tanzania intermodal and rail development project …€¦ · major goal is to provide reliable...
TRANSCRIPT
UNITED REPUBLIC OF TANZANIA
MINISTRY OF WORKS, TRANSPORT AND COMMUNICATION
TANZANIA INTERMODAL AND RAIL DEVELOPMENT PROJECT (TIRP)
REHABILITATION OF RAILWAY LINE INCLUDING TRACK RENEWAL AND
BRIDGES BETWEEN DAR ES SALAAM AND ISAKA
ABBREVIATED RESETTLEMENT ACTION PLAN
PACKAGE B, KILOSA-ISAKA
FINAL REPORT
May 2018
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
i
TABLE OF CONTENTS
EXECUTIVE SUMMARY ........................................................................................................... 1
LIST OF ABBREVIATIONS AND ACRONYMS ...................................................................... 5
CHAPTER ONE ............................................................................................................................ 6
1.1 Introduction ........................................................................................................................... 6
1.2 Scope of the Abbreviated Resettlement Action Plan ............................................................ 6
1.3 Principles Governing ARAP ................................................................................................. 7
CHAPTER TWO ........................................................................................................................... 8
2.1 Study Methodology ............................................................................................................... 8
2.2 Number of Project Affected Persons .................................................................................... 8
2.3 Survey and Socio-economic Study of Project Affected Persons (PAPs) ............................. 9
2.4 Cut-off Date for Entitlements ............................................................................................... 9
2.5 Study Limitations .................................................................................................................. 9
2.6 Disclosure of the ARAP...................................................................................................... 10
CHAPTER THREE ..................................................................................................................... 11
3.1 Results of Socio-Economic Study along the Project Corridor ............................................ 11
3.2 Heads of Households .......................................................................................................... 11
3.3 Gender Distribution in Households .................................................................................... 11
3.4 PAPs Economic Activities .................................................................................................. 11
3.5 Level of Education among Household members ................................................................ 13
CHAPTER FOUR ........................................................................................................................ 14
4.1 Potential Impacts of the Project on Identified PAPs ........................................................... 14
4.2 Positive Anticipated Impacts .............................................................................................. 14
4.2.1 Employment opportunities .................................................................................................. 14
4.2.2 More efficient way of transporting farm produce ............................................................... 14
4.3 Negative Anticipated Impacts ............................................................................................. 14
4.3.1 Farmers ............................................................................................................................... 14
4.3.2 Traders ................................................................................................................................ 14
4.3.3 Nomadic Livestock Keepers ............................................................................................... 15
CHAPTER FIVE ......................................................................................................................... 15
5.1 Policy and Legal Framework .............................................................................................. 15
CHAPTER SIX ............................................................................................................................ 16
6.1 Impact Mitigation Measures and Implementation Arrangements ...................................... 16
ii
6.2 Farmers ............................................................................................................................... 16
6.3 Livestock Keepers ............................................................................................................... 16
6.4 Petty Traders ....................................................................................................................... 16
6.5 Communications Plan ......................................................................................................... 17
CHAPTER SEVEN ..................................................................................................................... 17
7.1 Institutional Responsibilities and Grievance Redress Mechanism ..................................... 17
7.2 Other Organizations and Agencies ..................................................................................... 18
7.2.1 Civil Works Contractor ....................................................................................................... 18
7.2.2 Local Government Authorities, District Level ................................................................... 18
7.3 Grievance Redress Mechanism ........................................................................................... 18
7.4 GRM Procedures ................................................................................................................. 18
7.5 GRM Committee ................................................................................................................. 19
CHAPTER EIGHT ...................................................................................................................... 20
8.1 Implementation Schedule .................................................................................................... 20
8.2 Costs and Budget ................................................................................................................ 22
CHAPTER NINE ......................................................................................................................... 23
9.1 Monitoring and Evaluation ................................................................................................. 23
9.2 Evaluation ........................................................................................................................... 23
ANNEXES ................................................................................................................................... 24
Annex A: Summary of issues raised during discussions with each PAP. ................................... 24
Annex B: Entitlement Matrix....................................................................................................... 25
Annex C: Photography and Size of Affected Farms. ................................................................... 26
Annex D: Summary Table of the Gaps between WB Policies and Tanzania Laws .................... 41
Annex E: Sample of Grievance Redress Mechanism form. ........................................................ 48
LIST OF TABLES
Table 1:Social baseline information of interviewed PAPs ........................................................ 12
Table 2:Implementation Schedule of ARAP .............................................................................. 20
Table 3:Tentative Budget For Mitigation Measures and GRM. .............................................. 22
LIST OF FIGURES
Figure 1:Area covered by the project ........................................................................................... 2
Figure 2:Map showing location of PAPs ....................................................................................... 8
1
EXECUTIVE SUMMARY
The Ministry of Works, Transport and Communication through TRC (RAHCO) intends to
rehabilitate Dar es Salaam - Isaka section of railway line. This initiative is financed by the World
Bank and will be implemented under Tanzania Intermodal and Rail Development Project, whose
major goal is to provide reliable transportation of goods and promote access to services. The project
has major four components as scribed below:
Component A: Improvement of Rail Infrastructure
This component involves rehabilitation of Railway Track and Structures (Bridges and Culverts)
Rehabilitation Works from Kilosa – Isaka and Supervision of Track and Bridge Works.
Component B: Rolling Stock
Component includes Supply of Three Locomotives, Refurbishment of Two Locomotives, Supply
of Fifteen Ballast Hopper Wagons, Forty-four Freight Flat Wagons, Tamping and Regulating
Machines, Track Recording Car and Train Control System.
Component C: Development of Isaka Terminal, Ilala Terminal and Dar es Salaam Port
Platform.
This Component comprises the development of Intermodal Container Terminals in the port of
Dar es Salaam, in Ilala and in Isaka to allow for more efficient modal transfers to and from the
railway.
Component D: Institutional Strengthening, Capacity Building, and Implementation Support
This Component comprises preparatory Design studies, Enhancement of Information Technology,
Setting up of the Project Implementation Team (PIT), and Capacity Strengthening of TRC (TRL).
The Project would also support the Strengthening of TRC (TRL) management, due diligence
process and five year Business Plan.
Other Capacity Strengthening Measures for TRC, SUMATRA and MoWTC
Funds are allocated for technical assistance for: (i) designing the right maintenance organization
and a pilot maintenance program within TRC (RAHCO) for maintenance activities;
(ii) implementing effective regulation for open access policy, which is key in ensuring economic
sustainability of the Project; (iii) technical assistance and training to TRC and SUMATRA staff;
(iv) communication strategy for project implementation; (v) support to the Ministerial Delivery
Team established for monitoring BRN and the Monitoring & Evaluation Team of the MoWTC for
undertaking the monitoring & evaluation of the Project.
2
This ARAP applies to component A on rehabilitation of railway track sections and weak bridges
which is 970 km from Dar es Salaam to Isaka Terminal. It is categorised into two packages where
package A coves Dar es Salaam to Kilosa (283km) and Package B which covers Kilosa to Isaka
(687km). This report is for Package B only which is Kilosa -Isaka section.1 Area covered by the
project is indicated in the figure 1.
Area covered by the project is indicated in Figure 1.
Figure 1:Area covered by the project
1 The ARAP for package A, Dar es Salaam to Kilosa, was prepared separately, cleared by the Bank and publicly
disclosed in-country and by the WB.
3
The construction corridor of this project is 7.5m left and right from the centre of the railway truck.
The total area of the corridor is 20.61sq.km. This area needs to be cleared before commencement
of railway rehabilitation. Due to this fact, people who are conducting human activities within 7.5m
both sides of the railway track have to be moved for the project to be implemented.
According to World Bank operation policy (OP 4.12) on involuntary resettlement for any person to
be moved from World Bank supported project area, compensation or assistance must be provided
subject to eligibility criteria of the individual. The OP 4.12 states that when less than 200 people
are impacted by Project activities, there is no physical resettlement and less than 10 percent of
PAPs’ productive assets are lost, an Abbreviated Resettlement Action Plan (ARAP) can be
produced.
Regarding World Bank requirements, this ARAP is developed specifically for 7.5m right of way to
ensure that, people who will be affected by the project are consulted in order to safeguard their
interests during and after project implementation. This report follows WB OP 4.12 and the
Resettlement Policy Framework (RPF) that was developed during the project preparation, for
formulating an (Abbreviated) Resettlement Action Plan and requirements for compensation and
assistance for the Project Affected Persons (PAPs).
Methodology employed in developing this ARAP includes:
Review of relevant background reports and documentation
PAPs identification field visit.
Observation.
Socio-economic survey of PAPs.
Following above methodology, PAPs were identified and categorized into three categories:
a. Farmers
b. Petty Traders
c. Nomadic Livestock keepers
During the site visits in February and April 2018, 17 farmers were identified and interviewed;
eleven (11) PAPs are railway workers, where main source of their income is through employment,
five (5) PAPs depends on agriculture as their main economic activity and all of the five have their
main farms located outside the project corridor. Only one PAP was found to be a business man. All
PAPs conduct their activities in the corridor on temporal bases and they are all aware that the land
does not belong to them and they are ready to move at any time. Petty traders were not identified
during the site visits but there was information from station masters that petty traders conduct their
activities on temporary bases especially when there are passenger trains coming through. Livestock
keepers were observed crossing the railway but it was difficult to meet them and most of these
livestock keepers are nomadic in nature. So, in this case petty traders and nomadic livestock keepers
have been addressed as a group and not as individuals.
All the farmers utilize very small portions of land along the railroad tracks (see Annex C for more
details) and after the commencement of the project they will lose access to them. They do not have
4
any legal rights to this land and therefore they will not be compensated for the land but some
assistant measures will be provided to them.
Measures which will be taken to all the PAPs will be provision of grace period to farmers to harvest
their crops before the civil works commence, preparing IDs for petty trades and assisting livestock
keepers in allocation of new areas for them to graze their cattle.
Impacts of the project on the identified PAPs are very minor, including limited access to the project
area for all identified PAPs.
Impact mitigation measure for the identified impact will be as follows;
Provision of a grace period giving enough time for the farmers to harvest their seasonal
crops - three months.
Creation of employment opportunities for the PAPs during project implementation.
Periodic campaign with affected communities to make them aware of the project and
precautions that they should take during the civil works and operation of the railways.
Security operations along project corridor.
Provision of access for petty traders to sell their products at different stations at specified
times.
National policies/legislation and the World Bank safeguard policies were considered in
implementation of this ARAP. TRC (RAHCO) is the main agency for implementation of this
ARAP in collaboration with other agencies such as Ministry of Works, Transport and
Communication and local government authorities.
PAPs are expected to harvest their crops by the end May - June 2018 and construction is
expected to start in June - July 2018. PAPs were notified about the project and its activities on
18 February 2018. Information was also shared with village leaders, station masters and gangers
so that they can transfer the information to the entire community.
All expenses associated with the ARAP and associated mitigation measures implementation
will be covered by TRC (RAHCO).
Monitoring and evaluation of ARAP implementation will be conducted by TRC (RAHCO).
5
LIST OF ABBREVIATIONS AND ACRONYMS
ARAP Abbreviated Resettlement Action Plan
BRN Big Results Now
DED District Executive officer
DTS Director of Technical Services
ESIA Environnemental and Social Impact Assessment
FPIC Free-Prior Informed Consent
GRC Grievance Redress Committee
GRM Grievance Redress Mechanism
ID Identity Cards
MoWTC Ministry of Works, Transport and Communication
OP Operational Policies
PAP Project Affected Persons
PIT Project Implementation Team
RoW Right of Way
RPF Resettlement Policy Framework
RAHCO Reli Assets Holding Company
SIA Social Impact Assessment
SUMATRA Surface and Marine Transport Regulatory Authority
TIRP Tanzania Intermodal and Rail Development Project
TRL Tanzania Railways Limited
TRC Tanzania Railways Cooperation
VEO Village Executive Officer
WB World Bank
WEO Ward Executive Officer
6
CHAPTER ONE
Introduction
The World Bank finances the Tanzania Intermodal and Rail Development Project (TIRP). This
project aims at rehabilitating the existing rail network along the Central Corridor between
Dar es Salaam Port and the proposed Dry Port at Isaka. According to the ESIA 2017 Report for
TIRP, the rehabilitation will focus on improving current rail infrastructure and rolling stock to meet
existing and emerging intermodal transport requirements. The project consists of two Packages
whereby Package A covers Dar es Salaam to Kilosa and Package B covers Kilosa to Isaka.
The purpose of the assignment is to develop a plan such that rail rehabilitation from Kilosa to Isaka
is undertaken in compliance with World Bank requirements, in particular, the WB operational
policy (OP 4.12) on involuntary resettlement.
According to this policy, Paragraph 25 states that when a Bank-supported project’s impact is manor
and leads to displacement of fewer than 200 people, an Abbreviated Resettlement Action Plan
(ARAP) must be formulated to take care of the interests of the project affect persons (PAPs). To
this effect, a Consultant was engaged to assist the Government/ TRC (RAHCO) in developing an
Abbreviated Resettlement Action Plan (ARAP) to ensure that people who will be affected by the
project are consulted in order to safeguard their interests during and after project rehabilitation
works. The Right of Way (RoW) for this project as agreed and detailed in the RPF is 7.5 m from
the centre on left and right side of the railway. This ARAP specifically covers the stretch of the
railway from Kilosa to Isaka (Package B), the total area of the corridor under Package B is 20.61
sq km.
This ARAP has been developed based on consultations with Project Affected People, TRC
(RAHCO), and other key stakeholders such as local government leaders and station masters in each
station along the project corridor. In this process three categories of PAPs were identified: farmers,
petty traders and nomadic livestock keepers.
However, it should be noted that with reference to the Resettlement Policy Framework (RPF) the
project corridor is only 7.5 metres left and right from the centre of the railway track and must be
cleared for the Contractor to start work. It should also be noted that all encroachers no matter what
human activity they are undertaking, have no legal claim to the land.
Scope of the Abbreviated Resettlement Action Plan
The scope and level of details in this ARAP include:
Range of potential risks and impacts to which the affected persons may be subjected.
Results of the socio-economic survey in the form of a clear social baseline and relevant cut-
off date(s).
A description of resettlement assistance and livelihood improvement options to be provided.
A description of the procedures for redress of grievances.
Institutional responsibilities for implementing, monitoring and evaluating ARAP.
7
A schedule, budget and sources of funds, which should be agreed upon with the executing
agency.
Principles Governing ARAP
In developing this ARAP, the following principles have been applied.
Transparency: ensure that affected people are consulted and give their demonstrable
acceptance to the ARAP.
Standards: Maintain the standards of the World Bank’s Operational Policy (OP4.12) on
Involuntary Resettlements.
Best Practices: Adherence to world’s best practices regarding consultation and disclosure
of information to the PAPs
Use of cost replacement cost for calculation of all compensation.
Compensation to all PAPs irrespective of possession of title to land.
Implementation of Grievance Redress Mechanism (GRM).
8
CHAPTER TWO
2.1 Study Methodology
Preparation of the ARAP commenced in February 2018. The methodology applied included:
Literature review of relevant documents
Observations
Socio-economic survey of Project Affected Persons
2.2 Number of Project Affected Persons
During the field visit along the project corridor from Kilosa to Isaka in February 2018 where
affected locations are indicated in Figure 2 below on social baseline information of each PAP,
Figure 2: Map showing location of PAPs
GPS were used to identify the coordinates of the location and magnitude of the cultivated land
within the project corridor. A tape measure was used to confirm the 7.5 metre distance (left and
right) from the centre of the rail track. Initially, during the first visit in February, 2018, the TRC
(RAHCO) safeguards specialist and consultant met with only 2 PAPs. Additional individual
discussions between each PAP and social safeguard specialist were conducted in April to ensure
broader engagement of PAPs and made total number of PAPs identified and consulted to be 17.
Most of the discussion was on social and economic information of PAPs and the results are
indicated in Table 1. As these were individual discussions, the summary of issues raised are
included in Annex A in addition to the information about the PAPs reflected in Table 1. All farmers
identified utilized a minimal portion of the project corridor, and crops which are cultivated in these
areas are for subsistence use and not for commercial purposes. The PAPs do not depend on these
plots for their livelihood and the yields were less than one sack of maize or rice, as such, the loss of
9
these land plots will not cause any significant economic impact to the farmers. Ten PAPs have other
bigger farms outside of the project area.
During the site visits it was difficult to identify the exact number of petty traders and livestock
keepers due to the transient nature of their activities. During the field visit traders were not identified
at all but village leaders and station masters gave information that there are petty traders who come
along the project corridor to sell their goods especially when passenger trains pass. The exact
number of petty traders is hard to determine, as their numbers fluctuate based on the seasonality of
various crops for sale, time of the day, schedule of the trains and other factors.
Livestock keepers were observed crossing at different points in the corridor and it was not easy to
meet and have discussion with them as they are always in transit. Different groups of herders come
and go and cross the railroad in various stretches of the railroad. A lot of the herders do not come
from the settlements along the railroad. Identifying every herder poses significant challenge and
may not be representative. Given the above identification challenges of traders and herders, the
petty traders and livestock keepers are treated as a group, rather than as individually impacted
persons, and the mitigation measures are designed accordingly. Communication was made to station
masters and village leaders about what they are supposed to do to inform the traders about the
upcoming civil works and potential impact on the traders and herders. There will also be a
communication campaign in July 2018 which will be conducted by project implementation team
and cover the whole corridor from Kilosa to Isaka. The communication campaign aims to reach all
PAPs as well as the entire communities in the vicinities of the railroad line.
2.3 Survey and Socio-economic Study of Project Affected Persons (PAPs)
The purpose of the Survey and Socio-Economic Study was to describe baseline conditions of PAPs.
It was conducted only with farmers who were identified as being affected by the project.
During interviews, a questionnaire was used to establish the census and carry out a socio-economic
survey. The Census and Socio-Economic Survey were conducted in February 2018 and additionally
in April 2018 for broader engagement of PAPs.
2.4 Cut-off Date for Entitlements
Cut-off dates determine eligibility of persons. They represent the actual date that human economic
activities were recorded during the census survey. For this project, the cut-off date was 18 February
2018 when interviews with affected farmers for Package B were first held. This will be the eligible
deadline to qualify for assistance for this particular phase of the project. Any person who encroaches
in this area after this date will not be entitled to any assistance.
2.5 Study Limitations
This assignment faces some limitations like difficulties in identifying exact numbers and consulting
PAPs such as petty traders and livestock keepers. This is due to transient nature of their activities.
It was also difficult to conduct public consultation meetings with PAPs as they are very scattered,
instead, individual meetings with each farmer were held (see annex A for the summary of the
discussions). Individual consultations were conducted to make sure that all identified PAPs
10
(farmers) were engaged. Additionally, village leaders were consulted and requested to
communicate the message about the project and its impact with their communities. Also, there will
be public consultation, as part of the overall project communication campaign, with all PAPs and
other members of the community during communication campaign which will be held in July 2018.
The main objective of this campaign is to inform communities about the project safety during civil
works and train operations. The communication campaign will also discuss mitigation measures of
the ARAP. Also, the campaign will emphasis on the precautions which the community have to take
so as to be safe during and after constructions.
2.6 Disclosure of the ARAP
This ARAP will be approved by the Government of Tanzania and cleared/endorsed by the World
Bank and disclosed locally to PAPs and stakeholders in a manner and language appropriate to the
area. It will also be disclosed on the World Bank website.
It will be available to the districts, wards and villages located in the project area so that people
comment or seek clarification before implementation takes place.
Members of the public shall be given the opportunity to respond to the ARAP, in writing or verbally
to the relevant District Executive Directors or Ward Executive Officers who will then pass
responses on to TRC (RAHCO).
11
CHAPTER THREE
3.1 Results of Socio-Economic Study along the Project Corridor
The following information was elicited during the socio-economic survey census carried out with
17 interviewed farmers along the corridor for Package B, between Kilosa and Isaka in February
and April 2018 during the ARAP preparations.
3.2 Heads of Households
All 17 household heads interviewed, were male. A typical Tanzanian family is headed by a man,
who often dominates the decision-making and production processes.
3.3 Gender Distribution in Households
The households of 17 PAPs interviewed consist of 55 household members: 30 females and 20
males.
In all households, women engage in agricultural activities more than men. Women seem to have
less voice in their families as they do not make decision even on the farming produce which they
cultivate. Only men can decide what to be done with the farming produce and everything in their
families.
3.4 PAPs Economic Activities
Out of 17 interviewed PAPs only 5 depend on agriculture as their main economic activities while
the remaining 12 are railway workers. PAPs have their main farms outside the project corridor
which will not be touched by the project only portion of land which is in the project corridor will
be affected which is very small portion of land comparing to sizes of farms they own. They own
average of two acres farms outside the corridor. Sizes of affected part of farms is indicated in the
table 1 on social baseline information of PAPs. They are all aware that the land belongs to TRC
(RAHCO) and they are ready to stop cultivating their crops in the corridor. This was revealed during
dialogue with each PAP (see summary of the discussions included in Annex A). They added that
what they harvest from that portion of land in the corridor is very small and is just for consumption
and the source of their income comes from other farms and employment.
All categories of PAPs will be considered by the project, for farmers will be given time to harvest
their seasonal crops and they will be restricted from conducting cultivation activities in the project
corridor after that. These farmers will be encouraged to engage themselves in business
opportunities which will be available in the corridor. During the meetings with the PAPs, farmers
were told about employment opportunities which will be available in the corridor and more details
about these were given during communication campaign in May 2, 2018. As one of the mitigation
measures there will be process of identifying all those who are interested to sell produce in the
corridor and they will be given a special identity card which will give them access to the corridor
to do business in a controlled manner. Also, farmers were advised to take part in different
employment opportunities which will be available during construction for those who are not
employed.
Entitlement Matrix for PAPs is attached in Annex B.
12
Table 1:Social baseline information of interviewed PAPs
ID
Gender
Main
Occupation
Size of
Other Farm
Owned by
the PAP
Marital
Status
Size of
Affected
Farm/
Amount of
Land Lost
(m)
Location
Legal Status
of Land
Lost/Affected
Type of
Crop
Grown
M1 Male Agriculture One Acre Married 41x 2m Kilosa Owned by
TRC
(RAHCO)
Maize
M2 Male Agriculture Two Acres Married 47 x 1.4m Kilosa Owned by
TRC
(RAHCO)
Maize
M3 Male Agriculture Four Acres Married 28x1.4m Kidete -
Godegode
Owned by
TRC
(RAHCO)
Maize
M4 Male Agriculture Four Acres Married 19x1.4m Kidete-
Godegode
Owned by TRC
(RAHCO)
Maize
M5 Male Business man NIL Married 44x1.4m Bahi-
kitinku
Owned by
TRC
(RAHCO)
Rice
M6 Male Railway
worker
NIL Single 360x1.7m Kitinku-
Makutupor
a
Owned by
TRC
(RAHCO)
Rice
M7 Male Railway
worker
Four Acres Married 642x1.7m Kitinku –
Makutupor
a
Owned by
TRC
(RAHCO)
Rice
M8 Male Agriculture Five Acres Married
46 x 2.4m
Uyui
Owned by
TRC
(RAHCO)
Rice 109 x 3.8m
M9 Male Railway
Employee
Two Acres Married 170x2.1m Nzubuka Owned by
TRC
(RAHCO)
Rice
M10 Male Railway
Employee NIL Married
140 x 2.2m
Ipala Owed by TRC
(RAHCO) Rice
1379 x 1.1m
M11 Male Railway
Employee
Two Acres Married 251x2.3m Ipala Owned by
TRC
(RAHCO)
Rice
M12 Male Railway
Employee
NIL Married 158x3.2m Bukene Owned by
Rahco
Rice
M13 Male Railway
Employee
NIL Married 70.4x3.6m Bukene Owned by
TRC
(RAHCO)
Rice
M14 Male Railway
Employee
Three Acres Married 105x2.7m Mahene Owed by TRC
(RAHCO)
Rice
M15 Male Railway
Employee
NIL Married 95x2.7m Mahene Owned by
TRC
(RAHCO)
Rice
M16 Male Railway
Employee
NIL Married 170x2.3m Mahene 0wned by TRC
(RAHCO)
Rice
13
ID
Gender
Main
Occupation
Size of
Other Farm
Owned by
the PAP
Marital
Status
Size of
Affected
Farm/
Amount of
Land Lost
(m)
Location
Legal Status
of Land
Lost/Affected
Type of
Crop
Grown
M17 Male Railway
Employee
Two Acres Married 100x2.3m Ipala Owned by
TRC
(RAHCO)
Rice
3.5 Level of Education among Household members
Household members who were either primary school leavers or still attending primary school
account for 63.6% of all the household members, equivalent to 35 people. Secondary school
leavers and those still in secondary school is 27.4% equals to 15 in number, college level is
5.4% equivalent to 3 people and 3.6% equivalent to 2 people not attended school at all. The
figures reflect mixed of skilled and unskilled labour force, the unskilled labour force supersede
the skilled one, hence, it has implication on employment consideration during project
construction. This means that, in general, majority of PAPs will only be eligible for unskilled
jobs within the project during its implementation.
14
CHAPTER FOUR
4.1 Potential Impacts of the Project on Identified PAPs
Taking into consideration that this Report covers only Package B, of the Dar es Salaam - Isaka
railway line, the following positive and negative impacts were captured. Some of these potential
impacts are direct while others are indirect. This chapter summarises the anticipated railway line
construction on human activities inside the 7.5 meter demarcation.
4.2 Positive Anticipated Impacts
A number of positive impacts are anticipated from the project to the PAPs as well as the entire
community along the corridor. Some of these impacts are on employment opportunities and
efficient ways of transporting farm produce.
4.2.1 Employment opportunities
During project implementation, PAPs can benefit from employment opportunities which
will be available during construction. By taking part in construction activities, members of the
community can secure means to cover their economic needs.
4.2.2 More efficient way of transporting farm produce
Residents may expect a faster and more reliable means of transporting their farm products to other
parts of the country. This will facilitate agribusiness and hence more profit to the farmers.
However, it is not certain that the Railway will decide to engage in such transport.
4.3 Negative Anticipated Impacts
Project activities will not have any significant negative impact on the livelihoods of PAPs. To all
three group of PAPs identified, the impacts can be as follows;
4.3.1 Farmers
All the farmers identified will lose access to the railway that they were using for cultivation of
crops for subsistence (which was anyway an unsafe practice).
4.3.2 Traders
Traders will partially lose access to the railway for business, during the construction and later during
operation. Trade will be carried out in an organized manner to ensure safety of people and train
operation, both during the construction and operation. Trading will be allowed with permission
given from the station masters at set location at the train stations and time frame to coincide with
train stops. Process of identifying traders, who are interested in receiving permits, will start soon
after clearance and disclosure of this ARAP so that petty traders will not take long time to be
accommodated in the corridor. Most of these traders are located at Saranda and Tabora stations. At
the moment there are no trades in other stations but community members will be given chance to
conduct business even in other stations. This impact is very trivial compared to improvements in
their safety proposed under the project. Ability to trade at the stations, rather than along the railway
15
tracks, will keep traders away from dangers of moving trains. After the renovations the trains are
expected to move faster and more regularly than previously. The current train moves at a speed of
35KPH while after rehabilitation it is expected to be 70KPH. This safety enhancement is to ensure
safety of people and train operations. There will be no monetary compensation for the temporary
loss of income during the works, for several reasons. Firstly, it is challenging to identify the traders
due to their transient nature and activities. Secondly, TRC (RAHCO) will expedite the process
certifying all traders to minimize any potential impact. Thirdly, the benefit of safety to traders and
organized business is significant to both the people and the train operations.
4.3.3 Nomadic Livestock Keepers
There will be no loss to nomadic livestock keepers as they do not settle in one place for grazing.
Some access to land which they periodically use to pasture their cattle will be restricted. This on
the other hand works for their good as it will protect them and their cattle from many accidents in
which they are involved from time to time when they graze along the corridor or cross the railway
without any precaution.
Photograph and description of affected farms is attached in Annex C.
CHAPTER FIVE
5.1 Policy and Legal Framework
The Constitution of Tanzania defines the legal context for all aspects of human development for
Tanzanians. Overall, the law ensures that project activities comply with policy requirements.
Relevant policies and laws were reviewed to provide guidance for preparation of this ARAP.
WB OP 4.12 (among others) was used as a base to govern this ARAP.
Reference can be made to the Resettlement Policy Framework (RPF) document of the project for a
detailed analysis of legal framework. This document is available on RAHCO’s website and no
changes have been made to this document. Therefore, all the policies and laws detailed in it remain
relevant to the project and it is also used as a point of reference for implementation of this ARAP.
Analysis of the gap between national laws and World Bank policies is described in the Resettlement
Policy Framework (RPF); a summary table of the gaps is attached in Annex D.
It should be noted that in case of divergence between national laws and World Bank Policy, the
World Bank’s Operational Policy OP/BP 4.12 will apply.
The ARAP will not provide any assistance to PAPs on the land they lose since they do not own land
and they do not have any claims to it. The ARAP allows them to harvest their crops that they
cultivated during the current farming season.
16
CHAPTER SIX
6.1 Impact Mitigation Measures and Implementation Arrangements
Given that identified farmers do not have legal rights for the land and the size of land is very small,
according to the national law and World Bank Policy OP 4.12, they will not be compensated for the
land. They will be allowed to harvest their seasonal crops and be given information about the date
for starting construction so that they do not plant further crops.
Other measures proposed include the following:
6.2 Farmers
All farmers identified during the visit in February will be given time to harvest their crops;
this is a three months period which started from 18 February 2018 and will end in June 2018.
TRC (RAHCO) will provide public notices advising that farming along the corridor must
cease; these notices will be posted at every affected station and village.
A communications campaign will be conducted initially and then periodically.
Farmers will be encouraged to seek employment opportunities which may be available
during construction.
Security operations will be conducted periodically to ensure that the right of way is kept
clear at all times even after completion of the project. This will be done by the safety and
security department.
6.3 Livestock Keepers
The ROW under this project is very narrow (7.5m on both sides from the centre of the
railroad line), livestock keepers will not be allowed to graze within the ROW for their own
safety, safety of the livestock and safety of the train operation.
Public notices/posters will be displayed in every village; these notices will be promoting the
health and safety of people who are grazing animals along the corridor.
Public announcements will be made from motor trolleys along the corridor every month
where everyone will be able to receive announcements about the project and what
precautions should be taken by community members especially farmers who are nomads.
Security operations will be conducted periodically to ensure that the right of way is kept
clear at all times even after completion of the project. This will be done by the safety and
security department.
6.4 Petty Traders
Petty traders will be assisted by being given access to sell their products at each station.
During communication campaign that has started in May 2018 all traders will be notified
on the measures given to them and they will be allowed to register their names so as to be
given IDs to conduct business in the corridor. Additionally, all village leaders of
communities along the rail line have been informed about the project and mitigation
measures. After clearance and disclosure of this ARAP the process of identifying traders,
who are interested in receiving an ID and the right to trade at the stations will follow. Train
schedules will be given to them so that they know specific times to sell their products.
17
Station masters will coordinate this by giving IDs to all identified and registered traders so
as to have controlled movement.
Employment opportunities will be provided for traders along the corridor; they will be
encouraged to apply for work in construction activities as a means of catering for their
economic need provided they have necessary skills.
A communications campaign through posters, public meetings and TV and Radio programs
will be conducted initially and then periodically to ensure health and safety is maintained
during rehabilitation and operation of the railroad. This campaign will cover all villages and
stations along the corridor
Security operations will be conducted periodically to ensure that the right of way is kept
clear at all times even after completion of the project. This will be done by TRC (RAHCO)’s
safety and security department.
6.5 Communications Plan
There will be a Communications Campaign which will be launched in advance of start of
construction work. A TRC (RAHCO) Communications Team will visit every affected line side
community between Kilosa and Isaka, and will describe what’s being done, why, how and when.
Later prior to start of enhanced railway operations, this team will again visit every affected line side
community between Kilosa and Isaka and will describe the new dangers to human and animal life
and how everyone and everything can stay safe. Posters and media advertisements will support
these missions.
At all stages there will be opportunities for dialogue between Communities and the Railway.
Questions will be answered in real time and by correspondence. A hotline in TRC (RAHCO) is
already in operation (toll-free: 0800-110042).
CHAPTER SEVEN
7.1 Institutional Responsibilities and Grievance Redress Mechanism
TRC (RAHCO) is the lead institution in implementing this ARAP. Its responsibilities include:
Overseeing the implementation of impact mitigation measures.
Monitoring and evaluation of implementation of ARAP.
Reporting on ARAP activities and indicators to the World Bank.
Ensuring that the mitigation measures efficiently delivered.
Ensuring that the grievance redress mechanism is efficient.
Clearly demarcating the RoWs of the rail assets.
18
7.2 Other Organizations and Agencies
7.2.1 Civil Works Contractor
The Civil Works Contractor will be responsible for mitigating effects resulting from construction
activities. Construction activities will be monitored closely by TRC (RAHCO) and the Supervision
Consultant to ensure compliance of the temporary mitigating measures.
7.2.2 Local Government Authorities, District Level
Each District Executive Director (DED) is to be consulted as the main party responsible for
overseeing the implementation of the ARAP. The District Community Development Departments
will then collaborate with the Social Development Officer of TRC (RAHCO) in the planning and
implementation of this ARAP.
Ward Level: DED will communicate to the respective Ward Executive Officers (WEO) to provide
the necessary support for the success of ARAP implementation in:
Organising meetings
Communicating with grass root village leaders
Participating in grievance redress whenever it arises
Participating in community engagement meetings
Village Level: Village chairpersons in rural settings and street leaders in urban settings will be
responsible for the application of ARAP through the Village Councils. Their responsibilities
include:
Mobilization and sensitization of PAPs
Providing communication channels for grievances between PAPs and higher authorities
Participating in the monitoring and evaluation of ARAP
Facilitating in the consultation of PAPs
Ensuring that the grievance mechanism is efficient.
7.3 Grievance Redress Mechanism
The proposed ARAP includes a mechanism to ensure that entitlements are effectively transferred to the PAPs and there is proper disclosure of information and consultations with the affected community. However TRC (RAHCO) has an established Grievance Mechanism Committee which responds to people’s queries and addresses all matters pertaining to the project.
7.4 GRM Procedures
The project has established the following channels through which community members and PAPs
can make complaints regarding project activities.
19
a. A dedicated mobile phone line which every PAP is allowed to call and send text
massage. (RAHCO/TRC is on the process of registering the number once is done it will be
announced to the members of community through communication campaigns.)
b. Suggestion boxes located at each station along the corridor PAPS and other members of
community will be informed to put their complaints and suggestions in these boxes
c. Verbal or written complaints to project staff (directly or through project meetings). (If
project stakeholders provide verbal feedback/complaint, project staff will lodge the
complaint on their behalf, and it will be processed through the same channels.
d. Project Grievance Committees
e. Grievance Redress Mechanism Form, PAPs will be informed on how to fill grievance
forms and these forms will be available to every station and villages along the corridor.
Confidentiality and conflict of interest
Complaints will be made anonymously and confidentiality will be ensured in all instances,
including when the person making the complaint is known. For this reason, multiple channels to
make a complaint have been established and conflicts of interested will be avoided.
7.5 GRM Committee
The committee comprises a Project Coordinator, Social Development Officer, Project Engineer, Ward Executive Officer, Station Masters, Gangers and Village Leader from each local village along the ROW.
The same committee is suitable to respond to all grievances which arise from PAPs identified in this ARAP. There will be additional members of committee; these are representative of PAPs from every ward where there are identified PAPs. These PAPs will be in the committee only to respond to issues related to the implementation of this ARAP.
Grievances which are acceptable by this committee are disturbances resulted from project activities
and those which are related to mitigation measures stipulated in this ARAP including destruction
on PAPs crops before harvesting time and when traders are not given access to sell their products
to the project corridor as agreed in this ARAP.
20
CHAPTER EIGHT
8.1 Implementation Schedule
The rehabilitation of the railway line is expected to start at the end of May 2018. Before mobilizing the contractor to site, all human activities being
carried out within 7.5 meters from the center line have to cease and the site cleared. Therefore, some of the ARAP implementation activities must be
implemented as soon as possible. In this regard, an implementation schedule of these activities which synchronize with project implementation has
been prepared:
Table 2:Implementation Schedule of ARAP
S/N
o.
Task
Feb
201
8
Marc
h
2018
Ap
ril
2018
May
2018
Ju
ne
20
18
Ju
ly
2
018
Au
gu
st
2018
Sep
tem
ber
2018
Oct
ob
er
2018
Novem
ber
2018
Dec
emb
er
2018
Jan
uary
201
9
Responsible Agency
1 Completion of draft ARAP
X Consultant
2 Approval of Draft ARAP
X TRC (RAHCO) /
World Bank
3
Training of TRC
(RAHCO) staff and others
in ARAP implementation
X TRC (RAHCO)
4
Communication campaign
to the community
X X
Social Development
Officer/Public
relations
Officer/Project
Engineer
21
S/N
o.
Task
Feb
2018
Marc
h
2018
Ap
ril
2018
May 2018
Ju
ne
208
Ju
ly
2018
Au
gu
st
2018
Sep
tem
ber
2018
Oct
ob
er
2018
Novem
ber
2018
Dec
em
ber
2018
Jan
uary
2019
Responsible Agency
5
Implementation of the
ARAP/ farmers to harvest
their crops
X Project coordination
team
6
Implementation of the
ARAP/ Assistance to petty
traders and herders
X Project coordination
team
7
Performance monitoring
X X Project Coordination
Team
8
External evaluation
(bi-annual for three years
X X Independent Evaluator
22
8.2 Costs and Budget
Since the scale of impact of the project is very small and no monetary compensation will be
provided to the PAPs, no item is to be indicated in the budget. Time of specialists to supervise
and monitor the implementation of ARAP, mitigation measures for all PAPs including petty
traders and nomads will be covered internally by TRC (RAHCO). The budget to operate the
GRM is also built in into the project budget, since the GRM is a comprehensive project-wide
mechanism. The exact number of petty traders is hard to identify thus the budget will be
adjusted on rolling bases reflect on the number of applicants for IDs. Below is a tentative
budget for the proposed mitigation measures and operating of the GRM.
Table 3:Tentative Budget For Mitigation Measures and GRM.
SN DESCRIPTION UNITY RATE QUANTITY AMOUNT
1 Identity cards for petty
trades
Stations $ 1.36 522 $ 70.91
2 Radio programs Quarterly $ 1,136.36 8 $ 9,090.91
3 TV programs Annually $ 2,727.27 2 $ 5,454.55
4 Stakeholders
Engagement
Allowances3
Lumpsum $ 11,363.64 1 $ 11,363.64
5 Security operations Quarterly $ 1,363.64 8 $ 10,909.09
6 Documentaries Annually $ 9,090.91 2 $ 18,181.82
7 Suggestion boxes for
Grievances Redress
Mechanism
stations $ 22.73 524 $ 1,181.82
8 Mobile phone for
Grievance Redress
Mechanism
Piece $ 136.36 1 $ 36.36
9 Facilitation for
Grievance Mechanism
committee meetings
Monthly $ 90.91 24 $ 2,181.82
10 Air Time for
communication
especially on
Grievance Redress
Mechanism
Monthly $ 22.73 245 $ 545.45
Total $ 59,116.36
2 This is an indicative number. The actual number of ID cards issued to the petty traders will depend on the
demand. 3 This means allowances for government leaders who works with the project team during field visits. 4 Total number of stations is 52, suggestion boxes will be fixed one in each station. 5 Air time will be provided monthly,24 means total number of months in 2 years.
23
CHAPTER NINE
9.1 Monitoring and Evaluation
Internal and external monitoring are proposed for the project as put forth in the RPF prepared
for this project. Internal monitoring of ARAP implementation will be the responsibility of the
Social Development Officer who will be responsible for monitoring and evaluation of ARAP
activities, as well as performance of the GRM. The officer will prepare simple formats for
monitoring social plans. These formats will be duly filled every month by railway station staff
and sent to the Social Development Officer. Regular reports on implementation of the ARAP
and performance of the GRM will be submitted to the WB. Once the ARAP is implemented in
full, a Resettlement Implementation Report will be prepared by TRC (RAHCO) and submitted
to the World Bank.
For mid-term and post-activity, external monitoring and evaluation will be done by a
consultant or outsourced to a qualified practitioner as per the project design outlined in the
Project Appraisal Document.
Since the scale of impact of the project activities on resettlement is small and the PAPs do not
meet the criteria for compensations, there is no monetary compensation. Monitoring will be
done by ensuring that identified farmers are able to harvest their crops and properly informed
not to cultivate again. There are no vulnerable groups and no additional assistance and
monitoring of provision of such assistance is needed under this ARAP. The Grievance Redress
Mechanism will continue working throughout the project implementation.
Employment process by the contractor will also be monitored to make sure that all eligible
PAPs are considered for employment opportunities.
There will be monitoring on how petty traders and nomads are handled during and after
construction. This will be in terms of access given to them to conduct their activities and their
right to be given information and give their feedback. Also, the safety of the areas allocated for
them to conduct their activities will be monitored.
9.2 Evaluation
There will be a mid-term and a post-activity evaluation of the implementation of the ARAP.
On both occasions, a comprehensive socio-economic survey of the PAPs will be conducted.
The results of these surveys will be compared to baseline information obtained from the census
survey to gauge the effectiveness of the rehabilitation process over time. Prior to the beginning
of the civil works, the review will verify among things:
• Clearance of the ROW
• Quality of interaction between TRC (RAHCO) and PAPs.
• Effectiveness of the mitigation measures, include the communication campaign
• Effectiveness of the GRM
24
ANNEXES
Annex A; Summary of issues raise during discussions with Each PAP.
Field visit to identify PAPs were conducted in February and April 2018.First visit which was
on 19-25 February, Social Specialist together with the consultant identified Farms within the
corridor but they were able to meet only two PAPs. The second visit were conducted on 3-11
April 2018 where social specialist met 15 PAPs individually and make total of 17 PAPs.
Issues raised during individual discussions with each PAP were as follows;
Social baseline information: In the discussion PAPs explained about their
marital status, family composition and their education status. Information about
social baseline information can be referred in table 1.
Economic activities of PAPs: Issues like occupation of PAPs and main
economic activities were discussed, PAPs admitted to have other farms outside
the project corridor and others are employed in TRC.
PAPS Expectations towards the project: PAPs expects to boost their
economic status through transportation of their farm products after
rehabilitation of railways. During the discussion PAPs revealed that they are
ready to contribute their efforts towards success of the project. They are also
ready to stop human activities within the project corridor so as to allow
contractor to perform works in a conducive manner.
Land ownership: Issues about ownership of the portion of land by which they
are cultivating were discussed and all PAPs confessed that they are using
Railway land for cultivation because the land was available at their disposal but
they understand that the land does not belong to them. They asked
TRC/RAHCO to give them grace period to harvest their crops which were in
the field and promised to stop cultivation in the corridor.
Bushes around the corridor: In the project corridor especially areas where
there is no any human activities, there are bushes where criminals uses as their
hides. PAPs revealed some of those areas and they asked TRC/RAHCO to make
sure that those bushes are cleared for the safety of the communities and railways
properties.
Demarcation of TRC/RAHCO land: PAPS asked TRC to put bacons on their
territory to avoid future encroachments. They said that in the right of way there
are areas where there is no clear demarcation of TRC (RAHCO) land and
community land.
25
Annex B: Entitlement Matrix
Persons Affected by
the Project
Type of Impact Entitlement
Farmers Loss of access to
Railway land for
cultivation
Farmers will be given grace
period to harvest their crops
which are currently in the
corridor.
They will be given priority to take
part in construction activities for
those who will be interested and
eligible.
Most farmers who are also doing
business as their main economic
activities will be given access to
sell their products within the
corridor by guidance from the
station masters.
Traders Partially loss of
access to the railway
for their business
They will be given access to sell
their products in each station
before, during and after
construction in a controlled
manner so that they conduct their
business in safely manner.
They will be given priority for
employment opportunities in the
corridor during construction by if
found eligible.
Nomads Nomads will have
nothing to lose as
they do not have
specific places where
they use to graze their
castles. Only access
to the railway land
will be restricted.
This will be with the
aim of protecting
them from accidents.
Village leaders will allocate
grazing areas to Nomads outside
the corridor where they can graze
their cattle.
There will be control to ensure
that they are outside the corridor
for their own safety.
26
Annex C: Photography and Size of Affected Farms.
PAPS VERIFICATION FORMS
Form No.1
1.0 Chainage (Km) 308.2
2.0 GPS Coordinates
3.0 Location Mzaganza
4.0 Section Munisagala – Mzaganza
5.0 Inspection Date 19-02-2018
6.0 Property Description
Maize farm portion extending to TIRP corridor
6.1 Size 41m × 2m
6.2 Usage Farming
6.3 Temporary/ Permanent Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names Y.B.
27
Form No.2
1.0 Chainage (Km) 308.2
2.0 GPS Coordinates
3.0 Location Mzaganza
4.0 Section Munisagala – Mzaganza
5.0 Inspection Date 19-02-2018
6.0 Property Description
Maize farm portion extending to TIRP corridor
6.1 Size 68m × 2.4m
6.2 Usage Farming
6.3 Temporary/ Permanent Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names
J.M.
Form No.3
28
1.0
Chainage (Km) 324.88
2.0 GPS Coordinates
E246426.5 N9264066.2
3.0
Location Kidete
4.0 Section Kidete – Godegode
5.0 Inspection Date 19-02-2018
6.0 Property Description
Maize farm portion extending to TIRP corridor
6.1 Size
47m × 1.4m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names A.K (19m x 1.4m)
S.A (28m x 1.4m)
29
Form No.4
1.0
Chainage (Km) 423
2.0 GPS Coordinates
3.0
Location
4.0 Section Bahi – Kitinku
5.0 Inspection Date 19-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
44m × 1.4m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names
R. J
30
Form No.5
1.0
Chainage (Km) 437.1
2.0 GPS Coordinates
3.0
Location Gang 33
4.0 Section Kintinku – Makutupora
5.0 Inspection Date 20-02-2018
6.0 Property Description
Maize farm portion extending to TIRP corridor
6.1 Size
1002m × 1.7m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names M.Y (360m X 1.7m)
K.N (642m x 1.7m)
31
Form No.6
1.0
Chainage (Km) 10.4
2.0 GPS Coordinates
E482295.5 N9454696.2
3.0
Location
4.0 Section Tabora – Kakola
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
46m × 2.4m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names
S.B
32
Form No.7
1.0
Chainage (Km) 10.9
2.0 GPS Coordinates
E482313.8 N9455361.4
3.0
Location
4.0 Section Tabora – Kakola
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
109m × 3.8m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names S. B
33
Form No.8
1.0
Chainage (Km) 35
2.0 GPS Coordinates
E485282.9 N9484640.9
3.0
Location
4.0 Section Kakola – Nzubuka
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
170m × 2.1m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names
E.C
34
Form No.9
1.0
Chainage (Km) 41
2.0 GPS Coordinates
E485282.9 N9484640.9
3.0
Location
4.0 Section Nzubuka – Ipala
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
140m × 2.2m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names
D.S
35
Form No.10
1.0
Chainage (Km) 41
2.0 GPS Coordinates
E485288.8 N9484621.3
3.0
Location
4.0 Section Nzubuka – Ipala
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
1379m × 1.1m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names
D.S
36
Form No.11
1.0
Chainage (Km) 60.7
2.0 GPS Coordinates
E487101.1 N9502916.0
3.0
Location
4.0 Section Ipala – Bukene
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
251m × 2.3m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names
M.J
37
Form No.11
1.0
Chainage (Km) 69.6
2.0 GPS Coordinates
E488153.8 N9512252.4
3.0
Location
4.0 Section Ipala – Bukene
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
158m × 3.2m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names
O.M
38
Form No.12
1.0
Chainage (Km) 69.8
2.0 GPS Coordinates
E488160.4 N9512210.4
3.0
Location
4.0 Section Ipala – Bukene
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
70.4m × 3.6m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names
A.S
39
Form No.13
1.0
Chainage (Km) 93
2.0 GPS Coordinates
E486813.9 N9534888.6
3.0
Location
4.0 Section Bukene – Mahene
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
200m × 2.7m
6.2 Usage Farming
6.3 Temporary/ Permanent Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names M.H (105m x 2.7m)
Y.M (95m x 2.7m)
40
Form No.14
1.0
Chainage (Km) 105.65
2.0 GPS Coordinates E485544.9 N9548186.5
3.0
Location
4.0 Section Bukene – Mahene
5.0 Inspection Date 21-02-2018
6.0 Property Description
Rice farm portion extending to TIRP corridor
6.1 Size
270m × 2.3m
6.2 Usage Farming
6.3 Temporary/ Permanent
Temporary
7.0 Sketch Photograph
8.0 Encroachers’ Names O.M (170m X 2.3m)
M.K (100m X 2.3m)
Annex D: Summary Table of the Gaps between WB Policies and Tanzania Laws
Types of affected
Tanzanian Law World Bank OP 4.12 Comparison/Gaps Mitigation Measures
Lend
Tenant
s/Squatte rs
Tanzanian law does not recognize
tenants as being entitled to
compensation
PAPs are entitled to some form of
compensation whatever the
legal/illegal recognition of their
occupancy
WB OP 4.12 recognizes a wider
spectrum of PAPs. The
Tanzania spectrum is limited to
those who can prove proprietary
rights. It does not include
tenants
Under the project the WB
categorization of PAPs will be
used and tenants will be
recognized as PAPs.
Squatters may be paid
compensation on the whims of the
government.
In some cases however they are not
paid. This include those who
construct on road reserves
Squatters may fit under category (c)
above and are provided resettlement
assistance in lieu of compensation
for the land they occupy as well as
other relocation assistance.
WB OP 4.12 recognizes those
without recognizable legal right
or claim to land they occupy,
therefore could include
squatters among the PAPs who
are entitled to resettlement
assistance in lieu of the land
they occupy, as well as other
assistance.
This is different from the Tanzanian situation where such people are not entitled to any assistance
Under the project squatters
will be recognized under OP
4.12 and compensated for lost
assets.
Land Users Tanzania law on compulsory
acquisition and compensation is
limited to those who can prove de
jure or de facto land ownership.
Users are not covered
WB OP 4.12 includes displaced
persons who have no recognizable
legal right or claim to the land they
are occupying
Under the project OP 4.12 will
be applied to identify land
users.
Types of affected
Tanzanian Law World Bank OP 4.12 Comparison/Gaps Mitigation Measures
Owners of non-permanent Owners of Buildings
Tanzanian law makes no differentiation between owners of permanent and non-permanent buildings. As long as ownership can be proved compensation is payable.
Determination of compensation is based on the market value of the property. In practice though, the depreciated replacement cost approach is used, meaning that PAPs do not get the full replacement cost of the lost assets.
Under the WB OP 4.12 permanent and non-permanent buildings need to be compensated. Where however, the displaced
persons have no recognizable legal
rights they are to be provided with
resettlement assistance in lieu of
compensation for the land they
occupy, as well as other assistance. Cash compensation levels should
be sufficient to replace the lost land and other assets at full replacement cost in local markets.
The gap between Tanzania and WB OP 4.12 is about eligibility, which is hinged upon formal or informal ownership.
While, in Tanzania, compensation is based on market value, determined using the depreciated replacement cost approach for developments on land, WB OP 4.12 requires that compensation should be sufficient to replace the lost land and other assets at full replacement cost.
Under the project the full replacement cost of structures as defined under OP 4.12 will be applied.
Timing of
compensation
payments
Tanzanian law requires that
compensation be full, fair and
prompt. Prompt means it should be
paid within six months, failure to
do which attracts an interest rate
equivalent to the average rate
offered by commercial banks on
fixed deposits.
Legally, compensation for the
acquired land does not have to be
paid before possession can be
taken, but in current practice it is
usually paid before existing
occupiers are displaced.
WB OP 4.12 displaced persons are
provided prompt and effective
compensation at full replacement
cost for losses of assets directly
attributable to the project before
construction starts.
In terms of timing, both
Tanzanian laws and WB OP
4.12 require that compensation
be paid promptly.
This however, rarely happens in
practice as can be testified from
may projects that have involved
large scale land acquisition.
The project will ensure that the
compensations are paid in
timely manner.
Types of affected
Tanzanian Law World Bank OP 4.12 Comparison/Gaps Mitigation Measures
Calculation of compensation and valuation
According to the Land
Assessment of the value of Land
for Compensation) Regulations,
2001, as well as the Village Land
Regulations, 2001, compensation
for loss of any interest inland
shall include the value of
unexhausted improvements,
disturbance allowance, transport
allowance, accommodation
allowance, and loss of profits.
The basis for assessment any land
and unexhausted improvement for
purposes of compensation is the
market value of such land.
The market value is arrived at by
the use of comparative method
evidenced by actual recent sales
of similar properties; or by the use
of the income approach, or
replacement cost method, where
the property is of special nature
and not saleable.
In practice, with land an attempt is made to establish market value from
WB OP 4.12 requires that the
displaced persons be provided with
prompt and effective compensation
at full replacement cost for losses of
assets attributable direct to the
project.
Replacement cost is the method of
valuation of assets that helps
determine the amount sufficient to
replace lost assets and cover
transaction costs. Depreciation is not
to be taken into account when
applying this method.
For losses that cannot easily be valued or compensated in monetary terms (e.g. access to public services, customers and suppliers, or to fishing, grazing or forest areas) attempts are made to establish access to equivalent and culturally acceptable resources and earning opportunities.
Tanzania law provides for the
calculation of compensation on
the basis of the market value of
the lost land and unexhausted
improvements, plus a
disturbance, accommodation,
and accommodation allowance,
and loss of profits where
applicable.
Since depreciation is applied, the amount paid does not in most cases amount to that required to replace the lost assets. Besides, other types of assets (besides land) are not taken into consideration.
Under the project the full replacement cost of structures as defined under OP 4.12 will be applied. No deduction for depreciation or for salvage materials will be made.
Types of affected
Tanzanian Law World Bank OP 4.12 Comparison/Gaps Mitigation Measures
recent sales, but these are usually not transparent. As for unexhausted improvements in terms of buildings and other civil infrastructure, the depreciated replacement cost approach is used
Relocation and
Resettlement
Tanzanian laws do not provide for relocation and resettlement. However, there are a few cases where the government has provided both compensation and alternative land, but this has been done at its discretion. In general however, the government feels that it has discharged its duty once compensation is paid, and it is up to the displaced persons to resettle and re-establish themselves elsewhere.
OP 4.12 stipulate that where project impacts include physical relocation, measures should be taken to ensure that the displaced persons are: (i) provided with assistance (such as moving allowance) during relocation; and (ii) provided with residential housing, or housing sites, or, as required, agricultural sites for which a combination of productive potential, locational advantages and other factors is at least equivalent to the advantages lost.
Tanzanian law provides for transport allowance for 12 tons of luggage for up to 12 kilometres from the acquired land, provided the displaced person was living on that land. In lieu of housing accommodation allowance is made in the form of rent for 36 months.
Occasionally, in a discretionary manner alternative land is awarded.
Allowances under Tanzania laws will be provided
Completion of resettlement and compensation
The government can, under the law, take possession of the acquired land at the end of the notice to acquire period, before paying compensation.
Current practice however is such that possession is usually after the payment of compensation
WB OP 4.12 stipulates that it is necessary to ensure that displacement or restriction to access does not take place before necessary measures for resettlement are in place. In particular, taking of land and related assets may take place only after compensation has
The Land Acquisition Act,
1967, allows the government to
take possession of the acquired
land before paying
compensation.
Current practice endeavors to pay compensation before taking possession of the land.
All compensation will be paid before the commencement of the civil works
Types of affected Persons/Lost Assets
Tanzanian Law World Bank OP 4.12 Comparison/Gaps Mitigation Measures
to vacate the land, which is usually as soon as possible
been paid, and where applicable, resettlement sites and moving allowance have been provided to the displaced persons.
Livelihood restoration and assistance
There are no legal provisions requiring the government to restore livelihood or to provide assistance towards the restoration of such livelihoods.
Indeed, compensation is not payable in the case of restrictions to access to areas of livelihood opportunities.
Moreover there are no provisions that require the
WB OP 4.12 provides that the resettlement plan or policy include measures to ensure that the displaced persons are (i) offered support after displacement for a transitional period, based on a reasonable estimate of the time likely to be needed to restore their livelihood and standard of living; and, (ii) provided with development assistance in addition to compensation measures, such as land preparation, credit facilities, training or job opportunities.
There are no transitional measures provided for under Tanzanian law and practice; nor are there provisions for compensation as a result of restrictions to access to livelihood. The Tanzanian law does not make provisions requiring the government to pay special attention to vulnerable groups in the administration of compensation
The project will ensure that livelihoods of PAPs will be restored to comply with Banks requirements.
Consultation and disclosure
There scanty provisions related to consultation and disclosure in Tanzanian law.
The notice, under the Land Acquisition Act, informs land owners about the President’s need to acquire their land, and
WB OP 4.12 requires that displaced persons are (i) informed about their options and rights pertaining to resettlement; and, (ii) consulted on, offered choices among, and provided with technically and economically feasible resettlement alternatives.
The provisions in WB OP 4.12 requiring consultation and disclosure have no equivalent in Tanzanian law and practice
The PAPs will be consulted and the relevant documents disclosed per the OP 4.12.
Types of affected Persons/Lost Assets
Tanzanian Law World Bank OP 4.12 Comparison/Gaps Mitigation Measures
requiring that their land be valued, and giving their own opinion as to what their assets are worth.
Since resettlement is not provided for legally, there are no provisions about informing the displaced persons about their options and rights; nor are they offered choice among feasible resettlement alternatives.
Grievance mechanism and dispute resolution
Under s. 13 of the Land Acquisition Act, where there is a dispute or disagreement relating to any of .the following matters: (a) the amount of compensation; (b) the right to acquire the land; (c) the identity of persons entitled to compensation; (d) the application of section 12 to the land;
WB OP 4r.12 provides that displaced persons and their communities, and any host communities receiving them, are provided with timely and relevant information, consulted on resettlement options, and offered opportunities to participate in planning implementing and monitoring resettlement. Appropriate and accessible grievance mechanisms must be established for these groups
The law in Tanzania does not provide for the establishment of grievance resolution mechanisms specific to particular resettlement cases.
The project will have a Grievance Redress Mechanism throughout the life cycle of the project.
Types of affected
Persons/Lost Assets
Tanzanian Law World Bank OP 4.12 Comparison/Gaps Mitigation Measures
(e) any right privilege or liability conferred or imposed by this Act;
(f) the apportionment of compensation between the persons entitled to the same and such dispute or disagreement is not settled by the parties concerned within six weeks from the date of the publication of notice that the land is required for a public purpose the Minister or any person holding or claiming any interest in the land may institute a suit in
(g) the High Court of Tanzania for the determination of the dispute.
In practice the government
tries to resolve grievances
through public meetings of
the affected persons.
Annex E: Sample of Grievance Redress Mechanism form.
Name (Filer of Complaint): ___________________________________
ID Number: __________________________________ (PAPs ID number)
Contact Information: ___________________________________ (Village; mobile phone)
Nature of Grievance or Complaint:
Date Individuals Contacted Summary of Discussion
Signature _______________________ Date: ____________
Signed (Filer of Complaint): _____________________________________
Name of Person Filing Complaint: ___________________________ (if different from Filer)
Position or Relationship to Filer: __________________________________
Review/Resolution
Date of Conciliation Session: _____________________________________
Was Filer Present? : Yes No
Was field verification of complaint conducted? Yes, No
Findings of field investigation:
Summary of Conciliation Session Discussion:
Issues
Was agreement reached on the issues? Yes, No If
agreement was reached, detail the agreement below:
If agreement was not reached, specify the points of disagreement below:
Signed (Conciliator): ___________________________ Signed (Filer):
Signed: __________________________
Independent Observer,
Date: