1 Think Infrastructure. Think IDFC. The Jawaharlal Nehru National Solar Mission Implementation Issues on Bundling Scheme

Upload: dinhtuong

Post on 08-Mar-2018

219 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

1

Think Infrastructure.

Think IDFC.

The Jawaharlal Nehru

National Solar Mission

Implementation Issues

on Bundling Scheme

Page 2: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

2

Think Infrastructure.

Think IDFC.

Towards a solar future…

What is the Solar Mission?

How is it being implemented?

Key issues

Page 3: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

3

Think Infrastructure.

Think IDFC.

From 6 MW of solar power in Oct 2009 …

Solar power accounts for less than 0.1% of grid

interactive renewable power

But solar power has been deployed for off-

grid electrification

Programme/Systems Achievement*

Off-Grid/Distributed Power

Solar PV Power Plants &

Street Lights2.39 MWp

Decentralized systems

Home Lighting Systems 5,10,877 nos

Solar Lanterns 7,67,350 nos

Street Lighting System 82,384 nos

PV Pumps 7,247 nos

Solar Water Heating Systems 3.12 million sq.m. of

collector area

Solar Cookers 6.57 lakh

Source : MNRE

Small Hydro Power 16.2%

Cogeneration-bagasse 8.0%

Wind Power 70.1%

Biomass 5.3%

Waste to Energy 0.4%

Solar power 0.04%

Page 4: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

4

Think Infrastructure.

Think IDFC.

…to 20,000 MW of solar power by 2022

Phases Grid solar power including roof topOff grid solar

applications

Phase I (2010-13) 1000 MW 200 MW

Phase II (2013-17) 4000 MW (10,000 MW based on enhanced

international finance & technology transfer)

1000 MW

Phase III (2017-22) 20,000 MW 2000 MW

… and Grid Parity by 2022 & Coal Parity by 2030

Land based utility scale solar power projects thru a bundling scheme

Grid connected Roof top PV systems thru Generation Based Incentives (GBI)

20 million solar lighting systems and other off-grid systems to cover about 10,000 villages through

capital subsidies

3 key focus areas

Page 5: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

5

Think Infrastructure.

Think IDFC.

To make targets a reality, the Mission aims to provide an

enabling environment for developers & manufacturers

20000 MW

Regulation

Fiscal incentives

R&D

Indigenous manufactu

ring

Demo Projects

HRD

… & envisages gradual deployment to attain critical mass till costs come down & rapid scale up thereafter

Page 6: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

6

Think Infrastructure.

Think IDFC.

Salient features of the Mission…(1/2)

Renewable Purchase Obligations of utilities to be

split into solar and non-solar

RPO may start with 0.25% in Phase I and increase to

3% by 2022

RPO to be fixed after modification of the National

Tariff Policy 2006

RE Certificates to meet RPO

NVVN appointed as Nodal Agency for purchase & sale

of grid connected solar power at 33 kV & above

under Phase –I

For each MW of solar power, MOP to allocate

equivalent MW capacity from unallocated quota of

NTPC stations

NVVN to bundle solar & thermal power & sell it at

regulated tariff plus facilitation charges

Provision of GBI to100 MW capacity solar projects

connected to LT/11 KV grid

Eligibility: own consumption as well as power fed into

the grid

GBI rate: tariff fixed by CERC minus notional tariff of

Rs. 5.5 per unit, with 3% annual escalation

Technology configurations not covered under 1,000

MW capacity

Projects to be set up following competitive bidding

to enable price discovery

Maximize indigenous content

Technology transfer

Solar RPOBundling scheme

Demonstration ProjectsGeneration Based Incentive

Page 7: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

7

Think Infrastructure.

Think IDFC.

Salient features of the Mission…(2/2)

Improve efficiency of existing/new materials &

applications & develop cost effective storage

technologies

Development of National Centre of Excellence &

Centres of Excellence to undertake & fund R&D

High level Research Council to guide overall strategy

Support Incubation & Innovation through a Venture

Fund

Promote solar home lights & other power applications

to cover 10,000 MW villages & hamlets

Re-finance facility/Soft loans up to 5% annual interest

rate by IREDA

30% subsidy for select applications

90% subsidy for niche applications to special category

areas

R&D

Off - grid opportunity

Build technically qualified manpower of international

standard

Develop specialized courses at engineering colleges

Ministry of Labour to introduce training modules/

course materials for technicians

100 fellowships a year to support students/ groups

National Centre for PV Research & Education at IIT,

Mumbai

Increase competitiveness of solar projects & provide

enabling environment for solar manufacturers

Recommendation to MoF for custom and excise duty

concessions/exemptions on specific capital

equipment, critical materials, components & project

imports

SEZ like incentives to manufacturing parks

Fiscal/Financial incentives

HRD

Page 8: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

8

Think Infrastructure.

Think IDFC.

Towards a solar future…

What is the Solar Mission?

How is it being implemented?

Key issues

Page 9: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

9

Think Infrastructure.

Think IDFC.

Bundling scheme proposes to make solar power cheaper

by bundling it with coal based power

Solar Power Developer NTPC Unallocated Power

PV: Rs. 17.91/unit

CSP: Rs. 15.31/unit

NVVN

Rs. 2.5/unit

X kwh4X kWh

Price of bundled power or weighted price

PV: (17.91X + 10X)/5X = Rs. 5.58/unit

CSP: (15.315X + 10X)/5X = Rs. 5.06/unit

Sale price of power given ratio of

PV to CSP is 50:50 = Rs. 5.32/unit

Utility

… to approx. Rs. 5.50/unit & make it more attractive than power purchased in the marketAlso addresses concern of payment security for SPDs

Figure for illustrative purposes only

Page 10: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

10

Think Infrastructure.

Think IDFC.

There are separate schemes for projects under

development & new projects

SPDs who have signed a PPA with a discom

on or before November 19, 2009 but project

CoD not achieved

SPDs who have filed a Petition and PPA for

determination of tariff with the concerned

SERC but project CoD not achieved

Only about 25-30 MW expected (SPDs under

earlier GBI scheme)

SPDs approaching with new proposals

Confirmation for plant CoD to be on or

before March 31, 2013

New Projects SchemeMigration Scheme

Two pronged approach here: state provides land, water, sanctions & grid connectivity and GoI takes care of PPAs and sale of power

Page 11: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

11

Think Infrastructure.

Think IDFC.

Migration Scheme

Page 12: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

12

Think Infrastructure.

Think IDFC.

Criteria for participation as per guidelines issued

Concurrence of discom/State Government for migration to JNNSM

Confirmation from Discom for power purchase from plant through NVVN

Possession of 100% of land (defined at 2 hectares/MW)

Approval from STU for evacuating power to the grid at 33 kV & above

Necessary water linkage (for CSP plants)

Letters of comfort for funding the project

BG @ Rs. 50 Lac per MW to NVVN, half on signing of MoU & half on signing of PPA

BG valid for 15 months for PV & 31 months for thermal projects

No change in equity holding from signing of MOU till PPA execution; but listed companies exempt

After PPA, controlling shareholding in SPD to be maintained for 3 years after commencement of power

supply

Financial closure within 3 months of signing PPA; no extension allowed

Project to be removed from list of projects eligible for migration & BG will be forfeited

CoD for PV within 12 months of PPA & of Solar Thermal within 28 months of PPA

PPAs to be the same as that signed with discoms & power to be sold to the same discoms

Page 13: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

13

Think Infrastructure.

Think IDFC.

Time frame for implementation

Announcement of

list of eligible projects

Mar 18, 2010

Signing of MoU

Apr 17, 2010

Signing of PPA

July 17, 2010

SPD to give

details to NVVN

Feb 26, 2010

Page 14: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

14

Think Infrastructure.

Think IDFC.

New Projects Scheme

Page 15: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

15

Think Infrastructure.

Think IDFC.

Salient features

Ratio of PV and thermal at 50: 50

Technology agnostic within PV & thermal

Encourage deployment of latest technologies through projects wherein SPDs could tie up with proven

technology providers/module manufacturers offering better efficiency/technology (with successful

operation for at least 2 years) than what is available & being deployed in India, after an evaluation of

the proposed technology

Review status after one year to make any modifications

Technology portfolio

PV: min of 5 MW & max of 25 MW

Thermal: min of MW & max of 100 MW

Min & Max capacity of projects

PV: projects to use indigenous modules; proposal to mandate use of indigenous cells

Thermal: 30% of total project cost to be utilized for domestic equipment

Domestic content

Page 16: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

16

Think Infrastructure.

Think IDFC.

Salient features

Net worth of Rs 2 Crore/MW

Technical Criteria

SPD to propose deployment of commercially established technology - at least 1 project operational of

the proposed technology for last 2 years anywhere in the world

Detailed technical parameters specified

Land arrangement

Land requirement specified at 2 Hectares/MW

SPD to have at least 50% of land when submitting EoI & entire land before signing PPA

Allotment letter of state in case of government land, ‘Agreement for Sale of land’ with land owner in

case of Private Land, long term lease arrangement (for at least 30 years) in case of land being taken

on lease

Grid connectivity

At 33kv/132kv or higher voltage levels with grid sub-station & not distribution sub-station

SPD to give letter from STU confirming technical feasibility of connectivity

SPD responsible for transmission arrangement from plant to sub-station

Water arrangement

SPD to submit documentary approval from state/local authority for quantity of water required for

thermal plants

Qualification criteria

Page 17: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

17

Think Infrastructure.

Think IDFC.

Salient features

All projects meeting qualification criteria irrespective of share of technologies

Short-listing of projects

For PV projects, phased selection by allocating overall capacities over FY 2010-11 & FY 2011-12

If total aggregate capacity short listed under any technology is higher than the capacity to be selected

Option 1 : Reverse bidding where SPDs indicate percentage of tariff to be shared with NVVN for

administrative costs & risk sharing. SPD offering max share to be selected first & so on

Option 2: All projects up to a capacity of 5 MW for PV & 20 MW for thermal selected. Remaining

projects to be allotted remaining capacity equally

To buffer for implementation failures, total capacity can be 105% of capacity to be selected for that

technology

Provision to be used only if last project selected is proposed for a capacity, which requires total

capacity for the technology to be increased beyond what was originally decided

Selection of projects

Page 18: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

18

Think Infrastructure.

Think IDFC.

Salient features

BG @ Rs. 50 Lac per MW to NVVN, half on signing of MoU & half on signing of PPA

BG valid for 15 months for PV & 31 months for thermal projects

No change in equity holding from signing of MOU till PPA execution; but listed companies exempt

After PPA, controlling shareholding in SPD to be maintained for 3 years after commencement of

power supply

Financial closure within 3 months of signing PPA; no extension allowed

CoD for PV within 12 months of PPA & of Solar Thermal within 28 months of PPA

Others

Page 19: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

19

Think Infrastructure.

Think IDFC.

Time frame for implementation

Invitation

of EOI

Mar 31, 2010

Jun 30, 2010

Sep 15, 2010

Last date for

applications

Selection of

projects by

Central

Empowered

Committee

Sep 30, 2010

Signing of MoUs

with SPDs

Signing of

PPAs & PSAs

Oct 31, 2010

Company to provide Board Resolution on intention to develop

project

Page 20: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

20

Think Infrastructure.

Think IDFC.

Some features of PPAs

PPAs and PSA are co-terminus agreements & are back-to-back

NVVN to assign payment of LD on SPD if CUF of the plant is found to be below CERC specified CUF

By 5% at any point in the term, or

By 3% for consecutively or non-consecutively for 3 months in a year

Right to contracted capacity:

SPD to sell exclusively to NVVN the entire Contracted Capacity subject to maximum of energy generation

NVVN not obligated to purchase power generated beyond the contracted number of units. SPD free to sell

such power to third party

SPD free to sell power generated before Scheduled COD to third party

Limitation of Payment Liability

NVVN’s payment liability limited to payments realized from Discom after exhausting all payment security

measures

Page 21: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

21

Think Infrastructure.

Think IDFC.

Some features of PSAs

Payment Security Mechanism

Discom to open LC within 1 month of Scheduled COD to be made operative prior to Due Date of first

Monthly Bill

LC to be revoked if Discom fails to pay a Monthly Bill or Supplementary Bill or part thereof within 30 days

from the Due Date

Renewable purchase obligation of Discom shall be considered to be met only if there is no payment default

towards NVVN

Third Party Sale by NVVN

In case NVVN is not able to realize the due payments beyond 30 days after the Due Date, NVVN shall have

the right to divert the Bundled Power or part thereof and sell it to any third party

Page 22: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

22

Think Infrastructure.

Think IDFC.

Towards a solar future…

What is the Solar Mission?

How is it being implemented?

Key issues

Page 23: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

23

Think Infrastructure.

Think IDFC.

General concerns

Lack of long term strategy

How will 4000 MW be scaled to 10,000 MW at the end of 12th plan?

Is technology the Achilles Heel?

No solar supply chain in India

Land acquisition issues will affect solar plants

No time frame defined for finalization of R&D strategy

Page 24: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

24

Think Infrastructure.

Think IDFC.

Concerns on bundling scheme

Cheap coal based power has been made more expensive

GoI was contemplating using unallocated power to incentivize open access in states. What happens to that?

Bankability of agreements given that SPDs will not sign PPAs directly with offtaker

Adequacy of time frame for commissioning of solar thermal projects

Financial criteria not at par with established practices in coal sector

Overall issues

Specific issues on New Projects Scheme

No justification for restriction of plant size

Current capacity does not promote economies of scale

Transmission arrangements

Will cost justify small sized projects?

Transmission line to be compatible with high voltage levels; capacity of line may remain unutilized

Adequacy of time frame for financial closure

Land acquisition for entire proposed capacity but eventual capacity allocation may be less

Page 25: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

25

Think Infrastructure.

Think IDFC.

Main concerns on proposed PPAs/PSAs

LD on SPD if CUF is below CERC specified level

CERC CUF already on higher side & does not reflect locational differences

NVVN will not offtake power beyond specified maximum generation

Where does SPD go to sell such high cost power?

NVVN does not bear payment risks

How will SPDs get paid if discom defaults more than once?

Page 26: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

26

Think Infrastructure.

Think IDFC.

Regulatory, Credit & Technology risk hindering

robust financing possibilities

Regulatory

Lack of visibility on approved capex beyond FY 2012 & 2013

NVVN does not bear payment risks

PPA & PSA co-terminus

Inability of GoI to force states to adopt JNNSM

SEB

Poor health of most of SEBs

Willingness of SEBs to be bound by JNNSM

Technology & Developer

Existing technology unproven in Indian context

No clear technology leader

Lack of credible developers

Page 27: The Jawaharlal Nehru National Solar Mission Implementation ... · PDF fileNational Solar Mission Implementation Issues on Bundling Scheme. 2 ... NTPC stations NVVN to bundle ... Technical

27

Think Infrastructure.

Think IDFC.

Thank You