Segment 2: The Coast Guard’s Next
Generation C4ISR System
CDR James Betz | 20 May 2015 | ASNE ISS Symposium
![Page 2: Segment 2: The Coast Guard’s Next Generation C4ISR System CDR James Betz | 20 May 2015 | ASNE ISS Symposium](https://reader036.vdocuments.site/reader036/viewer/2022062309/56649ea05503460f94ba3341/html5/thumbnails/2.jpg)
2
Topics
• Coast Guard C4ISR Acquisitions
• National Security Cutter (NSC) class – C4ISR / CGC2
• C4ISR CGC2 Segment 1 – Segment 2 evolution
• Design and development of CGC2 Segment 2
• Installation of CGC2 Segment 2 aboard NSC class
• Operation of CGC2 Segment 2
• Future of CGC2 Segment 2
ASNE ISS Symposium| CDR James Betz | 20 May 2015
![Page 3: Segment 2: The Coast Guard’s Next Generation C4ISR System CDR James Betz | 20 May 2015 | ASNE ISS Symposium](https://reader036.vdocuments.site/reader036/viewer/2022062309/56649ea05503460f94ba3341/html5/thumbnails/3.jpg)
3ASNE ISS Symposium| CDR James Betz | 20 May 2015
U.S. Coast Guard C4ISR Acquisitions
• Headquartered in Washington, DC
– Segment 2 C4ISR system developed at detached office in Moorestown, NJ (near Lockheed Martin OEM)
• Mission
– We are professionals who oversee and execute the acquisition of C4ISR systems from design through sustainment planning in support of the Coast Guard’s Operational Forces
• Vision
– To be the benchmark for advanced C4ISR/C5ISR systems acquisition and integration for the Coast Guard, DHS, and maritime components
![Page 4: Segment 2: The Coast Guard’s Next Generation C4ISR System CDR James Betz | 20 May 2015 | ASNE ISS Symposium](https://reader036.vdocuments.site/reader036/viewer/2022062309/56649ea05503460f94ba3341/html5/thumbnails/4.jpg)
4
National Security Cutter class – C4ISR / CGC2
• 8-ship National Security Cutter class
– 5 cutters delivered since 2008 (Huntington Ingalls, MS shipyard)
• NSC class C4ISR systems
– Sourced from government (NTNO) and industry
– Coast Guard Command and Control (CGC2) acquired from Lockheed Martin, Moorestown, NJ
– First 4 ships of class initially delivered with Increment 1 CGC2
• Second ship (USCGC WAESCHE) served as technology demonstrator platform for next-generation Segment 2 CGC2
– Final 4 ships of class being delivered with Segment 2 CGC2
– Remaining 3 ships of class being retrofitted with Segment 2 CGC2
ASNE ISS Symposium| CDR James Betz | 20 May 2015
![Page 5: Segment 2: The Coast Guard’s Next Generation C4ISR System CDR James Betz | 20 May 2015 | ASNE ISS Symposium](https://reader036.vdocuments.site/reader036/viewer/2022062309/56649ea05503460f94ba3341/html5/thumbnails/5.jpg)
5
C4ISR CGC2 Increment 1 – Segment 2 evolution
• Meet evolving USCG mission requirements
– Need for real-time data
• Technology obsolescence
– Global Command and Control System (GCCS) drop Unix
– Windows OS - not real-time
• Combat System safety and Combat System certification drivers
• Sustainment: reduce lifetime support costs
• Coast Guard as Systems Integrator
ASNE ISS Symposium| CDR James Betz | 20 May 2015
![Page 6: Segment 2: The Coast Guard’s Next Generation C4ISR System CDR James Betz | 20 May 2015 | ASNE ISS Symposium](https://reader036.vdocuments.site/reader036/viewer/2022062309/56649ea05503460f94ba3341/html5/thumbnails/6.jpg)
6
Design and Development of CGC2 Segment 2
• Tactical and Situational Awareness Domains
– Real-time versus non-real time capability
• Use of U.S. Navy Common Source Library (software)
• Additional capabilities, e.g. certified tactical data link
ASNE ISS Symposium| CDR James Betz | 20 May 2015
![Page 7: Segment 2: The Coast Guard’s Next Generation C4ISR System CDR James Betz | 20 May 2015 | ASNE ISS Symposium](https://reader036.vdocuments.site/reader036/viewer/2022062309/56649ea05503460f94ba3341/html5/thumbnails/7.jpg)
7
Contractor: Little to no CG insight/influence
Goal: Successful Operational Readiness (OT&E)
COMOPTEVFOR
SAT: Gov’t revised/adaptedExecuted by Gov’t in Gov’t lab w/opt. contractor supt.
Asset-specific ST: Gov’t developedExecuted by Gov’t in Gov’t labw/Contractor supt. as req.)
FATFAT: Contractor Dev. – Gov’t Approval Executed by Contractor in Contractor lab w/ Gov’t Oversight
SAT
INPUT
Asset-specific
ST
USCG/DoDTest
Engineers
ORD
A004/S005 Platform P-Spec
INPUT
SOVTSOVT: Gov’t developedExecuted by asset crew w/Gov’t/Contractor supt as req.)
FAT = Factory Acceptance TestSAT = System Acceptance Test/IV&VST = System TestSOVT = System Operational Verification Test
CG-System Acquisition & Integration Laboratory (CGSAIL) Functions
SPAWAR, DCMA, NAVSEA, NAVAIR
ASNE ISS Symposium| CDR James Betz | 20 May 2015
SAT@CGSAIL (Gov Lab)
IV&V @CGSAIL
FAT@OEM
![Page 8: Segment 2: The Coast Guard’s Next Generation C4ISR System CDR James Betz | 20 May 2015 | ASNE ISS Symposium](https://reader036.vdocuments.site/reader036/viewer/2022062309/56649ea05503460f94ba3341/html5/thumbnails/8.jpg)
8
Installation of CGC2 Segment 2 aboard NSC class (USCGC WAESCHE)
• Retrofit installation, Coast Guard Island, Alameda CA
• 100 days: rip-out Increment 1; install, test/IV&V, and train Segment 2
ASNE ISS Symposium| CDR James Betz | 20 May 2015
![Page 9: Segment 2: The Coast Guard’s Next Generation C4ISR System CDR James Betz | 20 May 2015 | ASNE ISS Symposium](https://reader036.vdocuments.site/reader036/viewer/2022062309/56649ea05503460f94ba3341/html5/thumbnails/9.jpg)
9
Operation of CGC2 Segment 2 (USCGC WAESCHE)
• Arctic patrol, 2013
• Pacific patrols, 2014
• Rim of the Pacific (RIMPAC), 2015. Interoperability exercises with US Navy and Joint Forces
ASNE ISS Symposium| CDR James Betz | 20 May 2015
![Page 10: Segment 2: The Coast Guard’s Next Generation C4ISR System CDR James Betz | 20 May 2015 | ASNE ISS Symposium](https://reader036.vdocuments.site/reader036/viewer/2022062309/56649ea05503460f94ba3341/html5/thumbnails/10.jpg)
10
Future of CGC2 Segment 2
• Installation on board all 8 NSC class cutters
• Transition to sustainment, including plans for periodic Tech Refresh and Tech Insertion to minimize impacts due to obsolescence
• Relocation / expansion of CGC2 CGSAIL Lab to U.S. Navy facility in order to support Segment 2 sustainment including future USCG acquisition efforts