Strawberry River Sub-Watershed Project 11-1100 Izard County Conservation District Arkansas Natural Resource Commission U.S. Environmental Protection Agency

Upload: kami

Post on 22-Feb-2016

56 views

Category:

Documents


0 download

DESCRIPTION

Strawberry River Sub-Watershed Project 11-1100 . Izard County Conservation District Arkansas Natural Resource Commission U.S. Environmental Protection Agency. Izard County State Location Map. Izard County's Strawberry Sub- Watershed Map. Priorities for Planning. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Strawberry River  Sub-Watershed Project 11-1100

Strawberry River Sub-Watershed Project

11-1100 Izard County Conservation District

Arkansas Natural Resource CommissionU.S. Environmental Protection Agency

Page 2: Strawberry River  Sub-Watershed Project 11-1100

Izard County State Location Map

Page 3: Strawberry River  Sub-Watershed Project 11-1100

Izard County's Strawberry Sub- Watershed Map

Page 4: Strawberry River  Sub-Watershed Project 11-1100

Priorities for PlanningAll farms with riparian access along blue line

streams as indicated on the 7.5 minute USGS quadrangle maps.

All farms that lie within 1 mile of a blue line stream.

Page 5: Strawberry River  Sub-Watershed Project 11-1100

Getting the word out about the projectWord of mouthQuarterly newsletterAnnual field day and landowner conference

with 72 in attendanceEquipment RentalsNewspaper

Page 6: Strawberry River  Sub-Watershed Project 11-1100

Equipment and Landowner Conference

Page 7: Strawberry River  Sub-Watershed Project 11-1100

Word of mouthQuarterly newsletter

Page 8: Strawberry River  Sub-Watershed Project 11-1100

Best Management PracticesFence 19,573 ft

completed in FY 2012

Fence 30,576 planned in FY 2012

Page 9: Strawberry River  Sub-Watershed Project 11-1100

Best Management PracticesWatering Facilities =

12 planned 9 completed

Pipeline = 5412 ft planned 3434 ft completed

Heavy use protection areas = 12 planned 9 completed

Page 10: Strawberry River  Sub-Watershed Project 11-1100

Best Management Practices

Well = 1 planned 1 completed

Pumping Plant

(SOLAR SYSTEM) 1 planned 1 completed

Page 11: Strawberry River  Sub-Watershed Project 11-1100

Best Management PracticesAccess Control 114 acresBrush Management 135 acresPest Management 707 acresNutrient Management 271 acres Prescribed Grazing 191 acres

Page 12: Strawberry River  Sub-Watershed Project 11-1100

Conservation Plans51 Conservation Plans written on 4,803

acres.

Page 13: Strawberry River  Sub-Watershed Project 11-1100

Contracts

18 Contracts written in the last 12 months10 Contracts completed within the last 12

months$29,445.51 paid to landowners for installing

BMP’S$41,529.22 Match made by the landowners

by installing BMP’S