sediment cap design, modeling, and construction at a

39
Sediment Cap Design, Modeling, and Construction at a Former MGP Site Tom Boom, (Barr Engineering Co.); Andrew Santini (Consumers Energy) Great Lakes Environmental Remediation and Redevelopment Conference October 2019 Photo courtesy of Special Collections and University Archives, Kettering University

Upload: others

Post on 04-Oct-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Sediment Cap Design, Modeling, and Construction at a

Sediment Cap Design, Modeling, and Construction at a Former MGP Site

Tom Boom, (Barr Engineering Co.); Andrew Santini (Consumers Energy)Great Lakes Environmental Remediation and Redevelopment Conference October 2019

Photo courtesy of Special Collections and University Archives, Kettering University

Page 2: Sediment Cap Design, Modeling, and Construction at a

agenda

• site background • cap components• hydrodynamic modeling• groundwater modeling• design changes during construction

Page 3: Sediment Cap Design, Modeling, and Construction at a

site background

Page 4: Sediment Cap Design, Modeling, and Construction at a

former MGP in Flint, MI

Photo courtesy of Special Collections and University Archives, Kettering University

Gasholder AreaProduction Area

Page 5: Sediment Cap Design, Modeling, and Construction at a

project reach

~1,700 ft.

~300 ft.

Hamilton Dam

wetland

Pedestrian Bridge

University

University

E 5th Avenue

North

Page 6: Sediment Cap Design, Modeling, and Construction at a

consideration #1 - presence of NAPL

non-aqueous phase liquid (NAPL)

---- average water elevation, 2014

Upstream(5th Avenue)

Downstream(Hamilton Dam)Pedestrian

Bridge

Page 7: Sediment Cap Design, Modeling, and Construction at a

consideration #2 - changing groundwater flow

pre-dam lowering post- dam lowering

Local GW flow direction

losing reach

gaining reach

Page 8: Sediment Cap Design, Modeling, and Construction at a

consideration #3 – evolving Hamilton Dam plans

high hazard dam – poor condition, pending removal at time of design

Page 9: Sediment Cap Design, Modeling, and Construction at a

typical design process

RI FS Design Construction

iterative adaptive management

CSM

Page 10: Sediment Cap Design, Modeling, and Construction at a

sediment cap objectives

1. create a barrier between remaining impacted sediments below the cap and the river

2. provide stable riverbanks and riverbed for future dam scenarios3. develop channel /cap geometry compatible with river hydrodynamics4. incorporate bedform diversity elements for improved aquatic habitat

Page 11: Sediment Cap Design, Modeling, and Construction at a

capping considerations – site layout & features

~30 ft.

Soft sediments

Cut banks, steep slopes (factor of safety~1), some

softer clay layers.Storm sewer channel with

slope challenges, no headwall as-builts. Multiple storm outlets along reach.

52-inch sanitary sewer near river.

High hazard dam – poor condition, scheduled for removal

Old bridge pilings and piers

road on either side of river

Page 12: Sediment Cap Design, Modeling, and Construction at a

simplified iterative dredge and impermeable cap design

groundwater flow and chemical fate

and transport

surface water hydrodynamics

slope stability and consolidationcap components

habitat restoration

cap objectives

Page 13: Sediment Cap Design, Modeling, and Construction at a

cap components

Page 14: Sediment Cap Design, Modeling, and Construction at a

liner evaluation

liner options: • bentonite (clay)• bentonite (clay) and aggregate• geocomposite clay mat• geosynthetic fabrics and geomembranes

Aggregate AquaBlok

Textured HDPEBlended Barrier

Page 15: Sediment Cap Design, Modeling, and Construction at a

assessing technical limitations

Blended Barrier Assessment and Result Test Construction Consideration

Ability to form adequate barrier in river conditions

Bentonite swell tests confirmed behavior

Maintaining integrity of AquaBlok material essential to success

Material strength and stability limitations

Triaxial compression tests provided inputs for stability modeling and slope angle selection.

Material will stay on slope if reasonably densified

Maintainingintegrity and resilience to deterioration

Column capping tests aided in cover timing determination: density and strength w/ unconfined vs. confined hydration.

Timing important, but not critical; minimal segregation with controlled placement. Risk of erodibility if not covered expeditiously

Page 16: Sediment Cap Design, Modeling, and Construction at a

armoring

Design Requirement

Construction Consideration

Protect blended barrier and hdpecap from erosion and scouring

Achievable with 10” D50 rip rap below el. 705 ftand vegetation above el. 705 ft

Protect blended barrier from rip rap

Can’t place rip rap on blended barrier; evaluate passive filter layers

Page 17: Sediment Cap Design, Modeling, and Construction at a

filtering & clay hydration

Design Requirement

Construction Consideration

Adequate filtering – from clay sized fraction in blended barrier to large rip rap surface to avoid fines migration

Achievable with multi-layers

Protection of clay from NAPL during hydration

Provision of sand under layer

Gradation Gap

Page 18: Sediment Cap Design, Modeling, and Construction at a

cap components

above water section below water section

Page 19: Sediment Cap Design, Modeling, and Construction at a

stability modeling

genericized failure plane

sewer

genericized sliding failure

global stability cap stability

• in place density minimum 95 pounds per cubic foot to provide adequate strength to resist shear failure

• minimum slope angle below water 3H:1V• geomembrane friction angle minimum 27o to provide adequate

factor of safety against sliding

Page 20: Sediment Cap Design, Modeling, and Construction at a

hydrodynamic modeling

Page 21: Sediment Cap Design, Modeling, and Construction at a

existing and proposed slope

Upstream(5th Avenue)

Downstream(Hamilton Dam)

Page 22: Sediment Cap Design, Modeling, and Construction at a

incorporating bedform diversity elements

• slope on river bed• bankfull bench• rip rap surface infilling with gravel• native bank vegetation

Page 23: Sediment Cap Design, Modeling, and Construction at a

final bathymetry

Page 24: Sediment Cap Design, Modeling, and Construction at a

groundwater modeling

Page 25: Sediment Cap Design, Modeling, and Construction at a

why use a groundwater model?

• groundwater flow dependent on river conditions

• partially penetrating river• dam with uncertain future operation• many stakeholders

− state agency− city− property owners− public

Page 26: Sediment Cap Design, Modeling, and Construction at a

groundwater cap modeling - flow

Local Modeled Groundwater Flow Direction

Layer 2 Modeled Groundwater Elevation Contour (Contour Interval 1 ft)

Page 27: Sediment Cap Design, Modeling, and Construction at a

groundwater cap modeling – fate and transport

Maximum Minimum

Page 28: Sediment Cap Design, Modeling, and Construction at a

uplift protection

• model used to predict volume of water• relief drain installation• installation of vibrating wire piezometers

below cap to monitor pressures

sewer relief drain genericized uplift pressure

Page 29: Sediment Cap Design, Modeling, and Construction at a

final design

Page 30: Sediment Cap Design, Modeling, and Construction at a

final design

Gravel

SandBlended barrier (AquaBlok)

Rip-rapTopsoil/vegetation

GeomembraneGeotextile separator fabric

Page 31: Sediment Cap Design, Modeling, and Construction at a

design changes during construction

ConsumersEnergy(Owner)

Sevenson(Prime

Contractor)

Barr(Engineer)

Page 32: Sediment Cap Design, Modeling, and Construction at a

pedestrian bridge removal and replacement

Page 33: Sediment Cap Design, Modeling, and Construction at a

storm outfall design

show picture of outfall design, picture of pile of rocks

sitting on area below proposed outfall to surcharge it, use typical construction materials for storm

Page 34: Sediment Cap Design, Modeling, and Construction at a

modification to transition areas

plan view – upstream tie-in

profile – upstream tie-in modifications

Page 35: Sediment Cap Design, Modeling, and Construction at a

Newberry riffles

Two riffles comprised of 6-inch minus material, 12-inch height at toe, tapering to 0-inch toward channel center; 4:1 upstream slope, 40:1 downstream slope. Total length approx. 44 feet.

Page 36: Sediment Cap Design, Modeling, and Construction at a

construction camera

Page 37: Sediment Cap Design, Modeling, and Construction at a

before

after

[email protected]

Page 38: Sediment Cap Design, Modeling, and Construction at a

overall project objectives

1. address direct contact exposure pathway for MGP-related impacts

2. meet compliance criteria for groundwater venting to the river

3. restore riverbanks and infrastructure compatible with future dam scenarios

Page 39: Sediment Cap Design, Modeling, and Construction at a

existing bathymetry

scour

deposition (wetland)