  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    1/72

    S.P. 840-43-0001

    Fort Buhlow Bridge

    And Approaches

    Spanning the Red River

    Between Alexandria & Pineville

    US 71/165

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    2/72

    Fort Buhlow Bridge and Approaches

    Contractor:

    Jensen Construction Company

    Des Monies, Iowa

    Construction Engineering& Inspection:

    Pan American Engineers-Alexandria, Inc.

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    3/72

    Fort Buhlow Bridge and Approaches

    Original Contract Time: 1,120 Calendar Days

    Revised Contract Time: 1,597 Calendar Days

    Original Contract Amount: $82,861,116.04

    Revised Contract Amount: $84,441,870.00

    Contractor Began: January 29, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    4/72

    Existing OK Allen Bridge

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    5/72

    Plan View of Piers No. 14 & 15 & Red River

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    6/72

    Top View of Cofferdam and Pile Foundation

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    7/72Side View of Cofferdam and Pier 14

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    8/72Side View of Cofferdam and Pier 14 August 4, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    9/72Top View of Completed Cofferdam at Pier 14 August 4, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    10/72Picture of Completed Pier 14 February 8, 2013

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    11/72

    Driving 24 Steel Pipe Piles

    at Pier 14

    November 8, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    12/72Driving 24 Steel Pipe Piles at Pier 14 November 8, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    13/72Driving 24 Steel Pipe Piles at Pier 14 November 8, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    14/72Jessica and Michelle Visiting Cofferdam at Pier 14 November 8, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    15/72Jessica and Michelle Visiting Cofferdam at Pier 14 November 8, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    16/72

    Diver in Cofferdam at

    Pier 14

    January 20, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    17/72

    Diver in Cofferdam at

    Pier 14

    January 20, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    18/72Diver Cutting off Sheet Piles at Cofferdam, Pier 14 November 9, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    19/72

    Diver Cutting Off Sheet

    Piles at Cofferdam, Pier

    14

    November 9, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    20/72

    Driven Template / Jacking Piles at Pier 15 September 8, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    21/72

    September 13, 2011Jacking Piles and Hanger Rods, Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    22/72

    Hydraulic Jacks at Pier 15

    October 25, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    23/72

    Damaged Pile Tips (template/jacking piles) from Pier 14 October 3, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    24/72

    Damaged Pile Tips

    (Template/Jacking Piles) from

    Pier 14

    October 3, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    25/72

    September 21, 2011Installation of Waler Rings at Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    26/72

    Pre-Augering for Sheet

    Piles at Pier 15

    October 26, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    27/72

    Driving Sheets for Pier 15 November 2, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    28/72

    November 4, 2011Driving Sheets for Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    29/72

    Vibratory Hammer Used to Drive Sheet Piles October 25, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    30/72

    Driving Sheet Piles for Pier 15 November 21, 2011

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    31/72

    January 18, 2012Driving Sheets with Diesel Hammer at Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    32/72

    Side View of the

    Cofferdam and Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    33/72

    March 8, 2012

    Pre-Drilling Prior to

    Clamming at Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    34/72

    Clamming at Pier 15 March 8, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    35/72

    Unconfined Compressive

    Strength

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    36/72

    March 29, 2012Pier 15 Coring Report

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    37/72

    March 29, 2012Pier 15 Coring Report

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    38/72

    March 29, 2012Pier 15 Coring Report

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    39/72

    March 29, 2012Pier 15 Coring Report

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    40/72

    Chisel April 5, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    41/72

    April 5, 2012Chisel

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    42/72

    Using Chisel Inside the Cofferdam April 6, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    43/72

    Drilling For Explosives June 28, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    44/72

    Drilling for Blasting

    May 23, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    45/72

    Installing Explosives October 5, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    46/72

    Installing Explosives October 5, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    47/72

    Technical Sheet for Explosives

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    48/72

    Installing Explosives

    October 5, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    49/72

    Installing Explosives October 5, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    50/72

    October 25, 2012Clamming in Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    51/72

    Clamming Material on to Barge October 25, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    52/72

    June 1, 2012Barge being Pushed Across the River

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    53/72

    Clay Boulders at Pier 15 August 2, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    54/72

    Clay Boulders at Pier 15 August 2, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    55/72

    Drawing for 1st Test Pileat Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    56/72

    Drawing for 2nd Test Pileat Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    57/72

    2nd Test Pile at Pier 1524 Test Pile with Conical

    Tip

    November 27, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    58/72

    DOTD Personnel Setting up PDA November 27, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    59/72

    Installing Wiring toInstruments on Test Pile

    November 27, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    60/72

    Placing the Hydraulic Hammer on Test Pile November 27, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    61/72

    November 27, 2012Power Pack for Hydraulic Hammer

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    62/72

    November 27, 2012Driving Test Pile and Recording Data on the PDA

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    63/72

    2nd Test Pile Drove toRefusal

    November 27, 2012

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    64/72

    November 29, 2012

    Pulled Test Pile the NextDay, No Damage

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    65/72

    Layout of 54 Diameter Drill Shafts

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    66/72

    Details for 54 Drill Shafts

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    67/72

    Cutting off Sheet Piles at Pier 15 January 22, 2013

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    68/72

    Cutting off Sheet Piles at Pier 15 January 24, 2013

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    69/72

    January 25, 2013Cutting off Sheet Piles at Pier 15

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    70/72

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    71/72

    Fort Buhlow Bridge and Approaches

  • 7/29/2019 S22_Construction of the CofferdamsPiers at Fort Buhlow Bridge Project_LTC2013

    72/72

    Fort Buhlow Bridge and Approaches

    Questions

    Questions