school of accounting - university of new south wales€¦ · school of accounting research seminar...
TRANSCRIPT
School of Accounting
Research Seminar – Session 1, 2010
The role for management controls at different stages of project management. Some insights
from a qualitative study.
Chang-Yuan Loh
University of Sydney Date: Friday 23 April Time: 3.00-4.30pm Venue: M032 Red Center
1
The role for management controls at different stages of
project management. Some insights from a qualitative study.
FIRST DRAFT ONLY
Chang-Yuan Loh
Abstract
Capital investment projects can represent a significant proportion of an organisation’s
budget but are also subject to risks of failure. Causes of project failure have often
been attributed to the lack of effective project management controls. This paper
explores how capital investment projects are controlled within companies and where
these controls are located at different stages of a project. Semi-structured interviews
were held with project managers across various industries. Results from the
interviews suggest that proper implementation of controls at certain stages of a project
is critical to the success of that project, but that not all organisations implement them.
Results also suggest that while some organisations do have project controls, these
controls are unlikely to be effective where some users – particularly top management
– may not comply with them.
1. Introduction
A project is defined as “..a series of activities designed to achieve a specific outcome
within a set budget and timescale. It has clear start and end points, a defined set of
objectives, and a sequence of activities in between.” (Bruce and Langdon, 20011).
According to Rozenes, Vitner and Spraggett (2006), as time passes “there is a need to
update the methods, tools and techniques used in the management of projects” (p. 5).
The implementation of controls for a project is important as the lack of has been cited
as a major reason behind project failures (De Falco and Macchiaroli, 19982).
One of the major concerns in project management is delay or avoidance of
termination of projects even though they have been identified as failing. Delayed
1 As cited in Chartered Institute of Management Accountants (CIMA), Project Management: Topic Gateway Series No. 19, November 2008, www.cimaglobal.com 2 As cited in Rozenes et al, 2006, p. 6
2
project terminations can lead to the project being run to completion – however,
completed projects do not necessarily mean they have been successful in delivering
the promised objectives. It is not uncommon to see projects run to completion and
subsequently deliver a product/service that falls short of requirements. For example,
IT organizations report some 50% of total initiated projects are subsequently
terminated only after 10-100% of allocated costs have been consumed (Hormozi,
2000, p. 47). Up to 57% of organizations spent 70% of allocated costs prior to
termination, with most of the costs being unrecoverable.
Avision, Bakerville and Myers, (2001) argued that project performance (e.g. cost,
time and successful delivery) can be improved if more attention is given to the issue
of control. The lack of appropriate controls in a project can lead to a laissez faire
approach to project management where project objectives are not quantified,
performance is not measured and therefore not achieved. For example, weak
budgetary control can lead to increasing investment that may never deliver its
promised returns.
This paper examines this critical issue in project management; whether and how
controls can reduce increasing investment (time and money) in a failing project. More
specifically, this paper seeks to investigate whether the mere presence of controls can
reduce such investment, or if equal care needs to be given to individual adherence to
the controls. For example, it is easy to assert that controls are important and thus
project failures to date must be in some way caused by the absence of appropriate
controls. However, it should also be counterintuitive that modern organisations do not
have some form of management control system implemented. Perhaps it can be
argued that project failures have occurred – not due to a lack of controls necessarily –
but rather that some factor prevented those controls from being effectively used. A
notable example was presented by Free, Macintosh and Stein (2007) in relation to
Enron. Reportedly, Enron had a ‘state-of-the-art’ and award-winning management
control system, and yet its presence had limited effect where certain individuals
subverted that same system.
This exploratory study seeks to increase understanding of the issues surrounding
unsuccessful project management. Specifically, it aims to provide insights into why
3
projects fail and what controls are perceived to play a role in reducing project failures.
The rest of the paper is structured as follows. Section 2 provides a literature review
and development of the research questions. Section 3 describes the research method.
Section 4 discusses the results and Section 5 concludes.
2. Literature Review and Development of Research Questions
Capital investment projects play a major role in organisations. They can be
infrastructure investments (such as plants and equipment, hardware and software
installations) to augment the organisation’s ability to operate and/or new
products/services launched to the market. These are core to business operations and
often involve significant cost outlays. However, such projects are also susceptible to
high risks of failure. Ross and Staw (1993) described the Long Island Lighting
Company’s Shoreham nuclear plant project which was delayed for over ten years,
was more than USD$4 billion over budget and ended up decommissioned before
operations. Eden, Ackermann and Williams (2005) noted an abundance of public and
private projects that have suffered massive cost overruns within Europe. Eden et al
(2005) cited public projects including the 800 million Danish kroner (approx
USD$135m) Oresund bridge that was 68% overspent (Flyvberg, Bruzelius, &
Rothengatter, 2003), the UK’s Scottish Parliament, which was expected to cost ten
times the original budget (Scottish Parliament, 2003), and the description of 258
major transportation infrastructure projects where 90% of projects were overspent
(Flyvberg, Holm, and Buhl, 2002).
Morris and Hough (1987) (as cited in Eden et al 2005), also concluded the following
about projects in private industries:
“the track record of projects is fundamentally poor, particularly for the larger
and more difficult ones.… Projects are often completed late or over budget, do
not perform in the way expected, involve severe strain on participating
institutions or are cancelled prior to their completion after the expenditure of
considerable sums of money” (p. 7).
4
In many of the above scenarios, one can argue that a lack of appropriate controls or
compliance with existing controls may have enabled management to continue
investment in a project that had indications of failure. Escalation of commitment
(EoC) research, within management accounting, is dedicated to investigating this very
aspect of project management – that is, why do management often continue to commit
scarce resources to failing capital investment projects long after any rational person
would have given up - also known as 'pouring good money after bad' (Drummond
1996). In the case of Denver International Airport in 1992, for example, persistence
with a problematic baggage system resulted in a system that was $2 billion over
budget, several months behind schedule and plagued with operational issues
(Monteleagre and Keil 2000). It is important to note here that the problem illustrated
within the EoC literature is not necessarily that these projects were not needed nor
that persistence in projects generally is necessarily dysfunctional. Rather the problem
is increasing (or escalating) investment in a project that had early and consistent
indications of failure, that any other rational individual would have terminated or
reassessed.
The EoC literature has significant implications for the business world as it
investigates what factors drive managers (to make certain decisions) to continue
unprofitable projects that logically should be discontinued. Understanding such
factors also help design control systems to mitigate actions which would be
detrimental to the organization’s goal of creating value.
EoC has been explained from different theoretical perspectives including agency
theory (Harrell and Harrison 1994), prospect theory (Whyte 1991), and self-
justification theory (Staw 1976), as well as from different contexts: exhibition shows
(Ross and Staw 1986), nuclear plant construction (Ross and Staw 1993), airport
baggage systems (Monteleagre and Keil 2000), software projects (Keil, Mann and Rai
2000), mergers (Bruner 1999) and new product developments (Schimdt and Calantone
2002).
A significant number of such research utilised an experimental approach to investigate
potential variables that may affect EoC. Some of these are outlined below:
5
Harrell and Harrison (1994) examined the interaction between four cases (privately
held information [yes/no] with incentive to shirk [yes/no]) and found that, consistent
with agency theory, managers possessing both an incentive to shirk (i.e. self interest)
and privately held information (information asymmetry) were more likely to continue
a project which is identified as failing.
Ghosh (1997) conducted an experiment adapted from an actual project based on a
national fast-food chain and found that providing unambiguous feedback about
previous expenditures and information on benefits of future expenditures significantly
reduced tendency to escalate commitment. This could be attributed to the
informativeness of specific feedback in aiding more effective decision-making
(Sprinkle, 2000). Similarly, Ghosh (1997) found that preparation of a project’s
progress report also greatly moderated the funds committed to it compared to the
absence of such a report.
Schimdt et al (2001) investigated EoC in New Product Developments (NPDs) with
respect to individuals, face-to-face teams and virtual teams. Their results indicate that
teams make more effective project continuation decisions than individuals who were
more likely to escalate their commitment to unprofitable projects. In particular, the
authors found that virtual teams made the best decisions, and that the effectiveness of
decision-making teams at project reviews can be significantly magnified when teams
are dispersed and communicate via asynchronous media.
Schimdt & Calantone (2002) also found that managers who initiate a NPD are less
likely to perceive it as failing, and thus are more committed to it, than managers who
assume leadership of a project after it has started. The authors also find that there is a
tendency for greater commitment to innovative products rather than less innovative
ones. Their results suggest that simply giving managers better information may not
lead to better decisions, and that the escalation commitment is a more serious problem
during NPD than after the product is commercialised. McNamara et al (2002)
suggested two methods to aid in de-escalation of commitment. Their results showed
6
that increased monitoring and subsequent rotation of project responsibility had the
desired effect of reducing escalation.
Heng et al (2003) investigated how social and psychological factors could help reduce
EoC in software projects. The results show that under conditions of low sunk cost,
superiors can adopt the shelter strategy (by shouldering blame for botched projects) or
the support strategy (by providing assurance) to reduce EoC by individuals. However,
their results show that under conditions of high sunk costs, all these strategies do not
appear to reduce EoC. This is consistent with prior research findings that high sunk
cost triggers escalation. The results from Heng et al (2003) provide a contrast to those
of Sabherwal et al (2003). Whereas the latter showed that the tough standing taken by
top management on botched projects help in early reduction of escalation, Heng et al
(2003) suggest that a more accommodating environment can reduce EoC as well.
Booth and Schulz (2005) found that a strong ethical environment was instrumental in
reducing EoC problems both in the presence and absence of agency problems. Booth
and Schulz (2005) also found that project managers under a weak ethical environment
and no agency problems made similar project termination decisions to managers who
experienced a strong ethical environment and agency problems. This builds upon the
findings of Rutledge and Karim (1999) who found that the level of moral reasoning
contributed to decisions of commitment. Their results illustrate the importance of
establishing a strong ethical culture within organizations in order to mitigate potential
losses from EoC dilemmas.
Although there is extant research on EoC, several gaps can be argued to exist:
First, the literature tends to portray EoC as undesirable managerial behaviour
extending the life of costly projects which will inevitably fail (often caused by
individual motivations or cognition issues [Keil, Depledge and Rai 2007; and Cueller,
Keil and Johnson 2006]). This is not unfounded since research has attributed the high
number of project failures to the EoC to failing projects (Schimdt and Calantone
2002). However, this paper argues that extant literature often takes the failure of the
7
project as a given - that is, there has been little explanation of why projects fail in the
first instance, and whether the factors which have allowed the failure of these projects
are related to those which encourage subsequent EoC. This is argued to be important
since literature has noted the establishment of an effective management control
system to be important for project success (de Falco and Macchiaroli 1998; Avision,
Bakerville and Myers 2001). Yet, few studies in EoC – to date – have examined (from
a qualitative perspective) what management controls are perceived to reduce the
likelihood of project failures.
Second, much of extant EoC research is dominated by studies using experimental
settings. Such studies typically include a capital budgeting scenario where subjects are
often presented with a project continuance decision asking them to evaluate whether
they would invest more or less into a specific project. An assumption is often made
that the decision to continue/terminate a project is fixed at an arbitrary point in time
and there is often no justification for the chosen timeframe. However, this paper
argues that project continuance decisions are not static; managers are often faced with
the decision to continue or abandon a project at different stages of a project. Staw and
Ross (1987) noted that the abundance of EoC literature to date had been examining
occurrences of escalation prompted by a single isolated event. It was suggested that
future studies move away from this approach to a consideration of the effect of a
range of variables in a variety of contexts: “greater efforts are needed to capture
experimentally the life-span of escalation episodes so that the relative influence of
contributing variables can be tracked over time” (Staw and Ross 1987, p. 246).
However, relatively few studies to date have considered the role of project stages
(Mahring and Keil, 2008) nor which controls are important at different project stages
(Hyvari, 2006).
To explore these gaps, the aims of this paper can be formulated into two research
questions:
RQ1. What management controls are perceived to be important in reducing project
failure?
RQ2. At which stages of a project are these controls perceived to be important?
8
The purpose of this paper is thus exploratory - to study organisational project
management practices and explore which controls are perceived to be important at
different project stages in preventing project failures. To explore the perceived role of
project stages, this paper will be using the temporal framework by Staw and Ross
(1987) which proposed that the EoC to a project can occur over different project
stages and each stage is influenced by different factors (project, psychological, social
and organisational). An adapted illustration of this framework is shown in Figure 1
(please see Appendix A).
According to Staw and Ross (1987), the typical escalation episode beginning with the
conception of the project, spurred on by predictions of favourable outcomes. As the
project progresses through its middle and late stages, it gradually becomes more and
more of a losing prospect before culminating in the final stage where there is
substantially high negative feedback. Project variables are argued to be influential in
the early stages of the project as uncertainty is high in this period, and project
information is needed to test the viability of the project as well and build up the
necessary support for initial commitment. As the project continues with increasing
negative feedback, it is suggested that project variables take less precedence as the
desire to collect additional negative feedback diminishes. During the middle stages,
psychological and social variables become more influential. As the outcome of the
project becomes increasingly bleak, managers may continue to escalate commitment
to a losing course of action due to: responsibility to the project (Whyte 1991); threats
of self-justification (Staw 1976); job insecurity (Sabherwal, Sein and Marakas 2002);
sunk costs (Heng, Tan and Wei 2003); and fear of ‘loss of face’ (Chow, Harrison,
Lindquist and Wu 1997). Finally, in the late stages of the project, organizational
variables begin to influence escalation. At this stage, factors including the need for
completion (Garland and Conlon 1998; Moon 2001), and organizational inertia (Ross
and Staw 1993) become most influential.
There have been few studies to date which have tested Staw and Ross' (1987)
temporal model. For example, Ross and Staw (1993) applied the model against a case
study of the Shoreham Nuclear Plant and found that organisational factors are also
important in the early stages of a project. Subsequent studies by Sabherwal, Sein and
Marakas (2003) and He and Mittal (2007) that used Staw and Ross’ (1987) model
9
found some support for the sequencing of factors during different project stages but
relied on experimental approaches. It is the aim of this paper to explore the relevance
of this temporal model to practitioners using a qualitative approach.
3. Research Method
For the aims of this paper, semi-structured interviews were conducted with twelve
managers with experience in managing capital investment projects. This paper argues
that the use of interviews is helpful in understanding the key issues of project
management as perceived by practitioners across a range of industries. By using a
qualitative approach, this paper seeks to offer additional insights into practical project
management to those offered by previous escalation studies which have mostly used
experimental approaches. The semi-structured nature of the interviews also allows the
interviewees the freedom to develop issues not scripted by the interviewer and thus
reduces the potential for any bias. Before the actual interviews, a pilot study was
taken to trial the interview with collaboration from academic researchers and project
managers.
Key issues raised in the interviews included how projects are initiated, controlled and
concluded. Questions were asked on issues of quantifying project objectives,
performance measures and incentives. Also important were the outstanding issues
project managers have faced with regards to successful project performance.
Interviewees were also given a copy of Figure 1 (Appendix A) to comment on the
perceived relevance of Staw and Ross’ (1987) proposition. A copy of the interview
instrument is included in the Appendix B.
Interviewees had experience in a variety of industries, including construction,
engineering, information technology, retail and finance. On average, managerial
experience ranged from 5 to over 10 years. Approximately half of the interviews are
current project managers, while the other half are now currently employed as
consultants and partners at a U.S. based project consultancy firm. The data collected
contain information pertaining to the types and nature of projects within
organizations, controls used in project management, the relevance of project stages,
and the main reasons perceived to lead to project failure.
10
Each interview took between 60 to 90 minutes and were audio-taped and summarised
with the permission of the interviewees. In an attempt to address potential bias and
clarification of issues, the following steps were taken to triangulate the data: 1. A
summary of each interview was written and sent to the interviewees for confirmation;
2. Interviews were supplemented with a short survey requiring interviewees to
complete a checklist of some key issues highlighted in the interviews; 3. Discussion
between the researchers on the interpretation of issues raised from the interviews. A
summary of the interviewee demographic is provided in Table 1 below:
Designation Industry Years of experience
1 IT, Manufacturing 10+
2 Engineering 20+
3 IT 17
4 IT 15
5 Project consultancy 10+
6 Retail, accounting, manufacturing 20+
7 Retail, manufacturer 10+
8 Retail 10+
9 Retail, manufacturing, mechanical 20+
10 Project consultancy 10+
11 Project consultancy 10+
12 Project consultancy 20+ Table 1
4. Results and Discussion
Consistent with the suggestions by Guest, Bunce and Johnson (2006) that themes in
interviews recur after six interviews and data saturation occurs after twelve
interviews, this paper found that key themes regarding project management began to
recur with the third and subsequent interviews. On the whole, the majority of
interviewees expressed support for, and an interest in, this type of research into
project management.
Do I believe [project management] to be important? Yes – I’m not aware of
much research being done on this.
Interviewee 11
11
Results suggest that practitioners perceive project management to be an under-
researched field, and that theoretical approaches should not serve as a substitute for
field experience:
Project management is a discipline – not something learnt from a textbook.
Experience in the field is very important.
Interviewee 5
When interviewees were asked to comment on the likelihood of projects that were
terminated too early, most interviewees disagreed that it was a common occurrence, if
at all. Rather the main problem identified stemmed from failing projects where
termination happened too late (due to EoC). An interesting note from the interviews
was that there was little perceived difference between factors that cause a project to be
unsuccessful and those that cause subsequent EoC. Impressions from the interviews
were that factors that are related to a project’s failure can often be the same as those
that encourage escalation to that project later on. For example, one interviewee
mentioned that it is often easy in hindsight to identify poor projects, but escalation
may not have been visible at that decision moment. A project that lacks certain
controls but was nevertheless initiated with the promise to deliver, can result in EoC
where the individual who made the promise simply found it too difficult to save ‘face’
in termination.
There is trust placed in [that person’s] technical ability to deliver. Sometimes
the hardest thing is to admit defeat.
Interviewee 3
This paper argues that the aforementioned results are important as this highlights that
the problem of project failure and escalation of commitment is a contemporary one,
and that practitioners believe there to be benefits from additional research into this
area.
Given its contemporary relevance, this paper argues it is important to gain additional
insights into practical nature of project management, since results suggest
practitioners perceive the factors which affect project failure can be related to EoC.
12
Although there is extant research into EoC, this paper argues that prior studies often
rely on experimental approaches where project failure is taken as a given and project
stages are often not considered. This paper seeks to offer additional insights into these
gaps by using a qualitative perspective.
The following section presents and discusses the data collected in relation to the
research questions:
RQ1. What management controls are perceived to be important in reducing project
failure?
RQ2. At which stages of a project are these controls perceived to be important?
To better present the results relating to the research questions, the management
controls highlighted during the interviews will be grouped in chronological order by
project stages.
Not surprisingly, the importance of a formal project management control system had
the overwhelming support from all interviewees. Indeed, this is consistent with
literature assertions that project control - which includes the proper planning,
measurement, monitoring and corrective actions - of the different stages of a project
was considered to be instrumental to a project's success (Rozenes, Vitner and Spragett
2006):
Without a defined methodology, a project is not only open to criticism or
blowout, but importantly, exposed to failure.
Interviewee 3
Essential as there are very specific actions and skills required for each stage.
Interviewee 5
It was also reassuring to see that most interviewees were comfortable with Ross and
Staw’s (1993) discussion of the three main stages of project development. While not
using the same Stage 1, 2, 3 approach per se, most interviewees described three to
13
four stages of a project along similar lines: project pre-feasiblity analysis > project
initiation (early) > project implementation (middle) > project delivery (late).
Important controls at the early stages of a project:
Early project definition and subsequent performance
Results suggest that poor project definition is among major reasons as to why projects
fail.
Projects stem from a decision – the best projects are those that are defined
clearly at the start, or run the risk of being 'dead in the water' later on.
Interviewee 12
Interviewees stated that projects that are ill-defined simply cannot be planned well
and the resulting lack of direction has been argued to be one reason why managers
may choose to “just ‘wing it’” and continue the project even if there exists sufficient
negative feedback on its performance to justify discontinuance.
Many organisations have a culture where project management was a doing (roll
out) process rather than a thinking process. [We] attempt to move towards a
‘think first, then act’ philosophy. Projects must be properly defined or there will
be no way to reliably measure performance or determine ‘what should be done’
Interviewee 9
Interviewees commented that many organisations seem content to borne changes late
in the project where costs have mounted and it becomes increasingly difficult to
terminate or redirect a failing project rather than take the time early in the project
lifecycle to properly define and plan.
Some organisations seem content to suffer execution pain rather than upfront
pain - often citing a lack of time to define early, but willing to then revise and
repeat the project later on where costs and time investment is higher. It’s like
that habit of 'digging out of a hole to climb a mountain'.
Interviewee 12
14
Project ‘creep’, where ad-hoc modifications are added to the project (often a by-
product of poor project definition), was also a recurring issue of concern as one of the
reasons why projects continue to drag on past its budgeted timeframe.
I think we need to manage project creep – people like to tack on more objectives
for a project, potentially overloading it. [Oraganisations] need to be careful in
properly defining scope of project and keeping it on track.
Interviewee 11
Implementing consistent performance criteria
All interviewees made the recommendation that all projects should be measured
against set criteria.
Sometimes I see a lack of commitment to goals, of engagement to the project.
People don’t really know what is required, desired or how to get there.
Interviewee 7
However, the consensus was also that these criteria – where existent – are often not
standardised in organisations, which can allow for the occasional ‘topical’ project
(aka CEO’s pet) to receive attention and resources. Interviewees also argued that the
question should not be simply whether financial hurdles (such as ROI, NPV) are met,
but also “why is the project being done in the first place?” Projects that are not chosen
according to the organisation’s strategic criteria are often those which are most likely
to fail.
Ideally projects should follow the Strategy > Business plan > Project approach,
with the ability to assess the project back to how it relates to the strategy at
regular reviews.
Interviewee 12
Incentives
The idea of rewards for project completion is an interesting issue. For the
interviewees, recommendations on the implementation of an incentive system were
divided. Some interviewees noted that project completion is not the same as project
15
success, and incentives could perhaps be implemented to reward success as opposed
to mere completion (to avoid fast-tracking troubled projects, and to ensure all projects
deliver value). Not all organisations implemented incentives - several have a 'bleed-
down' effect, where the department gets a bonus, and it trickles down to project
members. Some recommended an incentive system to motivate, while some
mentioned that bonuses are often based on total project performance, which makes it
difficult to attribute incentives based on individual performance. Interviewees who
noted the existence of an incentive system specifically for project completion often
commented such incentives to be tied to the project manager rather than project
members. On projects that occur as a result of a tendering process (e.g.
engineering/build projects), the issue of incentives become even more complicated.
Here, the marketing team responsible for getting the tender receives incentives for
securing the bid, but the project team who gets 'passed the baton' often may not
received incentives tied to project completion (interviewees here commented project
management to be 'part of the salary'). This bred concerns where ambitious tendering
can adversely affect the project team where there is an inability to deliver that project.
Important controls during the middle stages of a project
Dedicated project management
Top management support, as well as clear segregations of duties between what is
know as ‘day-to-day’ operational activities and project management duties, have been
argued to be vital for project success.
Organisations need to differentiate individual roles and strike a balance between
day-to-day operational activities and project 'future oriented' activities. It is not
uncommon to see organisations consider [project] management as secondary,
and assume a project to turn out 'okay on the day'.
Interviewee 12
Interviewees also stated that this segregation is often “not done well”, with project
management being treated as a ‘secondary’ activity and reducing the amount of
attention a manager is willing to spend on monitoring the performance of a project.
16
The lack of a resident project manager career path means that the reins of
project management may be given to inexperienced or overworked staff. I can
give you examples of staff ‘burn-outs’ due to lean staffing, and a lack of defined
roles and workloads. This lack of project management expertise may not be due
to a lack of the ‘right’ staff, but rather a problem of misallocation of that staff.
Execution of projects – and in an optimal manner – is still an issue, and may not
be resolved until the establishment of a career path dedicated to project
managers.
Interviewee 9
Interviewees suggested that this lack of dedicated project managers may be due to the
low visibility of employee skills within the organisation – a problem potentially
worsened by what was called a lack of ‘cross-state project management fertilisation’
or choosing staff with management expertise from different parts of the organisation.
Another reason may also be related to the difficulty some organisations face
identifying the ‘right’ project manager for the job.
How do we identify which skills are preferred for a project manager, and how
do we identify that individual in the organisation?
Interviewee 9
Competence
Interviewees recommended that the individual with the best skills should undertake
the responsibility of project management.
Good project management requires a need for good processes and good people.
Past experience sees good people – rather than good processes – managing to
execute projects and ‘getting stuff done’. There is still however, the need for a
process which allows for a common language – as in communication,
procedures, means to an end – to bring people together.
Interviewee 9
However, some managers are chosen on the basis of their having championed the
project and/or having the technical competency. Interviewees argue that the best
17
project managers are those who possess both technical as well as project management
skills (e.g. people skills – “it is the people who manage a project not the software”).
Project management is a professional skill and technical competence is not
always enough. For example, some may pick a senior engineer to be a project
manager due to his/her technical skills, but it may not be a good choice if the
individual has little experience or knowledge in project management.
Interviewee 5
Project management is a discipline and is not a role that can be filled by
someone with technical competence alone. Not all functional heads, engineers
make for good project managers. They need not be content experts, but should
have exceptional people skills.
Interviewee 9
Furthermore, the project manager should have the “responsibility, accountability and
authority” for the project’s day-to-day operation, but be distinct from the project
champion to avoid conflicts of interest.
Project reviews
Consensus from the interviewees recommended the need for a formal and consistent
reporting system on the status of projects.
I think it is important…to conduct [project] reviews. Key issue in project
management is the discipline – humans resist discipline but can be critical to
success. It is important to clearly set out what needs to be measured, how to
measure these and then compare actuals. This allows for the optimisation of
resources.
Interviewee 10
The critical problem identified by the interviewees, however, was that some
organisations either lack this process, or conduct status reports by 'word-of-mouth'.
For example, one of the interviewed managers stated that it is not uncommon for
18
project managers to simply respond “we’re good” or “everything’s fine” and have the
project continued without formal assessment.
[Nowadays] we test against strict criteria. It’s a contrast to the informal
collegial approach we had but we need to balance generosity versus timeliness
and budget realism. No one wants to be seen [anymore] to be wasting money.
Interviewee 4
There is only a limited pool from which projects can draw resources from,
however, some organisations lack adequate control blocks. Some implement
'protocols' which some projects try to meet, but there is often no effort made to
back review the project to the original protocols.
Interviewee 12
Results from the interviews suggest that the timing of reviews was dependent on
several factors: the nature of the project, project size/length, and/or managerial
preference. Earlier stages such as project designs and feasibility can conduct weekly
reviews and implementation or construction stages may involve fortnightly or
monthly reviews. Interviewees also suggest that the longer a project is forecasted to
run, the longer the difference between timing of reviews (e.g. quarterly). As with the
criteria, however, interviewees note that not all projects have frequent and consistent
timing of project reviews.
[Timing of reviews is] dependent…some are not reviewed at all. It is
recommended that reviews are conducted as frequently as possible – for
example weekly. The rationale for this is that if delays occur, then you will only
be delayed by a week. The shorter a project is kept off-track, the better. But this
kind of control usually drops upon the [project consultant’s] withdrawal.
Interviewee 11
Several managers recommended a ‘red, amber, green’ approach where projects area
assessed on a routine basis on whether it has met critical hurdles. Projects that
successfully meet hurdles on cost, and time delivery are awarded the 'green' light;
projects falling short of some hurdles are held at the 'yellow' light for reassessment;
19
and finally the 'red' light is highlighted on projects falling critically short on
performance measures.
Interestingly, the results also suggest it is during these review stages where the
management accountant becomes most visible during project management. It has been
argued from the literature that proper accounting and budgeting of projects are critical
parts of a project control process (Wooldrige, Garvin and Miller 2001). Results from
the interviews support this; management accountants are often considered the ‘right-
hand’ of project managers, playing a critical role in ensuring projects stay on track,
and deliver the promised returns.
Is there a role for management accountants? Yes. Especially in large-scale
projects, they can be regarded as the right hand man of the project manager.
The accountant can focus on the numbers, allowing the project manager to
specialise in other key areas requiring his/her attention. Having a dedicated
accountant also allows for more control, with greater visibility/accountability. I
have a rule of thumb: projects involving more than $1m we hire a part-time
accountant, greater than $50m, a full-time position. They are like the three legs
of the tripod. Time/Cost/Performance of projects can optimally be managed via
the Project Manager/Management Accountant/Project Team.
Interviewee 9
Their roles, however, go beyond that of cost accounting and budget preparation to
more of a business advisor:
We would like to hire one [accountant] who is not just a beancounter...but also
one with business acumen, who understands the business.
Interviewee 8
I do see a role – the most useful MAs are those who are not mere beancounters,
but active in day-to-day assistance with the project manager. They can be
regarded as the major people to audit and sign-off on expenditure and confirm
that a project is indeed delivery its benefits (e.g. through assessing potential
savings in fixed/variable costs). They are often closer to the marketing/sales
20
staff, assisting them with the forecast of future benefits and preparing the reports
for the project manager.
Interviewee 11
Important controls during later stages of a project
Post-project audits
The majority of interviewees agreed to a common problem in many organisations -
that of a lack of proper audits of performance post-project.
A glaring problem perhaps lies in the lack of post-project reviews. There is no
audit into what made certain projects successful and others not. The ‘why’ of
success is not critically done.
Interviewee 3
Most interviewees also suggested the need to evaluate projects on not just “what has
been done”, but also ‘how it was done” and “what has not been done, and what can be
done about it?”
Often project managers are measured on ‘getting the job done’ rather than
‘how’ the job was done. For example, a job could be done by yelling incessantly
at the involved parties, but what effect does this have on staff within the
company? What else was not done and have not been measured? From
experience, companies often fail due to a lack of measurement of the critical
indicators.
Interviewee 10
However, interviewees mentioned that many organisations found such audits to be
time-consuming and unnecessary, especially following a project's successful delivery.
Projects that were non-successful (or completed, but over budget etc), were treated
like a 'hot potato' - it was commented on that many project members were simply
unwilling to spend more time on such projects and preferred to sign off and close
down as soon as possible.
21
People often don’t learn from their mistakes. Projects perform badly, and issues
are recognised, but few talk about how they can be addressed. This can be
attributed to frustration, and some can get too emotive about it.
Interviewee 5
However, interviewees raised the argument that audits are equally important for both
successful and non-successful projects. For unsuccessful projects - audits fulfil the
function of analysing what went wrong and how future mistakes can be corrected. In
the case of successful projects, audits are also a learning tool - "learning what went
well, and how it was done" for the sakes of accomplishing the same with future
projects.
There is a need for organisations to get better at capturing learnings, and not
make the same mistakes.
Interviewee 8
Other recurring issues
Another recurring theme throughout the interviews was that not all organisations have
formal controls for their projects, or if they have, the effectiveness of that system
depends heavily on top management's own willingness to follow through on it in all
project. Clear rules and guidelines on how projects should be introduced, approved
and reviewed is something that interviewees have commented as missing in project
control, or if available, not always followed. It has been commented by some that
such loopholes can lead to the birth of pet projects by powerful stakeholders:
Theoretically, there is a set of standardised procedures...but it can be
‘forgotten’, and not all projects follow the rules. Rules are important, but it is
critical that top management champions and advocates the ideas or no one will
follow them
Interviewee 1
Interestingly, one common issue also arose from the interviewees - that of a need to
develop a formal framework for training the 'rational manager' on project
management across all organisations. Several of the interviewees mentioned their
22
organisations were beginning to implement a consistent framework for rational
project management which seemed to be developed by an international project
consultancy firm based in North America. This suggests that several organisations are
increasingly moving towards a dedicated project management team and a consistent
framework for managing their capital projects.
Results from the interviews also suggest that while interviewees were familiar with
the project stages proposed by Staw and Ross (1987), they were divided on the
influence of non-project factors (e.g. psychological and social factors) in project
continuance decisions.
All interviewees strongly supported the importance of project (e.g. financial
performance) and organisational (e.g. political) factors in deciding whether to
continue a project.
Money for the project’s existence is fundamental. Without it, the project can’t
get started.
Interviewee 2
Politics can drive the speed to complete.
Interviewee 1
On the other hand, most interviewees (particularly those in a current managerial
position) were less likely to attribute project continuance decisions to psychological or
social factors.
Generally top managers are paid to make decisions based on $ not
emotions...Businesses rarely have the luxury or cash to compete on such things.
Interviewee 7
Complacency can detract from the exercise of achieving a complete data
collection by constructing imaginary barriers.
Interviewee 3
23
Also interesting was the mixed support on the relative importance of the different
factors (project, psychological, social and organisational) at different stages of a
project. Findings from the interviews give little support on whether these different
variables are weighted differently in different stages of a project. A few interviewees
did weight project factors as being more important in the earlier stages followed by
psychological and organisational factors in the later stages when assessing their
impact on EoC. Others, however, either weighted the four factors as of similar
influence throughout different stages or disagreed on the value of considering factors
other than project related. In addition, results also found a distinct difference in the
admission of the importance of non-project factors in escalation decisions between the
interviewees who are current project managers, and those who are current project
consultants (but with prior management experience). The latter group was more likely
to recognise the impact of non-project related factors on escalation decisions.
Interviewees were also more likely to mention the impact of non-project related
factors during the interviews than to rate them on the supplementing surveys.
5. Conclusion
This exploratory study seeks to increase understanding of project management in
organisations, specifically with regards to the role of management controls in
preventing project failure in relation to different stages of a project. Using a
qualitative approach to explore some practitioner perceptions of project management
in capital budgeting, this paper also aims to address gaps in extant research in EoC
which largely relies on experimental approaches. Using semi-structured interviews
with practitioners in project management across a range of organisations and
industries, results from this paper suggest that the issue of a dedicated project
management function and philosophy is of great interest to organisations, but is also
perceived to be underutilised in practice and somewhat under-researched.
Results from this study suggest that certain controls are perceived to be important in
reducing project failures and that the absence of these controls are also perceived to
influence EoC to failing projects. This paper argues that the identification of these
controls is important since studies in EoC - to date - have taken project failure as a
24
given and few have examined the underlying reasons behind project failure and how
these may be related to subsequent escalation to these failing projects.
This paper also argues few studies in EoC have integrated project stages as part of
their experimental designs. By exploring the role of project stages and which controls
should be present at certain stages of a project to reduce project failure, this study
aims to provide additional contexts to the EoC literature and help inform experimental
designs in future studies in EoC. Future studies may also shed additional insights into
how the controls identified in this paper may reduce project failure and/or escalation
of commitment, and whether other controls may also be of importance.
This study also investigates the impact of different factors (project, psychological,
social and organisational) and their weighting on project escalation at different stages
of a project. Results indicate project factors taking precedence throughout the
project’s lifecycle, and other factors (psychological, social and organizational) were
either secondary considerations or were not considered at all. This is an important
finding as it is inconsistent with the findings from Ross and Staw's (1993) case study
and the later experiments of Saherwal et al (2003) and He and Mittal (2007).
Lastly, results from the interviews suggest that having a consistent control system for
project management is critical to its success. Results also suggest however, that not all
organisations have a formal consistent project control system. In addition, the ‘people’
element was highlighted by several interviewees – that technology and processes are
by themselves insufficient if the people involved do not follow them. This is
considered to be an important finding as it raises two key issues that need to be
addressed in project management and EoC. First, while there is the general
recognition that management controls are important, the recurring concern from the
practitioners is that not all organisations implement a formal consistent system of
controls to manage projects. The second issue is the concern that even in
organisations where controls are implemented, a problem may stem from management
override of those controls which limits their effectiveness.
This study has a number of limitations. First, although the interviewees in this paper
came from a range of industries and experience (national and international), the aim
25
of the paper is not to generalise its findings across the international context.
Additional research – perhaps in the form of case studies into industries – can offer
additional insights into how project management practices are perceived. Second, the
majority of interviewees related their experiences to for-profit projects. This may have
introduced a bias towards project-related factors as opposed to non-project factors.
While several interviewees advocated a similar project management framework across
both for and not-for-profit projects, future research into the latter can reveal whether
non-project factors may also affect project decisions. Third, a limitation lies in the
potential sensitivity project managers may have in acknowledging that factors other
than project performance can influence their decision. Interviewees (particularly those
associated with project consultancy) were more comfortable with providing relevant
details by referring to the third person than on the supplementing surveys. This
sensitivity may be a potential explanation for the mixed support for the model
proposed by Staw and Ross (1987). Future research may be helpful in further
illuminating the mixed results between experimental-driven and interview-driven
research on this topic.
26
References
Avison, D., Baskerville, R., & Myers, M., 2001.Controlling research projects. Information Technology and People 14(1), p. 28–45
Booth, P. & Schulz, A K-D. 2004. The impact of an ethical environment on managers’ project
evaluation judgments under agency problem conditions. Accounting, Organizations and
Society, 29, p. 473-488.
Bruner, R.F., 1999. An analysis of value destruction and recovery in the alliance and
proposed merger of Volvo and Renault. Journal of Financial Economics, 51(1), p.125-166. Chartered Institute of Management Accountants (CIMA), Project Management: Topic Gateway Series No. 19, November 2008, www.cimaglobal.com.
Chow, C.W. Harrison, Lindquist and Wu, 1997. Escalating commitment to unprofitable
projects: replication and cross-cultural extension. Management Accounting Research, 8(3),
p.347-361. Cueller, M.J., Keil, M., & Johnson, R.D. 2006. The deaf effect response to bad news reporting in infromation systems projects, e-Service Journal, p. 75-97. Drummond, H. Escalation in Decision-Making: The Tragedy of Taurus, Oxford University Press, Oxford, UK, 1996. Eden, C., Ackermann, F., & Williams, T., 2005. The amoebic growth of project costs. Project Management Journal, 36(1), p. 15-27. Free, C., Macintosh, N., & Stein, M., 2007. Management controls: the organisational fraud triangle of leadership culture and control in Enron. Ivey Business Journal, 71(6), p.1-10.
Garland, H. & Conlon, D.E., 1998. Too Close to Quit: The Role of Project Completion in
Maintaining Commitment. Journal of Applied Social Psychology, 28(22), p.2025-2048.
Guest, G., Bunce, A. & Johnson, L. 2006. How many interviews are enough? An experiment
with data saturation and variability. Field Methods, 18(1), p. 59-82.
Ghosh, D., 1997, De-escalation strategies: some experimental evidence, Behavioral Research
in Accounting, 9, pp.88-112.
Harrell, A. & Harrison, P., 1994. An incentive to shirk privately held information, and
managers project evaluation decisions. Accounting, Organizations & Society, 19(7), p.569-
577. He, X. & Mittal, V., 2007. The effect of decision risk and project stage on escalation of commitment. Organizational Behavior & Human Decision Processes, 103(2), p.225-237.
Heng, C., Tan, B.C. & Wei, K., 2003. De-escalation of commitment in software projects:
Who matters? What matters? Information & Management, 41(1), p.99. Hormozi, A.M., McMinn, R.D., & Nzeogwu, O., 2001. The project life cycle: the termination phase. S.A.M. Advanced Management Journal, 65(1), p. 45-51.
27
Hyvari, I. 2006. Success of projects in different organizational conditions. Project Management Journal, 37(4), p. 31-41. Keil, M., Depledge, D., & Rai, A., 2007. Escalation: the role of problem recognition and cognitive bias. Decision Sciences, 38(3), p.391-421. Keil, M., Mann, J. & Rai, A., 2000. Why software projects escalate: an empirical analysis and test of four theoretical models. MIS Quarterly, 24(4), p.631-664. Mahring, M. & Keil, M., 2008. Information technology project escalation: a process model. Decision Sciences, 39(2), p. 239-272. McNamara, G., Moon, H. & Bromiley, P. 2002. Banking on commitment: intended and unintended consequences of an organization’s attempt to attenuate escalation of commitment. Academy of Management Journal, 45(2) p. 443-452. Montealegre, R. & Keil, M., 2000. De-escalating information technology projects: lessons from the Denver International Airport. MIS Quarterly, 24(3), p.417-447.
Moon, H., 2001. Looking Forward and Looking Back: Integrating Completion and Sunk-Cost
Effect Within an Escalation-of-Commitment Progress Decision. Journal of Applied
Psychology, 86(1), p.104-113. Rozenes, S., Vitner, G. & Spraggett, S. 2006. Project control: a literature review. Project Management Journal, 37(4), p. 5-14. Ross, J. & Staw, B.M. 1986. Expo 86: an escalation prototype. Administrative Science Quarterly, 31, p. 274-297. Ross, J. & Staw, B.M., 1993. Organizational Escalation and Exit: lessons from the Shoreham Nuclear Power Plant. Academy of Management Journal, 36(4), p.701-732. Rutledge, R.W & Karim, K.E. 1999. The influence of self interest and ethical considerations on managers’ evaluation judgments. Accounting, Organizations and Society, 24, p. 173-184. Sabherwal, R., Sein, M. & Marakas, G. 2003. Escalating commitment to information system projects: findings from two simulated experiments. Information and Management, 40, p. 781-798. Schimdt, J.B., Montoya-Weiss, M.M., Massey, A.M., 2001. New product development decision-making effectiveness: comparing individuals, face-to-face teams, and virtual teams, Decision Sciences, 32(4), pp.575-600. Schmidt, J.B. & Calantone, R.J., 2002. Escalation of Commitment During New Product Development. Journal of the Academy of Marketing Science, 30(2), p.103-118.
Staw, B.M., 1976. Knee-deep in the big muddy: a study of escalating commitment to a chosen
course of action. Organizational Behavior & Human Performance, 16, p. 27-44.
Staw, B.M. & Ross, J., 1987. Behavior in escalation situations: antecedents, prototypes and
solutions. Research in Organizational Behavior, 9, p.39.
28
Wooldridge, S.C., Garvin, M.M., Miller, J.B. 2001. Effects of accounting and budgeting on
capital allocation for infrastructure projects. Journal of Management in Engineering, 17(2), p.
86-94.
Whyte, G., 1991. Diffusion of Responsibility: Effects on the Escalation Tendency. Journal of Applied Psychology, 76(3), p.408-415.
29
Appendix A
Figure 1: Decision points during a project’s lifecycle (model adapted from Ross and Staw 1993) An illustration of how certain factors are proposed to affect project continuance decisions at different stages of a project’s lifecycle.
Early Stage
Design/Approval
Mid Stage
Build
Late Stage
Deliver
Decision to continue project can be influenced by the above factors:
Project: Factors to do with the project itself, including financials
and time
Psychological: Individual factors that influence the way information is
gathered, interpreted and
acted on
Social factors: Cultural or
workplace factors that influence the way information is
gathered, interpreted and
acted on
Organizational
factors: Organizational-wide factors that influence the way information is gathered, interpreted and acted on
More emphasis Less emphasis
Projects
Stages
30
Appendix B
Issues of Interest
1. Background � Title of position � Years of experience � Role within organisation � Types of projects
� for-profit or not-for-profit
� Size of projects � physical � investment � time to complete and/or duration of end product/service
� External environment considerations � Economical, political, environmental, technological
� Is the organisation highly centralised or de-centralised (degree of bureaucracy) � Are projects initiated on an organisational level or business-unit level?
2. Project Initiation Stages
� Who introduces a project and how? � What process is involved to assess the feasibility of a project?
� Is this a standardised process for all projects?
� Who are involved in the feasibility process? � Who makes the decision to approve the project?
� Time taken between project introduction and approval?
� How important is top management support for a project? � Do all projects have to be approved by top management?
� Beliefs system – How important is staff commitment to projects (at different levels)? � Are efforts made to promote staff awareness and engage support for projects (missions)?
� Are projects funded solely by the organisation? � Who are other sponsors?
� How important is sponsorship to the successful launch and completion of projects?
3. Project Management Stages
� Does the person introducing the project also manage it?
� If not, is someone chosen to manage a project (and on what criteria)? � Individual or team management � Change in management during project? Why and how?
� How frequently are projects reviewed? � Is the lifecycle of the project considered, and if so, how is it represented?
� time to completion, or lifespan of end product/service?
� Who are involved in evaluating a project (individual or committee)? � How is project performance assessed?
� Financial, non-financial
� What possible actions are available if progress is not desirable? � Termination, re-direction?
� Are the remunerations of project managers linked to project completion (besides salary) � for other staff? � Financial, non-financial incentives?
� Have there been occurrences where projects have been continued despite information suggesting otherwise? � Perceived reasons for such persistence? � Possible for politics to be controlled?
� What types of controls are in place to prevent such occurrences and to ensure the successful progress and completion of a project?
31
� Examples of a good project vs. a bad project?
4. Project Completion Stages
� Is there a perceived difference between project completion and project success? � How is project success and/or project completion defined?
� Physical completeness � Within budget � On-time � Meets operational requirements
� How common are project terminations, once commenced? � When are these likely to occur (early, late or in between)? � What are the reasons for such terminations?
� What are the impacts of such terminations? � Purely financial? � Reputation effects? � Staff security?
5. Interviewee Perceptions: outstanding issues in project management?