s22_construction of the cofferdamspiers at fort buhlow bridge project_ltc2013
TRANSCRIPT
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
1/72
S.P. 840-43-0001
Fort Buhlow Bridge
And Approaches
Spanning the Red River
Between Alexandria & Pineville
US 71/165
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
2/72
Fort Buhlow Bridge and Approaches
Contractor:
Jensen Construction Company
Des Monies, Iowa
Construction Engineering& Inspection:
Pan American Engineers-Alexandria, Inc.
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
3/72
Fort Buhlow Bridge and Approaches
Original Contract Time: 1,120 Calendar Days
Revised Contract Time: 1,597 Calendar Days
Original Contract Amount: $82,861,116.04
Revised Contract Amount: $84,441,870.00
Contractor Began: January 29, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
4/72
Existing OK Allen Bridge
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
5/72
Plan View of Piers No. 14 & 15 & Red River
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
6/72
Top View of Cofferdam and Pile Foundation
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
7/72Side View of Cofferdam and Pier 14
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
8/72Side View of Cofferdam and Pier 14 August 4, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
9/72Top View of Completed Cofferdam at Pier 14 August 4, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
10/72Picture of Completed Pier 14 February 8, 2013
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
11/72
Driving 24 Steel Pipe Piles
at Pier 14
November 8, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
12/72Driving 24 Steel Pipe Piles at Pier 14 November 8, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
13/72Driving 24 Steel Pipe Piles at Pier 14 November 8, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
14/72Jessica and Michelle Visiting Cofferdam at Pier 14 November 8, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
15/72Jessica and Michelle Visiting Cofferdam at Pier 14 November 8, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
16/72
Diver in Cofferdam at
Pier 14
January 20, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
17/72
Diver in Cofferdam at
Pier 14
January 20, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
18/72Diver Cutting off Sheet Piles at Cofferdam, Pier 14 November 9, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
19/72
Diver Cutting Off Sheet
Piles at Cofferdam, Pier
14
November 9, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
20/72
Driven Template / Jacking Piles at Pier 15 September 8, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
21/72
September 13, 2011Jacking Piles and Hanger Rods, Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
22/72
Hydraulic Jacks at Pier 15
October 25, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
23/72
Damaged Pile Tips (template/jacking piles) from Pier 14 October 3, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
24/72
Damaged Pile Tips
(Template/Jacking Piles) from
Pier 14
October 3, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
25/72
September 21, 2011Installation of Waler Rings at Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
26/72
Pre-Augering for Sheet
Piles at Pier 15
October 26, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
27/72
Driving Sheets for Pier 15 November 2, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
28/72
November 4, 2011Driving Sheets for Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
29/72
Vibratory Hammer Used to Drive Sheet Piles October 25, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
30/72
Driving Sheet Piles for Pier 15 November 21, 2011
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
31/72
January 18, 2012Driving Sheets with Diesel Hammer at Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
32/72
Side View of the
Cofferdam and Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
33/72
March 8, 2012
Pre-Drilling Prior to
Clamming at Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
34/72
Clamming at Pier 15 March 8, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
35/72
Unconfined Compressive
Strength
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
36/72
March 29, 2012Pier 15 Coring Report
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
37/72
March 29, 2012Pier 15 Coring Report
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
38/72
March 29, 2012Pier 15 Coring Report
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
39/72
March 29, 2012Pier 15 Coring Report
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
40/72
Chisel April 5, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
41/72
April 5, 2012Chisel
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
42/72
Using Chisel Inside the Cofferdam April 6, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
43/72
Drilling For Explosives June 28, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
44/72
Drilling for Blasting
May 23, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
45/72
Installing Explosives October 5, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
46/72
Installing Explosives October 5, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
47/72
Technical Sheet for Explosives
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
48/72
Installing Explosives
October 5, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
49/72
Installing Explosives October 5, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
50/72
October 25, 2012Clamming in Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
51/72
Clamming Material on to Barge October 25, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
52/72
June 1, 2012Barge being Pushed Across the River
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
53/72
Clay Boulders at Pier 15 August 2, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
54/72
Clay Boulders at Pier 15 August 2, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
55/72
Drawing for 1st Test Pileat Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
56/72
Drawing for 2nd Test Pileat Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
57/72
2nd Test Pile at Pier 1524 Test Pile with Conical
Tip
November 27, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
58/72
DOTD Personnel Setting up PDA November 27, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
59/72
Installing Wiring toInstruments on Test Pile
November 27, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
60/72
Placing the Hydraulic Hammer on Test Pile November 27, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
61/72
November 27, 2012Power Pack for Hydraulic Hammer
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
62/72
November 27, 2012Driving Test Pile and Recording Data on the PDA
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
63/72
2nd Test Pile Drove toRefusal
November 27, 2012
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
64/72
November 29, 2012
Pulled Test Pile the NextDay, No Damage
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
65/72
Layout of 54 Diameter Drill Shafts
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
66/72
Details for 54 Drill Shafts
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
67/72
Cutting off Sheet Piles at Pier 15 January 22, 2013
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
68/72
Cutting off Sheet Piles at Pier 15 January 24, 2013
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
69/72
January 25, 2013Cutting off Sheet Piles at Pier 15
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
70/72
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
71/72
Fort Buhlow Bridge and Approaches
-
7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013
72/72
Fort Buhlow Bridge and Approaches
Questions
Questions