solar power system implementation for the tragon building...
TRANSCRIPT
page 1
Solar Power System Implementation for the Tragon Building
Project Plan
Amanda ChapmanChelsea HertleinDavid RogersMark RundelTish RzeszutkoOytun Seven
Prepared by 6 Aces Team Members:
UC Berkeley, ExtensionProject Management, x470August 9, 2007
page 2
Table of Contents• Project Lifecycle p. 3• Scope Statement p. 4
– Project Deliverables p. 5– Project Objectives p. 6– Assumptions p. 7– Constraints p. 8
• Risk Response Plan p. 9• Work Breakdown Structure p. 11 • Stakeholder reviews p. 13 • Project timeline p. 14• Cost Baseline p. 15• Responsibility Assignments p. 17• Communication Plan p. 18
page 3
Functional and operating system
Operations and maintenance manualsOperations and maintenance training
System installed:Structural/electrical upgradesSolar panelsBattery shelterBatteriesTransformers
Signed contract ConstructionScheduleCost estimate
Feasibility study AnalysisElectrical load analysis
Product Process Deliverables
Closing documentsLessons learnedOwner acceptance
Coordination of training –people and schedules
Schedule and budget updates Contract management
Scope statementWork breakdown structureRFQ
Risk AnalysisInformation Briefing to owner
Project Management Deliverables
Phase Name Feasibility Planning and Design
Construction Training Turnover
Project Lifecycle
page 4
Scope StatementVision Statement
• Promote social responsibility by becoming an environmentally conscious company
• Support cost management by utilizing free energy resources
Business Need• Immediate and Long-term Cost savings
o Reduce the amount of purchased commercial power and avoid futureincreased energy costs
• Capital Investmento Increase the resale value of the company-owned property
• Tax Benefitso Qualify for California Solar Power tax credits ($2.80/watt)o Qualify for 10% Federal tax credit
Project DescriptionInstall solar panels on the company’s building roof (to include the necessary batteries, transformers, and connections) to generate solar power electricity for the building’s operations in order to reduce the amount of commercial power that the company must purchase.
page 5
Scope Statement - Project Deliverables
The following deliverables are in the scope of this project:1. Installation of solar panels, structural improvements, transformers, batteries, a battery-
shelter facility, and necessary connections, wiring, and meters.2. Training of building maintenance team on operation and maintenance of the installed
solar panels and associated equipment.3. Construction drawings and specifications.4. Generation of solar power electricity to power the company’s building.5. Feasibility study to determine cost, cost savings, and tax rebates for the project.
The following deliverables are out of the scope of this project:1. Conversion of the entire building to new green standards (i.e., energy efficient lighting,
equipment, windows, etc.)2. Engagement of third party to provide on-going operations and maintenance by others
to maintain the system after it is installed and operating. 3. Expansion of the parking lot to compensate for spaces lost to install the batteries/
transformers.4. Generation of electricity to any other facilities in the vicinity of the building.6. Relocation of any employees or operations during construction.7. Providing electricity to any other facilities in the vicinity.
page 6
Project Objectives
Electrical meters indicate that solar power is being generated and powering the building.
Providing solar power electricity to the company’s building.
Building maintenance staff receives training and is fully capable of operating and maintaining the system.
Provide 48 hours of training to the building maintenance staff to operate and maintain the solar power system.
Construction is completed on-time and within budget.
Equipment is installed according to the design with minimal changes.
Owner receives necessary information to authorize funding for design and construction.
Perform a feasibility study to determine cost, cost savings, and tax rebates for the project.
Products are fully operational.
Commercial power requirement is reduced by the amount predicted in the feasibility study.
OBJECTIVES
Pre- and post-construction electrical energy usage and solar energy usage meet or exceed forecasted goals.
Solar panels, transformers, batteries, battery facility are installed and connections are completed.
CRITERIA FOR EVALUATION
page 7
Assumptions
• Permits are already acquired
• Electrical demand for the building’s operation will not change
• Existing site conditions on the property and around the building will not impede construction
• On-site storage areas for construction materials is available
• Normal daytime working hours allowed (0700-1700)
page 8
Constraints
• Budget for the construction and materials will be fixed once contracts are awarded
• Long lead time required for the procurement of some materials
• Building will remain occupied and business operations will continue throughout the project
o Will not include relocation of any employees or operations during construction
o High traffic days for the company’s market research operations –coordination required to allow for construction to take place onthese days
• No full-time security staff – materials will need to be secured on-site to avoid theft
page 9
Risk Response Plan
OpenProject Manager/ Engineering Consultants
Mitigation1-HighHighMediumScope/ Cost/ Quality/ Schedule
Design Problems8
ClosedAcceptance1-HighHighMediumCostBudget Overrun7
OpenProject Manager
Mitigation1-HighHighMediumSchedule/Cost
Schedule Overrun6
OpenProject Manager
Mitigation1-HighHighMediumScope/ Schedule
Scope Creep/ Mismanagement of Changes
5
OpenPM/ Contractor
Transference/ Mitigation
1-HighHighMediumSchedule/Cost
Injury to Construction Worker
4
OpenPM TeamTransference1-HighHighMediumScheduleExcessive Lead Times for Materials
3
OpenPM TeamTransference2-Medium
HighLowSchedule/Cost
General Contractor/ Subcontractor Solvency
2
ClosedAcceptance1-HighHighMediumSchedule/Cost
Unexpected Weather Patterns
1
Status(Open
or Closed)
Owner
Strategies/ Actions
(Avoidance, Transference,
Mitigation, Acceptance)
Priority*Impact on Project
*ProbabilityOf
Occurrence
Affected Area/s
RiskDescriptionID
page 10
Risk Response Plan
Probability of
Occurrence
Risk Prioritization Matrix
High ImpactMedium Impact
Low Impact
2 - Medium3 - Low3 - LowLow Probability
1 - High2 - Medium3 - LowMedium Probability
1 - High1- High2 - MediumHigh Probability
Impact on Project
page 11
Work Breakdown StructureSolar Power System Installation
Phase 1: Feasibility Phase 2: Planning and Design
1.1: Feasibility Study(budget: $50,000)
1.1.1: Risk Analysis (budget: $10,000)
1.1.2: Electrical/Solar Load Analysis (budget: $10,000)
1.2: Owner decision (Go, No Go)
2.1: Statement of Work
2.1.1: General Requirements
2.3: RFQ (Bid)
2.2: Work Schedule and Cost Estimate
2.1.2: Structural
2.1.1.3: Roof (patch)
2.1.3.1: Materials
2.1.1.4: Paint
2.1.3: Electrical
2.1.2.1: Materials
2.1.2.2: Labor
2.1.1.5: Concrete
2.1.1.1: Overhead
2.1.1.2: Fence
2.1.3.2: Labor
2.2.1: Work Schedule
2.2.2: Cost Estimate
2.1.3.1.1: Batteries
2.1.3.2.1: Solar Panels
2.1.3.1.2: Solar Panels
2.1.3.1.1: Batteries
2.3.3: Award Project
2.3.1: Contractor Response
2.4.1: Sign Contract2.4: Write Contract2.3.2: Bid Analysis
page 12
Work Breakdown Structure (cont’d)
Phase 3: Construction/Building
3.1: General Contractor 3.1.1.: Structural & electrical upgrades
3.1.2: Install Solar Panels and Electrical Hook-up
3.1.3: Build battery shelter
3.1.4: Install Batteries
3.1.5: Install Transformers
Phase 4: Training
4.1.1: O & M Manuals-Batteries
4.1.2: O & M Manuals-Solar Panels
Phase 5: Turnover
5.1: Review Acceptance Documents
5.2: Acceptance to Owner
5.2.1: Release Liens
5.2.2: Pay General Contractor
5.1.1: Accept As-Built Drawings
page 13
Stakeholder Reviews
-Training schedule
-
-Access to electrical meter-Notification of power change over
-Complete building/parking lot access-As-built drawings of the existing building
-Access to the building power system-Complete building/parking lot access-On site storage location
-Access to the building power system-Complete building/parking lot access-On site storage location
-Ability to monitor & control project-Owner approval and funding
- Safe and convenient access to the building
-Safe and convenient access to the building
-Minimal impact on the business operations
Needs
-Maintenance team fully trained by the end of the scheduled training
Trainers
-Minimal noise-Minimal impact to public roads and parking
Building Neighbors
-Fully functioning systemPower Company
-Owner cooperation-Access to electricity bills for usage requirements
Engineering Consultants
-Regular communication with GC-Prompt payment-Owner cooperation
Subcontractors
-Regular communication with Owner and PM-Prompt payment-Owner cooperation-Subcontractor completing work on-time
General Contractor
-Complete Owner cooperation- Regular communication with Owner and GC
Project Manager
-Minimal noise during business hours-Minimum disruption to testing schedule
Clients/Product Testers
-Minimal noise during business hours-Minimum disruption to testing schedule
Building Occupants
-Regular communication with PM and GC-Completed on time and within budget-Fully operational system
Owner(s)
ExpectationsStakeholder Name
ID WBS Task Name Duration Start Finish
1 1 Feasibility 35 days Mon 6/2/08 Fri 7/18/082 1.1 Feasibility Study 25 days Mon 6/2/08 Fri 7/4/083 1.1.1 Risk Analysis 5 wks Mon 6/2/08 Fri 7/4/084 1.1.2 Electrical/Solar Load Analysis 5 wks Mon 6/2/08 Fri 7/4/085 1.2 Owner decision (Go/NoGo) 2 wks Mon 7/7/08 Fri 7/18/086 2 Planning & Design 61 days Mon 7/21/08 Mon 10/13/087 2.1 Statement of Work 21 days Mon 7/21/08 Mon 8/18/088 2.1.1 General requirements 7 days Mon 7/21/08 Tue 7/29/089 2.1.1.1 Overhead 2 days Mon 7/21/08 Tue 7/22/0810 2.1.1.2 Fence 1 day Wed 7/23/08 Wed 7/23/0811 2.1.1.3 Roof (patch) 1 day Thu 7/24/08 Thu 7/24/0812 2.1.1.4 Paint 1 day Fri 7/25/08 Fri 7/25/0813 2.1.1.5 Concrete 2 days Mon 7/28/08 Tue 7/29/0814 2.1.2 Structural requirements 7 days Wed 7/30/08 Thu 8/7/0815 2.1.2.1 Materials 3.5 days Wed 7/30/08 Mon 8/4/0816 2.1.2.2 Labor 3.5 days Mon 8/4/08 Thu 8/7/0817 2.1.3 Electrical requirements 7 days Fri 8/8/08 Mon 8/18/0818 2.1.3.1 Materials 3 days Fri 8/8/08 Tue 8/12/0819 2.1.3.1.1 Batteries 2 days Fri 8/8/08 Mon 8/11/0820 2.1.3.1.2 Solar Panels 1 day Tue 8/12/08 Tue 8/12/0821 2.1.3.2 Labor 4 days Wed 8/13/08 Mon 8/18/0822 2.1.3.2.1 Batteries 2 days Wed 8/13/08 Thu 8/14/0823 2.1.3.2.2 Solar Panels 2 days Fri 8/15/08 Mon 8/18/0824 2.2 Work Schedule & Cost Estimate 10 days Tue 8/19/08 Mon 9/1/0825 2.2.1 Work Schedule 1 wk Tue 8/19/08 Mon 8/25/0826 2.2.2 Cost Estimate 2 wks Tue 8/19/08 Mon 9/1/0827 2.3 RFQ (Bid) 20 days Tue 9/2/08 Mon 9/29/0828 2.3.1 Contractor Response 2 wks Tue 9/2/08 Mon 9/15/0829 2.3.2 Bid Analysis 1 wk Tue 9/16/08 Mon 9/22/0830 2.3.3 Award Project 1 wk Tue 9/23/08 Mon 9/29/0831 2.4 Contracting 10 days Tue 9/30/08 Mon 10/13/0832 2.4.1 Write Contract 1 wk Tue 9/30/08 Mon 10/6/0833 2.4.2 Sign Contract 1 wk Tue 10/7/08 Mon 10/13/0834 3 Building & Construction 35 days Tue 10/14/08 Mon 12/1/0835 3.1 General Contractor 35 days Tue 10/14/08 Mon 12/1/0836 3.1.1 Structural & electrical upgrades 4 wks Tue 10/14/08 Mon 11/10/0837 3.1.2 Install solar panels & electrical hookup 3 wks Tue 11/11/08 Mon 12/1/0838 3.1.3 Build battery shelter 2 wks Tue 10/14/08 Mon 10/27/0839 3.1.4 Install batteries 4 wks Tue 10/28/08 Mon 11/24/0840 3.1.5 Install transformers 4 wks Tue 10/28/08 Mon 11/24/0841 4 Training 6 days Tue 12/2/08 Tue 12/9/0842 4.1 O & M Batteries 24 hrs Tue 12/2/08 Thu 12/4/0843 4.2 O & M Solar Panels 24 hrs Fri 12/5/08 Tue 12/9/0844 5 Turnover 10 days Wed 12/10/08 Tue 12/23/0845 5.1 Review Acceptance Documents 1 wk Wed 12/10/08 Tue 12/16/0846 5.1.1 Accept As-Built Drawings 1 wk Wed 12/10/08 Tue 12/16/0847 5.3 Owner Acceptance 5 days Tue 12/16/08 Tue 12/23/0848 5.3.1 Release Liens 1 wk Wed 12/17/08 Tue 12/23/0849 5.3.2 Pay General Contractor 0 days Tue 12/16/08 Tue 12/16/08
Feasibility
Feasibility Study
Risk Analysis
Electrical/Solar Load Analysis
Owner decision (Go/NoGo)
Planning & Design
Statement of Work
General requirements
Overhead
Fence
Roof (patch)
Paint
Concrete
Structural requirements
Materials
Labor
Electrical requirements
Materials
Batteries
Solar Panels
Labor
Batteries
Solar Panels
Work Schedule & Cost Estimate
Work Schedule
Cost Estimate
RFQ (Bid)
Contractor Response
Bid Analysis
Award Project
Contracting
Write Contract
Sign Contract
Building & Construction
General Contractor
Structural & electrical upgrades
Install solar panels & electrical hookup
Build battery shelter
Install batteries
Install transformers
Training
O & M Batteries
O & M Solar Panels
Turnover
Review Acceptance Documents
Accept As-Built Drawings
Owner Acceptance
Release Liens
12/16
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W TJun 1, '08 Jun 8, '08 Jun 15, '08 Jun 22, '08 Jun 29, '08 Jul 6, '08 Jul 13, '08 Jul 20, '08 Jul 27, '08 Aug 3, '08 Aug 10, '08 Aug 17, '08 Aug 24, '08 Aug 31, '08 Sep 7, '08 Sep 14, '08 Sep 21, '08 Sep 28, '08 Oct 5, '08 Oct 12, '08 Oct 19, '08 Oct 26, '08 Nov 2, '08 Nov 9, '08 Nov 16, '08 Nov 23, '08 Nov 30, '08 Dec 7, '08 Dec 14, '08 Dec 21, '08 Dec 28, '08
Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
6 Aces - Solar Power Project
UC Berkeley Extenstion, x470
Project: 6AcesSolarScheduleDate: Thu 7/26/07
page 15
Cost Baseline Graph
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
Cost $
Feasibi
lity -
Planning
& Desig
n -Con
struc
tion -
Training -
Turnove
r -
Phase
Solar Power System Installation
Phase VPhase IVPhase IIIPhase IIPhase I
page 16
Cost Baseline
102.2 Work Schedule & Cost Estimate
22.1.3.2.2 Solar Panels
22.1.3.2.1 Batteries
42.1.3.2 Labor
12.1.3.1.2 Solar Panels
22.1.3.1.1 Batteries
32.1.3.1 Materials
72.1.3 Electrical
3.52.1.2.2 Labor
3.52.1.2.1 Materials
72.1.2 Structural
22.1.1.5 Concrete
12.1.1.4 Paint
12.1.1.3 Roof (Patch)
12.1.1.2 Fence
22.1.1.1 Overhead
72.1.1 General Requirements
212.1 Statement of Work
$30,000.0061Phase 2: Planning & Design
101.2 Owner Decision
$10,000.00251.1.2 Electrical/Solar Load Analysis
$10,000.00251.1.1 Risk Analysis
$50,000.00251.1 Feasibility Study
35Phase 1: Feasibility
Total CostDaysTask 52.2.1 Work Schedule
102.2.2 Cost Estimate
05.2.2 Pay General Contractor
55.1.1 Accept As-Built Drawings
$685,000.00Total Cost
55.2.1 Release Liens
55.2 Acceptance to Owner
$10,000.0055.1 Review Acceptance Documents
10Phase 5: Turnover
$7,500.0034.2 O&M Solar Panels
$7,500.0034.1 O&M Batteries
6Phase 4: Training
$90,000.00203.1.5 Install Transformers
$40,000.00203.1.4 Install Batteries
$10,000.00103.1.3 Build Battery Shelter
$220,000.00153.1.2 Install Solar Panels & Electrical Hook-up
$108,000.00203.1.1 Structural & Electrical
$92,000.00353.1 General Contractor
35Phase 3: Construction/Building
52.4.1 Sign Contract
52.4 Write Contract
102.3.2 Award Project
52.3.1 Bid Analysis
102.3 RFQ (Bid)
Total CostDaysTask
page 17
Responsibility Assignments
ISAccept. Docs to owner5.2
IISReview Acceptance Documents
5.1
IIRTurnover5
ISTraining4
SIIIConstruction / Building3
SISIWrite Contract2.4
ISRequest for Quote2.3
IIRWork schedule and Cost estimate
2.2
IIIR/SStatement of Work2.1
IIPlanning/Design2
ISOwner Decision1.2
IIRSFeasibility Study1.1
TrainerGen Contractor
Eng. Consultant
PM TeamPMOwner
ResourcesDeliverable DescriptionWBS#
LEGEND: O- Owner I – Input Required R – Reviewer S – Sign Off Required
page 18
Communication: Project Management
XXXWordmeeting/email1PMRisk Plan
XXXExcelmeeting/emailEach lifecycle phase
PMCost Baseline
XXXMS Projectmeeting/emailWeeklyPMProject Schedule
XXXWordmeeting/emailWeeklyPMResource Assignment Matrix
XXXWordmeeting/emailUpon chg request
submission
PMWBS
XWordmeeting/email1PMProject Scope
Building Occupants
Eng Consult
GCOwnerType of Document
Distribution Format
FrequencyDocument Owner
PROJECT MANAGEMENT
COMMUNICATION
Recipient(s)
page 19
Communication: Product Process
XXWordmeeting/email1GCAcceptance Documents
XXWordemail1 or if chg request
GCCost Estimate
XXXMS Projectmeeting/emailWeeklyGCConstruction Schedule
XXWordemailAs edits are made
GCContract Iterations
XXWordemailAs edits are made
Eng ConsultSOW Iterations
XXWordemailAs edits are made
Eng ConsultFeasibility Study Iterations
Building Occupants
Eng Consult
GCOwnerType of Document
Distribution Format
FrequencyDocument Owner
PRODUCT PROCESS COMMUNICATION
Recipient(s)