study on dobrotvirska coal-fired power extension project ... · pdf filestudy on dobrotvirska...

210
Study on Economic Partnership Projects in Developing Countries in FY2013 Study on Dobrotvirska Coal-Fired Power Extension Project in Dobrotvirska, Ukraine Final Report February 2014 Prepared for: The Ministry of Economy, Trade and Industry Ernst & Young ShinNihon LLC Japan External Trade Organization Prepared by: ITOCHU Corporation Tokyo Electric Power Services Co., Ltd.

Upload: dangdat

Post on 14-Mar-2018

230 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Study on Economic Partnership Projects in Developing Countries in FY2013

Study on Dobrotvirska Coal-Fired Power Extension Project in

Dobrotvirska, Ukraine

Final Report

February 2014

Prepared for:

The Ministry of Economy, Trade and Industry Ernst & Young ShinNihon LLC

Japan External Trade Organization

Prepared by: ITOCHU Corporation

Tokyo Electric Power Services Co., Ltd.

Page 2: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Reproduction Prohibited

Page 3: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Preface

This report summarizes the study being prepared for Study on Economic Partnership Projects in Developing

Countries in FY 2013 commissioned by the Ministry of Economy, Trade and Industry.

This Study, “Study on Dobrovirska Coal-Fired Power Extension Project in Dobrotvirska, Ukraine”, was made in

order to examine the viability of the project to construct 600MW Ultra-Supercritical Coal-Fired Thermal Power

Plant at the existing power plants site with the cost of United State Dollar 870 million, for the purpose of

efficiency improvement and reducing emission of Sulfur Oxide, Nitrogen Oxide and dust.

We hope that the report will be helpful for the realization of the project and be of reference to all the members

concerned.

February 2014

ITOCHU Corporation

Tokyo Electric Services Co., Ltd.

Page 4: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Project Site Map

Source: prepared by the Study team based on Google Map

Page 5: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

List of Abbreviation

Abbreviation Full Name

B/C Benefit Cost Ratio

BOP Balance of Plant

CCS Carbon Dioxide Capture and Storage

CDM Clean Development Mechanism

CFB Circulation Fluidaized Bed

CFD Contract for Difference

CHPP Combined Heat and Power Plant

CIS Commonwealth of Independent States

CO2 Carbon Dioxide

COD Commercial Operation Date

CPM Capacity Payment Mechanism

℃ Degree Celsius

DBJ Development Bank of Japan, Inc.

Dob TPP Dobrotvirska Thermal Power Plant

DTEK Donbass Fuel-Energy Company

EBITDA Earnings Before Interest, Taxes, Depreciation, and Amortization

EBRD European Bank for Reconstruction and Development

EC European Comission

EcoNet Ecological Network

ECU Energy Company of Ukraine

EFF Extended Fund Facility

EHS Environmental, Health and Safety

EIA Environmental Impact Assessment

EIB European Investment Bank

EIRR Economic Internal Rate of Return

ENTSO-E European Network of Transmission System Operators for Electricity

EOJ Embassy of Japan

EPC Engineering, Procurement and Construction

ESIA Environmental Social Impact Assessment

ESP Electrostatic Precipitator

EU European Union

EUR Euro

FD Forced Draft

FGD Flue-gas Desulphurization

FIRR Financial Internal Rate of Return

FIT Feed in Tariff

Page 6: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

F/S Feasibility Study

FSA Fuel Supply Agreement

g Gram

GDP Gross Domestic Production

GFATM The Global Fund to Fight AIDS, Tuberculosis and Malaria

GIS Green Investment Scheme

GW Giga Watt (1GW = 1,000,000. kilo Watt)

GWh Giga Watt hour (1GWh = 1,000,000.kilo Watt hour)

ha Hectare (1ha = 100a = 10,000m2)

HP High Pressure

Hydromet State Hydro meteorological Service

I&C Instrumentation and Control

IBRD International Bank for Reconstruction and Development

IDC Interest during the Construction

IDF Induced Draft Fan

IMF International Monetary Fund

IP Intermediate Pressure

IPP Independent Power Producer

JBIC Japan Bank for International Cooperation

JETRO Japan External Trade Organization

JICA Japan International Cooperation Agency

JOGMEC Japan Oil, Gas and Metals National Corporation

JPY Japanese Yen

km kilo meter (1km = 1,000 meter)

km2 square kilo meter (1km2 = 1,000,000 m2)

kt kilo ton

kV kilo Voltage (1kV = 1,000 V)

kW kilo Watt (1kW = 1,000W)

kWh kilo Watt hour (1kWh = 1,000Wh)

LHV Lower Heating Value

LP Low Pressure

m Meter

m3 cubic meter

MAC Maximum Allowable Concentration

mm Millimeter (1mm = 1/1,000mt)

MECI Ministry of Energy and Coal Industry

MENR Ministry of Environment and Natural Resources

MEP Ministry of Environmental Protection

Page 7: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

METI Ministry of Economy, Trade and Industry

mm Millimeter

MPa Mega Pascal

MW Mega Watt (1MW = 1,000,000 Watt)

MWh Mega Watt hour (1MWh = 1,000,000 Watt hour)

NATO North Atlantic Treaty Organization

NEDO New Energy and Industrial Technology Development Organization

NERC National Electricity Regulatory Commission

NEXI Nippon Export and Investment Insurance

NIS New Independent States

NOx Nitrogen Oxides

NPV Net Present Value

NTP Notice to Proceed

ODA Official Development Assistance

OECD Organization for Economic Co-operation and Development

O&M Operation and Maintenance

PM Particle Matter

PPA Power Purchase Agreement

RUB Russian Ruble

SC Super Critical

SCM System Capital Management

SCR Selective Catalytic Reduction

SDR Special Drawing Rights

SEE State Ecological Enterprises

SO2 Sulfur Dioxide

SOx Sulfur Oxides

S/S Sub-station

t Ton

T/L Transmission Line

TPP(s) Thermal Power Plant(s)

TSO Transmission System Operator

TWh Tera Watt hour

UAH hryvnia

UK United Kingdom

UN United Nations

USA United States of America

USC Ultra-Super Critical

US$ United States dollar

Page 8: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

V Voltage

VAT Value Added Tax

WB World Bank

WEM Wholesale Electricity Market

WTO World Trade Organization

Page 9: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Table of Contents

Preface

Project Site Map

List of Abbreviations

Table of Contents

Executive Summary

(1) Background and Necessity of the Project ················································································ S-1

1) Background of the Project ······························································································· S-1

2) Necessity of the Project ·································································································· S-1

(2) Basic Policy of Project Scope Determination ··········································································· S-2

1) Basic Policy of Project Scope Determination ········································································· S-2

2) Conceptual Design and the applicable Specification································································· S-2

(3) Overview of the Project Plan ······························································································ S-3

1) Project Scope ·············································································································· S-3

2) Project Cost Estimation ·································································································· S-5

3) Outline of Preliminary Financial and Economic Evaluation ························································ S-7

4) Evaluation of Environmental and Social Impacts ···································································· S-9

(4) Planned Project Schedule ································································································· S-11

(5) Feasibility of the Project Implementation ·············································································· S-12

(6) Advance on the Technical Aspect of Japanese Companies ·························································· S-13

(7) Map of the Project Area in the Country ················································································· S-14

Chapter 1 Overview of the Host Country and Sector

(1) Economic and Fiscal Situation in Ukraine ·············································································· 1-1

1) General Information ······································································································ 1-1

a) Geography and Climate ······························································································· 1-1

b) Brief History of Ukraine ······························································································ 1-3

c) Domestic Affairs ······································································································ 1-4

d) Foreign Relations ······································································································ 1-5

e) Social Circumstances ·································································································· 1-5

2) Economic and Fiscal Conditions ························································································ 1-7

a) Economic Overview ··································································································· 1-7

b) Brief Economic History ······························································································· 1-8

c) Issues related to Supply of Natural Gas and Crude Oil from Russia ··········································· 1-10

d) The Relation with IMF ······························································································· 1-11

e) External Debt Problems ······························································································ 1-12

f) The Trend of Trade and Investment ················································································ 1-12

Page 10: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

g) The Prime Industries and their Challenges ········································································ 1-15

3) Economic Assistance ···································································································· 1-19

(2) Overview of the Power Sector ·························································································· 1-20

1) Power Sector in Ukraine ································································································ 1-20

2) Overview of Thermal Power Generation Sector ····································································· 1-34

(3) Situation in the Target Area ······························································································ 1-40

Chapter 2 Study Methodology

(1) Content of the Study ········································································································ 2-1

1) Outline of the Study ······································································································ 2-1

2) Target Fields ··············································································································· 2-2

(2) Method of the Study and Team Members ··············································································· 2-3

1) Method of the Study ······································································································ 2-3

2) Team Member and Organization ······················································································· 2-4

3) Supporting Organization in Ukraine ··················································································· 2-4

(3) Study Schedule ·············································································································· 2-5

1) The 1st Mission ·········································································································· 2-5

2) The 2nd Mission ·········································································································· 2-8

3) The 3rd Mission ·········································································································· 2-11

4) The 4th Mission ·········································································································· 2-12

5) The 5th Mission ·········································································································· 2-13

6) Persons Interviewed during the Study················································································· 2-14

Chapter 3 Justification, Objectives and Technical Feasibility of the Project

(1) Background and Necessity of the Project ················································································ 3-1

1) Scope of the Project ······································································································· 3-1

2) Analysis of the Present Situation and Future Forecast ······························································· 3-3

3) Effect caused by the Project Implementation ········································································· 3-5

4) Comparison with other Options ························································································· 3-5

a) Alternative 1: Natural Gas-fired Power Plants ····································································· 3-5

b) Alternative 2: Coal-fired Power Plants (Sub-critical type) ······················································· 3-6

c) Alternative 3: Imported Capacity to be increased (No new power plant) ······································ 3-6

d) Alternative 4: Renewable Energy ···················································································· 3-6

(2) Efficiency and Rationalization of Energy Usage ······································································· 3-8

(3) Various Types of Studies required for the Decision of Project Scope ··············································· 3-9

1) Demand Forecast ·········································································································· 3-9

2) Necessary Analysis of Problems for the Appraisal and Determination of Project Scope ···················· 3-9

a) Technical Aspects ······································································································ 3-9

b) Environmental Aspects ······························································································· 3-10

c) Financial and Economic Aspects ··················································································· 3-11

Page 11: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

d) Project Development Aspects ······················································································· 3-12

3) Study of Engineering Practice ·························································································· 3-13

(4) Overview of the Project Plan ····························································································· 3-14

1) Basic Policy of Project Scope Determination ········································································ 3-14

a) Project Scope and Study of the Technical Aspects ······························································· 3-14

b) Environmental and Social Considerations ········································································· 3-14

c) Financial and Economic Analysis ·················································································· 3-14

2) Conceptual Design and the Applicable Specification ······························································· 3-14

a) Boiler and Auxiliaries ································································································ 3-15

b) Turbine ················································································································· 3-18

c) Steam Turbine Auxiliary Machine ·················································································· 3-19

d) Generator ··············································································································· 3-21

e) Generator Auxiliary Machines ······················································································ 3-22

f) Instrument and Control System ······················································································ 3-23

g) Air Quality Control System-AQCS ················································································ 3-26

3) Overview of the proposed Project ····················································································· 3-28

4) Solutions for the proposed Technologies and Systems Adoption ················································· 3-29

Chapter 4 Evaluation of Environmental and Social Impacts

(1) Analysis of the Current Status of the Environmental and Social Aspects ·········································· 4-1

1) Location of the Project Site ······························································································ 4-1

2) Natural Environment ····································································································· 4-2

a) Meteorology ············································································································ 4-2

b) Geography··············································································································· 4-3

c) Rivers ···················································································································· 4-3

d) Ecosystem ··············································································································· 4-3

3) Environmental Pollution ································································································· 4-6

a) Air Quality ·············································································································· 4-6

b) Water Quality ··········································································································· 4-6

c) Noise ····················································································································· 4-7

d) Waste ···················································································································· 4-7

4) Social Environment ······································································································· 4-8

a) Land Use ················································································································ 4-8

b) Social Infrastructure ··································································································· 4-8

c) Traffic ···················································································································· 4-8

(2) Environment Improvement Effects by Project Implementation ······················································ 4-9

1) Environmental Mitigation Measures for Air Quality ································································ 4-9

2) Atmospheric Diffusion Estimation of Air Pollutants ······························································· 4-10

a) Calculation Formula ·································································································· 4-10

b) Calculation Conditions ······························································································· 4-11

Page 12: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

c) Meteorological Conditions ··························································································· 4-11

d) Exhaust Emission Conditions ······················································································· 4-12

e) Calculation Results ···································································································· 4-13

(3) Environmental and Social Impacts of the Project Implementation ················································· 4-27

1) JICA Guidelines ·········································································································· 4-27

2) Review Results of Environmental and Social Consideration ······················································ 4-27

(4) Overview of the Laws and Regulations concerning Environmental-Social Considerations of

the Host Country and the Measures needed for Clearing ···························································· 4-34

1) Environmental Administration in Ukraine ··········································································· 4-34

2) Environmental Laws and Regulations in Ukraine ··································································· 4-35

a) Environmental Protection Law ······················································································ 4-35

b) Law on the Protection of Atmospheric Air ········································································ 4-35

c) Water Quality Regulations ··························································································· 4-37

d) Noise ···················································································································· 4-38

e) Natural Environmental Protection ·················································································· 4-38

f) Hazardous Materials and Waste Management ···································································· 4-39

3) Outline of the EIA of the Host Country needed for the Project Implementation

and the Measures to be taken ·························································································· 4-39

a) EIA in Ukraine ········································································································ 4-39

b) Measures to be taken for the EIA ··················································································· 4-40

(5) The Requirement for the Host Country (Project Proponent and other related Organizations)

for the Implementation of the Project ··················································································· 4-42

Chapter 5 Financial and Economic Evaluation

(1) Project Cost Estimation ···································································································· 5-1

1) Construction Cost (Engineering, Procurement and Construction) ················································· 5-1

2) Initial Investment Cost ··································································································· 5-1

3) Running Cost ·············································································································· 5-2

(2) Preliminaly Financial and Economic Evaluation ······································································· 5-3

1) Financial Internal Rate of Return (FIRR) ·············································································· 5-3

2) Economic Internal Rate of return (EIRR) ············································································· 5-5

3) Sensibility of EIRR ······································································································· 5-8

a) Selling Price ············································································································· 5-8

b) EPC Cost ················································································································ 5-8

c) O&M Cost ··············································································································· 5-9

d) Fuel Cost ················································································································ 5-9

e) Plant Availability ······································································································ 5-10

f) Plant Efficiency ········································································································ 5-10

4) Comparative Verification with Alternative ··········································································· 5-11

5) Conclusion ················································································································ 5-12

Page 13: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Chapter 6 Planned Project Schedule ......................................................................................................................... 6-1

Chapter 7 Implementing Organizations

(1) Power Sector in Ukraine ··································································································· 7-1

1) Power Sector ··············································································································· 7-1

a) The Ministry of Energy and Coal Industry ········································································· 7-2

b) National Electricity Regulatory Commission ······································································ 7-2

c) Thermal Power Generation Companies ············································································· 7-2

d) Hydraulic Power Generation Companies ··········································································· 7-2

e) Nuclear Power Generation Company ··············································································· 7-2

f) Wholesale of Electricity, Transmission and Distribution Companies ··········································· 7-2

2) Privatization ·············································································································· 7-3

3) Zakhidenergo (the West Thermal Power Generation Company) ··················································· 7-3

(2) DTEK ························································································································· 7-5

1) General ····················································································································· 7-5

2) Coal Mining and Preparation ···························································································· 7-5

3) Electrical Power Generation ····························································································· 7-6

4) Electrical Power Sales and Supply ····················································································· 7-6

5) Key Production Indicators ······························································································· 7-6

6) Financial Performance ···································································································· 7-8

(3) Evaluation of Implementing Organizations ············································································· 7-9

1) Technical and Human Resources Aspects ··········································································· 7-9

2) Financial Arrangements ································································································· 7-10

Chapter 8 Technical Advantages of Japanese Companies

(1) Expected Formation of Japanese Companies’ Participation ·························································· 8-1

1) Equity Participation ······································································································· 8-1

2) Engineering, Procurement and Construction (EPC) ·································································· 8-1

3) Operation and Maintenance (O&M) ··················································································· 8-1

4) Fuel Supply ················································································································ 8-1

(2) Advantages of Japanese Companies on the Project ···································································· 8-3

1) Advantages in Technical Aspect ························································································ 8-3

2) Advantages in Economic Aspect ······················································································· 8-4

a) New Policies of US and European Financial Institutions ························································ 8-4

b) Policy of Japanese Government and Official Bodies in Japan··················································· 8-5

(3) Mesures Required to Promote Orders to Japanese Companies ······················································· 8-6

Page 14: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 15: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Executive Summary

Page 16: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 17: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-1

(1) Background and Necessity of the Project

1) Background of the Project

Project site has been prepared for the former expansion plan (225 Mega Watt (MW) x 3 units) in the existing

Dobrotvirska coal-fired thermal power plant (TPP). This new project for No.9 unit is planned to adopt more

efficient, ultra-supercritical (USC) technology (main steam temperature: 600 oC, main steam pressure: 26.4 Mega

Pascal (MPa)). The USC installation promotes Japanese manufacture’s participation on this project and reduces

the emission of greenhouse gas such as carbon dioxide.

2) Necessity of the Project

It is supposed to export the generating power from the new power plant to Poland. As a result, this project is

expected to contribute to the acquisition of foreign currency for Ukraine.

In Poland, existing power plants of 6,000 MW installed capacity are forced to shut down by 2017 in order to

achieve the EU environmental directives. It causes power supply shortage in 2016-2017 and power supply

shortage in winter season in 2017 to be assumed to as 1,100 MW. Therefore, it is possible to contribute to the

power supply stabilization of Poland by this project.

Also it is possible to contribute to the power supply stabilization of domestic power system in Ukraine by

connecting to domestic power system. As the result this project contributes economic activity.

In addition if the domestic power demand is increasing as planned then enhancement of power supply system is

necessary. The current power supply system will be insufficient in the future. But independence on importing

power influences on instability of power demand and supply balance and is not effective in utilization of domestic

natural resource. As a consequence USC power plant installation is essential for the environment prevention and

the effective use of domestic natural resources.

Also if the growth in demand is stagnant in the future, then the new power plant is utilized as base load supplier

instead of old existing power plants and there is no need to install environmental facility to existing old power

plants and it is possible to reduce operation and maintenance costs. It contributes to the economic and financial

improvement.

Page 18: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-2

(2) Basic Policy of Project Scope Determination

1) Basic Policy of Project Scope Determination

a) Project scope and study of the technical aspects

Data acquisition and analysis of power sector

Investigation of existing power plant, substation and transmission line and coal properties for the

specification of this project

Conceptual design based on the above specification

b) Environmental and social considerations

Impact on the social environment of the project: Investigation of land acquisition, promotion of

employment, economic benefit effect, greenhouse gas reduction, per impact on other social environment

due to the project construction

Investigation of permission from government, environmental impact assessment, related laws and

regulations

c) Financial and economic analysis

Integration of the construction costs based on the proposed specification

Integration of the financial and economic analysis for the business profitability to examine the scheme from

electricity sales

2) Conceptual Design and the applicable Specification

Japanese manufacturers have constructed a lot of USC power plants in Japan and other foreign countries so far.

The followings are the main equipment for this project.

USC boiler

Steam turbine and generator equipment

Environmental facilities (electrostatic precipitator, desulfurization and denitrification equipment, etc.)

Ancillary equipment (outdoor equipment, etc.)

Electrical and Instrumentation and Control (I&C) equipment

Heat supply is expected to be sent from existing power plant to the district. Heat supply system that is typically

required in the European market is not prepared by this project.

Page 19: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-3

(3) Overview of the Project Plan

1) Project Scope

Project site has been prepared for the former expansion plan (225 MW x 3 units) in the existing Dobrotvirska

coal-fired power plant. This new project for No.9 unit is planned to adopt more efficient USC technology (main

steam temperature: 600 ℃, main steam pressure: 26.4 MPa). The installation of USC technology advances

Japanese manufacture’s participation on this project and reduce the emission of greenhouse gas such as carbon

dioxide.

Major equipment of the new plant is composed of USC pressure boiler and steam turbine generator equipment.

The others are composed of the following equipment.

Boiler auxiliary equipment (Regenerative air heater, Forced draft fan, Induced draft fan (IDF), Primary air

fan, Coal mill, etc.)

Turbine auxiliary equipment (Condenser, Boiler feed pump, Condensate pump, Condensate booster pump,

Circulating water pump, Low pressure feed water heater, Deaerator, High pressure feed water heater,

Condensate polishing equipment, etc.)

Generator auxiliary equipment (Seal oil system, Cooling system, etc.)

Electrical equipment

C&I equipment

Environmental facilities (Electrostatic Precipitator (ESP), Flue-gas Desulfurization (FGD) equipment,

Denitrification equipment, etc.)

Compressed air equipment

Water treatment facilities

Wastewater treatment facilities

Ash handling facilities

Cooling water equipment

Coal handling equipment

Limestone handling equipment

Gypsum handling equipment

Fire prevention equipment, etc.

Page 20: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-4

Table 1 shows scope of works for this project.

Table 1 Scope of Works

Item Contents

Name Dobrotvirska Power Plant

Unit No. 9

Scope of Works

Coal-fired power plant construction work

Civil engineering work

Detailed design of coal-fired power plant

Engineering, procurement and construction work for boilers, boiler auxiliaries, turbine,

turbine auxiliary, generator, generator auxiliary, electrical, I&C, environmental,

compressed air, cooling water, coal and ash handling, limestone handling, gypsum

handling, and fire prevention equipment

Commissioning of the power plant

Consulting work

Out of Scope

For these terms, it is assumed to be implemented by local jurisdiction.

Development costs of coal mine

Removal and relocation work associated with this project

(Source: prepared by the Study Team)

Page 21: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-5

2) Project Cost Estimation

The Construction (Engineering, Procurement and Construction: EPC) cost, the initial investment cost and the

running cost are estimated as the following Tables with the conversion rate of United States dollar (US$) 1=

Ukrainian hryvnia (currency code: UAH) 8.20.

Table 2 EPC Cost of 600MW USC Coal-Fired TPP

Item Cost Breakdown

Foreign (US$ mil) Local (UAH mil.) Total (US$ mil)

1 Boiler & Environmental Equipment 311.8 188.0 334.7

2 Steam Turbine Generator 213.2 56.4 220.1

3 Coal & Ash Handling Systems 73.4 56.4 80.2

4 I&C and Electrical Equipment 59.6 18.8 61.9

5 Mechanical Equipment 87.1 56.4 94.0

6 Civil & Installation Works incl. in the above incl. in the above incl. in the above

7 Sub-total 745.1 376.0 790.9

8 Contingency (10% of Sub-total) 74.5 37.6 79.1

9 Total 819.6 413.6 870.0

(Source: prepared by the Study Team)

Table 3 Initial Investment Cost

Item Remarks Cost Breakdown

Foreign (US$ mil) Local (UAH mil) Total (US$ mil)

1 EPC Table 2 above 819.6 413.6 870.0

2 S/S and T/L T/L length: 20km 10.0 82.0 20.0

3 Other Costs 5% of (1+2 ) 41.5 24.8 44.5

4 IDC Table 5-3 50.5 0.0 50.5

Total 921.6 520.4 985.0

Sub-station (S/S)

Transmission Line (T/L)

Interest during Construction (IDC)

(Source: prepared by the Study Team)

Page 22: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-6

Table 4 Running Cost

Item Annual Cost

Foreign (US$ mil/year) Local (UAH mil/year) Total (US$ mil/year)

1 O&M Cost 10.0 164.0 30.0

2 Fuel Cost 0.0 1,303.8 159.0

3 Land Cost 0.0 0.0 0.0

4 Insurances included in O&M Cost included in O&M Cost included in O&M Cost

5 Interest Rate 3.00% 0.0 3.00%

6 Corporate Tax 0.0 16% 16%

Operation and Maintenance (O&M)

(Source: prepared by the Study Team)

Page 23: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-7

3) Outline of Preliminary Financial and Economic Evaluation

Preliminary Financial and Economic Evaluation is made with the following preconditions.

Table 5 Preconditions for Preliminary Financial and Economic Evaluation

Item Condition

1 Selling Price US$60 per Mega Watt hour (MWh)

2 Annual Operation Hours 7,440hours (24hours/d x 310 days)

3 Plant Efficiency 41%

4 Own Use of Electricity 7.8%

5 Calorific Value of Coal 5,750kcal/kg

6 Coal Price US$ 90/ton (t)

7 Inflation Rate 2.39%

8 Construction Period 5 years

9 Depreciation 40 years, equal amount, residual value zero

10 Operation Years 40 years

11 Debt Equity Ratio Debt 80:Equity 20

12 Lender Japan International Cooperation Agency (JICA)

13 Repayment 20 years, equal semi-annual installment

14 Interest 3.00% per annum

15 Discount Rate

Opportunity Cost of Capital

10.4%

(Source: prepared by the Study Team)

The result is shown below.

Table 6 Preliminary Financial and Economic Evaluation

Evaluation Index Evaluation

1 Financial Internal Rate of Return (FIRR) 8.11%

2 Economic Internal Rate of Return (EIRR) 15.06%

3 Net Present Value (NPV) US$ 131.78 million

4 Benefit Cost Ratio (B/C) 1.07

(Source: prepared by the Study Team)

Page 24: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-8

As FIRR of 8.11% is bigger than 7.50~7.75% which are Ukrainian policy interest rates in the recent years, the

project is financially viable as far as the above preconditions are actual and reasonable ones.

EIRR is calculated at 15.06% which is higher than the opportunity cost of capital 10.4%. And NPV and B/C are

calculated at US$131.78 million and 1.07. These figures show that the implementation of the project would be

economically viable.

However, on 24th September 2013 international rating agency, Moody’s Investors Service has dropped Ukrainian

credit rating by one notch from B3 “regarded as speculative and high risk” to Caa1”probability of default rating”

and announced the possibility of another one notch downgrade.

Therefore, if the trend would continue, the opportunity cost of capital should be considered at the higher rate and

EIRR be targeted at more challenging number by both the investors and the lenders. In fact, the Study Team is

informed by DTEK, the owner of the plant, that they expect higher yield for making new investment.

In order to achieve the target, it is imperative to scrutinize EPC and other costs, and to verify the scheme for

improvement in earnings.

Page 25: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-9

4) Evaluation of Environmental and Social Impacts

a) Analysis of the Current Status of the Environmental and Social Aspect

The project relates to the expansion of the existing power plant. The project site is already developed and is not

rich with flora and fauna.

There is no other large fixed emission source near the power plant site, and the current air quality status is

supposed to be mainly influenced by emission gas from the power plant. The existing units of the power plant is

equipped with scrubber or electrostatic precipitators, but not with desulfurization and denitration equipment.

There is information that the existing units do not meet the emission standards of Ukraine, European Union (EU),

International Finance Corporation (IFC) and the World Bank (WB).

There is no other large fixed discharge source near the power plant site, and water discharge from agricultural

activity in the surrounding area and sewage discharged by the households are supposed to be the main water

pollution source. It was confirmed during the field survey that noise level within the power plant site and near the

boundary of the site is not significantly high.

Dobrotvirska Town in the south of the site has been constructed for labors of the existing power plant and the

infrastructure such as accommodation; hospital and school has been established. The access road to the power

plant is the main road of the town.

b) Environment Improvement Effects by Project Implementation

Sulfur Dioxide (SO2) concentration by impact only from the power plant is currently expected to exceed EU

standards. However, in the case that the exciting Units 5-6 and Units 7-8 are abandoned, impact from the power

plant will largely decrease, and it will meet EU standards.

c) Overview of the Laws and Regulations Concerning Environmental and Social Considerations of the Host

Country and the Measures Needed for Clearing it

In Ukraine, the legal revision of the Environmental Impact Assessment (EIA) is in progress according to the

European legal systems. Paying attention to the trend of these revisions, the EIA for the project needs to be

implemented in the future.

It is essentially important to disclose the information and conduct public consultation from the earliest possible

stage of the project’s EIA according to the laws and regulations of Ukraine and the environmental social

consideration guidelines of JICA and others, and thereby appropriately collecting the local people and

stakeholder’s opinions and reflecting them to the design, construction activity and operation of the project.

d) Requirement for the Host Country (Project Proponent and Other Related Organizations) for the Implementation

of the Project

Page 26: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-10

The project proponent should develop the EIA report according to the laws and regulations of Ukraine based on

the result of the survey and prediction listed below, including the adequate consideration of

stopping/decommission of the existing units, efficiency of the fuel gas treatment system, water use, thermal

effluent discharge, taking special attention on the cumulative impact, in order to improve or not to deteriorate the

present status.

・ Air quality: assessment of the current pollution level

・ Water quality: assessment of the current water temperature of the reservoir in relation to the thermal

effluent discharge

・ Noise: assessment of noise level in the surrounding residential area

Page 27: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-11

(4) Planned Project Schedule

Our assuming overall project schedule is shown in the diagram below.

Figure 1 Project Schedule

2014 2015 2016 2017 2018 2019 2020 2021

Feasibility Study

Environmental Social

Impact Assessment (ESIA)

Contracts’ Negotiations

Permits and Licenses

Finance Close

Site Preparation

Procurement and

Transportation

Civil & Installation

Commissioning

Commercial Operation

(Source: prepared by the Study Team)

Page 28: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-12

(5) Feasibility of the Project Implementation

In February 2010, ITOCHU Corporation together with Tokyo Electric Power Services Co., Ltd. made a

preliminary study on Power Sector and Thermal Power Plants (TPPs) in Ukraine, taking the following points into

consideration;

・ There were many coal-fired TPPs in Ukraine whose commercial operations had started since 40-50 years ago,

・ The installed capacity had decreased since the independence from Soviet Union, and

・ Ukraine has committed herself in the agreement on the cooperation in the energy field with European Union

(EU) to promote the efficiency and safety of TPPs, and meet EU standard in environmental aspects.

During the study, three (3) coal-fired TPPs including Dobrtvirska TPP (Dob TPP) were visited and Dob TPP was

selected to follow with the following reasons;

・ The others used anthracite coal and only Dob TPP combusted bituminous coal which USC technology can be

applied to, and

・ It is near from Polish border and there is transmission line between two countries and the electricity generated

by the plant could be exported to Poland.

Green Investment Scheme (GIS) agreed in 2009 between Japan and Ukraine or Yen Loan would be utilized for the

project implementation in the beginning stage. However since

・ There is no surplus in GIS, and

・ The company that owns Dob TPP has been privatized and Yen Loan is not applicable,

the project would be implemented in the form of joint venture with Ukrainian partner.

The outline of preliminary financial and economic evaluation is shown in the above (3) 3). JICA’s overseas loan

makes the project implementation more bankable; however Ukrainian current situation is taken into consideration,

the yield level should be improved more by scrutinizing EPC and other costs narrowly.

Power Purchase Agreement (PPA) which secures debt repayments is required for the project finance. It is also

necessary to check how to establish such the scheme.

Page 29: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-13

(6) Advance on the Technical Aspect of Japanese Companies

Japanese manufactures and utility companies have the advantage to those in other countries in especially USC

technologies.

Through the long experience of implementing USC TPPs under the highest environmental requirements in Japan,

Japanese companies have been maintaining high standard at the world state-of-the-art level. As the result,

Japanese manufacturers have enjoyed a lot of delivery records and kept competitiveness against European

manufactures. Some of Japanese manufactures give licenses of USC technology to foreign manufactures and

receive orders even from European countries.

It is necessary to meet the more strict environmental standards required by the local government in Japan rather

than USA or Europe, which advances Japanese technological level in the highest one.

Not only plant performance, but also O&M technology in USC such as advanced automation operation, high

availability factor and etc. is in the level of the world state-of-the-art. Japanese companies have established O&M

support system, responding carefully to the needs of the owners.

Also Japanese manufacturers have advanced software technology so that Japanese manufacturers can propose

competitive infrastructural systems.

The Japanese manufacturers have a competitive edge in the field of less environmental impact and energy

conservation. In particular, they can accommodate advanced requirements from the foreign clients against the

background of the technical capabilities that they have corresponded O&M issues to domestic power company.

Page 30: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

S-14

(7) Map of the Project Area in the Country

Figure 2 Map of the Project Area in the Country

(Source: prepared by the Study Team based on Google Map)

Page 31: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Chapter 1 Overview of the Host Country and Sector

Page 32: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 33: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-1

(1) Economic and Fiscal Situation in Ukraine

1) General Information

a) Geography and Climate

a)-1 Geography

Ukraine is located in Eastern Europe, bordering Russia to the east and northeast, Poland, Slovakia, Hungary,

Romania and Moldova to the west, the Black Sea to the south and Belarus to the north, extending approximately

1,400 km from east to west (24~40 degrees east longitude) and 900 km from north to south (44~52 degrees north

latitude) with a total land area of 603,700 km2, which is the 2nd largest following Russia in Europe and about 1.6

times larger than Japan.

Figure 1-1 Location of Ukraine

(Source: Google Map)

The Ukrainian landscape consists mostly of fertile plains (steppes) and plateaus. Ukraine also has a number of

highland regions such as Polesye marshy areas in the north, Donetsk Hills in the east and Carpathian Mountains in

the west.

Being covered by fertile black soil “chernozem”, the plain fields from the central to the southern parts are utilized

for cultivated areas such as wheat and have been called as “European Breadbasket” since Russian Czarism era.

Page 34: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-2

The climate of Crimean Peninsula is Mediterranean climate. Yalta, where the Yalta Conference was held in the

end stage of World War II (February 4th to 11th, 1945), is located in the peninsula and famous for one of

Mediterranean resorts.

The Dnieper is the 3rd longest river (after the Volga and the Danube) and used for the core stuff of water transport

as well as drinking water and hydraulic power plants.

a)-2 Climate

Ukraine is situated between latitudes 44º and 52º north and longitude 24º and 40º east. The northern and western

regions belong in subarctic humid continental climate zone and are the area of high rainfall. The climate of

south-eastern region is dry steppe climate and that of Crimean Peninsula is temperate Mediterranean climate.

The southern region sometimes faces water shortage and suffers from water supply restriction. Carpathian region

has the heaviest rainfall through the year with the average number of 1,200~1,600 millimeter (mm). The eastern

region has the least rainfall and the average number is 300mm.

The figure 1-2 shows monthly average highest and lowest temperatures in Lviv, that is the nearest major city from

the project site, and the figure 1-3 shows those of rainfall. The average annual temperature in Lviv is 7.1 degree

Celsius (ºC), the average of monthly highest temperature is 10.5 ºC and that of monthly lowest temperature is 3.7

ºC. The annual amount of rainfall in Lviv is 600mm.

Figure 1-2 Average Temperature

(Source: ZenTech Home Page)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Ave.Highest Temp in Lviv -1.0 0.0 5.0 11.0 17.0 20.0 21.0 21.0 17.0 11.0 4.0 0.0

Ave.Highest Temp in Tokyo 9.8 10.0 12.9 18.4 22.7 25.2 29.0 30.8 26.8 21.6 16.7 12.3

Ave.Lowest Temp in Lviv -5.0 -5.0 -1.0 3.0 8.0 11.0 12.0 12.0 8.0 4.0 0.0 -3.0

Ave.Lowest Temp in Tokyo 2.1 2.4 5.1 10.5 15.1 18.9 22.5 24.2 20.7 15.0 9.5 4.6

-10.0

-5.0

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0Ave.Highest Temp in LvivAve.Highest Temp in TokyoAve.Lowest Temp in LvivAve.Lowest Temp in Tokyo

Page 35: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-3

Figure 1-3 Amount of Rainfall

(Source: ZenTech Home Page)

b) Brief History of Ukraine

Ukraine was first populated by nomadic tribes such as the Cimmerians, Scythians, and the Goths. Both Greece

and Rome established cities in Ukraine at the peak of their empires.

In the 10th century, the Kievan Rus emerged as a growing city-state based out of the city of Kiev, and in the 11th

century the Kieven Rus was the largest empire in Europe. With the rule of Vladimir the Great in 980, the Kievan

Rus became a Christian empire and reached its peak under the rule of his son, Yaroslav the Wise. In the 12th

century the empire began to decline and in the 13th century Mongol raiders destroyed the city of Kiev.

In later years, the Ukraine became part of other countries, first Poland and later Russia. The Ukrainians made

efforts to keep their culture alive despite limits imposed on them by Russia. Russia even banned the use and study

of the Ukrainian language. When the Soviet Union took over, things became even worse. Joseph Stalin created an

artificial famine to maintain control of the area which killed millions of people. World War II did not make things

better for the Ukraine. It is estimated that the German Nazi's killed 1 million Ukrainian Judaism people.

Yet another disaster struck the Ukraine in 1986 when the Chernobyl nuclear power plant exploded. The Soviet

Union tried to hide the disaster and refused international help. Finally, the Soviet Union collapsed and Ukraine

became an independent country in 1991.

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Rainfall in Lviv 30.0 30.0 30.0 40.0 60.0 80.0 90.0 70.0 50.0 40.0 40.0 40.0

Rainfall in Tokyo 48.6 60.2 114.5 130.3 128.0 164.9 161.5 155.1 208.5 163.1 92.5 39.6

0.0

50.0

100.0

150.0

200.0

250.0Amountmm

Page 36: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-4

c) Domestic Affaires

Proclaiming sovereign power on 16th July 1990, Ukraine has declared her independence on 24th August 1991and

changed her name as “Ukraine”.

The Constitution of Ukraine, which was created and promulgated on 28th June 1996 by the parliament, stipulates

that Ukraine is a republic under mixed semi-parliamentary semi-presidential systems with separate legislative

(unicameral parliament, 450 seats, 5-years term, Chairman: Volodymyr Lytvyn), executive (Cabinet of Ministers),

and judicial (courts) branches.

The President of Ukraine (5-year term) is the head of state and guarantees that state sovereignty, territorial

integrity, conformity of the Constitution, and, citizen’s right and freedom. The current President is H.E. Mr. Victor

Yanukovych whose second round has started since 25th February 2010.

The Constitution of Ukraine stipulates that the voting right is given those whose ages are 18 or over and the

minimum eligible age for both the President and members of the parliament is 25. The members of the parliament

are elected by a system of proportional representation, and the President is elected by public referendum.

Ukraine consists of 27 administrative districts, that is one autonomous republic (Crimean), twenty-four provinces

and the cities of Kiev, the capital, and Sevastopol, both having a special legal status.

Figure 1-4 Administrative Districts

(Source: edited by the Study Team based on the data in Wikipedia)

Page 37: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-5

d)Foreign Relations

d)-1 Foreign Diplomacy

Ukraine has established diplomatic relations with one hundred and eighty countries, and opened eighty-three

embassies and eight representative offices within the international organizations in the world. And there are

seventy-two embassies established by the foreign countries in Ukraine (as of April 2012).

Under the former President H.E. Mr. Yushchenko, the relation with Russia soured, because of those disputes such

as supply of natural gas, staying of Russian Black Sea Fleet, accession to North Atlantic Treaty Organization

(NATO), historical recognition, languages, and religious affiliation.

The current President H.E. Mr. Victor Yanukovych makes effort to mend relations with Russia whilst keeping the

policy to become a member of European Union (EU). There is some progress by compromising time frame of

staying of Russian Black Sea Fleet; however the negotiation on natural gas price is extended for a long period of

time.

Ukraine has declared her non-alignment by means of the domestic law since July 2010.

The process of criminal prosecuting against the former Prime Minister H.E. Mrs. Tymochenko and other

politicians belonging to opposition political parties makes the relation with European Union worse.

d)-2 National Defenses

Ukraine maintains conscription system and holds the largest military power among New Independent States (NIS),

having about 150,000 military personnel under arm and 50,000 civilian staff, then in total army 200,000 strong.

Keeping alliance with NATO, Ukraine will not become a member of it.

Ukraine has finally reached the agreement with Russia on Black Sea Fleet being split up at the end of May 1997.

Ukraine allowed Russian in April 2010 to extend the stay of her Black Sea Fleet until 2042 (the original time

frame was 2017) as a bargaining point for receiving a discount of natural gas price.

e) Social Circumstances

e)-1 Population

The population of Ukraine was 45.57 million and that of Capital City, Kiev was 2.82 million in May 2012.

Figure 1-5 shows the demographic changes in Ukraine for the period of 1980-2010. Ukraine is facing a declining

population, basically because of extreme decrease of childbirth and sharp increase of passing away. Besides

merely the population is decreasing, childbearing, mortality, natural change (social changes such as immigrant and

relocation are not included), easy-generated birth rate (the total number of live births of a year divided by the

population at the middle of the year), basic death rate (the total number of death of a year divided by the

population at the middle of the year), and fertility rate (the total number of live births of a year divided by the

Page 38: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-6

female population with childbearing age (from fifteen to forty-five) at the middle of the year), are sharply

worsening, after a few years since the Chernobyl disaster occurred in April 1986.

Figure 1-5 Demographic Changes in Ukraine

(Source: The World Bank Homepage Indicators by Countries)

e)-2 Languages

There stipulate in the Constitution that the official language in Ukraine is Ukrainian, which is one of east Slavic

languages, and family with Russian and Belarusian languages. Being compared with Russian, Ukrainian keeps old

Slavic grammar and has a lot of words whose meanings are same as Polish.

Since the official language was Russian in the Soviet era, Ukrainian can speak both the languages and often mix

them.

e)-3 Peoples

Ukrainian is the largest and accounts for 77.8%. The others are Russian (17.3%), Belarusian (0.6%), Moldavian

(0.5%), Bulgarian (0.4%), Crimean Tatar (0.5%), Hungarian (0.3%), Rumanian (0.3%), Polish (0.3%), Jewish

(0.2%), Armenian (0.2%) Greek(0.2%), Tatar (0.2%).

e)-4 Religions

Most of Ukrainian citizens keep Christiane identities, however most of them do not belong to specific religious

organization. The traditional religion is Ukrainian Orthodox Church-Kyiv Patriarchate, which is one of Orthodox

Churches. There are believers of the Ukrainian Greek Catholic Church, Jewish, Muslim (Sunni), Catholic and etc.

e)-5 Currencies

The national currency of Ukraine is the hryvnia whose code is UAH. The hryvnia is subdivided into 100 kopiyok.

United States dollar (US$) 1 is UAH 8.285 with the exchange rate of 18 December 2013.

42,000

43,000

44,000

45,000

46,000

47,000

48,000

49,000

50,000

51,000

52,000

53,000

1980 1985 1990 1995 2000 2005 2010

x1,000

Page 39: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-7

e)-6 Main Public Holidays

January 1st New Year Holiday

January 7th Orthodox Christmas

March 8th International Women’s Day

April Easter (moveable feast)

May 1st&2nd Mayday

May 9th Victory Day against Germany

June Holy Trinity (moveable feast)

June 28th Constitution Memorial Day

August 24th Independence Day

2) Economic and Fiscal Conditions

a) Economic Overview

The World Bank reports that the nominal Gross Domestic Production (GDP) of Ukraine in 2012 was US$ 176.3

billion which is just less than the economic magnitude of Fukuoka prefecture in Japan. GDP per capita in 2012

was US$ 3,867 and less than 50% of the world average.

In Soviet times, the economy of Ukraine was the second largest (now the third after Russia and Kazakhstan)

among the Commonwealth of Independent States (CIS). With the planned and specialized economy in the union,

Ukraine took the central role in iron and steel, shipbuilding, military industry such as aerospace, and cereal

production. The figure 1-6 shows nominal GDPs of major CIS countries in 2012.

Figure 1-6 Nominal GDP’s of major CIS countries in 2012

(Source: The World Bank Data Table)

2,014,775

201,680

176,309

67,198

51,113

33,679

0 500,000 1,000,000 1,500,000 2,000,000 2,500,000

Russia

Kazakhstan

Ukraine

Azerbaijan

Uzbekistan

Turkmenistan Unit: million US$

Page 40: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-8

The stock of those industries has been contributing on economic growth of Ukraine since the dissolution of the

Soviet system. Especially, iron and steel industry exports huge amounts and takes important role.

Ukraine is covered by fertile black soil “chernozem” and called as “European Bread Basket”. Agriculture is one of

important industries too.

On the other hand, depending almost all of her energy resources such as natural gas on import from Russia and

delaying structural reforms, Ukraine is easily affected by the neighboring countries.

b) Brief Economic History

In 1991, the government liberalized almost all prices of goods and developed legal systems for the privatization of

the state-own companies. However, political reforms were suspended due to push-back from both the cabinet and

the parliament and most of state-own companies were excluded from the privatization process.

The loose monetary policies of the early 1990s pushed inflation to hyperinflationary levels. For the year 1993,

Ukraine holds the world record for inflation in one calendar year.

The President Leonid Kuchma, who took up the post in 1994, promoted political reforms with the support from

the International Monetary Fund (IMF). In August 1996, the currency was redenominated at a rate of 1 new unit =

100,000 old unit and the new currency, the hryvnia was introduced.

In 1999, the GDP had fallen to about 40% of the 1991 level, however Ukraine enjoyed trade surplus for the first

time in the same year. Thereafter the growth rate of GDP and the growth rate of industrial production in 2000

were 6% and 12.9% respectively, thanks to increase in export of heavy industries, such as iron and steel, being

supported by depreciation of hryvnia. These were the first economic growth after independence. The economic

growth had continued for the years of 2001-2004 thanks to sharp increase in export of iron and steel to China.

However, the economy of Ukraine took a bad turn after the President Yushchenko came to power. Until then, the

economic growth of Ukraine was backed up by cheaper energy resources and materials supplied from Russia, and

export to the emerging market such as Russia and China.

The President Yushchenko kept the distance from Russia and expressed his will to strengthen relationship with EU

and United States of America (USA). He expected increase in foreign investment from USA and Western

countries, which however did not increase as expected in fact. Ukraine could not receive cheaper energy resources

from Russia, reduced the export value to China due to her domestic demand declining, and suffered from

economic deterioration.

Ukraine was hit by the economic crisis of 2008 and about limping toward default. Under such circumstances, the

government requested monetary support to IMF and IMF approved a stand-by loan of about US$ 16.4 billion in

Page 41: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-9

November 2008. In July 2010, IMF again approved a new stand-by loan of about us$ 15 billion and the

government has started structural reforms of taxation system, pension system, gas supply system, price up of

utility charges and etc.

The Figure 1-7 shows the transition of nominal GDP and growth rate of real GDP in Ukraine for the period of

2003-2012, and major economic indices are shown in the Table 1-1.

Figure 1-7 Transition of nominal GDP and Growth Rate of real GDP in Ukraine

(Source: National Statistic Bureau)

Table 1-1 Key Macroeconomic Indicators

(Source: Statistic Bureau and Ministry of finance in Ukraine)

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012

Nominal GDP 50.1 64.9 86.1 107.8 142.7 180.4 113.5 137.7 164.9 176.3

Actual GDP Growth rate 9.6% 12.1% 2.7% 7.3% 7.9% 2.3% -14.8% 4.2% 5.2% 0.2%

-20.0%

-15.0%

-10.0%

-5.0%

0.0%

5.0%

10.0%

15.0%

0

50

100

150

200

US$ billion

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012

Nominal GDP (US$ billion) 50.1 64.9 86.1 107.8 142.7 180.4 113.5 137.7 164.9 176.3

Nominal GDP per Capita (US$) 1,049 1,367 1,829 2,303 3,069 3,891 2,545 2,974 3,576 3,867

Growth Rate of Real GDP 9.6% 12.1% 2.7% 7.3% 7.9% 2.3% -14.8% 4.2% 5.2% 0.2%

Jobless Rate 9.1% 8.6% 7.2% 6.8% 6.4% 6.4% 8.8% 8.1% 7.9% 8.1%

Consumer Price Increase Rate 5.2% 9.0% 13.5% 9.1% 13.6% 9.0% -12.2% 6.4% 11.1% 9.6%

Average Wage Increase Rate 12.1% 10.8% 6.9% 5.4% 7.1% 1.9% 5.5% 17.7% 17.5% 19.7%

Trade Balance (US$ million) 462 -1,937 -8,152 -14,350 -5,733 -9,309 -14,197 -15,900

 Export Value (US$ million) 23,080 33,432 34,287 38,368 49,248 67,003 39,703 51,431 68,410 68,800

 of which to Japan (US$ million) 110.1 133.1 141.6 173.2 156.6 216.0 212.3 201.1 169.9 484.7

 Import Value (US$ million) 23,021 29,691 36,141 45,035 60,670 85,534 45,436 60,740 82,607 84,700

 of which from Japan (US$ million) 147.1 256.7 385.4 675.7 1,081.7 1,991.1 388.3 456.0 665.6 572.4

Current Account (US$ million) 2,890 6,910 2,530 -1,620 -5,270 -12,760 -1,732 -3,018 -10,250 -14,410

Capital Account (US$ million) -3,922 11,478 6,551Foreign Direct Investment (US$million)

1,424 1,715 7,808 5,604 9,891 10,913 4,816 5,759 7,015 7,090Foreign Currency Reserves (US$million)

6,937 9,524 19,394 22,256 32,462 31,543 26,505 34,576 31,795 24,600

Foreign Debt balance (US$ million) 23.8 30.6 39.6 54.5 80 101.7 103,396 117,346 126,236 137,000

Policy interest rate 7.25% 7.33% 9.00% 9.50% 8.25% 10.00% 10.25% 7.75% 7.75% 7.5%Exchange Rate (UAH/US$) on yearend

5.35 5.313 5.376 5.123 5.052 5.057 8.044 7.948 7.986 7.99

Page 42: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-10

c) Issues related to Supply of Natural Gas and Crude Oil from Russia

Ukraine has limited natural resources and depends more than 70% of her demand of natural gas and crude oil on

import from Russia. In 2010, Ukraine imported about 36.5 billion cubic meter of natural gas, about 36.4 billion

cubic meter of which were transited to European countries. Russia exports about 80% of natural gas to European

countries via Ukraine.

After the President Yushchenko came to power in 2005, Russia proposed natural gas price hike in three times.

Since Ukraine rejected it, Russia proposed further price hike and could not reach an agreement by the end of the

year.

On 1st January 2006, Russian semi-sate-own company, Gazprom sopped the supply of natural gas to Ukraine, and

as the result EU suffered from lack of natural gas.

On 1st January 2009, Russia reduced supply of natural gas extremely. Ukraine continued to supply of natural gas

to EU by tapping a reserve for her domestic demand. However on 7th January Russia stopped the supply of natural

gas completely, complaining Ukraine’s extraction, which Ukraine flatly denied.

The President Yanukovych had committed himself to negotiate gas price with Russia since the inauguration and in

April 2010 succeeded in 30% price down or price reduction of US$ 100 per 1,000 cubic meters, compromising on

extension of the stay of Russian Black Sea Fleet in Ukraine for another 25 years.

Ukraine is nicely located. There are well facilitated pipe lines for crude oil and natural gas. Ukraine takes great

role in transporting energy produced in Russia and central Asian countries to EU and therefor is deeply involved

in EU’s energy security. Leveraging those circumstances, Ukraine aims to become a member of EU.

Page 43: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-11

Figure 1-8 Natural Gas Pipelines Map

(Source: Japan Oil, Gas and Metals National Corporation (JOGMEC) Website,

http://oilgas-info.jogmec.go.jp/report_pdf.pl?pdf=0901_B04_motomura_RussiaUkraine.pdf&id=2227)

d) The Relation with IMF

Taking an enormous amount of debt into consideration, the relation with the international financial institutions is

very important for Ukraine. The government takes economic policy respecting those conditions required by IMF.

In September 1998, IMF decided to allocate Special Drawing Rights (SDR) 1,920 million (about US$ 2.5

billion) ) the Extended Fund Facility (EEF) to Ukraine. However, since Ukraine delayed

・ implementing 2002’s national budget,

・ solving debt issue related to Value Added Tax (VAT),

・ the reforms of fuel and energy sector,

・ the completion of privatizing regional electricity distribution companies and etc.,

which were IMF’s conditions for the allocation of EEF, in September 2002, the program terminated, 38% of EEF

(about US$ 966 million) not being disbursed.

In March 2004, recognizing Ukraine’s sound economic management, IMF allocated another SDR 411.6 million

(about US$ 600 million) EFF with the available period of one year. However Ukraine did not use the program.

In October 2008, the international financial crisis hit Ukrainian economy and her international balance of

payments worsened rapidly. To assist Ukrainian economy, IMF decided to allocate SDR 11 billion (about

Ukraine

Kiev

Underground Storage Facilities

Romania

Belarus

Poland

Moldova

Hungary

Slovakia

Black Sea

Sea of Azov

Sevastopol

Uzhgorod

SumyScheduled Station Pizalevka

Scheduled Station

Valuik Scheduled Station

Page 44: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-12

US$ 16.4 billion) standby loan which could be disbursed within two years. IMF ordered the government as quick

as possible to rebuild financial sector including the exchange policy be established by the central bank. Until

November 2009, about US$ 10.6 billion had been disbursed in three tranches, however facing the political turmoil

caused by presidential election, another disbursement was not made.

After the President Yanukovych was elected, in July 2010 another standby loan agreement with the amount of

about US$ 15 billion was made and two disbursements were made by March 2011. Although Ukraine expects 3rd

disbursement, IMF does not accept it since Ukraine does not meet IMF’s requirements such as price hike of

natural gas for household use. To make matters worse, in 2012 and thereafter Ukraine should make numerous debt

repayments and without IMF’s 3rd disbursement Ukraine would be pushed into serious economic situation.

e) External Debt Problems

According to the announcement made by the Ministry of Finance of Ukraine, as of 1st January 2001 the total

amount of her external debt was US$ 10.3 billion. In July 2001, the Paris Club of government creditors agreed to

the rescheduling of Ukrainian about US$ 580 million debt and the repayment being made for 12 years including

the grace period of three years. The agreement officially entered into force in November 2001.

Japanese government agreed with Ukrainian government to the rescheduling of Japanese Yen 6.6 billion which

was a part of the debt in the total amount of about US$ 200 million lent by the former Export Import Bank of

Japan in October 2002.

Ukrainian and Russian governments agreed to reschedule Ukrainian about US$ 1.4 billion debt for importing

natural gas in October 2001 with the following conditions.

・ Repayment Period: 12 years (including grace period of 3 years)

・ Interest Rate: London Inter-Bank Offered Rate + 1%

・ The deal is private transaction however the payment is guaranteed by the government.

・ Russia would pay natural gas transit fee to Ukraine in cash or kind.

Finally, both of the countries agreed to the method of payment for the debt in August 2004.

Due to hryvnia depreciation caused by the international financial crisis occurring in 2008 made, it is worried if the

repayments in foreign currencies could be made timely.

f) The Trend of Trade and Investment

f)-1 Transition of Trade Volume

The total trade volume had registered declines since 1996 and recorded the lowest figure in 1999. Ukraine

suffered from trade deficits in 1997-1998, however enjoyed trade surplus US$ 131 million in 1999 with export

value of US$11.5 billion (15.4 % decrease from the previous year) and import value of US$ 11.4 billion (37.3%

decrease from the previous year).

Page 45: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-13

Thanks to depreciated hryvnia and Russia’s economic recovery, Ukraine continuously had exported large number

of iron and steel, and products of light industries and recorded trade surplus since 2000.

On the other hand, because of income level up and influx of foreign capital, import value for consumable products

had become enlarged. Then, in 2005 and the following years Ukraine again registered trade deficits. Year by year

trade deficit became larger and reached US$ 18.5 billion in 2008.

Trade deficit in 2009 scaled down to US$ 5,733 million due to the international financial crisis and depreciated

hryvnia. As to trade volume, both the export and import figures in 2009 dropped down extremely.

In 2010, although the trade volume recovered, the trade deficit increased again. In 2011, both the export and

import values increased largely, however the import figure expanded larger than the export figure and trade deficit

continued.

Figure 1-9Transition of Trade Volume

(Source: Statistic Bureau in Ukraine)

f)-2 Trade Structure Aspects

Ukraine imports natural gas and crude oil, and exports steel mill products, mineral manufactures, machineries,

chemical products, agricultural commodities, and etc. Ukraine is famous for the transit country of natural gas from

Russia to European countries.

Page 46: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-14

I. Major Export Products (Source: National Statistic Report 2011)

・ Steel mill products (32.3% of the total)

・ Mineral manufactures (12.6%)

・ Machineries and equipment (9%)

・ Agricultural commodities (6.3%)

II. Major Import Products (Source: National Statistic Report 2011)

・ Mineral manufactures (36.4% of the total)

・ Machineries and equipment (15.5%)

・ Chemical products (9.7%)

・ Automobiles and vehicles (7.5%)

f)-3 Major Trade Partners (Source: National Statistic Report 2011)

I. Export: 1st Russia (29.0%), 2nd Turkey (5.5%), 3rd Italy (4.4%), 4th Poland (4.1%)

II. Import: 1st Russia (35.3%), 2nd Germany (8.3%), 3rd China (7.6%), 4th Belarus (5.1%)

f)-4 Trade with Japan

The trade volume between Ukraine and Japan sharply increased in the previous years and the total figure in 2008

exceeded US$ 3 billion. According to the National Statics Bureau, Japan exported US$ 2,795.8 million of values

to Ukraine in 2008, which was about double on year-on-year basis, whilst Ukraine exported US$ 115.7 million of

values to Japan, which was almost same figure in 2007. The mainly article of export from Japan was automobile

which accounts for 83% of the total value in 2008.

The volume fell down a lot in 2009 by the reasons of the international financial crisis, introduction of an

additional 13% customs, decrease of access numbers to personal loans and etc.

With regard to the agricultural sector, Japan for the first time imported crop with the value of US$ 6.3 million

from Ukraine in 2002. In the following years, small quantity of fruit and alcoholic beverages had been imported.

In 2009, crop became one of the main imported articles.

The export figure of automobiles from Japan still occupied for 66% and Ukrainian top export article was iron,

steel and slag in 2011 which accounted for 31% of the total value.

The followings are Ukrainian export and import articles respectively to and from Japan.

(Source: National Statistic Bureau)

I. Export to Japan (figures in 2011)

i) Iron, Steel and slag US$ 47.5 million (31%)

ii) Crops US$ 30.7 million (20%)

iii) Non-ferrous Metal US$ 17.8 million (12%)

iv) Raw Materials for iron & steel US$ 16.9 million (11%)

Page 47: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-15

II. Import from Japan (figures in 2011)

i) Automobiles US$ 673.8 million (66%)

ii) Machineries & Equipment US$ 82.1 million (8%)

iii) Devices & Affairs US$ 47.89 million (5%)

iv) Raw Materials for iron & steel US$ 45.4 million (4%)

f)-5 Trade Topics

Ukraine has officially joined in World Trade Organization (WTO) since 16th May 2008 as the 152nd member.

f)-6 Foreign Direct Investments

Foreign direct investments into Ukraine demonstrate an upward trend. Due to the international financial crisis they

once slowed down, however the balance have reach US$ 50,793.5 million as of 31st March 2012 (cumulative

figure since 1992).

The major foreign direct investors are as follows;

① Cyprus US$ 13,661.9 million (26.9% of the total)

② Germany US$ 7,468 million (14.7%)

③ Netherland US$4,906.6 million (9.7%)

④ Russia US$ 3,661 million (7.2%)

⑤ Austria US$ 3,446.6 million (6.3%)

⑥ United Kingdom US$2,345 million (4.6%)

⑦ France US$ 2,276.5 million (4.5%)

Russia has increase foreign direct investments toward Ukraine since 1999. Russian and Ukrainian capitals were

influent into Ukraine, flight capitals being transferred from Cyprus and British Virgin Islands,

About US$ 4.8 billion out of foreign direct investments from Germany was used for the acquisition of

Kryvorizhstal Ironworks through privatization program. (Arcelor Mittal grope purchased the asset through the

group company in Germany.)

One of the main investments from Austria is the acquisition of Aval Bank made by Raiffeisen credit cooperatives.

g) The Prime Industries and their Challenges

g)-1 Agriculture Sector

Ukraine is covered by fertile black soil “chernozem”, where wheat, sugar beet, sunflower and etc. are cultivated,

and had been called as “European Breadbasket”.

Page 48: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-16

Post-Soviet era, those issues are pointed out such as the delay of technological modernization and structural

reforms, and worsened soil conditions due to desolation. However, agricultural products such as wheat, sugar and

sunflower oil are Ukrainian important exports, and majority of those are exported to CIS and European countries.

In 2002, Ukraine exported feed grains to Japan for the first time.

It is necessary to make several reforms for reconstruction of Ukrainian agricultural sector. As part of them, in

October 2001 the “New Land Law”, which would have entered into force in 2005 and enabled Ukrainian people

to buy and sell agricultural lands each other, was established.

However, the concern, that large capitals might acquire huge lands, had made the law not effective. At last, the

parliament is discussing how to enact the law, now.

In 2007, “Agriculture Land Development Program of Ukraine for the period until 2015” was adopted.

The price escalation of agricultural products attracts Western capitals and state-dominated funds moneys in

middle-east countries toward investments in agricultural businesses. The agriculture sector in Ukraine occupies

important place in her economy in the view points of land trade, bio-energy and international food supply depot.

Although the international financial crisis occurring in 2008 hit Ukrainian economy, GDP of agriculture sector in

Ukraine recorded positive growth in 2009.

On the other hand, many issues, such as agricultural land reforms, restructuring for increase in productivity,

developing logistic and storage infrastructures, remain unsolved.

The bad weather in 2010 damaged crop yields and in October 2010, the government of Ukraine had introduced

quota controls for export of cereal until the end of the year. In December 2010, the period was extended until the

end of March 2011 and again done until the end of June 2011 in March 2011.

As of 30th June 2011, the quota controls was lifted, however the government had introduced a special tax for

export of wheat, barley and corn which was effective until the end of 2011.

g)-2 Heavy Industry

Heavy and chemical industry including steel industry is one of important sectors in Ukraine. The volume of crude

steel production in 2010 was ranked 8th in the world and steel mill products occupy more than 30% of export

value.

Page 49: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-17

Steel industry have started in Donbass region located in the eastern part of Ukraine since Russian czarism era,

utilizing coal procured from Donets coal mine and iron ore from Kryvyi Rih iron mine. Donbass is famous for

“the city of steel industry”, and the open-cut mining, Kryvyi Rih iron mine is famous for the biggest iron mine in

the world.

Further industrialization was promoted in the Soviet era and army complex with higher technology had been

established. Paton Electric Welding Institute in Kiev keeps the highest level in welding technology. Shipbuilding

industry is active in the Black Sea coast area, where many of aircraft careers including Minsk and submarines

were built in the Soviet era.

Also Ukraine keeps the highest level in aerospace industry. The world’s biggest transport aircraft “Mriya” is

manufactured by Antonovov. The Dnieper Rocket, which wss set off in Japan, is manufactured too.

g)-3.Privatization driven by Foreign Capitals

The government announced that Ukraine would have access to foreign money in privatization of the state-own

companies such as power, telecommunication and agricultural infrastructure bodies. In 2001, six “oblenergo”s,

which are distribution companies in each province, and the aluminum smelting plant located in Mykolayiv were

privatized.

However, under Prime Minister Mrs. Tymochenko, who served 1st since February 2005, those privatizations were

re-started all over from scratch, since the privatizations such as Kryvorizhstal Ironworks had been done under

unfair process.

In recent years, although the government still struggles to privatize state-own companies including Ukrtelekom,

the progress does not go well.

g)-4. Coal Industry

Ukraine’s proven coal reserves amount 34.0 billion tons, which is 3.3% - 3.9% of global reserves and 10.0% of

European reserves. The coal reserves of operating mines total 6.1 billion tons, of which 3.5 billion tons is thermal

coal and 2.6 billion tons is coking coal.

The main deposits are located in the Donetsk, Lviv-Volyn and Dnipro coal basins, as well as in the Dnipro-Donets

and Zakarpattia coal depressions. The deposits are in widely extended thin (0.8 - 1.0 m) formation.

As shown in Table 1-2, Ukraine is 2nd biggest coal producer after Poland in Europe.

Page 50: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-18

Table 1-2 Largest Producers of Hard Coal in Europe

Unit: million tons

Country 2011 2012 Change

Poland 75.7 78.1 3.7%

Ukraine 62.7 64.7 3.2%

United Kingdom (UK) 18.3 16.8 -9.3%

Germany 13.0 11.6 -10.8%

Czech Republic 11.3 11.4 0.9%

Spain 6.6 6.1 -3.0%

(Source: Euro-Coal Market Report 1/2013)

Today, more than 350 companies are involved in coal, lignite and peat production, including about 250 companies

that produce and process hard coal. There are more than 145 mines in Ukraine, of which 43 mines are privatized.

The number of people employed in the industry declined by 5,500 to 248,000 in 2012. However, the volume of

coal, lignite and peat sales by Ukrainian enterprises grew at an annual rate of 9% to US$ 6.3 billion in 2012. The

share of sales in coal industry grew from 4.1% in 2011 to 4.5%.

Ukraine conducted coal export-import transactions with 58 countries in 2012. She imported 15.3 million tons of

coal for US$ 2.9 billion. The largest coal suppliers to Ukraine were Russia, USA and Kazakhstan. Coal exports

reached 8.7 million tons with the value of US$ 1.2 billion. The biggest lots were supplied to Bulgaria, India,

Turkey and Russia.

Ukraine consumed about 74.3 million tons of coal in 2012, out of which 41.2 million tons were used in the energy

sector and 28.6 million tons were used by the iron and steel industry.

Coal in Ukraine is sold either under direct contracts between coal producers and consumers or through the

wholesale market operated by state-own enterprise Ugol Ukrainy.

About 65% of coal supplied by state-own enterprises is sold under the contract with Ugol Ukrainy. The wholesale

market operator distributes coal products at the fixed prices, which results in cross-subsidization of loss-making

mines at the expense of profitable ones. Private companies set the prices for their products based on supply and

Page 51: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-19

demand in Ukraine, taking the general trends on international markets into account.

The government of Ukraine controls coal prices. The wholesale price of coal per ton dropped to US$ 69.30 in

2012. While at the same time, the production cost was US$ 120.50. The government allocated US$ 1.3 billion

from the national budget to bridge the gap

3) Economic Assistance

Ukraine promotes economic reform and improvement of her economic position in the world as a top priority, and

works through structural reforms in order to stabilize her economy, such as infrastructure development, energy

conservation, effective usage of energy, development of agricultural sector, establishment of legal framework for

investment promotion, improvement in social and living standards and etc.

Paying attention to Ukrainian strategy and challenges for development, the government of Japan continues to

support her economic growth especially in the fields, which Japan has technical advantages in and contribute to

Japanese companies’ activities in Ukraine.

Japanese Government had given the following Official Development Assistance (ODA) supports to Ukraine till

the fiscal year 2010.

・ODA Loan Japanese Yen 19,092 million

Kiev Boryspil State International Airport Development Project

・Grant Aid JPA 2,859 million

Non-Project, Upgrading of medical equipment for children hospital and etc.

・Technical Cooperation.(ODA) JPY 1,237 million

Dispatching/Inviting experts related to Chernobyl disaster, economy, Japan Center and etc.

・Humanitarian Support US$ 8.22 million

Medical equipment/devices, medicines and etc.

・Support for being freed of Nuclear Arms JPY 2,235 million

・Fund for Safety Usage of Nuclear Energy US$ 19 million + euro 3.68 million

・Fund for Chernobyl sarcophagus about US$ 50 million

The major donor countries or organizations to Ukraine are EU Institutions (153.02), USA (140.16), Germany

(89.11), Japan(53.17), The Global Fund to Fight AIDS, Tuberculosis and Malaria (GFATM, 32.06),

Sweden(31.43), France(21.54).

(Source: Ministry of Foreign Affairs of Japan ODA Home Page, figures in 2010, Unit: US$ million)

Page 52: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-20

(2) Overview of the Power Sector

1) Power Sector in Ukraine

Table 1-3 shows the transition of power sector in Ukraine.

Ukraine was independent from the Soviet Union in 1991. In 1992, the electric power and heat supply sector was

shifted to be organized by Ministry of power and electrification in Ukraine that used to be the subordinate

organization of Ministry of electric power in former Soviet Union. Under supervision of the Ministry, a total of

eight regional corporate entities called Joint Power was organized.

Then the government has repeatedly been restructuring power sector organization for electricity business

reconstruction till 2013.

After Orange Revolution in 2005, thermal power plant (TPP) and local distribution company under the umbrella

of state-owned holding company, Energy Company of Ukraine (ECU) were planned to privatize. All the local

distribution companies have already been privatized until now.

Major private energy company DTEK (Donbass Fuel-Energy Company) now owns three thermal generation

companies in five thermal generation companies in Ukraine and account for 65% of annual electricity production

in Ukraine in 2013.

Page 53: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-21

Table 1-3 Transition of power sector in Ukraine.

Year Politics / Economy Power sector Generation division Electricity Market Transmission line /

distribution division

1975

The construction of a lot of

thermal power plants in 60s

to 75.

(No new thermal power plant

construction up to the current

2013 or later)

1986 Accident at Chernobyl

nuclear power plant

1990

Maximum record of annual amount

of generation (2,985 [TWh]) (Of

which about 2/3 2013 now)

1991 Independent from the

Soviet Union

1992

Ministry of power and electrification

in Ukraine that used to be

subordinate organization of the

Soviet Union has started for

electricity business

1993

For foreign business, including

import and export power, the

state-owned international energy

company, Ukrinterenergo established

Power system separated

from the Russian system

Page 54: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-22

Year Politics / Economy Power sector Generation division Electricity Market Transmission line /

distribution division

1995

Power sector restructuring based on

the Presidential Decree

The restructuring

state-owned companies, four

thermal and two hydro

power companies

Restructuring the load

dispatch center and

wholesale electricity

market

National Electricity

Regulatory Commission

(NERC) established

Restructuring state-owned

transmission company

Ukrenergo and 27 local

distribution companies

1996

State-owned nuclear power

company Energoatom

established

Wholesale Electricity

Market (WEM)

established

1998

Load dispatch center and

WEM integrated into the

state-owned power

company Ukrenergo

State-owned power

company Ukrenergo

established

1999 Signed in Kyoto Protocol Determine the privatization of the

power sector by Presidential Decree

2000

Ministry of Fuel and Energy

established by the restructuring of

government ministries

State-owned

Energorynok of WEM is

independent from the

Ukrenergo

WEM separated from the

state-owned power company

Ukrenergo

2001

Private power generation

company founded

Skhidenergo

Thermal power generation

Power system restarted

interconnection with Russia

system

Page 55: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-23

Year Politics / Economy Power sector Generation division Electricity Market Transmission line /

distribution division

sector became 5-company

system

2004

Orange Revolution

Yushchenko regime

started

Withdraw the privatization policy of

the power sector by Presidential

Decree

State-owned holding

company Ukraine energy

company (ECU) founded

State-owned company

Ukrhydroenergo established

by the two companies

merged

2005

Gas dispute with Russia Ministry of coal industry separated

by restructuring of government

ministries

Private power generation

company DTEK founded,

and after, the privatization of

thermal power sector by

DTEK led promotion

2006

The cabinet decision of Ukraine

energy strategy up to 2030

Electricity price increases (Never

revised till the 2013)

Power distribution sector

fully privatized

2008

Member of WTO

To receive emergency

loans from the IMF by

the financial crisis

2009 Emissions trading with

Japan

Page 56: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-24

Year Politics / Economy Power sector Generation division Electricity Market Transmission line /

distribution division

2010 Yanukovych regime

started

2011

The co-hosts Poland and

the European Football

Championship

(Infrastructure of roads,

airports, etc.)

Member of the European energy

community

2012 Energy strategy revised

2013

Power sector reform bill created to

promote foreign capital

The bill planned to started from 2017

DTEK owns three thermal

generation companies and

account for 65% of total

annual electricity production

Power sector reform bill

created (Power deal

possible without through

Energorynok)

(Source: The Study Team on the basis of the interviews, such as from ECU)

Page 57: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-25

Figure 1-10 shows power sector organization.

Ministry of Energy and Coal Industry manages electric power business in Ukraine. The ministry has directed the

development of energy policy, the power restructuring and supervision of the energy industry.

In the power sector, nuclear and hydropower sector is still state-owned. All the nuclear power plants are operated

by state-owned Energoatom. Almost all of the hydropower plants are operated by state-owned Ukrhydoenergo.

Privatization of thermal power sector has been in progress.

Figure 1-10 Power Sector Organization

(Source: prepared by the Study Team on the basis of the interview from ECU)

ECU that is under the umbrella of Ministry of Energy and Coal Industry manages thermal power division. There

are five generation companies such as Centrenergo, Donbasenergo, Dniproenergo, Zakhidenergo and Skhidenergo

under ECU. Each thermal power plant of generation companies supplies electric power to consumer via

Wholesale Electricity Market (WEM).

Figure 1-11 shows stock shares in each generation company in Ukraine

Progress of privatization is significant for each company. Three generation companies (Dniproenergo,

Zakhidenergo and Skhidenergo) have been privatized by the capital of DTEK as of now. Two left ones are still

public joint-stock company. As the result of sold of 60.77% shares to the public in August 2013, 75% shares of

Donbasenergo is in the private capital.

Page 58: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-26

Figure 1-11 Stock Shares in each Generation Company in Ukraine

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Page 59: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-27

Figure 1-12 shows power supply system.

Figure 1-12 Power Supply System

(Source: prepared by the Study Team on the basis of the interview from ECU)

Each power plant has to sell the generating power to state-owned Energorynok as WEM Operator under the

domestic law. Therefore electric power shall be supplied via WEM so that each counterpart becomes the

participant in WEM.

Based on the single buyer model, WEM exists as single wholesale power market that deals with more than 90% of

the amount of power supply in Ukraine.

Figure 1-13 shows power system in Ukraine

Operation of power system and management of transmission line and substation equipment are operated by

state-owned company Ukrenergo.

Page 60: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-28

Figure 1-13 Power System in Ukraine

(Source: Map of network / Material from Ukrenergo)

Page 61: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-29

National Electricity Regulatory Commission (NERC) was established in 1995. NERC is an independent

regulatory agency to monitor the WEM. In addition to that, NERC executes retail license issued for electric

business owner and to regulate transmission fee and retail price by local distribution companies.

Each power plant generates electricity according to the order from load dispatching center and sell the generating

power to Energorynok. NERC regulates the market and sets the electricity and heat supply tariff.

Figure 1-14 shows installed capacity. Installed capacity of thermal power is maximized in the whole.

The total power generation capacity of 2012 is about 53.8 Giga Watt (GW). The breakdown is as following.

Thermal power: 30.6 GW (56.9%), nuclear power: 13.8 GW (25.7%), Hydro power: 5.5 GW (10.2 %), and other

3.9GW (7.2 %). Since gas dispute with Russia, most of the thermal power plant is now using coal as fuel. In

between 2008 to 2012, the total power generation capacity is almost immutable.

Figure 1-14 Installed Capacity [GW]

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Page 62: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-30

Figure 1-15 shows electric power generation. Amount of electric power generation was reduced due to the impact

of the global financial crisis in 2009. However it is growing steadily thereafter. Electric power generation by

thermal power is next to by nuclear power in the whole.

Annual energy production of 2012 is about 198.1 Tera Watt hour (TWh). The breakdown is as following. Thermal

power: 388.6TWh (44.7%), nuclear power: 90.1TWh (45.5%), Hydro power: 10.8TWh (5.5 %), and other

8.6TWh (4.3 %).

Figure 1-15 Electric Power Generation [TWh]

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Page 63: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-31

Figure 1-16 shows electric power export.

State-owned international energy company, Ukrinterenergo was founded in 1993 and is in charge of foreign

business including import and export electric power. Ukrinterenergo cooperates with European power grid

operators and conducts electricity exports to neighboring countries.

Ukraine has been gaining the foreign currency income by the electric power export. Amount of electric power

export is 9.7TWh in 2012. It means that Ukraine have exported 4.9% of the total power generated.

Figure 1-16 Electric Power Export [TWh]

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Page 64: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-32

Figure 1-17 shows electric power export in 2012.

Ukraine power system is referred to as the integrated power system because it connects with other CIS countries

such as Russia, Belarus, Moldova and also Eastern European countries such as Poland, Slovakia, Hungary, and

Romania. Therefore, it is possible to export generating power to neighboring countries.

Power system in Ukraine separated from the Russian system in 1993. After that power system in Ukraine

reconnected from the Russian system in 2001.

2,500 Mega Watt (MW) Power plant capacities around Burshtynska TPP under Zakhidenergo separates from

power system in Ukraine and interconnected with Hungary, Romania and Slovakia. As the result the power system

has been synchronized with t European Network of Transmission System Operators for Electricity (ENTSO-E). In

the future, all the power system in Ukraine is planned to connect to the ENTSO-E system.

Figure 1-17 Electric Power Export in 2012

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Page 65: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-33

Figure 1-18 shows electric power consumption. Generating power is consumed by industrial, public works, and

home. In recent years, demand for electricity in the home is increasing in particular.

Figure 1-18 Electric Power Consumption [TWh]

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Page 66: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-34

2)Overview of Thermal Power Generation Sector

Most of the existing thermal power plants started commercial operation in 1960 - 1975.

Main fuel for thermal power generation is coal. Heavy oil or natural gas is used for the auxiliary combustion for

anthracite utilization and emergent operation. The actual output of the majority of thermal power plants is lower

than the output of design specification. This is due to aging, obsolete specification, inefficient maintenance

procedure because of the insufficient financial reasons. It is about time to replace to new construction or major

rehabilitation of any power plants.

The following is the supplier of the main equipment in the existing thermal power plants.

Most of the boiler equipment has been supplied by Taganrog in the former Soviet Union (now in Russia).

Supercritical pressure boiler as steam conditions of 25.5 Mega Pascal (MPa) main steam pressure and 545 0C

main steam temperature is adopted for power plant of rated output to more than 300MW. Most of the turbine

equipment, has been supplied by Electrotajumash manufactured in the former Soviet Union (now in Kharkov,

Ukraine). Most of the generator equipment has been supplied by turbo Atom manufactured in the former Soviet

Union (now in Ukraine).

Figure 1-19 shows installed capacity of each TPP in 2012 and Figure 1-20 shows installed capacity ratio of TPPs

in 2012. Vuglegiska and Zaporizka are the largest capacity of TPP and the each capacity accounts for 13.1% of

TPP in Ukraine.

Page 67: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-35

Figure 1-19 Installed Capacity [MW] of each TPP in 2012

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Figure 1-20 Installed Capacity Ratio of TPPs in 2012

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Page 68: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-36

Figure 1-21 shows installed capacity of each thermal generation company in 2012.

DTEK dominates for 62% of the total installed capacity.

Figure 1-21 Installed Capacity [MW] of each Thermal Generation Company in 2012

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Figure 1-22 shows annual electric power generation by each TPP in 2012 and Figure 1-23 shows annual electric

power generation ratio by each TPP in 2012

Burshtynska TPP recorded a maximum annual amount power generation, 9.6TWh (12.2%) in 2012.

Page 69: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-37

Figure 1-22 Annual Electric Power Generation [GWh] by each TPP in 2012

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Figure 1-23 Annual Electric Power Generation Ratio by each TPP in 2012

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Page 70: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-38

Figure 1-24 shows annual electric power generation [GWh] by thermal generation company in 2012.

DTEK dominates for 65% of the total electric power generation.

Figure 1-24 Annual Electric Power Generation [GWh] by Thermal Generation Company in 2012

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Figure 1-25 shows capacity factor of TPPs and CHPs and Figure 1-26 shows capacity factor of TPPs in 2011 and

2012. Nuclear power is used for base load role in Ukraine. On the other hand, thermal power generation is used

for load adjustment role. Therefore the capacity factor of the thermal power plant is very low as 33.4% on

average.

Page 71: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-39

Figure 1-25 Capacity Factor of TPPs and CHPs

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Figure 1-26 Capacity Factor of TPPs in 2011 and 2012

(Source: Fuel and energy complex of Ukraine / Material from Ministry of Energy and Coal Industry)

Page 72: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-40

(3) Situation in the Target Area

Photo 1-1 shows existing Dobrotvirska power plant overview and Table 1-4 shows outline of existing

Dobrotvirska power plant

Photo 1-1 Existing Dobrotvirska Power Plant Appearance

(Source: taken by the Study team from the existing discharge point)

Page 73: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-41

Table 1-4 Outline of existing Dobrotvirska Power Plant

Item Contents

Name Dobrotvirska power plant

Owner DTEK Zakhidenergo

Location About 70 km from Lviv city

Capacity 500 MW (100 MW x 2 units and 150 MW x 2 units)

Power plant

1st line

Boiler: TP-10 by Taganrog (Russia), Turbine: LMZ (Russia), Generator:

Electrussia (Russia)

Power plant

2nd line

Boiler: TP-92 by Taganrog (Russia), Turbine: Turboatom (Ukraine), Generator:

ETM (Ukraine)

Power plant

The others

No. 9-11 Units (225MW x 3 units) construction work started in 1988. The

project stopped because of the collapse of the Soviet Union in 1991 and

discontinued.

The turbine building for No. 9-11 Units and the boiler outer frame for Unit No.

9 are left alone and aging.

Fuel

Coal (bituminous)

The coal is transported from Cervonograd coal mine which is located 15km

from the Dobrotvirska power plant (Coal properties is 40% volatile matter and

25% ash)

Commercial

operation Started in 1959

Efficiency 32.49 % in 2007

Current status Operating

(Source: prepared by the Study Team on the basis of the interview from DTEK)

Page 74: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-42

Figure 1-27 shows the location of existing power plant

Figure 1-27 Location of existing power plant

(Source: prepared by the Study Team on the basis of Google Map)

Figure 1-28 shows power system in western Ukraine.

Existing Dobrotvirska power plant has exported the half of the generating power to Poland by 220 kilo Volt (kV)

transmission line (green colored line). On the other hand, 750kV transmission line (purple colored line) is about

20 km from Dobrotvirska power plant and not utilized because nuclear power plant’s shutdown for long-term.

It is possible to export power to Poland to take advantage of this existing 750kV transmission line for this project.

In that case, it is necessary to construct new 750kV transmission line and substation for the connection between

the power plant and 750kV transmission line.

Lviv city

Dobrotvirska power plant

About 70km

Page 75: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

1-43

Figure 1-28 Power System in western Ukraine

(Source: Map of network / Material from Ukrenergo

Dobrotvirska power plant

220kVTransmission Line

750kV Transmission Line

Poland

Ukraine

About 20km

Lviv city

Page 76: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 77: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Chapter 2 Study Methodology

Page 78: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 79: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-1

(1) Content of the Study

1) Outline of the Study

This Study was made in order for building, owning and operating 600 MW Ultra-Super Critical (USC) Coal-Fired

Thermal Power Plant (TPP), which is economically efficient, environmentally friendly and Japanese companies

keep technical advantage in, within aging Dobrotvirska TPPs site area in the form of joint venture with Ukrainian

partner. The electricity generated by the new TPP would be exported to Poland.

Figure 2-1 Image of USC Coal-Fired TPP (Kozienice unit No. 11)

(Source: prepared by HITACHI Ltd.)

Contents of this Study are summarized as follows;

① General information including power sector

② The existing facilities (TPP, substation and transmission lines) and present electricity market situation

③ Characteristics of fuel coal and the suppliers

④ Basic design, specification, project schedule and cost estimation

⑤ Environmental and social consideration

⑥ Licenses, permissions and the other necessary process for the implementation of the Project

⑦ Implementing organizations

⑧ Financial and economic evaluation

⑨ Financial source and financing plan

⑩ Technical and other advantages of Japanese companies

Page 80: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-2

2) Target Fields

The target field of this Study is the area where Dobrotvirska TPPs are located.

Figure 2-2 Transmission Lines Map in Ukraine

(Source: Ministry of Energy and Coal Industry Home Page)

Photo 2-1 Aerial Photo of Dobrotvirska TPPs

(Source: provided by DTEK)

Page 81: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-3

(2) Method of the Study and Team Members

1) Method of the Study

The Study was made since September 17, 2013 until February 10, 2014. The Study Team collected and reviewed

all the necessary data and information, interviewed those people concerned, and made field investigations. The

Study Team had visited Ukraine and those countries concerned 5 times.

The 1st mission was sent from September 24 to October 6, 2013. They paid visits to both Ukrainian and Japanese

organizations concerned in order to explain the outline of the Study and the schedule, hand over the questionnaires

and request to prepare the answers by the 2nd visit. The field survey of the project site was made too.

The 2nd mission was sent from October 13 to 25, 2013 in order for collecting the answers to the questionnaires

distributed during the 1st visit. The information that could not be received in writing was obtained by means of

interviews with concerned stuff. They again visited the plant site.

The 3rd mission was sent from November 7 to 15, 2013 to exchange views with the international financial

institutions based in Europe with respect to investment and project finance toward coal-fired TPP, political and

other risks in Ukraine and other topics. They also visited PSE-Operator, which is the state-owned grid operator in

Poland, as well as the bodies concerned in Poland so as to obtain general overview of the energy sector in Poland

and the forecast of the electricity volume to be imported from Ukraine.

The 4th mission was sent from December 8 to 14, 2014 to check the current situation of Energy Market Reform

which is expected to be introduced by Polish government. They paid a visit to DTEK and presented the interim

report.

The 5th mission was sent from January 14 to 22, 2014 for making presentations on the draft of the Study to all the

concerned organizations and reflecting their views on the final report.

Reviewing and analyzing all the obtained data and information, the Study Team made up project outline and

schedule, estimated total project cost, made economic and financial analysis, evaluated natural and social

environmental impact, and finalized this report.

In order to obtain the latest technical information related to USC coal-fired TPP, reputable TPP and manufacturer

in Japan were visited.

Page 82: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-4

2) Team Member and Organization

The Study Team members consist of the employees of ITOCHU Corporation, Tokyo Electric Power Services Co.,

Ltd., HITACHI Ltd. and Japan NUS Co., Ltd. The members are shown in Figure 2-3.

Figure 2-3 Study Team Members

(Source: prepared by the Study Team)

3) Supporting Organization in Ukraine

Dobrotvirska Coal-Fired TPP is owned and operated by privatized Zakhidenergo (West Thermal Power Company),

which is under control of DTEK. The Study Team members were fully supported by DTEK.

Figure 2-4 Supporting Organization of DTEK

(Source: prepared by the Study Team)

Project manager

Y. OZAKI Name Professional Affiliation

Y. OZAKI Power Project Department

K. HINO Kiev Office

S. YAMASHITA Power Project Department

N. YAMATO Power Project Department

S. OHARA Power Project Department

Sergay Trigolov Kiev Office

Olesia Perehrest Kiev Office

Name Professional Affiliation

H. OKANOOverseas Thermal PowerEngineering Department

M. SHOJIOverseas Thermal PowerEngineering Department

T. KAGEOverseas Thermal PowerEngineering Department

ITOCHU Corporation

TOKYO ELECTRIC POWER SERVICES CO., LTD.

OUTSOURCING

in Charge

Project Manager

General OverviewOutline of UkraineEconomic & Financial Analysis

Environmental and SocialConsiderationGeneral Overview and Assistances

Coordination in mission

Coordination in mission

in Charge

Technical OverviewPower Sector, Generation FacilityInstrument and ControlBalance of PlantFeeding SystemsCoal and Ash Handling

Outsourcing Company

HITACHI LTD.

JAPAN NUS CO.,LTD.

Outsourcing Work

Environmental and Social Consideration

Basic Design, Specification, Plant Performance,Cost Estimation, Project Schedule

DTEK

Coal Mining Power generationPower Distribution

and SalesOthers

ZakhidenergoDTEK Trading

(Coal Sales)

DobrotvirskaCoal-Fired TPP

Lviv Design Institute

Page 83: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-5

(3) Study Schedule

The Study was done since September, 2013 until February, 2014. The overall schedules are shown below.

Figure 2-5 Overall Schedules

2013 2014

Aug. Sept. Oct. Nov. Dec. Jan. Feb.

Works in Abroad

1. The 1st Mission to Ukraine

2. The 2nd Mission to Ukraine

3. The 3rd Mission to Europe

4. The 4th Mission to Poland and Ukraine

5. The 5th Mission to Ukraine

Works in Japan

1. Advance Preparation

2. Technical Consideration

3. Environmental &Social Consideration

4. Financial & Economic Analysis

5. Completion of the Report

Presentation 8/20 JICA

10/30 Interim

12/3 Interim 2/13 Final

Submission of the Report Outline

12/27 Draft

2/10 Final

(Source: prepared by the Study Team)

1) The 1st Mission

The 1st mission was sent from September 24 to October 6, 2013. They visited both Ukrainian and Japanese

organizations concerned in Kiev and Lviv in order to explain the outline of the Study and the schedule. Then, they

handed over the questionnaires and requested to prepare the answers by the 2nd visit. The field survey of the plant

site and the existing TPPs in about 70km north from Lviv was also made.

Photo 2-2 the Meeting with DTEK on September 30

(Source: taken by the Study Team)

Page 84: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-6

Table 2-1 1st Mission Itinerary

Days Date Day Activity

1 24-Sep Tue ・Trip from Tokyo to Kiev via Frankfurt (Ozaki)

2 25-Sep Wed ・Meeting with ITOCHU Kiev Office

3 26-Sep Thu

・ Trip from Tokyo to Kiev via Frankfurt (Koka of Japan External Trade

Organization (JETRO))

・Data purchased at the Statistic Bureau, the Ministries concerned and Shops

4 27-Sep Fri ・Meeting with the Ministry of Ecology and Natural Resources of Ukraine

・Meeting with European Investment Bank (EIB)

5 28-Sep Sat ・Review of the Data obtained

6 29-sep Sun

・Trip from Tokyo to Kiev via Paris (Shimizu of Hitachi)

・Trip from Dusseldorf to Kiev (Tanaka of Hitachi)

・Review of the Data obtained

7 30-Sep Mon

・Meeting with DTEK

・Meeting with DTEK Trading

・Trip from Kiev to Lviv (Koka, Shimizu, Tanaka, Ozaki, Olesia)

8 1-Oct Tue ・Meeting with West Thermal Power Company

・Meeting with Lviv Design institute

9 2-Oct Wed ・Field Survey at Dobrotvirska Coal-Fired TPP

・Trip from Lviv to Tokyo via Munich (Koka, Tanaka)

10 3-Oct Thu

・Arrive in Tokyo (Koka, Tanaka)

・Maps and Data purchased at the Shops

・Trip from Lviv to Kiev (Shimizu, Ozaki, Olesia)

11 4-Oct Fri ・Meeting with Embassy of Japan

・Lap-up Meeting among the Study Team members

12 5-Oct Sat ・Trip from Kiev to Tokyo via Frankfurt (Ozaki)

・Trip from Kiev to Tokyo via London (Shimizu)

13 6-Oct Sun ・Arrive in Tokyo (Shimizu, Ozaki)

(Source: prepared by the Study Team)

Photo 2-3 the Meeting with West Thermal Power Company on October 1

(Source: taken by the Study Team)

Page 85: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-7

Photo 2-4 Safety Lecture Photo 2-5 Overview of Dobrotvirska TPP

(Source: taken by DTEK) (Source: taken by the Study Team)

Photo 2-6 Fuel Storage Area Photo 2-7 Electrostatic Precipitator under construction

(Source: taken by DTEK) (Source: taken by DTEK)

Photo 2-8 Water Intake Photo 2-9 Water Reservoir

(Source: taken by the Study Team) (Source: taken by the Study Team)

Page 86: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-8

2) The 2nd Mission

The 2nd mission was sent from October 13 to 25, 2013. They collected the answers to the questionnaires handed

over during the 1st visit and related information from the bodies concerned. The field survey of the plant site was

made to consider how to allocate the new facilities with the layout drawing of the existing TPPs.

They paid visits to a foreign bank in Kiev, a consulting company in energy sector and the foreign enterprise that is

doing electricity businesses in Ukraine to have their views on electric power business in Ukraine.

Table 2-2 2nd Mission Itinerary

Days Date Day Activity

1 13-Oct Sun ・Trip from Tokyo to Kiev via Munich (Ozaki)

2 14-Oct Mon ・Meeting with ITOCHU Kiev Office

3 15-Oct Tue

・Trip from Tokyo to Kiev via Paris (Shimizu)

・Trip from Tokyo via Munich (Okano, Shoji, Fukazawa)

・Meeting with DTEK

4 16-Oct Wed ・Meeting with Energy Company of Ukraine

・Meeting with IMEPOWER Consulting

5 17-Oct Thu ・Meeting with DTEK

・Trip from Kiev to Lviv (Ozaki, Okano, Shoji, Shimizu, Fukazawa, Olesia)

6 18-Oct Fri

・Meeting with West Thermal Power Company

・Meeting with DTEK in Lviv

・Meeting with Lviv Design institute

7 19-Oct Sat ・Meeting with DTEK/West Thermal Power Company

・Field Survey at Dobrotvirska Coal-Fired TPP

8 20-Oct Sun ・Review of the Data obtained

・Trip from Lviv to Kiev (Ozaki, Okano, Shoji, Shimizu, Fukazawa, Olesia)

9 21-Oct Mon

・Meeting with National Electricity Regulatory Commission

・Lap-up Meeting among the Study Team members

・Trip from Kiev to Tokyo via London (Shimizu)

10 22-Oct Thu

・Arrive in Tokyo (Shimizu)

・Meeting with State-owned Company “ENERGORYNOK”

・Meeting with Embassy of Japan

・Trip from Kiev to Tokyo via Munich (Okano, Shoji, Fukazawa)

11 23-Oct Wed

・Arrive in Tokyo (Okano, Shoji, Fukazawa)

・Meeting with Credit Agricole

・Meeting with Activ Solar

12 24-Oct Thu ・Trip from Kiev to Tokyo via Frankfurt (Ozaki)

13 25-Oct Fri ・Arrive in Tokyo (Ozaki)

(Source: prepared by the Study Team)

Page 87: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-9

Photo 2-10 Overview of Dbrotvirska TPP from the extension area

(Source: taken by the Study Team)

Photo 2-11 Meeting with Lviv Design Institute Photo 2-12 Meeting with DTEK/West Power Company

(Source: taken by the Study Team) (Source: taken by the Study Team)

Page 88: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-10

Photo 2-13 Ash Disposal Area (total area 144 Hectare (ha))

(Source: taken by the Study Team)

Photo 2-14 Drain Photo 2-15 Meeting with ECU

(Source: taken by the Study Team) (Source: taken by the Study Team)

Photo 2-16 Meeting with NERC Photo 2-17 Meeting with ENERGORYNOK

(Source: taken by the Study Team) (Source: taken by the Study Team)

Page 89: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-11

3) The 3rd Mission

The 3rd mission was sent from November 7 to 15, 2013 so as to exchange views with the international financial

institutions based in Europe with respect to

a) investment and project finance toward coal-fired TPP

b) political and other risks in Ukraine, and

c) other topics.

They also visited PSE-Operator, which is the state-owned grid operator in Poland, as well as the bodies concerned

in order to obtain general overview of the energy sector in Poland and the forecast of the electricity volume to be

imported from Ukraine.

Table 2-3 3rd Mission Itinerary

Days Date Day Activity

1 7-Nov Thu ・Trip from Tokyo to Paris via Frankfurt (Ozaki)

・Meeting with Credit Agricole

2 8-Nov Fri ・Meeting with Nippon Export and Investment Insurance (NEXI) Paris

・Meeting with Japan Bank for International Cooperation (JBIC) Paris

3 9-Nov Sat ・Trip from Paris to London via Dusseldorf (Ozaki)

4 10-Nov Sun ・Meeting with ITOCHU Europe

・Review of the Meetings held in the last week

5 11-Nov Mon ・Meeting with DBJ (Development Bank of Japan, Inc.) Europe Ltd.

・Trip from London to Warsaw via Frankfurt (Ozaki)

6 12-Nov Tue

・Meeting with JETRO Warsaw

・Meeting with Energy Regulatory Office

・Meeting with Ernst & Young, Warsaw

7 13-Nov Wed ・Meeting with Deloitte, Warsaw

・Meeting with PSE Operator

8 14-Nov Thu ・Trip from Warsaw to Tokyo via Frankfurt (Ozaki)

9 15-Nov Fri ・Arrive in Tokyo (Ozaki)

(Source: prepared by the Study Team)

Page 90: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-12

4) The 4th Mission

The 4th mission was sent from December 8 to 14, 2013 to check the current situation of Energy Market Reform,

which Polish government is going to introduce, using the mechanism in USA and UK as the reference, such as

a) Capacity Payment Mechanism (CPM), and

b) Feed in Tariff (FIT) with Contract for Difference (CFD).

They paid a visit to DTEK and presented the interim report.

Table 2-4 4th Mission Itinerary

Days Date Day Activity

1 8-Dec Sun ・Trip from Tokyo to Helsinki (Ozaki)

2 9-Dec Mon ・Trip from Helsinki to Warsaw (Ozaki)

・Meeting with ITOCHU Warsaw

3 10-Dec Tue

・Meeting with Domanski Zakrzewski Palinka (Law Firm)

・Meeting with Ernst & Young, Warsaw

・Meeting with KPMG, Warsaw

4 11-Dec Wed

・Meeting with Bank Pekao/UniCredit

・Meeting with Deloitte, Warsaw

・Trip from Warsaw to Kiev (Ozaki)

5 12-Dec Thu ・.Meeting with DTEK

・Trip from Kiev to Warsaw (Ozaki)

6 13-Dec Fri ・Rap up Meeting with ITOCHU Warsaw

・Trip from Warsaw to Tokyo via Helsinki (Ozaki)

7 14-Dec Sat ・Arrive in Tokyo (Ozaki)

(Source: prepared by the Study Team)

Page 91: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-13

5) The 5th Mission

The 5th mission was sent from January 14 to 22, 2014 for making presentations on the draft of the Study to all the

concerned organizations and reflecting their views on the final report.

Table 2-5 5th Mission Itinerary

Days Date Day Activity

1 14-Jan Tue ・Trip from Tokyo to Kiev via Frankfurt (Shimizu, Tanaka, Ozaki)

2 15-Jan Wed ・Trip from Tokyo to Kiev via Munich (Okano, Shoji)

・Preparation for tomorrow’s presentation

3 16-Jan Thu ・Presentation to DTEK

4 17-Jan Fri ・Meeting with Embassy of Japan

・Trip from Kiev to Munich (Shimizu, Tanaka)

5 18-Jan Sat ・Arrive in Tokyo (Shimizu, Tanaka)

・Trip from Kiev to Frankfurt (Ozaki)

6 19-Jan Sun ・Arrive in Tokyo (Ozaki)

7 20-Jan Mon ・Documentation work required by DTEK

8 21-Jan Tue ・Trip from Kiev to Munich (Okano, Shoji)

9 22-Jan Wed ・Arrive in Tokyo (Okano, Shoji)

(Source: prepared by the Study Team)

Photo 2-18 Final Presentation to DTEK held on January 16

(Source: taken by the Study Team)

Page 92: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-14

6) Persons interviewed during the Study

The Study Team members visited the persons shown in Table 2-6 below to obtain the necessary data and

information.

Table 2-6 Persons interviewed during the Study

Professional Affiliation Position Dates of Interview

DTEK Head, Engineering and Project

Department

2013.9.30-10.1, 2013.10.19,

2014.1.16

DTEK Head, Energy Department 2014.1.16

DTEK Expert, Energy Department 2014.1.16

DTEK Expert, Energy Department 2014.1.16

DTEK Expert, Big Project Department 2014.1.16

DTEK Manager, International affairs 2013.9.30-10.1, 2013.10.17-18

201312.12, 2014.1.16

DTEK International affairs 2013.9.30, 2014.1.16

DTEK Specialist, Foreign Department 2014.1.16

DTEK Head of Coal Mining, Engineering

and Project Department 2013.10.1

DTEK Unit Head, Engineering and Product

Management Department 2013.10.17

DTEK Legal Department 2013.12.12.

DTEK Trading Manager, Coal Sales 2013.9.30

Zakhidenergo Director, Technical Division 2013.10.1, 2013.10.18-19

Dobrotvirska Coal-Fired TPP General Director 2013.10.1, 2013.10.18-19

2014.1.16

Dobrotvirska Coal-Fired TPP Acting Director 2013.10.1, 2013.10.19

Dobrotvirska Coal-Fired TPP Chief Engineer 2013.10.1, 2013.10.19

Lviv Designer Institute Director 2013.10.18

Lviv Designer Institute Chief Engineer 2013.10.1, 2013.10.18

Lviv Designer Institute Project Chief Engineer 2013.10.1, 2013.10.18

National Electricity Regulatory

Commission of Ukraine

Head

Directorate of Power Generation 2013.10.21

National Electricity Regulatory

Commission of Ukraine Directorate of Power Generation 2013.10.21

National Electricity Regulatory

Commission of Ukraine

Head, Directorate of Power

Transmission and Distribution 2013.10.21

Energy Company of Ukraine Head, Energy generation Dept. 2013.10.16

Energy Company of Ukraine Deputy, Energy Generation Dept. 2013.10.16

Energy Company of Ukraine Energy Generation Department 2013.10.16

Energy Company of Ukraine Energy Generation Department 2013.10.16

Page 93: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-15

State Company ENERGORYNOK Deputy Director of Development 2013.10.22

State Company ENERGORYNOK Deputy Head,

Perspective Development Dept. 2013.10.22

State Company ENERGORYNOK Perspective Development Dept. 2013.10.22

State Company ENERGORYNOK Perspective Development Dept. 2013.10.22

State Company ENERGORYNOK Perspective Development Dept. 2013.10.22

IMEPOWER Consulting Director 2013.10.16

IMEPOWER Consulting Director 2013.10.16

Ministry of Ecology and Natural

Resources of Ukraine

Head of State Environmental and

Geological Examination 2013.9.27

Environmental Institution Center Director 2013.9.27

Activ Solar General Director 2013.10.23

Activ Solar Business Development Manager 2013.10.23

Activ Solar Sales Manager 2013.10.23

Energy Regulatory Office of Poland Chief Consulting Engineer

Markets Development Dept. 2013.11.12

Energy Regulatory Office of Poland Markets Development Dept. 2013.11.12

Energy Regulatory Office of Poland Markets Development Dept. 2013.11.12

PSE Operator, Poland Senior Specialist

Grid Development Strategy Dept. 2013.11.13

PSE Operator, Poland Grid Development Strategy Dept. 2013.11.13

PSE Operator, Poland Senior Specialist

Transmission Services Department 2013.11.13

PSE Operator, Poland Transmission Services Department 2013.11.13

Deloitte, Warsaw Partner, Energy & Resources,

Central Europe 2013.11.13, 2013.12.11

Deloitte, Warsaw Senior Manager, Japanese Service 2013.11.13

Deloitte, Warsaw Manager, Corporate Finance 2013.11.13, 2013.12.11

Ernst & Young, Warsaw Japanese Business Service 2013.11.12, 2013.12.10

Ernst & Young, Warsaw Senior Manager CAP (Japan)

Japanese Business Service 2013.12.10

Ernst & Young, Warsaw Manager, Corporate Finance 2013.11.12, 2013.12.10

KPMG, Warsaw Partner 2013.12.10

KPMG, Warsaw Manager, Corporate Finance 2013.12.10

Domanski Zakrzewski Palinka Partner 2013.12.10

Domanski Zakrzewski Palinka Partner 2013.12.10

UniCredit Director 2013.12.11

Bank Pekao Director 2013.12.11

Bank Pekao Director 2013.12.11

Page 94: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-16

European Investment Bank Head of Representative in Ukraine 2013.9.27

European Bank for Reconstruction

and Development Senior Banker, Natural Resources 2013.9.6

Japan International Cooperation

Agency (JICA)

Investment Officer

Private Sector Investment Division 2013.12.3

JICA Assistant Director, Europe Division 2013.12.3

JBIC Deputy Director

Power & Water Finance Department2013.10.28

JBIC Power & Water Finance Department 2013.10.28

JBIC, Paris Representative Office Director General 2013.11.8

JBIC, Paris Representative Office Senior Representative 2013.11.8

NEXI Director

Power & Mining Group 2013.9.10

NEXI Vice President, Power & Mining G. 2013.9.10

NEXI, Paris Representative Office Representative 2013.11.8

NEXI, Paris Representative Office Representative 2013.11.8

Development Bank of Japan Inc. Vice President, Corporate Finance

Department 2013.9.5

DBJ Europe Ltd. Head of Corporate and Structured

Finance 2013.11.11

DBJ Europe Ltd. Vice President 2013.11.11

Bank of Tokyo-Mitsubishi UFJ Senior manager

Corporate Banking 2013.9.18

Bank of Tokyo-Mitsubishi UFJ Associate, Corporate Banking 2013.9.18

Credit Agricole Managing Director, Global Head of

Power, Utility & Mining 2013.11.7

Credit Agricole Executive Director 2013.11.7

Credit Agricole, Ukraine Branch Commercial Director 2013.10.23

Credit Agricole, Ukraine Branch Relationship Manager 2013.10.23

Credit Agricole, Ukraine Branch Chief Economist 2013.10.23

Embassy of Japan in Ukraine First Secretary, Economic Section 2013.10.4, 2013.10.22, 2014.1.16

JETRO Warsaw Director General 2013.11.12

JETRO Warsaw Research & Projects Coordinator 2013.11.12

The Chugoku Electric power Co.,

Ltd.

Manager

International Business Section 2 2013.11.28

The Chugoku Electric power Co.,

Ltd.

Assistant Manager

International Business Section 2 2013.11.28

The Chugoku Electric power Co.,

Ltd.

International Business Section 2

Group Management Division. 2013.11.28

Page 95: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

2-17

ITOCHU Europe General Manager, Power Project 2013.11.10

ITOCHU Warsaw General Manager 2013.12.9

(Source: prepared by the Study Team)

Page 96: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 97: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Chapter 3 Justification, Objectives and Technical

Feasibility of the Project

Page 98: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 99: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-1

(1) Background and Necessity of the Project

1) Scope of the Project

Project site has been prepared for the former expansion plan (225 MW x 3 units) in the existing Dobrotvirska

coal-fired power plant. This new project for No.9 unit is planned to adopt more efficient, ultra-supercritical (USC)

technology (main steam temperature: 600 oC, main steam pressure: 26.4 MPa). The installation of USC

technology advances Japanese manufacture’s participation on this project and reduce the emission of greenhouse

gas such as carbon dioxide.

Figure 3-1 Former Dobrotvirska Power Plant Expansion Plan

(Source: Illustration’s Photo taken by the Study team at Dobrotvirska Power Plant)

Major equipment of the new plant is composed of USC pressure boiler and steam turbine generator equipment.

The others are composed of the following equipment.

Page 100: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-2

Boiler auxiliary equipment (Regenerative air heater, Forced draft fan, Induced draft fan (IDF), Primary air

fan, Coal mill, etc.)

Turbine auxiliary equipment (Condenser, Boiler feed pump, Condensate pump, Condensate booster pump,

Circulating water pump, Low pressure feed water heater, Deaerator, High pressure feed water heater,

Condensate polishing equipment, etc.)

Generator auxiliary equipment (Seal oil system, Cooling system, etc.)

Electrical equipment

C&I equipment

Environmental facilities (Electrostatic Precipitator (ESP), Flue-gas Desulfurization (FGD) equipment,

Denitrification equipment, etc.)

Compressed air equipment

Water treatment facilities

Wastewater treatment facilities

Ash handling facilities

Cooling water equipment

Coal handling equipment

Limestone handling equipment

Gypsum handling equipment

Fire prevention equipment, etc.

Table 3-1 shows scope of works for this project.

Table 3-1 Scope of Works

Item Contents

Name Dobrotvirska Power Plant

Unit No. 9

Scope of Works

Coal-fired power plant construction work

Civil engineering work

Detailed design of coal-fired power plant

Engineering, procurement and construction work for boilers, boiler auxiliaries, turbine,

turbine auxiliary, generator, generator auxiliary, electrical, C&I, environmental,

compressed air, cooling water, coal and ash handling, limestone handling, gypsum

handling, and fire prevention equipment

Commissioning of the power plant

Consulting work

Out of Scope

For these terms, it is assumed to be implemented by local jurisdiction.

Development costs of coal mine

Removal and relocation work associated with this project

(Source: prepared by the Study Team)

Page 101: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-3

2) Analysis of the Present Situation and Future Forecast

Energy strategy of Ukraine for the period until 2030 was approved by the Cabinet in June 2006. Energy policy in

Ukraine is planned based on the energy strategy.

Figure 3-2 shows the forecast of the installed capacity and Figure 3-3 shows the forecast of electricity generation.

Energy strategy has been significantly modified and revised down in 2012 because of the world economic

recession. Accordingly, the annual power production forecast and power development plan has also been revised

downward.

Power generation capacity is assumed to be 53.5 GW in 2020 and 65.2 GW in 2030 in the power development

plan (2012 version).

Also annual power production is assumed to 237 TWh in 2020 and 282 TWh, in 2030 in the power development

plan (2012 version).

Figure 3-2 Forecast of the Installed Capacity

(Source: Energy strategy of Ukraine until 2030 / 2006 and 2012 version)

Page 102: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-4

Figure 3-3 Forecast of the Electricity Generation Capacity

(Source: Energy Strategy of Ukraine until 2030 / 2006 and 2012 version)

New large-scale power development plan does not exist in 2013. The following is the information by interviews.

In the nuclear power division, it is planned to execute feasibility study of Khmelnytsky power plant expansion

plan of 1,000 MW x 2 units by state-owned enterprises Energoatom.

In the hydro power division, it is planned to execute rehabilitation for existing power plant and construction for

new power plant by International Bank for Reconstruction and Development and European Bank for

Reconstruction and Development (EBRD) loan.

In the thermal power division, there has been no new project for 20 years because it is focused on the

rehabilitation of existing power plant. On the other hand, existing old power plants are operating in low heat

efficiency such as 29 to 34%. Replacement from the existing power plants to high-efficiency thermal power plants

is necessary from the viewpoint of environmental impact reduction, energy saving (fuel cost reduction) and heat

efficiency improvement.

Page 103: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-5

3) Effect caused by the Project Implementation

It is supposed to export the generating power from this plant to Poland. As a result, this project is expected to

contribute to the gain of foreign currency for Ukraine.

In Poland, 6,000 MW capacities of the existing power plants are forced to shut down by 2017 in order to achieve

the EU environmental standards. It causes power supply shortage in 2016-2017 and power supply shortage in

winter season in 2017 to be assumed to as 1,100 MW. Therefore, it is possible to contribute to the power supply

stabilization of Poland by this project.

Also it is possible to contribute to the power supply stabilization of domestic power system in Ukraine by

connecting to domestic power system power to international power system.

In addition if the domestic power demand growth is increasing as planned then enhancement of power supply is

necessary. The current supply capacity is insufficient ability in the future. But enhancement of importing power

influences on instability of power demand and supply balance and not effective utilization of domestic natural

resource. As a consequence USC power plant installation is essential for the environment prevention and the

effective use of domestic natural resources.

If the growth in demand is stagnant in the future then there is no need to install environmental facility to existing

old power plants and it is possible to reduce operation and maintenance costs. It contributes to the economic and

financial improved.

4) Comparison with other Options

The following four alternatives are assumed except the proposed project.

a) Alternative 1: Natural Gas-fired power plant

b) Alternative 2: Coal-fired power plant (Sub-critical type)

c) Alternative 3: Imported Capacity to be increased (No new power plant)

d) Alternative 4: Renewable energy

a) Alternative 1: Natural Gas-fired Power Plant

Coal is one of the few valuable energy resources in Ukraine. Basic policy in Ukraine is to effectively utilize the

coal and import gas and other natural resources. As the result Ukraine can deal with domestic energy demand and

supply matters. Therefore coal industry is the major business in Ukraine.

DTEK now owns ones coal mines and manages coal production and electricity business. DTEK dominates 65 %

of the gross domestic power generation in power sector and 50 % of gross domestic coal production in coal sector

in 2013. In case of transition from coal to gas combustion at boiler, it causes a lot of energy security problem such

as unemployment issue of many workers at coal mine, land acquisition, procurement and long-term fuel purchase

Page 104: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-6

contracts.

Gas pipeline is already prepared for stable gas supply to gas-fired power plant. However it can’t be a realistic

alternative on the energy policy in Ukraine intended to reduce gas imports because of the gas dispute with Russia

in the past.

b) Alternative 2: Coal-fired Power Plant (Sub-critical type)

Coal is the primary industry in Ukraine and shall be actively utilized. However coal is used effectively because of

the limited resources and keeping competitiveness.

It is necessary to take into consideration the efficiency difference between the conventional and high-efficiency

type. In case of installation of high-efficiency coal-fired power plant, the time to resource depletion become

approximately 1.5 times longer. In addition it is assumed that if energy policy does not change significantly the

next few decades then the high efficiency type installation is better than conventional installation economically.

Low initial cost does not mean better economical solution all the time because operation and maintenance cost is

more important for long-term operation.

c) Alternative 3: Imported Capacity to be increased (No new power plant)

This alternative means that this project is canceled. Power supply shall be managed by increasing amount of

import power. This alternative can not deal with demand increasing. Therefore it is decided to use the power

trading for long-term. It takes advantage of the power trading for peak load corresponding but it is possible to

depart from the government policy in Ukraine. The use of the imported power makes Ukraine huge economic

damage.

In addition decreasing of supply capacity from coal-fired power plant, it causes stagnation of the coal industry and

unemployment issue of many workers at coal mine as same as Alternative 1.

d) Alternative 4: Renewable Energy

In the energy strategy, it is proposed to actively introduce renewable energy. From the viewpoint of environmental

prevention, utilization of renewable energy such as photovoltaic and wind mill power shall be promoted.

However it is not realistic solution to replace the renewable energy because of the huge costs and

long-implementation time. In comparison to fossil fuel, energy density of renewable energy such as photovoltaic

and wind mill power is lower. In addition to that output from renewable energy is influenced on the natural

environment so that stably supply power is not expected.

From the above each alternative has problems which shall be solved. In order to obtain the same effect as the

proposed project, it is necessary to spend enormous cost and time.

Therefore USC power plant is the best solution to manage the power demand matters and achieve EU

Page 105: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-7

environmental standard without any influence on stable power supply in Ukraine.

Page 106: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-8

(2) Efficiency and Rationalization of Energy Usage

This project implements the efficiency and rationalization of energy usage by adopting USC power plant.

Pulverized coal-fired power generation systems are widely used because of the reliability and established

technology. There have been a lot of introduction examples for USC power plant in Japan since introduce of USC

method introduced in Tachibana-wan TPP (1,050 MW x 2 units) by J-power in 2000. Thermal efficiency at

generator end of thermal power generation is improved to 43% and efficiency and rationalization of use of energy

became possible.

Additionally it is also effective for environmental protection. USC power plants can achieve lower emissions of

carbon dioxide, sulfur oxide and nitrogen oxide.

Page 107: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-9

(3) Various Types of Studies required for the Decision of Project Scope

1) Demand Forecast

Power demand is forecasted to be 53.5 GW in 2020 and 65.2 GW in 2030 in power development plan (2012

version). Amount of annual power production is forecasted to be 237 TWh in 2020 and 282 TWh in 2030 in f

annual power production forecast (2012 version).

2) Necessary Analysis of Problems for the Appraisal and Determination of Project Scope

Table 3-2 shows extraction of the important items in each aspect.

Table 3-2 Extraction of the Important Items in each Aspect

a) Technical aspects b) Environmental aspectsc) Economic and

financial aspects

d) Project development

aspects

1. Steam conditions

2. Coal properties

3. Reduction of NOx,

SO2 and Dust

4. Equipment layout

1. Reconfirmation of the

environmental

standards, the value

and enforcement year

2. Necessity confirmation

of Environmental

Impact Assessment

(EIA) application

1. Economic and

financial analysis

1. Contract method

(Source: prepared by the Study Team)

a) Technical Aspects

1. Steam Conditions

Aiming for high temperature and high pressure steam condition is important for high efficiency coal-fired

power plant. Table 3-3 shows type of power plant.

In recent years, power generation technology by SC and USC has been adopted as a high-efficiency

coal-fired power plant with high reliability.

In this section it is considered which power generation method is suitable for this project from technical and

economical point of view. As the result USC power generation technology is adopted because of the high

efficiency, less environmental impact and the possibility of participant for Japanese companies.

Page 108: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-10

Table 3-3 Type of power plant

Name Abbreviation Steam conditions

Sub Critical - Steam pressure is lower than 22MPa as the critical pressure

Super Critical SC Steam pressure is higher than 22MPa as the critical pressure

Ultra Super Critical USC SC and the steam temperature is higher than 593 oC

(Source: prepared by the Study Team)

2. Coal Properties

Basic design of boiler, combustion system, coal storage yard, coal handling system relies on the coal

properties. Table 3-4 shows coal properties for this project. Domestic bituminous coal is utilized. Bituminous

coal’s lower heating value (LHV) is more than 5,000 kcal/kg. The moisture is low and Volatile matter content

is high value. It means that bituminous coal is suitable for boiler combustion. Therefore bituminous coal is

used for coal-fired power plant around the coal mine. This project is also planned to be supplied from

neighbor coal mine. In comparison to boiler by foreign companies, planned Japanese boiler for this project

has advantage in the combustion of bituminous coal.

Table 3-4 Coal properties

Item Coal properties

Coal type A B

LHV kcal/kg 5,280 5,782

Ash % 28.3 26.0

Sulfur % 1.9 1.6

Moisture % 8.1 3.0

(Source: prepared by the Study Team on the basis of data from DTEK)

3. Reduction of NOx, SO2 and Dust

Optimum desulfurization system is applied for this project to consider the emission properties from the

existing power plant, environmental standards in Ukraine and EU, installation space, construction cost,

operation and maintenance cost. Also the possibility of participant for Japanese manufactures shall be

considered.

4. Equipment Layout

There was an expansion plan (225 MW x 3 units) before the collapse of the former Soviet Union. Foundation

work, boiler steel structure, intake and discharge channels have been already constructed. It is necessary to

study the possibility of reuse and demolition existing facilities at the basic design-term.

b) Environmental Aspects

1. Reconfirmation of the Environmental Standards, the Value and Enforcement Year

Page 109: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-11

It is necessary to study the regulated value and the introduction year of the applied environmental standards.

2. Necessity Confirmation of EIA Application

EIA for an expansion plan (225 MW x 3 units) is already acquired before the collapse of the former Soviet

Union. It is necessary to study if the EIA is valid or not at the basic design-term.

c) Financial and Economic Aspects

1. Economic and financial analysis

It is necessary to study the feasibility of projects from the economical aspect.

Page 110: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-12

d) Project Development Aspects

1. Contract method

Generally Engineering Procurement and Construction (EPC) full turnkey contract is common for large-scale

thermal power plant construction. Also this coal-fired power plant project is supposed to be contracted by

EPC full turnkey.

EPC full turnkey contract requires carrying out the services of all necessarily comprehensive works such as

engineering, procurement and construction. EPC full turnkey contract includes the design of the equipment,

production, procurement, transportation, inspection, construction, installation, commissioning, performance

test, operation and maintenance training.

On the other hand, in case of individual contract, it is necessary to contract for each lot unlike the EPC

turnkey contract. It is important to decide the interface for each contractor. Further, it is necessary to clearly

define the project schedule such as delivery time, completion day and turnover.

The followings are example of lot split cases.

・ Boiler lot

・ Turbine lot

・ Coal and ash handling lot

・ Civil, architecture and installation lot

In the case of individual contract, cost down effect is expected by principle of competition. There used to be

a lot of proposals from companies previously when the individual bids are applied. Currently only one

company or a few tend to participate the bidding. If there is no comparison or other choice, it is expected to

be difficult to manage contract negotiations. In this case, it is not possible to take advantage of the benefits of

the individual contracts. Moreover, the owner side must manage adjust the schedule.

Therefore EPC full turnkey contract is recommendable for this project.

Page 111: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-13

3) Study of Engineering Practice

In order to save energy and reduce environmental impact USC technology is adopted for this project. Table 3-5

shows steam conditions and the plant performance. In comparison to sub-critical type, it is expected that plant

efficiency is improved about 106% with USC technology.

Table 3-5 Steam Conditions and the Plant Performance

Items Sub Critical Super Critical Ultra Super Critical

Main steam pressure 16.6 MPa 24. 1MPa 26.4 MPa

Main / reheat steam temperature 538 oC /538 oC 566 oC /566 oC 600 oC /610 oC

Gross efficiency 100 % (Base) 104 % 106 %

Emission of CO2 100 % (Base) 96 % 94 %

Amount of cooling water 100 % (Base) 92 % 90 %

(Source: prepared by the Study Team)

Page 112: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-14

(4) Overview of the Project Plan

1) Basic Policy of Project Scope Determination

a) Project Scope and Study of the Technical Aspects

・ Data acquisition and analysis of power sector

・ Investigation of the existing power plant, substation and transmission line and coal properties for the

specification of this project

・ Conceptual design based on the above specification

b) Environmental and Social Considerations

・ Impact on the social environment of the project: Investigation of land acquisition, promotion of

employment, economic benefit effect, greenhouse gas reduction, per impact on other social environment

due to the project construction

・ Investigation of permission from government, environmental impact assessment, related laws and

regulations

c) Financial and Economic Analysis

・ Integration of the construction costs based on the proposed specification

・ Integration of the financial and economic analysis for the business profitability to examine the scheme

from electricity sales

2) Conceptual Design and the Applicable Specification

Major power generation facilities are roughly composed of Boiler, Turbine and environmental facilities.

The Boiler is tower-type pulverized coal firing boiler. The Turbine is high, medium and low pressure turbines and

a tandem compound Turbine composed of a single axis.

As the environmental facilities, Electrostatic Precipitator and Flue Gas Desulphurisation equipment will be

installed. It is planned that the composition of this equipment will comply with the EU environmental standard on

flue gas emissions.

Figure 3-4 shows the configuration of the Power Plant. Heat supply is expected to be sent from existing power

plant to the district. Heat supply system that is typically required in the European market is not prepared by this

project.

Page 113: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-15

Figure 3-4 Configuration of the Power Plant

(Source: prepared by the Study Team)

a) Boiler and Auxiliaries

(i) Basic Specification

Equipment herein specified to comprise:

One reheat steam generating unit, ultra super critical, once-through type, balanced draft operation. The boiler is

designed for indoor operation arranged in the form of self contained construction and suspended from structural

steelwork within the boiler house.

The boiler is equipped with one Forced Draft (FD)-fan (100%). The back end of the boiler is equipped with one

regenerative air heater, two electrostatic precipitators (ESP) followed by two induced draft fans (ID-fans) and one

flue gas desulphurization plant (FGD).

The boiler is designed with adequate tube spacing to avoid plugging and ash build-up, to allow for proper cleaning by soot blowers and to permit maintenance access.

(ii) Circuit arrangement of the boiler on the Water-steam side

The circuit arrangement of the boiler on the water-steam side is shown in the flow diagrams.

For start-up and in order to control failures the unit is equipped with a safety by-pass station on the HP steam side

and with safety valves on the reheater steam side designed for the max. steam flow.

IP Turbine

HP Turbine

LP Turbine

Generator

Condenser

HP-Heater

LP-Heater

DRT

Grand steam condenser

Page 114: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-16

Figure 3-5 The circuit arrangement of the boiler on the water-steam side (example)

(Source: prepared by the Study Team)

The turbine bypass system is connected from the main steam pipe in front of the high pressure turbine to the cold

reheat steam pipe to bypass the high pressure turbine. The turbine bypass system is also connected from the hot

reheat steam pipe in front of the intermediate pressure turbine to the condenser to bypass the intermediate pressure

and low pressure turbines.

In this way, the turbine bypass system has the following functions:

Improving start-up characteristics of the plant

When the plant starts, the boiler load is adjusted by the turbine bypass system, so that the boiler steam

temperature becomes the optimal ventilation temperature of the turbine.

Absorbing the load difference between the boiler and turbine when the load is changed

When there is a load difference between the turbine and boiler when the load is interrupted, the turbine

bypass system absorbs the surplus load of the boiler.

An auxiliary function of the boiler superheater safety valve

When the pressure of the boiler superheater becomes excessive, the turbine bypass system reduces the

pressure.

Page 115: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-17

(iii) Circuit arrangement of the boiler on the flue gas side

The circuit arrangement of the boiler on the flue gas side is shown in the flow diagram Figure 3-6.

Figure 3-6 The circuit arrangement of the boiler on the flue gas side

(Source: prepared by the Study Team)

Page 116: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-18

b) Turbine

The steam turbine is composed of the turbine main unit and BOP (Balance of Plant) devices (such as condensers,

deaerator, heaters and pumps). The specifications of the steam turbine and BOP devices are shown in the table

below.

An illustration (bird’s eye view) of the tandem compound steam turbine is shown on the next page. Steam

discharged from the high pressure turbine is reheated at the boiler, and brought back to the intermediate pressure

turbine to rotate the turbine blades. Then, the steam is led to the centre of the low pressure part from the

intermediate pressure turbine. The steam at the outlet of the low pressure turbine is cooled at the condenser on the

bottom of the turbine and reused as boiler feed water.

Table 3-6 Steam Turbine Basic Specifications

Item Specification

Type Tandem compound

TC4F

Output 650 MW (gross)

600 MW (net)

Steam Conditions

(turbine inlet)

Pressure: 26.4 MPa

Temperature: 600°C/610°C

Turbine Casing High and

Intermediate pressure: 1

Low pressure: 2

Extraction Stage High and

Intermediate pressure: 4

Low pressure: 4

High Pressure (HP), Intermediate Pressure (IP), Low pressure (LP)

(Source: prepared by the Study Team)

Table 3-7 Steam Turbine BOP Device Specifications

Item Specification

Condenser Single Shell type

Feed Water Heater High pressure: 3 heaters

Low pressure: 4 heaters

Horizontal U-tube type

Deaerator Single Shell type

Condensate pump 100% × 2

Condensate booster pump 100% × 2

(Source: prepared by the Study Team)

Page 117: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-19

Figure 3-7 Steam Turbine Bird’s Eye View (600 MW Class)”

(Source: prepared by the Study Team)

c) Steam Turbine Auxiliary Machine

(i) Condenser

Figure 3-8 shows Bird’s Eye View of the condenser.

Figure 3-8 Condenser Bird’s Eye View

(Source: prepared by the Study Team)

HP/IP Combined Casing

2LP Casing ( 4 Flow )

Page 118: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-20

(ii) Feed-water heater and deaerator

Figure 3-9 and 3-10 shows Bird’s Eye View of the feed-water heater and deaerator :

Figure 3-9 High and Low Pressure Feed Water Heater

(Source: prepared by the Study Team)

Figure 3-10 Deaerator

(Source: prepared by the Study Team)

Page 119: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-21

d) Generator

The structure of the generator is shown in the Figure 3-11 by a bird's-eye view. This structure is typical structure

based on many experiences in the past.

Figure 3-11 Generator Bird’s Eye View

(Source: prepared by the Study Team)

Page 120: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-22

e) Generator Auxiliary Machines

(i) Seal oil system

Seal oil system is to seal hydrogen to cool rotor and core in a generator. The system removes impurities by

vacuum processing from separated oil from lubrication system and supplies oil to seal of generator both sides.

Generator inner pressure difference between hydrogen and seal oil are kept by mechanical differential pressure

control valve. The hydrogen side oil is returned to the lubricant oil system after hydrogen removal at extended

batch and float trap, and mixture the oil of the air side at air extraction tank.

(ii) Cooling system

Stator cooling system is to supply high purity water to stator coil of water cooling. After the water which raised

purity at ion exchange tower is pressurized with a pump, and having cooled off with an air conditioner, it is

controlled to regulated temperature at a temperature control valve. The pure water is transported to stator coil

through the membrane filter. The rotor cooled by hydrogen gas is composed of a hydrogen gas cooler, a hydrogen

gas cylinder storage, etc.

Page 121: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-23

f) Instrument & Control System

(i) Basic concept

Start, stop and normal operation of the plant is operated by the minimum number of staff in the central control

room.

All necessary plant operation information is constantly monitored at the operator station of central control room.

Large-scale screen is not but can be installed in the central control room. The reason is appropriate number of

operator station is installed in the central control room including the operator station for exclusive use of the

leader.

Minimum hardware controller as the urgent operation of the plant is installed.

At the time of accident of main and auxiliary equipment, runback to low load or safely stop without needing the

regulated manual operation will start.

(ii) Automation

i) Plant automatic start

The plant start is automated. But manual operation is necessary at plant cold start operations (electrical system, completion of each system finishing) and at the time of operations such as the following examples.

Circulating water system

Auxiliary steam system

Closed cooling water system

Compressed air system

Turbine oil system

Turbine turning system

Generator seal oil system

Generator hydrogen system

ESP insulator heating

Waste water system

FGD waste water treatment system

Manual operation is usually not required at the time of warm and hot start.

Page 122: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-24

ii) Plant normal operation

The test operation for check of the important equipment is conducted by the manual start operation from central

control room. Each test operation is conducted in response to the manual start order sequentially.

(Example)

Turbine main valve closing test

Turbine emergency oil pump start test

iii) Plant automatic shutoff

The automation range at the time of the plant stop is from normal operation to a condensate pump stop, and

meanwhile, the manual operation does not need.

At a long term maintenance stop by the plan of customer, manual operations are necessary such as the following

example after automatic shut off.

(Example)

Circulate water system

Vacuum break

Auxiliary steam system

Closed cooling water system

Compressed air system

Turbine oil system

Turbine turning system

Generator seal oil system

Generator hydrogen system

FGD waste water treatment system

Page 123: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-25

iv) Trip Interlock

Boiler, turbine and generator tripping interlock concept is shown in Table 3-8

Table 3-8 Tripping interlock concept

Event Concept

Boiler Failure Boiler will be tripped immediately by shutting-off of the fuel shut off

valve. Turbine will be concurrently tripped to prevent the wet steam due

to the tripping of the boiler by Boiler trip signal.

Turbine Failure Turbine will be tripped immediately by closing of the turbine valves, and

the bypass system will be activated. However, if the bypass system is not

activated, Boiler will be tripped immediately.

By Turbine trip, the Generator will be concurrently tripped, which means

the simultaneous opening of both generator circuit breaker and excitation

field.

Generator failure Generator will be immediately tripped by the simultaneous opening of

both generator circuit breaker and excitation field switch, and Turbine

will be concurrently tripped for stopping generator and preventing the

extended accident.

Grid failure Disconnecting from the grid, the plant will reduce the load to minimum

load by using the bypass system and continue the island operation.

(Source: prepared by the Study Team)

Page 124: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-26

g) Air Quality Control System-AQCS

The flue gas coming from the boiler has to be cleaned from hazardous substances.

At first the Electrostatic precipitator (ESP) will remove dust. In a second step the flue gas will be cleaned from the

SO2 by a flue gas desulphurisation plant (FGD).

(i) Electrostatic precipitator (ESP)

To separate the dust from flue gas one electrostatic precipitator (ESP) is arranged downstream of the regenerative

air preheater.

The flue gas passes through several fields arranged in series and parallel. While passing these fields, the

high-voltage electrode system of the ESP generates an electrical effect, which affects the flue gas flow in such a

manner, that the dust is separated from the gas.

Figure 3-12 ESP Bird’s Eye View

(Source: prepared by the Study Team)

Page 125: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-27

(ii) Flue gas desulphurisation plant (FGD)

The FGD mainly removes SO2 out of the flue gas and is based on a wet limestone process to produce gypsum as a

by-product.

The FGD consists mainly of:

Flue gas system

Absorber system

Oxidation Air System

Mist Eliminator System

Drainage System

Limestone Slurry System

Gypsum System

Process Water System

Figure 3-13 FGD Bird’s Eye View

(Source: prepared by the Study Team)

Page 126: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-28

3) Overview of the proposed Project

Project site has been prepared for the former expansion plan (225 MW x 3 units) in the existing Dobrotvirska

coal-fired power plant. This new project for No.9 unit is planned to adopt more efficient, ultra-supercritical (USC)

technology (main steam temperature: 600 oC, main steam pressure: 26.4 MPa). The USC technology installation

promotes Japanese manufacture’s participation on this project and reduces the emission of greenhouse gas such as

carbon dioxide.

It is supposed to export the generating power from this project to Poland. As a result, this project is expected to

contribute to the acquisition of foreign currency for Ukraine.

Table 3-9 shows project cost.

Table 3-9 Project cost

Item Unit Price

Power plant equipment and common equipment (civil, intake, discharge and

coal handling equipment) [US$ million] 790.9

Contingency funds [US$ million] 79.1

Project cost [US$ million] 870.0

Unit cost [US$/kW] 1,450

(Source: prepared by the Study Team)

Page 127: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

3-29

4) Solutions for the proposed Technologies and Systems Adoption

There is a great advantage of the higher plant efficiency to adopt USC technology. On the other hand, it is

important to train operator and maintenance staff because of the plant automation. Therefore, it is necessary to

equip a simulator of USC power plant and to enhance measures for operation and maintenance training.

Also feed water quality control is so important for USC power plant that it is necessary to have knowledge of feed

water quality control and training of feed water quality control for operation period.

Under EPC turn-key contract, the owner appraises guarantee item in contract form and no defect of equipment for

installation and commissioning-term, with the result that the power plant is taken over to the owner side.

In addition, various technical problems often occur after the commercial operation. It is necessary to be supported

by power plant experts to deal with the various technical problems.

Existing Dobrotvirska power plant is exporting the half of the generating power to Poland, utilizing 220kV

transmission line. On the other hand, 750kV transmission line, which is about 20 km from Dobrotvirska power plant

toward the south, is not being utilized because of nuclear power plant’s shutdown for long-term.

It is one of the alternatives to export power to Poland, taking advantage of this existing 750kV transmission line for

this project. In that case, it is necessary to construct a new 750kV transmission line and a substation for the

connection between the power plant and 750kV transmission line.

Page 128: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 129: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Chapter 4 Evaluation of Environmental and Social Impacts

Page 130: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 131: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-1

(1) Analysis of the Current Status of the Environmental and Social Aspects

1) Location of the Project Site

The project relates to the expansion of the existing Dobrotvirska Power Plant. The power plant site is located in

Kamenka-Bug district, Lviv State, approximately 50km northeast of Lviv City and 14km north of Kamenka-Bug

City. In the south side of the site, Dobrotvir Town is located and the north side also faces a village. Coal ash

disposal site of the power plant is located 1km south-southwest of the project site.

Figure 4-1 Location of the Power Plant Site

(Source: prepared by the Study Team from Google Map)

Dobrotvirska Power Plant

Kamenka-Bug City

Dobrotvirska Power Plant

Coal Ash Disposal Site

Kamenka-Bug Town

N

N

Page 132: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-2

2) Natural Environment

a) Meteorology

Ukraine is located at 44-52 degrees north latitude and 24-40 degrees east longitude. Northern and western areas

are in the cool temperature zone and have humid continental climate with relatively high precipitation. The

southeastern area has a dry steppe climate, and the Crimean Peninsula has a relatively mild Mediterranean

climate.

The southern area sometimes suffers a serious water shortage involving water supply restriction. Carpathian area

is the highest with yearly precipitation of 1,200-1,600mm, and the eastern area is the lowest with the yearly

precipitation of 300mm.

In Lviv which is the nearest major city from the power plant site, the annual average temperature is 7.1℃, the

annual average high temperature is 10.5 ℃, the annual average low temperature is 3.7℃, and the annual

precipitation is 600mm.

The monthly average temperature and the precipitation in Lviv are shown in Table 4-1

Table 4-1 Monthly Average Temperature and Precipitation in Lviv

Month Jan. Feb. Mar. April May June July Aug. Sept. Oct. Nov. Dec.

Average high

temperature

(℃)

-1 0 5 11 17 20 21 21 17 11 4 0

Average low

temperature

(℃)

-5 -5 -1 3 8 11 12 12 8 4 0 -3

Precipitation

(mm) 30 30 30 40 60 80 90 70 50 40 40 40

(Source: prepared by the Study Team from ZenTech Home Page)

Page 133: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-3

b) Geography

Half land of Ukraine is a flat field, with Polesye Marsh area in the north, Donetsk hills in the east, and the high

land stretching from Carpathian Mountains in the west. The flat field in the central and southern area is covered

with rich chernozem (black earth) and used for field of wheat and other crops. 5% of the land is a high land

stretching from Carpathian Mountains toward the southern area of Crimean Peninsula. The area around the power

plant site is a flat area without hills.

c) Rivers

Dnieper River flows through the center of Ukraine, Dniester River flows in the west, both toward Black Sea.

Dnieper, the third biggest river in Europe, next to Volga and Danube, is used not only for public water,

hydropower generation, but also for the main water traffic route.

There are no large rivers around the power plant site except small rivers and irrigation canals (Figure 4-2). A

reservoir, which is an artificial pond installed at the time of construction of the power plant and the town of

Dobrotvir, is located in the east area of the power plant site. This reservoir supplies cooling water and plant water

for the operation of the power plant, and thermal effluent is discharged from the discharge channel extending 1km

north and 6km south of the power plant and returns to the reservoir.

Figure 4-2 Rivers and Waterways Around the Power Plant

(Source: prepared by the Study Team from Google Map)

d) Ecosystem

The land of Ukraine is categorized into 3 zones in view of vegetation (Figure 4-3).

Dobrotvirska Power Plant

South Outlet

North Outlet

Page 134: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-4

・ Forest zone

The forest zone is located adjacent to Belarus, in latitude north of Kiev, consisting of low dump area covered

mainly with forest and marsh. The soil is poor and dairy is the main industry.

・ Forest steppe

Forest steppe extends in the south of the forest zone from Kirovohrad, crosses Donieper and up to Kremenchug

and Kharkiv. Adequate precipitation, mostly concentrated in spring and early summer, makes this area the richest

agricultural area of Ukraine, with sugar beet, autumn-sown wheat, corn, sunflower and various other crops.

・ Steppe zone

Steppe zone extends in the south of forest steppe. This is a flat area with few valleys and dry climate. Major crops

are autumn-sown wheat, corn and sunflower.

Plants living in Ukraine include 6,086 species of vascular plants, 5,227 species of fungi, 1,322 species of

bryophyte and 4,908 species of algae. Fauna living in Ukraine includes 35,000 species of insects, 117 species of

mammals, 400 species of birds, 21 species of reptiles, 17 species of amphibian, and 182 species of fish. 440

species of the above-described species are precious species. Forest zone is especially rich in precious plant

species.

There are 7,000 protected areas in Ukraine with the total area of 2.8million ha, of which forest zone is dominant.

Page 135: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-5

Figure 4-3 Vegetation in Ukraine

(Source: UKRAINE FAA119 BIODIVERSITY ANALYSIS: ACTIONS NEEDED FOR CONSERVATION, the

United States Agency for International Development (USAID), 2011)

Figure 4-4 Protected Areas of Ukraine

(Source: UKRAINE FAA119 BIODIVERSITY ANALYSIS: ACTIONS NEEDED FOR CONSERVATION, the

United States Agency for International Development (USAID), 2011)

Page 136: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-6

3) Environmental Pollution

a) Air Quality

The measurement of pollutant in the ambient air in Ukraine is conducted at over 162 points in 53 cities by

Hydromet (State Hydrometeorological Service). There are 6 monitoring stations on data in Liviv (Figure 4-5). The

monitoring stations have not been renewed since the time of Independence in 1991. The monitoring frequency is

once a day for PM, four times a day for SO2 and NO2. Continuous measurement conducted in Japan is not

performed.

The pollutants contained in the exhaust gas emitted from fixed emission sources such as the power plant is

measured by the State Ecological Inspectorate (SEI). The project area is located away from Liviv and the air

quality measurement by Hydromet is not likely to be conducted. There is no other large fixed emission source

near the power plant site, and the current air quality status is supposed to be mainly influenced by emission gas

from the power plant. The existing units of the power plant are equipped with scrubber or electrostatic

precipitators, but not with desulfurization and denitration equipment. There is information that the existing units

do not meet the emission standards of Ukraine and EU, and the current pollution level needs to be assessed.

Figure 4-5 Air Quality Monitoring Points in Ukraine

(Source: Environmental Performance Reviews UKRAINE Second Review, UNITED NATIONS, 2007)

b) Water Quality

The measurement of water quality in Ukraine is conducted at over 240 points with 374 measurement equipment in

151 water areas presumably by Hydromet mentioned above, and also by Ministry of Health and the state authority.

Page 137: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-7

The water quality data around the power plant site has not been acquired. There is no other large fixed discharge

source near the power plant site, and water discharge from agricultural activity in the surrounding area and sewage

discharged by the households are supposed to be the main water pollution source.

In this project, thermal effluent will be discharged from the discharge channel extending 1km north and 6km south

of the power plant into the reservoir. Considering that thermal effluent will be cooled down by heat release while

flowing in the discharge channel, and that the reservoir is quite large (200-500m width and over 10km length), the

temperature rise in the whole river is not predicted. The prediction of the extent area of temperature rise should be

conducted in the future.

c) Noise

The measurement result of noise level around the power plant site has not been acquired. It was confirmed during

the field survey that there is no other large noise generation source near the power plant site, and noise level

within the power plant site and near the boundary of the site is not significantly high. Nevertheless, the assessment

of the current noise level should be conducted; because there is a residential area in the north and south of the

power plant site.

d) Waste

Waste generated during the project operation includes coal ash and plaster. Coal ash disposal site is already

established, treating coal ash by slurry method. The vast area of the disposal site is still unused, having sufficient

capacity for coal ash disposal, and the capacity for plaster disposal is to be discussed. The reuse of coal ash and

plaster into brick and others is proposed by the project proponent. The capacity of disposal site and the feasibility

of reuse of waste are the issues to be considered.

Photo 4-1 Current Status of Coal Ash Disposal Site

(Source: prepared by the Study Team)

Coal Ash Slurry Outlet

Page 138: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-8

4) Social Environment

a) Land Use

The major area of Ukraine consists of fertile flatland (steppe) and hills, with a part of Carpathian Mountains (the

highest peak of Ukraine: 2,061m) in the west and Crimean Peninsula in the south. Approximately 58% of land in

Ukraine is used for agriculture, 13% meadowland and 18% forest area. The area around the power plant is used

primarily for agriculture, with relatively vast forest area.

b) Social Infrastructure

The above-described Dobrotvirska Town in the south of the site has been constructed in 1951 at the beginning of

the existing power plant project in the period of the former Soviet Union to accept workers for the power plant,

including the river and the artificial reservoir. The initial population was about 1,500, which has expanded today

to 6,500 inhabitants and remains in the same level since 2000. On the implementation of the project, already the

infrastructure such as accommodation, hospital and school had been established. The access road to the power

plant is the main road of the town.

Table 4-2 Population of Dobrotvirska Town

Year 1959 1970 1979 2001 2010 2011 2012 2013

Population 1,528 3,272 3,894 6,685 6,437 6,457 6,457 6,480

(Source: prepared by the Study Team from Wikipedia)

c) Traffic

Highway 17 running on the south of the project site and the railway station located in the west of Dobrotvirska

Town constitute the traffic network around the power plant site.

Page 139: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-9

(2) Environment Improvement Effects by Project Implementation

1) Environmental Mitigation Measures for Air Quality

In this project, the project proponent requests the compliance to European Union(EU)emission standards as well

as Ukraine domestic standards concerning air pollutant. The installation of the flue-gas treatment equipment

described below is the basic policy of this project in this context.

・ Sulfur Oxides(SOx)

As the existing units are not equipped with Flue Gas Desulfurization(FDG) system to absorb and remove SOx in

exhaust gas, SOx contained in exhaust gas is directly discharged into ambient air. It is proposed in this project to

install wet type flue gas desulfurization method of a limestone-gypsum method using lime as desulfurization

agent, which is globally used for its high removal efficiency (85-98%*).

(Source :(Environmental, Health, and Safety(EHS) Guidelines for Thermal Power Plant (International Finance

Corporation(IFC) / World Bank (WB), 2008)

・ Nitrogen Oxides(NOx)

As the existing units are not equipped with denitration system to absorb and remove NOx in exhaust gas, NOx

contained in exhaust gas is directly discharged into ambient air. It is proposed in this project to install: Selective

Catalytic Reduction (SCR)-type denitration system using ammonia as denitration agent, which is globally used for

its high removal efficiency (85-98%*).

(Source :(Environmental, Health, and Safety(EHS) Guidelines for Thermal Power Plant (International Finance

Corporation(IFC) / World Bank (WB), 2008)

・ Particle Matter (PM) (dust)

The existing units are equipped with an old-type wet scrubber that collects and removes PM in the exhaust gas. It

is proposed in this project to install Electro Static Precipitators(ESP), which is globally used for its high removal

efficiency (96.5-99.95 %*).

(Source :(Environmental, Health, and Safety(EHS) Guidelines for Thermal Power Plant (International Finance

Corporation(IFC) / World Bank (WB), 2008)

Electricity produced by this project is transmitted to Poland, and DTEK plans that it is based on the discharge

standards of the EU or less, such as not only emission standards Ukrainian.by reducing contaminant concentration

in the exhaust gas..

Page 140: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-10

Table 4-3 Target Values of Pollutant Concentration in Exhaust Gas in This Project

Pollutant Unit

Emission Standard Values in Ukraine EU Emission

Standard Values

(>300MW)

IFC /WB EHS Guidelines (Thermal

Power Plant:2008)

New Units (100MW and

over)

Regulation from 2016/1/1 for Existing Units

(applied to the generation capacity of Unit No. 5-8)

Solid Fuel, 600MW>,Non-degraded airshed

SOx mg/Nm3 200 400-2,000

(100~≦500MW) 150 850

NOx mg/Nm3 200 600

(≦500MW) 200 510

PM mg/ Nm3 30 100

(<500MW) 10 50

*: standard value is dry gas base, 0℃, 1 atm, O2 6% equivalent.

(Source: prepared by the Study Team)

2) Atmospheric Diffusion Estimation of Air Pollutants

The air diffusion estimation surrounding area is conducted to predict the environmental impact of the air

pollutants emitted from the power plant. The calculation was conducted on 1hour value and 24 hour value of SO2,

NO2, and PM10 to confirm the compliance with the respective environmental standards of Ukraine, EU and the

IFC/WB EHS Guideline.

The ground concentrations of air pollutants are estimated for two cases; in the operation of the existing units Nos.

5-8 and in the operation of the planned units in future. In the operation of new unit, it is estimated for three cases;

all existing units and new unit (case 1) ,the existing units Nos. 7-8 and new unit (case 2; the existing units Nos.

5-6 are abandoned.).and new unit only (case 3; the existing units Nos. 5-8 are abandoned due to very old.)

a) Calculation Formula

It is relatively flat surrounding the project site, and the ground concentrations of air pollutants are predicted using

the following Gaussian diffusion model which is used commonly in Western countries and Japan.

6

2z

2

2z

2

2z

2

zy

P 102σ

(z+He)-+exp

(z-He)-exp

y-・exp

Uσ2πσ

Qz)=y,C(x,

C : Ground concentration at a point R (m) below the downwind axis

Qp: Emission volume (g/s)

σy: Parameter in the horizontal direction (m)

σz: Parameter in the vertical direction (m)

u: Wind speed (m/s)

R: Horizontal distance between emission source and calculated point (m)

z: Ground height

He: Effective stack height (m)

Page 141: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-11

He=H+ΔH

H: Stack height (m)

ΔH: Stack elevation height (m): CONCAWE formula

ΔH= 0.175 QH1/2u-3/4

ΔH: Emission elevation height (m)

QH: Exhaust heat (cal/s)

u: Wind speed at the top of stack (m/s)

QH =ρ・Q・Cp・ ΔT

ρ: Emission gas density at 0 ℃ (cal/s) (1.293×103g/m3)

Q: Amount of exhaust gas per unit time (Nm3/s)

Cp: Constant pressure specific heat (0.24cal/K/g)

ΔT: Difference between emission gas temperature and atmospheric temperature (K)

Figure 4-6 Gaussian Diffusion Model Diagram

(Source: Lecture of Air Environment Prediction, Shinichi Okamoto, 2001)

b) Calculation Conditions

1 hour value and 24 hours value were calculated. 24 hours value is calculated under the condition that wind

direction does not change in 24 hours, and considering that wind direction varies with time under natural

condition and so does the diffusion direction, the calculated concentration is higher than the actual diffusion.

c) Meteorological Conditions

The ground concentration of the pollutants discharged from the stack heavily depends on the diffusion

parameter for each of the wind speed and atmospheric stability, as shown in the aforementioned calculation

formula. Calculation simulation is conducted under the conditions shown in Table 4-4 based on the stability

EEffffeeccttiivvee eemmiissssiioonn

ssttaacckk hheeiigghhtt

pplluummee

ssttaacckk

((00,,00,,00))

WWiinndd

σσyy

DDiiffffuussiioonn ppaarraammeetteerr

σσzz

DDiiffffuussiioonn ppaarraammeetteerr

AAssssuummeedd oouuttlleett ooff

EEmmiissssiioonn ggaass

Page 142: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-12

and wind speed indicated in the atmospheric stability classification of Pasquill. From the atmospheric

stability indicated in the atmospheric stability classification of Pasquill, the normal meteorological condition

is selected air stability B to D based on the following reasons.

・ Air stability A is applicable to the emission source near the ground level, but the condition at the stack

height of 100m is less stable than on the ground level.

・ In Air stability E and F, ground concentration tends to be much lower compared to other air stability

condition in a flat geography.

Table 4-4 (1) Setting Conditions for Stability and Wind Speed

Stability Wind speed conditions at ground level (m/s)

Unstable B 1.0, 2.0, 3.0, 4.0

Neutral C 2.0, 3.0, 4.0,6.0,10.0

D 1.0, 2.0, 3.0, 4.0, 6.0,10.0

Table 4-4 (2) Pasquill Stability Categories

Wind speed at ground level

U (m/s)

Daytime Nighttime (rate of solar radiation = 0)

Rate of solar radiation Q (unit 0.01 kWm-2) 60 < Q 30 – 59 15 - 29 1 - 14

U < 2.0 A A-B B D F 2.0 - 2.9 A-B B C D E 3.0 - 3.9 B B-C C D D 4.0 - 5.9 C C-D D D D 6.0 < U C D D D D

(Source: Lecture of Air Environment Prediction, Shinichi Okamoto, 2001)

d) Exhaust Emission Conditions

The data on the amount of emission of pollutant from the existing units Nos.5-8 has not obtained. Therefore, the

amounts of gas emission and pollutants are calculated from the ratio of fuel use (100:94) and power generation

ratio (600:100 or 600:150) per unit generation amount of the existing and the new unit, based on the value of

exhaust gas specification at the USC boiler outlet calculated from characteristics of typical coal used in this

project. As the existing boiler is 50-60 years old and the document of data on the emission amount etc. is not

available, the re-examination of the monitoring data of the power plant is necessary.

Table 4-5 describes the exhaust gas flow, emission gas temperature, stack height, and emission amount of the

respective pollutant used for calculation. The calculation is conducted on the assumption that SOx, NOx and dust

are entirely converted into sulfur dioxide, nitrogen dioxide and suspended particulate matter (PM10). Stack height

is set to 200m so that stack height 2.5 times higher than the surrounding building (boiler building) is assured to

avoid the influence of such building to smoke diffusion.

Page 143: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-13

Table 4-5 Exhaust Emission Data Used for the Simulation

Item Unit

Existing Units New Unit

Unit 5 Unit 6 Unit 7 Unit 8 Unit 9

Reference

(boiler

outlet)

Power Generation MW 100 100 150 150 600 600

Exhaust Gas Flow (wet) x1,000Nm3/h 338 338 507 507 1,905 1,905

Exhaust Gas Flow (dry) x1,000Nm3/h 312 312 468 468 1,760 1,760

Exhaust Gas Temperature °C 140 140 140 140 95 140

Exhaust Gas Velocity m/s 6.6 10.0 23 -

Stack Height m 105 120 200 -

Stack Inner Diameter m 6 6 6 -

Sulfur Dioxide (SO2) emission

concentration: dry-gas base

concentration (*26% equivalent)

mg/Nm3 3,132

(2.780)

3,132

(2.780)

3,132

(2.780)

3,132

(2.780)

169

(150)

3,132

(2.780)

Nitrogen Dioxide (NO2) emission

concentration: dry-gas base

concentration (*26% equivalent)

mg/Nm3 563

(500)

563

(500)

563

(500)

563

(500)

225

(200)

563

(500)

Particulate matter (PM): dry-gas

base concentration (*26%

equivalent)

mg/Nm3 112

(100)

112

(100)

112

(100)

112

(100)

11

(10)

38,870

(34.500)

Sulfur Dioxide (SO2) emission rate kg/h 977 977 1,466 1,466 297 5,512

Nitrogen Dioxide (NO2) emission

rate kg/h 176 176 263 263 396 991

Suspended particulate matter

emission rate (PM) kg/h 35 35 52 52 20 68,411

Notes:

1) The data for PM emission concentration and emission rate is calculated from the emission standard (100 mg/Nm3) of the existing

units in Ukraine, since dust collection efficiency is not known.

2) The emission concentrations and emission rates of SOx, NOx and PM for the new boiler were set to the value compliant to the EU

emission standards.

3) O2 concentration of dry gas is set to 4.1%.

4) The exhaust gas temperature for the new boiler is set with consideration to raising up of temperature again in order to enhance

diffusion effect, since the temperature decreases by the desulfurization system.

(Source: prepared by the Study Team

e) Calculation Results

First the ground concentrations of SO2 (1 hour value) for the existing Units 5-6, Units 7-8 and the new Unit 9 are

simulated, because the emission amount of SOx is large. The results are shown in Figure 4-7. The emission

Page 144: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-14

concentrations from the existing Units 5-6, Units 7-8 and the new Unit 9 become highest under the condition of

stability B and ground wind speed of 1m/s.

Under any meteorological conditions, the maximum ground concentrations for the existing Units 5-6 and Units

7-8 are more than 10 times higher than the new Unit 9. In certain points, the pollutants in the ambient air are

assumed to already exceed the environmental quality standards for air at this time. In the future operation period

of the new Unit 9, ambient air quality surrounding the project site should be improved to meet the environmental

quality standards for air.

Page 145: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-15

Figure 4-7(1) Predicted Ground Concentration of SOx for Each Stability/Wind Speed (Existing Units 5-6)

SOx-StabilityB

0

40

80

120

160

200

0 5000 10000 15000 20000 25000 30000

m

μg/

m3

1

2

3

4

SOx-StabilityC

0

40

80

120

160

200

0 5000 10000 15000 20000 25000 30000

m

μg/m3

2

3

4

6

10

SOx-StabilityD

0

40

80

120

160

200

0 10000 20000 30000 40000 50000

m

μg/

m3

1

2

3

4

6

10

(Source: prepared by the Study Team)

Wind speed

(m/s)

Wind speed

(m/s)

Wind speed

(m/s)

Page 146: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-16

Figure 4-7(2) Predicted Ground Concentration of SOx for Each Stability/Wind Speed (Existing Unit 7-8)

SOx-StabilityB

0

50

100

150

200

250

0 5000 10000 15000 20000 25000 30000

m

μg/m3

1

2

3

4

SOx-StabilityC

0

50

100

150

200

250

0 5000 10000 15000 20000 25000 30000

m

μg/m3

2

3

4

6

10

SOx-StabilityD

0

50

100

150

200

250

0 10000 20000 30000 40000 50000

m

μg/

m3

1

2

3

4

6

10

(Source: prepared by the Study Team)

Wind speed

(m/s)

Wind speed

(m/s)

Wind speed

(m/s)

Page 147: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-17

Figure 4-7(3) Predicted Ground Concentration of SOx for Each Stability/Wind Speed (New Unit 9)

SOx-StabilityB

0

5

10

15

20

0 5000 10000 15000 20000 25000 30000

m

μg/m3

1

2

3

4

SOx-StabilityC

0

5

10

15

20

0 5000 10000 15000 20000 25000 30000

m

μg/m3

2

3

4

6

10

SOx-StabilityD

0

5

10

15

20

0 10000 20000 30000 40000 50000

m

μg/

m3

1

2

3

4

6

10

(Source: prepared by the Study Team)

Wind speed

(m/s)

Wind speed

(m/s)

Wind speed

(m/s)

Page 148: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-18

Next, the possibility and extent of the future improvement of ambient air quality by stopping or decommissioning

the existing units is considered. Regarding the impact of the whole power plant, ground concentrations of

one-hour value and 24-hour value are simulated for following 4 cases. The calculations are conducted under the

condition of stability B (unstable) where ground concentrations are the maximum.

・ Current conditions: Existing Units 5-6 and Units 7-8 are in operation.

・ Future - Case 1: Existing Units 5-6, Units 7-8 and New Unit 9 are in operation.

・ Future - Case 2: Existing Units 5-6 are stopped or decommissioned; Units 7-8 and New Unit 9 are in

operation.

・ Future - Case 3: Existing Units 5-6 and Units 7-8 are stopped or decommissioned, and New Unit 9 are in

operation.

e)-1 SO2 (Table 4-6, Figure 4-8)

In the current status, the existing Units 5-8 are not equipped with desulfurization system. Exhaust gas is emitted

into the environment with the concentration exceeding the environmental quality standards of Ukraine, EU and

IFC/WB. In this context, the maximum ground concentration of SO2 emitted from the existing units is 408μg/m3

for 1-hour value and 216μg/m3 for 24-hour value, indicating that both 1-hour and 24-hour values exceeds the EU

standard by only impact of the power plant.

In Case 1 where the new Unit 9 will be installed, concentration slightly increases (one-hour value: 422μg/m3,

24-hour value: 223μg/m3). Both 1-hour and 24-hour values exceeds the EU standard by only impact of the power

plant, similar to the current status.

In Case 2 where the existing Units 5-6 will be stopped or decommissioned, and the existing Units 7-8 and the new

Unit 9 is in operation, the impact of the power plant decreases (one-hour value: 229μg/m3, 24-hour value:

121μg/m3).

In Case 3 where the existing Units 5-6 and 7-8 will be stopped or decommissioned, and the new Unit 9 is in

operation, the impact of the power plant largely decreases, the maximum ground concentration is 15.1μg/m3 for

1-hour value and 8.0μg/m3 for 24-hour value, double-digit lower than other 24-hour values, satisfies the EU

standard and the Ukrainian standard.

e)-2 NO2 (Table 4-6, Figure 4-9)

In the current status, the existing Units 5-8 are not equipped with denitration system. Exhaust gas is emitted into

the environment with the concentration exceeding the environmental quality standards of Ukraine, EU and

IFC/WB. In this context, the maximum ground concentration of NO2 emitted from the existing units is not as high

as in case of SO2. One-hour value of 73.3μg/m3 and 24-hour value of 38.8μg/m3, which indicates that the impact

of the power plant, satisfies the EU standard for one-hour value and the Ukrainian standard for 24-hour value.

Page 149: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-19

In Case 1 where the new Unit 9 will be installed, the concentration slightly increases up to one-hour value of

91.9μg/m3 and 24-hour value of 48.6g/m3, indicating that the impact of the power plant satisfies the EU standard

for one-hour value but exceeds the Ukraine standard for 24-hour value, as is the case in the current status.

In Case 2 in which the existing Units 5-6 will be stopped or decommissioned, the impact of the power plant

decreases (one-hour value: 58.0μg/m3, 24-hour value: 30.7μg/m3).

In Case 3 where the existing Units 5-6 and 7-8 will be stopped or decommissioned, the impact of the power plant

largely decreases (one-hour value: 20.2μg/m3, 24-hour value: 10.7μg/m3), meeting both EU and Ukrainian

standards.

e)-3 PM10 (Table 4-6, Figure 4-10)

In the current status, the existing Units 5-8 are equipped with dust collection system to improve concentration of

exhaust gas to meet the environmental quality standards of Ukraine, IFC/WB and EU. Thus, the maximum ground

concentration of PM10 from the existing units is 14.5μg/m3 in one-hour value and 7.7μg/m3 in 24-hour value,

indicating that the impact of the power plant meets the EU standard.

In Case 1 where the new Unit 9 will be installed, the concentration rises only slightly, 15.5μg/m3 for one-hour

value and 8.2μg/m3 for 24-hour value, indicating that the impact of the power plant well meets the EU standard.

In Case 2 in which the existing Units 5-6 will be stopped or decommissioned, the impact of the power plant

decreases (one-hour value: 8.6μg/m3, 24-hour value: 4.5μg/m3).

In Case 3 where the existing Units 5-6 and Units 7-8 will be stopped or decommissioned, the impact of the power

plant farther decreases (one-hour value: 1.0μg/m3, 24-hour value: 0.5μg/m3), well meeting EU standards.

Page 150: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-20

Table 4-6 Maximum Ground Concentration Prediction Results (Stability B (unstable)) (unit: μg/m3)

Pollutant

Measured Time

Current status Future Case 1 Future Case 2 Future Case 3 Environmental Quality Standard

Maximum

Ground Concentration

Distance

(km)

Maximum

Ground Concentration

Distance

(km)

Maximum

Ground Concentration

Distance

(km)

Maximum

Ground Concentration

Distance

(km)

Ukraine

EU

IFC/WB EHS

Guideline(general)

Japan

SO2

1hr 408 3.1 422 3.2 229 3.5 15.1 3.9 500 (20 min)

350 500

(10 min) 262

24hr 216 3.2 223 3.2 121 3.5 8.0 3.9 50 125 125

(Interim target 1)

105

NO2

1hr 73.3 3.2 91.9 3.3 58.0 3.6 20.2 3.9 200 (20 min)

200 200

(guideline)

-

24hr 38.8 3.2 48.6 3.3 30.7 3.6 10.7 3.9 40 - - 113

PM1

0

1hr 14.5 3.2 15.5 3.2 8.6 3.5 1.0 3.9 - - - 200

24hr 7.7 3.2 8.2 3.2 4.5 3.5 0.5 3.9 - 50 150

(Interim target 1)

100

(Source: prepared by the Study Team)

Page 151: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-21

Figure 4-8 (1) Ground Concentration Prediction Results for SO2 (Current Status: Existing Units 5-8)

Figure 4-8 (2) Ground Concentration Prediction Results for SO2

(Future Case 1: Existing Units 5-8 and New Unit 9)

(Source: prepared by the Study Team)

Wind Speed (m/s)

Stability B

Stability B

Wind Speed (m/s)

Page 152: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-22

Figure 4-8 (3) Ground Concentration Prediction Results for SO2

(Future Case 2: Existing Units 7-8 and New Unit 9)

Figure 4-8 (4) Ground Concentration Prediction Results for SO2 (Future Case 3: New Unit 9)

(Source: prepared by the Study Team)

Wind Speed (m/s)

Wind Speed (m/s)

Stability B

Stability B

Page 153: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-23

Figure 4-9 (1) Ground Concentration Prediction Results for NO2 (Current Status: Existing Units 5-8)

Figure 4-9 (2) Ground Concentration Prediction Results for NO2

(Future Case 1: Existing Units 5-8 and New Unit 9)

(Source: prepared by the Study Team)

Wind Speed (m/s)

Wind Speed (m/s)

Stability B

Stability B

Page 154: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-24

Figure 4-9 (3) Ground Concentration Prediction Results for NO2

(Future Case 2: Existing Units 7-8 and New Unit 9)

Figure 4-9 (4) Ground Concentration Prediction Results for NO2 (Future Case 3: New Unit 9)

(Source: prepared by the Study Team)

Wind Speed (m/s)

Wind Speed (m/s)

Stability B

Stability B

Page 155: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-25

Figure 4-10 (1) Ground Concentration Prediction Results for PM10 (Current Status: Existing Units 5-8)

Figure 4-10 (2) Ground Concentration Prediction Results for PM10

(Future Case 1: Existing Units 5-8 and New Unit 9)

(Source: prepared by the Study Team)

Wind Speed (m/s)

Wind Speed (m/s)

Stability B

Stability B

Page 156: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-26

Figure 4-10 (3) Ground Concentration Prediction Results for PM10

(Future Case 2: Existing Units 7-8 and New Unit 9)

Figure 4-10 (4) Ground Concentration Prediction Results for PM10 (Future Case 3: New Unit 9)

(Source: prepared by the Study Team)

Wind Speed (m/s)

Wind Speed (m/s)

Stability B

Stability B

Page 157: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-27

(3) Environmental and Social Impacts of the Project Implementation

1) JICA Guidelines

Japan International Cooperation Agency (JICA) proclaimed the new "JICA guidelines for environmental and

social considerations" (herein after "the new Guidelines") on April, 1st, 2010.

The objectives of the guidelines are to encourage Project proponents etc. to have appropriate consideration for

environmental and social impacts, as well as to ensure that JICA’s support for and examination of environmental

and social considerations are conducted accordingly. The guidelines outline JICA’s responsibilities and

procedures, along with its requirements for project proponents etc., in order to facilitate the achievement of these

objectives. In this guidelines, JICA requests “that Project proponents etc. fill in the screening form; the

information in this form will be a reference for the categorization of proposed projects.”, and “JICA conducts an

environmental review in accordance with the project category, and refers to the corresponding environmental

checklists for each sector when conducting that review as appropriate.”

2) Review Results of Environmental and Social Consideration

The project is to consider the expansion of the existing Dobrotvirska Power Plant. The environmental and social

consideration items, which are necessary at the next stage after this survey, are reviewed extensively using JICA

Environmental Checklist “2. Thermal Power Plant). Table 4-7 shows the review results of the environmental

checklist items at present. This checklist should be updated after the Environmental Impact Assessment(EIA) by

Ukraine in the next stage.

Table 4-7 JICA Environmental Checklist (2. Thermal Power Plant)

Category

Environmental Item

Main Check Items Major Impact

Impact Level (●: large, ○: small, ×: none)

Mitigation Measure to be Conducted and Necessary Consideration

1 Perm

its and Explanation

(1) EIA and Environmental Permits

(a) Have environmental assessment report (EIA reports) been officially completed?

- - This project relates to the alteration of the initial plan (225MW×3 units) that has been approved in 1990’s into 600MW×1unit. The EIA will be re-implemented according to the regulations of Ukraine.

(b) Have EIA reports been approved by authorities of the host country’s government?

- - The approval of the State authority will be acquired after the implementation of the EIA mentioned above.

(c) Have EIA reports been unconditionally approved? If conditions are imposed on the approval of EIA reports, are the conditions satisfied?

- - The conditions will be considered in the course of the EIA procedure by an authority.

(d) In addition to the above approvals, have other required environmental permits been obtained from the appropriate regulatory authorities of the host country’s government?

- - The reacquisition of necessary approval and permits may be needed according to the change of the initial project plan.

(2) Explanation to the local stakeholders

(a) Are contents of the project and the potential impacts adequately explained to the public based on appropriate procedures, including information disclosure? Is understanding obtained from the public?

- - The re-implementation of the EIA is needed according to the laws and regulations of Ukraine. The stakeholders explanation meeting will be held during the EIA process and the local people’s opinions will be appropriately collected.

Page 158: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-28

Category

Environmental Item

Main Check Items Major Impact

Impact Level (●: large, ○: small, ×: none)

Mitigation Measure to be Conducted and Necessary Consideration

(b) Are proper responses made to comments from the public and regulatory authorities?

- - The comments from the public will be appropriately corresponded.

(3) Consideration of the alternatives

(a) Are plural alternatives of the project plan considered (including the environmental social issues )?

- - The alternatives of generation method etc. will be considered according to the EIA procedure based on the laws and regulations of Ukraine, including environmental and social issues.

2 Pollution P

revention Measures

(1) Air quality

(a) Do air pollutants, such as sulfur oxides (SOx), nitrogen oxides (NOx), and soot and dust emitted by power plant operations comply with the country’s emission standards? Is there a possibility that air pollutants emitted from the project will cause areas that do not comply with the country’s ambient air quality standards?

・Sox, NOx and dust are generated from the coal-fired power plant ・Cumulative impact of the existing units

● ●

・It is necessary to introduce flue-gas desulfurization/denitration system in order to meet the emission standard of Ukraine applied to the installation of a new unit, emission standards of EU and IFC/WB EHS guidelines. ・ Quantitative survey, prediction, assessment in the EIA, including cumulative impact

(b) In the case of coal-fired power plants, is there a possibility that fugitive coal dust from coal piles, coal handling facilities, and dust from coal ash disposal sites will cause air pollution? Are adequate measures taken to prevent the air pollution?

・Flying coal dust ・Flying coal ash

○ ○

Implementation of mitigation measures currently used at the existing units (water sprinkling at the coal storage site, transportation of coal to the coal disposal site through slurry method)

(2) Water quality

(a) Do effluents including thermal effluents from the power plant comply with the country’s effluent standards? Is there a possibility that the effluents from the project will cause areas that do not comply with the country’s ambient water quality standards or cause a significant temperature rise in the receiving waters?

・Thermal effluent discharge ・Plant effluent discharge ・Cumulative impact of the existing units

● ○ ●

・ Installation of wastewater treatment plant to meet standards of EU, IFC/WB EHS guidelines for effluent (consideration of the capacity of the existing units, installation of additional treatment plant) ・ Quantitative survey, prediction, assessment in the EIA, including cumulative impact

(b) In the case of coal-fired power plants, do leachates from coal piles and coal ash disposal sites comply with the country’s effluent standards?

・Leachate from the coal storage site ・Leachate from ash disposal site

○ ○

・ Installation of wastewater treatment plant to meet standards of EU, IFC/WB EHS guidelines for effluent (consideration of the capacity of the existing units, installation of additional treatment plant) ・Preventive measures against leachate (check the permeability of the layer)

(c) Are adequate measures taken to prevent contamination of surface water, soil, groundwater, and seawater by the effluents?

Same as (a), (b) Same as (a), (b)

Same as (a), (b)

(3) Waste

(a) Are wastes (such as waste oils, and waste chemical agents), coal ash, and by-product gypsum from flue gas desulfurization generated by the power plant operations properly treated and disposed of in accordance with the country’s standards?

・Generation of coal ash ・Generation of plaster from desulfurization system ・Generation of waste oil and sludge

● ○ ○

・Confirmation of the capacity of the coal ash disposal site ・Consideration for reuse of coal ash and plaster ・ Continue implementation of waste disposal method used for the existing units

Page 159: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-29

Category

Environmental Item

Main Check Items Major Impact

Impact Level (●: large, ○: small, ×: none)

Mitigation Measure to be Conducted and Necessary Consideration

(4) Noise and Vibration

(a) Do noise and vibrations generated by the power plant operations comply with the country’s ambient standards, and occupational health and safety standards?

・ Noise from the machines and equipment ・ Cumulative impact of the existing units

○ ・Continuous implementation of noise mitigation method used for the existing units ・ Quantitative survey, prediction, assessment in the EIA, including cumulative impact

(5) Subsidence

(a) In the case of extraction of a large volume of groundwater, is there a possibility that the extraction of groundwater will cause subsidence?

× × Water used for the project is supplied from river water and not from ground water. Therefore, subsidence will not occur.

(6) Odor

(a) Are there any odor sources? Are adequate odor control measures taken?

Generation of residual ammonia

○ Appropriate injection of ammonia used in the flue gas denitration system

3 Natural E

nvironment

(1) Protected Areas

(a) Is the project site located in protected areas designated by the country’s laws or international treaties and conventions? Is there a possibility that the project will affect the protected areas?

Power generation equipment

× The project relates to the expansion of the existing power plant. The project site is not located within the protected area, and is distant from the nearest protected area.

(2) Ecosystem and biota

(a) Does the project site encompass primeval forests, tropical rain forests, ecologically valuable habitats (e.g., coral reefs, mangroves, or tidal flats)?

Power generation equipment

× The project relates to the expansion of the existing power plant, and there is no a natural forest within the site.

(b) Does the project site encompass the protected habitats of endangered species designated by the country’s laws or international treaties and conventions?

Power generation equipment

× The project relates to the expansion of the existing power plant, and the site does not include habitat of precious species of fauna and flora.

(c) If significant ecological impacts are anticipated, are adequate environmental protection measures taken to reduce the impacts on ecosystem?

Power generation equipment

○ The project relates to the expansion of the existing power plant. The project site is already developed and is not rich with flora and fauna.

(d) Is there a possibility that the amount of water (e.g., surface water, groundwater) used by the project will adversely affect aquatic environments, such as rivers? Are adequate measures taken to reduce the impacts on aquatic environments, such as aquatic organisms?

Acquisition of cooling water and plant water

○ ・Reconsideration of the acquisition of water amount required (decreased quantity of cooling water and increased quantity of denitrition) ・ Field and document surveys concerning organisms in rivers during the EIA process

(e) Is there a possibility that discharge of thermal effluents, intake of a large volume of cooling water or discharge of leachates will adversely affect the ecosystem of surrounding water areas?

・ Thermal effluent discharge ・ Discharge of wastewater from the plant ・ Cumulative impact of the existing units

● ○ ●

・ Installation of wastewater treatment plant to meet standards of EU, IFC/WB EHS guidelines for effluent (consideration of the capacity of the existing units, installation of additional treatment plant) ・ Quantitative survey, prediction, assessment in the EIA, including cumulative impact

Page 160: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-30

Category

Environmental Item

Main Check Items Major Impact

Impact Level (●: large, ○: small, ×: none)

Mitigation Measure to be Conducted and Necessary Consideration

4 Social Environm

ent

(1) Resettlement

(a) Is involuntary resettlement caused by project implementation? If involuntary resettlement is caused, are efforts made to minimize the impacts caused by the resettlement?

Land acquisition

× The project relates to the expansion of the existing power plant. The coal ash disposal site has already been installed, and further land acquisition and resettlement is not necessary.

(b) Is adequate explanation on relocation and compensation given to affected persons prior to resettlement?

ditto ditto Ditto

(c) Is the resettlement plan, including proper compensation, restoration of livelihoods and living standards developed based on socioeconomic studies on resettlement?

ditto ditto Ditto

(d) Will compensation paid before resettlement?

ditto ditto Ditto

(e) Is the compensation policy established in a document?

ditto ditto Ditto

(f) Does the resettlement plan pay particular attention to vulnerable groups or persons, including women, children, the elderly, people below the poverty line, ethnic minorities, and indigenous peoples?

ditto ditto Ditto

(g) Are agreements with the affected persons obtained prior to resettlement?

ditto ditto Ditto

(h) Is the organizational framework established to properly implement resettlement? Are the capacity and budget secured to implement the plan?

ditto ditto Ditto

(i) Is a plan developed to monitor the impacts of resettlement?

ditto ditto Ditto

(j) Is a grievance system developed?

ditto ditto Ditto

(2) Living and Livelihood

(a) Is there a possibility that the project will adversely affect the living conditions of inhabitants? Are adequate measures considered to reduce the impacts, if necessary?

Inflow of workers and increased economic activity

○ Enhancement of local activity by promotion of employment of local people and active utilization of the local companies.

(b) Is sufficient infrastructure (e.g., hospitals, schools, roads) available for the project implementation? If existing infrastructure is insufficient, is a plan developed to construct new infrastructure or improve existing infrastructure?

Inflow of workers and development of infrastructure

× The infrastructures in the town for the workers (school, hospital), reservoir, access road are already developed in the surrounding area of the power plant, since the exciting power plant had already constructed.

Page 161: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-31

Category

Environmental Item

Main Check Items Major Impact

Impact Level (●: large, ○: small, ×: none)

Mitigation Measure to be Conducted and Necessary Consideration

(c) Is there a possibility that large vehicle traffic associated with the project will affect road traffic in the surrounding areas? Are adequate measures considered to reduce the impacts on traffic, if necessary?

Increased traffic caused by construction vehicles

○ Prior notification of construction schedule, implementation of safety measures for vehicle traffics

(d) Is there a possibility that diseases (including communicable diseases, such as HIV) will be introduced due to immigration of workers associated with the project? Are adequate considerations given to public health, if necessary?

Increased traffic caused by construction vehicles

○ Prior notification of construction schedule, implementation of accident prevention measures for vehicle traffics

(e) Is there a possibility that the amount of water used (e.g., surface water, groundwater) and discharge of thermal effluents by the project will adversely affect existing water uses and uses of water areas (especially fishing)?

・ Water intake for cooling water and plant water ・ Thermal effluent discharge ・ Discharge of wastewater from the plant

○ ・Reconsideration of the amount of water needed (reduction of cooling water use and increase of desulfurization system water) ・Survey of fishing operation status

4 Social Environm

ent

(3) Heritage

(a) Is there a possibility that the project will damage the local archeological, historical, cultural, and religious heritage sites? Are adequate measures considered to protect these sites in accordance with the country’s laws?

Installation of power generation facility

× The project relates to the expansion of the existing power plant. There are no archaeological, historical, cultural, religious heritage sites within the project site.

(4) Landscape

(a) Is there a possibility that the project will adversely affect the local landscape? Are necessary measures taken?

Installation of power generation facility

× There are agricultural land and town around the project site, but no tourist site.

(5) Ethnic Minorities and Indigenous Peoples

(a) Are considerations given to reduce the impacts on culture and lifestyle of ethnic minorities and indigenous peoples?

Land acquisition

× The town for project workers has already been developed, and impact on the life of ethnic minorities and indigenous people is not predicted. The project relates to the expansion of the existing power plant and coal ash disposal site has already been developed.

(b) Does the project comply with the country’s laws for rights of ethnic minorities and indigenous peoples?

ditto ditto Ditto

(5) working conditions(including working safety)

(a) Is the project proponent not violating any laws and ordinances associated with the working conditions of the country which the project proponent should observe in the project?

Employment of workers

○ Laws and regulations concerning working environment should be checked.

(b) Are tangible safety considerations in place for individuals involved in the project, such as the installation of safety equipment which prevents industrial accidents, and management of hazardous materials?

Employment of workers

○ Fire preventive equipment and safety gear should be checked, including the equipment of the existing units.

Page 162: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-32

Category

Environmental Item

Main Check Items Major Impact

Impact Level (●: large, ○: small, ×: none)

Mitigation Measure to be Conducted and Necessary Consideration

(c) Are intangible measures being planned and implemented for individuals involved in the project, such as the establishment of a safety and health program, and safety training (including traffic safety and public sanitation) for workers etc.?

Employment of workers

○ Safety management, safety education, public sanitation, emergency management plan should be checked, including the equipment of the existing units.

(d) Are appropriate measures being taken to ensure that security guards involved in the project do not violate safety of other individuals involved, or local residents?

Employment of security personnel

○ Security personnel are placed at the entrance of the site at the existing power plant.

5 Others

(1) Impacts during construction

(a) Are adequate measures considered to reduce impacts during construction (e.g., noise, vibrations, turbid water, dust, exhaust gases, and wastes)?

・ Generation of dust ・ Generation of noise ・ Generation of turbid water ・ Generation of waste

○ The following mitigation measures should be taken in consideration of the nearby residential area. ・The rear deck of vehicles transporting sand and soil should be covered, and construction site and traffic road should be watered. ・Material-transportation vehicles should be kept in good condition. ・Piling activity should be limited to daytime to the possible extent. ・ Installation of drainage fitted to the geography and capacity prior to construction work. ・Pollutant should be appropriately managed similar to the existing units.

(b) If construction activities adversely affect the natural environment (ecosystem), are adequate measures considered to reduce impacts?

Land development

○ The project relates to the expansion of the existing power plant. The project site is already developed and is not rich with flora and fauna.

(c) If construction activities adversely affect the social environment, are adequate measures considered to reduce impacts?

・ Inflow of workers and increased economic activity ・ Increased traffic caused by construction vehicles

○ ○

・ Enhancement of local activity by promotion of employment of local people and active utilization of the local companies ・ Prior notification of construction schedule, implementation of accident prevention measures for vehicle traffics

(2) Accident prevention

(a) In the case of coal-fired power plants, are adequate measures planned to prevent spontaneous combustion at the coal piles? (e.g., sprinkler systems).

Combustion at the coal storage

The coal storage site should be equipped with a water sprinkler to prevent spontaneous fire, similar to the existing units.

(3) Monitoring

(a) Does the proponent develop and implement monitoring program for the environmental items described above that are considered to have potential impacts?

- - Regular monitoring of exhaust gas, effluent, ambient air quality, water quality, and noise according to the monitoring plan developed during the EIA process.

(b) Are the items, methods and frequencies included in the monitoring program judged to be appropriate?

- - Implementation of appropriate monitoring items, method and frequency in cooperation with the regulatory authority according to the monitoring plan developed during the EIA process.

Page 163: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-33

Category

Environmental Item

Main Check Items Major Impact

Impact Level (●: large, ○: small, ×: none)

Mitigation Measure to be Conducted and Necessary Consideration

(c) Does the proponent establish an adequate monitoring framework (organization, personnel, equipment, and adequate budget to sustain the monitoring framework)?

- - Development of monitoring organization according to the environmental management plan

(d) Are any regulatory requirements pertaining to the monitoring report system identified, such as the format and frequency of reports from the proponent to the regulatory authorities?

- - Report the results to the regulatory authority.

6 Note

Reference to Checklist of Other Sectors

(a) Where necessary, pertinent items described in the Power Transmission and Distribution Lines checklist should also be checked (e.g., projects including installation of electric transmission lines and/or electric distribution facilities).

- - The plan for transmission line will be considered.

(b) Where necessary, pertinent items described in the Ports and Harbors checklist should also be checked (e.g., projects including construction of port and harbor facilities).

- - Railways will be used for transportation. The installation of port facility such as jetty is not planned.

Note on Using Environmental Checklist

(a) If necessary, the impacts to transboundary or global issues should be confirmed (e.g., the project includes factors that may cause problems, such as transboundary waste treatment, acid rain, destruction of the ozone layer, and global warming).

- - High-efficiency USC (ultra supercritical) boiler is used to reduce CO2 emission per power generation compared to the existing units.

(Source: prepared by the Study Team)

Page 164: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-34

(4) Overview of the Laws and Regulations concerning Environmental-Social Considerations of the Host Country and the Measures needed for Clearing

1) Environmental Administration in Ukraine

In February 2002, MENR (Ministry of Environment and Natural Resources) was established in Ukraine as the

national governmental organization responsible for environmental administration, which was later reorganized

into MEP (Ministry of Environmental Protection) and State Committee for National Resources in September 2003.

MEP is responsible for the development and implementation of national regulations and policies concerning

environmental protection.

The Ministry consists of five departments supervising the activities of five inspectorates (ecological and forest at

the national level, and three sea inspectorates) with a total of approximately 4,000 staffs. The Ministry also

oversees the work of three State Services (Geological, Natural Reserves, and Geodesy and Cartography), five

research institutes and six state enterprises. Figure 4-11 describes the structure of the subordinated agencies of the

Ministry for Environmental Protection.

Figure 4-11 Structure of the Subordinated Agencies of the Ministry for Environmental Protection

(Source: UNITED NATION, ENVIRONMENTAL PERFORMANCE REVIEWS UKRAINE, 2007)

Page 165: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-35

2) Environmental Laws and Regulations in Ukraine

a) Environmental Protection Law

Over the first decade since the time Ukraine was declared independent in 1991, a system of ecological regulations

was being built in Ukraine. Of the principal legal documents referring to environmental protection, around 80.

The Environmental Protection Law approved in 1991 constitutes the main environmental regulation. It

encompasses a new policy and rules compared to the time of Soviet Union, as can be seen from the description

“Environmental protection, the rational use of natural resources, providing of ecological safety of vital functions

of man are an inalienable condition of permanent economic and social development of Ukraine”.

Other principal laws and regulations are:

・ 1992 Law on the protection of Atmospheric Air(1992, amended in 2001)

・ 1992 Land Code

・ 1993 Law on the Sanitary and Epidemiological Prosperity of Population

・ 1994 Forest Code

・ 1995 Water Code

・ 1995 Law on Environmental Examination

・ 1998 Law on Waste

・ 2001 The Law on Air Protection (Revision)

・ 2002 The procedure for approving investment programs and construction projects and performing complex

state environmental impact assessments (Cabinet of Ministers Resolution No. 483)

・ 2003 The State Construction Norms DBN A.2.2-1-2003 “Structure and content of the documentation for

environmental impact assessment (EIA) in designing and building industrial enterprises, buildings and

structures. Main regulations for design”

・ 2004 The Law on Environmental Audits

The system of the environmental law and regulations in Ukraine is complicated: the United Nation’s

Environmental Performance Review Report pointed out that “it should be more systematically-organized to be

consistent with the regulation system of EC (European Commission) laws of EU”.

b) Law on the Protection of Atmospheric Air

The ambient air quality standards are regulated by State Sanitary rules for Air Protection from Pollution (with

Chemical and Biological Agents) in Human Settlements, the MOH on 09.07.1997 № 201 in Ukraine. 24-hours

average concentration, the maximum allowable concentration, and risk classification are established for 509

materials. The standard values for PM2.5 and PM10 are not established in Ukraine. The standard value for dust is

regulated based on the dust types and the content rate of silicon compounds, not on particle sizes.

Table 4-8 Ambient Air Quality Standards (μg/m3)

items Ukraine1 EU2 IFC3

Maximum 500 - 500(10min)

SO2 One-hour value - 350 -

24-hour value 50 125 125(Target

Value 1)

Maximum 200 - -

NO2 One-hour value - 200 200

24-hour value 40 - -

Annual average - 40 40

Page 166: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-36

NO Maximum 400 - -

24-hour value 60 - -

PM10 24-hour value - 50 150(Target

Value 1)

Annual average - 40 70(Target Value

1)

PM2.5 24-hour value - - 75(Target Value

1)

Annual average - 25

35(Target Value

1)

1. State sanitary rules for air protection from pollution (with chemical and biological agents) in human

settlements, the MOH on 09.07.1997 № 201

2. Directive 2008/50/EC of the European Parliament and of the Council of 21 May 2008 on Ambient Air

Quality and Cleaner Air for Europe

3. Environmental, Health, and Safety Guidelines, General

(Source: prepared by the Study Team)

The emission standard of hazardous materials from over 50MW thermal power plant is regulated by MEP Order

No. 541 of October 22, 2008 in Ukraine. Table 4-9 and 4-10 indicate the emission standard applied to the existing

unit and the new unit, respectively.

Page 167: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-37

Table 4-9 Emission Standards for the Existing Units (mg/Nm3)

Item Ukraine1(>50MW)

EU2

(>300MW) IFC3

(Boiler) Before 2015/12/31

After 2016/1/1

Dust 1,000 50(≧500MW) 100(<500MW)

10 50

SO24 400-5,100

2,000 (≦100MW) 400-2,000(100~≦500MW)

400 (>500MW) 150

200-850 (≧600MW)

NOx 400-2,000 600(≦500MW) 200(>500MW)

200 510

CO 250 250 - -

Notes: solid, O26%

1. On adoption of limit values on emission of pollutants from power-generating units with nominal capacity

more than 50MW, MEP Order No. 541 of October 22, 2008

2. Directive 2010/75/EC of the European Parliament and of the Council of 24 November 2010 on industrial

emissions (integrated pollution prevention and control)

3. Environmental, Health, and Safety Guidelines for Thermal Power Plants

4. In case the power plant is operated for 2,000 hours a year until 2015/12/31 and 1,500 hours a year from

2016/1/1, SO2 emission standard of 800 (mg/Nm3) is applied.

(Source: prepared by the Study Team)

Table 4-10 Emission Standards for the new unit (mg/Nm3)

Item Ukraine1

(>100MW) EU2

(>300MW) IFC3

(Boiler)

Dust 30 10 50

SO2 200 150 200-850

(≧600MW) NOx 200 200 510 CO 250 - -

Notes: solid, O26%

1. On adoption of limit values on emission of pollutants from power-generating units with nominal capacity

more than 50MW, MEP Order No. 541 of October 22, 2008

2. Directive 2010/75/EC of the European Parliament and of the Council of 24 November 2010 on industrial

emissions (integrated pollution prevention and control)

3. Environmental, Health, and Safety Guidelines for Thermal Power Plants

(Source: prepared by the Study Team)

c) Water Quality Regulations

In Ukraine, the Environmental Quality Standards for water are established based on the standards of the Soviet

Union period (The Maximum Permissible Concentrations of Hazardous Substances in Water of Water Bodies,

Used for Industrial, Drinking, Cultural and Domestic Water Use (1,345 substances) (4/7/88)). The water quality

standards in Ukraine regulate the safety standard concerning water use, water quality standard for water

area/system and the maximum allowable concentrations, and not the total discharge amount. The maximum

allowable concentrations are usually determined according to the environmental quality standards of the

relevant water system/area by the experts of MEP, etc. Table 4-11 describes the environmental quality standards

for water.

Page 168: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-38

Table 4-11 Environmental Quality Standards for Water

Parameter Unit Maximum Allowable

Concentration pH - 6.5-8.5 Ammonia mg/l 2.0 NO3 mg/l 45.0 NO2 mg/l 3.3 Arsenic mg/l 0.05 Lead mg/l 0.03 Cr3 mg/l 0.5 Cr6 mg/l 0.05 Cadmium mg/l 0.001 Copper mg/l 1.0 Nickel mg/l 0.1 Mercury mg/l 0.0005 Zinc mg/l 1.0 Fluorides mg/l 1.5 Sulfates mg/l 500.0 Iron mg/l 0.3 PO4 mg/l 3.5 Cobalt mg/l 0.1

(Source: prepared by the Study Team)

d) Noise

The noise standards in Ukraine are established based on the standard values settled in the period of Soviet Union

(DBN360-92 State sanitary regulations for settlement planning and development, 1996)(Table 4-12).

Table 4-12 Noise Standards

Central frequency of the octave-band (Hz) Equivalent sound

level (LAeq) 63 125 250 500 1,000 2,000 4,000 8,000 Day(dB) 75 66 59 54 50 47 47 43 55dB(A)

Night(dB) 67 57 49 44 40 37 37 33 45dB(A)

(Source: State Sanitary Regulations)

e) Natural Environmental Protection

The Government of Ukraine approved “the Strategy for National Environmental Policy in Ukraine to 2020” on

December 21, 2010. A National Action Plan for Environmental Protection in Ukraine for 2011-2015, was

developed during the last half of 2010 for implementing the above Strategy. On December 15, 2010, the Cabinet

of Ministers of Ukraine approved a draft funding agreement "On Support for the Implementation of the Strategy

for the National Environmental Policy of Ukraine."

Ukraine’s key environmental laws and legislated programs on biodiversity conservation and protected areas

include:

・ Environmental Protection Act: The Act that sets up the overall environmental framework for all

environmental activities.

・ Land Code: Ukraine’s land use legislation, it is supposed to ensure “rational land use and protection of

lands,” as well as “environmental security.” The Land Code divides all lands of Ukraine into nine

categories by the purpose of their end use, including four categories especially relevant to biodiversity

conservation, protected areas, forest lands, agricultural lands, and water lands.

・ Protected Areas Act: The main framework to establish classification and effective use of protected areas in

Ukraine.

・ Forest Code: The Forest Code covers not only forested lands, but all lands supervised by the State Forestry

Page 169: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-39

Committee, which include many wetlands and certain agricultural lands.

・ Water Code: defines roles and responsibilities of state institutions in water management, briefly mentioning

that waters found within protected areas are thereby protected.

・ Law on Ecological Expertise (IEE) (1995): The framework for environmental impact assessments (EIAs)

that apply to new projects that may have adverse impacts on the environment.

・ Law on the Ukraine Nature Reserve Fund (1992)

・ Law on Animals (2001)

・ Law on Plants (1999)

・ Law on the Red Book of Ukraine (2002)

・ Law on Environmental Audits (2004)

・ National Program for Establishment of the Ecological Network (EcoNet) in Ukraine in 2000-2015: The

objective of the program is to establish an EcoNet in Ukraine by 2015 in a manner compatible with the

pan-European EcoNet. The EcoNet has 3 tiers -natural regions (which normally should have a protected

area as its core), buffer zones, and corridors. One of the key objectives of the EcoNet Program is to extend

the EcoNet coverage and thus maintain as much as possible of ecosystems in their natural condition, while

allowing for sustainable economic activities (both within and outside of protected areas).

・ Action Program for Biodiversity Conservation and Protected Area Management in Ukraine through 2020:

The Program calls for the establishment of a representative and well-managed protected area network, the

“Ecological Network” or “EcoNet,” by 2020.

f) Hazardous Materials and Waste Management

The laws and regulations concerning waste management in Ukraine includes:

・ On Approval of the Regulation on Development, Approval and Amending of Waste Production and

Disposal Limits, No. 1218, 3 August 1998, with amendments No. 1518 of 11.10.2002.

・ On Approval of the Regulation on the Register of Waste Disposal Sites, No. 1216, 3 August 1998.

・ On Approval of the Regulation on the Register of Waste Production, Treatment and Utilization Objects,

No.1360, 31 August 1998.

・ On Approval of the Regulations on Control of the Transboundary Movement, Utilization and Elimination

of Hazardous Waste and Yellow and Green Lists of Dangerous Chemical Substances, No. 1120, 13 July

2000, with amendments No. 1481 of 28.09.2000 and No. 1518 of 11.10.2002.

・ The law of Ukraine from March 5, 1998 of No. 187/98-BP "About waste" (current state on 16.10.2012)

・ The resolution of the Cabinet of Ministers of Ukraine from September 11, 1996 of No. 1100 "About the

Procedure for development and approval of standard rates of maximum permissible waste interception of

polluting substances and the list of the polluting substances, which waste interception is normalized"

(current state on 17.10.2012)

3) Outline of the EIA of the Host Country needed for the Project Implementation and the Measures to be taken

a) EIA (Environmental Impact Assessment) in Ukraine

The EIA system in Ukraine is established on the basis of the system from the time of Soviet Union. The EIA

system is regulated by plural statute laws, guidelines and national standards, and the amendments of regulation

are in progress in order to adapt the EIA procedure to the EU's EIA.

The EIA system constitutes a principal part of the approval for engineering (design) and construction, and is

mandatory for a national project or a project related to plural local administration and to be considered to have

high environmental risk. For a project with potential low risk, only a limited EIA approved by MEP and

Ministry of Health is required. Approximately 6,000 EIA are conducted in a year in Ukraine, most of which are

conducted in the stage of F/S survey in the early stage of the project.

Page 170: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-40

22 categories of projects excluding agriculture are considered as high-risk and required to conduct hearing of

the State Ecological Expertise (SEE)’s opinion. Expert’s opinion is required in a national, state, regional level.

Opinions of MEP expert are necessary in case of the project with investment of over 6 million dollars, whereas

opinions of expert of high level are generally not required in case of the project with investment less than 6

million. The following items are assessed by SEE.

・ Compliance with the Environmental Laws

・ Compliance with the local regulations

・ MAC (Maximum Allowable Cconcentration) of pollutants

・ Rational use of resources

・ Minimization of the environmental impact

In accordance with the amendment of the Law of Ukraine on amendments to certain laws of Ukraine concerning

the implementation of the provisions of the Convention on Environmental Impact Assessment in a

Transboundary Context, certification No. 318, the following items are required to be described in the EIA.

・ Description of the planned activities, which should include: a description of the physical characteristics of

the production facility and associated facilities, schedule of the construction, types and quantities of

materials to be used, etc.

・ Goals of the planned activities

・ Alternatives (territorial or technological, etc.)

・ Current status: population, fauna, flora, soil, water, air, climatic factors, cultural heritage, landscape, etc.

・ Potential impacts to the natural and social environment: the use of natural resources, emissions, discharges

of pollutants, noise, the implementation of waste management, etc.

・ Environmental impact prediction

・ Environmental impact mitigation measures: environmental protection measures, emission reduction

measures, etc.

・ Non-technical summary

・ Identification of problems

・ Comments and suggestions, which were received after the publication of the Statement of Intent

・ Outline for monitoring program

The EIA report, after including the opinions from the State Ecological Expertise (SEE), will finally be approved

by the cabinet council. The SEE endorsement is valid for 3 years from the date of issue. This means that if

construction does not start during this period, the whole EIA procedure would need start all over from the

beginning. The EIA approval procedure includes:

・ Submission of the “Statement of Intent” by the project proponent

・ Preparation of the EIA report by the project proponent

・ Opinions from the SEE

・ Public consultation

・ Final approval of EIA

In Ukraine, the implementation of public consultation and information disclosure concerning EIA is required by

the law during the approval process of the project. An EIA report is disclosed on the official website of the

government and opinions from the public invited. The procedure of the public consultation and information

disclosure is regulated by the MEP Order No.168 of 18/12, 2003.

b) Measures to be taken for the EIA

In Ukraine, the legal revision of the EIA is in progress according to the European legal systems. Paying attention

to the trend of these revisions, the EIA for the project needs to be implemented in the future.

Page 171: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-41

It is essentially important to disclose the information and conduct public consultation from the earliest possible

stage of the project’s EIA according to the laws and regulations of Ukraine and the environmental social

consideration guidelines of JICA and others, and thereby appropriately collecting the local people and

stakeholder’s opinions and reflecting them to the design, construction activity and operation of the project.

Page 172: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

4-42

(5) The Requirement for the Host Country (Project Proponent and other related Organizations) for the Implementation of the Project The project is planed for the expansion of the existing power plant. In view of the deterioration of the existing

units, the project proponent should develop the EIA report according to the laws and regulations of Ukraine based

on the result of the survey and prediction listed below, including the adequate consideration of

stopping/decommission of the existing units, efficiency of the fuel gas treatment system, water use, thermal

effluent discharge, taking special attention on the cumulative impact, in order to improve or not to deteriorate the

present status.

・ Air quality: assessment of the current pollution level

・ Water quality: assessment of the current water temperature of the reservoir in relation to the thermal

effluent discharge

・ Noise: assessment of noise level in the surrounding residential area

Page 173: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Chapter 5 Financial and Economic Evaluation

Page 174: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 175: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-1

(1) Project Cost Estimation

1) Construction Cost (Engineering, Procurement and Construction: EPC)

Based on the configuration diagram of the proposed power plant shown in Figure 3-3 Chapter 3 and the average

figure of the contract amounts of the recent USC coal-fired TPPs being used as a reference, EPC cost is estimated

as the Table 5-1. District heating shall be provided by the existing facilities and no cost is included for this

purpose.

Table 5-1 Construction Cost of 600MW USC Coal-Fired TPP

Item Cost Breakdown

Foreign (US$ mil) Local (UAH mil.) Total (US$ mil)

1 Boiler & Environmental Equipment 311.8 188.0 334.7

2 Steam Turbine Generator 213.2 56.4 220.1

3 Coal & Ash Handling Systems 73.4 56.4 80.2

4 I&C and Electrical Equipment 59.6 18.8 61.9

5 Mechanical Equipment 87.1 56.4 94.0

6 Civil & Installation Works incl. in the above incl. in the above incl. in the above

7 Sub-total 745.1 376.0 790.9

8 Contingency (10% of Sub-total) 74.5 37.6 79.1

9 Total 819.6 413.6 870.0

US$1=UAH8.20

(Source: prepared by the Study Team)

2) Initial Investment Cost

The following items are counted as the initial investment cost.

a) EPC cost shown in the above 1)

b) Construction cost of 750kV sub-station (S/S) and transmission line (T/L)

c) Costs for finance arrangement and approvals/licenses

d) Interest during the construction (IDC)

Table 5-2 Initial Investment Cost

Item Remarks Cost Breakdown

Foreign (US$ mil) Local (UAH mil) Total (US$ mil)

1 EPC Table 5-1 819.6 413.6 870.0

2 S/S and T/L T/L length: 20km 10.0 82.0 20.0

3 Other Costs 5% of (1+2 ) 41.5 24.8 44.5

4 IDC Table 5-3 50.5 0.0 50.5

Total 921.6 520.4 985.0

(Source: prepared by the Study Team)

Page 176: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-2

IDC is calculated, the following parameters being used.

a) Debt Amount: 80% of the sum of item no 1, 2 and 3 in Table 5-2

b)Disbursement: equal installment every 6 months for 4.5 years of construction period

c) Interest Rate: 3.00% JICA’s overseas investment and loan with the maturity of 25 years (5 years’ grace

and 20 years’ repayment) including 20 years’ swap spread for converting Yen to US$

Table 5-3 IDC Calculation

Year Disbursement (US$ mil) Loan Balance (US$ mil) Interest (US$ mil)

0.5 83.067 83.067 0.623

1.0 83.067 166.133 1.869

1.5 83.067 249.200 3.115

2.0 83.067 332.267 4.361

2.5 83.067 415.333 5.607

3.0 83.067 498.400 6.853

3.5 83.067 581.467 8.099

4.0 83.067 664.533 9.345

4.5 83.067 747.600 10.591

Total 747.60 50.46

(Source: prepared by the Study Team)

3) Running Cost

The following items are counted as the running cost.

a) Operation and Maintenance (O&M) Cost

b) Fuel Cost: 600,000kW÷ (1-0.078(own use)) x 24hrs x 310d/y (availability:85%) x 860kcal/kWh

(conversion)÷5,750kcal/kg (calorific value of coal)÷41%(efficiency of TPP) x US$0.09/kg (price of coal)

c) Land cost: 0 (since TPP will be constructed within the existing TPPs’ site)

d) Insurance costs are included in the above a).

e) Interest Rate: 3.00%, principal repayment in equal 40 installments (every 6 months for 20years)

f) Corporate Tax: 16% (The government has announced the rate shall be reduced to 16% in 2014.)

Table 5-4 Running Cost

Item Annual Cost

Foreign (US$ mil/year) Local (UAH mil/year) Total (US$ mil/year)

1 O&M Cost 10.0 164.0 30.0

2 Fuel Cost 0.0 1,303.8 159.0

3 Land Cost 0.0 0.0 0.0

4 Insurances included in above1 included in above1 included in above1

5 Interest Rate 3.00% 0.0 3.00%

6 Corporate Tax 0.0 16% 16%

US$1=UAH8.20

(Source: prepared by the Study Team)

Page 177: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-3

(2) Preliminary Financial and Economic Evaluation

1) Financial Internal Rate of Return (FIRR)

FIRR is calculated with the following preconditions:

① Selling price is US$60 per Mega Watt hour (MWh), which is advised by NERC as the current selling price

of electricity generated by coal-fired TPPs in Ukraine.

② Annual operation hours are 7, 440 hours (24hours/d x 310d/y (availability 85%)).

③ The efficiency of the plant is 41% and efficiency degradation or drop in output is not considered thanks to

adequate maintenance.

④ TPP’s own use of electricity is 7.8%.

⑤ Calorific value of fuel coal is 5,750kcal/kg and the price of coal is US$90/t.

⑥ 2.39%, which is the average figure of USA’s last 10 years, is used as the inflation rate, since the calculation

is made in US$. It is applied for the income and the operation cost from the next year of commercial

operation.

⑦ Construction period is 4.5 years, however “5 years” is used in this calculation. And commercial operation

starts on 6th year when the repayment stars too.

⑧ Depreciation period is 40 years. The same amount is depreciated in every year and the residual value is

zero.

⑨ Operation years are 40 years which is same as the depreciation period.

⑩ Debt equity ratio is 80%:20%.

The result is shown in Table 5-5 and FIRR is calculated at 8.11%.

As FIRR is bigger than 7.50~7.75% which are Ukrainian policy interest rates in the recent years, the project is

financially viable as far as the above preconditions are actual and reasonable ones.

Page 178: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-4

Table 5-5 FIRR Calculation

(Unit: US$ million)

(Source: prepared by the Study Team)

O&M DebtCost Repayment

1 2 3 4 5 6=2-3-4-5 7 8=6-7 9=8+5+4-11 189.39 -189.392 194.38 -194.383 199.36 -199.364 204.34 -204.345 197.49 -197.496 267.84 188.96 62.74 24.62 -8.48 0.00 -8.48 78.887 274.24 193.47 61.56 24.62 -5.42 0.00 -5.42 80.778 280.80 198.10 60.38 24.62 -2.30 0.00 -2.30 82.709 287.51 202.83 59.20 24.62 0.85 0.14 0.72 84.54

10 294.38 207.68 58.01 24.62 4.06 0.65 3.41 86.0511 301.41 212.64 56.83 24.62 7.31 1.17 6.14 87.6012 308.62 217.73 55.65 24.62 10.62 1.70 8.92 89.1913 315.99 222.93 54.47 24.62 13.97 2.24 11.74 90.8314 323.55 228.26 53.29 24.62 17.38 2.78 14.60 92.5115 331.28 233.71 52.10 24.62 20.84 3.33 17.50 94.2316 339.20 239.30 50.92 24.62 24.35 3.90 20.45 96.0017 347.30 245.02 49.74 24.62 27.92 4.47 23.45 97.8218 355.60 250.87 48.56 24.62 31.55 5.05 26.50 99.6819 364.10 256.87 47.38 24.62 35.23 5.64 29.59 101.6020 372.80 263.01 46.19 24.62 38.98 6.24 32.74 103.5621 381.71 269.30 45.01 24.62 42.78 6.85 35.94 105.5722 390.84 275.73 43.83 24.62 46.65 7.46 39.19 107.6423 400.18 282.32 42.65 24.62 50.58 8.09 42.49 109.7624 409.74 289.07 41.47 24.62 54.58 8.73 45.85 111.9425 419.54 295.98 40.28 24.62 58.65 9.38 49.27 114.1726 429.56 303.05 24.62 101.89 16.30 85.59 110.2127 439.83 310.29 24.62 104.91 16.79 88.12 112.7528 450.34 317.71 24.62 108.01 17.28 90.73 115.3529 461.10 325.30 24.62 111.18 17.79 93.39 118.0130 472.12 333.08 24.62 114.42 18.31 96.11 120.7431 483.41 341.04 24.62 117.75 18.84 98.91 123.5332 494.96 349.19 24.62 121.15 19.38 101.76 126.3933 506.79 357.54 24.62 124.63 19.94 104.69 129.3134 518.90 366.08 24.62 128.20 20.51 107.69 132.3135 531.31 374.83 24.62 131.85 21.10 110.76 135.3836 544.00 383.79 24.62 135.59 21.69 113.90 138.5237 557.01 392.96 24.62 139.42 22.31 117.11 141.7438 570.32 402.35 24.62 143.34 22.93 120.41 145.0339 583.95 411.97 24.62 147.36 23.58 123.78 148.4040 597.90 421.81 24.62 151.47 24.23 127.23 151.8641 612.19 431.90 24.62 155.67 24.91 130.77 155.3942 626.83 442.22 24.62 159.98 25.60 134.39 159.0143 641.81 452.79 24.62 164.40 26.30 138.09 162.7244 657.15 463.61 24.62 168.91 27.03 141.89 166.5145 672.85 474.69 24.62 173.54 27.77 145.77 170.40

984.96 1,030.27 984.96 2,663.36 3,693.63

FIRR 8.11%

PAT Cash FlowYear Investment Revenue Depriciation PBT Tax

Page 179: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-5

2) Economic Internal Rate of Return (EIRR)

GDP growth has close linkage with that of electricity demand. Considering the income obtained by selling

electricity as the social benefit, EIRR is calculated as shown in Table 5-6 under the same conditions given in the

previous section 1).

10.4%, which is the interest rate of euro bond with the maturity of 10 years issued by Ukrainian government on

30th September 2013, is used as the opportunity cost of capital and discount rate, and Net Present Value (NPV)

and Benefit Cost Ratio (B/C)are calculated. The result is shown in Table 5-7.

EIRR is calculated at 15.06% which is higher than 10.4%. And NPV and B/C are calculated at US$131.78 million

and 1.07, respectively. These figures show that the implementation of the project would be economically viable.

The results of sensitivity studies for

a) Selling Price

b) EPC Cost

c) O&M Cost

d) Fuel Cost

e) Plant Availability

f) Plant Efficiency

are shown in the next section.

Page 180: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-6

Table 5-6 EIRR Calculation

(Unit: US$ million)

(Source: prepared by the Study Team)

O&M DebtCost Repayment

1 2 3 4 5 6=2-3-4-5 7 8=6-7 9=6+5-11 37.88 -37.882 38.88 -38.883 39.87 -39.874 40.87 -40.875 39.50 -39.506 267.84 188.96 62.74 24.62 -8.48 0.00 -8.48 16.147 274.24 193.47 61.56 24.62 -5.42 0.00 -5.42 19.218 280.80 198.10 60.38 24.62 -2.30 0.00 -2.30 22.329 287.51 202.83 59.20 24.62 0.85 0.14 0.72 25.48

10 294.38 207.68 58.01 24.62 4.06 0.65 3.41 28.6811 301.41 212.64 56.83 24.62 7.31 1.17 6.14 31.9412 308.62 217.73 55.65 24.62 10.62 1.70 8.92 35.2413 315.99 222.93 54.47 24.62 13.97 2.24 11.74 38.6014 323.55 228.26 53.29 24.62 17.38 2.78 14.60 42.0015 331.28 233.71 52.10 24.62 20.84 3.33 17.50 45.4616 339.20 239.30 50.92 24.62 24.35 3.90 20.45 48.9717 347.30 245.02 49.74 24.62 27.92 4.47 23.45 52.5418 355.60 250.87 48.56 24.62 31.55 5.05 26.50 56.1719 364.10 256.87 47.38 24.62 35.23 5.64 29.59 59.8620 372.80 263.01 46.19 24.62 38.98 6.24 32.74 63.6021 381.71 269.30 45.01 24.62 42.78 6.85 35.94 67.4122 390.84 275.73 43.83 24.62 46.65 7.46 39.19 71.2823 400.18 282.32 42.65 24.62 50.58 8.09 42.49 75.2124 409.74 289.07 41.47 24.62 54.58 8.73 45.85 79.2125 419.54 295.98 40.28 24.62 58.65 9.38 49.27 83.2726 429.56 303.05 24.62 101.89 16.30 85.59 126.5127 439.83 310.29 24.62 104.91 16.79 88.12 129.5328 450.34 317.71 24.62 108.01 17.28 90.73 132.6329 461.10 325.30 24.62 111.18 17.79 93.39 135.8030 472.12 333.08 24.62 114.42 18.31 96.11 139.0531 483.41 341.04 24.62 117.75 18.84 98.91 142.3732 494.96 349.19 24.62 121.15 19.38 101.76 145.7733 506.79 357.54 24.62 124.63 19.94 104.69 149.2634 518.90 366.08 24.62 128.20 20.51 107.69 152.8235 531.31 374.83 24.62 131.85 21.10 110.76 156.4836 544.00 383.79 24.62 135.59 21.69 113.90 160.2237 557.01 392.96 24.62 139.42 22.31 117.11 164.0438 570.32 402.35 24.62 143.34 22.93 120.41 167.9739 583.95 411.97 24.62 147.36 23.58 123.78 171.9840 597.90 421.81 24.62 151.47 24.23 127.23 176.0941 612.19 431.90 24.62 155.67 24.91 130.77 180.3042 626.83 442.22 24.62 159.98 25.60 134.39 184.6143 641.81 452.79 24.62 164.40 26.30 138.09 189.0244 657.15 463.61 24.62 168.91 27.03 141.89 193.5445 672.85 474.69 24.62 173.54 27.77 145.77 198.16

196.99 1,030.27 984.96 2,663.36 3,961.72

EIRR 15.06%

Year Investment Revenue Cash FlowPATTaxPBTDepreciation

Page 181: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-7

Table 5-7 NPV & B/C Calculation

Figures in NPV (Unit: US$ million)

(Source: prepared by the Study Team)

Year Investment O&M CostDebt

Repayment Tax Total Cost Benefit NPV

1 2 3 4 5=1+2+3+4 6 7=6-51 37.88 37.88 -37.882 35.21 35.21 -35.213 32.71 32.71 -32.714 30.37 30.37 -30.375 26.59 26.59 -26.596 115.22 38.26 0.00 153.48 163.32 9.847 106.86 34.00 0.00 140.86 151.47 10.618 99.11 30.21 0.00 129.32 140.48 11.169 91.91 26.83 0.06 118.80 130.29 11.49

10 85.25 23.81 0.27 109.33 120.83 11.5011 79.06 21.13 0.44 100.63 112.07 11.4412 73.32 18.74 0.57 92.63 103.93 11.3013 68.00 16.62 0.68 85.30 96.39 11.0914 63.07 14.72 0.77 78.56 89.40 10.8415 58.49 13.04 0.83 72.36 82.91 10.5516 54.25 11.54 0.88 66.67 76.90 10.2317 50.31 10.21 0.92 61.44 71.32 9.8818 46.66 9.03 0.94 56.63 66.14 9.5119 43.28 7.98 0.95 52.21 61.35 9.1420 40.14 7.05 0.95 48.14 56.89 8.7521 37.23 6.22 0.95 44.40 52.77 8.3722 34.53 5.49 0.93 40.95 48.94 7.9923 32.02 4.84 0.92 37.78 45.39 7.6124 29.70 4.26 0.90 34.86 42.09 7.2325 27.54 3.75 0.87 32.16 39.04 6.8826 25.54 1.37 26.91 36.21 9.3027 23.69 1.28 24.97 33.58 8.6128 21.97 1.20 23.17 31.14 7.9729 20.38 1.11 21.49 28.88 7.3930 18.90 1.04 19.94 26.79 6.8531 17.53 0.97 18.50 24.85 6.3532 16.26 0.90 17.16 23.04 5.8833 15.08 0.84 15.92 21.37 5.4534 13.98 0.78 14.76 19.82 5.0635 12.97 0.73 13.70 18.38 4.6836 12.03 0.68 12.71 17.05 4.3437 11.15 0.63 11.78 15.81 4.0338 10.35 0.59 10.94 14.66 3.7239 9.59 0.55 10.14 13.60 3.4640 8.90 0.51 9.41 12.61 3.2041 8.25 0.48 8.73 11.70 2.9742 7.65 0.44 8.09 10.85 2.7643 7.10 0.41 7.51 10.06 2.5544 6.58 0.38 6.96 9.33 2.3745 6.11 0.36 6.47 8.66 2.19

2,008.53 2,140.31 131.78B/C 1.07

Page 182: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-8

3) Sensibility of EIRR

a) Selling Price

Figure 5-1 shows the result.

Figure 5-1 Sensibility in relation to Selling Price

(Source: prepared by the Study Team)

b) EPC Cost

Although the improvement of EIRR is about 2% only by means of EPC cost being cut by 10%, it is very

important to scrutinize this cost.

Figure 5-2 Sensibility in relation to EPC Cost

(Source: prepared by the Study Team)

9.86%

15.06%

20.08%

24.75%

28.98%

0%

10%

20%

30%

50 55 60 65 70 75US$/MWh

17.09%16.37%

15.69%15.06%

14.46%13.90%

13.38%

10%

12%

14%

16%

18%

20%

1,250 1,300 1,350 1,400 1,450 1,500 1,550 1,600 1,650 US$/kW

Page 183: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-9

c) O&M Cost

10% cost down causes increase of EIRR at about 0.7%.

Figure 5-3 Sensibility in relation to O&M Cost

(Source: prepared by the Study Team)

d) Fuel Cost

This factor makes higher impact to EIRR calculation, too. Thanks to shale gas revolution, international coal

market is heavily affected and the coal prices are trending south. It is important to procure quality coal with the

reasonable price.

Figure 5-4 Sensibility in relation to Fuel Cost

(Source: prepared by the Study Team)

12.97%13.67%

14.36%15.06%

15.75%16.43%

17.12%

10%

12%

14%

16%

18%

20%

60% 70% 80% 90% 100% 110% 120% 130% 140%

20.99%19.06%

17.08%15.06%

13.01%10.95%

8.88%

0%

5%

10%

15%

20%

25%

70 75 80 85 90 95 100 105 110 US$/ton

Page 184: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-10

e) Plant Availability

85% of Plant availability is normal figure and it is likely to result in poorer performance. It is better to study the

other factor.

Figure 5-5 Sensibility in relation to Plant Availability

(Source: prepared by the Study Team)

f) Plant Efficiency

Plant efficiency at 41% is rather conservative premise 43% or more efficient plant should be targeted at the

detailed design stage

Figure 5-6 Sensibility in relation to Plant Efficiency

(Source: prepared by the Study Team)

10.60%12.10%

13.59%15.06%

16.55%18.00%

0%

5%

10%

15%

20%

65% 70% 75% 80% 85% 90% 95% 100%

12.14%

13.17%

14.14%

15.06%

15.93%

16.75%

17.53%

10%

12%

14%

16%

18%

20%

37% 38% 39% 40% 41% 42% 43% 44% 45%

Page 185: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-11

4) Comparative Verification with Alternative

There was the expansion plan in the beginning of 1990’s that another 675MW (225MWx3units) coal-fired TPP

would be constructed in the plant site.

As well as USC technology, DTEK, the owner of the plant, is also considering Circulation Fluidized Bed (CFB)

Boiler technology since all the permits and licenses for the construction of 225MWx3 coal-fired TPPs have been

obtained.

However, CFB Boiler technology has the following negative aspects being compared with USC technology.

a) EPC Cost

In 2011 a EPC contract of 450MW (150MWx3units) was made. Its contract price per kW is US$2,180/kW

which is much more expensive than the proposed plant.

b) O&M Cost

In general CFB technology gives damages its parts due to the circulation and fluidizing and needs much

spare parts. Three units need more manpower than one unit for O&M. USC is the most efficient technology

among coal-fired technologies and CFB TPP consumes more amount of fuel.

c) Financing Source

International financial institutions in USA and Europe have negative opinion about coal-fired TPPs.

Japanese government supports USC and SC technologies, however since there is no manufacture in Japan

that has 225MW CFB boiler technology, they are not in the position to support CFB technology.

Thus, there is no major financial institution that can give loan to 225MW CFB technology.

As for quality of fuel coal such as calorific value, volatility, moisture content, there is no specific reason why CFB

boiler technology should be introduced.

Because of the aforementioned reasons, USC technology is better than CFB boiler technology.

Page 186: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

5-12

5) Conclusion

① EPC cost must be scrutinized.

The average figure of the recent USC coal-fired TPPs’ contract amounts is used as a reference for this

evaluation. However, as there are several contracts whose unit figure is less than US$ 1,400/kW in especially

Asian countries, the same level shall be targeted for EPC cost.

② The scheme for revenue up shall be established.

The electricity prices in Ukraine are one of lowest levels among European countries. IMF has requested

Ukrainian government to hike utility charges as the one of the conditions for its financial support and therefore

the price is in uptrend.

Poland, which the electricity generated by the plant will be exported to; will have to stop the operation of

6,000MW coal-fired TPPs by 2016-2017 pursuant to EU directives. And she is going to introduce the

mechanism of “Capacity Payment” and/or Feed in Tariff with Contract for Difference following USA and UK

in order to invite foreign direct investments for building new TPPs. Thus, it will become a likely scenario to

make long term contract with the selling price of higher than US$60/MWh.

③ More economical fuel coal shall be procured.

Thanks to shale gas revolution, international coal market is heavily affected and the coal prices are trending

south.US$90 per ton is the current market price in Europe and cheaper fuel will be available in the future.

Page 187: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Chapter 6 Planned Project Schedule

Page 188: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 189: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

6-1

Our assuming overall project schedule is shown in the diagram below.

Figure 6-1 Project Schedule

2014 2015 2016 2017 2018 2019 2020 2021

Feasibility Study

Environmental Social

Impact Assessment (ESIA)

Contracts’ Negotiations

Permits and Licenses

Finance Close

Site Preparation

Procurement and

Transportation

Civil & Installation

Commissioning

Commercial Operation

(Source: prepared by the Study Team)

1)Feasibility Study (F/S)

Due to very limited time allocated, this study is merely preliminary one. It therefore is necessary to implement

detailed F/S, investing a good deal of time and effort so as to optimize plant performance, re-evaluate total plant

cost and economics, and obtain the data and information for ESIA.

2)Environmental Social Impact Assessment (ESIA)

JICA’s overseas investment and loan is expected for developing the project. The international financial bodies

including JICA establish guidelines for environmental and social consideration and require implementation of

ESIA in line with the guidelines.

3)Contracts’ Negotiations

In parallel with ESIA, such agreements/contracts as Power Purchase Agreement (PPA), Fuel Supply Agreement

(FSA), EPC contract, O&M contract and etc. are negotiated.

4)Permits and Licenses

This project is not new one but extension and land acquisition for the extension unit is not necessary. So it may

take rather shorter period to obtain all the necessary permits and licenses than those projects that start from scratch.

However, in former Soviet Union countries the conformity to GOST standard is required and it takes a great deal

of time to clear the process.

Page 190: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

6-2

5)Finance Close

Simultaneously with the above 2), 3) and 4), the negotiation with JICA and other lenders is launched.

6)From Notice to Proceed (NTP) of EPC till Commercial Operation Date (COD)

In general, the construction period of coal-fired thermal power plant depends on the delivery period of steam

turbine. The standard construction period of such plant is four and a half years.

Page 191: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Chapter 7 Implementing Organizations

Page 192: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 193: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-1

(1) Power Sector in Ukraine

1) Power Sector

The structural reforms in Ukrainian power sector started during the Kuchma era with the support of

Euro-American consultants and international financial institutions. The trigger event was the Presidential decree

“Structural Reforms in the Power Sector in Ukraine” published on 4th April 1995.

Taking the reference to the reforms in UK, the sector was divided into generation, transmission and distribution

arms under the decree. Before the decree enacted, there existed 8 regional thermal power companies which

managed both generation and distribution of the electricity. The reforms in 1995 re-organized 4 thermal power

companies and 27 regional distribution companies. Ukraine consists of 27 administrative districts (24 provinces, 2

special cities and 1 autonomous republic), those distribution companies were established in each administrative

districts.

The organization established in 1995 are kept until now, which is shown below.

Figure 7-1 Power Sector in Ukraine

Ministry of Energy and Coal Industry (Policy making and implementation) Administrative

Bodies National Electricity Regulatory Commission (Regulator)

Thermal

Power Plants

Hydraulic

Power Plants

Nuclear

Power Plants Power

Generation Privatized State-Owned State-Owned

Ukrenergo (Transmission) State-Owned Power

Transmission

Wholesales Energorynok (Wholesales) State-Owned

Regional Distribution Companies & Independent Providers Power

Distribution Privatized

(Source: prepared by the Study Team)

Page 194: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-2

a) The Ministry of Energy and Coal Industry (MECI)

On 14 April 2000, the MEC of Ukraine was established by the Decree of the President of Ukraine #598/2000. The

MECI is the main body in the system of central bodies of the executive power that provides realization of a state

policy in electrical power-generating, nuclear-industrial, and oil-gas complexes, often referred simply as the

Fuel-Energy Complex. The MECI is directed and coordinated by the Cabinet of Ministers of Ukraine.

b) National Electricity Regulatory Commission (NERC)

NERC is main regulatory for the wholesale electricity market (WEM) of Ukraine. The NERC has the authority to

・ participate in creating national policy for the development and operation of WEM,

・ regulate natural monopolies in the electricity sector,

・ implement pricing and tariff policy,

・ issue licenses for companies that produce, distribute and supply electricity,

・ approve amendments to the agreement among the WEM participants subject to approval by the MECI and

the Anti-Monopoly Committee, and

・ protect electricity consumers’ rights.

c) Thermal Power Generation Companies

5 thermal power companies exist; those are Dniproenergo (the South Thermal Power Generation Company),

Centrenergo (the Central Thermal Power Generation Company), Zakhidenergo (the West Thermal Power

Generation Company), Donbasenergo (the East Thermal Power Generation Company) and newly established

Skhidenergo.

d)Hydraulic Power Generation Companies

In 1994 Dniprohydroenergo and Dnisterhydroenergo were established by water systems. In 2004 these companies

merged into Ukrhydroenergo.

e)Nuclear Power Generation Company

State-owned company, Energoatom has been established since 1996.

f)Wholesale of Electricity, Transmission and Distribution Companies

State-owned company, Energorynok is the monopoly in electricity wholesale. Ukrenergo is the national electrical

power transmission company. 42 regional electric power distribution companies and 81 independent

power providers sell the electricity to the end users.

Page 195: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-3

2) Privatization

The MECI reported that the aging ratio of thermal power plants in Ukraine increased from 65% to 76% in the past

five years. According to Energy Strategy of Ukraine for the period until 2030, it costs U$ 40 billion to modernize

all the thermal power plants. Her national budget cannot afford to do and it is necessary to invite private funds to

the fields.

The Azarov cabinet eliminated electrical power generation and distribution companies from “the significant

companies” in economic aspect and national security by means of the governmental decision made on 23

February 2011. And those companies can be privatized. Then 4 thermal power generation companies and 20

regional electrical power distribution companies became the target for privatization.

The list of thermal power generation companies and electrical power distribution companies to be privatized in

2011 and 2012 were announced by the governmental mandate dated on 11 April 2011. The information how many

shares of those companies the government would sell were also disclosed. Those were Dniproenergo: 25%,

Zakhidenergo: 45.1%、Kievenergo (thermal power generation and electricity distribution company in Kiev): 25%

and etc.

3) Zakhidenergo (the West Thermal Power Generation Company)

DTEK, which is an energy holding company, acquired 45.103 % shares of Zakhienergo. Then, about 70% of the

company is under control of DTEK, since DTEK had owned about 25% shares of the company. DTEK is part of

System Capital Management (SCM), a leading Ukrainian financial and industrial group. It was formed in 2002

and is an association of various companies from coal mining to power generation.

Zakhidenergo owns and operates 3 coal-fired thermal power plants; those are Dobrotvirska coal-fired thermal

power plant in Lviv region, Burshtynskaya coal-fired thermal power plant in Ivano-Frankivska region and

Ladyzhinskaya coal-fired thermal power plant in Vinnitsya.

Exceptionally, Dobrotvirska and Burshtynskaya coal-fired thermal power plants connect to European Network of

Transmission System Operators for Electricity (ENTSO-E) and therefore electricity generated by those power

plants can be exported to the surrounding countries such as Poland, Hungary, Slovakia and Romania.

Page 196: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-4

Figure 7-2 European Network of Transmission System

(Source: ENTSO-E Statistical Year Book 2009)

Page 197: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-5

(2) DTEK

1) General

DTEK is an energy holding company headquartered in Donetsk, Ukraine. It was formed in 2002 and is an

association of various companies from coal mining to power generation. The name of the company is an

abbreviation from its original name Donbass Fuel-Energy Company in Ukrainian

The key business segments of DTEK are coal mining and preparation, electrical power generation, and electrical

power sales and supply.

Figure 7-3 Company Structure

(Source: DTEK Annual Report 2011)

2) Coal Mining and Preparation

The coal mining of DTEK is represented by 6 largest companies in the industry: DTEK Pavlogradvuhillia (10

mines), DTEK Dobropilliavuhillia (5 mines), DTEK Rovenkianthracite (6 mines), DTEK Sverdlovanthracite (5

mines), DTEK Mine Komosomolets Donbassa (1 mine) and ALC Mine Bilozerska (1 mine). In addition, the coal

preparation of DTEK consists of 12 plants.

The coal mining product is thermal and coking coal. The main consumers are companies of DTK electricity

generation. (There are some differences between 2011’ and the current data)

4 Operations

TPP: Thermal Power Plant

CHPP:

DTEK Pavlogradugol(10 mines)

DTEK Skhidenergo(3 TPPs)

Service-InvestDTEK Trading

(Coal Sales)

DTEK

Coal Mining Power Generation Power Distribution and Sale Other

DTEK Mine KomsomoletsDorbase (1 mine)

DTEK Dniproenergo(3 TPPs)

DTEK Energougol ENEDTEK Power Trade(Electricity Sales)

DTEK Dobropolyeugol(6 mines)

CHPP-5, CHPP-6 DTEK Donetskoblenergo Wind Power

Socis (Management ofSocial Infrastructure)

DTEK Rovenkyanthracite(6 mines)

DTEK Zakhidenergo(3 TPPs)

Kyvenergo DTEK Oil & Gas

DTEK Sverdlovathracite(5 mines)

DTEK DniprooblenergoDTEK Service

(Administrative Support)

Coal Processing(11 factories)

DTEK KrymenergoCombined Heat &Power Plant

Page 198: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-6

3) Electrical Power Generation

The electrical power generation of DTEK consists of

① DTEK Skhidenergo,

② DTEK Dniproenergo (DTEK owns 72.9%),

③ Kyivenergo (DTEK owns 72.39%), and

④ DTEK Zahidenergo (DTEK owns 70.91%).

The total installed capacity of the above 4 companies is 18.2 GW. The generated electrical power is supplied to

the wholesale electricity market of Ukraine. In addition to electricity sale in Ukraine, DTEK exports electricity to

Slovakia, Romania, Hungary, Poland, and Belarus. DTEK is the only Ukrainian company that exports electricity.

4) Electrical Power Sales and Supply

The electrical power sales and supply of DTEK consists of the network companies

① DTEK Dniprooblenergo (DTEK owns 51.50%),

② Kievenergo (DTEK owns 71.82%),

③ DTEK Donetskoblenergo (DTEK owns 71.34%),

④ DTEK Krymenergo (DTEK owns 57.6%),

⑤ DTEK Energougol ENE and

⑥ Service-Invest.

They purchase electrical power in the wholesale electricity market and sell and supply it to end consumers. Key

consumers are the metal and coal industry, and population. The total length of the network is 159,000 km.

5) Key Production Indicators

DTEK’s key production indicators in recent years are shown below.

Table 7-1 DTEK’s Key Production Indicators

Indicators unit 2011 2012 Change Change (%)

Coal Production kilo ton (kt) 24,001.4 39,693.3 15,691.9 65.4

Coal Preparation

Run of Mine Coal Preparation kt 1,3690.0 27,692.3 14,002.3 102.3

Concentrate Output kt 8,729.8 18,311.1 9,581.3 109.8

Electricity Generation GWh 17,135.1 51,382.7 34,247.6 199.9

Electricity Purchased from WEM GWh 14,066.1 53,918.4 39,852.3 283.3

Electricity Exports GWh 5,091.9 9,707.0 4,615.1 90.6

Coal Exports kt 3,396.0 2,745.1 -650.9 -19.2

Coal Imports kt 569.0 1.4 -567.6 -99.8

(Source: DTEK Annual Report 2012)

Page 199: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-7

DTEK’s market share in Coal mining, electricity generation and electricity distribution are shown below.

Figure 7-4 DTEK’s Market Share

(Source: DTEK Annual Report 2012)

The following table shows the countries that DTEK sold electricity to and those volumes in 2011 and 2012.

Table 7-2 Electricity Exports from Ukraine

Unit: TWh

Country 2011 2012 Change

Belarus 2.56 4.05 58.2%

Hungary 2.47 3.60 45.7%

Moldova 0.67 0.85 26.9%

Slovakia 0.59 0.10 -83.1%

Russia 0.06 0.00 -100%

Poland 0.06 1.01 1,583.3%

Romania 0.03 0.16 433.3%

Total 6.44 9.75 51.4%

(Source: DTEK Annual Report 2012)

DTEK46.1%

Coal Mining

DTEK28.5%

Electricity Generation

DTEK37.8%

Electricity Distribution

Page 200: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-8

6) Financial Performance

DTEK’s key financial performance in the last three years is shown below.

Figure 7-5 DTEK’S Key Financial Performance

EBIDA: Earnings Before Interest, Taxes, Depreciation, and Amortization

(Source: DTEK Annual Report 2012)

3,060

4,969 10,332

773 1,290

2,119

360 442 741

0

2,000

4,000

6,000

8,000

10,000

2010 2011 2012Revenue EBITDA Net Profit

Unit: US$ million

Page 201: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-9

(3) Evaluation of Implementing Organizations

1) Technical and Personnel Aspects

DTEK that 140,000 professionals are working for is the largest energy company in Ukraine. In addition to

creation of new jobs, paying US$ 1.93 billion for taxes in 2012, which is three times bigger than the figure in

2011, DTEK contributes to economic and social development in Ukraine.

As mentioned in the above, DTEK owns and operates 9 coal-fired TPPs and 2 CHPPs under 4 thermal power

companies.

As all the coal-fired TPPs are old and in accordance with Directive 2001/80/EU, DTEK has started taking

measures to reduce the emissions of Sulfur Oxide (SOx), Nitrogen Oxide (NOx), and soot dust. As the result,

DTEK invested more than US$ 1,275 million in 2012 to modernize and develop its facilities. The figure is more

than half of all of the investments of SCM group.

DTEK currently is selecting technologies for desulfurization and deNOx systems to be installed to all of DTEK’s

coal-fired TPPs, and has the plan to build 800MW coal-fired TPP at Burshtynska TPP with the most advanced

technologies. With the grant fund provided by the United States Trade and Development Agency, the feasibility

study is developed including the justification of the selected technologies in accordance with the requirements of

Ukraine and ENTTSO-E.

Thus, any problem cannot be seen in both technical and human resources aspects.

Page 202: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

7-10

2) Financial Arrangements

Most of DTEK’s debt as of yearend 2012 was denominated in Russian Ruble (RUB), Euro (EUR) and US$.

Borrowings denominated in RUB amounted to US$ 879 million, which was equivalent to 34.0% of the loan

portfolio; in EUR – US$ 844 million or 32.6%; in US$ - US$ 636 million or 24.6%. Debt denominated in UAH

amounted to US$ 226 million or 8.8% of the loan portfolio.

Figure 7-6 Debt Currency Portfolio

(Source: DTEK Annual Report 2012)

The DTEK’s debts were mostly long-term liabilities. The average repayment period as of yearedn 2012 was 3.3

years. The largest part of DTEK’s debt was comprised of Eurobonds, bilateral bank loans and the club loan. The

share of long-term liabilities in the overall loan portfolio was 83.5%.

The key ratios of DTEK’s equity to borrowe funds as of 31 December 2012 were shown below. The figures show

debt ratio is relatively high.

Table 7-3 The Key Ratios of DTEK’ Equity borrowed Funds

2010 2011 2012

Total Debt/EBITDA 0.9 1.65 1.36

Net Debt/EBITDA 0.6 0.63 1.04

EBITDA/Interst and Expenses 13.5 16.7 10.9

(Source: DTEK Annual Report 2012)

According to DTEK Annual Report 2012, a long term credit rating of DTEK in December 2012 was evaluated as

“B3” with an outlook of “Negative” by Moody’s Investors Services. In January 2013, Fitch Ratings gave a long

term credit rating of DTEK of “B” with an outlook of “Stable”.

The above circumstances make it even more difficult to make financial arrangement.

RUB, 34.0%

EUR, 32.6%

US$, 24.6%

UAH, 8.8%

20,662UAH mil.

Page 203: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

Chapter 8 Technical Advantages of Japanese Companies

Page 204: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired
Page 205: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

8-1

(1) Expected Formation of Japanese Companies’ Participation

JICA’s overseas investment and loan is expected to be offered for the implementation of the project. In this regard,

substantial involvement of Japanese companies is imperative. The following fields are expected for Japanese

companies’ participation.

1) Equity Participation

JBIC/NEXI requires Japanese investors to take 30% or more of equity participation in order for them to provide

project finance/investment insurance, respectively. JICA has limited experience to make overseas investment or

offer project finance, and the conditions demanded by JICA shall be established with the reference JBIC/NEXI’s

requirements in the process of the negotiation with Japanese investors,

2) Engineering, Procurement and Construction (EPC)

There are several Japanese heavy electric machinery manufactures that have outstanding capacity for

technological development to meet advanced technology requirements. They keep price competitiveness

especially in the fields of environmental responsiveness, energy conservation, reduction in size and weight.

They also have been developing USC technology in the domestic market and are proud of rich supply records of

USC coal-fired TPPs, and therefore keep price competitiveness against US/EU manufactures.

3) Operation and Maintenance (O&M)

ITOCHU Corporation affiliates NAES Corporation which is one of leading O&M companies for TPPs in USA.

NAES covers European markets and will be able to take O&M role of the project.

4) Fuel Supply

Ukraine is the 2nd largest producer of hard coal in Europe, however, due to inefficient mining technology and

redundant staff for the purpose of job creation, loses price competitiveness in the international market.

DTEK, the owner of the plant, has coal mines in the eastern part of the country. However because of the

transportation cost, it procures 90% of fuel for the plant from their competitors whose coal mine is located near

the plant. There is a chance for Japanese companies to supply fuel if an attractive price could be proposed.

Page 206: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

8-2

The fields filled with yellow color in Figure 8-1 are those where Japanese companies’ participation are expected.

Figure 8-1 Expected Project Scheme

(Source: prepared by the Study Team)

Page 207: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

8-3

(2) Advantages of Japanese Companies on the Project

1) Advantages in Technical Aspect

Japanese manufactures and utility companies have technical advantages over those in other countries in especially

USC technologies.

Through the long experience of implementing USC TPPs under the highest environmental requirements in Japan,

Japanese companies have been maintaining high standard at the world state-of-the-art level. As the result,

Japanese manufacturers have enjoyed a lot of delivery records and kept competitiveness against European

manufactures. Some of Japanese manufactures give licenses of USC technology to foreign manufactures and

receive orders even from European countries.

It is necessary to meet the more strict environmental standards required by the local government in Japan rather

than USA or Europe, which advances Japanese technological level to the highest one.

Not only plant performance, but also O&M technology in USC such as advanced automation operation and high

availability factor etc. is in the level of the world state-of-the-art. Japanese companies have established O&M

support system, responding carefully to the needs of the owners.

Also Japanese manufacturers have advanced software technology so that Japanese manufacturers can propose

competitive infrastructural systems.

The Japanese manufacturers have a competitive edge in the field of environmental impact reduction and energy

conservation. In particular, they can accommodate advanced requirements from the foreign clients against the

background of the technical capabilities that they have corresponded O&M issues to domestic power companies.

Page 208: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

8-4

2) Advantages in Economic Aspect

a) New Policies of US and European Financial Institutions

The financial public sector agencies in USA and Europe tend to stop giving loan to the coal-fired TPPs.

On 25th June 2013, Mr. Obama, the President of USA, announced the “Climate Action Plan”, in which he

declared to terminate official support to the construction of coal-fired TPPs abroad, and requested the other

countries and international financial institutions to take the similar actions.

The export and import bank of USA supported the policy of the President and decided on 18th July 2013 not to

allocate finance to Thai Binh unit 2 sub-critical coal-fired TPP in Vietnam. Despite this, the EIA process for the

project had being finalized.

The bank had given US$ 800 million of finance to 4,800MW coal-fired TPPs in South Africa and US$ 900

million of finance to 4,000MW coal-fired TPPs in India in the last five years.

Denmark, Finland, Island, Norway, and Sweden agreed to the policy of USA and those 6 countries made a joint

announcement in September 2013.

The World Bank, European Investment Bank (EIB) and European Bank for Reconstruction and Development

(EBRD) endorse the action of USA.

The board meeting of the World Bank held on 16th July 2013 and argued the new policy on the energy sector. It

has been announced to the public that the bank stops giving loan to the coal-fired TPPs except for the very

specific case.

The board meeting of EIB held on 23rd July 2013 and argued the new policy on the energy sector too. Since then

EIB has restricted the eligible coal-fired TPPs to those

① whose CO2 emission is 550g/kWh or less, and

② where CO2 Capture and Storage (CCS)facility is ready to be installed.

EBRD, which is established in order for the countries located in Central and Eastern Europe to move to market

economies, announced the draft of the new policy on the energy sector and accepted public comments on it until

30th September 2013.

Under such circumstances, the export credit agencies in German and France are paid marked attention to if they

follow EIB/EBRD’s actions, since Siemens and Alstom, which are main equipment suppliers of coal-fired TPP,

have manufacturing bases in those countries.

Page 209: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

8-5

b) Policy of Japanese Government and Official Bodies in Japan

On the other hand, Japanese government has committed herself in White Paper on International Economy and

Trade 2013 to supporting Japanese companies’ exporting infrastructures and systems including the USC coal-fired

TPPs by using official development assistance (ODA). Japan now exports Japanese Yen 10,000 billion of

infrastructures and systems, which includes the returns from overseas investments. The government has targeted

the figures to be triple in 2020.

The Ministry of Economy, Trade and Industry (METI) has tightened up on the collaboration with those

organizations which have ODA tools in order for Japanese companies to get more orders from abroad. METI tries

to support Japanese companies from the stage of fact findings to financial closure of projects in a consistent way.

METI has regular meetings with JBIC, JICA, JETRO, and NEDO (New Energy and Industrial Technology

Development Organization) in order to implement those projects that METI has given its supports to.

JICA has been giving soft loans to developing countries and restarted overseas investment and loan to those

projects to which Japanese companies make investment since October 2012.

NEXI takes an important role in overseas investment and loan to provide a variety of insurances to cover political

risks.

For the achievement of the target, it is important to make the bodies concerned fully understand the advantages in

both the technical aspect and management of Japanese companies and strengthen relationship with the key

persons. JICA undertakes this role and in 2012 accepted 2,202 trainees to Japan and dispatched 127 specialists to

abroad.

Page 210: Study on Dobrotvirska Coal-Fired Power Extension Project ... · PDF fileStudy on Dobrotvirska Coal-Fired Power Extension Project ... 2014 Prepared for: The Ministry ... Coal-Fired

8-6

(3) Measures Required to Promote Orders to Japanese Companies

JICA’s overseas investment and loan is expected to be offered for the implementation of the project.

As mentioned in the previous section, the financial public sector agencies in USA and Europe tend to stop

providing finance toward coal-fired TPPs.

On the other hands, Chinese contractors and manufacturers boost their orders in this field. Being not the member

of Organization for Economic Co-operation and Development (OECD), China does not need to follow the

guidelines of OECD and can give loan to any projects.

Japanese companies have been facilitating advanced technologies such as USC coal-fired TPPs and making effort

to realize the low carbon society. In order to achieve the target more smoothly, the official support from Japanese

government is also indispensable.