HENRY COUNTY SPLOST IV PROJECT UPDATE Ron Burckhalter, SPLOST Capital Projects Director and Roque Romero, SPLOST Transportation Director BOARD OF COMMISSIONERS MEETING September 15, 2015

Upload: henry-county-government

Post on 23-Jul-2016

219 views

Category:

Documents


0 download

DESCRIPTION

SPLOST IV Project Update - Henry County, GA

TRANSCRIPT

Page 1: SPLOST IV  Project Update - Henry County, GA

HENRY COUNTY SPLOST IVPROJECT UPDATE

Ron Burckhalter, SPLOST Capital Projects Director andRoque Romero, SPLOST Transportation Director

BOARD OF COMMISSIONERS MEETINGSeptember 15, 2015

Page 2: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEPROJECT UPDATE

Page 3: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDE911 RADIO REPLACEMENT

Budget: $7,000,000.00Status: In Progress(2) Vendors currently being

evaluated.Evaluation Committee meeting

scheduled for 9/22/2015.Once a vendor is selected and

awarded, the upgrade process will take approximately 1-year.

Page 4: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEAMBULANCES (1-REMOUNT/1-NEW)

Budget: $380,000.00Status: In Progress(1) Ambulance Remount

COMPLETE.Cost $100,214.00.

(1) New Ambulance Bid In Progress.

Ambulance Remount

Page 5: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEANIMAL CONTROL RENOVATION

Budget: $100,000.00Status: COMPLETECost: $98,167.00Renovation Items Included:New digital surveillance

camera system.Epoxy wall coating in kennels,

puppy room, and quarantine area.Additional fencing and new

automatic gate.New interior doors.

Digital Security System

Page 6: SPLOST IV  Project Update - Henry County, GA

Stonhard Epoxy Wall Coating

Page 7: SPLOST IV  Project Update - Henry County, GA

Additional Fencing and Automatic Gate

Page 8: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEFIRE STATIONS CAPITAL EQUIPMENT

Budget: $2,100,000.00Status: In Progress(3) New Fire Trucks – Bid In Progress.(3) New Ambulances – Bid In Progress.New Equipment for New Fire Stations 14 (Luella),15 (N.

Mt. Carmel) & 16 (Kelleytown).It takes approximately 12 months from the time the

equipment is ordered to receive.

Page 9: SPLOST IV  Project Update - Henry County, GA

FIRE STATIONCAPITAL EQUIPMENT

Page 10: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEFIRE STATION #14 (Luella Area)

Budget: $2,000,000.00Status: In ProgressLocation: 1875 Hampton Locust Grove Road, Locust Grove, GAArchitect: The Howell GroupDesign Nearing Completion.This will be the first of the new Fire Stations to be put out for bid for

construction.Final building construction drawings and specifications are COMPLETE.Site development drawings are being revised for septic system.Pending Henry County Plan Review approval.Once a contractor is selected and awarded, the construction process will take

approximately 9 months.

Page 11: SPLOST IV  Project Update - Henry County, GA
Page 12: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEFIRE STATION #15 (N. Mt. Carmel Area)

Budget: $2,000,000.00Status: In ProgressLocation: 325 N. Mt. Carmel Road, Hampton, GAArchitect: The Howell GroupDesign In Progress.This will be the second of the new Fire Stations to be put out for bid for

construction.Final building construction drawings and specifications are COMPLETE; pending

Henry County Plan Review approval.Site development drawings have been approved.Once a contractor is selected and awarded, the construction process will take

approximately 9 months.

Page 13: SPLOST IV  Project Update - Henry County, GA
Page 14: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEFIRE STATION #16 (Kelleytown Area)

Budget: $2,000,000.00Status: In ProgressLocation: 1575 Kelleytown Road, McDonough, GAArchitect: The Howell GroupDesign In Progress.This will be the third of the new Fire Stations to be put out for bid for

construction.Final building construction drawings and specifications are COMPLETE;

pending Henry County Plan Review approval.Site development drawings have been submitted for review/approval.Once a contractor is selected and awarded, the construction process will take

approximately 9 months.

Page 15: SPLOST IV  Project Update - Henry County, GA
Page 16: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEHCDOT CONSTRUCTION EQUIPMENT

Budget: $450,000.00Status: In ProgressPurchase of 2015 ROADTEC

FB-100 Heavy Duty Front Mount Broom COMPLETE. Cost $67,757.00

HCDOT in process of evaluating the purchase of a Material Transfer Vehicle.

Page 17: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEJAIL RENOVATIONS

Budget: $1,500,000.00Status: In ProgressInitial Plumbing Renovation and Fixture Replacement COMPLETE.Surveillance Camera and Access Control Preliminary Work In Progress.Renovation Items Include:New Digital Surveillance Camera System.New Access Control System.Plumbing Renovation.Plumbing Fixture Upgrade.Epoxy Wall Coating in Shower/Toilet Area.

Page 18: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDENEW INTERCHANGE ON I-75

Budget: $5,500,000.00 (Feasibility Study & Design)Status: In ProgressEngineer: Kimley-HornFeasibility Study COMPLETE.Four (4) interchange alternative locations have been

identified.Feasibility Study submitted to GDOT for review.

Page 19: SPLOST IV  Project Update - Henry County, GA
Page 20: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDE(30) POLICE PATROL VEHICLES

Budget: $1,406,806.00Status: In ProgressPurchase of Initial (15) Police Patrol Vehicles COMPLETE.Cost $682,158.00

(15) Additional Police Patrol Vehicles Received.Vehicle graphics COMPLETE.Equipment Installation In Progress.Expected completion mid-October.

Page 21: SPLOST IV  Project Update - Henry County, GA

Police Patrol Vehicles

Page 22: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDESEWER TO AIRPORT

Budget: $2,000,000.00Status: In ProgressDesign By: Henry County Water

AuthorityConceptual Routing Plan COMPLETE.HCWA Design In Progress.

Page 23: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDESEWER TO FAIRVIEW

Budget: $2,000,000.00Status: In ProgressDesign By: Henry County Water

AuthorityConceptual Routing Plan COMPLETE.HCWA Design In Progress.

Page 24: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – COUNTY WIDEPROJECT STATUS SUMMARY

13 of 17 County Wide Projects COMPLETE or In Progress - 76%These (13) projects represent 74% of the total County Wide

Projects Budget. NOTE: Excludes Program Management.

Page 25: SPLOST IV  Project Update - Henry County, GA

SPLOST IV - DISTRICT 1PROJECT UPDATE

Commissioner Bo Moss

Page 26: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 1FIRE STATION #2 (Replacement)

Budget: $2,000,000.00Status: In ProgressLocation: 35 Frances Ward Drive, Locust Grove, GAArchitect: The Howell GroupDesign Nearing Completion.This will replace the existing Fire Station #2 and will be part of the City of

Locust Grove Master Plan.Final building construction drawings, specifications and site development

drawings are COMPLETE and approved.Bid opening October 8, 2015.Once a contractor is selected and awarded, the construction process will

take approximately 9 months.

Page 27: SPLOST IV  Project Update - Henry County, GA
Page 28: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 1TANGER BALL FIELDS

Budget: $550,000.00Status: In ProgressLocation: 2951 Tanger Blvd., Locust Grove, GAJoint project with the City of Locust Grove.Concession Bldg. and Sports Lighting COMPLETE.Parking Lot Design COMPLETE.Storage/Meeting Bldg. Construction Punch-List In Progress.

Page 29: SPLOST IV  Project Update - Henry County, GA

Tanger Ball Fields

Page 30: SPLOST IV  Project Update - Henry County, GA

Tanger Ball Fields Concession Stand

Storage/Meeting Bldg.

Page 31: SPLOST IV  Project Update - Henry County, GA

SPLOST IV - DISTRICT 1MAJOR TRANSPORTATION (1 of 3 Projects In Progress)

McDonough Parkway (Henry Parkway to SR20/81)Budget:$5,000,000.00Status: Concept Design COMPLETEEngineer: Heath & Lineback Engineers

• City of McDonough to Contribute $750,000.00.

Page 32: SPLOST IV  Project Update - Henry County, GA

McDonough Parkway (Henry Parkway to SR20/81)

Page 33: SPLOST IV  Project Update - Henry County, GA

SPLOST IV - DISTRICT 1INTERSECTION IMPROVEMENTS (3 of 3 Projects COMPLETE or In Progress)

Locust Road/Jackson Street @ SR42Status: COMPLETED by GDOT

South Bethany @ Old JacksonBudget: $1,000,000.00Status: Concept Design COMPLETEEngineer: AECOM

SR81 @ Mt. Bethel/WynnD1 Budget: $500,000.00 (50/50 Shared Cost w/District 3)

Status: Construction In ProgressContractor: Pittman Construction Company

Page 34: SPLOST IV  Project Update - Henry County, GA

South Bethany @ Old Jackson

Page 35: SPLOST IV  Project Update - Henry County, GA
Page 36: SPLOST IV  Project Update - Henry County, GA

SPLOST IV - DISTRICT 1DIRT ROADS (2 of 5 Projects In Progress)

Harris Drive (Leguin Mill Road to South Bethany Road)Budget:$1,870,176.00Status: Construction In ProgressContractor: Southeastern Site Development

Lester Mill Road (Hampton L.G. to Indian Creek)Budget:$2,843,250.00Status: Right of Way Acquisition In ProgressEngineer: AECOM

Page 37: SPLOST IV  Project Update - Henry County, GA
Page 38: SPLOST IV  Project Update - Henry County, GA

LESTER MILL ROAD

Page 39: SPLOST IV  Project Update - Henry County, GA

LESTER MILL ROAD

Page 40: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 1BRIDGE IMPROVEMENTS (1 of 5 Projects In Progress)

Jackson Lake over Mackey Creek (Bridge Replacement)D1 Budget: $456,750.00 (1/3 Cost District 1)(2/3 Cost District 3)Status: Concept Design In ProgressEngineer: Moffatt & Nichols

Page 41: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 1RESURFACING, WIDENING OR SURFACE TREATMENT

Ingram’s Lane (Peeksville Road to Cul de sac)Leguin Lane (Leguin Mill Road to Cul de sac)Trestle Road (SR155 to Cul de sac)

3 ROADS COMPLETE

Page 42: SPLOST IV  Project Update - Henry County, GA

Ingram’s Lane

Page 43: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 1PROJECT STATUS SUMMARY

2 of 3 Capital Projects In Progress – 67%These (2) projects represent 82% of the District 1 Capital

Projects Budget.

7 of 16 Transportation Projects In Progress – 44%These (7) projects represent 81% of the District 1 Transportation

Projects Budget. NOTE: Excludes Resurfacing; three (3) Resurfacing projects are COMPLETE.

Page 44: SPLOST IV  Project Update - Henry County, GA

SPLOST IV - DISTRICT 2PROJECT UPDATECommissioner Brian Preston

Page 45: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 2SENIOR/RECREATION CENTER

Budget: $3,500,000.00Status: In ProgressLocation: 56 McDonough Street, Hampton, GAArchitect: Flynn, Finderup ArchitectsDesign In Progress.Schematic design and design development COMPLETE.Construction Documents 50% Complete.Estimated design completion 10/01/2015.Pending Henry County Plan Review approval.

Page 46: SPLOST IV  Project Update - Henry County, GA

Hampton Senior/Recreation Center

Page 47: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 2INTERSECTION IMPROVEMENTS (5 of 6 Projects In Progress)

Industrial Parkway @ SR20Budget:$500,000.00 (Joint Project with GDOT)Status: Traffic Study In Progress - GDOT

Jodeco Road @ Blackhall RoadBudget:$659,000.00 (Joint Project with GDOT)Status: Preliminary Design In Progress - GDOT

Mill @ SR81Budget:$1,250,000.00Status: Concept Design In ProgressEngineer: AECOM

Page 48: SPLOST IV  Project Update - Henry County, GA

Jodeco Road @ Blackhall Road

Page 49: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 2INTERSECTION IMPROVEMENTS (Continued)

Mt. Carmel @ ChambersBudget: $1,000,000.00Status: Concept Design COMPLETEEngineer: Heath & Lineback Engineers

Simpson Mill @ Hampton-L.G.Budget: $620,000.00Status: Concept Design In ProgressEngineer: AECOM

Page 50: SPLOST IV  Project Update - Henry County, GA

Mt. Carmel @ Chambers

Page 51: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 2DIRT ROADS (8 of 10 Projects COMPLETE or In Progress)

Amah Lee (Old SR3 to End of Pavement)Budget: $390,000.00Status: Concept Design In ProgressEngineer: Wolverton & Associates

Farmer Drive (Surface Treatment)Cost: $24,988.00Status: COMPLETE

Fields Drive (Surface Treatment)Cost: $20,686.00Status: COMPLETE

Floyd Road (Surface Treatment)Cost: $9,085.00Status: COMPLETE

Page 52: SPLOST IV  Project Update - Henry County, GA
Page 53: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 2DIRT ROADS (Continued)

Jones Road (Surface Treatment)Cost: $44,776.00Status: COMPLETE

Mt. Olive Road (Jonesboro to End of Pavement)Cost: $55,472.00Status: COMPLETE

South Mt. Carmel (Surface Treatment)Cost: $17,529.00Status: COMPLETE

Thoroughbred Drive (Greenwood Road to End of Pavement)Budget: $507,000.00Status: Concept Design In ProgressEngineer: Wolverton & Associates

Page 54: SPLOST IV  Project Update - Henry County, GA

Jones Road

Page 55: SPLOST IV  Project Update - Henry County, GA
Page 56: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 2BRIDGE IMPROVEMENTS (5 of 5 Projects In Progress)

Blackhall over Rum Creek (Bridge Replacement)Budget: $300,000.00 (Joint Project with GDOT)Status: Design In Progress - GDOT

Hampton over Indian Creek (Culvert Repair)Budget: $150,000.00Status: Design In ProgressEngineer: AECOM

Hampton over Towaliga River (Bridge Repair)Budget: $200,000.00Status: Design In ProgressEngineer: AECOM

Page 57: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 2BRIDGE IMPROVEMENTS (Continued)

Jonesboro over Walnut Creek (Bridge Repair)Budget: $75,000.00Status: Design In ProgressEngineer: AECOM

Old SR3 over Norfolk Southern RR (Bridge Repair)Budget: $80,000.00Status: Design In ProgressEngineer: AECOM

Page 58: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 2RESURFACING, WIDENING OR SURFACE TREATMENT

Arnold Road (Old Hwy. 3 to Floyd Road)David Road (SR81 to Steele Drive)Dillion Drive (Hill View Road to Cul de sac)Lake Talmadge Dam (North Circle to South Circle)Manley Drive (SR20 to Cul de sac)North Drive (US 19/41 to Dam)South Drive (US 19/41 to Dam)

7 ROADS COMPLETE

Page 59: SPLOST IV  Project Update - Henry County, GA

Manley Drive

Page 60: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 2PROJECT STATUS SUMMARY

1 of 2 Capital Projects In Progress – 50%This (1) project represents 99% of the District 2 Capital Projects Budget.

18 of 23 Transportation Projects COMPLETE or In Progress – 78%These (18) projects represent 49% of the District 2 Transportation Projects

Budget. NOTE: Excludes Resurfacing; seven (7) Resurfacing projects are COMPLETE.

Page 61: SPLOST IV  Project Update - Henry County, GA

SPLOST IV - DISTRICT 3PROJECT UPDATE

Commissioner Gary Barham

Page 62: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3HERITAGE PARK IMPROVEMENTS

Budget: $25,000.00Status: COMPLETECost: $21,437.00Improvements Included:Steps with handrails from upper parking lot to Military Museum

and crosswalk.Sidewalk with handrails to Veteran’s Wall of Honor.

Page 63: SPLOST IV  Project Update - Henry County, GA

Sidewalk toVeteran’s Wall of Honor

Steps to Military Museum

Page 64: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3NORTH OLA PARK

Budget: $1,500,000.00Status: In ProgressNew 3-4 Year Old T-Ball Field In Progress.Fencing and sod COMPLETE.Benches and bleachers In Progress.Sports lighting installation scheduled for 9/30/2015.

Exploring the use of BOE property, behind Ola Elementary south of the park, for park expansion.

Page 65: SPLOST IV  Project Update - Henry County, GA

North Ola Park New 3-4 Year Old T-Ball Field

Page 66: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3MAJOR TRANSPORTATION (1 of 2 Projects In Progress)

McDonough Parkway (SR42 to SR155)Budget: $2,827,000.00Status: Preliminary Design In ProgressEngineer: Kimley-Horn

Page 67: SPLOST IV  Project Update - Henry County, GA

McDonough Parkway (SR42 to SR155)

Page 68: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3INTERSECTION IMPROVEMENTS (7 of 9 Projects COMPLETE or In Progress)

Bethany Road @ SR81Status: COMPLETED by GDOT

Campground Road @ SR155Budget: $600,000.00Status: Concept Design In ProgressEngineer: AECOM

Dailey Mill @ Jodeco RoadBudget: $250,000.00Status: Concept Design In ProgressEngineer: McGee Partners

East Lake @ SR20 D3 Budget: $1,121,566.00 (50/50 Shared Cost w/District 4)Status: Construction In ProgressContractor: Baldwin Paving

Page 69: SPLOST IV  Project Update - Henry County, GA
Page 70: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3INTERSECTION IMPROVEMENTS (Continued)

Jodeco Road @ Oak Grove RoadBudget: $303,000.00Status: Preliminary Design In ProgressEngineer: McGee Partners

Lake Dow/Rodgers @ RosserBudget: $1,500,000.00Status: Preliminary Design In ProgressEngineer: Heath & Lineback Engineers

SR81 @ Mt. Bethel/WynnD3 Budget: $500,000.00 (50/50 Shared Cost w/District 1)Status: Construction In ProgressContractor: Pittman Construction

Page 71: SPLOST IV  Project Update - Henry County, GA

Jodeco Road @ Oak Grove Road

Page 72: SPLOST IV  Project Update - Henry County, GA

Lake Dow/Rodgers @ Rosser

Page 73: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3DIRT ROADS (6 OF 7 Projects COMPLETE or In Progress)

Butler’s Bridge Drive (Surface Treatment)Cost: $52,904.00Status: COMPLETE

Candler Road (Surface Treatment)Cost: $31,176.00Status: COMPLETE

East Knight Road (Surface Treatment)Cost: $30,348.00Status: COMPLETE

Page 74: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3DIRT ROADS (Continued)

Eskew Road (Surface Treatment)Cost: $37,419.00Status: COMPLETE

Turner Church Road (East of Bridge to SR20)Budget:$1,802,000.00Status: Preliminary Design In ProgressEngineer: Pond & Co.

Turner Circle (Surface Treatment)Status: Starting October 2015

Page 75: SPLOST IV  Project Update - Henry County, GA
Page 76: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3BRIDGE IMPROVEMENTS (2 of 4 Projects In Progress)

Elliott Road over Walnut Creek Tributary (Bridge Repair)Budget:$300,000.00 (Joint Project with GDOT)Status: Design In Progress - GDOT

Jackson Lake over Mackey Creek (Bridge Replacement)District 3 Budget: $1,370,250.00 (2/3 Cost D3)(1/3 Cost D1)Status: Concept Design In ProgressEngineer: Moffatt & Nichol

Page 77: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3RESURFACING, WIDENING OR SURFACE TREATMENT

Brookdale CourtChardonnay Oaks DriveCharming CourtClearview CircleLakehaven Parkway

Millbrook WayMillstone CourtPost Oak RidgeWhispering Pines LaneWood Valley Drive

10 ROADS COMPLETE

Page 78: SPLOST IV  Project Update - Henry County, GA
Page 79: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 3PROJECT STATUS SUMMARY

2 of 3 Capital Projects COMPLETE or In Progress – 67%These (2) projects represent 50% of the District 3 Capital Projects Budget.

16 of 22 Transportation Projects COMPLETE or In Progress – 73%These (16) projects represent 80% of the District 3 Transportation Projects

Budget. NOTE: Excludes Resurfacing; ten (10) Resurfacing projects are COMPLETE.

Page 80: SPLOST IV  Project Update - Henry County, GA

SPLOST IV - DISTRICT 4PROJECT UPDATE

Commissioner Blake Prince

Page 81: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 4BUD KELLEY PARK

Budget: $2,750,000.00Status: In ProgressLocation: 1605 Kelleytown Road, McDonough, GADesign/Build Firm: Sports Turf CompanyConstruction In Progress.Erosion Control In Progress.Estimated Project Completion 4/1/2016.

Page 82: SPLOST IV  Project Update - Henry County, GA
Page 83: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 4INTERSECTION IMPROVEMENTS (3 of 4 Projects In Progress)

Banks Road @ Rock Quarry RoadBudget: $1,345,434.00Status: Construction In ProgressContractor: Matriarch Construction

Hemphill Road @ SR138Budget: $2,342,000.00Status: Preliminary Design In ProgressEngineer: AECOM

East Lake Road @ SR20Budget: $1,121,566.00 (50/50 Shared Cost w/District 3)Status: Construction In ProgressContractor: Baldwin Paving

Page 84: SPLOST IV  Project Update - Henry County, GA
Page 85: SPLOST IV  Project Update - Henry County, GA

SR138 @ Hemphill Road

Page 86: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 4DIRT ROADS (1 of 2 Projects In Progress)

Elliott Road (East Lake Drive to Crumbley Drive)Budget: $2,272,000.00Status: Concept Design In ProgressEngineer: Wolverton & Associates

Page 87: SPLOST IV  Project Update - Henry County, GA

ELLIOTT ROAD

Page 88: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 4RESURFACING, WIDENING OR SURFACE TREATMENT

COMPLETE:

Holloway RoadKelley WayPleasant Grove Circle

In Progress:

Kelleytown Woods DriveKelleytown Woods ParkwayNorth Grove CourtWoods CourtWoods Lane

8 ROADS COMPLETE or IN PROGRESS

Page 89: SPLOST IV  Project Update - Henry County, GA

Holloway Road

Page 90: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 4PROJECT STATUS SUMMARY

1 of 2 Capital Projects In Progress – 50%This (1) project represents 73% of the District 4 Capital

Projects Budget.

4 of 11 Transportation Projects In Progress – 36%These (4) projects represent 49% of the District 4

Transportation Projects Budget. NOTE: Excludes Resurfacing; eight (8) Resurfacing projects are

COMPLETE or In Progress.

Page 91: SPLOST IV  Project Update - Henry County, GA

SPLOST IV - DISTRICT 5PROJECT UPDATECommissioner Bruce Holmes

Page 92: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 5DISTRICT 5 NEW PARK

Budget: $4,850,000.00Status: In ProgressLocation: 750 Fairview Road, Ellenwood, GAArchitect/Engineer: Breedlove Land PlanningPark Design In Progress.Civil Plans are approximately 70% Complete.Civil Plans to be submitted for review the week of 9/28/2015.Building Plans to be submitted for review mid-October.Once a contractor is selected and awarded, the construction

process will take approximately 9 months.

Page 93: SPLOST IV  Project Update - Henry County, GA

DISTRICT 5NEW PARK

Page 94: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 5MAJOR TRANSPORTATION (2 of 3 Projects In Progress)

Anvil Block Road WideningBudget:$5,500,000.00Status: Preliminary Design In ProgressEngineer: AECOM

West Village Parkway (Previously Known as West Panola)Budget:$4,238,639.00Status: Preliminary Design In ProgressEngineer: McGee Partners

Page 95: SPLOST IV  Project Update - Henry County, GA

Anvil Block Road Widening

Page 96: SPLOST IV  Project Update - Henry County, GA

West Village Parkway (Previously West Panola)

Page 97: SPLOST IV  Project Update - Henry County, GA

SPLOST IV – DISTRICT 5INTERSECTION IMPROVEMENTS (1 of 3 Projects In Progress)

East Atlanta @ Thurman & Flat RockBudget:$2,002,000.00Status: Concept Design In ProgressEngineer: Wolverton & Associates

Page 98: SPLOST IV  Project Update - Henry County, GA

SPLOST IV - DISTRICT 5PROJECT STATUS SUMMARY

1 of 2 Capital Projects In Progress – 50%This (1) project represents 89% of the District 5 Capital

Projects Budget.

3 of 9 Transportation Projects In Progress – 33%These (3) projects represent 84% of the District 5

Transportation Projects Budget. *Excludes Resurfacing.

Page 99: SPLOST IV  Project Update - Henry County, GA

SPLOST IV PROJECT STATUS SUMMARY

CAPITALPROJECTS

Total Projects: 28Projects COMPLETE: 2Projects In Progress: 18

71% of Capital Projects are COMPLETE or In Progress.

TRANSPORTATIONPROJECTS

Total Projects: 82Projects COMPLETE: 12Projects In Progress: 37

60% of Transportation Projects are COMPLETE or In Progress.

Page 100: SPLOST IV  Project Update - Henry County, GA

SPLOST III – DISTRICT 5MAJOR TRANSPORTATION

Fairview Road WideningBudget:$12,524,959.00Status: Construction In ProgressContractor: CMES

Page 101: SPLOST IV  Project Update - Henry County, GA

Fairview Road @ Panola Road

Page 102: SPLOST IV  Project Update - Henry County, GA

Fairview Road near East Atlanta Road

Page 103: SPLOST IV  Project Update - Henry County, GA

Fairview Road

Page 104: SPLOST IV  Project Update - Henry County, GA

Fairview Road near Anvil Block Road