the art of delivering value on time

59
ristophe Achouiantz (@ChrisAch) The Art of Delivering Value on Time (The Art of Succeeding) hristophe Achouiantz ean/Agile Coach

Upload: christophe-achouiantz

Post on 09-May-2015

356 views

Category:

Technology


0 download

TRANSCRIPT

Page 1: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

The Art of Delivering Value

on Time

(The Art of Succeeding)

Christophe AchouiantzLean/Agile Coach

Page 2: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

About me

Christophe Achouiantz (fr)

Lean/Agile coach– Consultant since 2007– Sogeti since 2010– Coach, Project Leader, Programmer

Twitter: @ChrisAchBlog: http://leanagileprojects.blogspot.seLinkedIn

Page 3: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

The Art of Delivering Value on Time

1. A tale about a ’real’ project

2. Classical Techniques (to try and NOT to try)

3. Advanced techniques Helping a project to be more Effective and Efficient

Christophe Achouiantz @ChrisAch - Sogeti

Page 4: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

A Tale about a ’Real’ Project:

The Death Star 2 Project

a long time ago, in a galaxy far, far away

Christophe Achouiantz @ChrisAch - Sogeti

Page 5: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

Huge Program/Projects!• Massive Hardware• Looks Hugely Complex• Lot of Manpower• Heavy Security, Protocols, Processes• Probably nightmarish complex Software

Systems

What is all this about?

Christophe Achouiantz @ChrisAch - Sogeti

Page 6: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

$850,000,000,000,000,000

- Estimated Cost by The White HouseChristophe Achouiantz @ChrisAch - Sogeti

Page 7: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

$1,215,500,000,000,000,000

- Including typicall cost overrun of 43% For IT projects, an industry study by the Standish Group

found that the average cost overrun was 43 percent (Wikipedia)

Christophe Achouiantz @ChrisAch - Sogeti

Page 8: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

Senior Executive, sent to ”fix it”

Project Manager

Team Members(Glad they are not the PM)

Christophe Achouiantz @ChrisAch - Sogeti

Page 9: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

Seek desperate solutions, that will only make things worse this late in the project…

Christophe Achouiantz @ChrisAch - Sogeti

Page 10: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

Management by Fear…Christophe Achouiantz @ChrisAch - Sogeti

Page 11: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

How did the project get into this situation?

Christophe Achouiantz @ChrisAch - Sogeti

Page 12: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

How did the project get into this situation?

• Complex!• But manage it as if it is not…• Everything is high prio OR prioritized between

epics (all of Epic1, then all of Epic2) • Dubious motivational methods (no one really

cares?)• Unplanned changes due to market conditions

(new due date + changes to design)• Lack of experience (design team ’disapeared’

with DS1)

Christophe Achouiantz @ChrisAch - Sogeti

Page 13: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

What will happen now?

• Stress to get the job done in time! Overtime!• Multiple projects competing for the same

expert resources• Task-switching (actually gets less done)• Take short-cuts (technical debt++)• Everything becomes urgent! Hard to follow a

plan• Errors due to human factor (exhaustion, forced

to use underqualified resources, etc.)• Add people late makes the project later• Poor Quality!Christophe Achouiantz @ChrisAch - Sogeti

Page 14: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

From a ”venting shaft” to a ”highway” to the highly explosive core!?

Result of Stress, Task Switching &Technical Debt!

Result:

Christophe Achouiantz @ChrisAch - Sogeti

Page 15: The art of delivering value on time

Christophe Achouiantz (@ChrisAch) TM & © LUCASFILM LTD. ALL RIGHTS RESERVED.

”Delivered!” Success

“Why would we spend countless taxpayer dollars on a Death Star with a fundamental flaw that can be exploited by a one-

man starship?”- The White House

Christophe Achouiantz @ChrisAch - Sogeti

Page 16: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Why Do Projects Fail?

“The project focuses not primarily on creating value, profit and customer

satisfaction for the business, but to get the project completed on time

and on budget.”Christer Cragnell (Group CIO Swedbank)

Christophe Achouiantz @ChrisAch - Sogeti

Page 17: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Success!”Value Delivered on Time”

• To Deliver Value on Time means to deliver something of value to the customer, when it is needed…– not before, as it would be waste– not after, as it would be a cost and a missed opportunity

• …and with the necessary qualities to realize that value

Christophe Achouiantz @ChrisAch - Sogeti

Page 18: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Become an Artist to Deliver Value on Time

Today, despite an abundance of methods and processes,

60-80% of projects fail.

Therefore, to succeed is still an art!

If no method can fix it for us, we should all become better artists.

Let us learn some techniques!

Christophe Achouiantz @ChrisAch - Sogeti

Page 19: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Classical Techniques to Deliver Value on Time

• Techniques that usually do not help:– Change Control Boards– Add people late– Remove all constraints

• Techniques that usually help:– Intelligent Constraints– Know Why– Limit size of project– Reuse experience– Trim the tail

Christophe Achouiantz @ChrisAch - Sogeti

Page 20: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Use a CCB

”Changes are killing this project, we need a Change Control Board

(CCB)!”

Christophe Achouiantz @ChrisAch - Sogeti

Page 21: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Do Not Use a CCB

CCBs are only good for:– Making sure that the customer does not get

what is needed/wanted– Create conflicts– Focus attention on contract rather than

solution

Christophe Achouiantz @ChrisAch - Sogeti

Page 22: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Add People Late

”I need more men!”

Christophe Achouiantz @ChrisAch - Sogeti

Page 23: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Do Not Add People Late

Brooks’s Law: Adding manpower to a late software project

makes it later!

Christophe Achouiantz @ChrisAch - Sogeti

Page 24: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Remove Constraints

”Let’s take our time on this one. No time limit, no pressure, no

constraints!”

Christophe Achouiantz @ChrisAch - Sogeti

Page 25: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Duke Nukem

Page 26: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Do Not Remove Constraints

Student Syndrome: People will start to fully apply themselves to a task just at the last possible moment

before a deadline

Parkinson’s Law: “Work expands so as to fill the time available for its completion.”

Murphy’s Law: With sufficient time/trials, "Anything that can go wrong, will go wrong"

Christophe Achouiantz @ChrisAch - Sogeti

Page 27: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Set Intelligent Constraints to Drive Creativity

"Constraints shape and focus problems, and provide clear challenges to overcome as well as inspiration.

Creativity loves constraints, but they must be balanced with a healthy disregard for the impossible.“

Yahoo! CEO Marissa Mayer

An intelligent constraint informs creative action by outlining the "sandbox" within which people can play and guides that action not just by pointing out what to pursue but perhaps more importantly what to ignore.

Christophe Achouiantz @ChrisAch - Sogeti

Page 28: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Intelligent Constraints: Understand How Much Time you Have

Karl

Sco

tland

Page 29: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

No Big Projects

Get rid of Big Projects! Only start small projects, or even better no project

at all!

Big Projects = Big Administration & Complexity

Christophe Achouiantz @ChrisAch - Sogeti

Page 30: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Reuse Experience

To deliver the rigth thing on time:• Only work with Teams that already have the

needed knowledge!

Did you know? The Empire State building was built, from scratch to ’done’, in 1 year. This would be impossible to do today…

Poppendieck : ”Leading Lean Software Development: Results Are not the Point”

Christophe Achouiantz @ChrisAch - Sogeti

Page 31: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Sofware Development is a Knowledge Creation Process

• To succeed we need premium knowledge about:– The Problem– The Solution– The Technology used– How to work together as a team– How to work with the customer– The fitness of our organization

Christophe Achouiantz @ChrisAch - Sogeti

Page 32: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Succeed with Experience

• So, to best succeed you should only work with:– The same type of problems– The same type of solutions– The same technology– The same team– The same customer

• If not: it is a Challenge! You are in a Complex problem (more about that in a moment).

Christophe Achouiantz @ChrisAch - Sogeti

Page 33: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Trim the Tail

• Get rid of the ”long tail” where there is a low value created / time spended ratio.

• This requires some planning (more on that later)

Christophe Achouiantz @ChrisAch - Sogeti

Page 34: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Know WHY

• Allways start with WHY! (the golden circle)– Not What, or How or Who (yet)

• Spread it to everyone, so that everyone can contribute to reaching the goal– So that everyone CARES about it!

Christophe Achouiantz @ChrisAch - Sogeti

Page 35: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Advanced Techniques to Deliver Value on Time

Advanced Techniques that usually help

to become more: • Effective ”Do the right thing”• Efficient ”Do the thing right”

Christophe Achouiantz @ChrisAch - Sogeti

Page 36: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Minimize Output, Maximize Outcome

• Effectivity Techniques– Seek Actionable Feedback– Minimize Rework– Plan to make an Impact– Flesh out details after the plan (and not the

plan efter the details)

• Efficiency Techniques– Select the Right Process– Optimize Flow

Christophe Achouiantz @ChrisAch - Sogeti

Page 37: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Effectivity”Do the Right Thing”

Christophe Achouiantz @ChrisAch - Sogeti

Page 38: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Speed Up Knowledge Creation with Actionable Feedback

• Expect & Plan for feedback!

• Feedback about:– The problem and the solution (Iterative and Incremental

Development, Paper protypes, demos, etc.)– The process (visual management)– The implementation (test in parallel)

Christophe Achouiantz @ChrisAch - Sogeti

Page 39: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

The Financial Value of Feedback

Christophe Achouiantz – Sogeti Inspiration Day 2011

Page 40: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Minimize Rework

• Avoid Failure Demand

• Build quality in!– Test & Validation (validation criteria)

Christophe Achouiantz @ChrisAch - Sogeti

Page 41: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Make an Impact

• Identify Who (the actors) to focus on in the short term

• How to impact them (strategy)• What to do to impact them (features)

How To: Impact Mapping!

Christophe Achouiantz @ChrisAch - Sogeti

Page 42: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Impact Map

Gojko Adzic: ”Impact Mapping: Making a Big Impact with Software Products and Projects”

Page 43: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Example of Impact Map

Gojko Adzic: ”Impact Mapping: Making a Big Impact with Software Products and Projects”

Page 44: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Create the Right Plan

• Flesh out details after the plan (and not the plan efter the details)

• Start with an IDEA and high level requirements (a handfull). – Ex: an iPad app, with a team of 4, within one week, to help

customers choose the right sun-glasses (Norstrom inovation lab)– Intelligent Constraints!

• Specifications (the details) are unknown at the start and should be discovered with the help of feedback.

• How To: User Story Mapping!

Christophe Achouiantz @ChrisAch - Sogeti

Page 45: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

User Story Mapping

• A technique to design a solution and create a plan to deliver it into small increments.

• Combined with Impact Mapping, allows you to design and discover a Minimum Viable Product (MVP).

• Resembles Toyota’s ”Success Assured” as well as Kickstarter’s target funding and strech goals.

Christophe Achouiantz @ChrisAch - Sogeti

Page 46: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

From Idea to Plan via User Story Mapping

Christophe Achouiantz @ChrisAch - Sogeti

Page 47: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Building a Car using a traditional System Development method

Stop!No time/$ left!

Brakes Engine Gears Body SuspentionInterior& Seats

Wheels & Tyres

Page 48: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Building a Car the Right Way

Increment

IncrementIncrement

Increment

Brakes Engine Gears Body Suspention Interior& Seats

Wheels & Tyres

Page 49: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Exempel -1

User Story Map

© Christophe Achouiantz, Från Krav till System

Page 50: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Exempel - 2

Beroende

Frågor

Validation /Tests

User StoriesTasks /Sub-Aktiviteter

Utv. TeametKundenAnvändaren

Aktiviteter

mindre ”optional”

Mer ”optional”

© Christophe Achouiantz, Från Krav till System

Page 51: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Exempel - 31: Structure

2: Control

3: Security

4: Data quality

5: Statistics (xtra)

6: Performance (xtra)

7: Interface (xtra)

Inkrement 1:”Basic”

Inkrement 2”Testa Kopplingar”

Inkrement 3”Säkerhet”

Inkrement 4”Kvalité”

Delmål / inkrement mål

Diskutera, klargöra, dela-upp, ändra, validera, bekräfta

Klar for Project ”Pete”

© Christophe Achouiantz, Från Krav till System

Page 52: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

A model for usingUser Story Mapping

A System Design Workshop Invite key stakeholders (a handfull) Together, design the system by discovering details and discussing when/how to fit them in. ”Drill-down” sufficiently deep to discover and manage most of the problems. Create a visual map as a support for the discussions. Create an incremental development plan/roadmap from the visual map.

A recurring re-planning meeting Manage changes contiuously (e.g. weekly). Re-design the system (the map) to fit the changes Re-plan to accomodate the changes.

After the workshop, adapt the plan continuously to accomodate:

• The new understanding about the problem, solution, system.

• The impact of the stakeholders feedback after an increment.• Life!

Page 53: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Efficiency”Do the Thing Right”

Christophe Achouiantz @ChrisAch - Sogeti

Page 54: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Use the Right Processfor the Right Problem

Page 55: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Optimize the Workflow• See and Understand your Value Stream

• Identify bottlenecks, blocks, queues (waste)

• Create experiments to get rid of them

• Create policies from successfull experiments

• Go further with Kanban & Personal Kanban(set extra constraints/policies. E.g. limit Work In Progress)

Christophe Achouiantz @ChrisAch - Sogeti

Page 56: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Kanban Board Ex.

Christophe Achouiantz @ChrisAch - Sogeti

A Kanban Board

Page 57: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Techniques for the Art of Delivering Value on Time

• Set intelligent constraints• Work with small projects, or no project• Plan for experience and re-use it• Effectivity

– Seek feedback (prototypes, demos, visual management, test and validate parallel to development)

– Minimize Rework (Failure Demand)– Plan to make an Impact (Impact Mapping)– Flesh out details after the plan (User Story Mapping)

• Efficiency– Use the right process (complex or complicated?)– Optimize Flow (Kanban)

Christophe Achouiantz @ChrisAch - Sogeti

Page 58: The art of delivering value on time

Christophe Achouiantz (@ChrisAch)

Thank You!

Christophe AchouiantzTwitter: @ChrisAchBlog: http://leanagileprojects.blogspot.se