SAN ANTONIO RIVER IMPROVEMENTS
PROJECT
September 28, 2009
2
Project Limits
3
Project Partners
• City of San Antonio– Provides project funding for project amenities (i.e.. Sidewalks,Landscaping, Lighting, etc.) and recreation. San Antonio Water System is providing funding for utility relocation
• Bexar County– Provides project funding for flood control and river restoration elements of the project
• San Antonio River Authority (SARA)– Provides project administration and management
• U.S. Army Corps of Engineers (USACE)– Provides federal funding for river restoration and some recreational components
• San Antonio River Foundation– Provides private funding to support project
• San Antonio River Oversight Committee– A 22 person citizens committee established in 1998 with members appointed by the City, County and SARA representing the various neighborhood and business stakeholders along the river.
4
Project Budget
Total City County Private Funds
SAWS USACE
Concept Design $1.0 $0.3 $0.7 - - -
Downtown Reach $13.3 $2.4 $10.9 - - -
Eagleland $13.6 $6.2 $4.8 - - $2.6
Mission Reach $271.9 $4.5 $115.3 $4.8 $6.0 $141.3
Museum Reach Urban
$72.1 $52.3 $13.1 $6.5 $0.2 -
Museum Reach Park
$12.6 $11 $1.6 - - -
TOTAL $384.5 $76.7 $146.4 $11.3 $6.2 $143.9
Presented in millions of dollars
5
Project Benefits
• Ecosystem Restoration – The changes proposed will increase water quality and the quantity and diversity of plant and animal species.
• Flood Damage Reduction – Project will maintain or decrease the elevation of the 100 year floodplain.
• Quality of Life – Add to San Antonio’s unique charm and make the city more attractive to residents, visitors, and businesses and provide enhanced recreational opportunities along an expanded linear park system.
• Cultural connections – Linking people, neighborhoods and cultural resources and celebrating the historical connection of the river to four of the five historic missions in the San Antonio Missions National Historical Park.
• Economic Development – Promote business development along and adjacent to the river. Improvements will also enhance tourism.
6
Museum Reach: Urban SegmentLexington Ave. to Josephine Street
7
Hugman Dam looking downstream
8
Brooklyn Ave. at Lock and Dam
9
Roy Smith Street looking downstream
10
Turning Basin at the Pearl looking downstream
11
‘Shimmer Field’by Martin Richman at Lexington Ave
Photos: San Antonio River Foundation and Mark Menjivar
12
‘29° 25' 57" N / 98° 29' 13" W’by Stuart Allen at McCullough and Brooklyn Streets
Photos: San Antonio River Foundation and Mark Menjivar
13
‘Under the Over Bridge’by Mark Schlesinger at 9th Street
Photos: San Antonio River Foundation and Mark Menjivar
14
‘Sonic Passage’by Bill Fontana at Jones Avenue (Sound Art)
Photos: San Antonio River Foundation and Mark Menjivar
15
‘F.I.S.H.’by Donald Lipski
at I‐35
Photos: San Antonio River Foundation and Mark Menjivar
16
‘The Grotto’by Carlos Cortes
at Camden & Newell Streets
Photos: San Antonio River Foundation and Mark Menjivar
• Museum Reach Park Segment: Extends from Josephine Street to Hildebrand Avenue
• Priority Betterments as approved by the San Antonio River Oversight Committee:
– Initial Trail Construction (to connect Josephine Street to Avenue B) with signage
– Habitat Restoration and Temporary Irrigation
– Removal of invasive plants and debris Removal, Channel Stabilization along San Antonio River and Catalpa-Pershing Channel
– Wetlands at Witte– Acequia Madre flow diversion– Additional trail connections and
improvements along Avenue B, to Mulberry and Avenue A and to and through Brackenridge Park up to Hildebrand Avenue
– New pedestrian bridge at Mulberry
Museum Reach Park Segment
Park Segment Concepts
Under US 281
Along Catalpa Channel
Along Avenue ANear Hildebrand at Historic Upper Labor
19
Mission Reach: Project Limits
Mission Reach Ecosystem Restoration
* per USACE study; based on scale with 1 as extremely degraded and 10 as pristine; proposed condition rating is at 50 year maturity period
Existing Riverine System Rating = 1.2*
Existing River Channel Proposed River Channel
ProposedRiverine System Rating = 8.2*
• 20,000+ young trees • 334 acres of riparian woodland habitat• 113 acres of aquatic habitat • 31 riffles • 13 acres of embayment• 2 river remnants: San Juan & Espada
Restoring Habitat Features
Photos: Sally & Andy Wasowski, Lady Bird Johnson Wildflower Center
Native Grasses & Wildflowers Native Trees & Shrubs
23
A partial list of trees and vegetation to be planted and of the wildlife that will be supported by the Mission Reach project:
BIRDS:•American Woodcock
•Winter Wren
•Red-eyed Vireo
•Peregrine Falcon
•Reddish Egret
•Yellow-billed Cuckoo
•Red-winged Blackbird
•Belted Kingfisher
•Red-headed Woodpecker
VEGETATION:•Live Oak
•Pecan
•Sycamore
•Cypress
•American Elm
•Anaqua
•Redbud
•Sugar Hackberry
•Condalia
•Native grasses
•Bluebonnets and other native flowers
FISH:•Bluegill
•Channel Catfish
•Red Shiner
•Yellow Bullhead
•Largemouth Bass
•Green Sunfish
•Texas Shiner
•Gizzard Shad
•Central Stoneroller
Ecological & Cultural Connections
• Throughout the 1700’s development of what is now known as the City of San Antonio, occurred when Spanish Colonial missions were established near the natural river banks for the access to water and food.
• Restoring the river will re-establish the ecological context of the historic Spanish Missions; The project will reconnect the river’s significance to the National Park Service’s San Antonio Missions National Historical Park.
Mission San Jose
Mission Concepcion
Mission Espada
Mission San Juan
Restoration Project Limits: Mission Reach
Phase 1: Construction underway; completion spring 2010
Phase 2A: Construction award Nov. 2009; duration 12-18 months
Phase 2B, 2C & 3:Construction award March 2010; duration 3 years
Phase 4: Construction award June 2010; duration 3 years
26
Phase 1 - Roosevelt Park
27
Phase 1 – Mitchell St.
28
Phase 1 - Weir and Pedestrian Bridge
29
Phase I Betterments
• Enhanced weirs and riffles • Additional trail at Lone Star
Brewery• Upgraded trail surface • Under-bridge improvements
for future art features• Additional aquatic plants• Art enhancements
30
Mission Reach ConceptUpgraded Trail Surfaces and Seating Area
31
Phase 2A Betterments
• Pocket park street connection at Theo
• Additional trail on west bank from Theo to Mission Road
• Additional fly over bridge at Concepcion Creek
• Upgraded shaded structure • Upgraded trail surface • Portal at Mission Concepcion
32
Pocket park street connection at Theo
33
Phase 2A Betterments – Trail/Bridge
34
Phase 2A Betterments – Shade Structure
35
Mission Reach Phase II
36
Mission Reach Phase III
37
Phase 2 B,C and Phase 3 Betterments
Phase II B,C• Additional trail at Hot Wells • Enhancements to San Juan Diversion Structure• Street connections at Mission, Roosevelt,
Southcross and VFW.• Mission Portals/Connection to Mission Trails for
Mission Concepcion and Mission San Jose • Art enhancements
Phase III• Additional trails near Davis Lake/Military Dr.• Overlook at Espada Park• Habitat/ecosystem restoration improvements to
San Antonio River remnant at Symphony Lane
38
Mission Reach Phase IV
39
Phase 4 Betterments
• Mission Portals/Connection to Mission Trails at Mission San Juan and Mission Espada
• Overlook at bottomland hardwood forest near Piedras Creek
• Create picnic area across from Historic Espada Dam
• Create art project at Bergs Mill• Restore Historic San Antonio River
bridge at Ashley Road and river remnant
40
For More SARIP Information
www.sanantonioriver.org• Information on project status• Design details• Project history• Construction progress photos