stormwater management plan proposed 7 eleven service station · the collected water will be used...
TRANSCRIPT
2
Stormwater Management Plan Proposed 7 Eleven Service Station
Eastern Road, Rooty Hill NSW 2766
CONTENTS
1.0 INTRODUCTION………………………………………………………………………… 3
2.0 STORMWATER CONCEPT……………………………………………………….……. 4
3.0 STORMWATER QUANTITY MANAGEMENT………………………………………... 5
4.0 STORMWATER QUALITY MANAGEMENT………………..………………………... 5
5.0 OVERLAND FLOW PATHS ………………………………..………………………... 7
6.0 CONCLUSION……………………………………………………..…………………..…... 7
APPENDIX A – MUSIC Model
APPENDIX B – Summary Sheets
3
Stormwater Management Plan Proposed 7 Eleven Service Station
Eastern Road, Rooty Hill NSW 2766
Site
1.0 INTRODUCTION
Richmond and Ross Pty Ltd, Consulting Engineers, were engaged to carry out a Stormwater Management
Plan for the proposed service station at Eastern Road, Rooty Hill, NSW 2766. This report addresses the
management of stormwater, within the proposed site boundaries.
The below assessment is based on site survey, hydraulic and hydrological calculations with respect to
the proposed development works and in accordance with
• Blacktown DCP 2015 – Part J
• Developer Handbook for Water Sensitive Urban Design
Reference should also be made to the civil drawings within the DA package.
The site forms part of an overall development which is subject to a subdivision development application.
1.1 SITE DETAILS
The area being developed for the service station has a total area of approximately 1,985m2 and is
currently used as a carparking area for the adjacent sports' fields.
Figure 1 - Aerial Photograph of site location
4
Stormwater Management Plan Proposed 7 Eleven Service Station
Eastern Road, Rooty Hill NSW 2766
1.2. PREVIOUS REPORTS
As part of the subdivision DA, Cardno have prepared a flood report for the site (80218006:VJ –
31/5/2018 with an updated assessment in 21/01/19). The flood report calculated a 1% AEP flood
depth for the site of RL 33.9. Council have advised that for the purposes of a flood planning level, a
1% AEP flood level of 34.2mAHD should be adopted.
Council’s engineering guide and DCP Part A states freeboard requirements for industrial and
commercial developments to be 300mm above the 1% Flood Levels. Therefore, the proposed finished
floor level is 34.5 m AHD to meet the freeboard requirements.
Cardno have also prepared an engineering assessment report (80218006 28/5/2018). In particular, this
report addresses issues of stormwater quantity for the overall development and provides a detention
basin to cater for the ultimate developed state of the site as part of the interallotment drainage system.
No additional OSD measures are proposed for the 7 Eleven site.
2.0 STORMWATER CONCEPT
It is proposed to build a service station with a shop building, a fueling canopy and associated and
associated customer parking. Entry to the site is from Eastern Road and from a circulation lane
through adjacent carparks to the west.
• Stormwater from shop building roof, canopy roof and pavement drains to a new underground
pipe network;
• Proposed roof area is approx. 530m2. 220m2 of building roof will be directed to a 4000L
above ground rainwater tank. The collected water will be used for toilet flush and bioretention
basin irrigation within the site. Overflow from the tank will be connected to the site’s
underground stormwater network and surcharge into Bio Basin C for treatment. Analysis by
MUSIC indicates that 80% of the estimated potable water requirement is provided by this
arrangement. 310m2 of the canopy roof surcharges in Bio basin C.
• Bio retention basins are proposed to filter the majority of the runoff.
• A Stormceptor is proposed to treat stormwater prior to it leaving the site. This is to achieve
two purposes. The first and main purpose is to capture hydrocarbons and satisfy council's
requirements for a GPT specifically targeting hydrocarbons (service station classified as a
high-risk development).
The stormceptor also assists in TSS removal for flows that bypass/overflow past the bio basins
5
Stormwater Management Plan Proposed 7 Eleven Service Station
Eastern Road, Rooty Hill NSW 2766
• The development connects to the proposed interallotment drainage system. Reference should
be made to the subdivision DA drawings for additional details.
3.0 STORMWATER QUANTITY MANAGEMENT
A detention basin is provided at the downstream end of the interallotment drainage system as part of
the overall subdivision. This basin has been sized by Cardno to cater for the developed sites and no
additional measures are required on the McDonald's site.
4.0 STORMWATER QUALITY MANAGEMENT
A stormwater quality improvement train is proposed as follows-
4.1 Rainwater Tank
The rainwater is designed to allow the reuse of collected rainwater for toilet flushing and garden
watering. Reuse has been estimated as 0.1kl/day for toilet flushing (1 pans x 0.1kl/day) and
11.6kl/year scaled as PET-Rain for irrigation (29m2 x 0.4kl/year/m2 bio). Referring to WSUD
guidelines, only irrigation of bio basins is required to be modelled. The remaining landscaped area
proposed to be turfed do not have to be modelled.
A 4kl rainwater tank has been proposed which has been modelled within MUSIC as having 3.2kl
capacity.
4.2 Gross Pollutant Traps (GPT’s)
A Stormceptor S.300/250.C1 is proposed. The purpose is to –
• Satisfy BCC's requirement for a specific treatment measure for total hydrocarbons. The
proposed model has been designed for a minimum 2EY (75% of the 1EY). The proposed
model has a treatment flow rate of 35l/s whereas the 2EY flow rate from the development is
31.9l/s (0.75 x 77 x 1985 x 0.000278).
• Provide additional TSS removal for area that bypass/overflow from the bio basin.
4.3 Bio retention basins
3 bio retention basins are proposed and are shown on the civil drawings. Reference should be made to
the drawings for sizes and locations. Due to constraints from the existing inter-allotment 600dia
stormwater drainage line, the subsoil drain in Bio basin A and B had to be directed to a separate
discharge point compared to the overflow. Discussion with council engineer has confirmed that the
subsoil drain is not required to pass through the stormceptor and therefore it discharges directly to pit
6
Stormwater Management Plan Proposed 7 Eleven Service Station
Eastern Road, Rooty Hill NSW 2766
D. Overflows are collected by shallow pits and the outlet pipes of these cross over the existing
stormwater line. Refer Section D in DWG C04. Bio basin A and B have a connected submerged zone.
4.4 Water Quality Outcome – MUSIC Modelling
MUSIC modelling was undertaken for the proposed treatment train. The model was set up using the
latest MUSIC-Link data and in accordance with BCC requirements. A copy of the MUSIC link
summary sheet is included in the appendices.
Figure 2: Treatment train and Pollution Removal as modelled in MUSIC
The removal rates calculated for the treatment train are as follows-
Source Residual % Reduction Target
TSS 328 34 89.6 85
TP 0.601 0.172 71.3 65
TN 3.08 1.62 47.3 45
GP 33.5 0.096 99.7 90
A copy of the MUSIC link summary sheet is included in the appendices.
5.0 OVERLAND FLOW PATHS
7
Stormwater Management Plan Proposed 7 Eleven Service Station
Eastern Road, Rooty Hill NSW 2766
The site generally grades towards the east and flows will generally run along the frontage of the site
towards Eastern Road. Reference should be made to the Cardno flood report for overall flow paths.
6.0 CONCLUSION
We believe that the proposed system satisfies the relevant requirements of Blacktown Council for
stormwater.
A
Stormwater Management Plan Proposed 7 Eleven Service Station
Eastern Road, Rooty Hill NSW 2766
APPENDIX A – MUSIC MODEL
A
Stormwater Management Plan Proposed 7 Eleven Service Station
Eastern Road, Rooty Hill NSW 2766
APPENDIX B – Summary Calculations
Project Details
Project: 7 Eleven Blacktown
Report Export Date: 24/06/2020
Catchment Name: 200056 - 7-Eleven-Blacktown (With Bio)V2
Catchment Area: 0.197ha
Impervious Area*: 138.0%
Rainfall Station: 67035 LIVERPOOL(WHITLAM
Modelling Time-step: 6 Minutes
Modelling Period: 1/01/1967 - 31/12/1976 11:54:00 PM
Mean Annual Rainfall: 857mm
Evapotranspiration: 1261mm
MUSIC Version: 6.3.0
MUSIC-link dataVersion: 6.33
Study Area: Blacktown
Scenario: Blacktown Development
Company Details
Company: Richmond & Ross Consulting Engineers
Contact: Harshad V
Address: Level 1, 38 Willoughby Rd, Crows Nest, 2065
Phone: 02 9490 9600
Email: [email protected]
Treatment Train Effectiveness
Node: Post-Development Node Reduction
Flow 7.69%
TSS 89.5%
TP 71.3%
TN 47.3%
GP 99.7%
Treatment Nodes
Node Type Number
Rain Water Tank Node 1
Bio Retention Node 2
GPT Node 1
Source Nodes
Node Type Number
Urban Source Node 8
MUSIC-link Report
* takes into account area from all source nodes that link to the chosen reporting node, excluding Import Data Nodes
Comments
Roof areas do not have baseflow. Therfore, the invalid results for roof areas can be ignored
NOTE: A successful self-validation check of your model does not constitute an approved model by Blacktown City CouncilMUSIC-link now in MUSIC by eWater – leading software for modelling stormwater solutions
1 of 3
Passing Parameters
Node Type Node Name Parameter Min Max Actual
Bio Bioretention A+B (18m�) Hi-flow bypass rate (cum/sec) None None 100
Bio Bioretention A+B (18m�) PET Scaling Factor 2.1 2.1 2.1
Bio Bioretention C (11m�) Hi-flow bypass rate (cum/sec) None None 100
Bio Bioretention C (11m�) PET Scaling Factor 2.1 2.1 2.1
GPT Stormceptor Interim Blacktown Node 2013-05-28 Hi-flow bypass rate (cum/sec) None None 0.035
Post Post-Development Node % Load Reduction None None 7.69
Post Post-Development Node GP % Load Reduction 90 None 99.7
Post Post-Development Node TN % Load Reduction 45 None 47.3
Post Post-Development Node TP % Load Reduction 65 None 71.3
Post Post-Development Node TSS % Load Reduction 85 None 89.5
Rain Rainwater Tank % Reuse Demand Met 80 None 83.9913
Urban Building roof (220m�) Area Impervious (ha) None None 0.022
Urban Building roof (220m�) Area Pervious (ha) None None 0
Urban Building roof (220m�) Total Area (ha) None None 0.022
Urban Bypass Landscaping (50m�) Area Impervious (ha) None None 0
Urban Bypass Landscaping (50m�) Area Pervious (ha) None None 0.005
Urban Bypass Landscaping (50m�) Total Area (ha) None None 0.005
Urban Canopy roof (310m�) Area Impervious (ha) None None 0.031
Urban Canopy roof (310m�) Area Pervious (ha) None None 0
Urban Canopy roof (310m�) Total Area (ha) None None 0.031
Urban Landscaping (80m�) Area Impervious (ha) None None 0
Urban Landscaping (80m�) Area Impervious (ha) None None 0
Urban Landscaping (80m�) Area Pervious (ha) None None 0.008
Urban Landscaping (80m�) Area Pervious (ha) None None 0.008
Urban Landscaping (80m�) Total Area (ha) None None 0.008
Urban Landscaping (80m�) Total Area (ha) None None 0.008
Urban Pavement Areas (220m�) Area Impervious (ha) None None 0.022
Urban Pavement Areas (220m�) Area Pervious (ha) None None 0
Urban Pavement Areas (220m�) Total Area (ha) None None 0.022
Urban Pavement Areas (60m�) Area Impervious (ha) None None 0.005
Urban Pavement Areas (60m�) Area Pervious (ha) None None 0
Urban Pavement Areas (60m�) Total Area (ha) None None 0.005
Urban Pavement Areas (960m�) Area Impervious (ha) None None 0.096
Urban Pavement Areas (960m�) Area Pervious (ha) None None 0
Urban Pavement Areas (960m�) Total Area (ha) None None 0.096
Only certain parameters are reported when they pass validation
NOTE: A successful self-validation check of your model does not constitute an approved model by Blacktown City CouncilMUSIC-link now in MUSIC by eWater – leading software for modelling stormwater solutions
2 of 3
Failing Parameters
Node Type Node Name Parameter Min Max Actual
Urban Building roof (220m�) Baseflow Total Nitrogen Mean (log mg/L) 0.32 0.32 0.11
Urban Building roof (220m�) Baseflow Total Phosphorus Mean (log mg/L) -0.82 -0.82 -0.85
Urban Building roof (220m�) Baseflow Total Suspended Solids Mean (log mg/L) 1.1 1.1 1.2
Urban Canopy roof (310m�) Baseflow Total Nitrogen Mean (log mg/L) 0.32 0.32 0.11
Urban Canopy roof (310m�) Baseflow Total Phosphorus Mean (log mg/L) -0.82 -0.82 -0.85
Urban Canopy roof (310m�) Baseflow Total Suspended Solids Mean (log mg/L) 1.1 1.1 1.2
Only certain parameters are reported when they pass validation
NOTE: A successful self-validation check of your model does not constitute an approved model by Blacktown City CouncilMUSIC-link now in MUSIC by eWater – leading software for modelling stormwater solutions
3 of 3