasting of project duration.
0.57 0.52
CSF 29 The project has a formal organizational chart
covering the entire project.
0.61 0.62
CSF 30 Risk identification management and
allocation.
0.62 0.60
CSF 31 Involvement of local community, project
beneficiaries and the affected parties in
project plans and policies.
0.65 0.68
Total Variance Explained
Using the output from iteration 4, there were three eigenvalues greater than 1. The
eigenvalue criterion stated that each component explained at least one item's worth of the
variability and therefore only components with eigenvalues greater than one should be
retained (Larose, 2006; Field, 2009). The latent root criterion for number of components
to derive would indicate that there were 3 components to be extracted for these items.
Results were tabulated in Table 4.18. The three components solution explained a sum of
the variance with component 1 contributing 44.51%; component 2 contributing 8.82%;
and component 3 contributing 8.20%. All the remaining components are not significant.
126
The three components were then rotated via varimax (orthogonal) rotation approach. This
does not change the underlying solution, or the relationships among the items. Rather, it
presents the pattern of loadings in a manner that is easier to interpret components (Field,
2009; Zaiontz, 2015). The rotated solution revealed that the three components solution
explained a sum of the variance with component 1 contributing 28.72%; component 2
contributing 21.11%; and component 3 contributing 11.70%. These three components
explained 61.53% of total variance for the varimax rotation which is acceptable since it
was more than 50%.
Table 4. 18: Total variance Explained of CSFs of planning and designing phase
Att
ribute
Initial Eigenvalues Extraction Sums of Squared
Loadings
Rotation Sums of Squared
Loadings
Tota
l
% o
f V
aria
nce
Cum
ula
tive
%
Tota
l
% o
f V
aria
nce
Cum
ula
tive
%
Tota
l
% o
f V
aria
nce
Cum
ula
tive
%
1 5.79 44.51 44.51 5.79 44.51 44.51 3.73 28.72 28.72
2 1.15 8.82 53.33 1.15 8.82 53.33 2.74 21.11 49.83
3 1.07 8.20 61.53 1.07 8.20 61.53 1.52 11.70 61.53
4 0.79 6.09 67.61
5 0.72 5.57 73.18
6 0.62 4.80 77.98
7 0.54 4.19 82.17
8 0.51 3.90 86.07
9 0.45 3.48 89.55
10 0.41 3.16 92.71
11 0.38 2.95 95.66
12 0.30 2.34 98.00
13 0.26 2.00 100.00
Scree Plot
The scree plot below in Figure 4.7 is a graph of the eigenvalues against all the
components for final run of analysis. This graph can also be used to decide on number of
components that can be derived. Although scree plots are very useful, component
selection should not be based on this criterion alone (Field, 2009). The point of interest is
where the curve starts to flatten. It can be seen that the curve begins to flatten between
127
components 3 and 4. Note also that component 4 has an eigenvalue of less than 1, so only
three components have been retained to be extracted.
Figure 4. 7: Scree Plot for CSFs of planning and designing phase
Rotated Component Matrix
Table 4.20 shows the component loadings after rotation of 13 items (from the original 19
items) on the three components extracted and rotated. The pattern of factor loadings
should be examined to identify items that have complex structure (complex structure
occurs when one item has high loadings or correlations (0.50 or greater) on more than
one component). If an item has a complex structure, it should be removed from the
analysis (Reinard, 2006; Field, 2009; Zaiontz, 2014). As shown in Table 4.20, all items
factor loading were above 0.50 and all items had simple structure. The items are listed in
the order of size of their factor loadings.
As a conclusion of analysis 6 Items were removed and 13 items remaining as summarized
in Table 4.19.
0.00
1.00
2.00
3.00
4.00
5.00
6.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13
Eig
en
valu
es
Component
128
Table 4. 19: Summary of remaining and removed CSFs in planning and designing phase as a
result of factor analysis runs
Item. CSFs Result
CSF 13 Coordinating with related formal parties such as
(municipalities, electricity companies, ministries,… etc.).
Remaining
CSF 14 Client contribution on project designing and planning. Remaining
CSF 15 Past relevant experience of consultant on designing similar
project.
Remaining
CSF 16 Ability of project parties to generate innovative ideas. Removed since
communalities less
than 0.5
CSF 17 Specific and measurable project quality standards. Remaining
CSF 18 Approved, clear and updated codes, specifications and
regulations for construction industry.
Remaining
CSF 19 Efficient technical capability of consultant for example
existence of skilled team and designers.
Remaining
CSF 20 Designing project according to updated codes and standards
in order to eliminate possible errors.
Remaining
CSF 21 Considering operation and maintenance requirements into
project design.
Removed since
communalities less
than 0.5
CSF 22 Social, cultural and environmental impacts on project type,
design and planning.
Removed since
communalities less
than 0.5
CSF 23 Project physical environment of project like (location, soil
works, availability of surrounding infrastructure, etc.).
Removed since
communalities less
than 0.5
CSF 24 Ease of having permits, licenses and any related approvals
from governmental institutions.
Removed since
communalities less
than 0.5
CSF 25 Availability of organized legal environment i.e. (laws of
industry encouragement, conflict resolution, litigations, etc).
Removed since
communalities less
than 0.5
CSF 26 Strong, detailed and updated integrated planning effort in
design and construction.
Remaining
CSF 27 All key participants have participate in the detailed project
planning within their area of expertise.
Remaining
CSF 28 Effective schedule management and realistic forecasting of
project duration.
Remaining
CSF 29 The project has a formal organizational chart covering the
entire project.
Remaining
CSF 30 Risk identification management and allocation. Remaining
CSF 31 Involvement of local community, project beneficiaries and
the affected parties in project plans and policies.
Remaining
129
Naming the Components
Once an interpretable pattern of loadings is done, the factors or components should be
named according to their substantive content or core. The components should have
conceptually distinct names and content. Items with higher loadings on a component
should play a more important role in naming the component. Also the common names for
components in previous studies were used in naming the components. In this study the
three components were named as the following:
Component 1: “Planning and designing management” with items: CSF 18, CSF
26, CSF 27, CSF 28, CSF 29, CSF 30 and CSF 31.
Component 2: “Consultant actions and capabilities” with items: CSF 15, CSF
17, CSF 19 and CSF 20.
Component 3: “Client related factors” with items: CSF 13 and CSF 14.
The proposed naming of the extracted components were discussed with experts and
academics to validate the naming of the principal components. Figure 4.8 below
describes the final results of the components extracted, percent total explained variance
and eigenvalues of each component.
Figure 4. 8: Final components extracted from factor analysis for CSFs in planning and
designing phase
Planning and designing phase
Total variance: 61.53%
Component 3
Client related factors
Eigenvalue: 1.07
Component 2
Consultant actions and capabilities
Eigenvalue: 1.15
Component 1
Planning and designing management
Eigenvalue: 5.79
130
Measures of reliability for each component
Once components have been extracted and rotated, it was necessary to cross checking if
the items in each component formed collectively explain the same measure within target
dimensions (Doloi, 2009). If items truly form the identified component, it is understood
that they should reasonably correlate with one another, but not the perfect correlation
though. Cronbach's alpha (Cα) test was conducted for each component. The higher value
of Cα denotes the greater internal consistency and vice versa. An alpha of 0.60 or higher
is the minimum acceptable level. Preferably, alpha will be 0.70 or higher (Field, 2009).
According to results which were tabulated in Table 4.20, Cα for component 1 is 0.85; Cα
for component 2 is 0.78; and Cα for component 3 is 0.67. They are considered to be
acceptable.
Table 4. 20: Factor loadings for a three-component model CSFs of planning and designing
phase
Component and factor loading
Fac
tor
load
ing
Eig
enval
ues
Var
iance
%
expla
ined
Cro
nbac
h's
Alp
ha
(Cα
)
Component 1: Planning and designing management
CSF 31 Involvement of local community, project
beneficiaries and the affected parties in
project plans and policies.
0.79
5.79 28.72 0.85
CSF 30 Risk identification management and
allocation.
0.75
CSF 27 All key participants have participate in the
detailed project planning within their area
of expertise.
0.71
CSF 29 The project has a formal organizational
chart covering the entire project.
0.70
CSF 28 Effective schedule management and
realistic forecasting of project duration.
0.61
CSF 26 Strong, detailed and updated integrated
planning effort in design and
construction.
0.58
CSF 18 Approved, clear and updated codes,
specifications and regulations for
construction industry.
0.56
131
Table 4. 20: Factor loadings for a three-component model CSFs of planning and designing
phase
Component and factor loading
Fac
tor
load
ing
Eig
enval
ues
Var
ian
ce %
exp
lain
ed
Cro
nb
ach
's
Alp
ha
(Cα
)
Component 2: Consultant actions and capabilities
CSF 15 Past relevant experience of consultant on
designing similar project.
0.75
1.15 21.11 0.78
CSF 19 Efficient technical capability of consultant
for example existence of skilled team and
designers.
0.72
CSF 20 Designing project according to updated
codes and standards in order to eliminate
possible errors.
0.70
CSF 17 Specific and measurable project quality
standards.
0.57
Component 3: Client related factors
CSF 14 Client contribution on project designing
and planning. 0.81
1.07 11.70 0.67 CSF 13 Coordinating with related formal parties
such as (municipalities, electricity
companies, ministries, etc.).
0.78
Kaiser-Meyer-Olkin measure of sampling adequacy = 0.90
Bartlett's test of sphericity: x2= 1461.18,df=78,p-value =0.00
Total variance explained (%) = 61.53 %
Total reliability Cornbach’s α = 0.89
Four insignificant factor loadings (< 0.5) are blanked
4.4.2.1.2 The extracted components
The next section will interpret and discuss each of the extracted components as follows:
Component C 1: Planning and designing management
First component named "Planning and designing management" explains 28.72 % of the
total variance and contains seven items. The majority of items had relatively high factor
loadings (≥ 0.56). The seven items are as follows:
1. Involvement of local community, project beneficiaries and the affected parties in
project plans and policies CSF 31, with factor loading=0.79.
2. Risk identification management and allocation CSF 30, with factor loading =0.75.
132
3. All key participants have participate in the detailed project planning within their area
of expertise CSF 27, with factor loading=0.71.
4. The project has a formal organizational chart covering the entire project CSF 29,
with factor loading=0.70.
5. Effective schedule management and realistic forecasting of project duration CSF 28,
with factor loading=0.61.
6. Strong, detailed and updated integrated planning effort in design and construction
CSF 26, with factor loading=0.58.
7. Approved, clear and updated codes, specifications and regulations for construction
industry CSF 18, with factor loading=0.56.
Results from Table 4.20 indicated that CSF “Involvement of local community, project
beneficiaries and the affected parties in project plans and policies” was the highest
loaded factor of this component with factor loading =0.79. In Palestinian public
construction projects local community and beneficiaries involvement is are very
important to guarantee project success. Since most Palestinian public projects were
funded from donors and one of the main things that demanded by funders was to satisfy
beneficiaries and local community since the projects holds for serving them. Also the KPI
"Beneficiaries satisfaction on project functionality" which determined in previous section
of this study was ranked as the 6th
important KPI. This support that it was very important
to involve beneficiaries on project planning to enhance their satisfaction. In Durban and
South Africa Garbharran et al (2012) had similar results. Garbharran et al (2012)
classified the community as one of the project stakeholders and they indicated that
community involvement was a key element for project success and enhances the
organization's social responsibility standing. They ranked the involvement of
stakeholders as being the most important item for project success in South Africa. Also
Ihuah et al (2014) concluded that beneficiaries' involvement was ranked as 8th
CSF in
sustainable housing estates’ delivery and provision in Nigeria.
The second high loaded CSF was “Risk identification management and allocation” with
factor loading = 0.75. This CSF indicated that before starting the project all the risks
should predicted to minimize the uncertainty of project environment in order to ensure
133
project success. In Palestine many political events should be considered like wars, ports
closure and windy and raining climate some times. So decision makers and planners
should give high important to identify all those risks. In UK Davies (2002) and Fortune
and White (2006) had the same result on their study and they concluded that risk
identification was an important CSFs that should take in consider in planning phase.
Similar results in Ismail et al (2012) study which held in Malaysia. Ismail et al (2012)
indicated that building industry is not well accepted by the construction parties because
of failure to adequately deal with risks and they concluded that risk management is 10th
ranked important success factor of building projects in Malaysia. Also Lehtiranta et al
(2012) study stated that the main contractor’s ability to manage project risks
systematically can be observed as a predictor of project success in Finland.
Component 2: Consultant actions and capabilities
Second component named "Consultant actions and capabilities" explains 21.11 % of the
total variance and contains four items. The majority of items had relatively high factor
loadings (≥ 0.57). The four items are as follows:
1. Past relevant experience of consultant on designing similar project CSF 15, with
factor loading=0.75.
2. Efficient technical capability of consultant for example existence of skilled team and
designers CSF 19, with factor loading =0.72.
3. Designing project according to updated codes and standards in order to eliminate
possible errors CSF 20, with factor loading=0.70.
4. Specific and measurable project quality standards CSF 17, with factor loading=0.57.
Results from Table 4.20 stated that the highest factor loaded CSF of the second
component was “Past relevant experience of consultant on designing similar project”
followed by CSF “Efficient technical capability of consultant for example existence of
skilled team and designers”. These CSFs indicated that consultant experience is a vital
issue to project success since his main responsibilities is to prepare the design of the
project, to identify required quality specification, types of materials, how to use new
technology and forecasting project costs. Without such previous experience in the field of
work the tendency of project to failure will be high. In Palestine most public projects
134
needed professional consultant team since client himself usually hadn't enough skilled
team. So recurring skilled consultant in Palestinian construction industry is main issue.
Tan and Ghazali (2011) study in Malaysia is in line with this study, they mentioned that
design team experience was very important CSF. Also same results in Taiwan in Chen et
al (2007) and Chen et al (2012) studies which ranked the technical experience as the
second important CSF. Chen et al (2007) and Chen et al (2012) concluded that
construction projects rely on organizing the abilities, experience, professional knowledge
and skills at the different levels of the teams involved include project owners, architects,
engineers, consultants, contractors, suppliers, etc.
Component C3: Client related factors
The third component named "Client related factors" explains 11.70 % of the total
variance and contains two items. The majority of items had relatively high factor loadings
(≥ 0.78). The two items are as follows:
1. Client contribution on project designing and planning CSF 14, with factor
loading=0.81.
2. Coordinating with related formal parties such as (municipalities, electricity
companies, ministries, etc.) CSF 13, with factor loading =0.78.
Results revealed that the highest factor loaded item in this component was CSF “Client
contribution on project designing and planning”. This CSF indicated that client should
have important contribution in designing and planning phase. Client contribution is
important because he is the most one who understand project goals, needs and purposes.
The lack in coordination between client, designers and planners will have bad effects like
variations, design changes and less commitment to project goals and objectives. In
Palestine public construction projects supervised generally by engineering departments of
ministries (such ministries like MPWH,MOLG, MOHE)or NGO's like UNRWA and
UNDP. Those organizations are the clients of Palestinian public construction projects. In
UK Andersen et al (2006) support this point of view since they found that the 3rd
most
important factor in improving managerial ability to deliver results in time and at cost was
the stakeholder contribution of project plans. Also in Thailand Toor et al (2008) found
that this CSF was the 3rd loading factor in the comprehension component. Toor et al
135
(2008) also indicated that goals and priorities, demands of client and interests of all
related parties are well recognized and considered in the project plans so for a reasonable
comprehension of the project, the main role is to be played by the client to first clearly
provide his requirements in the planning phase.
4.4.2.2 CSFs related to tendering and contracting phase
In this phase of data analysis process, factor analysis was employed to reduce a large
number of items (CSFs) to a smaller set of underlying factors that summarize the
essential information contained in the items. Using SPSS 22, Principle Component
Analysis (PCA) with Varimax rotation were performed to set up which items could
capture the aspects of same dimension of the 16 CSFs and examine the underlying
structure or structure of interrelationships among the CSFs. In order to perform the factor
analysis for used items, all the appropriate checks and procedures were fulfilled.
4.4.2.2.1 Appropriateness of factor analysis
The data was first assessed for its suitability to the factor analysis application. According
to the following:
Data distribution
The assumption of normality is most important requirement to generalize the results of
factor analysis test beyond the sample collected (Field, 2009; Zaiontz, 2015). The one-
sample Kolmogorov-Smirnov test was used to test that an item of interest is normally
distributed. Table 3.8 showed that the distributions of CSFs which related to tendering
and contracting phase is normally distributed. So the results had been satisfied with this
requirement.
Validity of sample size
The validity of factor analysis is dependent on sample size. PCA can be conducted on a
sample that has fewer than 100 respondents, but more than 50 respondents, and the
sample size for this study was 274. On the other hand, the common rule is to suggest that
sample size contains at least 10:15 respondents per item. In other words, sample size
136
should be at least 10 times the number of items and some even recommend 20 times
(Field, 2009; Zaiontz, 2015). Fortunately, for CSFs of tendering and contracting phase ,
the condition was verified. This field contains 16 items and the sample size was 274.
With 274 respondents and 19 items CSFs, the ratio of respondents to items are 17.1: 1,
which exceeds the requirement ratio 10:15.
Measures of reliability for the whole items
Cronbach's alpha test was performed on the items in CSFs of tendering and contracting
phase . The value of Cronbach’s alpha (Cα) could be anywhere in the range of 0 to 1,
where a higher value denotes the greater internal consistency and vice versa. An alpha of
0.60 or higher is the minimum acceptable level. Preferably, alpha will be 0.70 or higher
(Field, 2009). As shown in Table 4.21, the value of calculated Cα for all items in the field
CSFs of tendering and contracting phase for the final run was 0.85 which considered to
be marvelous.
Kaiser-Meyer-Olkin (KMO) and Bartlett's test
The Kaiser-Meyer-Olkin (KMO) sampling adequacy test and Bartlett's test of Sphericity
were carried out. The results of these tests are reported in Table 4.21. The value of the
KMO measure of sampling adequacy was 0.89 for first run and 0.86 for the final run
(close to 1), and was considered acceptable and marvelous because it exceeds the
minimum requirement of 0.50 (‘superb’ according to Kaiser, 1974; Field, 2009; Zaiontz,
2015). Moreover, the Bartlett test of sphericity was another indication of the strength of
the relationship among items. The Bartlett test of sphericity was 1617.57 for the first run
and 955.14 for the final run and the associated significance level was 0.00. The
probability value (Sig.) associated with the Bartlett test is less than 0.01, which satisfies
the PCA requirement. This indicated that the correlation matrix was not an identity
matrix and all of the items are correlated (Field, 2009; Zaiontz, 2015). According to the
results of these two tests, the sample data of (CSFs in tendering and contracting phase )
were appropriated for factor analysis.
137
Table 4. 21: KMO and Bartlett's Test for CSFs of tendering and contracting phase Factor analysis run description
First run Second run
(Final run)
Number of included items 16 11
Kaiser-Meyer-Olkin Measure of
Sampling Adequacy.
0.89 0.86
Bartlett's Test of Sphericity
Approx. Chi-
Square 1617.57 955.14
Df 120.00 55.00
P-value 0.00 0.00
Cronbach's Alpha 0.86 0.85
Validity of Correlation matrix (Correlations between items)
Table 4.22 illustrates the correlation matrix for the 19 CSFs. It is simply a rectangular
array of numbers which gives the correlation coefficients between a single item and every
other item in the investigation (Field, 2009; Zaiontz, 2015). As shown in Table 4.22, the
correlation coefficient between an item and itself is always 1; hence the principal
diagonal of the correlation matrix contains 1s. The correlation coefficients above and
below the principal diagonal are the same. PCA requires that there be some correlations
greater than 0.30 and less than 0.8 between the items included in the analysis. For this set
of items, that many of the correlations in the matrix are strong and greater than 0.30
(Field, 2009; Zaiontz, 2015). Correlations have been satisfied with this requirement so no
items was removed at this step.
138
Table 4. 22: Correlations between items of CSFs of tendering and contracting phase CSF CSF 32 CSF 33 CSF 34 CSF 35 CSF 36 CSF 37 CSF 38 CSF 39 CSF 40 CSF 41 CSF 42 CSF 43 CSF 44 CSF 45 CSF 46 CSF 47
CSF 32 1.00
CSF 33 0.44 1.00
CSF 34 0.35 0.37 1.00
CSF 35 0.16 0.14 0.35 1.00
CSF 36 0.23 0.26 0.40 0.35 1.00
CSF 37 0.17 0.22 0.27 0.37 0.54 1.00
CSF 38 0.35 0.41 0.40 0.26 0.46 0.41 1.00
CSF 39 0.28 0.53 0.25 0.17 0.27 0.37 0.46 1.00
CSF 40 0.32 0.41 0.36 0.11 0.35 0.20 0.43 0.51 1.00
CSF 41 0.21 0.21 0.27 0.18 0.32 0.33 0.35 0.32 0.43 1.00
CSF 42 0.28 0.31 0.26 0.22 0.39 0.31 0.43 0.38 0.40 0.43 1.00
CSF 43 0.28 0.38 0.34 0.32 0.46 0.37 0.56 0.40 0.42 0.46 0.57 1.00
CSF 44 0.14 0.35 0.26 0.19 0.35 0.25 0.40 0.40 0.42 0.32 0.34 0.52 1.00
CSF 45 0.15 0.17 0.44 0.38 0.38 0.28 0.42 0.22 0.27 0.32 0.30 0.43 0.42 1.00
CSF 46 0.13 0.33 0.35 0.30 0.36 0.32 0.46 0.44 0.41 0.34 0.36 0.45 0.54 0.52 1.00
CSF 47 0.23 0.16 0.31 0.29 0.39 0.44 0.52 0.37 0.34 0.28 0.43 0.44 0.37 0.43 0.52 1.00
139
Communalities (common variance)
Communalities represent the proportion of the variance in the original items that is
accounted for by the factor solution. The factor solution should explain at least half of
each original item's's variance, so the communality value for each item should be 0.50 or
higher (Field, 2009; Zaiontz, 2015). Two iterations of factor analysis were done. On first
iteration of factor analysis test, the communality for the item CSF 37, CSF 41 and CSF
42 were less than 0.50. Since they were less than 0.50, the items had to be removed and
the PCA was computed again (new iteration). Other CSFs which were (CSF 9 and CSF
14) removed in the other steps of factor analysis. Table 4.23 shows that all of the
communalities for all remaining items satisfy the minimum requirement of being larger
than 0.50.
Table 4. 23: Communalities of CSFs of tendering and contracting phase of first and
final runs
Item. CSFs First run
communalities
Second run
(Final run)
communalities
CSF 32 The client has a mechanism to manage the
bids.
0.67 0.69
CSF 33 Transparent and efficient procurement
criteria depends on applicable laws and
regulations.
0.66 0.74
CSF 34 Consider consultant and contractor past
performance and reputation as awarding
criteria.
0.53 0.60
CSF 35 Past relevant experience of client in
awarding bids and managing contracts.
0.58 0.64
CSF 36 Past related experience of consultant in
sharing in similar bids and contracts.
0.54 0.58
CSF 37 Past related experience of contractor in
sharing in similar bids and contracts.
0.48 Removed
CSF 38 The consultant and the contractor have a
mechanism to manage the tenders and
compete.
0.56 0.59
CSF 39 The client interprets all project requirements
and location during the bids preparatory
meeting.
0.57 0.57
CSF 40 Documentation the preparation meetings in
details.
0.58 Removed
140
Table 4. 23: Communalities of CSFs of tendering and contracting phase of first and
final runs
Item. CSFs First run
communalities
Second run
(Final run)
communalities
CSF 41 Visiting project location by all consultants
and contractors before filling out the bid
form.
0.37 Removed
CSF 42 Granting enough time for consultants and
contractors to fill out the bid form.
0.44 Removed
CSF 43 Participating of related project parties in
financial and technical evaluation of tenders.
0.58 0.57
CSF 44 Effective contract management included
precise formulation, documentation and
enough detailed incentives, bonds, penalties,
…etc.
0.58 0.61
CSF 45 Project profitability for consultant and
contractor
0.54 Removed
CSF 46 Economic environment in terms of materials
quantity, quality, and price, local currency
value, …etc.
0.61 0.66
CSF 47 Delegation and authority allocation of
project workers.
0.52 0.52
Total Variance Explained
Using the output from iteration 2, there were three eigenvalues greater than 1. The
eigenvalue criterion stated that each component explained at least one item's worth of the
variability and therefore only components with eigenvalues greater than one should be
retained (Larose, 2006; Field, 2009). The latent root criterion for number of components
to derive would indicate that there were 3 components to be extracted for these items.
Results were tabulated in Table 4.24. The three components solution explained a sum of
the variance with component 1 contributing 41.04%; component 2 contributing 10.68%;
and component 3 contributing 9.76%. All the remaining components are not significant.
The three components were then rotated via varimax (orthogonal) rotation approach. This
does not change the underlying solution, or the relationships among the items. Rather, it
presents the pattern of loadings in a manner that is easier to interpret components (Field,
2009; Zaiontz, 2015). The rotated solution revealed that the three components solution
141
explained a sum of the variance with component 1 contributing 26.95%; component 2
contributing 17.40%; and component 3 contributing 17.13%. These three components
explained 61.48% of total variance for the varimax rotation which is acceptable since it
was more than 50%.
Table 4. 24: Total variance Explained of CSFs of tendering and contracting phase
Att
rib
ute
Initial Eigenvalues Extraction Sums of Squared
Loadings
Rotation Sums of Squared
Loadings
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
1 4.51 41.04 41.04 4.51 41.04 41.04 2.96 26.95 26.95
2 1.18 10.68 51.72 1.18 10.68 51.72 1.91 17.40 44.35
3 1.07 9.76 61.48 1.07 9.76 61.48 1.88 17.13 61.48
4 0.78 7.10 68.58
5 0.67 6.05 74.63
6 0.60 5.48 80.11
7 0.58 5.31 85.42
8 0.48 4.38 89.80
9 0.42 3.82 93.61
10 0.37 3.35 96.96
11 0.33 3.04 100.00
Scree Plot
The scree plot below in Figure 4.9 is a graph of the eigenvalues against all the
components for the final run of analysis. This graph can also be used to decide on number
of components that can be derived. Although scree plots are very useful, component
selection should not be based on this criterion alone (Field, 2009). The point of interest is
where the curve starts to flatten. It can be seen that the curve begins to flatten between
components 3 and 4. Note also that component 4 has an eigenvalue of less than 1, so only
three components have been retained to be extracted.
142
Figure 4. 9: Scree Plot for CSFs of tendering and contracting phase
Rotated Component Matrix
Table 4.26 shows the factor loadings after rotation of 13 items (from the original 19
items) on the three components extracted and rotated. The pattern of factor loadings
should be examined to identify items that have complex structure (complex structure
occurs when one item has high loadings or correlations (0.50 or greater) on more than
one component). If an item has a complex structure, it should be removed from the
analysis (Reinard, 2006; Field, 2009; Zaiontz, 2014). According to that, it was necessary
to remove item CSF 9 and CSF 14 because they demonstrated complex structure. They
was loaded under two components (component 1 and component 3) in the same time with
a factor loading of more than 0.5. As shown in Table 4.26, all items factor loading were
above 0.50 and all items had simple structure. The items are listed in the order of size of
their factor loadings.
As a conclusion of analysis 5 Items were removed and 11 items remaining as summarized
in Table 4.25.
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
0 1 2 3 4 5 6 7 8 9 10 11
Eige
nva
lue
s
Component
143
Table 4. 25: Summary of remaining and removed CSFs in tendering and contracting phase as
a result of factor analysis runs
Item. CSFs Result
CSF 32 The client has a mechanism to manage the bids. Remaining
CSF 33 Transparent and efficient procurement criteria depends on
applicable laws and regulations.
Remaining
CSF 34 Consider consultant and contractor past performance and
reputation as awarding criteria.
Remaining
CSF 35 Past relevant experience of client in awarding bids and
managing contracts.
Remaining
CSF 36 Past related experience of consultant in sharing in similar
bids and contracts.
Remaining
CSF 37
Past related experience of contractor in sharing in similar
bids and contracts.
Removed since
communalities less
than 0.5
CSF 38 The consultant and the contractor have a mechanism to
manage the tenders and compete.
Remaining
CSF 39 The client interprets all project requirements and location
during the bids preparatory meeting.
Remaining
CSF 40 Documentation the preparation meetings in details. Removed since it have
complex structure
CSF 41
Visiting project location by all consultants and contractors
before filling out the bid form.
Removed since
communalities less
than 0.5
CSF 42
Granting enough time for consultants and contractors to fill
out the bid form.
Removed since
communalities less
than 0.5
CSF 43 Participating of related project parties in financial and
technical evaluation of tenders.
Remaining
CSF 44
Effective contract management included precise
formulation, documentation and enough detailed incentives,
bonds, penalties, …etc.
Remaining
CSF 45 Project profitability for consultant and contractor Removed since it have
complex structure
CSF 46 Economic environment in terms of materials quantity,
quality, and price, local currency value, …etc.
Remaining
CSF 47 Delegation and authority allocation of project workers. Remaining
Naming the Components
Once an interpretable pattern of loadings is done, the components or components should
be named according to their substantive content or core. The components should have
conceptually distinct names and content. Items with higher loadings on a component
should play a more important role in naming the component. Also the common names for
144
components in previous studies were used in naming the components. In this study the
three components were named as the following:
Component 1: “Bidding and contracting management” with items: CSF 38, CSF
39, CSF 43, CSF 44, CSF 46 and CSF 47.
Component 2: “Project Parties' capabilities” with items: CSF 34, CSF 35 and
CSF 36.
Component 3: “Client behavior” with items: CSF 32 and CSF 33.
The proposed naming of the extracted components were discussed with experts and
academics to validate the naming of the principal components. Figure 4.10 below
describes the final results of the components extracted, percent of total explained
variance and eigenvalue of each component.
Figure 4. 10: Final components extracted from factor analysis for CSFs in tendering and
contracting phase
Measures of reliability for each component
Once components have been extracted and rotated, it was necessary to cross checking if
the items in each component formed collectively explain the same measure within target
dimensions (Doloi, 2009). If items truly form the identified component, it is understood
Tendering and contracting phase
Total variance: 61.48%
Component 3:
Client behavior
Eigenvalue: 1.07
Component 2:
Project parties capabilities
Eigenvalue: 1.18
Component 1:
Bidding and contracting management
Eigenvalue: 4.51
145
that they should reasonably correlate with one another, but not the perfect correlation
though. Cronbach's alpha (Cα) test was conducted for each component. The higher value
of Cα denotes the greater internal consistency and vice versa. An alpha of 0.60 or higher
is the minimum acceptable level. Preferably, alpha will be 0.70 or higher (Field, 2009).
According to results which were tabulated in Table 4.26, Cα for component 1 is 0.82; Cα
for component 2 is 0.67; and Cα for component 3 is 0.61. They are considered to be
acceptable.
Table 4. 26: Factor loadings for a three-component model CSFs of planning and designing
phase
Component and factor loading
Fac
tor
load
ing
Eig
enval
ues
Var
iance
%
expla
ined
Cro
nbac
h's
Alp
ha
(Cα
)
Component 1: Bidding and contracting management
CSF 46 Economic environment in terms of
materials quantity, quality, and price,
local currency value, …etc.
0.79
4.51 26.95 0.82
CSF 44 Effective contract management included
precise formulation, documentation and
enough detailed incentives, bonds,
penalties, …etc.
0.76
CSF 47 Delegation and authority allocation of
project workers.
0.65
CSF 43 Participating of related project parties in
financial and technical evaluation of
tenders.
0.63
CSF 39 The client interprets all project
requirements and location during the bids
preparatory meeting.
0.58
CSF 38 The consultant and the contractor have a
mechanism to manage the tenders and
compete.
0.57
Component 2: Project parties capabilities
CSF 35 Past relevant experience of client in
awarding bids and managing contracts. 0.79
1.18 17.40 0.67 CSF 36 Past related experience of consultant in
sharing in similar bids and contracts.
0.66
146
Table 4. 26: Factor loadings for a three-component model CSFs of planning and designing
phase
Component and factor loading
Fac
tor
load
ing
Eig
enval
ues
Var
ian
ce %
exp
lain
ed
Cro
nb
ach
's
Alp
ha
(Cα
)
CSF 34 Consider consultant and contractor past
performance and reputation as awarding
criteria.
0.65
Component 3: Client behavior
CSF 32 The client has a mechanism to manage the
bids.
0.79
1.07 17.13 0.61 CSF 33 Transparent and efficient procurement
criteria depends on applicable laws and
regulations.
0.76
Kaiser-Meyer-Olkin measure of sampling adequacy = 0.86
Bartlett's test of sphericity: x2= 955.14,df=55,p-value =0.00
Total variance explained (%) = 61.48 %
Total reliability Cornbach’s α = 0.85
Six insignificant factor loadings (< 0.5) are blanked
4.4.2.2.2 The extracted components
The next section will interpret and discuss each of the extracted components as follows:
Component 1: Bidding and contracting management
First component named "Bidding and contracting management" explains 26.95% of the
total variance and contains six items. The majority of items had relatively high factor
loadings (≥ 0.57). The six items are as follows:
1. Economic environment in terms of materials quantity, quality, and price, local
currency value, …etc CSF 46, with factor loading=0.79.
2. Effective contract management included precise formulation, documentation and
enough detailed incentives, bonds, penalties, …etc CSF 44, with factor loading =0.76.
3. Delegation and authority allocation of project workers CSF 47, with factor
loading=0.65.
4. Participating of related project parties in financial and technical evaluation of
tenders CSF 43, with factor loading=0.63.
147
5. The client interprets all project requirements and location during the bids
preparatory meeting CSF 39, with factor loading=0.58.
6. The consultant and the contractor have a mechanism to manage the tenders and
compete CSF 38, with factor loading=0.57.
Results from Table 4.26 indicated that CSF “Economic environment in terms of materials
quantity, quality, and price, local currency value, …etc” was the highest loading factor in
this component with factor loading =0.79. This CSF indicated that it is important to
understand and study the economic environment in detailed on this phase because many
things will depend on this like pricing bids and tenders, determining quality levels,
identification of materials types and construction technology, agreement formulization.
Palestine situation like any other developing country suffer from bad economic
conditions and high level of uncertainty. So with clear studying and understanding of
project economic environment the hazard of failure this will be decreased. In line with
this study in Gaza Strip Enshassi et al (2009a) found that the most important factor
affecting project performance was delays due of borders/roads closure leading to
materials shortage. Also in Bangladesh, China, India and Thailand Ahsan and Gunawan
(2010) found that the main reason of cost underrun was devaluation of local currency.
The second high factor loaded CSF in this component was “Effective contract
management included precise formulation, documentation and enough detailed
incentives, bonds, penalties, …etc” with factor loading =0.76. This CSF indicated that in
contracting and tendering phase it is a responsibility of all parties to work together in
order to have enough detailed contract that contain all parties responsibilities, authorities
and rights. In Palestine any misfiled on the contract rises the hazard of variations orders,
rework, disputes and litigations. This result in line with Frimpong et al (2003) study in
Ghana who found that the second most important factor attributing to the cause of delay
and cost overruns in groundwater projects was poor contract management. Also in
Malaysia Abdul-Aziz and Kassim (2011) found that the failure factor which had the most
influential was absence of robust and clear agreement.
148
Component 2: Project parties capabilities
Second component named "Project parties' capabilities" explains 17.40% of the total
variance and contains three items. The majority of items had relatively high factor
loadings (≥ 0.65). The three items are as follows:
1. Past relevant experience of client in awarding bids and managing contracts CSF 35,
with factor loading=0.79.
2. Past related experience of consultant in sharing in similar bids and contracts CSF 36,
with factor loading =0.66.
3. Consider the reputation and the performance in previous projects as one of awarding
criteria CSF 34, with factor loading=0.65.
Results from table 4.26 showed that CSF “Past relevant experience of client in awarding
bids and managing contracts” with factor loading =0.79 was the highest loaded factor of
this component. This CSF indicated that client should know how to evaluate the bids. In
Palestine the most spread wide way to award the bids is lowest bidder with less attention
to other important factors like technical capability. May be due to the limited funds
lowest bid is a solution but it is not always the right one because may be the lowest
bidder have inadequate experience so respondents agreed with that it is very important
for client to have experience in similar bids awarding strategies. Similar results in
Malaysia Sambasivan and Soon (2007) found that the 3rd
cause of delay was awarding
bids to inadequate contractor experience. In contrary in Malaysia Yong and Mustaffa
(2013) ranked Awarding bids to the right designers/ contractors as the 22th
CSF. In
Bangladesh, China, India and Thailand Ahsan and Gunawan (2010) found that contract
evaluation and award was the main cause of delay.
The second high factor loaded CSF in this component was “Past related experience of
consultant in sharing in similar bids and contracts” with factor loading =0.66. This CSF
indicated that consultant should have wide knowledge to compete in order to win. Bid
form considered as a contractor plan for the project. Without availability of past relevant
experience in similar bids contractor may fall in big mistakes and faults in estimation of
cost and time. Also consultant should know his rights and responsibilities and how to
document them on the contract. In Palestine contractors have limited knowledge in this
149
field and this rises many problems like variation orders, delay and cost overrun. Similar
result in Malaysia Sambasivan and Soon (2007) found that the 1st cause of delay was
improper planning during contracting. Also in China Lu et al (2008) ranked a successful
bidding strategy as the most important CSF for indicating a contractor’s or consultant
competitiveness.
Component 3: Client behavior
Third component named "Client behavior" explains 17.13% of the total variance and
contains two items. The majority of items had relatively high factor loadings (≥ 0.76).
The two items are as follows:
1. The client has a mechanism to manage the bids CSF 32, with factor loading =0.79.
2. Transparent and efficient procurement criteria depends on applicable laws and
regulations CSF 33, with factor loading=0.76.
Results from Table 4.26 revealed that CSF “The client has a mechanism to manage the
bids” and CSF " Transparent and efficient procurement criteria depends on applicable
laws and regulations" had high factor loadings. Client is the one who is mainly
responsible to manage the bids preparing, invitation, meetings, awarding and agreements
so he should have the required experience. In Palestine the bidding management is
adversarial in nature as clients and contractors tend to take advantage of one another
during the negotiation process. Clients try to suppress the project cost to an unrealistic
level in order to reap more profit while the contractors in response will bid at an
unrealistic price to get the project. Many projects in Palestine suffer from delay and cost
overrun due to misses in managing the bidders from client and because most of bids
awarded in lowest bid and consultant or contractor reputation rather than technical
capabilities. Recently MPWH give more attention to the technical capabilities in its
construction projects. In Egypt Marzouk and El-Rasas (2014) ranked the factor type of
project bidding and awarding (negotiation, lowest bidder) as the top factor causing delay
according to frequency index.
150
4.4.2.3 CSFs related to implementation phase
In this phase of data analysis process, factor analysis was employed to reduce a large
number of items to a smaller set of underlying factors that summarize the essential
information contained in the items. Using SPSS 22, Principle Component Analysis
(PCA) with Varimax rotation were performed to set up which items could capture the
aspects of same dimension of the 34 CSFs and examine the underlying structure or
structure of interrelationships among the CSFs. In order to perform the factor analysis for
used items, all the appropriate checks and procedures were fulfilled.
4.4.2.3.1 Appropriateness of factor analysis
The data was first assessed for its suitability to the factor analysis application. According
to the following:
Data distribution
The assumption of normality is most important requirement to generalize the results of
factor analysis test beyond the sample collected (Field, 2009; Zaiontz, 2015). The one-
sample Kolmogorov-Smirnov test was used to test that a item of interest is normally
distributed. Table 3.8 showed that the distributions of CSFs which related to
implementation phase are normally distributed. So the results had been satisfied with this
requirement.
Validity of sample size
The validity of factor analysis is dependent on sample size. PCA can be conducted on a
sample that has fewer than 100 respondents, but more than 50 respondents, and the
sample size for this study was 274. On the other hand, the common rule is to suggest that
sample size contains at least 10:15 respondents per item. In other words, sample size
should be at least 10 times the number of items and some even recommend 20 times
(Field, 2009; Zaiontz, 2015). Fortunately, for CSFs of implementation phase, the
condition was not verified. With 274 respondents and 12 items CSFs, the ratio of
respondents to items are 8.1: 1, which less than the requirement for the ratio of
respondents to items 10:15. So the accuracy of the factor analysis would depend on the
151
strength of the data itself. The communality of each item should be examined accurately
to measure strength of the data.
Measures of reliability for the whole items
Cronbach's alpha test was performed on the items in the field of CSFs of implementation
phase. The value of Cronbach’s alpha (Cα) could be anywhere in the range of 0 to 1,
where a higher value denotes the greater internal consistency and vice versa. An alpha of
0.60 or higher is the minimum acceptable level. Preferably, alpha will be 0.70 or higher
(Field, 2009). As shown in Table 4.27, the value of calculated Cα for all items in the
CSFs of implementation phase for the final run was 0.90 which considered to be
marvelous.
Kaiser-Meyer-Olkin (KMO) and Bartlett's test
The Kaiser-Meyer-Olkin (KMO) sampling adequacy test and Bartlett's test of Sphericity
were carried out. The results of these tests are reported in Table 4.27. The value of the
KMO measure of sampling adequacy was 0.92 for first run and 0.91 for the final run
(close to 1), and was considered acceptable and marvelous because it exceeds the
minimum requirement of 0.50 (‘superb’ according to Kaiser, 1974; Field, 2009; Zaiontz,
2015). Moreover, the Bartlett test of sphericity was another indication of the strength of
the relationship among items. The Bartlett test of sphericity was 5152.23 for the first run
and 2516.26 for the final run and the associated significance level was 0.00. The
probability value (Sig.) associated with the Bartlett test is less than 0.01, which satisfies
the PCA requirement. This indicated that the correlation matrix was not an identity
matrix and all of the items are correlated (Field, 2009; Zaiontz, 2015). According to the
results of these two tests, the sample data of (CSFs in implementation phase) were
appropriated for factor analysis.
152
Table 4. 27: KMO and Bartlett's Test for CSFs of implementation phase
Factor analysis run description
First run Fifth run (Final
run)
Number of included items 34 20
Kaiser-Meyer-Olkin Measure of
Sampling Adequacy.
0.92 0.91
Bartlett's Test of Sphericity
Approx. Chi-
Square 5152.23 2516.26
Df 561 190
P-value 0.00 0.00
Cronbach's Alpha 0.91 0.90
Validity of Correlation matrix (Correlations between items)
Table 4.28 illustrates the correlation matrix for the 34 CSFs. It is simply a rectangular
array of numbers which gives the correlation coefficients between a single item and every
other item in the investigation (Field, 2009; Zaiontz, 2015). As shown in Table 4.28, the
correlation coefficient between an item and itself is always 1; hence the principal
diagonal of the correlation matrix contains 1s. The correlation coefficients above and
below the principal diagonal are the same. PCA requires that there be some correlations
greater than 0.30 and less than 0.8 between the items included in the analysis. For this set
of items, that many of the correlations in the matrix are strong and greater than 0.30
(Field, 2009; Zaiontz, 2015). Correlations have been satisfied with this requirement so no
items was removed at this step.
153
Table 4. 28: Correlations between items of CSFs of implementation phase
CSF 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
48. 1.0
49. 0.4 1.0
50. 0.3 0.5 1.0
51. 0.3 0.5 0.6 1.0
52. 0.3 0.3 0.5 0.6 1.0
53. 0.2 0.5 0.5 0.6 0.6 1.0
54. 0.4 0.3 0.5 0.4 0.4 0.3 1.0
55. 0.2 0.4 0.3 0.4 0.2 0.4 0.3 1.0
56. 0.3 0.4 0.4 0.4 0.4 0.4 0.4 0.5 1.0
57. 0.1 0.3 0.3 0.4 0.4 0.4 0.2 0.4 0.4 1.0
58. 0.3 0.5 0.5 0.5 0.3 0.4 0.4 0.4 0.4 0.4 1.0
59. 0.3 0.4 0.4 0.4 0.2 0.3 0.3 0.4 0.3 0.2 0.4 1.0
60. 0.2 0.2 0.3 0.3 0.3 0.3 0.3 0.4 0.4 0.2 0.4 0.5 1.0
61. 0.3 0.3 0.3 0.5 0.4 0.4 0.3 0.3 0.4 0.3 0.4 0.5 0.5 1.0
62. 0.3 0.3 0.4 0.4 0.4 0.4 0.3 0.3 0.4 0.3 0.5 0.4 0.5 0.6 1.0
63. 0.4 0.3 0.3 0.4 0.4 0.3 0.3 0.2 0.4 0.3 0.4 0.4 0.5 0.6 0.7 1.0
64. 0.2 0.2 0.3 0.4 0.4 0.3 0.2 0.2 0.2 0.4 0.3 0.3 0.2 0.5 0.4 0.5 1.0
65. 0.3 0.4 0.4 0.5 0.5 0.4 0.5 0.3 0.5 0.4 0.4 0.4 0.4 0.5 0.4 0.5 0.5 1.0
66. 0.2 0.4 0.5 0.5 0.4 0.4 0.4 0.4 0.4 0.4 0.5 0.4 0.4 0.5 0.4 0.4 0.4 0.6 1.0
67. 0.3 0.3 0.5 0.5 0.4 0.5 0.4 0.3 0.4 0.5 0.4 0.3 0.3 0.4 0.4 0.4 0.5 0.6 0.6 1.0
68. 0.3 0.4 0.5 0.5 0.4 0.5 0.4 0.3 0.4 0.4 0.5 0.4 0.3 0.5 0.4 0.4 0.4 0.4 0.5 0.6 1.0
69. 0.4 0.5 0.6 0.6 0.5 0.5 0.4 0.3 0.4 0.4 0.5 0.3 0.4 0.5 0.5 0.4 0.4 0.5 0.5 0.5 0.6 1.0
70. 0.3 0.3 0.4 0.5 0.5 0.4 0.3 0.3 0.3 0.4 0.4 0.3 0.3 0.5 0.4 0.5 0.4 0.4 0.4 0.4 0.5 0.6 1.0
71. 0.3 0.3 0.5 0.5 0.5 0.5 0.3 0.2 0.3 0.4 0.4 0.3 0.3 0.4 0.5 0.4 0.3 0.5 0.5 0.4 0.4 0.5 0.5 1.0
72. 0.2 0.3 0.4 0.5 0.5 0.4 0.4 0.2 0.4 0.4 0.5 0.3 0.4 0.5 0.4 0.4 0.4 0.5 0.5 0.6 0.5 0.5 0.5 0.6 1.0
73. 0.2 0.2 0.3 0.4 0.5 0.4 0.2 0.2 0.2 0.3 0.4 0.3 0.2 0.3 0.3 0.4 0.4 0.4 0.4 0.3 0.4 0.5 0.4 0.4 0.5 1.0
154
Table 4. 28: Correlations between items of CSFs of implementation phase
CSF 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
74. 0.2 0.3 0.5 0.4 0.5 0.4 0.4 0.1 0.3 0.4 0.5 0.3 0.2 0.4 0.3 0.4 0.4 0.4 0.5 0.4 0.6 0.6 0.5 0.4 0.5 0.6 1.0
75. 0.2 0.2 0.2 0.3 0.3 0.2 0.2 0.2 0.2 0.3 0.3 0.2 0.2 0.2 0.2 0.2 0.1 0.2 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.4 0.4 1.0
76. 0.2 0.3 0.4 0.3 0.3 0.3 0.3 0.3 0.3 0.2 0.4 0.3 0.4 0.4 0.4 0.5 0.3 0.3 0.4 0.2 0.3 0.4 0.4 0.3 0.3 0.3 0.4 0.3 1.0
77. 0.2 0.3 0.4 0.4 0.4 0.3 0.3 0.3 0.3 0.3 0.5 0.3 0.4 0.3 0.4 0.5 0.3 0.4 0.4 0.4 0.4 0.5 0.4 0.4 0.5 0.4 0.4 0.3 0.5 1.0
78. 0.2 0.3 0.4 0.6 0.5 0.5 0.3 0.3 0.4 0.4 0.5 0.3 0.4 0.5 0.4 0.4 0.4 0.5 0.5 0.4 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.4 0.4 0.6 1.0
79. 0.3 0.4 0.5 0.5 0.4 0.5 0.4 0.3 0.4 0.3 0.6 0.4 0.5 0.5 0.5 0.4 0.3 0.5 0.5 0.5 0.5 0.5 0.4 0.4 0.6 0.3 0.4 0.3 0.4 0.5 0.6 1.0
80. 0.2 0.2 0.4 0.4 0.4 0.3 0.3 0.3 0.3 0.3 0.4 0.4 0.5 0.5 0.4 0.4 0.4 0.4 0.4 0.4 0.3 0.3 0.4 0.4 0.4 0.3 0.4 0.3 0.4 0.4 0.5 0.6 1.0
81. 0.2 0.3 0.4 0.4 0.5 0.4 0.4 0.3 0.3 0.3 0.5 0.4 0.3 0.4 0.4 0.4 0.3 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.5 0.4 0.4 0.3 0.4 0.4 0.5 0.5 0.5 1.0
155
Communalities (common variance)
Communalities represent the proportion of the variance in the original items that is
accounted for by the factor solution. The factor solution should explain at least half of
each original item's's variance, so the communality value for each item should be 0.50 or
higher (Field, 2009; Zaiontz, 2015). Five iteration of factor analysis were done. On
iteration 4 of factor analysis test, the communality for were less than 0.50. Since they
were less than 0.50, the items CSF 54, CSF 75 and CSF 77 in fourth run they had to be
removed. Other CSFs which were (CSF 51, CSF 52, CSF 53, CSF 58, CSF 59, CSF 68,
CSF 70, CSF 71, CSF 72, CSF 76 and CSF 78) removed in the other steps of factor
analysis. Table 4.29 shows that all of the communalities for all remaining items satisfy
the minimum requirement of being larger than 0.50 and not removed on the following
steps of factor analysis.
Table 4.29: Communalities of CSFs of implementation phase of first and final runs
Item. CSFs First run
communalities
Fifth run
(Final run)
communalities
CSF 48 The client follows project implementation
regularly.
0.59 0.69
CSF 49 Past relevant experience of contractor in
execution similar projects.
0.62 0.64
CSF 50 Appropriate safety practices during project
execution.
0.59 0.64
CSF 51 Updated plan for supervising and managing
project site.
0.64 Removed
CSF 52 Preparing and implementing environmental
plans included project waste management
works.
0.57 Removed
CSF 53 Commitment of team members on project
plans and objectives.
0.58 Removed
CSF 54 Clear and effective decision making
mechanism.
0.51 Removed
CSF 55 Project manager commitment to meet cost
quality and time of project.
0.74 0.64
CSF 56 Adequacy and effective management of
project financial and material resources.
0.52 0.60
CSF 57 Training the human resources in the skills
demanded by the project.
0.68 0.69
156
Table 4.29: Communalities of CSFs of implementation phase of first and final runs
Item. CSFs First run
communalities
Fifth run
(Final run)
communalities
CSF 58 Leadership, monitoring, coordinating and
organizing manager skills of project
manager.
0.54 Removed
CSF 59 Permanent presence of project manager in
project site.
0.63 Removed
CSF 60 Availability of enough staff in project site
according to works requirements.
0.67 0.66
CSF 61 Top management support for project
workers.
0.65 0.65
CSF 62 Collaborative team work environment.
0.63 0.69
CSF 63 Mutual trust and understanding between
project participants.
0.72 0.78
CSF 64 Social relationships and coordination
between project participants.
0.66 0.69
CSF 65 Annual organized meetings related to
project activities for all participants.
0.63 0.62
CSF 66 Timely and effective conflict resolution.
0.58 0.63
CSF 67 Effective project control , such as
monitoring, updating plans and feedback.
0.65 0.59
CSF 68 Control and monitoring subcontractors
works.
0.60 Removed
CSF 69 Annual measuring of KPIs.
0.65 0.64
CSF 70 Effective well established information and
communication routines.
0.55 Removed
CSF 71 The project is part of a well-documented or
understood strategy
0.57 Removed
CSF 72 Effective knowledge processing and
management systems.
0.65 Removed
CSF 73 Natural climates like winds, rains and high
temperature.
0.67 0.59
CSF 74 Consultant and contractor commitment to
continuous improvement.
0.67 0.72
CSF 75 Client changes in plans and goals during
execution.
0.51 Removed
CSF 76 Client approvals and Payment method.
0.52 Removed
CSF 77 Availability and execution of material
handling plans.
0.51 Removed
157
Table 4.29: Communalities of CSFs of implementation phase of first and final runs
Item. CSFs First run
communalities
Fifth run
(Final run)
communalities
CSF 78 Using applicable construction methods.
0.61 Removed
CSF 79 Continuous revision of project shop
drawings and approve them fast.
0.66 0.67
CSF 80 Saving as built drawings of the project.
0.63 0.69
CSF 81 Consultant and contractors involvement in
project operating and maintenance plan after
project execution.
0.52 0.57
Total Variance Explained
Using the output from iteration 5, there were five eigenvalues greater than 1. The
eigenvalue criterion stated that each component explained at least one item's's worth of
the variability and therefore only components with eigenvalues greater than one should
be retained (Larose, 2006; Field, 2009). The latent root criterion for number of
components to derive would indicate that there were 5 components to be extracted for
these items. Results were tabulated in Table 4.30 The five components solution explained
a sum of the variance with component 1 contributing 40.69%; component 2 contributing
7.27%; component 3 contributing 6.57%, component 4 contributing 5.80% and
component 5 contributing 5.13%. All the remaining components are not significant.
The five components were then rotated via varimax (orthogonal) rotation approach. This
does not change the underlying solution, or the relationships among the items. Rather, it
presents the pattern of loadings in a manner that is easier to interpret components
(components) (Field, 2009; Zaiontz, 2015). The rotated solution revealed that the five
components solution explained a sum of the variance with component 1 contributing
14.15%; component 2 contributing 14.06%; component 3 contributing 13.97%;
component 4 contributing 12.74%; and component 5 contributing 10.53%. These five
components explained 65.45% of total variance for the varimax rotation which is
acceptable since it was more than 50%.
158
Table 4. 30: Total variance Explained of CSFs of implementation phase
Att
rib
ute
Initial Eigenvalues
Extraction Sums of Squared
Loadings
Rotation Sums of Squared
Loadings
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
To
tal
% o
f V
aria
nce
Cu
mu
lati
ve
%
1 8.14 40.69 40.69 8.14 40.69 40.69 2.83 14.15 14.15
2 1.45 7.27 47.96 1.45 7.27 47.96 2.81 14.06 28.22
3 1.31 6.57 54.53 1.31 6.57 54.53 2.79 13.97 42.19
4 1.16 5.80 60.32 1.16 5.80 60.32 2.55 12.74 54.93
5 1.03 5.13 65.45 1.03 5.13 65.45 2.11 10.53 65.45
6 0.77 3.85 69.30
7 0.73 3.63 72.94
8 0.65 3.27 76.21
9 0.60 3.02 79.23
10 0.53 2.63 81.85
11 0.52 2.59 84.44
12 0.49 2.45 86.89
13 0.42 2.11 89.00
14 0.41 2.07 91.07
15 0.39 1.94 93.01
16 0.35 1.75 94.76
17 0.30 1.49 96.24
18 0.28 1.38 97.62
19 0.26 1.30 98.92
20 0.22 1.08 100.00
Scree Plot
The scree plot below in Figure 4.11 is a graph of the eigenvalues against all the
components for the final run of analysis. This graph can also be used to decide on number
of components that can be derived. Although scree plots are very useful, component
selection should not be based on this criterion alone (Field, 2009). The point of interest is
where the curve starts to flatten. It can be seen that the curve begins to flatten between
components 5 and 6. Note also that component 6 has an eigenvalue of less than 1, so only
three components have been retained to be extracted.
159
Figure 4. 11: Scree Plot for CSFs of implementation phase
Rotated Component Matrix
Table 4.31 shows the factor loadings after rotation of 21 items (from the original 34
items) on the five components extracted and rotated. The pattern of factor loadings
should be examined to identify items that have complex structure (complex structure
occurs when one item has high loadings or correlations (0.50 or greater) on more than
one component). If an item have a complex structure, it should be removed from the
analysis (Reinard, 2006; Field, 2009; Zaiontz, 2014). According to that, it was necessary
to remove items CSF 51, CSF 52, CSF 53, CSF 58, CSF 59, CSF 68, CSF 70, CSF 71,
CSF 72, CSF 76 and CSF 78 because all of them have factor loading less than 0.5. As
shown in Table 4.31, for each remaining items factor loading were above 0.50 and all
items had simple structure. The items are listed in the order of size of their factor
loadings.
Naming the Components
Once an interpretable pattern of loadings is done, the components should be named
according to their substantive content or core. The components should have conceptually
distinct names and content. Items with higher loadings on a component should play a
more important role in naming the component. Also the common names for components
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
0 2 4 6 8 10 12 14 16 18 20
Eige
nva
lue
s
Component
160
in previous studies were used in naming the components. In this study the three
components were named as the following:
Component 1: “Contractor and consultant actions and capabilities” with items:
CSF 49, CSF 69 and CSF 74.
Component 2: “Communication and resource management” with items: CSF 55,
CSF 56, CSF 57, CSF 65, CSF 66 and CSF 67.
Component 3: “Site management” with items: CSF 79, CSF 80 and CSF 81.
Component 4: “Coordination” with items: CSF 61, CSF 62, CSF 63 and CSF 64.
Component 5: “Client commitment” with items: CSF 48, CSF 50 and CSF 73.
The proposed naming of the extracted components was discussed with experts and
academics to validate the naming of the principal components. Figure 4.12 Below
describes the final results of the components extracted, percent of total explained
variance and eigenvalue of each component.
Figure 4. 12: Final components extracted from factor analysis for CSFs in phase 4
Measures of reliability for each component
Once components have been extracted and rotated, it was necessary to cross checking if
the items in each component formed collectively explain the same measure within target
dimensions (Doloi, 2009). If items truly form the identified component, it is understood
Implementation phase
Total variance: 65.45%
Component 1
Contractor and consultant actions and capabilities
Eigenvalue: 8.14
Component 2
Communication and resource management
Eigenvalue: 1.45
Component 3
Site management
Eigenvalue: 1.31
Component 4
Coordination
Eigenvalue: 1.16
Component 5
Client commitment
Eigenvalue: 1.03
161
that they should reasonably correlate with one another, but not the perfect correlation
though. Cronbach's alpha (Cα) test was conducted for each component. The higher value
of Cα denotes the greater internal consistency and vice versa. An alpha of 0.60 or higher
is the minimum acceptable level. Preferably, alpha will be 0.70 or higher (Field, 2009;
Weiers, 2011; Garson, 2013). According to results which were tabulated in Table 4.31,
Cα for component 1 is 0.79; Cα for component 2 is 0.83; Cα for component 3 is 0.79; Cα
for component 4 is 0.81; and Cα for component 5 is 0.71. They are considered to be
acceptable.
Table 4. 31: Factor loadings for a five-component model CSFs of implementation phase
Component and factor loading
Fac
tor
load
ing
Eig
enval
ues
Var
iance
%
expla
ined
Cro
nbac
h's
Alp
ha
(Cα
)
Component 1: Contractor and consultant actions and capabilities
CSF 74 Consultant and contractor commitment to
continuous improvement.
0.77
8.14 14.15 0.79 CSF 49 Past relevant experience of contractor in
execution similar projects.
0.72
CSF 69 Annual measuring of KPIs. 0.54
Component 2: Communication and resource management
CSF 57 Training the human resources in the skills
demanded by the project. 0.77
1.45 14.06 0.83
CSF 55 Project manager commitment to meet cost
quality and time of project. 0.64
CSF 67 Effective project control , such as
monitoring, updating plans and feedback. 0.59
CSF 66 Timely and effective conflict resolution. 0.55
CSF 65 Annual organized meetings related to
project activities for all participants. 0.54
CSF 56 Adequacy and effective management of
project financial and material resources. 0.50
Component 3: Site management
CSF 60 Availability of enough staff in project site
according to works requirements.
0.75
1.31 13.97 0.79 CSF 80 Saving as built drawings of the project. 0.68
CSF 79 Continuous revision of project shop
drawings and approve them fast.
0.66
162
Table 4. 31: Factor loadings for a five-component model CSFs of implementation phase
Component and factor loading
Fac
tor
load
ing
Eig
enval
ues
Var
ian
ce %
exp
lain
ed
Cro
nb
ach
's
Alp
ha
(Cα
)
CSF 81 Consultant and contractors involvement in
project operating and maintenance plan
after project execution.
0.59
Component 4: Coordination
CSF 62 Collaborative team work environment. 0.80
1.16 12.74 0.81
CSF 63 Mutual trust and understanding between
project participants.
0.71
CSF 61 Top management support for project
workers.
0.62
CSF 64 Social relationships and coordination
between project participants.
0.54
Component 5: Client commitment
CSF 48 The client follows project implementation
regularly.
0.75
1.03 10.53 0.71 CSF 73 Natural climates like winds, rains and high
temperature.
0.68
CSF 50 Appropriate safety practices during project
execution.
0.52
Kaiser-Meyer-Olkin measure of sampling adequacy = 0.91
Bartlett's test of sphericity: x2= 2516.26,df=190,p-value =0.00
Total variance explained (%) = 65.45 %
Total reliability Cornbach’s α = 0.82
Fourteen insignificant factor loadings (< 0.5) are blanked
4.4.2.3.2 The extracted components
The next section will interpret and discuss each of the extracted components as follows:
Component 1: Contractor and consultant actions and capabilities
First component named "Contractor and consultant actions and capabilities" explains
14.15 % of the total variance and contains three items. The majority of items had
relatively high factor loadings (≥ 0.54). The three items are as follows:
1. Consultant and contractor commitment to continuous improvement CSF 74, with
factor loading=0.77.
2. Past relevant experience of contractor in execution similar projects CSF 49, with
factor loading =0.72.
163
3. Annual measuring of KPIs CSF 69, with factor loading=0.54.
Results from Table 4.31 showed that CSF “Consultant and contractor commitment to
continuous improvement” was the highest loaded factor of this component with factor
loading =0.77. This CSF indicated that continous improvement has a significant
important due to the fast development in technology and in order to keep up with clients
expectations. Globalization put the world in new phase of evolution and to moderate this
phenomenon it is important to improve the capabilities in order to compete successfully
in construction industry. In Palestine contractor and consultant capabilities still behind
the required since ports are closed and few modern equipment's were entered. Also at
human resource level, contractors and consultants suffer from poor training and
instability in workers experience since the materials prohibited to enter for long times
which enforce construction workers turns to other crafts. This result in line with Davies
(2002) in UK who concluded that continuous improvement of project management
processes and practices represents the 5th
and highest phase of project management
maturity in an organization. And also similar to this results in Taiwan Chen and Chen
(2007) stated that the CSF commitment to continuous improvement had a high loadings
and they ranked it as the 12th
CSF in importance.
The next high factor loading in this component was CSF “Past relevant experience of
contractor in execution similar projects” with factor loading=0.72. In implementation
phase the contractor plays the main role so his experience should coincide with his
importance role. Past relevant experience of the contractor may enhance project
performance since non value added activities will be known to him so he have possible
advantage to minimize project time and cost. In Palestine there were some projects which
executed for first time however due to political situation internal contractors will execute
the projects and preferably to choose the experienced ones. In Malaysia Sambasivan and
Soon (2007) found that the 3rd
cause of delay was inadequate contractor experience. Also
in UK Alzahrani and Emsley (2013) concluded that the CSF contractor past relevant
experience account high factor loading and they concluded that it was better to select a
contractor who has the requisite experience from a similar project type.
164
Component 2: Communication and resource management
Second component named " Communication and resource management" explains 14.06
% of the total variance and contains six items. The majority of items had relatively high
factor loadings (≥ 0.50). The six items are as follows:
1. Training the human resources in the skills demanded by the project CSF 57, with
factor loading=0.77.
2. Project manager commitment to meet cost quality and time of project CSF 55, with
factor loading =0.64.
3. Effective project control , such as monitoring, updating plans and feedback CSF 67,
with factor loading=0.59.
4. Timely and effective conflict resolution CSF 66, with factor loading=0.55.
5. Annual organized meetings related to project activities for all participants CSF 65,
with factor loading=0.54.
6. Adequacy and effective management of project financial and material resources CSF
56, with factor loading=0.50.
Results from Table 4.31 found that CSF “Training the human resources in the skills
demanded by the project” was the highest factor loading item of component 2 with factor
loading of 0.77. This CSF indicated that in Palestine training is a basic requirement of
public projects success. Generally in Palestine and especially in Gaza strip ports close for
long time which effect on construction human resources experience and numbers. To
overcome this problem training is important issue however Palestine suffer from the
shortage of good trainers in some fields of construction industry. Different studies results
considering this factor as one of most important CSFs such as in China Lu and Yuan et al
(2010) found out that most workers in the construction industry in China were from rural
areas who have not been trained sufficiently before starting work on construction
projects. Lu and Yuan et al (2010) findings indicated that the training is the 8th
most CSF.
Also in Taiwan Yang et al (2015) grouped the CSFs into four components in which
training was the most high loaded factor in component one of their study.
The next high factor loading CSF was “Project manager commitment to meet cost quality
and time of project” with factor loading=0.64. This CSF indicated that project manager's
165
commitment plays important role in achieving project success. In Palestine project
manager plays a vital rule in public construction project since he is the one who links the
different stakeholders and the one who monitors project implementation. Similar to this
result in Vietnam Nguyen et al (2004) the most CSF effect on construction projects was
the competent project manager and team. Also in Malaysia Omran and Mamat (2011)
concluded that project manager commitment in works was the most important success
factors affecting the cost performances of projects.
Component 3: Site management
Third component named "Site management" explains 13.97 % of the total variance and
contains four items. The majority of items had relatively high factor loadings (≥ 0.59).
The four items are as follows:
1. Availability of enough staff in project site according to works requirements CSF 60,
with factor loading=0.75.
2. Saving as built drawings of the project CSF 80, with factor loading =0.68.
3. Continuous revision for the project shop drawings and approve them fast CSF 79,
with factor loading =0.66.
4. Consultant and contractors involvement in project operating and maintenance plan
after project execution CSF 81, with factor loading=0.59.
Results from Table 4.31 stated that the highest factor loading of the third component was
CSF “Availability of enough staff in project site according to works requirements” with
factor loading= 0.75. This item indicated that the human resources in project site should
be available from different crafts and specialists. The shortage or surplus in human
resources numbers in the site will affect project performance by increasing project time
and cost, decreasing the profitability of project or increase the difficulty of managing and
directing them. In Palestine contractor employed few number in order to decrease project
costs and this affects projects quality. Also most contractors did not hire a safety
specialists for example. In line with this result in Nigeria Ihuah et al (2014) indicated that
adequate resources for project are identified as common in four of the frameworks and
ranked as 4th
in the set of the critical success factors for project success. Not far results in
Taiwan Yang et al (2015) found that the relationship is stronger for projects with fewer
166
groups members than it was for those with more groups members which affect quality
and stability and project performance.
The next high factor loading CSF was “Saving as built drawings of the project” with
factor loading=0.68. This CSF indicated was added by experts and it is cleared that it is
important in Palestine. May be due to the extensive amount of variation orders which
happens in Palestinian projects as built drawings should be important CSF. As built
drawings facilitate monitoring, save contractor rights, and important to maintenance
phase.
Component 4: Coordination
Fourth component named " Coordination" explains 12.74% of the total variance and
contains four items. The majority of items had relatively high factor loadings (≥ 0.54).
The four items are as follows:
1. Collaborative team work environment CSF 62, with factor loading=0.80.
2. Mutual trust and understanding between project participants CSF 63, with factor
loading =0.71.
3. Top management support for project workers CSF 61, with factor loading =0.62.
4. Social relationships and coordination between project participants CSF 64, with
factor loading=0.54.
Results from Table 4.31 revealed that the highest factor loading of the fourth component
was “Collaborative team work environment” with factor loading= 0.80 followed by CSF
"Mutual trust and understanding between project participants" with factor loading=0.71.
All levels of staff in projects must be engaged in work and its success can be seen as
collective effort which requires cooperation from everyone involved. Generally in
Palestine collaboration and good relations between project team exists. Similar results in
Alhaadir and Panuwatwanich (2011) study in Australia which had used AHP and
indicated that teamwork was ranked as 4th
CSF in importance and effect on successful
safety program on construction projects. Also in line with this result in Finland,
Netherlands and Switzerland Verburg et al (2013) concluded that
communication/collaboration within the team: i.e., clear communication rules, openness,
167
and trust was the most important condition that needs to be fulfilled for successful project
execution.
Component 5: Client commitment
Fifth component named "client commitment" explains 10.53% of the total variance and
contains three items. The majority of items had relatively high factor loadings (≥ 0.52).
The three items are as follows:
1. The client follows project implementation regularly CSF 48, with factor
loading=0.75.
2. Natural climates like winds, rains and high temperature CSF 73, with factor loading
=0.68.
3. Appropriate safety practices during project execution CSF 50, with factor loading
=0.52.
Results from Table 4.31 showed that the highest factor loading of the fifth component
was CSF “The client follows project implementation regularly” CSF 48 with factor
loading= 0.75. According to that it is very important for client to follow implementation
phase in order to guarantee that project is executed within the required goals. In Palestine
public construction projects clients engineers have good experience in construction
industry such as MPWH, MOLG, UNRWA and UNDP and they supervised their projects
periodically.. In China Chan et al (2004b) considered this factor as CSF without ranking
the factors. In Nigeria Ihuah et al (2014) ranked this factor as the 3rd
critical project
management success factors for sustainable social housing.
The next high factor loading CSF was “Natural climates like winds, rains and high
temperature”. This attribute indicated that it is important to take natural climates on
consider during planning and execution phases. Forecasting project time and schedule
preparing affected directly with this factor. Also natural climates have an important effect
on construction works like concrete works and streets paving. In Palestine seasons
weather mostly expected but in recent years temperature degrees rises and rain quantity
increased which affect the projects implementation phase and. But generally, CSF has
moderate affect in Palestine. In Ghana Frimpong et al (2003) ranked unexpected
168
geological conditions as the 12th
CSF which causes delays and cost overrun on
construction industry. also in Malaysia Yong and Mustaffa (2013) considered weather
conditions as critical factors with moderate effect and ranked it as 44th
important CSF.
4.4.2.4 Summary of factor analysis for CSFs
Factor analysis were used in order to reduce the number of factors and group the related
CSFs in components. The number of used CSFs in the questionnaire were 81 divided
into four phases. After using factor analysis 29 CSF removed and 52 CSF remained. Also
each of phases 1, 2 and 3 divided into three components except phase 4 divided into five
components. Table 4.32 summarized the results of factor analysis.
Table 4. 32: Factor analysis summary of CSFs
Phase Components No. of CSFs in
each component
CSFs No.
before factor
analysis
CSFs no.
after factor
analysis
No. of
removed
CSFs
Conceptualizing and
preparation phase
Component1 4
12 8 4 Component 2 2
Component 3 2
Planning and designing
phase
Component1 7
19 13 6 Component 2 4
Component 3 2
Tendering and contracting
phase
Component1 6
16 11 5 Component 2 3
Component 3 2
Implementation phase
Component1 3
34 20 14
Component 2 6
Component 3 4
Component 4 4
Component 5 3
Sum 14 52 81 52 29
169
4.4.3 Ranking of CSFs which affect public construction projects
A list of the 81 CSFs was adopted from literature and pilot study. These CSFs were
subjected to the views of respondents. In the previous section factor analysis was used
and in this section another analysis will be used like mean value, RII, SD, test value, P-
value, and ranks of each CSF. Analysis of this section considered to be the answer of the
second question of this study which was Question 2: What is the ranking of CSFs
according to their degree of importance?.
RII was calculated to weight each CSFs (from CSF 1 to CSF 81) according to the
numerical scores obtained from the questionnaire responses and results have been ranked
from the highest degree (The most important CSF) to the least degree (The most
vulnerable CSF). Table (A 7) in Appendix VI shows RIIs and ranks of CSFs,
respectively. The numbers in the “rank” column represent the sequential ranking. It worth
mentioning that ranking of CSFs was based on the highest mean, RII, and the lowest SD.
If some items have similar means as in the case of (CSF 9 and CSF 10) ranking will be
depended on the higher RII. More precisely, although CSF 9 and CSF 10 have the same
mean, but CSF 9 was ranked higher than CSF 10 because it has higher RII. Also if some
items have similar means and RII as in the case of (CSF 15 and CSF 19) ranking will be
depended on the lowest SD. More precisely, although CSF 15 and CSF 19 have the same
mean and RII, but CSF 15 was ranked higher than CSF 19 because it has higher SD.
Items were categorized with ratings from 92.55% to 75.51% (Figures 4.12 – Figure 4.16
show the RII for CSFs in the different phase.
170
The mean of the CSF “Project feasibility and priority for the society” equals 4.63
(92.55%), Test-value = 45.65, and P-value=0.000 which is smaller than the level of
significance 0.05. The sign of the test is positive, so the mean of this factor is
significantly greater than the hypothesized value 3. It can be concluded that the
respondents agreed to that this CSF is very important and in the same time the most
important factor that affect Palestinian public construction projects. The main importance
of feasibility study in Palestine is that donors used it to decide the amount of fund. Since
most Palestinian public projects are funded from donors so it is recommended to give
enough time and consult experts when making feasibility study without neglecting to
share the community. This study result is not the same as the majority of previous studies
since they were not considered this CSF as the most important one. In South Korea Son
and Kim (2014) concluded that the cost and schedule performance of green building
projects was highly dependent on the quality of definition in the pre-project planning
phase.
Results also indicated that the mean of the CSF “Coordinating with related formal
parties such as (municipalities, electricity companies, ministries,… etc.)” equals 4.57
(91.43%), Test-value = 42.64, and P-value=0.000 which is smaller than the level of
significance 0.05. The sign of the test is positive, so the mean of this factor is
significantly greater than the hypothesized value 3. It can be concluded that the
respondents agreed to that this CSF is very important and in the same time the second
most important factor that affect Palestinian public construction projects. This factor was
not detailed like here in previous studies. The researcher in piloting study detailed it
based on expert A, expert C and expert F suggestion. Experts said projects faced many
difficulties on this region specially since permits take long time and many conflicts
appear with municipalities like land property. In this study respondents agree with
experts since this CSF is ranked as the 2nd
important CSF.
The mean of the CSF “Documentation the preparation meetings in details” equals 4.53
(90.62%), Test-value = 36.32, and P-value=0.000 which is smaller than the level of
significance 0.05. The sign of the test is positive, so the mean of this factor is
171
significantly greater than the hypothesized value 3. Results revealed that the respondents
agreed to that this CSF is very important and in the same time the third most important
factor that affect Palestinian public construction projects. This factor was not found like
here in previous studies. The researcher in piloting study added it based on expert A,
expert B suggestion. Experts said projects faced many difficulties due to poor
documentation on construction projects in Palestine and as found here also respondents
agree with them since it is ranked as the 3rd
important CSF.
The mean of the CSF “Project manager commitment to meet cost quality and time of
project” equals 4.46 (89.26%), Test-value = 36.32, and P-value=0.000 which is smaller
than the level of significance 0.05. The sign of the test is positive, so the mean of this
factor is significantly greater than the hypothesized value 3. According to that results
indicated that respondents agreed to that this CSF is very important and in the same time
the fourth most important factor that affect Palestinian public construction projects. In
contract to this study in China Chan et al (2004b) considered this factor as CSF without
ranking the factors. Similar indication in Australia Orangi et al (2011) study who ranked
the lack of communication between client and project team as the 3rd
cause of projects
delay. Also in line with this result in Nigeria Ihuah et al (2014) ranked this factor as the
3rd
critical project management success factors for sustainable social housing.
The mean of the CSF “The client follows project implementation regularly” equals 4.46
(89.26%), Test-value = 39.02, and P-value=0.000 which is smaller than the level of
significance 0.05. The sign of the test is positive, so the mean of this factor is
significantly greater than the hypothesized value 3. That means majority of respondents
agreed to that this CSF is very important and in the same time the fifth most important
factor that affect Palestinian public construction projects. In Palestine project managers is
new phenomenon. The need for finding committed project manager rises from the
complex environment and multi stakeholders of the public projects in Palestine. Not far
study in Vietnam Nguyen et al (2004) concluded that competent project manager and
team is the most important CSF. Also in Nigeria Ihuah et al (2014) consider the project
manager performance as the most important CSF affected public construction projects.
Also Hong Kong, Australia, Singapore, China and Greece Zou et al (2014) indicated that
172
the most essential successful factor for effective relationship management in PPP was
commitment and participation of senior executives.
At phases level the mean of the tendering and contracting phase “project tendering and
contracting phase” equals 4.28 (85.53%), Test-value = 45.43, and P-value=0.000 which
is smaller than the level of significance 0.05. The sign of the test is positive, so the mean
of this component is significantly greater than the hypothesized value 3. The respondents
agreed to that tendering and contracting phase is the most important phase that affects
Palestinian public construction projects. Tendering and contracting phase divided
consists of 17 CSFs. In China Lu et al (2008) used factor analysis and he classified 35
CSFs into 8 clusters bidding is one of them and it ranked as 6th factor loading cluster. On
South Africa Park (2009) ranked the clarity of contract as the most important CSF affect
the construction projects. Another study in china by Chan et al (2010) grouped 18 CSF
into 5 groups and ranked transparent and efficient procurement process group as the 3rd
high loading component. In this study this phase was ranked as most important phase
may be the basic reasons are that in this phase most agreements will be formulated,
project parties will be determined and the relations, authorities, rights and responsibilities
between project parties will be determined and begun in this phase. Any fault in pricing
bids, choosing the appropriate contractor, writes all needed provisions will effect on
project implementation and results. So it is recommended on this phase for all parties to
work together to guarantee the project success.
173
4.5 KPIs and CSFs relationship
This part aims to accomplish the third objective of this study by evaluating the
relationship between KPIs and CSFs in the public construction projects. For that,
different analysis processes and tests were held in order to formulate the basic
conclusions related to the third objective of this study. Hypothesis testing will be
conducted to answer Question 3: Are there a significant relationship between KPIs and
the degree of importance of CSFs on Palestine?.
Hypothesis 1 "H0": Null hypothesis: There is no significant statistical relationship at
level (α>= 0.05) in respondents evaluations for CSFs affected public construction
projects and the degree of importance of KPIs in Palestine.
Hypothesis 1 "H1": Alternative hypothesis: There is significant statistical relationship at
level (α>= 0.05) in respondents evaluations for CSFs affected public construction
projects and the degree of importance of KPIs in Palestine.
Table 4.33 showed that the p-value (Sig.) of correlation coefficient between CSFs and the
degree of importance of KPIs in Palestine less than 0.05, so the correlation coefficient is
statistically significant at 0.05. As a result the null hypothesis is rejected and the
alternative hypothesis is accepted. That means there exists a significant relationship
between CSFs and the degree of importance of KPIs in Palestine. Many researches in
developing countries (Sambasivan and Soon, 2007; Chen and Chen , 2007; Lu et al,
2008; Cho et al, 2009; Enshassi et al, 2009a; Omran and Mamat , 2011; Chou et al ,
2013; Mir and Pinnington, 2014; Son and Kim, 2014; Shehu et al, 2014; Alias et al, 2014
and Yang et al, 2015) and developed countries (Andersen et al, 2006; Ahsan and
Gunawan, 2010; Orangi et al, 2011; Hwang et al, 2013 and Zavadskas et al, 2014) found
a relationship between The CSFs and KPIs. Also in this study the positive relationship
between CSFs and KPIs was found and this enhance the project parties to consider CSFs
in order to guarantee better project performance.
174
Hypothesis 2 "H0": Null hypothesis: There is no significant statistical relationship at
level (α>= 0.05) in respondents evaluations for CSFs affected public construction
projects and the degree of importance of KPIs in Gaza Strip.
Hypothesis 2 "H1": Alternative hypothesis: There is significant statistical relationship at
level (α>= 0.05) in respondents evaluations for CSFs affected public construction
projects and the degree of importance of KPIs in Gaza Strip.
Table 4.33 showed that the p-value (Sig.) of correlation coefficient between CSFs and the
degree of importance of KPIs in Gaza Strip less than 0.05, so the correlation coefficient is
statistically significant at 0.05. As a result the null hypothesis is rejected and the
alternative hypothesis is accepted. That means there exists a significant relationship
between CSFs and the degree of importance of KPIs in Gaza Strip.
Hypothesis 3 "H0": Null hypothesis: There is no significant statistical relationship at
level (α>= 0.05) in respondents evaluations for CSFs affected public construction
projects and the degree of importance of KPIs in West Bank.
Hypothesis 3 "H1": alternative hypothesis: There is significant statistical relationship at
level (α>= 0.05) in respondents evaluations for CSFs affected public construction
projects and the degree of importance of KPIs in West Bank.
Table 4.33showed that the p-value (Sig.) of correlation coefficient between CSFs and the
degree of importance of KPIs in West Bank less than 0.05, so the correlation coefficient
is statistically significant at 0.05. As a result the null hypothesis is rejected and the
alternative hypothesis is accepted. That means there exists a significant relationship
between CSFs and the degree of importance of KPIs in West Bank.
175
Table 4. 33: Correlation coefficient between CSFs and the degree of importance of KPIs
Item
Gaza Strip West Bank Palestine
Pearson
Correlation
Coefficient
P-
Value
(Sig.)
Pearson
Correlation
Coefficient
P-
Value
(Sig.)
Pearson
Correlation
Coefficient
P-
Value
(Sig.)
Relationship between CSFs
related to conceptualizing and
preparation phase and the
degree of importance of KPIs
0.67 0.00* 0.37 0.00* 0.58 0.00*
Relationship between CSFs
related to planning and
designing phase and the
degree of importance of KPIs
0.63 0.00* 0.38 0.00* 0.59 0.00*
Relationship between CSFs
related to tendering and
contracting phase and the
degree of importance of KPIs
0.56 0.00* 0.23 0.008* 0.51 0.00*
Relationship between factors
related to implementation
phase and the degree of
importance of KPIs
0.58 0.00* 0.21 0.016* 0.50 0.00*
* Correlation is statistically significant at 0.05 levels
4.6 Differences among respondents toward the analysis of CSFs and KPIs on
Palestine
In this part the differences among respondents will be developed toward the analysis of
CSFs and KPIs due to place of resident, organization type, projects size and years of
experience in the construction industry of Palestine. This part will answer the Q4 of the
study. Question 4: Are their differences among respondents toward the analysis of CSFs
and KPIs due to place of resident, organization type, projects size and years of experience
in the public construction industry of Palestine?
Place of resident
Hypothesis 4 "H0": Null hypothesis: There is no differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
place of resident.
176
Hypothesis 4 "H1": Alternative hypothesis: There is differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
place of resident.
Table 4.34 showed that the p-value (Sig.) was smaller than the level of significance =
0.05 for the fields "The degree of importance of KPIs", "Factors related to
conceptualizing and preparation phase", "Factors related to planning and designing
phase", "Factors related to tendering and contracting phase" and "Factors related to
implementation phase", then as a result the null hypothesis is rejected and the alternative
hypothesis is accepted. That means there is significant difference among the respondents
toward these fields due to place of resident. So place of resident has an effect on
respondents' evaluation. The mean value for West Bank respondents is higher than Gaza
Strip respondents, then it was concluded that respondents on West Bank agreed on the
importance of the mentioned KPIs and CSFs much more than respondents on Gaza Strip.
Table 4. 34: Independent Samples T-test of the fields and their p-values for Place of resident
No. Field
Means Test
Value Sig.
Gaza
Strip
West
Bank
1. The degree of importance of KPIs 4.00 4.27 -4.56 0.000*
2. CSFS related to conceptualizing and preparation
phase 4.15 4.33 -3.27 0.001*
3. CSFs related to planning and designing phase 4.07 4.40 -5.89 0.000*
4. CSFs related to tendering and contracting phase 4.15 4.47 -5.92 0.000*
5. CSFs related to implementation phase 4.11 4.46 -6.30 0.000*
* The mean difference is significant a 0.05 level
Organization type
Hypothesis 5 "H0": Null hypothesis: There is no differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
respondents organizations type.
177
Hypothesis 5 "H1": Alternative hypothesis: There is differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
respondents organizations type.
Table 4.35 showed that the p-value (Sig.) was smaller than the level of significance 0.05
for the fields "The degree of importance of KPIs", "Factors related to planning and
designing phase", "Factors related to tendering and contracting phase" and "Factors
related to implementation phase", then as a result the null hypothesis is rejected and the
alternative hypothesis is accepted for those phases. That means there is significant
difference among the respondents toward these fields due to organization type. The mean
for the category "consultation office" respondents have the highest among the other
organizations type, then we concluded that the category "consultation" respondents
agreed on the importance of the mentioned KPIs and CSFs much more than the other
organization type.
For "Factors related to conceptualizing and preparation phase" field the p-value (Sig.)
was greater than the level of significance 0.05. then as a result the null hypothesis is
accepted and the alternative hypothesis is rejected for this phase. That means there was
insignificant difference among the respondents regarding these fields due to organization
type. It was concluded that the respondents' organization type has no effect on this field.
Table 4. 35: ANOVA test of the fields and their p-values for organization type
N
o. Field
Means
Test
Value Sig.
Govermental
organization
Non-
governmental
organization
Consultation
office
1. The degree of importance
of KPIs 4.10 3.88 4.19 9.37
0.000
*
2.
CSFS related to
conceptualizing and
preparation phase
4.20 4.07 4.28 4.49 0.012
*
3. CSFs related to planning
and designing phase 4.21 3.99 4.27 7.92
0.000
*
4. CSFs related to tendering
and contracting phase 4.29 4.12 4.33 4.80
0.009
*
5. CSFs related to
implementation phase 4.22 4.04 4.33 8.42
0.000
* * The mean difference is significant a 0.05 level
178
Projects size
Hypothesis 6 "H0": Null hypothesis: There is no differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
respondents organizations project size.
Hypothesis 6 "H1": Alternative hypothesis: There is differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
respondents organizations project size.
Table 4.36 showed that the p-value (Sig.) is smaller than the level of significance 0.05 for
the fields “Factors related to planning and designing phase", "Factors related to tendering
and contracting phase" and "Factors related to implementation phase”, then as a result the
null hypothesis is rejected and the alternative hypothesis is accepted for those phases.
That means there is significant difference among the respondents toward these fields due
to projects size. So projects size has an effect on this phase. The mean for the category "
Less than 5 M$" respondents have the highest among the other projects size, then we
conclude that the category " Less than 5 M$ " respondents agreed on the importance of
the mentioned KPIs and CSFs much more than the other projects size.
For "The degree of importance of KPIs" and "Factors related to conceptualizing and
preparation phase" fields the p-value (Sig.) was greater than the level of significance
0.05. then as a result the null hypothesis is accepted and the alternative hypothesis is
rejected for this field. That means there is insignificant difference among the respondents
regarding this field due to projects size. It is concluded that the respondents' projects size
has no effect on these fields.
179
Table 4. 36: ANOVA test of the fields and their p-values for projects size
No. Field
Means
Test
Value Sig. Less
than 5
M$
From 5 -
10 M$
From 11
- 20 M$
More
than 20
M$
1. The degree of importance
of KPIs 4.16 4.11 4.01 4.09 0.95 0.419
2.
CSFS related to
conceptualizing and
preparation phase
4.28 4.22 4.06 4.22 2.08 0.104
3. CSFs related to planning
and designing phase 4.28 4.21 3.97 4.20 3.99 0.008*
4. CSFs related to tendering
and contracting phase 4.35 4.32 4.10 4.25 3.09 0.028*
5. CSFs related to
implementation phase 4.34 4.28 4.07 4.21 3.44 0.017*
* The mean difference is significant a 0.05 level
Years of experience in the construction industry
Hypothesis 7 "H0": Null hypothesis: There is no differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
respondents years of experience in construction industry.
Hypothesis 7 "H1": Alternative hypothesis: There is differences at level (α>= 0.05) in
respondents evaluations for CSFs and KPIs toward the analysis of CSFs and KPIs due to
respondents years of experience in construction industry.
Table 4.37 showed that the p-value (Sig.) was greater than the level of significance 0.05
for the field “Factors related to implementation phase”, then as a result the null
hypothesis is rejected and the alternative hypothesis is accepted for those fields. That
means there is insignificant difference among the respondents toward this field due to
years of experience in the construction industry. We conclude that the years of experience
in the construction industry e has no effect on this field.
For the other fields, the p-value (Sig.) was smaller than the level of significance 0.05,
then as a result the null hypothesis is accepted and the alternative hypothesis is rejected
for those fields. That means there is significant difference among the respondents toward
180
these fields due to years of experience in the construction industry. So years of
experience in the construction industry has an effect on the other fields. The mean for the
category " From 16 -20 years " respondents have the highest among the other years of
experience in the construction industry, then it was concluded that the category " From 16
-20 years " respondents agreed on the importance of the mentioned KPIs and CSFs much
more than the other years of experience in the construction industry.
Table 4. 37: ANOVA test of the fields and their p-values for years of experience in the
construction industry
No. Field
Means
Test
Value Sig. From 5
-10
years
From 11
-15
years
From 16
-20
years
More
than 20
years
1. The degree of importance
of KPIs 4.12 4.03 4.30 3.93 3.02 0.030*
2.
CSFS related to
conceptualizing and
preparation phase
4.24 4.10 4.39 4.08 3.25 0.022*
3. CSFs related to planning
and designing phase 4.23 4.02 4.37 4.10 3.87 0.010*
4. CSFs related to tendering
and contracting phase 4.30 4.17 4.43 4.10 3.15 0.026*
5. CSFs related to
implementation phase 4.28 4.13 4.38 4.11 2.53 0.058
* The mean difference is significant a 0.05 level
4.7 Summary of results
Results of analysis showed that all the thirteen mentioned KPIs considered to be
important from respondents' viewpoint. Figure 4.7 showed that all KPIs RII above.
71.81%. Also all the 81 CSFs which derived from factor analysis and respondents
evaluation are considered to be important factors that affect the public construction
projects as shown in Figure 4.8 since their RII above 75.51%.
181
Figure 4. 13: The RII of the importance KPIs as evaluated by respondents
Figure 4. 14: The RII of the importance CSFs as evaluated by respondents
0
20
40
60
80
100
0 1 2 3 4 5 6 7 8 9 10 11 12 13
RII
KPIs
0
10
20
30
40
50
60
70
80
90
100
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85
RII
CSFs
182
Chapter 5
Conclusions and
Recommendations
183
5. Chapter 5: Conclusions and recommendations
This chapter summarizes the research aims and results and provides recommendations
and conclusions for the success factors that affecting public construction projects and
their relation to the key performance indicators. Research contribution and suggested
areas of future research were discussed in this chapter. By revising the research
objectives and key findings, an overview will be critically discussed to assess to which
extent the research objectives were met.
In achieving the aim of the research, three main objectives have been outlined and
achieved through the findings of the analyzed collected questionnaires. These objectives
are related with the research questions that were developed to increase one’s knowledge
and familiarity with the subject. The outcomes were found as followings:
Outcomes related to objective one: identification and evaluation of the key
performance indicators (KPIs) of public construction projects.
Key performance indicators used to compare the actual projects results in terms of cost,
time, quality, satisfaction and so on with the planned. Most construction projects in
Palestine and other countries especially developing ones suffer from poor projects
performance such as delay, cost overrun. Intensive literature review was used to specify
project KPIs. Initially 31 KPI were collected and after pilot study KPIs reduced to 13.
In order to minimize KPIs and group them into components factor analysis was used. As
a result the 13 KPIs reduced to 11 KPIs and grouped into three groups namely: 1) project
quality and environmental impact, 2) satisfaction and reputation of project parties and 3)
overall cost and time.
This result indicated that in Palestine quality and environmental impact component was
the highest component accounted variance equal to 24.92%. This component included
quality, environmental impact, safety and sustainability indicators. The second
component which accounted variance equal to 24.75% was satisfaction and reputation of
project parties and it contains KPIs about party's reputation, party's satisfaction, variation
184
orders and disputes and litigations. The third component which consists of KPIs concern
in cost and time was the lowest component accounted variance equal to 13.05%.
In order to rank and evaluate the importance of each KPIs descriptive analysis were used
such as mean, SD and RII. According to that the 13 KPIs was ranked and results revealed
that the top three most important KPIs in Palestine were 1) project conformity to quality
and technical specifications standards, 2) actual project costs comparing with estimations
and 3) actual project execution time comparing with scheduled. And the least important
KPI was number and size of disputes and litigations.
The results showed that the most important KPIs were quality; time and cost which
means that in Palestine construction industry the highest important KPIs are the
traditional basic ones. Generally public construction projects are funded from donors in
Palestine who give high important to quality more than any other consideration. Also the
limited budget of projects from donors gives the KPI cost large importance. In addition
project duration KPIs is very important due to the uncertainty of political conditions in
Palestine like annual wars.
Results also indicated that Palestinian construction projects suffer from cost and time
overrun and the quantity and costs of variation orders are high. On other hand other
indicators like projects quality, satisfaction and ability to cover project expenditures
ranked a good evaluation.
Recommendations related to objective one: It is recommended to measure project
quality, time and cost annually since they are the most important KPIs. Quality materials
should be of a greater interest for project parties in order to improve cost, time, and
quality performance. This can be done by applying quality training and meetings that are
necessary for performing an improvement. Contractors are urged to be more interested in
sequencing of work according to schedule. In addition, contractors should have a cost
engineer in their projects to successfully control costs.
Clients, consultants and contractors should have more realistic plans and estimations of
budget and project duration to improve projects performance. Consultants are urged to
185
facilitate and expedite orders delivered to contractors to obtain better time performance
and to minimize disputes and claims. Also project parties should works together to
improve safety issues and culture.
Outcomes related to objective two: investigating the critical success factors CSFs
affecting the public construction projects
Critical success factors are the factors which have the most effect on project performance.
Intensive literature review was used to specify project CSFs. Initially 125 CSF were
collected and after pilot study CSFs reduced to 81 and they were classified according to
project life cycle into four phases. First phase was conceptualizing and preparation phase
and contained 12 CSFs. Second phase was planning and designing phase and contained
19 CSF. Thired phase was tendering and contracting phase and contained 16 CSF. And
forth phase was implementation phase and contained 34 CSF.
To reduce the number of CSF in each phase and to categorize them into components
factor analysis were used. As a result 52 CSF out of 81 CSF was remaining categorized
into 14 component and 4 phases. CSFs of conceptualizing and preparation phase reduced
to 8 and grouped into three components First component named "Client actions and
capabilities" explains 29.17 % of the total variance and contains four items. Second
component named "Project characteristics" explains 20.50% of the total variance and
contains two items. Third component named "Project feasibility and goals" explains
18.91% of the total variance and contains two items.
CSFs of planning and designing phase reduced to 13 and grouped into three components.
First component named "Planning and designing management" explains 28.72 % of the
total variance and contains seven items. Second component named "Consultant actions
and capabilities" explains 21.11 % of the total variance and contains four items. The third
component named "Client related factors" explains 11.70 % of the total variance and
contains two items.
Also CSFs of tendering and contracting phase reduced by factor analysis to 11 and
grouped into three components. First component named "Bidding and contracting
186
management" explains 26.95% of the total variance and contains six items. Second
component named "Project parties' capabilities" explains 17.40% of the total variance and
contains three items. Third component named "Client behavior" explains 17.13% of the
total variance and contains two items.
Lastly, CSFs of phase 4 reduced by factor analysis to 20 and grouped into five
components. First component named "Contractor and consultant actions and capabilities"
explains 14.15 % of the total variance and contains three items. Second component
named "Communication and resource management" explains 14.06 % of the total
variance and contains six items. Third component named "Site management" explains
13.97 % of the total variance and contains four items. Fourth component named
"Coordination" explains 12.74% of the total variance and contains four items. Fifth
component named "client commitment" explains 10.53% of the total variance and
contains three items.
Results also showed that all 81 CSFs were important since the least RII was above
75.51%. The top five most important CSFs from the respondents view affected
Palestinian project success were 1) project feasibility and priority for the society, 2)
coordinating with related formal parties such as (municipalities, electricity companies,
ministries,… etc.), 3) documentation the preparation meetings in details, 4) project
manager commitment to meet cost quality and time of project and 5) the client follows
project implementation regularly. Also the results indicated that the most important phase
was tendering and contracting phase. Generally the respondents agreed to that tendering
and contracting phase is the most important phase that affects Palestinian public
construction projects.
Recommendations related to objective two: In order to enhance the performance of
public construction projects it is recommended to prepare projects proposals carefully
since donors depend on them basically to fund projects. Also local community and other
project related parties should participate in the feasibility study of the project.
Clients, consultants and contractors should focus in tendering and conceptualizing phase
since it is the most important phase as study results showed. Contract provisions,
documentation and awarding criteria need to be modified in order to guarantee project
187
success. And it is recommended to follow transparent policy for awarding bids rather
than lowest bidder. Visiting project site, document preparation meetings and take enough
time in planning and designing phase is recommended to improve projects success.
Clients play major rule in monitoring projects implementation and they recommended to
follow up projects implementation directly in order to guarantee it is executed according
to their goals and needs.
Also it is recommended to involve consultants in projects several phases. Consultants
should consider all surrounding circumstances while estimating projects cost and time.
Also they should coordinate with projects clients especially in planning and designing
phase to understand his requirements in order to reduce changes and variation orders.
Contractors have a big duty in project success. So they recommended improving their
abilities in tendering management and competing based on criteria other than lowest
bidding. Also they should appointment qualified project managers who have leadership
skills. In addition they recommended improving their abilities continuously and using
applicable methods.
Outcomes related to objective three: evaluate the relationship between KPIs and CSFs
in the public construction projects
In this study the analysis of respondents view points on Gaza Strip and West Bank
showed there was a positive significant relationship between KPIs and CSFs.
Recommendations related to objective three: Since CSFs and KPIs are related to each
other then it is recommended to focus on the CSFs which have mentioned in this study to
guarantee good projects performance.
Research contribution to previous studies
This research aimed to investigate success factors that affecting public construction
projects and their relation to key performance indicators in Palestine. An extensive
review of literature was conducted to achieve this aim. Generally most previous studies
searched on KPIs only or CSFs only but not both. Rare studies searched on KPIs and
CSFs together. In this research both KPIs and CSFs was examined.
188
Most previous studies investigated into CSFs which effect projects success and
categorized them in different clusters without linking with project life cycle. In this
research CSFs was categorized according to project life cycle phases which can help
decision makers to focus their efforts into the mentioned CSFs of each phase rather than
focusing on all CSFs together which will facilitate understanding project needs and
priorities. Also previous studies did not investigate the relation between KPIs and all
CSFs. In this research the relation between KPIs and CSFs was investigated.
Different instruments were conducted by previous studies such as questionnaire, case
studies and brain storming. The outcomes of this research can be used to enhance projects
success by give attention to the mentioned 81 CSFs and 13 KPIs. Most of CSFs were
modified in this study to fit Palestinian situation such as focusing in feasibility and
priority of the projects to the society, and other CSFs were added such as 1) saving as
built drawings of the project, 2) local community acceptance to execute the project in
their location, 3) continuous revision of project shop drawings and approve them fast, 4)
availability and execution of material handling plans, 5) Considering operation and
maintenance requirements into project design, 6) documentation of the preparation
meetings in details and 7) the client should interprets all project requirements and
location during the bids preparatory meeting. Generally the mentioned CSFs and KPIs
can be used in any country with some modifications.
Research value
Palestinian public construction projects faced different challenges such as material
shortage, limited funds and instable political environment. Also many problems faced
public construction projects like delay, cost overrun and big variation orders. This
research can be used practically to help projects decision makers on focusing on the CSFs
which affect project performance and thus to enhance projects ability to face challenges
and problems.
The mentioned KPIs and CSFs were collected from studies conducted in developing and
developed countries and they consider to be the conclusion of different countries
applications and experience in this area. Most CSFs and KPIs were modified and some
CSFs and KPIs were added in this study to fit Palestine situation. However, the used
KPIs and CSFs in this study are not limited to Palestine and can be used into other
189
countries especially developing countries which share Palestine with the similar
challenges and problems in construction projects.
Further Research
Upon completion of the research with the given research objectives, questions and scope,
it is observed that some critical and relevant issues have not been covered by this
research. To facilitate the application of key performance indicators and critical success
factors approach in public construction projects, further researches might be conducted
such as analyzing and introducing methods to measure projects KPIs, using case studies
to evaluate CSFs effect on KPIs. This study can be used to design the case studies by
considering the factors and indicators which mentioned in. Further studies can use other
population such as contractors firms in order to have integrated view of their interests in
this subject.
190
References
Abdul-Aziz, A. and Kassim, P.. (2011). Objectives, success and failure factors of housing public
private partnerships in Malaysia. Habitat international, 35, 150–157.
AbuHamra, L. (2015). An investigation into building information modeling (BIM)
application in architecture, engineering and construction (AEC) industry in Gaza
strip, published M.Sc. Thesis, Islamic university of Gaza, Palestine.
Adnan, H., Bachik, F., Supardi, A. and Marhani, M.. (2011). Success factors of design and build
projects in public universities. Asia Pacific international conference on environment-
behavior studies, Salamis Bay Conti resort hotel, Famagusta, north Cyprus, 7-9 December
2011. Procedia social and behavioral sciences: Malaysia, 35, 170–179.
Ahadzie, D., Proverbs, D., and Olomolaiye, D.. (2008). Critical success criteria for mass house
building projects in developing countries. International Journal of Project Management, 26,
675–687.
Ahadzie, D., Proverbs, D., and Olomolaiye, D.. (2008). Critical success criteria for mass house
building projects in developing countries. International Journal of Project Management, 26,
675–687.
Aksorn, T. and Hadikusumo, B.. (2008). Critical success factors influencing safety program
performance in Thai construction projects. Safety science, 46, 709–727.
Albatsh, N. (2015). AbuHamra, L. (2015). An assessment of delay causes of construction
projects in palestine, published M.Sc. Thesis, An-Najah national university of
Palestine.
Al haadir, S. and Panuwatwanich, K.. (2011). Critical success factors for safety program
implementation among construction companies in Saudi Arabia. The Twelfth East Asia-
Pacific Conference on Structural Engineering and Construction. Procedia Engineering:
Saudi Arabia, 14, 148–155.
Ali, H., Al-Sulaihi, I. and Al-Gahtani, K.. (2013). Indicators for measuring performance of
building construction companies in kingdom of Saudi Arabia. journal of king Saud
university – engineering sciences, 25, 125–134.
Alias, Z., Zawawi, E., Yusof, K. and Nm, A.. (2014). determining critical success factors of
project management practice: a conceptual framework. Association of Malaysian
researchers. AMER international conference on quality of life the Pacific Sutera Hotel,
Sutera Harbour, Kota Kinabalu, Sabah, Malaysia 4-5 January 2014 . Procedia social and
behavioral sciences: Malaysia, 153, 61–69.
191
Al-Tmeemy, S., Abdul-Rahman, H. and Harun, Z.. (2011). Future criteria for success of building
projects in Malaysia. International journal of project management, 29, 337–348.
Alzahrani, J. and Emsley, M.. (2013). The impact of contractors’ attributes on construction
project success: A post construction evaluation. International Journal of Project
Management, 31, 313–322.
Alzahrani, J. and Emsley, M.. (2013). The impact of contractors’ attributes on construction
project success: A post construction evaluation. International Journal of Project
Management, 31, 313–322.
Andersen, E., Birchall, D., Jessen, S. and Money, A.. (2006). Exploring project success. Baltic
journal of management, 1, 2, 127-147.
Atkinson, R.. (1999). Project management: cost, time and quality, two best guesses and a
phenomenon, it's time to accept other success criteria. International journal of project
management, 17, 6, 337–342.
Berssaneti, F. and Carvalho, M.. (2014). Identification of variables that impact project success in
Brazilian companies. International journal of project management, 1, 2, 127–147.
Bourne, M., Neely, A., Platts, K. and Mills, J. (2002). The success and failure of performance
measurement initiatives: perceptions of participating managers. International journal of
operations and management, 22, 11, 1288–1310.
Bourque, L. and Fielder, P. (2003). How to conduct self-administered and mail surveys,
2nd Edition. California: SAGE publications, Inc.
Bryde, D. and Robinson, L.. (2005). Client versus contractor perspectives on project success
criteria. International Journal of Project Management, 23, 622–629.
Chan, A., and Chan, A.. (2002). Key performance indicators for measuring construction success.
Benchmarking: an international journal, 18, 120–128.
Chan, A., Chan, D. Chiang, Y., Tang, B. Chan, E. and Ho, K.. (2004a). Exploring critical success
factors for partnering in construction projects. Journal of construction engineering and
management, 130,2, 188–198.
Chan, A., Lam, P. Chan, D., Cheung, E. and Ke, Y.. (2010). Critical success factors for PPPs in
infrastructure developments: Chinese perspective. Journal of construction engineering and
management, 5, 484–494.
Chan, A., Scott, D. and Chan, A.. (2004b). Factors affecting the success of a construction project.
Benchmarking: an international journal, 130, 153–155.
192
Chan, A., Scott, D. and Lam, E.. (2002). Framework of success criteria for design and build
projects. Benchmarking: an international journal, 18, 120–128.
Chan, I. (2008). Optimizing stress and performance of Hong Kong construction
professionals: a cultural study, published M.Sc. Thesis, City University of Hong
Kong.
Chen, W. and Chen, T.. (2007). Critical success factors for construction partnering in Taiwan.
International Journal of Project Management, 25, 475–484.
Chen, W., Chen, T., Lu, C. and Liu, S.. (2012). Analyzing relationships among success variables
of construction partnering using structural equation modeling: a case study of Taiwan's
construction industry. Journal of civil engineering and management, 18, 6, 783–794.
Cho, K., Hong, T. and Hyun, C.. (2009). Effect of project characteristics on project performance
in construction projects based on structural equation model. Expert Systems with
Applications, 36, 10461–10470.
Chou, J., Irawan, N. and Pham, A.. (2013). Project management knowledge of construction
professionals: cross-country study of effects on project success. Journal of construction
engineering and management, 0733-9364.
Creative Research Systems, 2012 . Creative Research Systems. [Online], Available at:
http://www.surveysystem.com, [Accessed 25 2 2015].
Cserháti, G. and Szabó, L.. (2014). The relationship between success criteria and success factors
in organisational event projects. International Journal of Project Management, 32, 613–624.
Davies, T.. (2002). The ‘‘real’’ success factors on projects. International journal of project
management, 20, 185–190.
Doerr, L., Manev, I. and Rizova, P.. (2004). The meaning of success: network position and the
social construction of project outcomes in an RandD lab. Journal of engineering technology
and management, 21, 51-81.
Doloi, H. (2009). Analysis of pre‐qualification criteria in contractor selection and their
impacts on project success. Construction Management and Economics, 27, 12, 1245-
1263.
Dvir, D. and Lechler, T.. (2004). Plans are nothing, changing plans is everything: the impact of
changes on project success. Research policy, 33, 1-15.
Dvir, D., Lipovetsky, S., Shenhar, A. and Tishler, A.. (1998). In search of project classification: a
non-universal approach to project success factors. Research policy, 27, 915-935.
193
Dvir, D., Raz, T. and Shenhar, A.. (2003). An empirical analysis of the relationship between
project planning and project success. International journal of project management, 21, 89-
95.
Elshakour, H., Al-Sulaihi, I., and Al-Gahtani, K.. (2013). Indicator s for measuring performance
of building construction companies in Kingdom of Saudi Arabia. Journal of King Saud
University – Engineering Sciences, 25, 125–134.
Engineering Association Gaza center, 2015. [Online], Available at: http://www.enggaza.ps/ ,
[Accessed 25 2 2015].
Engineering Association Jerusalem center, 2015. [Online], Available at:
https://www.paleng.org/ , [Accessed 25 2 2015].
Enshassi, A. and Ayyash, A.. (2014). Factors affecting cost contingency in the construction
industry contractors’ perspective. International journal of construction management, 14, 3,
215-239.
Enshassi, A., Al-Najjar, J. and Kumaraswamy, M.. (2009b). Delays and cost overruns in the
construction projects in the Gaza Strip. Journal of financial management of property and
construction, 14, 2, 126–151.
Enshassi, A., Al-Najjar, J. and Kumaraswamy, M.. (2009b). Delays and cost overruns in the
construction projects in the Gaza Strip. Journal of financial management of property and
construction, 14, 2, 126–151.
Enshassi, A., Arain, F. and Tayeh, B.. (2012). Major causes of problems between contractors and
subcontractors in the Gaza Strip. Journal of financial management of property and
construction, 17, 1, 92-112.
Enshassi, A., Choudhry, R. and Alqumboz, M.. (2009c). Quality and safety in the Palestinian
construction industry. Revista ingeniería de construcción, 24, 1, 49–78.
Enshassi, A., Choudhry, R. Mayer, P., and Shoman, Y.. (2008). Safety performance of
subcontractors in the Palestinian construction industry. Journal of construction in
developing countries, 13, 1, 51–62.
Enshassi, A., Mohamed, S. and Abushaban, S.. (2009a). Factors affecting the performance of
construction projects in the Gaza Strip. Journal of civil engineering and management, 15, 3,
269–280.
Enshassi, A., Mohamed, S., Mayer, P., and Abed, K.. (2007). Reflective practice benchmarking
masonry labor productivity. International journal of productivity and performance
management, 56, 4, 358-368.
194
Famakin, I., Aje, I. and Ogunsemi, D.. (2012). Assessment of success factors for joint venture
construction projects in Nigeria. Journal of Financial Management of Property and
Construction, 17, 2, 153–165.
Fellows, R.F. and Liu, A.M.M. (2008). Research methods for construction. 3rd
Edition.
Oxford: Wiley-Blackwell.
Field, A.. (2009). Discovering statistics using SPSS, 3rd Edition. London: SAGE
Publications Ltd.
Fink, L.. (2014). The effect of customer focus competence on construction project performance.
IPMA. 27th IPMA World Congress . Procedia social and behavioral sciences: Slovenia, 119,
427–436.
Fortune, J. and White, D.. (2006). Framing of project critical success factors by a systems model.
International Journal of Project Management, 24, 53–65.
Frimpong, Y., Oluwoye, J., and Crawford, L.. (2003). Causes of delay and cost overruns in
construction of groundwater projects in a developing countries; Ghana as a case study.
International Journal of Project Management, 21, 321–326.
Garbharran, H., Govender, J. and Msani, T.. (2012). Critical success factors influencing project
success in the construction industry. Acta Structilia, 12, 2, 90-108.
Garson, G. D. (2013). Validity and Reliability (Statistical Associates Blue Book Series
12), Kindle Edition. USA: Statistical Associates Publishers.
Gudienė, N., Banaitis, A., Banaitienė, N. and Lopes, J.. (2013). Development of a conceptual
critical success factors model for construction projects: a case of Lithuania. Vilnius
Gediminas Technical university. 11th
International Conference on Modern Building
Materials, Structures and Techniques MBMST 2013. Procedia Engineering: Lithuania, 57,
392–397.
Gudienė, N., Banaitis, A., Podvezko, V. and Banaitienė, N.. (2014). Identification and evaluation
of the critical success factors for construction projects in Lithuania: AHP approach. Journal
of civil engineering and management, 20, 3, 350-359.
Hartman, F. and Ashrafi, R.. (2004). Development of the SMART project planning framework.
International Journal of Project Management, 22, 499–510.
Henry C. Thode, Jr. (2002). Testing for Normality. New York: Marcel Dekker, Inc.
p. 479. ISBN 0-8247-9613-6.
Hughes, S., Kakulu, I. and Thomas, W.. (2004). Measuring project success in the construction
industry. Engineering management journal, 16, 3, 31-37.
195
Hwang, B., Zhao, X., and Ng, S.. (2013). Identifying the critical factors affecting schedule
performance of public housing projects. Habitat International Journal, 38, 214–221.
Ihuah, P., Tippett, W. and Eaton, D.. (2014). A review of critical project management success
factors (CPMSF) for sustainable social housing in Nigeria. International journal of
sustainable built environment, 3, 62-71.
Ismail, F., Yusuwan, N. and Baharuddin, H.. (2012). Management Factors for Successful IBS
Projects Implementation. Planning and Surveying, University Technology in Malaysia. ASIA
Pacific international conference on environment-behaviour studies Mercure Le Sphinx
Cairo hotel, Giza, Egypt, 31 October 2 November 2012. Procedia Social and Behavioral
Sciences: Malaysia, 68, 99–107.
Israel, G. D. (2013). Determining Sample Size, (PEOD6). Agricultural Education and
Communication Department, Institute of Food and Agricultural Sciences,
University of Florida. Gainesville. Available from: The Savvy survey #8: Pilot
testing and pretesting questionnaires [Accessed on: 28/07/2014].
Iyer, K. and Jha, K.. (2006). Critical factors affecting schedule performance: evidence from
Indian construction projects. Journal of construction engineering and management, 132, 8,
871-881.
Jagboro, O., Babalola, G. and S.O, B.. (2012). Evaluation of the contribution of construction
professionals in budgeting for infrastructure development in Nigeria. International journal
of sustainable construction engineering and technology, 3, 2, 2180-3242.
Kaiser, H. F. (1974). An index of factorial simplicity. Psychometrika, 39, 1, 31-36.
Kerzner, H. Project management: a systems approach to planning, scheduling and
controlling. New York: Wiley; 2001.
Ko, C. and Cheng, M.. (2007). Dynamic prediction of project success using artificial intelligence.
Journal of construction engineering and management, 133, 4, 316-324.
Kothari, C.R. (2004). Research methodology. 2nd
Edition. New Delhi, India: New Age
International Ltd.
Lam, E., Chan, A. and Chan, D.. (2007). Benchmarking the performance of design-build projects
development of project success index. Benchmarking: An International Journal, 14, 5, 624-
638.
Larose, D. T. (2006). Data mining methods and models, 1st Edition. Hoboken, New
Jersey: John Wiley & Sons, Inc.
Lehtiranta, L., Karna, S., Mattijunnonen, J. and Julin, P.. (2012). The role of multi-firm
satisfaction in construction project success. Construction management and economics
journal, 30, 188-198.
196
Li, H., Arditi, D., and Wang, Z.. (2012). Transaction-related issues and construction project
performance. Construction management and economics journal, 30, 151-164.
Ling, F. and Bui, T.. (2010). Factors affecting construction project outcomes: case study of
Vietnam. Journal of professional issues in engineering education and practice, 136, 3, 148-
155.
Locatelli, G., Littau, P., Brookes, N. and Mancini, M.. (2014). Project characteristics enabling the
success of megaprojects: an empirical investigation in the energy sector. IPMA. 27th IPMA
World Congress . Procedia social and behavioral sciences: European United, 119, 625–634.
Love, P., Wang, X., Sing, C. and Tiong, R.. (2013). Determining the probability of project cost
overruns. Journal of construction engineering and management, 139, 321-330.
Lu, W. and Yuan, H.. (2010). Exploring critical success factors for waste management in
construction projects of China. Resources conservation and recycling, 55, 201-208.
Lu, W., Shen, L. and Yam, M.. (2008). Critical success factors for competitiveness of contractors:
China study. Journal of construction engineering and management, 134, 12, 972-982.
Malhotra, N.K. and Birks, D.F. (2006). Marketing research: an applied approach. 2nd
Edition. Harlow: Prentice Hall Financial Times.
Marczyk, G., DeMatteo, D. and Festinger, D.. (2013). Essentials of research design and
methodology, Kindle Edition. Canada: John Wiley & Sons, Inc.
Marzouk, M. and El-Rasas, T.. (2014). Analyzing delay causes in Egyptian construction projects.
Journal of advanced research, 5, 49-55.
Meeampol, S. and Ogunlana, S.. (2006). Factors affecting cost and time performance on highway
construction projects: evidence from Thailand. Journal of financial management of property
and construction, 11, 1, 3-20.
Memon, A., Abdul Rahman, I., Abdul Aziz, A. and Abdullah, N.. (2013). Using Structural
Equation Modeling to Assess Effects of Construction Resource Related Factors on Cost
Overrun. World applied sciences journal, 21, 6-15.
Meng, X.. (2012). The effect of relationship management on project performance in construction.
International Journal of Project Management, 30, 188–198.
Milosevic, D. and Patanakul, P.. (2005). Standardized project management may increase
development projects success. International journal of project management, 23, 181–192.
Mir, F. and Pinnington, A.. (2014). Exploring the value of project management: linking project
management performance and project success. International Journal of Project
Management, 32, 202–217.
197
Molenaar, K., Will, A., Bastias, A., Wardwell, M. and Saller, K.. (2013). Construction project
peer reviews as an early indicator of project success. Journal of management in engineering,
29, 4, 327-333.
Naing, L., Winn, T. and Rusli, B.N. (2006). Practical Issues in Calculating the Sample
Size for Prevalence Studies. Archives of Orofacial Sciences, 1 , 9-14.
Najmi, H. (2011). Project Management for Construction Projects, Unpublished M.Sc.
Thesis, An-Najah National University Palestine.
Ng, C. and Walker, D.. (2008). A study of project management leadership styles across life cycle
stages of an IT project in Hong Kong. International journal of managing projects in
business, 1,3, 404-427.
Ng, S., Tang, Z. and Palaneeswaran, E.. (2009). Factors contributing to the success of equipment-
intensive subcontractors in construction. International journal of project management, 27,
736-744.
Ng, S., Wong, Y. and Wong, J.. (2012). Factors influencing the success of PPP at feasibility
phase: a tripartite comparison study in Hong Kong. Journal of habitat international, 36,
423-432.
Nguyen, L., Ogunlana, O. and Lan, D.. (2004). A study on project success factors in large
construction projects in Vietnam. Journal of engineering construction and architectural
management, 11, 6, 404-413.
Ojiako, U., Johansen, E. and Greenwood, D.. (2008). A qualitative re-construction of project
measurement criteria. Journal of industrial management and data, 108, 3, 405-417.
Omran, A. and Bintimamat, S.. (2008). Factors affecting cost performance in construction
projects within Kelantan state in Malaysia. Journal of academic research in economics, 3, 1,
63-76.
Orangi, A., Palaneeswaran, E., and Wilson, J.. (2011). Exploring delays in Victoria-Based
Australian pipeline projects. The Twelfth East Asia-Pacific Conference on Structural
Engineering and Construction. Procedia Engineering,14, 874–884.
Park, S.. (2009). Whole life performance assessment: critical success factors. Journal of
Construction Engineering, 135, 11, 1146–1161.
[PCBS] Palestinian Central Bureau of Statistics. (2015b). Statistical yearbook of Palestine. 201,
16, Ramallah – Palestine. www.pcbs.gov.ps.
[PCBS] Palestinian Central Bureau of Statistics.(2015a). Labour force survey. Annual report of
2014, April 2015, Ramallah – Palestine, www.pcbs.gov.ps.
198
Poilt, D. and Hungler, B.(1985). Essentials of nursing research; Methods and
applications, J. B. Lippincott company.
Prabhakar, G.. (2008). What is project success: a literature review. International journal of
business and management, 3, 9, 3-10.
Reinard, J. C. (2006). Communication Research Statistics. USA: SAGE Publications, Inc.
Saad, A.. (2011). Factors impacting the project’s life cycle. Unpublished paper, Abu Dhabi,
United Arab Emirates.
Salameh, W. (2012). Towards sustainable construction systems of external walls of
buildings in the West Bank of Palestine, published M.Sc. Thesis, An-Najah national
university of Palestine.
Sambasivan, M. and Soon, W.. (2007). Causes and effects of delays in Malaysian construction
industry. International journal of project management, 25, 517-526.
Sanvido, V., Grobler, F., Parfitt, K., Guvenis, M. and Coyle, M.. (1992). Critical success factors
for construction projects. Journal of construction engineering and management, 118, 1, 94-
111.
Shehata, M. and El-Gohary, K.. (2012). Towards improving construct ion labor productivity and
projects’ performance. Alexandria engineering journal, 50, 321-330.
Shehu, Z., Endut, I., Akintoye, A. and Holt, G.. (2014). Cost overrun in the Malaysia n
construction industry projects: a deeper insight. International journal of project
management, 32, 1471-1480.
Skaates, M., Tikkanen, H.. and Lindblom, J.. (2014). Relationships and project marketing
success. Journal of business and industrial marketing, 17, 389-406.
Son, H. and Changwan, K.. (2014). Early prediction of the performance of green building projects
using pre-project planning variables: data mining approaches. Journal of cleaner
production, xxx, 1-8.
Tabish, S. and Jha, K.. (2011). Important factors for success of public construction projects. 2nd
International Conference on Construction and Project Management. IPEDR: Singapore, 15,
64–68.
Tan, D. and Ghazali, M.. (2011). Critical Success Factors for Malaysian Contractors in
International Construction Projects using Analytical Hierarchy Process. EPPM, 20-21.
Toor, S. and Ogunlana, S.. (2008). Critical COMs of success in large-scale construction projects:
Evidence from Thailand construction industry. International Journal of Project
Management, 26, 420–430.
199
Turner, J. and Müller, R.. (2005). The project manager’s leadership style as a success factor on
projects: a literature review. International Journal of Project Management, 36, 49–61.
[UN] United Nations. (2013). Statistical annex Country classification. World Economic Situation
and Prospects report. www.un.org.
Verburg, R., Sijtsema, P. and Vartiainen, M.. (2013). Getting it done: Critical success factors for
project managers in virtual work settings. International journal of project management, 31, 68-
79.
Wang, X. and Huang, J.. (2006). The relationships between key stakeholders project
performance and project success: Perceptions of Chinese construction supervising engineers.
International journal of project management, 24, 253-260.
Wibowo, A. and Alfen, W.. (2014). Identifying macro-environmental critical success factors and
key areas for improvement to promote public-private partnerships in infrastructure.
Engineering, construction and architectural management, 21, 4, 383-402.
Wikipedia. (2014). Likert scale. https://en.wikipedia.org/wiki/Likert_scale. Accessed in
22/10/2014.
Windapo, A. and Cattell, K.. (2013). The South African construction industry: perceptions of key
challenges facing its performance, development and growth. Journal of construction in
developing countries, 18, 2, 65-79.
Yang, J., Shen, G., Ho, M., Drew, D., and Chan, A.. (2009). Exploring critical success factors for
stakeholder management in construction projects. Journal of civil engineering and
management, 15, 4, 337-348.
Yang, L., Chen, J. and Huang, J.. (2012). Assessing impacts of information technology on project
success through knowledge management practice. Journal of automation in construction,
22, 182-191.
Yang, L., Chen, J. and Wang, X.. (2015). Assessing the effect of requirement definition and
management on performance outcomes: role of interpersonal conflict, product advantage
and project type. International journal of project management, 33, 67-80.
Yang, L., Huang, J. and Wu, K.. (2011). The association among project manager's leadership
style, teamwork and project success. International journal of project management, 29, 258-
267.
Yeung, J., Chan, A. and Chan, D.. (2008). Developing a performance index for relationship-based
construction projects in Australia: Delphi study. Journal of management in engineering, 25,
2, 59-68.
200
Yong, Y. and Mustaffa, N.. (2013). Critical success factors for Malaysian construction projects:
an empirical assessment. Journal of construction management and economics, 31, 9, 959-
978.
Yu, J. and Kwon, H.. (2011). Critical success factors for urban regeneration projects in Korea.
International journal of project management, 29, 889-899.
Zaiontz, C. (2014). Factor analysis. Real statistics using Excel. Available at:
http://www.real-statistics.com/multivariate-statistics/factor-analysis/ (Accessed at
August 18, 2015).
Zavadskas, E., Vilutiene, T., Turskis, Z. and Saparauskas, J.. (2014). Multi-criteria analysis of
Projects' performance in construction. Journal of archives of civil and mechanical
engineering, 14, 114-121.
Zawawi, E., Kamaruzzaman, S., Ithnin, Z. and Zulkarnain, S.. (2011). A conceptual framework
for describing CSF of building maintenance management. University Technology Malaysia.
The 2nd
International Building Control Conference 2011. Procedia Engineering: Malaysia,
20, 110–117.
Zhao, Z., Zuo, J. and Zillante, G.. (2013). Factors influencing the success of BOT power plant
projects in China: a review. Journal of Renewable and Sustainable Energy Reviews, 22,
446-453.
Zikmund, W., Babin, B., Carr, J., and Griffin, M. (2009). Business research methods.8th
Edition. South-Western: Cengage Learning.
Zou, W., Kumaraswamy, M., Chung, J. and Wong, J.. (2014). Identifying the critical success
factors for relationship management in PPP projects. International Journal of Project
Management, 32, 265-274.
Appendix I: Literature reviews summary tables
202
Table A 1: Summary of KPIs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
Background
1.
LI
et a
l (2
012)
Unit
ed S
tate
s of
Am
eric
a
To study the effects of
transaction-related issues
on project performance
const
ruct
ion o
wner
s
Ques
tionnai
re s
urv
ey
structural
equation
modeling
The findings indicated that higher
project performance can be achieved
if transaction costs were kept low;
transaction costs can be kept low if
the uncertainty in the transaction
environment is minimized; minimum
uncertainty in the transaction
environment also enhances contract
or behavior, indirectly contributing to
lower transaction costs; and the party
who can reduce the uncertainty in the
transaction environment is the
construction owner who can take
some or all of the actions.
2.
Sh
ehat
a an
d E
l-G
oh
ary
(20
12)
Eg
yp
t To improve construction
labor productivity and
projects’ performance.
Co
mp
lete
d p
roje
cts
Cas
e st
ud
y
Productivity
equations
There was no standard definition
of productivity and it is important
to define it in projects.
The key for productivity
improvement is not to complete as
many tasks as possible or to
maximize work-load, work output,
or work hours without following
the work plan.
203
Table A 1: Summary of KPIs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
3.
Ber
ssan
eti
and C
arval
ho
(2014)
Bra
zil To analyze the relation
between project
management maturity
and the project success
Pro
ject
man
agem
ent
pro
fess
ional
s
Ques
tionnai
re s
urv
ey
Comparative
analysis,
binary logistic
regressions
and
conceptual
modeling
Results showed that project
management maturity was
significantly related to all vertices
of the iron triangle (time, cost and
technical performance) dimensions
of success. However, it is not
related to the customer
satisfaction.
It suggests focus on efficiency
aspects rather than effectiveness.
KPI on developing countries studies
4.
Sh
enh
ar e
t al
(2001)
Isra
el
To develop a
multidimensional
framework for the
assessment of project
success.
Pro
ject
man
ager
s
Cas
e st
ud
y a
nd c
oll
ecti
on
of
stat
isti
cal
dat
a
Cross-case
comparative
analysis,
descriptive
Statistics and
Pearson
Correlation
coefficients
and factor
analysis
Project and top managers may
develop towards the need to identify
specific success dimensions for each
individual project according to its
goals, technology, business model,
strategy, and markets. In essence,
projects must be part of the strategic
thinking and the assessment of their
success must be aligned with such
thinking.
204
Table A 1: Summary of KPIs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
5.
Chan
et
al
(2002)
Hong K
ong
To establish criteria for
project success for a
design/build project in
construction, first by
identifying relevant
measures of project success
for a construction project to
establish a comprehensive
assessment framework for
project success for
design/build projects.
Journ
als
incl
uded
pro
ject
succ
ess
rese
arch
es
com
pre
hen
sive
revie
w o
f th
e
lite
ratu
re o
ver
10 y
ears
Contextual
analysis and
quantitative
equations
Results showed that the criteria for
project success can be divided into
objective and subjective categories,
with time, cost, quality, and satisfaction
the most significant measures.
6.
Ch
an a
nd C
han
(2004)
Hong K
ong
To develop a set of key
performance indicators
(KPIs) for measuring
construction success Journ
als
incl
uded
pro
ject
succ
ess
rese
arch
es
Co
mpre
hen
siv
e re
vie
w o
f
the
lite
ratu
re
and c
ase
study
Contextual
analysis and
comparison
analysis
Results showed that the KPIs in general
good indicators of the performance of
construction projects. They provided a
useful framework for measuring and
comparing project performance for
future studies.
205
Table A 1: Summary of KPIs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
7.
Ahad
zie
et a
l (2
008)
Ghan
a
To address what
constitutes the
determinants of success
in mass house building
projects (MHBPs)
Ques
tionnai
re s
urv
ey
One-sample t-
test and factor
analysis
Results showed that:
The factor scales identified four
clusters of success criteria,
namely; environmental impact,
quality, customer satisfaction and
cost and time.
With respect to MHBPs in
particular, the findings has
revealed that the expectation of the
customer is one of the critical
issues that property developers
have to contend within a
speculative venture such as in
MHBPs.
The study had also revealed the
emerging importance of
environmental issues.
8.
Ch
o e
t al
(20
09)
Ko
rea
To analyze the overall
relation-ship between
project performance and a
project’s characteristics
Mu
lti-
fam
ily
ho
usi
ng
an
d r
oad
con
stru
ctio
n
pro
ject
s
Cas
e st
udie
s
Factor analysis
and structural-
equation
modeling SEM
Results showed that SEM can identify
the project characteristics that affect the
level of project performance required by
owner in the planning stage, and is thus
expected to help facilitate the decision-
making process in the early planning
stage of a project.
206
Table A 1: Summary of KPIs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
9.
Al-
Tm
eem
y e
t
al
(2011)
Mal
aysi
a Proposing a framework to
categorize project success
for building projects in
Malaysia from the
contractors' perspective. Contr
acto
rs
Ques
tionnai
re
surv
ey
Factor analysis
The results indicated that a
categorization scheme for success
criteria for building projects should
include the categories of project
management success, product success,
along with market success.
10.
Ali
et
al
(2013)
Sau
di
Ara
bia
To explore the most
important indicators for
measuring company
performance as
perceived by large
building contractors
working in Saudi
Arabia. Cla
ssif
ied c
ontr
acto
rs
Ques
tionnai
re s
urv
ey
Relative
importance
index
Results showed that the traditional
financial measures can no more be
the sole determinant of firm success.
Other performance indicators such as
external customer satisfaction, safety,
business efficiency, and effectiveness
of planning are increasingly
becoming important.
207
Table A 1: Summary of KPIs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
11.
Lam
et
al
(2007
)
Hon g
Kong
To develop a project
success index (PSI) to
benchmark the
performance of design-
build projects from a
number of key
performance indicators
(KPIs).
Cli
ents
, co
nsu
ltan
ts a
nd m
ain
contr
acto
rs
Ques
tionnai
re s
urv
ey
Principal
components
analysis
The findings indicated time, cost,
quality and functionality should be
the principal success criteria for
design and build projects.
Benchmarking practice and
performance measures indeed
provide a reasonable indication of
the adequacy of a management
system.
KPI on developed countries studies
12.
Atk
inso
n
(19
99)
UK
to investigate how to
determine project
success
Results showed there were other
criteria in addition to iron triangle
criteria can be used to evaluate
project success like information
system, organization benefits and
stakeholder and community benefits
208
Table A 1: Summary of KPIs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
13.
Hughes
et
al
(2004)
Annap
oli
s To incorporate existing
Construction project
success measurements
into a technique that
accounts for the
subjective, as well as
objective, metrics in
order.
Exper
ience
d
const
ruct
ion p
roje
ct
man
ager
s
Cas
e st
udy a
nd
stru
cture
d i
nte
rvie
ws
Pearson’s
correlation
coefficients
The result was a tool that
accurately reflects the project
manager’s knowledge base and
covers the range of applicable
success metrics related to
construction projects that are not
confined to the classical objective
success metrics (cost, schedule,
performance, And safety).
14.
Bry
de
and
Robin
son (
2005)
UK
To report the findings of an
empirical study that
compares the measures of
success emphasized as
important by client and
contractor organizations. Contr
acto
r an
d
clie
nt
org
aniz
atio
ns
Ques
tionnai
re
surv
ey
(one way)
ANOVA test, chi
square and
Duncan Post Hoc
analysis
Results showed that contractors put
more emphasis on minimizing project
cost and duration, whilst clients put
more emphasis on satisfying the needs
of other stakeholders.
15.
Oji
ako e
t a
l (2
00
8)
Un
ited
Kin
gdo
m
To develop a different
understanding of project
measurement criteria
rather than time, cost
and quality.
Pro
ject
man
agem
ent
pro
fess
ion
als
Sem
i-st
ruct
ure
d
inte
rvie
ws Grounded
theory,
matrices and
coding forms
The results indicated that It is
impossible to generate a universal
checklist of criteria suitable for all
projects. Success (or failure) criteria
will differ from project to project
depending on a number of variables
including size, uniqueness, industry,
complexity and the stakeholders
involved.
209
Table A 1: Summary of KPIs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
16.
Yeu
ng e
t al
(2009)
Aust
rali
a To assess the success of
relationship based
construction projects in
Australia.
Const
ruct
ion
exper
ts
Del
phi
surv
ey
Four rounds of
Delphi
Questionnaires
Framework with eight KPIs which
were client’s satisfaction; cost
performance; quality performance;
time performance; effective
communications; safety performance;
aesthetics (trust and respect); and
innovation and improvement.
Table A 2: Summary of CSFs researches
NO
.
Au
tho
r/s
Co
un
try
Objectives
Ta
rget
gro
up
Met
ho
d
use
d
Analysis
approach Results and findings
CSFs on developing countries studies
210
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
17.
Har
tman
and A
shra
fi
(2004)
Om
an
to develop the simple
measurable analytic
realistic time bounded
"SMART" project
planning framework
based on research into
causes of both project
failure and success
Framework
They recognized that poor project
planning plays a major role as one
of the significant causes of project
failure. They also concluded that
good planning enabled creativity
and supported both team
formulation and effectiveness. It
brought out innovative ideas that
led to cost or time savings.
18.
Ch
an e
t a
l (2
004a)
.
Ho
ng
Ko
ng
To review of the
development of the
partnering concept in
general and identifies
critical success factors for
partnering projects from
the Hong Kong
perspective in particular.
Cli
ents
, co
nsu
ltan
ts, an
d c
ontr
acto
rs
Qu
esti
on
nai
re s
urv
ey
Factor analysis
and multiple
regression
Results showed that five of the success
factors are identified as critical in
explaining the personal perception of
partnering success from the multiple
regression results. ‘‘Establishment and
communication of conflict resolution
strategy,’’ ‘‘Willingness to share
resources among project participants,’’
‘‘Clear definition of responsibilities,’’
‘‘Commitment to win-win attitude,’’
and ‘‘Regular monitoring of partnering
process’’ proved to be essential in
bringing successful outcomes to
partnering projects.
211
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
19.
Wan
g a
nd H
uan
g
(2006)
Chin
a
Investigate to what extent
key project stakeholders
performance correlates
with project success. super
vis
ors
Ques
tionnai
re
surv
ey
Factor analysis
with varimax
rotation,
Independent
samples t –test
and Pearson
correlation
Results showed that the engineers use
relation among the key stakeholders as
the most important criterion of project
success, the stakeholder project
performance positively correlates with
each other and project owners play the
most important role in determining
project success.
20.
Lu a
nd Y
uan
et
al
(2010)
Chin
a
to identify the Critical
Success Factors (CSFs)
for Construction and
demolition waste
management in China. Pra
ctit
ioner
s,
rese
arch
ers
and
gover
nm
ent
off
icia
ls
Ques
tionnai
re
surv
ey a
nd se
mi-
stru
cture
d
inte
rvie
ws
Relative
importance
index
The results indicated that the most
important CSFs in Shenzhen (1)
regulations, (2) waste management
system (3) awareness (4) building
technologies, (5) design changes,
(6)research and development, and (7)
vocational training.
21.
Ad
nan
et
al
(20
11)
Mal
aysi
a
To determine the primary
factors which support the
successful application of
the design and build
method
Cli
ents
an
d c
on
trac
tors
Qu
esti
on
nai
re s
urv
ey
Descriptive
statistics
Results showed that client attributes
for the success of the design and build
projects in public universities are:
developing a clear understanding of
project scope, a clear brief thorough
assessment of the contractor’s
proposal, a clear understanding of
project costs, fulfilling the end-user
requirements, quality finish of the
project, completion within the time
frame as well as the budget allocated.
212
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
22.
Tab
ish a
nd
Jha
(2011)
India
To investigate success
factors of public
construction projects
Cli
ents
and
contr
acto
rs
Ques
tionnai
re
surv
ey
Descriptive
statistics
The results showed that the most
important factor for overall
performance is found to be
‘awareness of and compliance with
rules and regulations’.
23.
Abdul-
Azi
z an
d K
assi
m
(2011)
Mal
aysi
a To examine the objectives
of housing PPP, the
success and failure
factors.
Pro
ject
exec
uti
ve
and
engin
eeri
ng c
onsu
ltan
t
Ques
tionnai
re s
urv
ey,
inte
rvie
ws
and c
ase
studie
s
Descriptive
statistics
Results showed that the public
agencies desired to fulfill an array of
objectives when adopting PPP, the
most important being to enhance
organizational reputation. The success
factor which had the most impact is
action against errant developers. The
failure factor which has the most
influential is absence of robust and
clear agreement.
24.
Yu
an
d K
wo
n (
20
11
)
So
uth
Kore
a
To identify the critical
success factors (CSFs) of
such projects and to
prioritize CSFs in each
project phase so that
project promoters and
managers can
appropriately focus their
efforts.
Pro
ject
man
ager
s an
d
city
pla
nn
er,
Bra
inst
orm
ing
an
d
Del
ph
i p
roce
sses
an
d
qu
esti
onn
aire
su
rvey
Delphi rounds,
paired t-test and
Independent
two-sample t -
test
The top priority CSF of an urban
generation projects in South Korea was
minimization of conflict between
stakeholders.
213
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
25.
Yan
g e
t al
(2011)
Tai
wan
To examine the impact of
teamwork on project
performance to investigate
the relationships among
the project manager's
leadership style,
teamwork, and project
success
Pro
ject
dir
ecto
rs,
Pro
ject
pla
nner
s,
and p
roje
ct
super
inte
nden
ts
Ques
tionnai
re
surv
ey
Cluster analysis,
discriminant
analysis,
independent-
samples t tests
and two-way
ANOVAs
Results showed that the increased in
levels of leadership may enhanced
relationships among team members.
Also teamwork exhibits statistically
significant influence on project
performance.
26.
Chen
et
al
(2012)
Tai
wan
To explore the success
variables (SVs ) in
construction partnering
in Taiwan and the
relationships among these
identified SVs. H
ighly
-exper
ience
d
const
ruct
ion
pro
fess
ional
s
Ques
tionnai
re s
urv
ey Correlation
analysis using
Pearson’s
correlation
coefficient,
factor analysis
and structural
equation
modeling
Research results showed that four SVs
have a significant influence on the
success of construction partnering
which were collaborative team culture,
long-term quality perspective,
consistent objectives and resource
sharing.
214
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
27.
Ism
ail
et a
l (2
012)
Mal
aysi
a
To establish the
management factors
contributing to successful
implementation of IBS
projects from contractor
point of view.
Mai
n c
ontr
acto
r
Ques
tionnai
re s
urv
ey
The mean score
Results showed that the management
factors for successful IBS project
implementation were good working
collaboration, effective communication
channel, team members involved
during the design stage, close
relationship with suppliers, extensive
planning and scheduling, improvement
in planning and scheduling of the
project, risk management, management
of supply chain and logistics, top down
commitment, strategy and business
approach, environmentally friendly
methods, and industry marketing
strategies.
28.
Jag
boro
et
al
(20
12
)
Nig
eria
To investigate the
contribution of
construction professionals
to the budgeting process
for the infrastructure
sector.
Arc
hit
ects
, q
uan
tity
surv
eyo
rs, b
uil
der
s,
tow
n P
lan
ner
s, e
stat
e
surv
eyo
rs, en
gin
eers
Qu
esti
on
nai
re s
urv
ey
Descriptive and
inferential
statistics
Majority of projects budgeted for
execution lack adequate technical
evaluation and cost assessment as a
result of inadequate professional
involvement and this could be adduced
to be a significant problem of success
implementation of public financed
infrastructure projects in Nigeria.
215
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
29.
Yan
g e
t a
l (2
012)
Tai
wan
To assess the impacts of
information technology on
project success through
knowledge management
practice
Exec
uti
ve,
A
rchit
ect-
Engin
eeri
ng a
nd
Gen
eral
Contr
acto
r
Ques
tionnai
re s
urv
ey
Structural
equation
modeling
Results showed that knowledge
management was a key factor
influencing project performance
in terms of schedule, cost,
quality, and safety performance.
knowledge management fully
mediates the effects of IT on
project performance.
30.
Mem
on e
t al
(2013)
Mal
aysi
a
To assess the effects of
the resource related
factors on project cost in
the southern part of
peninsular Malaysia.
Ques
tionnai
re s
urv
ey
Structural
equation
modeling
technique with
partial least
square approach
Results showed that
approximately 47% of cost
overrun was influence with
resource related factors.
Effective financial management
can significantly improve the
project's success and help in
reducing the cost overrun.
31.
Yo
ng
an
d
Mu
staf
fa (
20
13)
Mal
aysi
a
To gain a renewed
understanding of the
emerging trend of CSFs
considered by various
stake-holders in the local
industry.
Dev
elo
per
s,
con
sult
ants
an
d
con
trac
tors
Qu
esti
on
nai
re
surv
ey
Kruskal-Wallis
one-way
analysis of
variance
(ANOVA)
Results showed that there were a
strong consistency among the
perception of project stakeholders in
recognizing the significance of human-
related ‘soft’ factors.
216
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
32.
Win
dap
o a
nd
Cat
tell
(2013)
South
Afr
ica
To investigate of the
challenges assumed to
influence the
performance,
development and growth
of the South African
construction industry Arc
hit
ects
, quan
tity
surv
eyors
,
const
ruct
ion
man
ager
s, p
roje
ct
man
ager
s
Des
crip
tive
surv
ey
and s
emi-
stru
cture
d
inte
rvie
ws
Mean item score
(MIS) method
Results showed that the main
challenge for construction industry in
South Africa is the increasing costs of
building materials.
33.
Ihuah
et
al
(2014)
Nig
eria
To investigate and
establish the critical
project management
success factors for the
sustainable social (public)
housing estates’ delivery/
provision in Nigeria. T
heo
reti
cal
revie
w o
f onli
ne
and
vis
ual
docu
men
t
reso
urc
es,
Docu
men
t m
ethod o
f dat
a
coll
ecti
on Content analysis
tools for
qualitatively
generated data
The study revealed that 22 critical
project management success factors
are essential for the achievement of
sustainable social (public) housing
estates’ delivery/provision in Nigeria.
These relate to: the project managers’
performance; the organization that
owns the development project; the
characteristics of the team members;
and the external project environment.
34.
Wib
ow
o a
nd
Alf
en
(20
14)
Ind
on
esia
To identify macro-
environmental critical
success factors (CSFs)
and key areas for
improvement for public-
private partnerships (PPP)
in infrastructure
development. Hig
h-r
ankin
g o
ffic
ials
An
d p
rofe
ssio
nal
s
Qu
esti
on
nai
re s
urv
ey
Gap
Analysis,
importance-
performance
analysis and
inter-rater
agreement
analysis
The results indicated that the factors
requiring immediate improvements are
all associated with commitments: to
policy continuity, financial
transparency, and corruption
eradication.
217
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
35.
Zou e
t al
(2014)
Hong K
ong,
Aust
rali
a,
Sin
gap
ore
, C
hin
a an
d
Gre
ece To identify the CSFs for
relationship management
in PPP projects.
Sen
ior
man
ager
s or
acad
emic
s
Inte
rvie
ws
and
ques
tionnai
re
surv
ey
Relative
importance
The results indicated that the essential
successful factors for effective
relationship management in PPP
included commitment and participation
of senior executives; defining the
objectives and project strategy; and
integration of the divisions of the
organization.
36.
Dv
ir e
t al
(2003)
Isra
el To examine the
relationship between
project planning efforts
and project success. E
nd-u
ser,
pro
ject
man
ager
, an
d
con
trac
ting o
ffic
e
Str
uct
ure
d q
ues
tionnai
res
and
inte
rvie
ws
Correlation
analysis
Results showed that project
success is insensitive to the level
of implementation of
management processes and
procedures, which are readily
supported by modern
computerized tools and project
management training.
Project success is positively
correlated with the investment in
requirements’ definition and
development of technical
specifications.
218
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
37.
Nguyen
et
al
(2004)
Vie
tnam
To research on project
success factors and their
interrelationships.
Des
igner
, ow
ner
,
consu
ltan
ts,
contr
acto
rs a
nd
subco
ntr
acto
rs
Ques
tionnai
re s
urv
ey
Factor analysis,
mean analysis
and Kaiser
Meyer Olkin test
The results showed that:
most critical factors are human
related.
The most CSF’s are competent
project manager and team,
inadequate funding, commitment
to project and availability of
resources.
38.
Chan
et
al
(2004
b)
Hong
Kong
To develop a conceptual
framework on critical
success factors CSFs maj
or
journ
als
in
the
const
ruct
io
n f
ield
Com
pre
he
nsi
ve
revie
w o
f
the
lite
ratu
re
Contextual
Analysis
The results was a conceptual
framework that includes and regroups
the identified variables affecting
project success.
39.
To
or
and
Og
un
lana
(2008)
Thai
land To explore the inter-
relationships between
various critical success
factors con
stru
ctio
n
pro
fess
ional
s
Qu
esti
onnai
re
surv
ey a
nd
sem
i-
stru
cture
d
inte
rvie
ws Factor analysis
and analysis of
variance
(ANOVA)
The results was a formulation of four
factor groupings which were together
called critical COMs of success and
were labeled as comprehension,
competence, commitment, and
communication, respectively.
40.
Ak
sorn
an
d
Had
iku
sum
o
(20
08)
Th
aila
nd
To assess and prioritize
the degree of influence of
those success factors have
on the safety programs as
perceived by the
respondents.
Med
ium
an
d
larg
e sc
ale
con
stru
ctio
n
pro
ject
s
Qu
esti
on
nai
re
surv
ey a
nd
cas
e
stu
dy
Factor analysis
Results showed that the most
influential factor on the safety
programs was management support.
219
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
41.
Yan
g e
t al
(2009)
Hong K
ong
To identify CSFs
associated with
stakeholder management
in construction projects,
and explore their ranking
and underlying
relationship. Pro
ject
man
ager
s
Ques
tionnai
re
surv
ey
Factor analysis
Results showed that the top three
ranked factors for stakeholder
management were “managing
stakeholders with social
responsibilities”, “assessing the
stakeholders' needs and constraints to
the project”, and “communicating with
stakeholders properly and frequently”.
42.
Par
k (
2009)
South
Kore
a
To identify the CFs
influencing whole life
performance of a
construction project and
evaluate their relative
importance
Cli
ents
, co
ntr
acto
rs
and s
ubco
ntr
acto
rs
Ques
tionnai
re s
urv
ey
Relative
importance
index, weighted
average and
Spearman’s rank
correlation
coefficients
Results showed that the most critical
individual factors were “clarity of
contract” scope; “fixed construction
period”; “precise project budget
estimate”; “material quality”;
“mutual/trusting relationships”;
“leadership/team management”; and
“management of work safety on site”.
43.
Ng
et
al
(20
09
)
Ho
ng
Ko
ng
. To identify and classify
subcontractor CSFs from
the perspective of the
principal stakeholders in
the construction industry
of Hong Kong.
Cli
ents
,
con
sult
ants
,
mai
n c
ontr
acto
rs
and
sub
contr
acto
rs
Qu
esti
on
nai
re
surv
ey
Factor analysis,
arithmetic
means and rank
orders, and ne-
way ANOVA
test
Results showed that the top five CSFs
identified in the study were ‘‘timely
completion”, ‘‘relationship with main
contractor/client/consultant”, , ‘‘profit
” , ‘‘cash flow ”, and ‘‘adoption of
new technologies/methodologies ”.
220
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
44.
Chan
et
al
(2010)
Chin
a
To explore the critical
success factors CSFs
necessary to conduct PPP
projects.
Indust
rial
pra
ctit
ioner
s
Fro
m t
he
publi
c,
pri
vat
e, a
nd o
ther
sect
ors
Ques
tionnai
re s
urv
ey
Factor analysis
Results showed that 18 CSFs are
grouped into five groups: stable
macroeconomic environment; shared
responsibility between public and
private sectors; transparent and
efficient procurement process; stable
political and social environment; and
judicious government control.
45.
Alh
aadir
and
Pan
uw
atw
anic
h
(2011)
Sau
di
Ara
bia
To identify the most
critical factors affecting
the implementation of
safety programs among
the construction
companies.
Exper
ts
Ques
tionnai
re
surv
ey
Pareto principle
and AHP
Results showed that critical success
factors which represent the areas
where companies should focus their
attention and effort to achieve better
safety levels through are effective
implementation of programs.
46.
Zaw
awi
et a
l (2
011)
Mal
aysi
a
To derive a generic
process and procedure in
maintenance management
to be used in various
organization in Malaysia.
Lo
cal
auth
ori
ties
org
aniz
atio
n p
erso
nnel
Cas
e st
ud
y
Conceptual
framework
Results showed that implementing
CSF concept would enhance the
management process and work
planning which would result in a more
economic use of resources, a
corresponding reduction in the total
cost and create successful competitive
performance organization.
47.
Tan
an
d G
haz
ali
(20
11)
Mal
aysi
a
To determine the CSFs
and provide some
guidance for contractors
interested in tapping
international markets
Pro
ject
man
ager
s,
dir
ecto
rs, k
ey
exec
uti
ve
and
engin
eeri
ng
firm
s
In-d
epth
inte
rvie
ws
and
seco
ndar
y d
ata
AHP model
Study evidences showed that project
management related factor is more
important than the other main factors
in terms of ranking and contractor’s
experience is the most critical among
all the sub-factors.
221
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
48.
Fam
akin
et
al
(2012)
Nig
eria
To assess the factors
affecting the performance
of partners in joint
ventures construction
projects in Nigeria.
Par
tner
s an
d c
onsu
ltan
ts
Ques
tionnai
re s
urv
ey Mean Item
Score,
Wilcoxon-
Mann-Whitney
(U-test) test,
Kruskal-Wallis
(H-test) test
And factor
analysis
The study results revealed that
communication, compatibility of
objectives and mutual understanding
among partners ranked as the most
important to the performance of
partners in Joint Venture Projects.
49.
Ng e
t al
(2012)
Hong K
ong
To explore the key
successful ingredients to
be assessed at the initial
stage of PPP projects as
perceived public sector,
private consortium and
general community.
Qu
esti
onnai
re s
urv
ey a
nd
sem
i-st
ruct
ure
d
inte
rvie
ws
Descriptive
analysis, Spear-
man’s rank
correlation
coefficient and
independent
sample t-tests
Results indicated that:
The most critical factor for
evaluating the feasibility of PPP
projects is an acceptable level of
tariff.
Cost effectiveness and financial
attractiveness are the most
important evaluation factors as
ranked by the public sector and
private consortium respectively.
222
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
50.
Gar
bhar
ran e
t al
(2012)
Durb
an,
South
Afr
ica To assess the perceptions
of contractors and project
managers regarding
critical success factors
which lead to project
success in the
construction industry in
Durban, South Africa. pro
ject
man
ager
s an
d
contr
acto
rs
ques
tionnai
re s
urv
ey
Descriptive and
inferential
statistics
The study emerged that there are
no significant differences
between project managers and
contractors regarding the critical
success factors.
Four COMs model has been
advocated as being a useful tool
in assessing project success,
especially in developing
countries.
51.
Zh
ao e
t al
(2013)
Chin
a
To identify factors
influencing the success of
Build–operate–transfer
power plant projects in
China.
Go
ver
nm
ent
off
icia
ls,
con
sult
ants
, D
esig
ner
s
and
Contr
acto
rs
Combination
of literature
survey,
Review of
case study
reports and
Semi-
structured
interviews
Conceptual
framework
The results showed that there are 14
factors at both macro level and micro
level, affecting the success of Chinese
BOT projects.
CSFs on developed countries studies
52.
Bo
urn
e et
al
(20
02)
Un
ited
Kin
gdo
m
To investigate the major
factors that impact the
success and failure of the
implementation of a
performance measurement
system.
Dir
ecto
rs a
nd
man
ager
s
Qu
esti
on
nai
re
surv
ey , c
ase
stu
die
s an
d
inte
rvie
ws
Contextual
Analysis
Four factors appeared to be significant.
These are how the introduction and
launch is handled, who is involved in
the project and project management
and procedure.
223
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
53.
Dvir
and L
echle
r
(2004)
Isra
el
To study empirically the
impact of project
planning, project goal
changes, and project plan
changes on project
success.
`-pro
ject
man
ager
,
tech
nic
ians
or
busi
nes
s m
ember
s
Ques
tionnai
re
surv
ey
Exploratory
correlation
analysis, linear
structural
relationships and
structural
equation model
The results of this study support
the view of plans are not nothing,
“changing plans is everything.”
The quality of project planning
affects the project success.
Plan changes is strongly affected
by goal changes
54.
Turn
er a
nd
Müll
er (
2005)
--
To determine Whether the
competence, including
personality and leadership
style, of the project
manager is a success
factor for projects and
whether its impact is
different on different
types of projects A
rtic
les
Lit
erat
ure
rev
iew
--
Results showed that effective leader-
ship as a critical success factor in the
management of organizations, and has
shown that an appropriate leadership
style can lead to better performance.
55.
Leh
tira
nta
et
al.
(20
12)
Fin
lan
d
To evaluate the extent to
which construction project
participants’ perception of
each other’s performance
reflects on the owner’s
perception of project
success
Pro
ject
ow
ner
s,
pro
ject
co
nsu
ltan
ts,
mai
n c
ontr
acto
rs
and
des
igner
s
Qu
esti
on
nai
re
surv
ey
Pearson’s
correlation
coefficients
The results supported the proposition
that satisfaction within both owner-
related and non-owner-related
relationships is reflected on success.
224
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
56.
Men
g (
2012)
Unit
ed K
ingdom
To explore the specific
characteristics of supply
chain relationships in
construction and to assess
their impact on project
performance Mai
n c
ontr
acto
rs,
man
agem
ent
consu
ltan
ts a
nd
spec
iali
st c
ontr
acto
rs
Ques
tionnai
re s
urv
ey
Percent
frequencies and
Chi-square test
Results showed that:
The deterioration of supply chain
relations hips is a major reason
for the occurrence of poor
performance.
Poor performance can be
effectively reduced by improving
some aspects of the relationship.
57.
Ver
burg
et
al
(2013)
Fin
land,
Net
her
lands
and
Sw
itze
rlan
d To determine conditions
that need to be fulfilled
for successful project
execution within
dispersed project settings.
Pro
ject
man
ager
s
In-d
epth
and
stru
cture
d
inte
rvie
ws
Means-End
Chain (MEC)
method
Results showed that important
conditions for successful project
execution in a dispersed setting
included rules of communication and
its clarity; project management style
and goal-setting; and managers'
competences and trust in a team.
58.
Mo
len
aar
et a
l (2
013)
Un
ited
Sta
tes
of
Am
eric
a To understand whether
project peer reviews could
be an indicator of project
success.
--
Pee
r re
vie
w
Point biserial
coefficient
The results showed that project
peer reviews can help to predict
project success.
The relationship between the
designer and contractor appears
to be very import ant to the
outcome of the project, regardless
of project delivery method.
225
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
59.
Loca
tell
i et
al
(2014)
EU
To empirically relate the
identification of a
characteristic of a
megaproject with whether
or not that megaproject
was
Successful.
Res
earc
her
s
Cas
e st
udie
s,
bra
inst
orm
ing
Fisher exact
test, chi-squared
test
Results showed that the different
typologies can point out the relevance
of the type of technology on the
project performance Stakeholders
might have high influence on time-
related Issues in megaprojects
60.
Fin
k (
2014)
Slo
ven
ia,
Bal
kan
countr
ies,
E
aste
rn
Euro
pea
n c
ountr
ies,
Wes
tern
Euro
pe
and
Nort
hea
ster
n
Euro
pe
and R
uss
ia
To examine how CF
competence influences
construction project
performance measured by
reaching internal and
overall budget, quality
and deadline goals.
Tea
m m
ember
s
Cas
e st
udy
Multiple
regression
model
Results showed positive effects of the
team average CF customer focus on
examined project goals.
61.
Fo
rtune
and
W
hit
e
(20
06)
Un
ited
Kin
gdom
To frame project critical
success factors by systems
model. Pu
bli
cati
on
s,
pro
ject
s
dat
a
Cas
e
stu
dy Comparison
analysis and
Formal System
Model
Results showed that the formal system
model allows the underlying benefits
of critical success factors in planning
phase.
62.
Gu
die
nė
et a
l
(20
13)
Lit
huan
ia
To develop a conceptual
critical success factors
model for construction
projects in Lithuania.
Co
mp
reh
ensi
ve
rev
iew
of
the
lite
ratu
re Decision-
making matrix
and a multiple
criteria analysis
of alternatives
Conceptual model adapted to
Lithuania is developed and grouped
decision-making matrix for the
multiple criteria analysis of critical
success factors of construction projects
is presented.
226
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
63.
Alz
ahra
ni
and E
msl
ey (
2013)
Unit
ed K
ingdom
To study the impact
of contractors’
attributes on project
success from a post
construction
evaluation
perspective.
To identify what
critical success
factors (CSFs) that
greatly impact the
success of project.
Contr
acto
rs
Ques
tionnai
re s
urv
ey
Factor analysis
and logistic
regression
techniques
Results showed that the success of a
project is significantly associated with
seven of the advocated variables. They
are: turnover history, quality policy,
adequacy of labor resources, adequacy
of plant resources, waste disposal, size
of past project completed, and
company image.
64.
Gu
die
nė
et a
l (2
014)
Lit
huan
ia To investigate the critical
success factors affecting
the implementation of
projects in construction
enterprises in Lithuania.
con
stru
ctio
n
pro
fess
ional
s
and
ex
per
ts
Qu
esti
on
nai
re s
urv
ey
AHP approach
The study showed that clear and
realistic project goals and project
planning play the key role in
successful implementation of
construction projects in Lithuania.
They should be supported by the top
project management, clear and
precise goals/objectives of the client,
and, finally, by the client’s ability to
make timely decisions.
227
Table A 2: Summary of CSFs researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
65.
Cse
rhát
i an
d S
zabó
(2014)
Aust
ria,
Cze
ch
Rep
ubli
c,
Ger
man
y,
Hungar
y,
Pola
nd, S
lovak
ia,
Slo
ven
ia a
nd
Sw
itze
rlan
d
To develop and
investigate of the
attributes of the success
criteria and factors of
organizational event
projects analysis of the
relationship between the
criteria and factor areas.
Even
t m
anag
ers
Ques
tionnai
re s
urv
ey
Exploratory
facto r analysis
Results showed that the correlations
suggests that relationship-oriented
success factors, such as
communication, co-operation and
project leadership, play a crucial role
in carrying out successful
organizational event projects.
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
KPIs and CSFs relationship on developing countries studies
66.
Fri
mp
on
g et
al
(20
03)
Gh
ana
To identify and evaluate
the relative importance of
the significant factors
contributing to delay and
cost overruns in Ghana
groundwater construction
projects.
Ow
ner
s, c
on
sult
ants
an
d
con
trac
tors
Qu
esti
on
nai
re s
urv
ey
Relative
Importance
Weight
The results of the study revealed the
main causes of delay and cost overruns
in construction of groundwater projects
included: monthly payment difficulties
from agencies; poor contractor
management; material procurement;
poor technical performances; and
escalation of material prices.
228
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
67.
Mee
ampol
and O
gunla
na
(2006)
Thai
land To give suggestions
regarding how to improve
cost and time performance
on public Sector projects.
Sit
e pro
ject
man
ager
s
Ques
tionnai
re s
urv
ey
Independent
Sample t-test and
Discriminant
analysis
Results suggested that:
The management of construction
resources, budget management,
construction method, and
communication and report should
reduce the chance of cost overrun.
Improvements in construction
method, construction resource
management, human resource
management, supervision and
control, schedule management, and
communication and report, can
reduce project delays.
68.
Iyer
an
d J
ha
( 2
00
6)
Ind
ia
To identify the relative
importance of success and
failure attributes in Indian
construction industry and
to understand the latent
properties of these success
and failure attributes by
studying the critical
success and failure factors.
Co
nst
ruct
ion
in
dust
ry
pro
fess
ion
als
Qu
esti
on
nai
re s
urv
ey
Mean analysis,
multinomial
logistic
regression and
log of odds ratio
The results showed that commitment of
the project participants; owner’s
competence; and conflict among
project participants have been found to
possess the capability to
enhance performance level.
229
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
69.
Sam
bas
ivan
and S
oon (
2007)
Mal
aysi
a To identify the delay
factors and their impact
(effect) on project
completion.
Cli
ents
, co
nsu
l-ta
nts
, an
d c
ontr
acto
rs
Ques
tionnai
re s
urv
ey
Relative
importance
indices and
Correlation
analysis
The results showed that the ten most
important causes for delay in Malaysian
projects are: (1)contractor’s improper
planning, (2)con-tractor’s poor site
management, (3)inadequate contractor
experience, (4)inadequate client’s
finance and payments for completed
work, (5)problems with subcontractors,
(6)shortage in material, (7)labor supply,
(8)equipment availability and failure,
(9)lack of communication between
parties, and (10)mistakes during the
construction stage.
70.
Ch
en a
nd
Chen
(2007)
Tai
wan
To distinguish between
success factors based on
their degrees of importance
in relation to success.
Go
ver
nm
ent
emplo
yee
s,
ow
ner
s, d
esig
ner
s, a
nd
con
trac
tors
Qu
esti
on
nai
re s
urv
ey
Mean analysis,
one-way
ANOVA and
factor analysis.
The results showed that certain
requirements must be met for partnering
to be successful, including a
collaborative team culture, a long-term
quality focus, consistent objectives, and
resource-sharing.
230
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
71.
Mir
and
pin
nin
gto
n (
2014)
Unit
ed A
rab E
mir
ates
To test the relationship
between project
management performance
and project success
Ques
tionnai
re s
urv
ey
Pearson
correlation,
linear regression
and cross-
tabulating
Study demonstrated that project
management performance is
correlated to project success within
United Arab Emirates
organizations.
The project management
performance construct and its
variables had markedly greater
impact on project success
attributes than did project
efficiency which is more limited in
its influence.
72.
Lu
et
al
(20
08)
Ch
ina
To utilize the CSF
approach to
Identify a few manageable
but vital factors
contributing to the
Overall competitiveness of
a contractor Gra
de
1 c
ontr
acto
rs
Qu
esti
on
nai
re s
urv
ey
Ranking analysis
and factor
analysis
Results showed that factor analysis
generates eight clusters from the 35
CSFs identified by the ranking analysis.
These clusters represent supercritical
success factors affecting a contractor’s
competitiveness, namely “project
management", “organization structure",
“resources", “competitive strategy",
“relationship", “bidding", “marketing,”
and “technology".
231
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
73.
Ensh
assi
et
al
(2009
a)
Pal
esti
ne To identify the factors
affecting the performance
of local construction
projects.
Pro
ject
man
ager
s, s
ite
engin
eers
/off
ice
engin
eers
, an
d
org
aniz
atio
ns’
man
ager
s
Ques
tionnai
re s
urv
ey Relative
importance
index method,
project
managers, site
engineers/office
engineers, and
organizations’
managers
The results indicated that the average
delay because of closures leading to
materials shortage was the most
important performance factor, as it
has the first rank among all factors
from the perspectives of owners,
consultants, and contractors.
74.
Om
ran a
nd
Mam
at (
2011)
Mal
aysi
a
To investigate the factors
affecting cost performance
of construction projects in
Kelantan State located in
the east-coast part of
Malaysia. Mai
n c
ontr
acto
r,
sub
contr
acto
r, s
uppli
er,
dev
eloper
Qu
esti
onnai
re s
urv
ey
Relative
importance
index method
The results indicated that the success
factors affecting the cost performances
of projects identified as project manager
competence in works.
Poor project specific attributes and not
existence of cooperate and ignorance
and lack of knowledge in operating,
techniques and decision by project
manager are identified as the most
important failure factors.
232
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
75.
Chou e
t al
(2013)
Tai
wan
, In
dones
ia ,
and
Vie
tnam
To determine the effects
of project management
body of knowledge
techniques/ tools/skills
(PM TTSs) on project
success
Pro
fess
ional
Engin
eers
in t
he
const
ruct
ion
indust
ry
Ques
tionnai
re s
urv
ey
Structural
equation
modeling and
importance
performance
analysis
The findings of the study provided
guidance for practitioners and
educators by clarifying the current
use of PM TTSs in the
construction engineering field.
To optimize PS, project managers
can use the model to perform
numerical studies of critical
indicators/constructs and to
prioritize and allocate the
components of their managerial
strategies.
76.
So
n a
nd
Kim
(2
014)
So
uth
Kore
a
To develop a model to
predict the cost and
schedule performance of
green building projects
based on the level of
definition during the pre-
project planning phase.
Arc
hit
ect,
dev
elo
per
, or
Pro
ject
man
ager
Qu
esti
on
nai
re s
urv
ey
Support vector
machine, back-
propagation
neural network,
decision tree
algorithm and a
logistic
regression
The cost and schedule performance of
green projects was highly dependent on
the quality of definition in the pre-
project planning phase.
233
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
77.
Sheh
u e
t al
(2014)
Mal
aysi
a
To investigate certain
project characteristics
influencing Malaysian
construction project
overruns. Consu
ltan
ts
Ques
tionnai
re s
urv
ey
Descriptive
analysis and
regression
analysis
More than half of Malaysian
construction projects (55%)
experienced cost overruns.
Public sector projects performed
better than private sector projects,
also design and build projects was
associated with reduced cost
overrun, and small and large
projects performed better than
medium and very large projects.
78.
Ali
as e
t al
(2014)
Mal
aysi
a
To identify the extent of
the relationship between
CSFs and project
performance and to assist
the organization in
evaluating the performance
of project management Pro
ject
man
ager
s
Lit
erat
ure
rev
iew
conceptual
framework
The results was a conceptual framework
for determining critical success factors
in project management practices
234
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
79.
Yan
g e
t al
(2015)
Tai
wan
To identify the roles of
interpersonal conflict,
product advantage, and
project type in the
relationship between
requirement quality and
stability in terms of project
performance and market
performance.
pro
duct
man
ager
s
Ques
tionnai
re s
urv
ey
Factor analysis
with varimax
rotation,
confirmatory
factor analysis
and chi-square
tests
The results suggested that resource
definition and management
implementation process and training and
improvement was associated with
requirement quality and stability. The
findings also indicated that the number
of groups moderates the relationship
between requirement quality and
stability and project performance.
KPIs and CSFs relationship on developed countries studies
80.
An
der
sen
et
al
(2006)
Un
ited
Kin
gdom
,
Fra
nce
,
No
rway
an
d C
hin
a
To study the relationship
between project success
factors and actual project
success.
Pro
ject
man
ager
, p
roje
ct
cham
pio
n a
nd c
lien
ts
Qu
esti
on
nai
re s
urv
ey
Exploratory
factor analyses,
using principal
component
analysis (PCA)
with Varimax
Rotation
And regression
The results showed that the most
important factors in improving
managerial ability to deliver results in
time and at cost were strong project
commitment, early stakeholder
influence, stakeholder endorsement of
project plans and rich project
communications.
235
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
81.
Ahsa
n a
nd G
unaw
an (
2010)
Asi
an c
ountr
ies
To identify the root causes
of project delay and cost
under-run.
Inte
rnat
ional
dev
elopm
ent
pro
ject
s
Sec
ondar
y d
ata
Descriptive
statistics
The results indicated that critical
causes of project delay can be
attributed to natural calamities and
host country bureaucracy. The main
reasons of cost under-run are
categorized as devaluation of local
currency, competitive bidding price,
lower then estimated bid, and large
contingency budgets.
82.
Ora
ng
i et
al
(2011)
Vic
tori
a, A
ust
rali
a
To study specific cost
overrun and time overrun
issues in the linear
construction projects in
Victoria, Australia.
Pro
ject
man
ager
s
Tar
get
ed i
nte
rvie
ws
and c
ase
stu
dy
Frequency of
occurrence
The results showed that the set of root
causes in Victoria-based pipeline
projects cost overrun and time overrun,
include design changes, design errors,
poor communication, customer/ end-
user related issues, subsurface
investigation inadequacies, issues
regarding permissions/ approvals,
weather conditions, procurement delays,
site management problems,
subcontractor issues, rework, cultural
and heritage management issues.
236
Table A 3: Summary of KPIs and CSFs relationship researches
NO
.
Au
thor/
s
Cou
ntr
y
Objectives
Targ
et
gro
up
Met
hod
use
d
Analysis
approach Results and findings
83.
Hw
ang e
t al
(2013)
Sin
gap
ore
To identify the critical
factors affecting schedule
performance of public
housing projects in
Singapore.
Reg
iste
red c
ontr
acto
rs
Ques
tionnai
re s
urv
ey
Impact index,
frequency index
and criticality
index
Results indicated that “site management
”, “coordination
Among various parties”, “design
changes by owner during construction”,
“availability of laborers on site ”,
“availability of material ”,and
“availability of staff to manage projects
” are the six most critical factors that
affect schedule performance of public
housing projects in Singapore.
84.
Zav
adsk
as e
t al
(2014)
Lit
huan
ia
To analyze common
project management
problems and projects
success factors and to
illustrate how to assess a
projects' execution
efficiency by mean of the
aggregated indicator in
particular company.
Ex
per
t
Cas
e st
udy Multi-criteria
analysis and
logarithmic
normalization
method
Results showed that by using the
aggregated indicators it is easy to
compare the projects, the received
impartial information is useful for
strategic planning, quality management,
for solving the tasks of resource
allocation, motivational project
evaluation.
Appendix II: Questionnaire (English)
238
The Islamic university of Gaza
Higher studies deanery
Faculty of engineers – master program
Engineering project management
Questionnaire for
The success factors that affecting public construction projects and their relation to
key performance indicators
Dear participants greetings:
Firstly, I want to thank and appreciate your kindness to grant me a part of your valuable
time to fill out my questionnaire, which considered as a basic requirement for the
completion of my research in order to award the master of science degree in engineering
project management at Islamic university of Gaza. This research titled as " The success
factors that affecting public construction projects and their relation to key performance
indicators; Palestine as case study".
The aim of my research is to determine the key performance indicators which affect the
performance of public construction projects and to specify the critical factors which
affecting the success of these projects. Also it aims to evaluate the relationship between
those success factors and the construction projects performance. The targeted
construction projects in the research include housing projects and infrastructure projects
such as roads, schools hospitals public buildings and so on.
This questionnaire target group is construction consultants and experts especially those
who worked in the public sector, NGO's and the engineering consulting offices. And in
order to achieve my research objectives I cordially invite you to fill out this
questionnaire. Knowing that it needs 15 minute to fill out and any collected information
from this study will be used to purely academic purposes.
All appreciations and thanks for your contribution to support scientific research
Researcher
Sirin K. Elbohisi
Supervisor
Dr. Adnan Enshassi
Associated professor in civil
engineering
239
The questionnaire contents:
This questionnaire consists of three sections:
First section: general information.
Second section: key performance indicators KPI's of projects.
Third section: critical success factors affecting public construction projects.
First section: general information
Please tick √ versus the convenient option for you, taking into account to put it in
front of only one option.
Place of your resident
Gaza Strip West Bank
The type of your organization
Govermental
organization
Consultation
office
Non-governmental
organization
other, specify……..
Size of your organization suppervised projects during the last five years (in million
dollar):
Less than 5 M$ From 5 -10 M$ From 11 - 20 M$ More than 20 M$
Your organization working field
Housing
bulidings
projects
Govermental
buildings
projects
Public service
projects (schools,
hospitals,..)
Rubble
removal
projects
Roads
projects
Other, specify
Job Title for the participant who filling out the questionnaire
Design consultant Supervising consultant project manager Else, specify:……..
Years of experience in the construction industry for the participant who filling out the
questionnaire
From 5 -10 years From 11 -15 years From 16 -20 years More than 20 years
Please determine in years your practical experince in the following fields
Govermental
engineering
experience
Consulting
offecies
experience
Contracting
companies
experience
Financing
organizations
experience
Other experiences,
specify
240
Second section: key performance indicators KPI's of projects. Selections in the following Table related to specify the most important KPIs which can be
used to measure the projects performance in order to know whether the project is
succeeded or not (so please give attention to tick √ sign versus your suitable choice for
degree of importance, periodically measure of indicator and performance evaluation of
organization projects ).
#
. KPI
Degree of importance
Was KPI measured
during or after the
project ends?
Your evaluation for the
public construction
projects followed by
your organization, in
comparative to planned
according to each KPI
Ver
y
imp
ort
an
t
Imp
ort
an
t
Sem
i
imp
ort
an
t
Lo
w
imp
ort
an
t
No
t
imp
ort
an
t
Alw
ay
s
Mo
stly
So
met
imes
Ra
rely
Nev
er
Ver
y h
igh
Hig
her
Eq
ua
l
Les
s
Mu
ch l
ess
1. Actual project costs compared with
planned budget.
2. Actual project duration compared with
planned duration.
3.
Financial ability for both owner and
contractor to cover project
expenditures.
4. Project profitability for contractor
comparing with other related projects.
5. Project conformity to quality and
technical specifications standards.
6. Project conformity to sustainability
criteria.
7. Project conformity to environment
protection standards during execution.
8. Accidents and injures number in the
project.
9. Quantity and costs of variation orders.
10. Number and size of disputes,
litigations.
11. Contractor and consultant reputation.
12. Project parties satisfaction.
13. Beneficiaries satisfaction on project
functionality.
241
Third section: critical success factors affecting public construction projects. Project consider to be successful when KPIs which second section of this questionnaire
very close to planning. There is many factors contribute in project success which named
success factors. In this following Table some factors were mentioned that seemed to be
success factors. These factors classified according to project life cycle.
Selections in the following Table related to specify the importance of the effect of each
mentioned factor on projects success (so please give attention to tick √ sign versus your
suitable choice).
#.
Important degree of the critical factor effect
Critical factor
Very
important Important Neutral
Low
important
Not
important
First: Factors related to conceptualizing and preparation phase
1. Studying the feasibility, cost and priority of the project for the
society.
2. Formalizing deterministic, clear and realistic objectives for
the project and sharing project relatives in.
3. Determining project size represented by its required budget.
4. Specifying the project type whether it is new, maintenance,
completion for existing one or rubble removal project)
5. Determining the construction project nature (housing,
infrastructure, public building, …)
6. Specifying the project designing and execution complexity
comparing with previous related projects.
7. Endeavoring to decrease the political instability effect on the
project.
8. Studying the level of acceptance of local community to
execute the project in their location.
9. Studying project tendency to accidents and hazards.
10. Existence of experienced and understandable client (his
representative) on project nature and clear priorities for
project execution.
11. Giving suitable and enough time for planning and designing
phase.
12. Recruiting and involving consultant in all project activities
and phases.
Second: Factors related to planning and designing phase
1. Coordinating with related formal parties such as
(municipalities, electricity companies, ministries,… etc.).
2. Client contribution on project designing and planning.
3. Past relevant experience of consultant on designing similar
project.
4. Ability of project parties to generate innovative ideas.
5. Specific and measurable project quality standards.
6. Approved, clear and updated codes, specifications and
regulations for construction industry.
242
#.
Important degree of the critical factor effect
Critical factor
Very
important Important Neutral
Low
important
Not
important
7. Efficient technical capability of consultant for example
existence of skilled team and designers.
8. Designing project according to updated codes and standards
in order to eliminate possible errors.
9. Considering operation and maintenance requirements into
project design.
10. Social, cultural and environmental impacts on project type,
design and planning.
11. Project physical environment of project like (location, soil
works, availability of surrounding infrastructure, etc.).
12. Ease of having permits, licenses and any related approvals
from governmental institutions.
13. Availability of organized legal environment i.e. (laws of
industry encouragement, conflict resolution, litigations, etc).
14. Strong, detailed and updated integrated planning effort in
design and construction.
15. All key participants have participate in the detailed project
planning within their area of expertise.
16. Effective schedule management and realistic forecasting of
project duration.
17. The project has a formal organizational chart covering the
entire project.
18. Risk identification management and allocation.
19. Involvement of local community, project beneficiaries and
the affected parties in project plans and policies.
Third: Factors related to tendering and contracting phase
1. The client has a mechanism to manage the bids.
2. Transparent and efficient procurement criteria depends on
applicable laws and regulations.
3. Consider consultant and contractor past performance and
reputation as awarding criteria.
4. Past relevant experience of client in awarding bids and
managing contracts.
5. Past related experience of consultant in sharing in similar bids
and contracts.
6. Past related experience of contractor in sharing in similar bids
and contracts.
7. The consultant and the contractor have a mechanism to
manage the tenders and compete.
8. The client interprets all project requirements and location
during the bids preparatory meeting.
243
#.
Important degree of the critical factor effect
Critical factor
Very
important Important Neutral
Low
important
Not
important
9. Documentation the preparation meetings in details.
10. Visiting project location by all consultants and contractors
before filling out the bid form.
11. Granting enough time for consultants and contractors to fill
out the bid form.
12. Participating of related project parties in financial and
technical evaluation of tenders.
13.
Effective contract management included precise formulation,
documentation and enough detailed incentives, bonds,
penalties, …etc.
14. Project profitability for consultant and contractor
15. Economic environment in terms of materials quantity,
quality, and price, local currency value, …etc.
16. Delegation and authority allocation of project workers.
Fourth: Factors related to implementation phase
1. The client follows project implementation regularly.
2. Past relevant experience of contractor in execution similar
projects.
3. Appropriate safety practices during project execution.
4. Updated plan for supervising and managing project site.
5. Preparing and implementing environmental plans included
project waste management works.
6. Commitment of team members on project plans and
objectives.
7. Clear and effective decision making mechanism.
8. Project manager commitment to meet cost quality and time of
project.
9. Adequacy and effective management of project financial and
material resources.
10. Training the human resources in the skills demanded by the
project.
11. Leadership, monitoring, coordinating and organizing
manager skills of project manager.
12. Permanent presence of project manager in project site.
13. Availability of enough staff in project site according to works
requirements.
14. Top management support for project workers.
15. Collaborative team work environment.
16. Mutual trust and understanding between project participants.
17. Social relationships and coordination between project
participants.
244
#.
Important degree of the critical factor effect
Critical factor
Very
important Important Neutral
Low
important
Not
important
18. Annual organized meetings related to project activities for all
participants.
19. Timely and effective conflict resolution.
20. Effective project control , such as monitoring, updating
plans and feedback.
21. Control and monitoring subcontractors works.
22. Annual measuring of KPIs.
23. Effective well established information and communication
routines.
24. The project is part of a well-documented or understood
strategy
25. Effective knowledge processing and management systems.
26. Natural climates like winds, rains and high temperature.
27. Consultant and contractor commitment to continuous
improvement.
28. Client changes in plans and goals during execution.
29. Client approvals and Payment method.
30. Availability and execution of material handling plans.
31. Using applicable construction methods.
32. Continuous revision of project shop drawings and approve
them fast.
33. Saving as built drawings of the project.
34. Consultant and contractors involvement in project operating
and maintenance plan after project execution.
Thank you for your participation
Appendix III: Questionnaire (Arabic)
غزة - الإسلامية الجامعة
العليا الدراسات عمادة
الماجستير برنامج - الهندسة كلية
مشاريع هندسية إدارة
استبانة في موضوع
كحالة عوامل النجاح التي تؤثر على مشاريع الإنشاءات العامة وعلاقتها بالأداء؛ )فلسطين
دراسية(
The success factors that affecting public construction projects and their relation to
key performance indicators; Palestine as case study
السادة الكرام /
السلام عليكم ورحمة الله وبركاته ،،،
بداية أتقدم لكم بالشكر والامتنان على إعطاء جزء من وقتكم الثمين لتعبئة هذه الاستبانة التي تعد جززء أساسزيا
من الدراسة البحثية المطلوبة لنيل درجة الماجستير في إدارة المشروعات الهندسية بالجامعزة الإسزلامية وهزي
ات العامززة وعلاقتهززا بززافداء نفلسززطين كحالززة عوامززل النجززات التززي تززمشر علززى مشززاريع الإنشززاءبعنززوان
دراسية( .
الهدف من الدراسة هو معرفة أهم ممشرات قياس أداء المشزاريع الإنشزاةية العامزة و تحديزد أهزم العوامزل التزي
تمشر على نجات تلك المشاريع. كما وتهدف لتقييم العلاقة بين عوامل النجات وأداء مشاريع الإنشزاءات العامزة.
مشاريع الإنشاءات العامة المستهدفة من الدراسة مشاريع الإسكان والبنيزة التحتيزة كزالطر و ازدمات وتشمل
كالمدارس والمشافي والمباني العامة وغيرها من المشاريع التي تنفذها الجهات المختلفة.
القطزا العزام وتستهدف هذه الدراسزة فئزة الخبزراء والاستشزاريين فزي مجزاا الإنشزاءات وااازة العزاملين فزي
والممسسات الدولية والمكاتب الاستشارية الهندسية. ولتحقيق أهداف هذه الدراسة تم ااتيزار سزيادتكم مزن اجزل
دقيقة لتعبئتها مع العلم انه سزيتم اسزتخدام البيانزات التزي سزتجمع 15تعبئة الاستبانة التي يتوقع أن تحتاج لقرابة
فغراض البحث العلمي فقط.
ر والتقدير على مساهمتكم في دعم البحث العلمي.ولكم كل الشك
الباحثة
سيرين البحيصي
إشراف
أ.د. عدنان انشااي
مكونات الاستبانة:
تتكون هذه الاستبانة من شلاشة أجزاء وهم:
:معلومات عامة ومعلومات حوا المشاريع التي تابعتها ممسستكم. الجزء الأول
:ممشرات قياس أداء المشاريع. الجزء الثاني
:العوامل الممشرة على نجات مشاريع الإنشاءات التابعة للقطا العام. الجزء الثالث
:معلومات عامةالجزء الأول:
مقابل الخيار الذي ترونه مناسبا ونرجو مراعاة وضعها أمام ايار واحد فقط.√ الرجاء وضع إشارة
مكان الإقامة
قطا غزة الضفة الغربية
حاليا نوع المؤسسة التي تعملون بها
ممسسة حكومية مكتب استشاري أارى، حدد............ ممسسة غير حكومية.....
حجم المشاريع التي تابعتها مؤسستكم خلال الخمس سنوات الأخيرة
مليون دولار 5أقل من مليون دولار10 -5من مليون دولار20 -11من مليون دولار 20أكثر من
نيمكن ااتيار أكثر من ايار(مجالات عمل المؤسسة التي تعملون بها حاليا
مشاريع
سكنية مباني
مشاريع
مباني حكومية
مشاريع ادمات عامة
نمدارس، مستشفيات،..(
مشاريع
إزالة أنقاض
مشاريع
طر
أارى، حدد............
الحالي لمن يقوم بتعبئة الاستبانة المسمى الوظيفي
استشاري تصميم استشاري إشراف غير ذلك . حدد .... مدير مشاريع.....
سنوات الخبرة في قطاع الإنشاءات لمن يقوم بتعبئة الاستبانة
سنوات 10- 5من سنة 15 -11من سنة 20-16من سنة 20أكثر من
نبرجاء كتابة عدد السنوات في الصندو (برجاء تحديد سنوات خبرتكم العملية الخاصة في المجالات التالية
ابرة حكومية
هندسية
ابرة بمكاتب
استشارية
ابرة في شركات
المقاولات
ابرة في
ممسسات ممولة
ابرات أارى،
حدد............
المشاريع.ممشرات قياس أداء الجزء الثاني:
Keyالااتيارات في هذا الجدوا تتعلق بتحديد أهم الممشرات التي قد تستخدم لقياس أداء المشاريع ن
Performance Indicators "KPI's") أم لا نلذا في كل فقرة وذلك لمعرفة إن كان المشرو ناجحا
من وجهة نظرك√ نرجو وضع إشارة دورية – درجة الأهميةم لكل من عند الخيار الذي تجدونه مناسبا
(تقييمكم لأداء مشاريع الإنشاءات العامة المنفذة بمتابعتكم – قياس المؤشر
مؤشر القياس م.
درجة الأهميةيتم قياس المؤشر خلال أو بعد
تنفيذ المشروع
تقييمكم بالمجمل لأداء المشاريع
العامة التي نفذت بمتابعتكم من حيث
كل مؤشر مقارنتها بالمخطط حسب
داجم ها
امه
ط ستوم
يةهملأا
ض خفمن
يةهملأا
ام هر غي
ما ائد
با الغ
نا ياحأ
را ادن
قا طلم
ة فعرتم
دا ج
عة تفمر
ية اوسم
قلأ
ير كث بلأق
1. تكاليف المشرو الحقيقية مقارنة
بالتقديرات افولية.
2. مدة تنفيذ المشرو الحقيقية
مقارنة بالجدوا الزمني المقدر.
3. الكفاءة المالية للمالك والمقاوا
لتغطية تكاليف المشرو .
4.
أربات المشرو للمقاوا مقارنة
مع مشاريع أارى في نفس
المجاا.
5. مراعاة المشرو لمعايير الجودة
والمواافات الفنية.
6. مراعاة معايير الاستدامة أشناء
التنفيذ.
7. مراعاة معايير حماية البيئة أشناء
التنفيذ.
8. عدد الحوادث والإاابات في
المشرو .
عدد وتكلفة افوامر التغييرية. .9
عدد وحجم القضايا والنزاعات. .10
11. تأشر سمعة منفذي المشرو من
مقاوا واستشاري.
12. درجة رضا أطراف تنفيذ
المشرو .
13. مدى رضا المستفيدين على تأدية
المشرو للوظيفة المحددة له.
العوامل الممشرة على نجات مشاريع الإنشاءات التابعة للقطا العام.الجزء الثالث:
يعتبر المشرو ناجحا عندما تكون ممشرات قياس افداء المذكورة في الجزء الثاني من هذه الاستبانة مقاربة
في تحقيق ذلك وتسمى تسهم إلى حد كبير لما اطط له في بداية المشرو . وهناك العديد من العوامل التي
عوامل النجات المحتملة في الجدوا وقد تم سرد عدد من (Success Factorsهذه العوامل بعوامل النجات ن
التالي. وقد تم تقسيم هذه العوامل بناء على دورة حياة المشرو حيث يمر المشرو بعدة مراحل.
الااتيارات في الجدوا التالي تتمثل في تحديد أهمية كل عامل من العوامل المذكورة لنجات المشرو نلذا في
الذي تجدونه مناسبا من وجهة نظركم(.عند الخيار √ كل سماا نرجو وضع إشارة
م. درجة أهميته في التأثير على نجاح المشروع
هام هام جدا العوامل المؤثرةمتوسط
الأهمية
منخفض
الأهمية
غير
هام
أولا : العوامل المتعلقة بمرحلة التحضير والاستعداد للمشروع
المشرو بالنسبة للمجتمع.دراسة جدوى و قيمة وأولوية .1
2. وضع أهداف محددة وواضحة وواقعية للمشرو ومشاركة جميع
افطراف في وضعها.
تحديد حجم المشرو متمثلا في مقدار موازنته المطلوبة. .3
4. تحديد نو المشرو من حيث أنه مشرو جديد أو ايانة أو
استكماا مشرو قاةم أو إزالة أنقاض.
تحديد طبيعة مشرو الإنشاءات نسكني، بنية تحتية، مبنى عام،...(. .5
6. تحديد مدى اعوبة تصميم وتنفيذ المشرو مقارنة بما تم تنفيذه سابقا
من مشاريع.
العمل على تقليل تأشر المشرو بحالات عدم الاستقرار السياسي. .7
8. بموقع المشرو لتنفيذه في دراسة رضا المجتمع المحلي المحيط
المكان.
دراسة المخاطر والحوادث التي قد تنجم عن طبيعة المشرو . .9
11. فهم وتوفر ابرة سابقة لدى المالك/ من يمثله لطبيعة المشرو وتحديد
أولويات تنفيذه بوضوت.
إعطاء فترة زمنية مناسبة لمرحلة التخطيط والتصميم. .11
الاستعانة باستشاري في كافة مراحل المشرو . .12
العوامل المتعلقة بمرحلة التخطيط والتصميمثانيا :
1. التنسيق مع الجهات الرسمية ذات العلاقة بلديات، شركة الكهرباء،
.الوزارات المختصة، ...إلخ(
2. مساهمة المالك/ من يمثله الفعالة في مراحل التصميم والتخطيط
للمشرو .
م. درجة أهميته في التأثير على نجاح المشروع
هام هام جدا العوامل المؤثرةمتوسط
الأهمية
منخفض
الأهمية
غير
هام
توفر ابرة سابقة ذات علاقة لدى استشاري المشرو . .3
وجود قدرة لدى أطراف المشرو على توليد افكار الاقة. .4
وضع معايير الجودة المطلوبة للمشرو بحيث يمكن قياسها بسهولة. .5
6.
وجود كودات ومواافات واضحة ومحدشة لصناعة الإنشاءات
الجهات المنظمة كجمعيات المهندسين واتحادات معتمدة من
الصناعات.
كفاءة القدرات الفنية للاستشاري مثل وجود طواقم ومصممين مهرة. .7
8. الدقة في التصميم والاستناد فحدث الكودات والمعايير لتلافي
افاطاء التي قد تنجم.
9. مرحلة الإدارة والصيانة افاذ بالحسبان عند إعداد الخطط والتصاميم
والتشغيل للمشرو .
11. مراعاة العوامل الثقافية والاجتماعية والبيئية وتأشيرها على نو
وتصميم وتخطيط المشرو .
11. مراعاة العوامل الفيزيقية للمشرو مثل نموقعه، أعماا التربة، وجود
بنى تحتية محيطة بالمشرو ،...(.
12. تصاريح وتراايص عمل المشرو وما يتعلق به سهولة استخراج
من اعتمادات من قبل الممسسات الحكومية ذات العلاقة.
13. توفر البيئة القانونية من قوانين تشجيع وسرعة حل النزاعات
وغيرها.
14. وجود اطة مفصلة ومتكاملة لكل من مراحل التصميم والإنشاء مع
المشرو .تحديثها الداةم وفق مستجدات
15. مشاركة جميع ذوي العلاقة والمعنيين بوضع اطط المشرو كل في
مجاا ااتصااه وابرته.
التنبم الدقيق للوقت المطلوب للمشرو والجدولة الزمنية له. .16
17. وجود هيكل تنظيمي واضح وشامل وناظم لجميع افطراف ذات
العلاقة بالمشرو .
18. التي قد تواجه المشرو وسبل إدارتها مع تحديد تحديد المخاطر
واضح لمسئوليات ودور الجهات المختلفة لتجاوزها.
19. مشاركة ذوي العلاقة مثل ممثلين عن المجتمع المحلي والمستفيدين
من المشرو والمتضررين في رسم سياساته والتخطيط له.
والتعاقداتثالثا : العوامل المتعلقة بمرحلة المناقصات
وجود آلية لإدارة المناقصة من قبل المالك/ من يمثله. .1
2. وجود معايير شفافة وعادلة تتوافق مع أنظمة وقوانين العطاءات
المعموا بها.
م. درجة أهميته في التأثير على نجاح المشروع
هام هام جدا العوامل المؤثرةمتوسط
الأهمية
منخفض
الأهمية
غير
هام
اعتبار معايير السمعة وافداء المسبق من ضمن معايير الترسية. .3
4. ترسية عطاءات وعقود وجود تجربة سابقة للمالك / من يمثله في
مشابهه.
5. وجود تجربة سابقة للاستشاري في المشاركة بعطاءات وعقود
مشابهه.
وجود تجربة سابقة للمقاوا في المشاركة بعطاءات وعقود مشابهه. .6
7. وجود آلية لإدارة المقاوا أو الاستشاري لمناقصة المشرو وقدرتهم
على المنافسة.
8. المالك / من يمثله لكافة متطلبات المشرو وشرت لموقعه توضيح
الاا الاجتما التمهيدي للمناقصات.
9. توشيق كافة النقاط المتفق عليها بالتفصيل الاا الاجتماعات التمهيدية
للمناقصات.
11. زيارة كافة الاستشاريين / المقاولين لموقع المشرو قبل تعبئة نموذج
العطاء.
إعطاء وقت كاف للمقاوا/ الاستشاري لتعبئة العطاء. .11
12. مشاركة الجهات ذات العلاقة كالاستشاري في تقييم العروض ماليا
وفنيا.
13. الإدارة الفعالة للعقود ودقة اياغتها و توشيقها وتفصيل بنودها من
حيث العقوبات والضمانات والحوافز وغيره.
بالنسبة للمقاوا والاستشاري.ربحية المشرو .14
15. البيئة الاقتصادية المتعلقة في وجود معابر لداوا المواد وأسعار مواد
البناء وقيمة العملة المحلية وغيرها.
تفويض وتحديد الصلاحيات والمسئوليات للعاملين في المشرو . .16
م. درجة أهميته في التأثير على نجاح المشروع
العوامل المؤثرة هام هام جدا
متوسط
الأهمية
منخفض
الأهمية
غير
هام
رابعا : العوامل المتعلقة بمرحلة التنفيذ
متابعة المالك/ من يمثله بشكل منتظم لمرحلة تنفيذ للمشرو . .1
علاقة لدى مقاوا المشرو .توفر ابرة سابقة ذات .2
اتخاذ التدابير المتعلقة بافمان والسلامة أشناء تنفيذ المشرو . .3
وجود اطة محدشة فعماا إدارة موقع المشرو والإشراف عليه. .4
5. إعداد وتطبيق اطط تراعي الوضع البيئي ويشمل ذلك أعماا
المشرو .التخلص من المخلفات التي قد تنتج عن
التزام جميع طاقم العمل بخطط وأهداف المشرو . .6
7. سلاسة ووضوت سلطة وآلية اتخاذ القرارات من القاةمين على
المشرو سواء المالك أو الاستشاري أو المقاوا.
م. درجة أهميته في التأثير على نجاح المشروع
العوامل المؤثرة هام هام جدا
متوسط
الأهمية
منخفض
الأهمية
غير
هام
8. التزام مدير المشرو بإنهاء المشرو ضمن الموازنة والوقت
والجودة المحددة للمشرو .
توفير و إدارة الموارد المالية والمادية للمشرو بشكل ممنهج. .9
تدريب الموارد البشرية على المهارات اللازمة للمشرو . .11
11. تعيين مدير المشرو بحيث يمتلك المهارات الإدارية المتمثلة في
.قدرته على القيادة والرقابة والتنسيق والتوجيه
المشرو الداةم في المشرو .تواجد مدير .12
تواجد طاقم المشرو بشكل كاف في موقع المشرو . .13
دعم الإدارة العليا للعاملين في المشرو . .14
وجود بيئة تعاونية بين فر العمل في المشرو . .15
وجود شقة متبادلة وتفاهم بين العاملين في المشرو . .16
اجتماعية وتنسيق داةم بين العاملين في المشرو .وجود علاقات .17
18. دورية الاجتماعات المنظمة المتعلقة بأنشطة المشرو يشارك بها
جميع ذوي العلاقة.
سرعة حل النزاعات التي قد تنشأ بمسئولية ووفق اطة مدروسة. .19
21. عبر التغذية التحكم الفعاا في المشرو والرقابة عليه وتحديث بياناته
الراجعة.
21. الرقابة والتحكم بأعماا مقاولي الباطن باعتبارها جزء متكاملا من
المشرو .
22. قياس أداء المشرو أولا بأوا وفق ممشرات القياس الموضوعية
الدالة على نجات المشرو من عدمه.
المشرو .وجود نظام فعاا للتواال وتبادا المعلومات بين أطراف .23
توشيق أعماا وأنشطة المشرو بشكل واضح وعبر تقارير دورية. .24
وجود نظام فعاا لإدارة معلومات وبيانات المشرو ومعالجتها. .25
العوامل الطبيعية من ريات وأمطار وارتفا في درجات الحرارة. .26
باستمرار.قيام الاستشاري والمقاوا بتطوير وتحسين قدراتهم .27
28. وجود أوامر تغيرية التي يحدشها المالك/ من يمثله في اطط وأهداف
وتصميم المشرو أشناء التنفيذ.
29. سرعة اعتماد المالك / من يمثله للمستخلصات والدفعات وارفها
وفق التعاقد.
وجود وتنفيذ اطة لتخزين المواد اللازمة للمشرو . .31
تنفيذ للمشرو قابلة للتطبيق. ااتيار طر .31
( وسرعة اعتمادها.shop drawingsتدقيق ومراجعة مستمرة لل ن .32
.As built drawingsحفظ مخططات تنفيذ المشرو مع وجود .33
34. مشاركة المقاوا والاستشاري بإعداد اطة وتعليمات التشغيل
والصيانة للمشرو بعد الانتهاء من تنفيذه.
نشكر ونقدر تعاونكم معنا لإنجاح هذا البحث العلمي
Appendix IV: Criterion and structural validity of the questionnaire
254
Table A 4: Internal validity of the questionnaire
Domain Item no.
Correlation
coefficient (r)
between items
and domain
Correlation
coefficient (r)
between items
and whole
questionnaire
Item
no.
Correlation
coefficient (r)
between items
and domain
Correlation
coefficient (r)
between items and
whole questionnaire
Correlation
coefficient (r)
between domain
and whole
questionnaire
KPIs
1 0.848** 0.716** 8 0.766** 0.522*
0.874**
2 0.824** 0.645** 9 0.734** 0.486*
3 0.712** 0.822** 10 0.636** 0.515*
4 0.767** 0.527* 11 0.583** 0.621**
5 0.607** 0.722** 12 0.705** 0.479*
6 0.5* 0.605** 13 0.652** 0.545**
7 0.694** 0.506*
Factors related to
conceptualizing and
preparation phase
1 0.678** 0.568** 7 0.581** 0.536*
0.812**
2 0.474* 0.706** 8 0.564** 0.781**
3 0.507* 0.654** 9 0.587** 0.545**
4 0.535* 0.54** 10 0.516* 0.82**
5 0.809** 0.664** 11 0.76** 0.717**
6 0.716** 0.498* 12 0.463* 0.61**
Factors related to
planning and
designing phase
1 0.435* 0.489* 11 0.787** 0.78**
0.794**
2 0.548** 0.474* 12 0.818** 0.446*
3 0.784** 0.635** 13 0.452* 0.51*
4 0.559** 0.634** 14 0.757** 0.44*
5 0.725** 0.461* 15 0.844** 0.568**
6 0.463* 0.53* 16 0.503* 0.631**
7 0.578** 0.643** 17 0.797** 0.64**
255
Table A 4: Internal validity of the questionnaire
Domain Item no.
Correlation
coefficient (r)
between items
and domain
Correlation
coefficient (r)
between items
and whole
questionnaire
Item
no.
Correlation
coefficient (r)
between items
and domain
Correlation
coefficient (r)
between items and
whole questionnaire
Correlation
coefficient (r)
between domain
and whole
questionnaire
8 0.696** 0.478* 18 0.808** 0.492*
9 0.474* 0.514* 19 0.488* 0.56**
10 0.539** 0.672**
Factors related to
tendering and
contracting phase
1 0.565** 0.587** 9 0.444* 0.528*
0.851**
2 0.606** 0.61** 10 0.457* 0.537**
3 0.512* 0.753** 11 0.514* 0.474*
4 0.642** 0.736** 12 0.475* 0.604**
5 0.57** 0.479* 13 0.748** 0.577**
6 0.654** 0.761** 14 0.841** 0.82**
7 0.49* 0.499* 15 0.596** 0.466*
8 0.596** 0.79** 16 0.62** 0.448*
Factors related to
implementation
phase
1 0.591** 0.721** 18 0.826** 0.521*
0.882**
2 0.541** 0.49* 19 0.538** 0.794**
3 0.541** 0.452* 20 0.681** 0.619**
4 0.665** 0.749** 21 0.72** 0.458*
5 0.615** 0.492* 22 0.796** 0.67**
6 0.637** 0.667** 23 0.643** 0.5*
7 0.729** 0.551** 24 0.612** 0.63**
8 0.492* 0.646** 25 0.834** 0.534*
9 0.471* 0.732** 26 0.627** 0.45*
10 0.817** 0.535* 27 0.522* 0.801**
256
Table A 4: Internal validity of the questionnaire
Domain Item no.
Correlation
coefficient (r)
between items
and domain
Correlation
coefficient (r)
between items
and whole
questionnaire
Item
no.
Correlation
coefficient (r)
between items
and domain
Correlation
coefficient (r)
between items and
whole questionnaire
Correlation
coefficient (r)
between domain
and whole
questionnaire
11 0.635** 0.536* 28 0.614** 0.671**
12 0.571** 0.833** 29 0.505* 0.841**
13 0.727** 0.797** 30 0.649** 0.649**
14 0.77** 0.46* 31 0.701** 0.79**
15 0.806** 0.705** 32 0.786** 0.566**
16 0.806** 0.654** 33 0.836** 0.621**
17 0.562** 0.453* 34 0.823** 0.449*
Appendix V: Summary of selected and omitted KPIs and CSFs
258
Table A 5: Summary of selected KPIs
No. Indicators from literature Resource Notes New Indicator
1 Schedule indicators
Shenhar et al (2001); Chan et al (2002);
Dvir et al (2003); Frimpong et al
(2003); Dvir and Lechler (2004); Chan
and Chan (2004); Chan et al (2004a);
Hughes et al (2004); Bryde and
Robinson (2005); Wang and Huang
(2006); Sambasivan and Soon (2007);
Ko and Cheng (2007); Ahadzie et al
(2008); Lam et al (2007); Enshassi et al
(2009a); Yeung et al (2009); Cho et al
(2009); Ling and Bui (2010); Ahsan and
Gunawan (2010); Yang et al (2011); Al-
Tmeemy et al. (2011); Meng (2012); Ng
et al (2012); LI et al (2012); Chou et al
(2013); Hwang et al (2013); Alzahrani
and Emsley (2013); Cserháti and Szabó
(2014); Alias et al (2014); Locatelli et al
(2014).
Modified Actual project duration compared
with planned duration.
2 Cost indicators
Shenhar et al (2001); Chan et al (2002);
Dvir et al (2003); Frimpong et al
(2003); Dvir and Lechler (2004); Chan
and Chan (2004); Chan et al (2004a);
Hughes et al (2004); Bryde and
Robinson (2005); Wang and Huang
(2006); Sambasivan and Soon (2007);
Ko and Cheng (2007); Ahadzie et al
(2008); Lam et al (2007); Enshassi et al
(2009a); Yeung et al (2009); Cho et al
(2009); Ling and Bui (2010); Ahsan and
Gunawan (2010); Yang et al (2011); Al-
Tmeemy et al. (2011); Meng (2012); Ng
Modified Actual project costs compared with
planned budget.
259
Table A 5: Summary of selected KPIs
No. Indicators from literature Resource Notes New Indicator
et al (2012); LI et al (2012); Chou et al
(2013); Ali et al (2013); Alzahrani and
Emsley (2013); Alias et al (2014);
Locatelli et al (2014).
3 Satisfying the customers' needs
Shenhar et al (2001); Chan et al (2002);
Dvir et al (2003); Dvir and Lechler
(2004); Chan and Chan (2004); Chan et
al (2004a); Hughes et al (2004); Bryde
and Robinson (2005); Lam et al (2007);
Enshassi et al (2009a); Yeung et al
(2009); ); Ling and Bui (2010); Yang et
al (2011); Al-Tmeemy et al. (2011);
Chou et al (2013); Ali et al (2013);
Alias et al (2014).
Modified Beneficiaries satisfaction on project
functionality.
4 Satisfying stakeholders (other
than customer)
Chan et al (2002); Chan and Chan
(2004); Chan et al (2004a); Hughes et al
(2004); Bryde and Robinson (2005);
Lam et al (2007); Ahadzie et al (2008);
Enshassi et al (2009a); Cho et al (2009);
Ling and Bui (2010); Yang et al (2011);
Chou et al (2013); Mir and Pinnington
(2014); Cserháti and Szabó (2014)
Modified Project parties satisfaction.
5 Quality of service and work
Chan et al (2002); Chan and Chan
(2004); Hughes et al (2004); Wang and
Huang (2006); Lam et al (2007);
Ahadzie et al (2008); Yeung et al
(2009); Enshassi et al (2009a); Ling and
Bui (2010); Cho et al (2009); Yang et al
(2011); Al-Tmeemy et al. (2011); Meng
(2012); Ng et al (2012); LI et al (2012);
Chou et al (2013); Hwang et al (2013);
Modified Project conformity to quality and
technical specifications standards.
260
Table A 5: Summary of selected KPIs
No. Indicators from literature Resource Notes New Indicator
Ali et al (2013); Alzahrani and Emsley
(2013); Alias et al (2014)
6 Safety (accident rate)
Chan and Chan (2004); Hughes et al
(2004); Ko and Cheng (2007); Enshassi
et al (2009a); Yeung et al (2009); Ali et
al (2013); Alzahrani and Emsley (2013)
Modified Accidents and injures number in the
project.
7 Financial stability
Chan et al (2002); Ali et al (2013);
Alzahrani and Emsley (2013); Mir and
Pinnington (2014)
Modified
Financial ability for both owner and
contractor to cover project
expenditures
8 Reputation “professional image”
Chan et al (2002); Dvir et al (2003);
Lam et al (2007); Al-Tmeemy et al.
(2011); Cserháti and Szabó (2014)
Modified Contractor and consultant reputation .
9 Benchmarks Lam et al (2007); Shehata and El-
Gohary (2012); Ali et al (2013) Modified
Project profitability for contractor
comparing with other related projects
10 Cost of change orders Ko and Cheng (2007); LI et al (2012) Modified Quantity and costs of variation orders.
11 Environmental impact
Chan et al (2002); Chan and Chan
(2004); Hughes et al (2004); Ahadzie et
al (2008); Enshassi et al (2009a);
Alzahrani and Emsley (2013)
Modified Project conformity to environment
protection standards during execution.
12 Disputes, arbitrations and
litigations
Chan et al (2002); Chan et al (2004a);
Sambasivan and Soon (2007); Chen and
Chen (2007); Lam et al (2007); LI et al
(2012)
Modified Number and size of disputes,
litigations.
13
Added Project conformity to sustainability
criteria.
14 Profitability
Chan et al (2002); Dvir et al (2003);
Chan and Chan (2004); Ling and Bui
(2010); Al-Tmeemy et al (2011); Ng et
al (2012); Ali et al (2013); Alzahrani
and Emsley (2013); Mir and Pinnington
(2014).
Merged
261
Table A 5: Summary of selected KPIs
No. Indicators from literature Resource Notes New Indicator
15 Meeting the technical
specification
Shenhar et al (2001); Chan et al (2002);
Dvir et al (2003); Chan and Chan
(2004); Bryde andRobinson (2005);
Ling and Bui (2010); Al-Tmeemy et al.
(2011); Alzahrani and Emsley (2013)
Merged
16 Efficiency
Chan et al (2002); Chen and Chen
(2007); Lam et al (2007); LI et al
(2012); Ali et al (2013); Mir and
Pinnington (2014)
Merged
17 Impact on Long Term Benefits
Shenhar et al (2001); Mir and
Pinnington (2014); Cserháti and Szabó
(2014
Merged
18 Functional requirements
Shenhar et al (2001); Chan et al (2002);
Dvir et al (2003); Chan and Chan
(2004); Lam et al (2007); Al-Tmeemy
et al. (2011)
Merged
19 Design team satisfaction Chan et al (2002); Chan and Chan
(2004) Merged
20 Construction team’s satisfaction Chan et al (2002); Chan and Chan
(2004) Merged
21 Quantity of change orders Ko and Cheng (2007); LI et al (2012) Merged
22 Overall performance Wang and Huang (2006); Sambasivan
and Soon (2007) Merged
23 Effectiveness of planning Ali et al (2013); Locatelli et al (2014) Cancelled
24 Growth/ market share
Shenhar et al (2001); Dvir et al (2003);
Cho et al (2009); Al-Tmeemy et al.
(2011); Ali et al (2013); Alzahrani and
Emsley (2013); Mir and Pinnington
(2014)
Cancelled
25 productivity Chan et al (2002); Ko and Cheng
(2007); Enshassi et al (2009a); Shehata Cancelled
262
Table A 5: Summary of selected KPIs
No. Indicators from literature Resource Notes New Indicator
and El-Gohary (2012)
26 Aesthetics Chan et al (2002); Lam et al (2007);
Yeung et al (2009); Chou et al (2013) Cancelled
27 Risk Chou et al (2013) Cancelled
28 Human resources Chou et al (2013) Cancelled
29 Communication Wang and Huang (2006); Yeung et al
(2009); Chou et al (2013) Cancelled
30 Procurement Dvir et al (2003); Chou et al (2013) Cancelled
31 Pre-contract costs LI et al (2012) Cancelled
32 Learning value Lam et al (2007); Enshassi et al
(2009a); Yeung et al (2009) Cancelled
263
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
1. Accidents and hazards
Park (2009); Gudienė et al (2013); Gudienė et al
(2014); Marzouk and El-Rasas (2014);
Zavadskas et al (2014).
Modified 1. Preparing safety and
health plans..
2. Change in goals plans and
orders
Davies (2002); Dvir and Lechler (2004); Hughes
et al (2004); Fortune and White (2006); Orangi et
al (2011); Lehtiranta et al (2012); Yong and
Mustaffa (2013); Hwang et al (2013); Marzouk
and El-Rasas (2014); Wibowo and Alfen (2014);
Yang et al (2015).
Modified
2. Client changes in plans
and goals during
execution.
3. Commitment to continuous
improvement
Davies (2002); Chen and Chen (2007); Meng
(2012); Cserháti and Szabó (2014); Yang et al
(2015)
Modified
3. Consultant and
contractor commitment
to continuous
improvement.
4. Knowledge management Davies (2002); Yang et al (2012); Zou et al
(2014). Modified
4. Effective knowledge
processing and
management systems.
5.
Performance measurement
(Management for successful
outcome).
Davies (2002); Omran and Mamat (2011); Yu
and Kwon (2011); Zawawi et al (2011); Meng
(2012); Mir and Pinnington (2014); Cserháti and
Szabó (2014); Yang et al (2015).
Modified 5. Annual measuring of
KPIs.
6. Control of subcontractor
works
Sambasivan and Soon (2007); Ling and Bui
(2010); Orangi et al (2011); LI et al (2012);
Yong and Mustaffa (2013).
Modified 6. Control and monitoring
subcontractors works.
7.
The project has a clear and
well-planned agenda of
meetings for all participants
Dvir et al (2003); Nguyen et al (2004); Andersen
et al (2006); Iyer and Jha ( 2006); Chen et al
(2012); Garbharran et al (2012).
Modified
7. Annual organized
meetings related to
project activities for all
participants.
8. Parties relationships and
coordination
Chan et al (2004); Meeampol and Ogunlana
(2006); Wang and Huang (2006); Iyer and Jha (
2006); Lu et al (2008); Ng et al (2009); Park
(2009); Tan and Ghazali (2011); Omran and
Modified
8. Social relationships and
coordination between
project participants.
264
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
Mamat (2011); Yu and Kwon (2011); Meng
(2012); Hwang et al (2013); Molenaar et al
(2013); Yong and Mustaffa (2013); Cserháti and
Szabó (2014); Yang et al (2015).
9. Team members number and
performance
Wang and Huang (2006); Zavadskas et al (2014);
Ihuah et al (2014); Yang et al (2015). Modified
9. Availability of enough
staff in project site
according to works
requirements.
10. Project nature Chan et al (2004); Cho et al (2009); Yong and
Mustaffa (2013); Shehu et al (2014). Modified
10. Determining the
construction project
nature (housing,
infrastructure, public
building, …)
11.
Leadership, monitoring,
coordinating, organizing
manager skills for both
contractor PM and owner
Bourne et al (2002); Dvir et al (2003); Turner
and Müller (2005); Iyer and Jha ( 2006);
Andersen et al (2006); Fortune and White
(2006); Lu et al (2008); Ng et al (2009); Park
(2009); Tan and Ghazali (2011); Yang et al
(2011); Omran and Mamat (2011); Zawawi et al
(2011); Lehtiranta et al (2012); Ismail et al
(2012); Alzahrani and Emsley (2013); Gudienė et
al (2013); Zhao et al (2013); Gudienė et al
(2014); Alias et al (2014); Mir and Pinnington
(2014).
Modified
11. Leadership,
monitoring,
coordinating and
organizing manager
skills of project
manager.
12. Decision-making
effectiveness
Frimpong et al (2003); Dvir et al (2003); Iyer
and Jha ( 2006); Park (2009); Tan and Ghazali
(2011); Yu and Kwon (2011); Meng (2012);
Lehtiranta et al (2012); Gudienė et al (2013);
Gudienė et al (2014); Ihuah et al (2014).
Modified
12. Clear and effective
decision making
mechanism.
13. Commitment of all project
participants
Bourne et al (2002); Chan et al (2004a); Nguyen
et al (2004); Hughes et al (2004); Iyer and Jha (
2006); Wang and Huang (2006); Chen and Chen
Modified
13. Commitment of team
members on project
plans and objectives.
265
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
(2007); Aksorn and Hadikusumo (2008); Chan et
al (2010); Omran and Mamat (2011); Tan and
Ghazali (2011);Chen et al (2012); Garbharran et
al (2012); Lehtiranta et al. (2012); Ismail et al
(2012); Ng et al (2012); Yong and Mustaffa
(2013); Cserháti and Szabó (2014); Alias et al
(2014); Zou et al (2014).
14. Environmental plan and
methods during construction
Fortune and White (2006); Lu et al (2008); Ng et
al (2009); Park (2009); Lu and Yuan et al
(2010); Ismail et al (2012); Alzahrani and
Emsley (2013); Son and Kim (2014); Wibowo
and Alfen (2014); Zavadskas et al (2014).
Modified
14. Preparing and
implementing
environmental plans
included project waste
management works.
15. Safety issues
Chan et al (2004); Hughes et al (2004); Lu et al
(2008); Aksorn and Hadikusumo (2008); Ng et al
(2009); Park (2009); Alhaadir and
Panuwatwanich (2011); Gudienė et al (2013);
Yong and Mustaffa (2013); Gudienė et al (2014);
Son and Kim (2014).
Modified
15. Appropriate safety
practices during project
execution.
16. Profitability
Ng et al (2009); Park (2009); Ng et al (2012);
Famakin et al (2012); Gudienė et al (2013); Zhao
et al (2013); Gudienė et al (2014); Zavadskas et
al (2014).
Modified
16. Project profitability for
consultant and
contractor
17.
Contract management and
documentation include
penalties, bonds, incentives,
..etc
Frimpong et al (2003); Dvir et al (2003); Nguyen
et al (2004); Chan et al (2004a); Hughes et al
(2004); Wang and Huang (2006); Lu et al
(2008); Ng et al (2009); Park (2009); Tan and
Ghazali (2011); Abdul-Aziz and Kassim (2011);
Chen et al (2012); LI et al (2012); Famakin et al
(2012); Ng et al (2012); Garbharran et al (2012);
Lehtiranta et al (2012); Verburg et al (2013);
Gudienė et al (2013); Yong and Mustaffa (2013);
Alzahrani and Emsley (2013); Gudienė et al
Modified
17. Effective contract
management included
precise formulation,
documentation and
enough detailed
incentives, bonds,
penalties, …etc.
266
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
(2014); Marzouk and El-Rasas (2014).
18. Subcontractor and contractor
Involvement
Chan et al (2004); Ng et al (2009); Park (2009);
Tan and Ghazali (2011); LI et al (2012). Modified
18. Participating of related
project parties in
financial and technical
evaluation of tenders.
19. Project type
Chan et al (2004); Yang et al (2011); Cho et al
(2009); Gudienė et al (2013); Gudienė et al
(2014); Locatelli et al (2014); Shehu et al (2014);
Yang et al (2015).
Modified
19. Project type (new,
maintenance,
completion for existing
one or rubble removal
project)
20. Reputation Ng et al (2009); Abdul-Aziz and Kassim (2011);
Verburg et al (2013) Modified
20. Consider consultant and
contractor past
performance and
reputation as awarding
criteria.
21. Transparent and efficient
procurement method
Frimpong et al (2003); Dvir et al (2003); Chan
et al (2004); Wang and Huang (2006); Lu et al
(2008); Ng et al (2009); Chan et al (2010); Ling
and Bui (2010); Tan and Ghazali (2011);
Garbharran et al (2012); Gudienė et al (2013);
Yong and Mustaffa (2013); Windapo and Cattell
(2013); Gudienė et al (2014); Shehu et al (2014);
Son and Kim (2014); Wibowo and Alfen (2014).
Modified
21. Transparent and
efficient procurement
criteria depends on
applicable laws and
regulations.
22. Size
Chan et al (2004); Fortune and White (2006); Lu
et al (2008); Cho et al (2009); Ng et al (2012);
Gudienė et al (2013); Gudienė et al (2014);
Shehu et al (2014); Yang et al (2015).
Modified 22. Predetermining of
project size and budget.
23. Legal environment
Lu et al (2008); Chan et al (2010); Yu and Kwon
(2011); Ng et al (2012); Gudienė et al (2013);
Zhao et al (2013)Gudienė et al (2014); Wibowo
and Alfen (2014).
Modified
23. Availability of
organized legal
environment i.e. (laws
of industry
encouragement, conflict
267
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
resolution, litigations,
…etc).
24. Design management change
and mistakes
Dvir et al (2003); Ahsan and Gunawan (2010);
Lu and Yuan et al (2010); Tan and Ghazali
(2011); Orangi et al (2011); Lehtiranta et al
(2012); LI et al (2012); Yong and Mustaffa
(2013); Son and Kim (2014); Marzouk and El-
Rasas (2014);
Modified
24. Designing project
according to updated
codes and standards in
order to eliminate
possible errors.
25. Clear and realistic and
sharable multi-benefit goals
vision and mission of projects
Bourne et al (2002); Dvir et al (2003); Nguyen et
al (2004); ); Hughes et al (2004); Chan et al
(2004a); Iyer and Jha ( 2006); Fortune and White
(2006); Andersen et al (2006); Chen and Chen
(2007); Aksorn and Hadikusumo (2008); Lu et al
(2008); Toor et al (2008); Yang et al (2009);
Ahsan and Gunawan (2010); Chan et al (2010);
Alhaadir and Panuwatwanich (2011); Tan and
Ghazali (2011); Garbharran et al (2012);
Lehtiranta et al. (2012); Ng et al (2012);
Famakin et al (2012); Gudienė et al (2013);
Molenaar et al (2013); Yong and Mustaffa
(2013); Verburg et al (2013); Gudienė et al
(2014); Ihuah et al (2014); Son and Kim (2014);
Cserháti and Szabó (2014); Zou et al (2014).
Modified
25. Deterministic, clear,
sharable and realistic
project objectives.
26. Technical capability
(contractor and managers)
Chan et al (2004); Iyer and Jha ( 2006); Wang
and Huang (2006); Chen and Chen (2007); Lu et
al (2008); Ng et al (2009); Tan and Ghazali
(2011); Gudienė et al (2013); Alzahrani and
Emsley (2013); Gudienė et al (2014).
Modified
26. Efficient technical
capability of consultant
for example existence
of skilled team and
designers.
27. Quality standards and criteria
Tan and Ghazali (2011); Gudienė et al (2013);
Yong and Mustaffa (2013); Gudienė et al (2014);
Son and Kim (2014); Yang et al (2015).
Modified
27. Specific and
measurable project
quality standards.
28. Consultant recruitment and Bourne et al (2002); Fortune and White (2006); Modified 28. Consultant recruitment
268
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
involvement in budgeting and
supervision
Wang and Huang (2006); Ahsan and Gunawan
(2010); Jagboro et al. (2012); Molenaar et al
(2013); Yong and Mustaffa (2013).
and involvement in all
project activities.
29. Design completed before
work on site Park (2009). Modified
29. Suitable and enough
time for project
planning and designing.
30. Value
Dvir et al (2003); Dvir and Lechler (2004); Cho
et al (2009); Ng et al (2012); Gudienė et al
(2013); Zhao et al (2013); Gudienė et al (2014);
Son and Kim (2014); Yang et al (2015).
Modified 30. Project feasibility and
priority for society.
31. Financial security and
stability (contractor, owner)
Frimpong et al (2003); Nguyen et al (2004);
Chan et al (2004); Chen and Chen (2007); Lu et
al (2008); Ng et al (2009); Park (2009); Chen et
al (2012); Famakin et al (2012); Ng et al (2012);
Hwang et al (2013); Zhao et al (2013); Gudienė
et al (2013); Gudienė et al (2014); Marzouk and
El-Rasas (2014); Wibowo and Alfen (2014).
Modified
31. Adequacy and effective
management of project
financial and material
resources.
32. Project team leader
involvement and authority
Chan et al (2004); Turner and Müller (2005);
Andersen et al (2006); Iyer and Jha ( 2006); Tan
and Ghazali (2011); Yong and Mustaffa (2013);
Ihuah et al (2014).
Modified
32. Delegation and
authority allocation of
project workers.
33. Construction regulations
Chan et al (2004); Park (2009); Lu and Yuan et
al (2010); Zhao et al (2013); Gudienė et al
(2013); Windapo and Cattell (2013); Gudienė et
al (2014); Ihuah et al (2014); Son and Kim
(2014); Wibowo and Alfen (2014).
Modified
33. Approved, clear and
updated codes,
specifications and
regulations for
construction industry.
34. Cultural issues
Bourne et al (2002); Chen and Chen (2007);
Ahsan and Gunawan (2010); Orangi et al (2011);
Zawawi et al (2011); Chen et al (2012); Gudienė
et al (2013); Gudienė et al (2014); Ihuah et al
(2014).
Modified
34. Social, cultural and
environmental impacts
on project type, design
and planning.
35. Community, international Fortune and White (2006); Chen and Chen Modified 35. Involvement of local
269
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
and end user involvement (2007); Orangi et al (2011); Yang et al (2011);
Garbharran et al (2012); Ng et al (2012); Ihuah
et al (2014).
community, project
beneficiaries and the
affected parties in
project plans and
policies.
36. Depreciation/devaluation of
local currency
Hughes et al (2004); Ahsan and Gunawan
(2010); Gudienė et al (2014). Modified
36. Economic environment
in terms of materials
quantity, quality, and
price, local currency
value, …etc.
37. Clear prioritization of project
goals by the client
Chan et al (2004); Toor et al (2008); Yang et al
(2009); Ling and Bui (2010); Yang et al (2011);
Yong and Mustaffa (2013); Gudienė et al (2013);
Gudienė et al (2014).
Modified
37. Client understanding of
project nature priorities
and needs.
38. Political influence
Chan et al (2004); Chan et al (2004a); Iyer and
Jha ( 2006); Fortune and White (2006); Ng et al
(2009); Chan et al (2010); Abdul-Aziz and
Kassim (2011); Tan and Ghazali (2011);
Garbharran et al (2012); Ng et al (2012); Yong
and Mustaffa (2013); Zhao et al (2013); Gudienė
et al (2013); Gudienė et al (2014).
Modified
38. Recognizing political
influence on the
project.
39. Natural calamities
Frimpong et al (2003); Iyer and Jha ( 2006);
Ahsan and Gunawan (2010); Orangi et al (2011);
Gudienė et al (2013); Yong and Mustaffa (2013);
Gudienė et al (2014).
Modified
39. Natural climates like
winds, rains and high
temperature.
40. Mutual trust and
understanding
Gudienė et al (2014); Gudienė et al (2013); Chan
et al (2004); Chan et al (2004a); Chen et al
(2012); Famakin et al (2012); Park (2009); Tan
and Ghazali (2011); Verburg et al (2013); Chen
and Chen (2007); Yong and Mustaffa (2013)
Modified
40. Mutual trust and
understanding between
project participants.
41. Collaborative team culture Chan et al (2004a); Iyer and Jha ( 2006); Aksorn
and Hadikusumo (2008); Lu et al (2008); Ng et Modified
41. Collaborative team
working environment.
270
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
al (2009); Park (2009); Yang et al (2009);
Alhaadir and Panuwatwanich (2011); Yang et al
(2011); Chen et al (2012); Meng (2012);
Famakin et al (2012); Ismail et al (2012);
Verburg et al (2013); Yang et al (2015).
42. Management support
Bourne et al (2002); Chan et al (2004a); Nguyen
et al (2004); Iyer and Jha ( 2006); Andersen et al
(2006); Fortune and White (2006); Aksorn and
Hadikusumo (2008); Lu et al (2008); Alhaadir
and Panuwatwanich (2011); Garbharran et al
(2012); Gudienė et al (2013); Yong and
Mustaffa (2013); Gudienė et al (2014); Alias et
al (2014); Chen et al (2012); Ihuah et al (2014);
Cserháti and Szabó (2014); Zou et al (2014).
Modified
42. Top management
support for project
workers.
43. Physical environment (civil
works, location, weather,
..etc)
Frimpong et al (2003); Chan et al (2004); Lu et
al (2008); Ahsan and Gunawan (2010); Tan and
Ghazali (2011); Zawawi et al (2011); Windapo
and Cattell (2013); Gudienė et al (2013);
Gudienė et al (2014); Ihuah et al (2014); Shehu
et al (2014); Son and Kim (2014); Marzouk and
El-Rasas (2014); Wibowo and Alfen (2014).
Modified
43. Project physical
environment of project
like (location, soil
works, availability of
surrounding
infrastructure, … etc.)
44. Realistic time forecasting and
schedule management
Bourne et al (2002); Dvir et al (2003); Fortune
and White (2006); Andersen et al (2006);
Meeampol and Ogunlana (2006); Lu et al (2008);
Ng et al (2009); Park (2009); Abdul-Aziz and
Kassim (2011); Famakin et al (2012); Hwang et
al (2013); Gudienė et al (2013); Molenaar et al
(2013); Gudienė et al (2014); Ihuah et al (2014);
Marzouk and El-Rasas (2014); Zavadskas et al
(2014)
Modified
44. Effective schedule
management and
realistic forecasting of
project duration.
45. Ability to Generate
Innovative Ideas
Chan et al (2004a); Lu et al (2008); Lu and Yuan
et al (2010); Ng et al (2012); Gudienė et al Modified
45. Ability of project
parties to generate
271
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
(2013); Gudienė et al (2014). innovative ideas.
46. Close relationship with
suppliers Orangi et al (2011); Ismail et al (2012). Merged
Availability and
execution of material
handling plans.
47. Client approvals and
Payment method
Frimpong et al (2003); Sambasivan and Soon
(2007); Ng et al (2009); Orangi et al (2011); LI
et al (2012); Marzouk and El-Rasas (2014).
Selected 46. Client approvals and
Payment method.
48. The project has effective well
established information and
communication routines
Bourne et al (2002); Dvir et al (2003); Nguyen et
al (2004); Chan et al (2004); Meeampol and
Ogunlana (2006); Wang and Huang (2006);
Fortune and White (2006); Iyer and Jha ( 2006);
Chen and Chen (2007); Sambasivan and Soon
(2007); Lu et al (2008); Aksorn and Hadikusumo
(2008); Park (2009); Yang et al (2009); Chan et
al (2010); Lu and Yuan et al (2010); Alhaadir
and Panuwatwanich (2011); Yang et al (2011);
Tan and Ghazali (2011); Omran and Mamat
(2011); Yu and Kwon (2011); Abdul-Aziz and
Kassim (2011); Orangi et al (2011) ; Chen et al
(2012); Alias et al (2014); Gudienė et al (2014);
Cho et al (2009); Famakin et al (2012);
Garbharran et al (2012); Ismail et al (2012);
Meng (2012); Lehtiranta et al. (2012); Molenaar
et al (2013); Yong and Mustaffa (2013); Gudienė
et al (2013); Verburg et al (2013); Ihuah et al
(2014); Cserháti and Szabó (2014); Zou et al
(2014).
Selected
47. Effective well
established information
and communication
routines.
49. Effective and timely conflict
resolution
Chan et al (2004a); Chan et al (2004); Iyer and
Jha ( 2006); Lu et al (2008); Park (2009); Cho et
al (2009); Yang et al (2009); Yu and Kwon
(2011); Famakin et al (2012); Gudienė et al
(2013); Gudienė et al (2014).
Selected 48. Timely and effective
conflict resolution.
272
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
50. Complexity and uniqueness
Chan et al (2004); Hughes et al (2004);
Meeampol and Ogunlana (2006); Fortune and
White (2006); Cho et al (2009); Park (2009); Tan
and Ghazali (2011); Yang et al (2011); LI et al
(2012); Gudienė et al (2013); Yong and Mustaffa
(2013); Gudienė et al (2014).
Selected 49. Project complexity and
uniqueness.
51. Risk identification
management and allocation
Davies (2002); Dvir et al (2003); Chan et al
(2004a); Fortune and White (2006); Lu et al
(2008); Park (2009); Chan et al (2010); Ismail et
al (2012); LI et al (2012); Lehtiranta et al
(2012); Ng et al (2012); Meng (2012); Yong and
Mustaffa (2013); Gudienė et al (2013); Gudienė
et al (2014); Ihuah et al (2014); Son and Kim
(2014); Zavadskas et al (2014).
Selected
50. Risk identification
management and
allocation.
52. Applicable Construction
methods
Bourne et al (2002); Meeampol and Ogunlana
(2006); Park (2009); Chan et al (2010);
Lehtiranta et al (2012); Hwang et al (2013);
Alzahrani and Emsley (2013); Gudienė et al
(2013); Gudienė et al (2014).
Selected 51. Using applicable
construction methods.
53. Effective control , such as
monitoring, updating plans
and feedback
Davies (2002); Frimpong et al (2003); Chan et al
(2004a); Nguyen et al (2004); Chan et al
(2004a); Andersen et al (2006); Wang and
Huang (2006); Iyer and Jha ( 2006); Meeampol
and Ogunlana (2006); Fortune and White
(2006); Toor et al (2008); Aksorn and
Hadikusumo (2008); Park (2009); Ahsan and
Gunawan (2010); Abdul-Aziz and Kassim
(2011); Tan and Ghazali (2011); Omran and
Mamat (2011); Chen et al (2012); Ng et al
(2012); Famakin et al (2012); Gudienė et al
(2013); Yong and Mustaffa (2013); Alias et al
(2014); Gudienė et al (2014); Ihuah et al (2014);
Selected
52. Effective project
control , such as
monitoring, updating
plans and feedback
273
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
Son and Kim (2014); Zavadskas et al (2014).
54. Training the human resources
in the skill demanded by the
project
Fortune and White (2006); Iyer and Jha (2006);
Ng et al (2009); Lu and Yuan et al (2010);
Wibowo and Alfen (2014); Yang et al (2015).
Selected
53. Training the human
resources in the skills
demanded by the
project.
55. Project manager commitment
to meet cost quality and time
of project
Dvir et al (2003); Chan et al (2004); Meeampol
and Ogunlana (2006); Chen and Chen (2007); Lu
et al (2008); Park (2009); Omran and Mamat
(2011); Chen et al (2012); Gudienė et al (2013);
Son and Kim (2014); Cserháti and Szabó (2014).
Selected
54. Project manager
commitment to meet
cost quality and time of
project.
56. The project has a formal
organizational chart covering
the entire project
Chan et al (2004); Andersen et al (2006); Lu et
al (2008); Park (2009); Yu and Kwon (2011);
Zawawi et al (2011); Famakin et al (2012);
Gudienė et al (2013); Tan and Ghazali (2011);
Gudienė et al (2014); Son and Kim (2014);
Cserháti and Szabó (2014);
Selected
55. The project has a
formal organizational
chart covering the
entire project.
57.
All key participants have
participated in the detailed
project planning within their
area of expertise
Hughes et al (2004); Fortune and White (2006);
Andersen et al (2006); Famakin et al (2012);
Lehtiranta et al (2012); Yong and Mustaffa
(2013).
Selected
56. All key participants
have participate in the
detailed project
planning within their
area of expertise.
58. Strong /detailed and updated
integrated planning effort in
design and construction
Bourne et al (2002); Frimpong et al (2003); Dvir
and Lechler (2004); Nguyen et al (2004); Hughes
et al (2004); Chan et al (2004); Chan et al
(2004a); Andersen et al (2006); Sambasivan and
Soon (2007); Fortune and White (2006); Ng et al
(2009); Cho et al (2009); Yu and Kwon (2011);
Garbharran et al (2012); Lehtiranta et al (2012);
Ismail et al (2012); LI et al (2012); Gudienė et al
(2013); Hwang et al (2013); Alias et al (2014);
Gudienė et al (2014); Ihuah et al (2014);
Locatelli et al (2014); Son and Kim (2014);
Selected
57. Strong, detailed and
updated integrated
planning effort in
design and
construction.
274
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
Cserháti and Szabó (2014); Marzouk and El-
Rasas (2014).
59. The project is part of a well-
documented or understood
strategy
Davies (2002); Dvir et al (2003); Hughes et al
(2004); Andersen et al (2006); Toor et al (2008);
Park (2009); Yu and Kwon (2011); Lehtiranta et
al (2012); Alzahrani and Emsley (2013); Ihuah et
al (2014); Son and Kim (2014); Mir and
Pinnington (2014); Zavadskas et al (2014).
Selected
58. The project is part of a
well-documented or
understood strategy
60. Parties relevant past
experience
Hughes et al (2004); Nguyen et al (2004); Dvir
and Lechler (2004); Chan et al (2004a); Fortune
and White (2006); Sambasivan and Soon
(2007);Chen et al (2007); Lu et al (2008); Ng et
al (2009); Park (2009); Cho et al (2009); Ling
and Bui (2010); Tan and Ghazali (2011); LI et al
(2012); Chen et al (2012); Famakin et al (2012);
Garbharran et al (2012); Ng et al (2012); Hwang
et al (2013); Alzahrani and Emsley (2013); Yong
and Mustaffa (2013); Zhao et al (2013); Gudienė
et al (2013); Gudienė et al (2014); Marzouk and
El-Rasas (2014).
Splitted
59. Past relevant
experience of
contractor in execution
similar projects.
60. Past relevant
experience of client in
awarding bids and
managing contracts.
61. Past related experience
of consultant in sharing
in similar bids and
contracts.
62. Past related experience
of contractor in sharing
in similar bids and
contracts.
63. Past relevant
experience of
consultant on designing
similar project.
61. Appropriate supervision and
site management
Bourne et al (2002); Meeampol and Ogunlana
(2006); Iyer and Jha ( 2006); Sambasivan and
Soon (2007); Aksorn and Hadikusumo (2008);
Lu and Yuan et al (2010); Orangi et al (2011);
Splitted
64. Updated plan for
supervising and
managing project site.
65. Permanent presence of
275
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
Alhaadir and Panuwatwanich (2011); Tan and
Ghazali (2011); Hwang et al (2013); Yong and
Mustaffa (2013); Gudienė et al (2013); Gudienė
et al (2014); Marzouk and El-Rasas (2014).
project manager in
project site.
62. Tendering/ bidding strategy
and management
Frimpong et al (2003); Nguyen et al (2004);
Wang and Huang (2006); Lu et al (2008); Toor
et al (2008); Park (2009); Lu and Yuan et al
(2010); Tan and Ghazali (2011); Abdul-Aziz and
Kassim (2011); Molenaar et al (2013); Yong and
Mustaffa (2013); Shehu et al (2014); Marzouk
and El-Rasas (2014).
Splitted
66. The client has a
mechanism to manage
the bids.
67. The consultant and the
contractor have a
mechanism to manage
the tenders and
compete.
63. Client contribution in design
and construction
Chan et al (2004); Chan et al (2004a); Nguyen
et al (2004); Hughes et al (2004); Andersen et al
(2006); Iyer and Jha ( 2006); Toor et al (2008);
Cho et al (2009); Orangi et al (2011); LI et al
(2012); Gudienė et al (2013); Ihuah et al (2014).
Splitted
68. Client contribution on
project designing and
planning.
69. The client follows
project implementation
regularly.
64. Construction permits Tan and Ghazali (2011); Ng et al (2012);
Gudienė et al (2013); Gudienė et al (2014). Splitted
70. Ease of having permits,
licenses and any related
approvals from
governmental
institutions.
71. Coordinating with
related formal parties
such as (municipalities,
electricity companies,
ministries,… etc.)
65. Added
72. Consultant and
contractors involvement
in project operating and
maintenance plan after
276
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
project execution.
66. Added 73. Saving as built
drawings of the project.
67. Added
74. Local community
acceptance to execute
the project in their
location.
68. Added
75. Continuous revision of
project shop drawings
and approve them fast.
69. Added 76.
70. Added
77. Granting enough time
for consultants and
contractors to fill out
the bid form.
71. Added
78. Visiting project
location by all
consultants and
contractors before
filling out the bid form.
72. Added
79. Documentation the
preparation meetings in
details.
73. Added
80. The client interprets all
project requirements
and location during the
bids preparatory
meeting.
74. Added
81. Considering operation
and maintenance
requirements into
project design.
277
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
75. Personal motivation
Aksorn and Hadikusumo (2008); Lu et al (2008);
Park (2009); Ahsan and Gunawan (2010);
Gudienė et al (2013); Alias et al (2014); Gudienė
et al (2014).
Canceled
76. Bureaucracy Nguyen et al (2004); Ahsan and Gunawan
(2010). Cancelled
77. The project is well described
and coordinated with other
projects and activities
Bourne et al (2002); Dvir and Lechler (2004);
Andersen et al (2006); Lu et al (2008); Zou et al
(2014).
Cancelled
78. Project ownership Davies (2002); Ihuah et al (2014). Cancelled
79. One major contractor and
consortium Ng et al (2012); Locatelli et al (2014). Cancelled
80. Project insurance Lu et al (2008); Ng et al (2009). Cancelled
81. Responsiveness of
correspondence Molenaar et al (2013). Cancelled
82. Commitment to corruption
eradication
Abdul-Aziz and Kassim (2011); Wibowo and
Alfen (2014). Cancelled
83. An acceptable level of tariff Ng et al (2012) Cancelled
84. Access to affordable
mortgage/credit Windapo and Cattell (2013). Cancelled
85. Critical global
issues/globalization Windapo and Cattell (2013). Cancelled
86. Contingency funds Ahsan and Gunawan (2010) Cancelled
87. Extent of subcontracting LI et al (2012); Gudienė et al (2013); Gudienė et
al (2014). Cancelled
88. Close supervision when new
construction techniques are
employed
Hughes et al (2004); Ling and Bui (2010). Cancelled
89. Willingness to Eliminate
Non-value Added Activities Chan et al (2004); Park (2009). Cancelled
90. Sustainable project design
and construction
Park (2009); Ng et al (2012); Windapo and
Cattell (2013). Cancelled
278
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
91. Project is not susceptible to
fast-paced change (e.g.
Technological change)
Dvir and Lechler (2004); Ng et al (2012). Cancelled
92. Customer focus competence Fink (2014) Cancelled
93. Fairness of new conditions to
employees Chen and Chen (2007); Ng et al (2012). Cancelled
94. Knowledge transfer Toor et al (2008); Famakin et al (2012); Cserháti
and Szabó (2014) Cancelled
95.
All the organizations
involved in the project effort
have agreed to provide the
project with sufficient
resources
Chan et al (2004); Chen et al (2012); Famakin
et al (2012); Garbharran et al (2012); Alzahrani
and Emsley (2013).
Cancelled
96. Commitment to Win-Win
Attitude (compatibility of
objectives)
Chan et al (2004); Abdul-Aziz and Kassim
(2011); Yu and Kwon (2011); Famakin et al
(2012); Meng (2012).
Cancelled
97. Partnering was started at the
design stage
Chan et al (2004); Chen and Chen (2007); Park
(2009); Chen et al (2012); Ismail et al (2012). Cancelled
98.
Open exchange and
consideration of ideas were
promoted during the
partnering process
Chan et al (2004a); Andersen et al (2006); Wang
and Huang (2006); Yang et al (2009); Chen et al
(2012).
Cancelled
99. A list of partner selection
criteria was developed
Chan et al (2004); Famakin et al (2012);
Verburg et al (2013). Cancelled
100. Strong and good private
consortium Chan et al (2010); Cserháti and Szabó (2014). Cancelled
101. Public -sector capacity Ng et al (2012); Windapo and Cattell (2013). Cancelled
102. Partnerships with local and
national stakeholders Ng et al (2012); Cserháti and Szabó (2014). Cancelled
103. Profit-sharing Abdul-Aziz and Kassim (2011); Meng (2012). Cancelled
104. Identifying stakeholders Yang et al (2009) Cancelled
105. Social environment Chan et al (2004); Iyer and Jha ( 2006); Park Merged
279
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
(2009); Yang et al (2009); Chan et al (2010);
Abdul-Aziz and Kassim (2011); Tan and Ghazali
(2011); Gudienė et al (2013); Yong and Mustaffa
(2013); Gudienė et al (2014).
106. Troubleshooting Gudienė et al (2013); Alias et al (2014); Gudienė
et al (2014). Merged
107. Project management was
systematic and methodical
Davies (2002); Frimpong et al (2003); Nguyen et
al (2004); Fortune and White (2006); Wang and
Huang (2006); Ng et al (2009); Park (2009); Yu
and Kwon (2011); Lehtiranta et al (2012); Son
and Kim (2014).
Merged
108. Transaction cost economics
(preplanning)
Park (2009); LI et al (2012); Son and Kim
(2014). Merged
109.
Service quality can be easily
defined and objectively
measured
Ng et al (2012); Marzouk and El-Rasas (2014);
Yang et al (2015). Merged
110. Product and service
certification Gudienė et al (2013); Gudienė et al (2014). Merged
111. Technological environment
Bourne et al (2002); Davies (2002); Dvir and
Lechler (2004); Nguyen et al (2004); Chan et al
(2004); Fortune and White (2006); Lu et al
(2008); Park (2009); Lu and Yuan et al (2010);
Tan and Ghazali (2011); Omran and Mamat
(2011); Garbharran et al (2012); Gudienė et al
(2013); Yong and Mustaffa (2013); Zhao et al
(2013); Verburg et al (2013); Windapo and
Cattell (2013); Alzahrani and Emsley (2013);
Gudienė et al (2014); Son and Kim (2014).
Merged
112. Skilled designers
Aksorn and Hadikusumo (2008); Park (2009);
Tan and Ghazali (2011);Gudienė et al (2014);
Locatelli et al (2014).
Merged
113. Staff qualification and skills Fortune and White (2006); Ng et al (2009); Park Merged
280
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
(2009); Tan and Ghazali (2011); Chen et al
(2012); Lehtiranta et al. (2012); LI et al (2012);
Yong and Mustaffa (2013); Alzahrani and
Emsley (2013); Verburg et al (2013); Windapo
and Cattell (2013); Cserháti and Szabó (2014);
Wibowo and Alfen (2014).
114. Rework due to errors during
construction
Sambasivan and Soon (2007); Orangi et al
(2011); Molenaar et al (2013); Marzouk and El-
Rasas (2014); Zavadskas et al (2014);
Merged
115. Litigation, disputes and
arbitrating tendency
Lu et al (2008); Park (2009); Molenaar et al
(2013); Alzahrani and Emsley (2013). Merged
116.
The detailed project plans are
understood and accepted by
all project team members
Andersen et al (2006); Iyer and Jha ( 2006);
Chen and Chen (2007); Toor et al (2008); Park
(2009).
Merged
117. Foreign (external) Experts’
Participation in Projects
Chan et al (2004a); Ling and Bui (2010); Chen et
al (2012). Merged
118. Having an explicit
competitive strategy Davies (2002); Lu et al (2008); Park (2009). Merged
119. Competition
Hughes et al (2004); Park (2009); Ahsan and
Gunawan (2010); Abdul-Aziz and Kassim
(2011); LI et al (2012); Ng et al (2012); Ihuah et
al (2014); Son and Kim (2014).
Merged
120. The costs of building
materials
Frimpong et al (2003); Windapo and Cattell
(2013). Merged
121. Delegation and allocation of
authority and responsibility
Chan et al (2004a); Andersen et al (2006); ); Iyer
and Jha ( 2006); Aksorn and Hadikusumo
(2008); Lu et al (2008); Park (2009); Chan et al
(2010); Alhaadir and Panuwatwanich (2011);
Omran and Mamat (2011); Zawawi et al (2011);
Lehtiranta et al. (2012); Alzahrani and Emsley
(2013); Gudienė et al (2013); Verburg et al
(2013); Gudienė et al (2014); Cserháti and Szabó
Merged
281
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
(2014); Zou et al (2014).
122. Sufficient resource allocation
Chan et al (2004b); Fortune and White (2006);
Aksorn and Hadikusumo (2008); Park (2009);
Alhaadir and Panuwatwanich (2011); Gudienė et
al (2014).
Merged
123. Waste management system Lu and Yuan et al (2010); Son and Kim (2014); Merged
124. Personal competency
Nguyen et al (2004); Fortune and White (2006);
Toor et al (2008); Aksorn and Hadikusumo
(2008); Ahsan and Gunawan (2010); Omran and
Mamat (2011); Tan and Ghazali (2011);
Garbharran et al (2012); Lehtiranta et al. (2012);
Gudienė et al (2013); Yong and Mustaffa (2013);
Gudienė et al (2014); Ihuah et al (2014); Cserháti
and Szabó (2014).
Merged
125.
Selection of PM with proven
track record at an early stage
by top management
Iyer and Jha ( 2006); Omran and Mamat (2011). Merged
126. Personal attitude and issues
Bourne et al (2002); Dvir and Lechler (2004);
Iyer and Jha ( 2006); Aksorn and Hadikusumo
(2008); Alhaadir and Panuwatwanich (2011);
Omran and Mamat (2011); Gudienė et al (2013);
Verburg et al (2013);Gudienė et al (2014).
Merged
127. Good governance
(government policy)
Ng et al (2009); Chan et al (2010); Ng et al
(2012); Wibowo and Alfen (2014). Merged
128. Research and development
Davies (2002); Lu et al (2008); Ng et al (2009);
Lu and Yuan et al (2010); Chan et al (2010);
Ismail et al (2012).
Merged
129.
A team leader or champion
was appointed to ensure that
partnering principles did not
slip out of focus
Chan et al (2004a) Merged
130. Government Officers’ Hughes et al (2004); Ling and Bui (2010); Chan Merged
282
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
Participation in Projects et al (2010); Locatelli et al (2014); Wibowo and
Alfen (2014).
131. Adequate and clear financial
budget
Bourne et al (2002); Dvir et al (2003); Frimpong
et al (2003); Wang and Huang (2006); Fortune
and White (2006); Andersen et al (2006);
Meeampol and Ogunlana (2006); Park (2009);
Ahsan and Gunawan (2010); Chan et al (2010);
Tan and Ghazali (2011); Yang et al (2011);
Garbharran et al (2012); Chen et al (2012);
Yong and Mustaffa (2013); Alzahrani and
Emsley (2013); Gudienė et al (2013); Alias et al
(2014); Gudienė et al (2014); Ihuah et al (2014);
Locatelli et al (2014); Son and Kim (2014);
Zavadskas et al (2014);.
Merged
132. Economic viability
environment
Chan et al (2004); Iyer and Jha ( 2006); Enshassi
et al (2009); Chan et al (2010); Ahsan and
Gunawan (2010); Tan and Ghazali (2011); Ng et
al (2012); Windapo and Cattell (2013); Gudienė
et al (2013); Yong and Mustaffa (2013); Zhao et
al (2013); Gudienė et al (2014); Son and Kim
(2014); Wibowo and Alfen (2014);
Merged
133. Adequacy and management
of resources
Frimpong et al (2003); Dvir et al (2003); Nguyen
et al (2004); Hughes et al (2004); Iyer and Jha (
2006); Meeampol and Ogunlana (2006);
Sambasivan and Soon (2007); Chen and Chen
(2007); Lu et al (2008); Ng et al (2009); Lu and
Yuan et al (2010); Omran and Mamat (2011);
Orangi et al (2011); Garbharran et al (2012);
Ismail et al (2012); LI et al (2012); Chen et al
(2012); Lehtiranta et al (2012); Gudienė et al
(2013); Alzahrani and Emsley (2013); Yong and
Mustaffa (2013); Verburg et al (2013); Hwang et
Merged
283
Table A 6: Summary of selected and modified CSFs
No. Factor Resource Notes New factor
al (2013); Memon et al (2013); Gudienė et al
(2014); Ihuah et al (2014); Son and Kim (2014);
Mir and Pinnington (2014); Marzouk and El-
Rasas (2014); Yang et al (2015).
134. Adaptability to changes,
management of Changes
Dvir et al (2003); Chan et al (2004); Andersen et
al (2006); Fortune and White (2006); Chen and
Chen (2007); Cho et al (2009); Ng et al (2009);
Chen et al (2012); Gudienė et al (2013); Yong
and Mustaffa (2013); Gudienė et al (2014);
Yang et al (2015).
Merged
135. Client ability on brief, define
roles and make decisions
Chan et al (2004); Iyer and Jha ( 2006); Cho et
al (2009); Tan and Ghazali (2011); Lehtiranta et
al (2012); Gudienė et al (2013); Hwang et al
(2013); Gudienė et al (2014); Son and Kim
(2014); Marzouk and El-Rasas (2014);
Merged
Appendix VI: RII, means, SD and rank of CSFs
285
Table A 7: RII, means, SD and ranks of CSFs
Item Mean S.D RII
Test
value
P-value
(Sig.)
Total
rank
Phase 1 Factors related to project conceptualizing and preparation phase 4.22 0.47 84.42 43.13 0.000* (3)**
CSF 1 Project feasibility and priority for the society. 4.63 0.59 92.55 45.56 0.000* 1
CSF 2 Deterministic, clear, sharable and realistic project objectives 4.38 0.67 87.69 34.07 0.000* 17
CSF 3 Predetermining of project size and budget. 4.38 0.67 87.53 34.04 0.000* 21
CSF 4 Project type (new, maintenance, completion for existing one or rubble removal
project). 4.19 0.79 83.85 24.65 0.000* 51
CSF 5 Determining the construction project nature (housing, infrastructure, public
building, …) 4.21 0.86 84.1 23.08 0.000* 48
CSF 6 Project complexity and uniqueness. 3.96 0.8 79.26 19.96 0.000* 74
CSF 7 Recognizing political influence on the project. 3.95 0.8 79.25 19.8 0.000* 75
CSF 8 Local community acceptance to execute the project in their location. 3.89 0.88 77.8 16.71 0.000* 77
CSF 9 Preparing safety and health plans. 4.13 0.79 82.64 23.57 0.000* 61
CSF 10 Client understanding of project nature priorities and needs 4.13 0.86 82.51 21.65 0.000* 62
CSF 11 Granting suitable and enough time for project planning and designing 4.35 0.88 86.96 25.35 0.000* 25
CSF 12 Consultant recruitment and involvement in all project activities. 4.2 0.96 83.96 20.59 0.000* 50
Phase 2 Factors related to project planning and designing phase 4.2 0.49 83.99 40.68 0.000* (4)**
CSF 13 Coordinating with related formal parties such as (municipalities, electricity
companies, ministries,… etc.). 4.57 0.61 91.43 42.64 0.000* 2
CSF 14 Client contribution on project designing and planning. 4.23 0.77 84.63 26.24 0.000* 46
CSF 15 Past relevant experience of consultant on designing similar project. 4.44 0.68 88.79 35.05 0.000* 9
286
Table A 7: RII, means, SD and ranks of CSFs
Item Mean S.D RII
Test
value
P-value
(Sig.)
Total
rank
CSF 16 Ability of project parties to generate innovative ideas. 4.06 0.72 81.17 24.29 0.000* 69
CSF 17 Specific and measurable project quality standards. 4.31 0.7 86.1 30.88 0.000* 34
CSF 18 Approved, clear and updated codes, specifications and regulations for
construction industry. 4.38 0.7 87.69 32.52 0.000* 18
CSF 19 Efficient technical capability of consultant for example existence of skilled
team and designers. 4.44 0.72 88.79 33.24 0.000* 10
CSF 20 Designing project according to updated codes and standards in order to
eliminate possible errors. 4.45 0.72 89.08 33.53 0.000* 7
CSF 21 Considering operation and maintenance requirements into project design. 4.26 0.81 85.15 25.73 0.000* 37
CSF 22 Social, cultural and environmental impacts on project type, design and
planning. 3.88 0.88 77.65 16.6 0.000* 78
CSF 23 Project physical environment of project like (location, soil works, availability
of surrounding infrastructure, … etc.). 4.24 0.78 84.84 26.26 0.000* 43
CSF 24 Ease of having permits, licenses and any related approvals from governmental
institutions. 4.16 0.73 83.22 26.11 0.000* 58
CSF 25 Availability of organized legal environment i.e. (laws of industry
encouragement, conflict resolution, litigations, …etc). 3.9 0.86 78.02 17.35 0.000* 76
CSF 26 Strong, detailed and updated integrated planning effort in design and
construction. 4.25 0.75 85.05 27.55 0.000* 40
CSF 27 All key participants have participate in the detailed project planning within
their area of expertise. 4.07 0.78 81.4 22.57 0.000* 67
CSF 28 Effective schedule management and realistic forecasting of project duration. 4.07 0.8 81.47 22.27 0.000* 66
CSF 29 The project has a formal organizational chart covering the entire project. 4.12 0.79 82.49 23.52 0.000* 63
CSF 30 Risk identification management and allocation. 4.14 0.78 82.78 24.04 0.000* 60
CSF 31 Involvement of local community, project beneficiaries and the affected parties
in project plans and policies. 3.81 0.9 76.12 14.71 0.000* 80
287
Table A 7: RII, means, SD and ranks of CSFs
Item Mean S.D RII
Test
value
P-value
(Sig.)
Total
rank
Phase 3 Factors related to project tendering and contracting phase 4.28 0.46 85.53 45.43 0.000* (1)**
CSF 32 The client has a mechanism to manage the bids. 4.37 0.66 87.43 34.08 0.000* 22
CSF 33 Transparent and efficient procurement criteria depends on applicable laws and
regulations. 4.46 0.67 89.23 36.08 0.000* 6
CSF 34 Consider consultant and contractor past performance and reputation as
awarding criteria. 4.18 0.84 83.59 23.18 0.000* 55
CSF 35 Past relevant experience of client in awarding bids and managing contracts. 4.02 0.85 80.44 19.9 0.000* 72
CSF 36 Past related experience of consultant in sharing in similar bids and contracts. 4.28 0.77 85.64 27.68 0.000* 36
CSF 37 Past related experience of contractor in sharing in similar bids and contracts. 4.24 0.68 84.87 30.22 0.000* 42
CSF 38 The consultant and the contractor have a mechanism to manage the tenders
and compete. 4.2 0.7 84.04 28.42 0.000* 49
CSF 39 The client interprets all project requirements and location during the bids
preparatory meeting. 4.33 0.73 86.59 30.16 0.000* 29
CSF 40 Documentation the preparation meetings in details. 4.53 0.7 90.62 36.32 0.000* 3
CSF 41 Visiting project location by all consultants and contractors before filling out
the bid form. 4.33 0.74 86.67 29.6 0.000* 27
CSF 42 Granting enough time for consultants and contractors to fill out the bid form. 4.18 0.75 83.59 25.88 0.000* 54
CSF 43 Participating of related project parties in financial and technical evaluation of
tenders. 4.25 0.8 85.07 25.84 0.000* 38
CSF 44 Effective contract management included precise formulation, documentation
and enough detailed incentives, bonds, penalties, …etc. 4.38 0.79 87.57 28.71 0.000* 20
CSF 45 Project profitability for consultant and contractor 4.08 0.77 81.69 23.2 0.000* 65
CSF 46 Economic environment in terms of materials quantity, quality, and price, local
currency value, …etc. 4.32 0.81 86.45 27.04 0.000* 31
288
Table A 7: RII, means, SD and ranks of CSFs
Item Mean S.D RII
Test
value
P-value
(Sig.)
Total
rank
CSF 47 Delegation and authority allocation of project workers. 4.25 0.8 85.07 25.99 0.000* 39
Phase 4 Factors related to implementation phase 4.25 0.48 85.01 43.02 0.000* (2)**
CSF 48 The client follows project implementation regularly. 4.46 0.66 89.26 36.32 0.000* 5
CSF 49 Past relevant experience of contractor in execution similar projects. 4.4 0.7 87.99 33.25 0.000* 16
CSF 50 Appropriate safety practices during project execution. 4.42 0.71 88.38 33.01 0.000* 12
CSF 51 Updated plan for supervising and managing project site. 4.34 0.73 86.74 30.26 0.000* 26
CSF 52 Preparing and implementing environmental plans included project waste
management works. 4.07 0.85 81.32 20.81 0.000* 68
CSF 53 Commitment of team members on project plans and objectives. 4.37 0.71 87.33 32 0.000* 24
CSF 54 Clear and effective decision making mechanism. 4.4 0.67 88.01 34.53 0.000* 15
CSF 55 Project manager commitment to meet cost quality and time of project. 4.46 0.62 89.26 39.02 0.000* 4
CSF 56 Adequacy and effective management of project financial and material
resources. 4.45 0.62 89.04 38.41 0.000* 8
CSF 57 Training the human resources in the skills demanded by the project. 4.16 0.71 83.25 27.08 0.000* 57
CSF 58 Leadership, monitoring, coordinating and organizing manager skills of
project manager. 4.44 0.74 88.71 32.07 0.000* 11
CSF 59 Permanent presence of project manager in project site. 4.19 0.77 83.82 25.56 0.000* 52
CSF 60 Availability of enough staff in project site according to works requirements. 4.41 0.72 88.16 32.34 0.000* 14
CSF 61 Top management support for project workers. 4.18 0.76 83.6 25.48 0.000* 53
CSF 62 Collaborative team work environment. 4.31 0.72 86.25 29.86 0.000* 32
289
Table A 7: RII, means, SD and ranks of CSFs
Item Mean S.D RII
Test
value
P-value
(Sig.)
Total
rank
CSF 63 Mutual trust and understanding between project participants. 4.31 0.74 86.25 29.25 0.000* 33
CSF 64 Social relationships and coordination between project participants. 3.78 0.93 75.51 13.73 0.000* 81
CSF 65 Annual organized meetings related to project activities for all participants. 4.03 0.84 80.66 20.31 0.000* 70
CSF 66 Timely and effective conflict resolution. 4.25 0.77 85 26.75 0.000* 41
CSF 67 Effective project control , such as monitoring, updating plans and feedback. 4.21 0.74 84.19 26.9 0.000* 47
CSF 68 Control and monitoring subcontractors works. 4.32 0.77 86.49 28.2 0.000* 30
CSF 69 Annual measuring of KPIs. 4.24 0.81 84.72 25 0.000* 44
CSF 70 Effective well established information and communication routines. 4.23 0.69 84.63 29.51 0.000* 45
CSF 71 The project is part of a well-documented or understood strategy 4.37 0.75 87.43 30.25 0.000* 23
CSF 72 Effective knowledge processing and management systems. 4.17 0.79 83.49 24.42 0.000* 56
CSF 73 Natural climates like winds, rains and high temperature. 3.87 0.9 77.35 15.98 0.000* 79
CSF 74 Consultant and contractor commitment to continuous improvement. 4.02 0.74 80.44 22.67 0.000* 71
CSF 75 Client changes in plans and goals during execution. 3.98 0.86 79.56 18.62 0.000* 73
CSF 76 Client approvals and Payment method. 4.28 0.71 85.66 29.96 0.000* 35
CSF 77 Availability and execution of material handling plans. 4.15 0.83 83.1 22.82 0.000* 59
CSF 78 Using applicable construction methods. 4.33 0.71 86.59 30.77 0.000* 28
CSF 79 Continuous revision of project shop drawings and approve them fast. 4.41 0.77 88.27 30.25 0.000* 13
290
Table A 7: RII, means, SD and ranks of CSFs
Item Mean S.D RII
Test
value
P-value
(Sig.)
Total
rank
CSF 80 Saving as built drawings of the project. 4.38 0.77 87.65 29.47 0.000* 19
CSF 81 Consultant and contractors involvement in project operating and maintenance
plan after project execution. 4.1 0.8 81.99 22.74 0.000* 64