Smoke control design to CEN/TR 12101-5
Paul Compton
Colt International Limited
1
-
LOGO
CEN/TR 12101-5:
Smoke and heat control systems Part 5: Guidelines on functional recommendations and calculation methods for smoke and heat exhaust
systems.
2
-
LOGO
Contents
Introduction
How to use the TR
Results
The future
3
-
LOGO
History
Based on British design methods:
-Fire papers 7 & 10 1963 & 1964
-BR 34 1979
-BR 186 1990
-BR 258 1994
-BR 368 1999
-BS 7346-4 2003
4
-
LOGO
Why a CEN/TR?
A CEN/TR is a Technical Report.
It does not have the same authority as an EN.
It is used when there is insufficient agreement for an EN.
5
-
LOGO
Purpose of the TR
Guidance to designers on function
and steady state calculation of SHEVS.
Doesnt cover equipment selection or installation (CEN/TR 12101-4).
Gives zoning, mass and volume flow rates, aerodynamic area of exhaust and inlet and minimum number of exhausts.
6
Time
Fir
e S
ize
-
LOGO
Weaknesses
Limited guidance on fire size.
Not very user friendly layout.
Best spill plume calculation is difficult to use.
More research is needed to improve some calculations.
7
-
LOGO
Who should use CEN/TR 12101-5
Intended for people with suitable understanding, knowledge and training.
Authorities checking designs also need knowledge so they can do more than simply check the maths.
8
-
LOGO
How to use it criteria
The starting point is to know what the system is for and what criteria need to be met:
-Maximum smoke layer temperature
-Minimum clear layer height
-Maximum air inlet velocity.
9
-
LOGO
How to use it design fire
This is the most critical part of the design:
-Pre flashover, not maximum possible size
-Realistic maximum before control by sprinklers or fire fighters
-Realistic high and low heat outputs.
10
-
LOGO
How to use it smoke reservoirs
Design formulae in the TR do not allow for cooling of the smoke layer. Therefore: -Maximum reservoir areas are limited to keep cooling low enough to be ignored, or; -Heat losses by conduction and radiation should be separately calculated. The 60m limit separately limits travel distance for evacuation under the smoke layer.
11
-
LOGO
Interaction with sprinklers
Sprinklers allow use of a smaller design fire. The heat output per m2 is unchanged. Cooling of the smoke layer due to sprinklers is explicitly included in the calculations. Guidance on initiation gives priority to sprinklers unless the SHEVS is a life safety system.
12
-
LOGO
Options
The standard is deliberately written with all calculations in Informative Annexes.
This allows use of alternative calculation methods, such as NFPA 92 or 204, while still following 12101-5.
Mixing calculation methods is not recommended. Follow one method throughout.
13
-
LOGO
Results
Following this standard provides design flow rates and ventilation areas.
There is still much work to be done to turn this into an installed system.
CEN/TR 12101-4 and/or national guidance can be used for this.
14
-
LOGO
The future
12101-12 for time dependent design is being written.
It takes a more European approach.
12101-5 will need to change to match it but probably not for at least 5 years.
In the meantime used properly CEN/TR 12101-5 is a good guide, probably the best.