September 2013

1

Page 2: September 2013 - INOGATE

Contents

1. Procedure for the Submission of FDPs

2. Presentation of FDPs and Electronic File Instructions

2

Page 3: September 2013 - INOGATE

After the completion of the Works of the Project Contractor is obliged to submit to DESFA the Final Technical Documentation Package (FDP) of the Project.

The Contractor is collecting and preparing on DESFA ’ s behalf , all the technical documentation related to the Project regardless of the documents issued by other parties.

The technical documents are submitted to DESFA in Final As Built Status. Those documents can be originated by contractor, study group, supplier, inspector , etc . and are submitted in volumes (Final Documentation Packages).

FDP are the Final Technical Documentation of a Contractor / vendor / engineer ,which is separated into volumes containing all types of document s necessary related to a specific activity such as Civil Works, Mechanical Works, Building constructions etc.

3

Page 4: September 2013 - INOGATE

The final technical documents are separated into the following categories :

1. Documents for Operation and Maintenance - DFOM

“Documents for Operation and Maintenance - DFOM “are the technical documents with information regarding the operation of a system (operating manual ) . Included in this category are the documents that provide instruction for the operation of a project such as the maintenance manual .

2. Quality Records - QR

“Quality Records – QR” are the documents that verify the quality of equipment materials or constructed work . These documents are in conformance with approved standards ( material certificate , welding log book ) .

3. Final “ as built ” documents and drawings - FAB

“Final “ as built ” documents and drawings – FAB” are the final issue of drawings and documents of a project such as various equipment list and drawings regarding a specific section completed ( as - built drawings ) .

4. Retained documents – RD

“Retained documents – RD” are the technical documents regarding the basic study of a project (basic design ) . This category also includes contract articles , basic drawings of the network , calculations , environmental study , etc .

4

Page 5: September 2013 - INOGATE

1. During the preparation phase of the FDP by the Contractor , the SUPERVISING ENGINEER carries out periodic audits and offers additional instructions to ensure the compliance of the FDP with DESFA Requirements under the responsibility of the Project Manager. The project ‘ s SUPERVISING ENGINEER is responsible for the completeness, correctness and acceptance of all final technical documentation from the Contractor.

DESFA ’s representative ( DCC Manager ) in cooperation with the Project Manager executes

periodic documentation audits during the construction phase of the Project and in

collaboration with the SUPERVISING ENGINEER give proper instruction to ensure

compliance with DESFA Requirements.

Contractor is obligated to adjust his documentation filing system in accordance to the

remarks and suggestions of DESFA’s DCC Manager, Project Manager and Supervising Engineer

and make available any information - documentation requested throughout the project .

5

Page 6: September 2013 - INOGATE

2. Final Documentation Package Registers – Final Lists – Overall Indexes are submitted by Contractor in advance in electronic format for review and approval by DESFA.

3. The Project ‘ s Contractor delivers the volumes to the Supervision (1 original and 3 copies of the documents are submitted) . The Supervision signs all the detailed FDP Registers. TPI has the obligation to verify the completeness and the correctness of the FDP’s that are under the scope of work of TPI contract with DESFA. During the FDP Audits, DESFA DCC issue a report of which FDP files are according to DESFA Requirements.

4. Contractor submits the approved by Supervision, TPI and DESFA DCC FDP files in physical and electronic format to DESFA DCC . An acceptance protocol is signed by all parties. The delivery , control and acceptance of the FDP can be accomplished in cooperation with Supervision, Project Manager and DESFA / DCC representative for time conservation.

6

Page 7: September 2013 - INOGATE

All Packages submitted are in binders (files) with transparency folders outside.

The FDP cover sheet identifies the Project, the section, the sub-section, the Contractor, the Supervision Engineer, the contract number, the contracts W.B.S, package description, package number, volume number, total number of volumes, copy number.

The front page is dated and is identifying the Project, the section, the sub-section, the FDP description, the FDP number, the FDP Revision, the FDP revision date

The index is dated and is identifying the Package description, package number, section, sub-section, volume number and for each document the Contractors document number, title, revision number, revision date, status, total number of pages per document and total number of pages per package. The Index is also identifying the computerised file number of each document, if this exists.

The As built drawings in paper are issued to DESFA like all other technical documents, that is in A4 binders (files) folded in A4 size.

7

Page 8: September 2013 - INOGATE

For the submitted X-ray films a cover page and index is included. The cover page is dated and identifies the unit, section, sub-section, the Km, the number of the box and the first and last joint. The index is also dated and identifies the number of each weld, the X-ray report, the number of the films, the necessary re-shots and the total number of films.

The X-ray films is issued to DESFA together with a radiographic film register, which contains data of the weld, the NDT report, the result, date of test, welder, reference drawings, reference K points, Km, section, sub-section and the box number in which the X-ray is included.

All final technical documents that are required in a computer based format should be in accordance to contract specifications, procedures and agreements concluded between Contractor, Supervision and DESFA. The information in electronic format must always be easily accessible. The Contractor has to ensure that this form of final documentation (documents / drawings) has been properly tested for validity of data, for readability of media (CD – DVD –HARD DISKS) and that all system problems that may occur have been corrected. All technical documents / drawings in digital format have to be identical to the physical hard copy and their file name to reflect the contents so that by the file name for easy recognition of the document / drawing (traceability).

All drawings are in AutoCAD format (.dwg). The drawings are designed in original coordinates.

8

Page 9: September 2013 - INOGATE

All Final Technical Documentation (Final Documentation Package) are also scanned by Contractor (structured according to the FDP Register) and digital files (TIFF format) are submitted by Contractor for review by Supervising Engineer / Project Manager and final acceptance by DESFA.

All approved Final “As-Built” drawings and the various Lists included in the Final Technical Documentation are submitted to DESFA / Project Manager also in a processable digital file format in standard DXF or DWG format for “AutoCAD” latest release in CD or DVD-ROM’s. The drawings are submitted in standard DXF or DWG format for “AutoCAD” latest release. The lists are submitted in “Microsoft Office Word/ Excel” files.

Final instructions for the type and structure of Final Documentation Packages are given by DESFA’s DCC.

9

Page 10: September 2013 - INOGATE

LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204

HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1

FDP No. Description Protocol

No. Date to PMN

Date To DEPA

VOL No

Comments

GEN DFOM

HPPL-ALIVERI/ FDP/PL-S/GEN/DFOM/001

BASIC PIPELINE OPERATION & MAINTENANCE MANUAL By DESFA

HPPL-ALIVERI/FDP/PL-S/GEN/DFOM/002

SYSTEM OPERATION & MAINTENANCE MANUAL By DESFA

HPPL-ALIVERI/FDP/PL-S/GEN/DFOM/003

VENDORS MANUALS

OPERATING MANUAL

MAINTENANCE MANUAL SPARE PARTS LIST AND SCHEDULE

HPPL-ALIVERI/FDP/PL-S/GEN/DFOM/004

EFD'S

HPPL-ALIVERI/FDP/PL-S/GEN/DFOM/005

VARIOUS LIST

VALVE LIST

EQUIPMENT LIST INSTRUMENT LIST AND SCHEDULE LIST OF K POINTS

LIST OF MARKER POSTS

LIST OF CROSSINGS LIST OF MEASURING POSTS

PROCUREMENT LIST RECEIVED

PIPE & MATERIAL LIST - SPARE PIECES INSTALLED

GUARANTEE WELD LIST

TELECOMUNICATION CABLE JOINTS LIST NOT APPLICABLE

HDPE JOINT LIST

INSULATING JOINT LIST

LIST OF HOT BENDS

LIST OF FIELD BENDS

LIST OF SADDLES

LIST OF LEVELS OF PIPE AND GROUND TOP BETWEEN SYMBOLS

OF DETAIL DRAWING

CLASS LOCATION LIST 10

Page 11: September 2013 - INOGATE

LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204

HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1

GEN FAB

HPPL-ALIVERI/FDP/PL-S/GEN/FAB/001 MATERIAL REQUISITIONS

HPPL-ALIVERI/FDP/PL-S/GEN/FAB/002 JOB SPECIFICATIONS

HPPL-ALIVERI/FDP/PL-S/GEN/FAB/003 STANDARD DRAWINGS

HPPL-ALIVERI/FDP/PL-S/GEN/FAB/004 AS BUILT DRAWINGS ,PIPE & WELD LOG BOOK ,VARIOUS LIST ,OVERALL

& DETAIL FDP REGISTER IN COMPUTERIZED FORMAT

GEN QR

HPPL-ALIVERI/FDP/PL-S/GEN/QR/001 QUALITY ASSURANCE MANUAL/PLAN / PROCEDURES

HPPL-ALIVERI/FDP/PL-S/GEN/QR/002 SAFETY MANUAL / PROCEDURES / PLAN

HPPL-ALIVERI/FDP/PL-S/GEN/QR/003 AUDIT REPORT (INTERNAL/EXTERNAL)

HPPL-ALIVERI/FDP/PL-S/GEN/QR/004 NON-CONFORMANCE REPORTS-CORECTIVE ACTION REPORTS /

TECHNICAL QUERIES

HPPL-ALIVERI/FDP/PL-S/GEN/QR/005 W.P.S. & P.Q.R

HPPL-ALIVERI/FDP/PL-S/GEN/QR/006 WELDER QUALIFICATION CERTIFICATES

HPPL-ALIVERI/FDP/PL-S/GEN/QR/007 CERTIFICATE OF NDT OPERATOR

HPPL-ALIVERI/FDP/PL-S/GEN/QR/008 DESTRUCTIVE TEST RECORDS

HPPL-ALIVERI/FDP/PL-S/GEN/QR/009 PIPE & MATERIAL RECEIPT REPORT

HPPL-ALIVERI/FDP/PL-S/GEN/QR/010 PIPE & MATERIAL RELEASE REPORT

HPPL-ALIVERI/FDP/PL-S/GEN/QR/011 INSPECTION DATA BOOKS / PIPE AND MATERIAL CERTIFICATES /

CALIBRATION CERTIFICATES

SUPPLY BY CONTRACTOR

HPPL-ALIVERI/FDP/PL-S/GEN/QR/012 INSPECTION DATA BOOKS / PIPE AND MATERIAL CERTIFICATES /

CALIBRATION CERTIFICATES SUPPLY BY DEPA

HPPL-ALIVERI/FDP/PL-S/GEN/QR/013 PIPE COATING CERTIFICATES BY VENDOR IF SEPARATE

HPPL-ALIVERI/FDP/PL-S/GEN/QR/014 PRECOMMISSIONING RECORDS BY DESFA

TELECOMUNICATION CABLE MEASUREMENT & DIAGRAM OPERATIONAL TEST FOR MOTOR OPERATING VALVES OPERATIONAL TEST FOR PILARS

HPPL-ALIVERI/FDP/PL-S/GEN/QR/015 COMMISSIONING RECORDS BY DESFA 11

Page 12: September 2013 - INOGATE

LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204

HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1

GEN RD

HPPL-ALIVERI/FDP/PL-S/GEN/RD/001 OVERALL AND DETAIL FDP REGISTER - EDR

HPPL-ALIVERI/FDP/PL-S/GEN/RD/002 CONTRACTUAL DOCUMENT-BASIC DESIGN

HPPL-ALIVERI/FDP/PL-S/GEN/RD/003 STUDIES-CALCULATIONS

HPPL-ALIVERI/FDP/PL-S/GEN/RD/004 DETAILED DESIGN DRAWINGS (AFC)

HPPL-ALIVERI/FDP/PL-S/GEN/RD/005 PERMITS/LICENCES/ACCEPT.CERTIFICATES

HPPL-ALIVERI/FDP/PL-S/GEN/RD/006 DAILY SITE LOG BOOKS

HPPL-ALIVERI/FDP/PL-S/GEN/RD/007 CONSTRUCTION PLANS FOR SPECIAL WORKS - METHOD STATEMENT

HPPL-ALIVERI/FDP/PL-S/GEN/RD/008 FIBRE OPTIC INSTALL. PROTOC. OF WORKS COMPLETION NOT APPLICABLE

HPPL-ALIVERI/FDP/PL-S/GEN/RD/009 MECHANICAL COMPLETION FILE-T.P. INSPECTION CERTIFICATE

HPPL-ALIVERI/FDP/PL-S/GEN/RD/010 CLOSE OUT REPORT BY SV -AND PM

HPPL-ALIVERI/FDP/PL-S/GEN/RD/011 PHOTO DOCUMENTATION FOR PIPELINE & STATIONS

SECTION 6300 FAB

HPPL-ALIVERI/FDP/PL/6300/FAB/001 AS-BUILT DRAWINGS FOR PIPELINE Recording Plans 1:1000)

HPPL-ALIVERI/FDP/PL/6300/FAB/002 AS-BUILT DRAWINGS FOR PIPELINE Longitudinal sections 1:1000)

HPPL-ALIVERI/FDP/PL/6300/FAB/003 AS-BUILT DRAWINGS FOR PIPELINE Detail Drawings 1:200, 1:500)

HPPL-ALIVERI/FDP/PL/6300/FAB/004 AS-BUILT DRAWINGS FOR PIPELINE Longitudinal sections of Detail

Drawings 1:100, 1:200, 1:500)

HPPL-ALIVERI/FDP/PL/6300/FAB/005 AS-BUILT DRAWINGS FOR PIPELINE Maps 1:50000, & Recording plan

1:5000)

HPPL-ALIVERI/FDP/PL/6300/FAB/006 AS-BUILT DRAWINGS FOR STATIONS (Piping

Arrangement & Isometric Piping Arrangement Drawings)

HPPL-ALIVERI/FDP/PL/6300/FAB/007 AS-BUILT DRAWINGS FOR STATIONS (Plot Plans,

Gabion, Reinf. Concrete Retaining Walls)

HPPL-ALIVERI/FDP/PL/6300/FAB/008 AS-BUILT DRAWINGS FOR STATIONS (Area

Classification Drawings)

HPPL-ALIVERI/FDP/PL/6300/FAB/009 X-RAY FILM HAND OVER PROTOCOLS FOR PIPELINE AND STATIONS 12

Page 13: September 2013 - INOGATE

LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204

HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1

SECTION 6300 QR

HPPL-ALIVERI/FDP/PL/6300/QR/001 MARKING THE ROW

PERMITS FOR WORKS IN ROW ROW PREPARATION REPORTS

HPPL-ALIVERI/FDP/PL/6300/QR/002 PERMITS FOR TRENCHING NOT APPLICABLE

TRENCHING REPORTS

HPPL-ALIVERI/FDP/PL/6300/QR/003 BEDDING REPORTS NOT APPLICABLE

HPPL-ALIVERI/FDP/PL/6300/QR/004 WELDING LOG (DAILY ) NOT APPLICABLE

HPPL-ALIVERI/FDP/PL/6300/QR/005 PIPE AND WELD LOG BOOK (FINAL )

HPPL-ALIVERI/FDP/PL/6300/QR/006 TIE-IN REPORTS NOT APPLICABLE

HPPL-ALIVERI/FDP/PL/6300/QR/007 GUARANTEE WELD

HPPL-ALIVERI/FDP/PL/6300/QR/008 WELDING REPORTS

RADIOGRAPHIC INSPECTION REPORTS ULTRASONIC EXAMINATION REPORTS DYE PENETRANT REPORTS MAGNETIC PARTICLE REPORT

HPPL-ALIVERI/FDP/PL/6300/QR/009 FIELD BENDING CONTROL SHEETS

HPPL-ALIVERI/FDP/PL/6300/QR/010 PIPE COATING REPORTS (FIELD JOINT)

HOLIDAY TEST REPORT

HPPL-ALIVERI/FDP/PL/6300/QR/011 PERMITS FOR LOWERING PIPE NOT APPLICABLE

LOWERING LAYING REPORTS

HPPL-ALIVERI/FDP/PL/6300/QR/012 PERMITS FOR BACKFILLING NOT APPLICABLE

BACKFILLING REPORTS

HPPL-ALIVERI/FDP/PL/6300/QR/013 PERMITS FOR REISTATMENT NOT APPLICABLE

REINSTATEMENT REPORT

HPPL-ALIVERI/FDP/PL/6300/QR/014 PERMITS FOR CROSSING

HPPL-ALIVERI/FDP/PL/6300/QR/015 PROTOCOL FOR AUGER BORED CROSSINGS PERMITS ONLY

HPPL-ALIVERI/FDP/PL/6300/QR/016 BORING REPORT CHECK LISTS,SURVEYING DATA

HPPL-ALIVERI/FDP/PL/6300/QR/017 PROTOCOLS FOR RIVER CROSSINGS PERMITS ONLY

HPPL-ALIVERI/FDP/PL/6300/QR/018 INSTALL. OF HDPE PIPE (CONDUIT)FOR FIBRE OPTIC CABLE

HPPL-ALIVERI/FDP/PL/6300/QR/019 HDPE PIPE TESTS REPORTS (CHECKS)

HPPL-ALIVERI/FDP/PL/6300/QR/020 QUALITY CONTROL FOR CONCRETE WORKS

HPPL-ALIVERI/FDP/PL/6300/QR/021 CONCRETE SADDLES INSPECTION REPORTS

HPPL-ALIVERI/FDP/PL/6300/QR/022 COMPACTION REPORTS

HPPL-ALIVERI/FDP/PL/6300/QR/023 GRANULOMETRIC GRADUATION OF AGGREGATE

HPPL-ALIVERI/FDP/PL/6300/QR/024 PIPELINE HYDROTEST REPORTS / DRYING

HPPL-ALIVERI/FDP/PL/6300/QR/025 QA FORMS & RECORDS FOR STATIONS 13

Page 14: September 2013 - INOGATE

LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204

HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1

SECTION 6300 RD

HPPL-ALIVERI/FDP/PL-S/6300/RD/001 REINSTATEMENT PROTOCOLS

HPPL-ALIVERI/FDP/PL-S/6300/RD/002 SURVEY WORKS-TECHNICAL DESCRIPTION

TRIANGULATION-DIAGRAM-SOLUTION OF TRIANGULATION

TABLE OF TRIANGULATION POINTS (CORDINATION & LEVELS)

DESCRIPTION & REFERENCE OF TRIAGULATION POINTS

TRIAGULATION POINTS PHOTO DOCUMENTATION

SOLUTION OF POLYGONOMETRY, NOT APPLICABLE

REFERENCE OF POLYGONOMETRY POINTS NOT APPLICABLE

TABLE OF POLYGONOMETRY POINTS (COORDINATES & LEVELS) NOT APPLICABLE

LEVELING-DIAGRAM OF LEVELING POINTS NOT APPLICABLE

DESCRIPTION & REFERENCE OF LEVELING POINTS NOT APPLICABLE

LIST OF GEODETICAL NETWORK NOT APPLICABLE

TABLE OF LEVELING POINTS NOT APPLICABLE

CP CATHODIC PROTECTION

CP-GEN DFOM

HPPL-ALIVERI/FDP/CP/GEN/DFOM/001 C.P. OPERATION & MAINTENANCE MANUAL NOT APPLICABLE

HPPL-ALIVERI/FDP/CP/GEN/DFOM/002 CONFIGURATION DIAGRAM FOR C.P.SYSTEM

HPPL-ALIVERI/FDP/CP/GEN/DFOM/003 KEY-PLAN DRAWINGS FOR C.P. AREAS

HPPL-ALIVERI/FDP/CP/GEN/DFOM/004 VENDORS MANUALS

HPPL-ALIVERI/FDP/CP/GEN/DFOM/005 SPARE PARTS

14

Page 15: September 2013 - INOGATE

LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204

HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1

CP-GEN FAB

HPPL-ALIVERI/FDP/CP/GEN/FAB/001

MATERIAL REQUISITIONS

HPPL-ALIVERI/FDP/CP/GEN/FAB/002

JOB SPECIFICATIONS

HPPL-ALIVERI/FDP/CP/GEN/FAB/003

STANDARD DWGS

CP-GEN QR

HPPL-ALIVERI/FDP/CP/GEN/QR/001 QUALITY ASSURANCE PROCEDURES

HPPL-ALIVERI/FDP/CP/GEN/QR/002 INSPECTION DATA BOOKS

HPPL-ALIVERI/FDP/CP/GEN/QR/003 NON CONFORMANCE RECORDS IF ANY

HPPL-ALIVERI/FDP/CP/GEN/QR/004 COMMISSIONING RECORDS IF ANY

CP-GEN RD

HPPL-ALIVERI/FDP/CP/GEN/RD/001 BASIC DESIGN

HPPL-ALIVERI/FDP/CP/GEN/RD/002 STUDIES - CALCULATIONS

HPPL-ALIVERI/FDP/CP/GEN/RD/003 DETAILED DESIGN DRAWINGS

HPPL-ALIVERI/FDP/CP/GEN/RD/004 DAILY SITE LOG BOOKS COPY OF ORIGINAL

CP AREA 30 FAB

HPPL-ALIVERI/FDP/CP/AREA 30/FAB/001

AS-BUILT DRAWING

15

Page 16: September 2013 - INOGATE

LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204

HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1

CP AREA 30 QR

HPPL-ALIVERI/FDP/CP/AREA 30/QR/001 CATHODIC PROTECTION PIN BRAZING & CABLE CONNECTION FOR

MEASURING POST REPORTS

HPPL-ALIVERI/FDP/CP/AREA 30/QR/002 CP PROTECTION,INSTALLATION OF MEASURING POSTS & CABLE

CONNECTIONS RECORD SHEET NOT APPLICABLE

HPPL-ALIVERI/FDP/CP/AREA 30/QR/003 CATHODIC PROTECTION CHECK & CALIBRATION OF POLARIZATION

PROBES REPORT (POST TYPE K9) NOT APPLICABLE

HPPL-ALIVERI/FDP/CP/AREA 30/QR/004 CATHODIC PROTECTION SOIL RESISTIVITY MEASUREMENTS FROM STUDY

HPPL-ALIVERI/FDP/CP/AREA 30/QR/005 CATHODIC PROTECTION TEST REPORTS FOR RIVER CROSSING NOT APPLICABLE

HPPL-ALIVERI/FDP/CP/AREA 30/QR/006 CATHODIC PROTECTION TEST REPORTS FOR ROAD/RAILWAY CROSSINGS

WITH CASING

HPPL-ALIVERI/FDP/CP/AREA 30/QR/007 TEMPORARY C.P. SACRIFICIAL ANODE INSTALLATION MEASUREMENTS

SHEETS

HPPL-ALIVERI/FDP/CP/AREA 30/QR/008 CATHODIC PROTECTION NATURAL POTENTIAL RECORDS SHEETS

HPPL-ALIVERI/FDP/CP/AREA 30/QR/009 CATHODIC PROTECTION GROUNDBED INSTALLATION RECORD SHEETS

HPPL-ALIVERI/FDP/CP/AREA 30/QR/010 CP, TRANSFORMER RECTIFIER INSTALLATION & FUNCTION RECORD

SHEET

HPPL-ALIVERI/FDP/CP/AREA 30/QR/011 CP, AS-BUILT TRANSFORMER RECTIFIER & ANODE BED INSTALLATION

SKETCH

HPPL-ALIVERI/FDP/CP/AREA 30/QR/012 CP, INSULATION JOINT TEST RESULTS

HPPL-ALIVERI/FDP/CP/AREA 30/QR/013 CP, PERMANENT GROUNDING INSTALLATION NOT APPLICABLE

HPPL-ALIVERI/FDP/CP/AREA 30/QR/014 PRECOMMISIONING RECORDS BY DESFA

CP AREA 32 FAB

HPPL-ALIVERI/FDP/CP/AREA 32/FAB/001 AS-BUILT DRAWING

16

Page 17: September 2013 - INOGATE

LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204

HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1

CP AREA 32 QR

HPPL-ALIVERI/FDP/CP/AREA 32/QR/001

CATHODIC PROTECTION PIN BRAZING & CABLE CONNECTION FOR MEASURING POST REPORTS

HPPL-ALIVERI/FDP/CP/AREA 32/QR/002

CP PROTECTION,INSTALLATION OF MEASURING POSTS & CABLE CONNECTIONS RECORD SHEET

NOT APPLICABLE

HPPL-ALIVERI/FDP/CP/AREA 32/QR/003

CATHODIC PROTECTION CHECK & CALIBRATION OF POLARIZATION PROBES REPORT (POST TYPE K9)

NOT APPLICABLE

HPPL-ALIVERI/FDP/CP/AREA 32/QR/004

CATHODIC PROTECTION SOIL RESISTIVITY MEASUREMENTS FROM STUDY

HPPL-ALIVERI/FDP/CP/AREA 32/QR/005

CATHODIC PROTECTION TEST REPORTS FOR RIVER CROSSING NOT APPLICABLE

HPPL-ALIVERI/FDP/CP/AREA 32/QR/006

CATHODIC PROTECTION TEST REPORTS FOR ROAD/RAILWAY CROSSINGS WITH CASING

HPPL-ALIVERI/FDP/CP/AREA 32/QR/007

TEMPORARY C.P. SACRIFICIAL ANODE INSTALLATION MEASUREMENTS SHEETS

HPPL-ALIVERI/FDP/CP/AREA 32/QR/008

CATHODIC PROTECTION NATURAL POTENTIAL RECORDS SHEETS

HPPL-ALIVERI/FDP/CP/AREA 32/QR/009

CATHODIC PROTECTION GROUNDBED INSTALLATION RECORD SHEETS

HPPL-ALIVERI/FDP/CP/AREA 32/QR/010

CP, TRANSFORMER RECTIFIER INSTALLATION & FUNCTION RECORD SHEET

HPPL-ALIVERI/FDP/CP/AREA 32/QR/011

CP, AS-BUILT TRANSFORMER RECTIFIER & ANODE BED INSTALLATION SKETCH

HPPL-ALIVERI/FDP/CP/AREA 32/QR/012

CP, INSULATION JOINT TEST RESULTS

HPPL-ALIVERI/FDP/CP/AREA 32/QR/013

CP, PERMANENT GROUNDING INSTALLATION NOT APPLICABLE

HPPL-ALIVERI/FDP/CP/AREA 32/QR/014

PRECOMMISIONING RECORDS BY DESFA

17