section 18 - web viewccg2 project scope_section 18_mot_ir draft.docx. page 18-18. ... may be closed...

29
document.docx 18 MAINTENANCE OF TRAFFIC The Developer shall be responsible for designing, providing, and maintaining safe and effective traffic control 24 hours a day for the duration of the Project. All traffic control devices shall be furnished, erected, maintained, and removed by the Developer. Maintenance of traffic (MOT) shall be implemented in a manner that minimizes both construction duration and impact to the traveling public. This section defines specific requirements, restrictions, and allowable closure durations for travel lanes. If in the opinion of the Department, the Developer fails to comply with the requirements of the Traffic Management Plan (TMP) and the Contract, the Department shall suspend Work until all requirements are met. Any costs or delays incurred as a result of the failure shall be the full responsibility of the Developer. This section includes the requirements for allowable outages and number of lanes to maintain; many of these requirements affect the construction of the tie-ins and the mainline bridge rehabilitations. At the commencement of the Project, I-90 traffic will be operating in the Bi-Directional Condition. This configuration provides two eastbound lanes and four westbound lanes on the viaduct bridge constructed in CCG1. Alternate route plans described later in this Section 18 will be in place at commencement of the Project. The Westbound Alternate Route Plan (WARP) shall remain in place until the Bi-Directional Condition is removed from I-90 westbound. The Eastbound Alternate Route Plan (EARP) shall remain in place until Substantial Completion. The construction of the interchanges in the Tremont and Gateway Districts and the tie-in to the original I-90 alignments at each end of the Project will require a clear and well communicated MOT scheme that addresses the phase construction of the ramps to and from these districts and the tie-ins. Due to the ramp closures, impacts to the local street grid beyond the Project Limits are anticipated. The Page 18-1

Upload: vominh

Post on 02-Feb-2018

219 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

18 MAINTENANCE OF TRAFFIC The Developer shall be responsible for designing, providing, and maintaining safe and effective traffic control 24 hours a day for the duration of the Project. All traffic control devices shall be furnished, erected, maintained, and removed by the Developer. Maintenance of traffic (MOT) shall be implemented in a manner that minimizes both construction duration and impact to the traveling public. This section defines specific requirements, restrictions, and allowable closure durations for travel lanes. If in the opinion of the Department, the Developer fails to comply with the requirements of the Traffic Management Plan (TMP) and the Contract, the Department shall suspend Work until all requirements are met. Any costs or delays incurred as a result of the failure shall be the full responsibility of the Developer.

This section includes the requirements for allowable outages and number of lanes to maintain; many of these requirements affect the construction of the tie-ins and the mainline bridge rehabilitations.

At the commencement of the Project, I-90 traffic will be operating in the Bi-Directional Condition. This configuration provides two eastbound lanes and four westbound lanes on the viaduct bridge constructed in CCG1. Alternate route plans described later in this Section 18 will be in place at commencement of the Project. The Westbound Alternate Route Plan (WARP) shall remain in place until the Bi-Directional Condition is removed from I-90 westbound. The Eastbound Alternate Route Plan (EARP) shall remain in place until Substantial Completion.

The construction of the interchanges in the Tremont and Gateway Districts and the tie-in to the original I-90 alignments at each end of the Project will require a clear and well communicated MOT scheme that addresses the phase construction of the ramps to and from these districts and the tie-ins. Due to the ramp closures, impacts to the local street grid beyond the Project Limits are anticipated. The Developer shall perform additional traffic counts and analysis at intersections to be determined. These locations will be dependent upon the TMP proposed by the Developer. The Department will provide the original Synchro model for downtown traffic and the CCG1 Synchro model updated for the Bi-Directional Condition prior to implementation. The Developer shall provide updates to the Synchro modeling data so the City of Cleveland Traffic Engineering can adjust existing signal timings on the local street grid for the anticipated changes in traffic patterns during construction.

Work being performed under the CCG1 contract will be substantially complete at the commencement of this Project. However, the CCG1 contractor may have work remaining to complete. The DBT shall coordinate and cooperate with the CCG1 contractor and contractors for other projects that may be active in the Project area. The Developer shall notify the Department when potential conflicts arise that impact Work schedule or MOT.

Page 18-1

Page 2: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

18.1 NOTIFICATION and COORDINATION REQUIREMENTSThe Developer shall provide to the agencies listed below 14 Days advance notice of pending changes in MOT or traffic patterns, including changes to any of the following: MOT configuration, access, schedule, duration, or other modifications that affect messaging and operations of Cleveland’s Freeway Management System (FMS). The notice shall include existing and proposed MOT configuration and all applicable changes affecting access, schedule, duration, and FMS.

Updates to the FMS may be required due to incidents or other unplanned events. The Developer shall comply with Section 4 (Public Communications and Involvement) and the Public Information Plan (PIP) for notifications and communication procedures.

ODOT Statewide Traffic Management Center1980 W. Broad St.Columbus, Ohio 43223 Phone (614) 466-4224Fax (614) [email protected]

Capt. John McKennaFire PreventionCity of Cleveland Division of Fire1645 Superior Ave. Cleveland, Ohio 44114(216) [email protected]

James MuhicTraffic CommissionerCity of Cleveland Division of Police2001 Payne Ave.Cleveland, Ohio 44114(216) [email protected]

Rob MavecCommissioner of TrafficCity of Cleveland Division of TrafficCity of Cleveland601 Lakeside AveCleveland, Ohio 44114

Page 18-2

Page 3: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

(216) [email protected]

Nick Jackson Deputy Chief of Business OperationsCleveland Metropolitan School DistrictCMSD1380 E.6th StreetCleveland, Ohio 44114(216) [email protected]

Mike SchipperDeputy General Manager, Engineering & Project ManagementGreater Cleveland Regional Transit AuthorityGCRTA1240 W.6th StreetCleveland, OH 44113(216) [email protected]

18.2 TRAFFIC MANAGEMENT PLAN (TMP)The Developer shall develop a Traffic Management Plan (TMP) that serves as a manual for the Department and affected stakeholders of all components of the Developer’s plan for maintaining traffic during construction. The TMP shall cover all phases of construction, from Project start to completion, defining and detailing specific MOT plans for each construction phase. The TMP shall include, at a minimum:

A. Cover page/title sheet signed and sealed by an Ohio-registered professional engineer. B. Name, all contact information, and applicable certifications for the Workzone Traffic Supervisor. C. PIP sections relevant to the TMP. D. Incident Management Plan. E. Contact information included in Section 18.1 and additional contacts as deemed necessary by

the Developer and Department. F. Schedule showing MOT phases and durations, including closure durations. The schedule shall

take into consideration snow and ice operations from December 1 through March 31. Lane shifts, restrictions, and closures may not be Approved if they adversely affect snow removal operations.

G. Discussion of sequence of operations and MOT procedures, identifying all-long term lane closures and all complete directional roadway closures (short term or long term).

Page 18-3

Page 4: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

H. Traffic data and analysis. I. Plans at an appropriate scale showing: the Work area; begin/end tapers; temporary pavement

and/or structures; locations of signs (existing overhead signs and all proposed, covered, or modified signs); locations of typical sections; detour routes; alternate routes; portable changeable message sign (PCMS) locations; and references to applicable SCDs.

J. Typical sections showing: lane widths; pavement markings; drums; portable concrete barrier (PCB); limiting stations; work area; and drop-offs.

K. Sign details for proposed signs and overlays/modifications.L. Information and guidance for signing and detour routes, including color-coded definitions of

detour routes. M. Identification and use of Law Enforcement Officers (LEO).

Any changes to the TMP must be approved by the IQF and submitted to the Department a minimum of seven Days prior to desired implementation of the proposed change(s).

18.3 MAINTENANCE OF TRAFFIC REQUIREMENTSThe Developer shall maintain all existing lanes of traffic, including the Bi-Directional Condition, at all times on existing, temporary, or new pavements and/or structures until the I-90 eastbound traffic is shifted to the new eastbound I-90 Viaduct Structure, except as noted herein. Allowable durations for lane closures, ramp closures, and road closures are defined below in Tables 18-1, 18-2, and 18-3.

The Developer shall show all MOT signing required for each MOT phase in each MOT plan set. This includes existing signs to remain in place, signing from the previous phase, and new signing required to support MOT movements.

Pedestrian traffic shall be maintained at all times per the OMUTCD, TEM Section 640-25, C&MS 614.02, and ADA requirements.

Widened structures for maintaining traffic shall meet the requirements of Section 14 (Structures). The Developer shall maintain or provide lighting for all travelled lanes and pedestrian routes, except for pedestrian routes along Orange Avenue, Broadway Avenue, East 9th Street, and East 14th Street, by use of existing, temporary, or new lighting facilities.

18.3.1 Disincentives for ClosuresDisincentives shall be applied at a rate of $500 per minute. Disincentives shall be applied to the Developer for the following closures:

A. Closures that exceed closure duration limits set forth in the allowable closures tables in this Section 18.

B. Closures not identified in allowable closures tables in this Section 18.

Page 18-4

Page 5: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

18.3.2 Closure RequirementsLane closures or restrictions over segments of the Project in which no Work is anticipated within a reasonable time frame, as determined by the Department, shall not be permitted. The level of utilization of MOT devices shall be commensurate with the Work in progress.

A long-term stationary closure is defined as a lane closure greater than 24 hours in duration.

Special Events shall be considered events at venues with a seating capacity greater than 25,000 or events at any downtown venue with a projected attendance of 20,000 or greater. The Developer shall not have any lane closure, except for long-term stationary closures, in the inbound direction from two hours before an event starts to one-half hour after it starts. For Cleveland Browns games, the Developer shall not have any lane closures, except for long-term stationary closures in the inbound direction, from four hours before the event to one-half hour after it starts. The Developer shall not have any lane closure except for long-term stationary closures in the outbound direction from two hours after an event ends.

The Permitted Lane Closure Table (PLCT) and notes are found at: http://www.dot.state.oh.us/districts/D12/HighwayManagement/Pages/PermittedLaneClosures.aspx

The PLCT and notes, effective date October 10, 2012, shall apply to lane closures on roadways not otherwise included in Tables 18-1, 18-2, or 18-3 or in other requirements of this Section 18.

The Developer shall not close any lanes (except allowable long-term stationary closures) during periods when snow accumulation is probable. During these periods, daily isolated lane closures may be used during non-peak hours, weather permitting. The Developer shall be responsible for clearing snow and salting the roadway prior to reopening an isolated lane closure during a snow event.

A Holiday Weekend, for traffic maintenance purposes, begins at noon on the last normal weekday preceding the weekend. The Holiday Weekend is considered to end at 12:00 a.m. on the first normal weekday following the Holiday. A day between the Holiday and Saturday or Sunday is considered part of the Holiday Weekend.

The Developer shall not close lanes (except for long-term stationary closures) during Holidays and Holiday Weekends. Holidays include New Year’s Day, Memorial Day, Fourth of July, Labor Day, Thanksgiving, Christmas, and Easter.

Page 18-5

Page 6: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

Table 18-1: Allowable Interstate Closures

Interstates Allowable Closure(s) Additional Requirements

I-90 (between I-71 and I-77)

Complete closures with traffic detoured are permitted as defined below. Without the ARP in place:

A. Weekday overnight closure: 9:00 p.m. through 5:00 a.m. (Sunday-Thursday)

B. Weekend closure: No full weekend closures

With the ARP in place:A. Weekday overnight closure: 8:00

p.m. through 6:00 a.m. (Sunday-Thursday)

B. Weekend closure: 8:00 p.m. Friday through 6:00 a.m. Monday

I-71 northbound Reduced to one lane north of the I-71/Jennings Freeway (SR-176) Interchange for the Bi-Directional Condition. Limits of the single lane segment may be adjusted to accommodate the Work on I-71.

Complete closure with traffic detoured is permitted in conjunction with I-90 eastbound complete closure at the I-490 interchange.

EARP active. Crossover to I-71 southbound permitted. I-71 shall be returned to normal Bi-Directional Condition during winter season (Nov. 1 to March 31).

I-71 southbound May be reduced to two lanes twice for up to 200 days in total for the two closures.

Complete closure with traffic detoured is permitted in conjunction with I-90 westbound complete closure.

Westbound Alternate Route active. Crossover to I-71 northbound permitted. I-71 shall be returned to normal Bi-Directional Condition during winter season (Nov. 1 to March 31).

I-77 northbound over I-490

May be reduced to one lane between 9:00 p.m. and 5:00 a.m.

I-77 southbound over I-490

May be reduced to one lane between 9:00 p.m. and 5:00 a.m.

Page 18-6

Page 7: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

Table 18-2: Allowable Ramp Closures

Ramps Allowable Closure(s) Additional Requirements

Ramp I-90 eastbound to I-90 eastbound (Ramp B-1)

Reduced to one lane during CCG1 with implementation of EARP.

Complete closures with traffic detoured are permitted as defined below. Without the EARP in place:

A. Weekday overnight closure: 9:00 p.m. through 5:00 a.m. (Sunday-Thursday)

B. Weekend closure: No full weekend closures

With EARP in place:

A. Weekday overnight closure: 8:00 p.m. through 6:00 a.m. (Sunday-Thursday)

B. Weekend closure: 8:00 p.m. Friday through 6:00 a.m. Monday

Shall be closed when I-90 eastbound is closed

Fairfield Avenue/W. 14th Street to I-90 eastbound (Ramp B-2

Closed during CCG1 and remains closed until new Ramp B-2 constructed and new I-90 eastbound structure open to traffic.

Ontario Street ramp to I-77 southbound

May be closed with traffic detoured twice for up to 14 days in total for the two closures for the removal of the existing Innerbelt superstructure.

I-90 eastbound ramp to Ontario Street (Ramp B-3) and to E. 9th Street southbound (Ramp B-4)

Closed until new Ramp B-3 and Ramp B-4 are constructed and the new I-90 eastbound structure is open to traffic.

Page 18-7

Page 8: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

Ramps Allowable Closure(s) Additional Requirements

I-90 eastbound ramp to E. 9th Street northbound (Ramp B-5)

May be closed and traffic detoured for up to 60 days in total.

I-90 eastbound ramp to E. 9th Street northbound may not be closed concurrently with any closure of the I-90 eastbound ramp to Ontario (Ramp B-3) Street northbound, except for one weekend for constructing tie-in.

I-77 northbound ramp to I-90 eastbound (ramp E-9)

Two lanes shall be maintained at all times while EARP is active.

I-90 westbound ramp to I-77 southbound (ramp E-10)

Two lanes shall be maintained at all times while the WARP is activated, except overnight closures are permitted between 10 p.m. and 6 a.m. for a maximum of 14 days for overhead structure work.

E. 21st Street ramp to I-77 southbound

Closed during CCG1 and remains closed while WARP is active.

After removal of WARP, provide a 32-inch bridge-mounted PCB along the outside edge of westbound I-90 at the exit to I-77 southbound. The PCB shall restrict traffic on the E. 21st Street entrance ramp to I-77 southbound from accessing I-90 westbound. Provide pavement markings and signing per the OMUTCD and a new approach terminus for this PCB to meet current design standards.

Page 18-8

Page 9: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

Ramps Allowable Closure(s) Additional Requirements

Orange Ave. to I-77 southbound

One lane shall be maintained while the ramp is altered for two-lane operation. Two lanes shall be open to traffic by May 15, 2014 and maintained at all times during construction thereafter.

Ramp to be in two-lane operation prior to either the Ontario St. or the E. 9th St. to I-77 southbound ramps being closed. The CUY-77-1435 bridge over I-490 shall be modified to accommodate three lanes southbound.

The E. 14th Street/Carnegie Avenue ramp to I-90 westbound (E-5)

Closed during CCG1 prior to the commencement of this Project. Ramp to remain closed throughout the Project.

The E. 14th Street/Carnegie ramp to I-77 southbound (E-16)

Closed during CCG1 prior to commencement of this Project and will remain closed at the completion of this Project.

Interim E. 14th Street/Carnegie ramp to I-77 southbound

Ramp shall be reconstructed to connect to I-77 southbound by May 15, 2014 and remain open in that configuration throughout the duration of the Project.

Two lanes shall be maintained at all times while the WARP is activated, except overnight closures are permitted between 10 p.m. and 6 a.m. for a maximum of 14 days for overhead structure work.

Ramp to remain open after completion of this Project.

I-90 eastbound ramp to E. 22nd Avenue.

Closed to I-90 eastbound traffic during CCG1 prior to the commencement of this Project and remains closed while EARP is active.

Ramp movement from I-77 northbound to E. 22nd Avenue to remain open at all times.

I-90 eastbound ramp to Carnegie Avenue.

Closed to I-90 eastbound traffic during CCG1 prior to the commencement of this Project and remains closed while EARP is active.

Ramp movement from I-77 northbound to Carnegie Avenue to remain open at all times.

I-77 northbound ramp from Woodland Avenue.

Closed during CCG1 prior to the commencement of this Project and remains closed while EARP is active.

Page 18-9

Page 10: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

Ramps Allowable Closure(s) Additional Requirements

I-490 westbound ramp to I-77 northbound

Closed during CCG1 prior to the commencement of this Project and remains closed while EARP is active.

Jennings Freeway (SR 176) ramp to I-71 northbound

Closed during CCG1 prior to the commencement of this Project and remains closed while EARP is active.

Page 18-10

Page 11: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

Table 18-3: Allowable Local Street Closures

Local Street Allowable Closure(s) Additional Requirements

All Local Streets Overnight and weekend complete closures of local streets with traffic detoured are permitted with overnight and weekend closures defined as:

A. Weekday overnight closure: 8:00 p.m. through 6:00 a.m. (Sunday-Thursday)

B. Weekend closure: 8:00 p.m. Friday through 6:00 a.m. Monday

All Local Streets Lane closures (except for long-term stationary closures) with traffic maintained are permitted on all local streets except as noted below:

Lane closures (except for long-term stationary closures) are prohibited on Ontario Avenue, E.9th Street, Carnegie Avenue, Orange Avenue, and W. 3rd Street between 7 a.m. and 9 a.m., and 3:30 p.m. and 6 p.m. weekdays.

Fairfield Avenue May be closed and traffic detoured for up to 28 days in total.

Fairfield Avenue shall not be closed concurrently with any closure on Starkweather Avenue, Kenilworth Avenue, or Abbey Avenue.

Kenilworth Avenue May be closed and traffic detoured for up to 14 days in total.

Kenilworth Avenue shall not be closed concurrently with any closure on Starkweather Avenue or Fairfield Avenue.

Page 18-11

Page 12: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

Local Street Allowable Closure(s) Additional Requirements

Starkweather Avenue May be closed and traffic detoured for up to 14 days in total.

Starkweather Avenue shall not be closed concurrently with any closure on Fairfield Avenue or Kenilworth Avenue.

Abbey Avenue May be closed and traffic detoured twice for up to 14 days per occurrence under the new Central Viaduct only.

Abbey Avenue shall not be closed concurrently with any closure on Fairfield Avenue, W. 14th Street or Kenilworth Avenue.

W. 14th Street southbound between Abbey and Fairfield

May be closed and traffic detoured to W. 11th Street for up to 45 days in total.

W. 14th Street northbound May be closed and traffic detoured for up to 30 days in total.

Closure shall not be concurrent with W. 14th Street southbound closure.

Harrison Street May be closed for 15-minute periods for the removal of the existing super structure and the erection of superstructure elements. It shall remain open a minimum of 15 minutes between closures or until traffic has returned to normal.

W. 13th Street and University Road

Shall remain open at all times to through traffic during construction.

No Work or MOT can occur on University Road or West 13th Street until the Tremont Neighborhood parking lot beneath the I-90 Viaduct Structure and adjacent to Abbey Avenue is completed and operational.

Abbey Avenue, W. 13th Street, University Road Parking Areas

All parking in these areas shall be maintained during construction.

Provide a temporary 30-space gravel parking area in the northwest corner infield of the W. 14th Street northbound/Abbey Avenue intersection if any parking in this area is disrupted.

Page 18-12

Page 13: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

Local Street Allowable Closure(s) Additional Requirements

W. 3rd Street May be closed for 15-minute periods for the removal of the existing superstructure and the erection of superstructure elements. It shall remain open a minimum of 15 minutes between closures or until traffic has returned to normal.

Ontario Street May be reduced to two lanes of northbound or southbound traffic for up to 14 days in total for the superstructure demolition.

Ontario Street ramp to I-77 southbound shall be closed during these lane reductions.

Ontario Street / Orange Avenue between Carnegie Avenue and E. 14th Street

May be reduced to two lanes of northbound or southbound traffic for up to 120 days in total.

Long-term lane reductions shall not coincide with long-term lane reduction on E. 9th Street.

E. 14th Street May be closed and traffic detoured between 8 p.m. and 6 a.m. for a maximum of 14 days in total for the overhead bridge demolition.

E. 9th Street Southbound May be reduced to one lane for up to 140 days in total after which it will be reconfigured and permanently striped for one lane, except at ramps and turn lanes.

Long-term lane reductions shall not coincide with long term lane reduction on Ontario Street.

E. 9th Street Northbound May be reduced to two lanes for up to 90 days in total and to one lane for up to 50 days in total.

Long-term lane reductions shall not coincide with long-term lane reduction on Ontario Street.

Commercial Road/new May be closed and traffic detoured for up to 14 days in total.

Emergency vehicle access through the Site must be provided at all times. Commercial Road shall not be closed concurrently with any closure on Canal Road or any lane restriction on Ontario Street.

Page 18-13

Page 14: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

Local Street Allowable Closure(s) Additional Requirements

Access between Fire Station on Central Viaduct Way Road and Canal Road for emergency egress

Shall be maintained at all times, with a minimum lane width of 12 feet and curves widened to accommodate outbound emergency response vehicles.

Canal Road A signalized two-way operation on one lane shall be used for the construction of the Canal Road relocation tie-ins.

May be closed for 15-minute periods for the removal of the existing superstructure and the erection of superstructure elements. It shall remain open a minimum of 15 minutes between closures or until traffic has returned to normal.

Emergency vehicle access through the site must be provided during any and all closures of Canal Road. The Project shall be able to accommodate emergency vehicle passage on Canal Road.

18.3.3 Alternate Route Plan RequirementsAll long-term stationary lane closures on I-90 will require concurrent implementation of an alternate route plan (ARP) along I-490 and I-77. Westbound implementation of the ARP will be referred to as the Westbound Alternative Route Plan (WARP). Eastbound implementation of the ARP will be referred to as the Eastbound Alternative Route Plan (EARP). Both the WARP and the EARP will be in place prior to commencement of the Project.

The limits of the in-place EARP and WARP encompass the roadways described below. The limits also include all connecting ramps affected by widening to establish the EARP and WARP.

A. I-71 from its junction with SR 176 to I-90B. I-490 from I-90 to I-77C. I-77 from I-490 to I-90D. I-90 from West 82nd Street to Chester Avenue

The WARP must remain in place until all lanes of the final westbound I-90 roadway are open, with no further long-term lane closures to be implemented. The EARP must remain in place until all lanes of the final eastbound I-90 roadway are open, with no further long-term lane closures to be implemented.

The Developer shall remove the WARP no later than 30 Days after Substantial Completion.

Page 18-14

Page 15: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

The Developer shall remove the EARP no later than 30 Days after Substantial Completion.

The Developer is responsible for the Plan development of additional alternate route plans.

18.3.4 Permanent Road ClosuresPermanent road closures shall be advance-signed at a minimum of 14 days prior to closure. Permanent closures include:

A. Ontario Street ramp to I-77 southbound shall be closed with traffic permanently rerouted via Orange Avenue and East 14th Street.

B. East 9th Street ramp to I-77 southbound shall be closed with traffic permanently rerouted via Orange Avenue and East 14th Street.

Access improvements shall be completed prior to either closing as noted below:

Opening E. 14th Street ramp to I-77 southbound Orange Avenue improvements:

o Orange Avenue widening improvements (from East 22nd Street to East 30 th Street)o E. 30th Street Ramp to I-77 southboundo Intersection improvement at Orange Avenue and East 30th Street

Permanent road closures do not require implementation of a detour. Guide signs and local signs shall be modified to reflect the closures.

18.3.5 MOT Phases and Local Street Traffic Counts and Operational AnalysesThe Developer shall complete appropriate traffic analyses of the Project area roadways, together with the adjacent, affected roadways and intersections, for each MOT phase to be implemented during the Project. To support this, the Developer shall undertake a traffic count program for the development of the MOT phase analysis, as well as the Interim Condition, in coordination with the Department. AM and PM peak hour counts shall be conducted at up to 15 intersections for each of the phases; based on 16 phases resulting in a maximum of 240 intersection counts for the AM and PM peaks. Traffic counts shall be three-hour minimum for rush hours from 6:30 a.m. to 9:30 a.m. and 3:00 p.m. to 6:00 p.m. Similarly, the Developer shall conduct up to 30 24-hour bi-directional automated traffic recorder (ATR) counts for each of the phases; this will result in a maximum of 480 ATR counts. The signal timing, capacity, and progression analyses shall be done by the Developer, using Synchro traffic simulation software. The Synchro model may be developed from a Snychro model provided to the Developer by the Department. The Department will provide the design Bi-Directional Condition Synchro model and the CCG1 Bi-Directional Condition model prepared prior to the implementation of the Bi-Directional Condition. (See Section 17.2.19 for more information.) The Developer shall obtain Acceptance of each updated Synchro model a minimum of seven days prior to implementing the new traffic pattern.

Page 18-15

Page 16: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

The Developer shall furnish signal timing plans for each analysis phase (AM, PM, and Average timing plans) within each MOT phase. The Developer shall work with City of Cleveland (Traffic) staff for implementation of the timing plans into the intersections within the network. City staff will implement all signal timing adjustments into the controllers; the Developer will not have access to the controllers.

18.3.6 Detour Routes, Alternate Routes, and I-90 Bi-Directional ConditionThe Developer shall provide a detour whenever all lanes in a direction are closed. Detours that have been agreed upon with the City (pre-arranged) are provided in Appendix MT-07 (Preliminary Detour Routes). In addition to these pre-arranged detours or any additional detour Approved by the Department, any roadway utilized by the Developer for diverting traffic for more than 14 days shall be considered a detour route.

Scranton Avenue shall not be used as a truck detour.

During the time that traffic is detoured or uses a designated alternate route, the Developer shall maintain the detour routes, alternate routes (WARP, EARP, and others Approved by the Department), and the I-90 Bi-Directional Condition area in a condition that is reasonably smooth and free from holes, ruts, ridges, bumps, dust, and standing water including bridge deck surfaces. The Developer shall be responsible for restriping these routes annually and maintaining the WARP and EARP signing during the construction of the Project. The Developer shall restripe the I-90 Westbound Viaduct Structure twice annually (spring and fall) using Item 642 Traffic Paint Type 1. The Developer shall maintain, remove, replace and/or reset portable concrete barrier, including the Bi-Directional Condition median portable concrete barrier. Any barrier that is inadvertently moved, either by an errant vehicle or other reason, shall be reset or replaced, if damaged, within four hours.

The Department will be responsible for maintaining existing guardrail, light poles, permanent signs and drainage structures, and storm sewers along detour routes and alternate routes. The Developer is responsible for maintaining all other items, including structural elements of bridges, glare screening, and longitudinal channelizers. Once a detour or alternate route is removed and traffic returned to its normal pattern, the detour route or alternate route shall be restored to a condition that is equivalent to that which existed prior to its temporary use for this Project. All such Work shall be performed when and as determined by the Department.

The Developer shall resurface per Section 11 (Pavements) and install new pavement markings per Section 17 (Traffic Control) after Substantial Completion all detour routes, alternate routes for detours, and alternate route implementations that exceed 14 consecutive days. Resurfacing limits for detours or alternate routes excludes Project full-depth pavement replacement and resurfacing limits.

18.3.7 Haul RoadsThe Developer shall comply with any and all load restrictions.

Scranton Avenue, West 14th Street and Central Viaduct Way shall not be used as haul roads.

Page 18-16

Page 17: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

18.4 GENERAL MOT CRITERIA In addition to the applicable governing regulations, the TMP and MOT shall comply with the following:

A. Design speed 1. Urban Interstate = 50 mph (posted 50 mph)2. Urban Arterial = 25 mph, 30 mph, or 35 mph, as posted3. Urban Collector = 25 mph, 30 mph or 35 mph, as posted4. Urban Local = 25 mph

B. 11-foot lane width minimum for Department FacilitiesC. 10-foot lane width minimum for City of Cleveland FacilitiesD. 1-foot minimum clearance from traveled lane edge to toe of barrier.

Where existing, new, or temporary shoulder pavement is used for maintaining traffic, the cross-slope shall be transitioned using the MOT design speed applicable superelevation transition relative gradient in L&D Volume 1. These criteria shall govern the transition of the roadway shoulder to the approach slab/bridge deck.

18.5 TEMPORARY TRAFFIC CONTROL ZONE DEVICESThe Developer shall provide, erect, and maintain drums, signs, barriers, and all other traffic devices used for MOT. The Developer shall maintain all devices in satisfactory condition in accordance with the Department’s Quality Guidelines for Temporary Traffic Control Devices & Features.

The Developer shall provide, install, and maintain six PCMSs for use during the entire duration of construction. Two PCMSs shall be small, and four PCMSs shall be large. The large signs shall be Class A on the Department’s approved list at:

http://www.dot.state.oh.us/Divisions/ConstructionMgt/Materials/Pages/PORTABLE-CHANGEABLE.aspx.

Dimensions of the small signs shall be a minimum of 90 inches by 42 inches and a maximum of 102 inches by 60 inches. They shall be full matrix and trailer mounted. The small signs must have all the same communication links as the Class ‘A’ PCMS; however, the small signs do not have to be on the Department’s approved list. Placement and relocation of the signs shall be in accordance with the TEM, OMUTCD or as directed by the Department. The Developer shall provide the Department with licensed software and wireless connection to supply control of the PCMS via laptop from a remote location.

SCD MT-101.70 shall be used to delineate PCB and guardrail. PCB on bridge decks shall be installed per the Bridge Design Data sheet PCB-DD and SCD PCB-91.

The Developer shall remove conflicting pavement markings by use of high pressure water. The Developer shall use ODOT CM&S Item 643 Polyester Pavement Marking for all work zone pavement marking to remain in place for more than 30 days. Work zone lane lines shall be 6 inches in width.

Page 18-17

Page 18: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

18.6 LAW ENFORCEMENT OFFICER (LEO) WITH PATROL CAR The Developer shall provide LEOs for the following situations:

A. LEOs shall be positioned to direct traffic at the point of lane restriction or road closure and to manually control traffic movements through intersections in work zones.

B. For lane closures, the use of LEOs is required during initial setup periods, tear down periods, substantial shifts of a closure point, or when new lane closure arrangements are initiated.

C. Use of LEOs is required during the entire advance preparation and closure sequence where complete blockage of traffic is required, and at traffic signal installation when impacting the normal function of the signal or the flow of traffic, or when traffic needs to be directed through an energized traffic signal contrary to the signal display. Law enforcement officers (LEOs) with patrol cars are effective for slowing traffic speed through work zones. Their use shall be specifically identified in the Construction Documents. Their purpose is to ensure the safe, efficient, and orderly movement of traffic.

In general, LEOs should be positioned to direct traffic at the point of lane restriction or road closure and to manually control traffic movements through intersections in work zones. If a lane has been closed to provide an acceleration/deceleration lane for the vehicles, then the LEO is not required.

18.7 WORK ZONE TRAFFIC SUPERVISORThe Developer shall provide and use a Work Zone Traffic Supervisor (WTS) in accordance with the TEM note 642-44. The WTS shall be available 24 hours per day, seven days per week for the duration of construction.

The Developer shall supply the Work Zone Traffic Supervisor with a ½ ton or greater pickup truck with at least 4 amber strobes lights and a full matrix message board attached to the truck (not towed). The minimum dimensions of the Full matrix message board shall be 70 inches by 30 inches. The message board must be able to display a flashing arrow and word messages. The message board must be able to be controlled from the cab of the truck. When being used the bottom of the message board must be at least 6 feet from the pavement. The Developer’s name must be on the vehicle in at least 2 locations with letters at least 6 inches high.

The pickup truck with the message board is intended to be used by the Worksite Traffic Supervisor to help Work Zone Traffic Control, rolling blocks, truck ingress and egress, and other work zone activities.

18.8 IMPROVEMENTS TO EXISTING ROADWAY NETWORK The Developer shall make improvements to the existing roadway network including:

The Developer shall remove median barriers on the I-77 and the median parapets on the I-77 bridge over I-490 and modify the joint between the northbound and southbound structure to minimize the gap to be 1/4” wide or less. The Developer shall install portable concrete barrier

Page 18-18

Page 19: Section 18 - Web viewCCG2 Project Scope_Section 18_MOT_IR Draft.docx. Page 18-18. ... May be closed for 15-minute periods for the removal of the existing super structure and the erection

document.docx

and striping to provide four lanes of traffic on I-77 northbound and southbound between the Orange Avenue entrance ramp and the I-77 southbound exit ramp to I-490. The Developer shall provide two northbound lanes and three southbound lanes on I-77 from the I-77 southbound exit ramp to I-490 through the interchange. This configuration is to be maintained until the WARP is removed. After the WARP is removed the Developer shall reinstall the median barriers and parapet in the I-77 median and return the I-77 lanes to existing configuration.

The Orange Avenue ramp to I-77 southbound shall be reconfigured from a single lane entrance ramp to a two lane entrance ramp.

18.9 CONSTRUCTION NOISEThe Developer shall comply with the requirements of Appendix EC-02 (City of Cleveland Noise Ordinance Variance).

18.10 DELIVERABLESUnless otherwise indicated, all deliverables shall be submitted in both electronic format and hardcopy format. Acceptable electronic formats include Microsoft Word, Microsoft Excel, or Adobe Acrobat (.PDF) files, unless otherwise indicated. At a minimum, the Developer shall submit the following to the Department:

Deliverable For Acceptance, Approval, or

Submittal

Number of Copies Submittal Schedule

Reference SectionHardcopy Electronic

TMP Approval 1 Within 30 days of NTP. Seven Days prior to

desired implementation of the proposed

change.

18.2

Page 18-19