rwe generation se – the new european generation approach · forward looking statement this...
TRANSCRIPT
RWE Generation SE –The new European generation approachEssen, 27 November 2012
Matthias HartungChief Executive OfficerRWE Generation SE
Dr. Frank WeigandChief Financial OfficerRWE Generation SE
2RWE Generation SE | Board meets Investors | 27 November 2012
Forward Looking StatementThis presentation contains certain forward-looking statements within the meaning of the US federal securities laws. Especially all of thefollowing statements: Projections of revenues, income, earnings per share, capital expenditures, dividends, capital structure or other financial items; Statements of plans or objectives for future operations or of future competitive position; Expectations of future economic performance; and Statements of assumptions underlying several of the foregoing types of statementsare forward-looking statements. Also words such as “anticipate”, “believe”, “estimate”, “intend”, “may”, “will”, “expect”, “plan”, “project”“should” and similar expressions are intended to identify forward-looking statements. The forward-looking statements reflect thejudgement of RWE’s management based on factors currently known to it. No assurances can be given that these forward-lookingstatements will prove accurate and correct, or that anticipated, projected future results will be achieved. All forward-looking statementsare subject to various risks and uncertainties that could cause actual results to differ materially from expectations. Such risks anduncertainties include, but are not limited to, changes in general economic and social environment, business, political and legalconditions, fluctuating currency exchange rates and interest rates, price and sales risks associated with a market environment in thethroes of deregulation and subject to intense competition, changes in the price and availability of raw materials, risks associated withenergy trading (e.g. risks of loss in the case of unexpected, extreme market price fluctuations and credit risks resulting in the event thattrading partners do not meet their contractual obligations), actions by competitors, application of new or changed accounting standardsor other government agency regulations, changes in, or the failure to comply with, laws or regulations, particularly those affecting theenvironment and water quality (e.g. introduction of a price regulation system for the use of power grid, creating a regulation agency forelectricity and gas or introduction of trading in greenhouse gas emissions), changing governmental policies and regulatory actions withrespect to the acquisition, disposal, depreciation and amortisation of assets and facilities, operation and construction of plant facilities,production disruption or interruption due to accidents or other unforeseen events, delays in the construction of facilities, the inability toobtain or to obtain on acceptable terms necessary regulatory approvals regarding future transactions, the inability to integratesuccessfully new companies within the RWE Group to realise synergies from such integration and finally potential liability for remedialactions under existing or future environmental regulations and potential liability resulting from pending or future litigation. Any forward-looking statement speaks only as of the date on which it is made. RWE neither intends to nor assumes any obligation to update theseforward-looking statements. For additional information regarding risks, investors are referred to RWE’s latest annual report and to othermost recent reports filed with Frankfurt Stock Exchange and to all additional information published on RWE's Internet Web site.
3RWE Generation SE | Board meets Investors | 27 November 2012
EindhovenHelmondBergen op Zoom
IneosMoerdijk s-Hertogenbosch
Claus
Amer
Swentibold
IbbenbürenEmsland
Enschede
EricaGreat Yarmouth
KlazienaveenLittle BarfordPembroke
Staythorpe
Aberthaw
Matra
Biblis
Gundremmingen
Eemshaven
Ensdorf
BochumDortmund
Gersteinwerk
Goldenberg
Dormagen
Niederaußem
Fabrik Berrenrath
Fabrik Fortuna-Nord
Fabrik Frechen
FrimmersdorfNeurath
BergkamenDatteln
HerneKnepperScholvenVoerde
Walsum
Westfalen
Huckingen
GK West
Mannheim
Plomin
Saar-Energie
Weisweiler
Lignite Hard Coal Gas
Fawley
Mühlheim-Kärlich
Nuclear
Littlebrook
Oil
Competitive positions
Dispatch portfolio
Market position
Coremarkets
Germany- own plants- contracted
No 1 24 GW7 GW
UK No 4 11 GW
Netherlands No 2 7 GW
New GenCo No 1 ~50 GW1
RWE power plants in Europe
TilburyDidcot
Hydro
Vianden
Schluchsee
Biomass
Herdecke
Cuijk
1 includes 1.3 GW from RWE East
RWE’s generation portfolio is ideally located to be managed as one pan-European operation
4RWE Generation SE | Board meets Investors | 27 November 2012
New organisational asset structure
1 Biomass co-firing 2 Pumped Storages, O&M-contracts, RoR-plants in RWE Innogy
Coal, Gas,Biomass1
Generation SE
RWE AG
Lignite
…
RWE Technology
New builds
GER
…
NL
…
UK
…
Hydro2
…
Power stations
…
Mines
…
Refining
…
Nuclear
> Bundling of generation activities in one European generation company
> SE as legal corporation based in Germany
> Asset structure along fuel types while keeping regional component on the next organisational level
> German hard coal and gas-fired power plants to be transferred from RWE Power to new GenCo SE
> After separation of generation from retail businesses, GenCo to steer Dutch and UK coal, gas and biomass plants
> Nuclear plants, lignite stations, open cast mines as well as O&M of hydro plants remain legally within RWE Power AG, but will also be steered by the new GenCo
New steering model for conventional generation will be based on asset type structures cross-nationally
5RWE Generation SE | Board meets Investors | 27 November 2012
Organisational setup is prepared to combine all Generation activities under one lean management
Management organisation of RWE’s generation business as of 1 January 2013
1 CCO is also member of RWE Supply & Trading Management Board 2 Governance function for RWE Group
Corp. & Org Dev.
Legal & Compliance
Comm. & Policy
Operational Safety
Lignite Planning
Accounting
Corp. Controlling
Asset Controlling / Bus. Partnering
Tax
RWETechnology GmbH
HC/Gas UK
HC/Gas NL
HC/Gas Germany
Project Mgmt Office
Mines
Lignite Power Plants
Nuclear
Hydro
CO2/ Climate Mgmt.
Refining
CoE Health & Safety2
Commercial Asset Management CE
CAO UK
Asset Optimisation CE
CTOHC/G/B CHO
Infrastr. / Facility
R&D Germany
HR & Change
CFOCEO CTO Lignite and Nuclear CCO1
Information Mgmt
6RWE Generation SE | Board meets Investors | 27 November 2012
RWE has one of the most balanced generation portfolios of European electricity generators
0%
20%
40%
60%
80%
100%
Centrica CEZ EDF Enel E.ON Fortum GDF Iberdrola RWE SSE
Share in power plant capacity of own generation by fuel type.Source: Annual reports 2011, company presentations, RWE
Fuel mix of European electricity generators 2011 – installed capacity
Nuclear
Lignite
Hard Coal
Gas
Hydro/Other
7RWE Generation SE | Board meets Investors | 27 November 2012
0,9
1
1,1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Q2 2011 Q2 2012 Q2 2012 at times of >15 GWsolar feed-in
Our lignite based electricity generation is at full load
> Photovoltaic installations have reached a new record high in Germany (c. 30 GW as of July 2012)
> Lignite base-load electricity generation still at full load if technically available
> Mid-merit generation (hard coal and gas) mainly affected
> Lignite plants offer high flexibility: capacity reduction of approx. 40% within 1 hour possible
> At times of high feed-in of renewables, Germany tends to export electricity to neighbouring countries
Average hourly utilisation of RWE’s 300 MW lignite blocks1
110%
90%
1 Average hourly market driven utilisation of our 300 MW lignite blocks.To compare the different periods, the numbers were adjusted for non-market drivenavailability factors, i.e. planned or unplanned outages like maintenance stops.
100%
8RWE Generation SE | Board meets Investors | 27 November 2012
Market scenario for the utilisation of power plants in Germany
> Long-term scenario for the development of renewable energies published by the BMU expects strong growth of renewables new build toc. 117 GW by the end of 2020
> RWE scenario assumes no further regulatory intervention into the market mechanism
> New build of renewables according to scenario will mainly impact (old) hard coal- and (old) gas-fired power plants
> New hard coal will also come under pressure after commissioning in 2014
> Utilisation of lignite-fired power plants remains high
Average utilisation of typical German power plants
0
20
40
60
80
100
2010 2012 2014 2016 2018 20200%
100%
20%
New lignite (1,000 MW unit)
New hard coal (750 MW unit)
New gas (800 MW unit)
Old (600 MW unit)
Old (400 MW unit)
Old (300/600 MW unit)
RWE model: Average utilisation assuming normalised non-market driven availability factors, i.e. planned outages like maintenance stops for 2012-2020. Demand development and renewables new build according to BMU (Federal Ministry of Environment) “Leitstudie Szenario A” March 2012.Commodity price assumptions based on forwards as of August 2012 until 2015 escalated with 1.5% p.a. for fuel and 5% p.a. for CO2 thereafter.
c. 28 GWinstalled
c. 19 GWinstalled c. 14 GW
installed
9RWE Generation SE | Board meets Investors | 27 November 2012
Synergy and restructuring potential is targeted across various functions of the generation business
> Improve functional and organisational efficiency and effectiveness> Reduce interfaces and adjust internal resources
> Adjust for future demands> Align all technical functions cross-nationally, eliminate duplications
> Establish international fleet management> Leverage O&M synergies across national portfolios (similar to
example of GT26 optimisation at new CCGTs)> Cost management in base-load fleet
> Harmonise sourcing processes> Optimise specifications, align make vs. buy strategy> Further bundling of procurement of services and materials
Management & support functions
Central technical functions
O&M cost
External spend / contracts
> Harmonise cross-border management of commodity positions and power plant dispatch
> Improve gross margin, in particular through further optimisation and close cooperation between technical and commercial units
Gross margin / Commercialasset optimisation
10
Back-up Charts
11RWE Generation SE | Board meets Investors | 27 November 2012
All three project modules have reached maturity status, so that RWE Generation is ready for operation by 1 January 2013
> Technical services and expertise
> RWE Technology and activities in regional units
> …> Spread and option
value allocation> Short term decision
processes> …
Project modules
Structure asset operations‘Grouping of Assets’
Design management model
Board Structure
Key PerformanceIndicators
Legal Structure
Special Processes(e.g. regional coordination)
CEO
Board memberCFO
1 3Align
complementary functions
2
> Strategy> Controlling> Portfolio management
> HR> Finance> IT> …
Management functions
Support functions
Technical functions
Commercial asset
management
GenCo
O&M
12RWE Generation SE | Board meets Investors | 27 November 2012
Scenarios for German capacity reserve margins
Starting point: Entso-E’s Scenario B (January 19:00 pm)1
Development of capacity reserve margin considering...
Scenario 1:... only announced new buildand most likely shut down of power plants
Scenario 2: ... additionally to scenario 1:plus shut down of plants>50 years of lifetime
Scenario 3: ... additionally to scenario 2:plus shut down of plants which are uneconomically according to RWE market model
Source: Entso-E (2012), RWE estimates (May 2012)
System required spare capacity (Entso-E)
Scenario 1 Scenario 2 Scenario 3
Scenarios
GW
Reliable available spare capacity for peak demand
-10
-8
-6
-4
-2
0
2
4
6
8
10
2012 2013 2014 2015 2016 2017 2018 2019 2020
1 Peak demand increased by 9 GW while reliable available capacity only by ~3 GW compared to System Adequacy Report 2011
13RWE Generation SE | Board meets Investors | 27 November 2012
0
4
8
12
1 German TSOs have contracted approx. 5 GW of balancing power to cover short-term grid imbalances.
Source: ENTSO-E, EEX, BDEW; German electricity import/export on 8 February 2012, 6:00 – 7:00 p.m.
0
50
100
150
Remaining sparecapacity (<2 GW)
Net exportbalance
German domesticconsumption
Installedcapacity
Capacitynot available
Requiredbalancing power1
0123456
France
Sufficient electricity supply was only guaranteed on the basis of hardly any outages in the thermal generation fleet
No relief through electricity imports during peak hours due to likewise high electricity demand in neighbouring countries: demand for electricity exports were higher than available imports
GW
GW
Austria Swiss Netherlands Denmark Poland CZ Net export(~2 GW)
EXPORT (from Germany) IMPORT (into Germany)
Thermalcapacity
HydroWindSolar
German electricity system at its limitCapacity situation on 8 February 2012
14RWE Generation SE | Board meets Investors | 27 November 2012
Forward selling1 by RWE Power in the German market
(Average realised price for 2011: €63/MWh (2010: €67/MWh)).
(Base-load & peak-load forwards in €/MWh)
40
60
80
100
40
60
80
100
2012
forw
ard
2013
forw
ard
01/01/2010 01/07/2010 01/01/2011 01/07/2011 01/01/2012
2014
forw
ard
01/07/2012 01/01/2013
Base-load electricity forward in €/MWh(prices until 31 October 2012)
Peak-load electricity forward in €/MWh(prices until 31 October 2012)
> x%
> 50%> 30% > 35% > 80% > 90%
> 10% > 30% > 50%
1 Hedge ratio in % of full year production(as of end of September 2012)
> 20%
40
60
80
100
> 80%
> 40%
> 90%
> 50%
15RWE Generation SE | Board meets Investors | 27 November 2012
Germany: Clean Dark and Spark Spreads (CDS/CSS)
Ø 14.88
Ø 4.93
Ø -1.64
Ø 9.99Ø 7.74
Ø 6.16
CDS Cal 2011–13 Base load (€/MWh)(assumed thermal efficiency: 36%)
Source: RWE Supply & Trading, prices until 31 October 2012.
CSS Cal 2011–13 Peak load (€/MWh)(assumed thermal efficiency: 49%)
Average CDS Cal 2011–13
Average CSS Cal 2011–13
2011 forward 2012 forward 2013 forward
Trading year 2010 Trading year 2011 Trading year 2012
16RWE Generation SE | Board meets Investors | 27 November 2012
UK: Clean Dark and Spark Spreads (CDS/CSS)
Ø 6.70Ø 3.55
Ø 3.44
Ø 22.14
Ø 13.78
Ø 8.19
CDS Cal 2011–13 Base load (€/MWh)(assumed thermal efficiency: 36%)
CSS Cal 2011–13 Base load (€/MWh)(assumed thermal efficiency: 49%)
Average CDS Cal 2011–13
Average CSS Cal 2011–13
2011 forward 2012 forward 2013 forward
Source: RWE Supply & Trading, prices until 31 October 2012
Trading year 2010 Trading year 2011 Trading year 2012
RWE Dea: Successful field development leading to growth
Essen, 27 November 2012
Thomas RappuhnChief Executive OfficerRWE Dea
Johannes KarlischChief Financial OfficerRWE Dea
2RWE Dea | Board meets Investors | 27 November 2012
Forward Looking StatementThis presentation contains certain forward-looking statements within the meaning of the US federal securities laws. Especially all of thefollowing statements: Projections of revenues, income, earnings per share, capital expenditures, dividends, capital structure or other financial items; Statements of plans or objectives for future operations or of future competitive position; Expectations of future economic performance; and Statements of assumptions underlying several of the foregoing types of statementsare forward-looking statements. Also words such as “anticipate”, “believe”, “estimate”, “intend”, “may”, “will”, “expect”, “plan”, “project”“should” and similar expressions are intended to identify forward-looking statements. The forward-looking statements reflect thejudgement of RWE’s management based on factors currently known to it. No assurances can be given that these forward-lookingstatements will prove accurate and correct, or that anticipated, projected future results will be achieved. All forward-looking statementsare subject to various risks and uncertainties that could cause actual results to differ materially from expectations. Such risks anduncertainties include, but are not limited to, changes in general economic and social environment, business, political and legalconditions, fluctuating currency exchange rates and interest rates, price and sales risks associated with a market environment in thethroes of deregulation and subject to intense competition, changes in the price and availability of raw materials, risks associated withenergy trading (e.g. risks of loss in the case of unexpected, extreme market price fluctuations and credit risks resulting in the event thattrading partners do not meet their contractual obligations), actions by competitors, application of new or changed accounting standardsor other government agency regulations, changes in, or the failure to comply with, laws or regulations, particularly those affecting theenvironment and water quality (e.g. introduction of a price regulation system for the use of power grid, creating a regulation agency forelectricity and gas or introduction of trading in greenhouse gas emissions), changing governmental policies and regulatory actions withrespect to the acquisition, disposal, depreciation and amortisation of assets and facilities, operation and construction of plant facilities,production disruption or interruption due to accidents or other unforeseen events, delays in the construction of facilities, the inability toobtain or to obtain on acceptable terms necessary regulatory approvals regarding future transactions, the inability to integratesuccessfully new companies within the RWE Group to realise synergies from such integration and finally potential liability for remedialactions under existing or future environmental regulations and potential liability resulting from pending or future litigation. Any forward-looking statement speaks only as of the date on which it is made. RWE neither intends to nor assumes any obligation to update theseforward-looking statements. For additional information regarding risks, investors are referred to RWE’s latest annual report and to othermost recent reports filed with Frankfurt Stock Exchange and to all additional information published on RWE's Internet Web site.
3RWE Dea | Board meets Investors | 27 November 2012
RWE Dea with wider regional scope Existing countries and new ventures focus regions
Algeria Libya Egypt
Mauritania
Norway
Denmark
Poland
Great Britain
Germany Kazakhstan
Azerbaijan
Ukraine
Turkmenistan
Ireland
Canary Islands
Current areas of interest
New areas of interest
Exploration / Development (Production)
Exploration
New ventures
Trinidad & TobagoTrinidad & Tobago
4RWE Dea | Board meets Investors | 27 November 2012
Value chain in upstream businessA long route to production
HR-ManagementLogistic
Contracts, Legal, FinanceInformation management
QHSE
Concession acquisition
Exploration wells
Restor-ation
Concept selectionReservoir description
Construction and building work
ProductionData capture andevaluation
New projects Exploration
Evaluationand feasi-
bilityField development Production
Recoveryand
restoration
> From the first new venture activities until the start of production in the upstream business, a period of 7 to 15 years or more can elapse.
Supp
ortin
g pr
oces
ses
1 - 10 3 to 6 2 to 6 2 to > 40 years
5RWE Dea | Board meets Investors | 27 November 2012
RWE Dea projects in the pipelineExploration & development projects secure production increase
New Ventures Exploration Appraisal Field Development New Production
Eastern EuropeCaspian RegionAfrica
EgyptGermanyIrelandLibyaMauritaniaNorwayTrinidad & TobagoTurkmenistanUK
Titan, Zidane, Skarfjell (Norway)North El Amriya(Egypt)
Breagh, (UK)West Nile Delta, Disouq (Egypt) Reggane (Algeria)NC 193/195 (Libya)Knarr (Norway)Re-entry in old fields (Germany)
Clipper South, Devenick (UK)
Production start RWE share
Capex1
(€bn)2012 2013 2014 2015 2016 2017 2018
West Nile Delta NA 40%WMDW 20% 3.0
Disouq 100%(Operator) 0.2
Breagh 70%(Operator) 0.5
Clipper South 50%(Operator) 0.2
Devenick 11.3% 0.1
Reggane 19.5% 0.4
Knarr2 10% 0.2
NC 193 / 195 100%(Operator) 0.5
Start: 11 August 2012
Start: 30 September 2012
1 Share in capex2 Formerly Jordbær
6RWE Dea | Board meets Investors | 27 November 2012
Example: Field development Clipper SouthProduction commenced after fast track development
ENSCO 92 rig and Clipper South platform
Resources (RWE Dea share)> ~ 2 MMm³ OE
Investments (RWE Dea share)> ~ €0.2 billion
History and current development> Discovered by Shell in 1983. Seen as not
commercial and sold in 2007.> RWE Dea recognised a new technology opportunity
and acquired a 50% stake and operatorship in 2009.> Technical challenges: First offshore development by
RWE Dea using Frac-technology. Five long-reach wells with multiple fracs. Innovative design new platform. New pipeline to LOGGS.
> Less than 18 months from UK Government approval. First gas came on stream better than expected in August 2012 at rates of 1.2 million cubic metres per day. Production is expected to peak at 2.8 million cubic metres per day in early 2013.
Clipper South (Operator RWE Dea 50%)
7RWE Dea | Board meets Investors | 27 November 2012
Example: Field development Clipper SouthA challenging triangle had to be managed
Geology/Geography
> Tight gas reservoir> Offshore location
> Ecologically sensitive are
Technology> Drilling throughunusual designed
fixed wellhead platform> Hydraulic fracturing
Economics> Use of existing
infrastructure> Hired jack-up drilling rig
> Ambitious time and cost schedule
Callenges ofClipper South
8RWE Dea | Board meets Investors | 27 November 2012
Example: Field development Clipper SouthGood project management enabled a RWE Dea success story
9RWE Dea | Board meets Investors | 27 November 2012
Example: Field development BreaghDrilling operations safely on track
Breagh Resources (RWE Dea share)> ~ 6 MMm³ OE
Investments (RWE Dea share)> Phase 1: ~ €0.5 billion
History and current development> Discovered by Mobil in 1997. > RWE Dea acquired a 70% stake and operatorship in 2009.> Biggest field development project under the operatorship of
RWE Dea UK.> The first three wells have been successfully completed since
start of drilling in May 2012. Wells to be tested in November/early December.
> Progress on work at the gas processing plant (TGPP) behind schedule.
> First gas is expected spring 2013.
Breagh (Operator RWE Dea 70%)
Breagh drilling rig (ENSCO 70)and Breagh platform
10RWE Dea | Board meets Investors | 27 November 2012
Example: Field developments EgyptWest Nile Delta more concrete, Disouq on schedule
EGYPT
Mediterranean Sea
North Alexandria
Alexandria
West Nile Delta
Disouq
Site D
Resources (RWE Dea share North Alex Phase 1)> ~ 50 MMm³ OEInvestments (RWE Dea share)> ~ €3 billionCurrent development> Evaluation of alternative site for onshore facilities. Location site D:
Works on the geotechnical study started. Soil analysis in progress. The final decision on the location is still pending.
> First gas expected in 2017 if the political situation stabilises further.
West Nile Delta(N. Alex: RWE Dea 40%, W. Med. Deep RWE Dea 20%; Operator BP)
Resources (RWE Dea share)> ~ 10 MMm³ OEInvestments (RWE Dea share)> ~ €0.2 billionCurrent development> Drilling program Phase A is completed. Soil replacement on Central
Treatment Plant and road construction has been finalised. The pipe laying has been started.
> First gas is expected in second half 2013.
Disouq (Operator RWE Dea 100%)
11RWE Dea | Board meets Investors | 27 November 2012
Successful divestment agreement in Norway
Edvard Grieg
> RWE AG reached an agreement on the sale of our 20% licence interest in the “Edvard Grieg” development in Norway to OMV (Norge) for a purchase price of €247.9 million as per effective date 1 January 2012 plus a contingent payment of up to €35 million based on achievement of certain operational milestones.
> The disposal is an important part of RWE Dea’s contribution to the group's disinvestment plans.
> The transaction is subject to approval by the Norwegian Ministry of Petroleum and Energy and Ministry of Finance. The ministry of Finance did approve on 9th November. Completion of the transaction is expected in the fourth quarter of 2012.
Edvard Grieg, former Luno (RWE Dea 20 %, Operator Lundin)
12RWE Dea | Board meets Investors | 27 November 2012
Europe gas
Africa oil
Europe oil
Africa gas
> Main production increase from development of gas projects
> Europe and Germany remain important production areas
> Increase of production in North Africa
> In 2014, a production level of 40 MMboe (2011: 32 MMboe) and an operating result of €800m after planned disposals is expected (2011: €558m)
> Doubling of production volumes, however due to the disposals not by 2016 but by the end of the decade at the latest2012 2017
Expansion of the Gas and Oil ProductionUpcoming projects secure future growth
13RWE Dea | Board meets Investors | 27 November 2012
855
507
687
0
200
400
600
800
1,000
€ million
2009 2010 2011 FC 2012 2013*
* Including acquisition of Breagh and Clipper South
RWE Dea investmentsSteadily increasing to prepare for future growth
14RWE Dea | Board meets Investors | 27 November 2012
203
305
558
695
0
200
400
600
800€ million
2009 2010 2011 FC 2012 Target 2014
RWE Dea operating resultOn track to achieve ambitious growth targets
15RWE Dea | Board meets Investors | 27 November 2012
RWE Dea Exploration and New Ventures Transferring high success rate to new focus regions and exploration activities – examples 2012
Successful appraisal of recently discovered resources; oil discovery Skarfjell approves further exploration potential for the neighboring Dea license
Exploration in Egypt, Libya and Mauretania will be pursued further; evaluation of possible farm-ins and participations in licensing rounds in West and East Africa
Great BritainExisting exploration portfolio under evaluation; participation in new license rounds ongoing
Norway
Trinidad & TobagoMarket entry successful, RWE Dea is partner in the offshore block NCMA2 with a 30% share; seismic acquisition finished, identification and evaluation of leads and prospects ongoing to decide on drilling location
TurkmenistanSeismic acquisition finished in Block 23, a highly prospective near shore area in the Caspian Sea; exploration well planned for 2013
Africa
47
1420 20
9 8 60
10
20
30
40
50
0
20
40
60
80
100In %# Wells
Exploration & Appraisal
2012FC
50%
6
2011
15
53%
7
2010
20
45%
11
2009
3263%
12
2008
40
20
2007
25
56%
11
2006
11
64%
4
2005
7
57%
3
12
SuccessDry
50% 20
2013MTP
16RWE Dea | Board meets Investors | 27 November 2012
RWE Dea Reserves and ResourcesSolid Basis for growth and sustainable development
594 465 507862 834
844897
570 655
510
698474
0
250
500
750
1,000
1,250
1,500
Contingent resourcesReserves
mmboe 1,4321,4041,3091,2081,068 1,490
2006 2007 2008 2009 2010 2012*2011
* as of 26 Nov 2012
17RWE Dea | Board meets Investors | 27 November 2012
Running the whole E&P value chainHarnessing the production upside potential as a basis for exploration and organic growth
> Development projects build infrastructure (offshore/desert)on a so far verified resource basis
> The industry average shows that with ongoing field development advanced reservoir knowledge increases producible volumesand provides upside potentialand new projects
> IRRs are higher for thesefollow-on projects where existing infrastructure can be used
> Cash flow from this upside production is typically usedto finance overall exploration activities and new development
P
D
E
E
D
P
P+
P+
Financing
Cash flow
ProjectSanction
Production Upside production
up to 20 years up to 15 years in addition2 to 3 years3 to 5 years
E = exploration/appraisal; D = field development; P = production; P+ = upside production
Cash flow
RWE Deutschland AG –strong value driver positionand additional growth potentialEssen, 27 November 2012
Arndt NeuhausChief Executive OfficerRWE Deutschland AG
RWE Deutschland AG | Board meets Investors | 27 November 2012 2
Forward Looking StatementThis presentation contains certain forward-looking statements within the meaning of the US federal securities laws. Especially all of the following statements:
Projections of revenues, income, earnings per share, capital expenditures, dividends, capital structure or other financial items;Statements of plans or objectives for future operations or of future competitive position;Expectations of future economic performance; andStatements of assumptions underlying several of the foregoing types of statements
are forward-looking statements. Also words such as “anticipate”, “believe”, “estimate”, “intend”, “may”, “will”, “expect”, “plan”, “project”“should” and similar expressions are intended to identify forward-looking statements. The forward-looking statements reflect the judgement of RWE’s management based on factors currently known to it. No assurances can be given that these forward-looking statements will prove accurate and correct, or that anticipated, projected future results will be achieved. All forward-looking statements are subject to various risks and uncertainties that could cause actual results to differ materially from expectations. Such risks and uncertainties include, but are not limited to, changes in general economic and social environment, business, political and legalconditions, fluctuating currency exchange rates and interest rates, price and sales risks associated with a market environment in the throes of deregulation and subject to intense competition, changes in the price and availability of raw materials, risks associated with energy trading (e.g. risks of loss in the case of unexpected, extreme market price fluctuations and credit risks resulting in the event that trading partners do not meet their contractual obligations), actions by competitors, application of new or changed accounting standards or other government agency regulations, changes in, or the failure to comply with, laws or regulations, particularly those affecting the environment and water quality (e.g. introduction of a price regulation system for the use of power grid, creating a regulation agency for electricity and gas or introduction of trading in greenhouse gas emissions), changing governmental policies and regulatory actions with respect to the acquisition, disposal, depreciation and amortisation of assets and facilities, operation and construction of plant facilities, production disruption or interruption due to accidents or other unforeseen events, delays in the construction of facilities, the inability to obtain or to obtain on acceptable terms necessary regulatory approvals regarding future transactions, the inability to integratesuccessfully new companies within the RWE Group to realise synergies from such integration and finally potential liability for remedial actions under existing or future environmental regulations and potential liability resulting from pending or future litigation. Any forward-looking statement speaks only as of the date on which it is made. RWE neither intends to nor assumes any obligation to update these forward-looking statements. For additional information regarding risks, investors are referred to RWE’s latest annual report and to other most recent reports filed with Frankfurt Stock Exchange and to all additional information published on RWE's Internet Web site.
RWE Deutschland AG | Board meets Investors | 27 November 2012 3
We are a leading energy utility in the German market
Key figures 2011 RWE Deutschland GroupSales revenue 20.4 Euro billion
Operating result/ EBITDA 1.5/2.2 Euro billion
Investments 1.2 Euro billion
Employees (FTE) 20,000
End customers 8 million
Electricity distributed 160 TWh
Gas distributed 84 TWh
Grid length electricity 342,000 km
Grid length gas 38,000 km
Essen
Market position GermanyElectricity supply No. 1
Gas supply No. 3
Dr. Arndt NeuhausCEO
Bernd BöddelingFinance
Dr. Heinz-WilliMöldersHuman Resources
Dr. Joachim SchneiderGrid Engineering
Dr. Bernd WideraSales and Regional Companies
Overview
RWE Deutschland AG | Board meets Investors | 27 November 2012 4
Strong and stable earnings contribution with additional growth potential
We play a strong role in the RWE Group: distribution and sales business are essential value drivers
Overview
26 %
Distribution
RWE Deutschland AG
Sales
Earnings contribution to RWE Group 2011
> Sales Margin
> Customer Base
> Operative Costs
> Asset Managementon RAB1
> O&M-Costs
> Regulatory Management
Value Drivers
26 %
EBITDA RWE Group:8.5 € bn
Operating result RWE Group5.8 € bn
Share RWE Deutschland
1 RAB = Regulated Asset Base
EBITDA OR
RWE Deutschland AG | Board meets Investors | 27 November 2012 5
Ongoing growth of operating result in past and futureOverview
Review operating result in € m1 Forecast 2012
Long-term
2003 2004 2005 2006 2007 2008 2009 2010 2011
Average growth rate of about 4.5% from 2003 to 2011:
Cost reduction through efficiency programmes
Increase of margin in sales business
Negative effect of regulation in grid business
1,150
1,505+4.5% p.a.
Stable income situation due to stable regulatory situation for this and the next regulatory period (until 2018)
Growth opportunities through efficiency improvements and smart energy system-
+
+
-
+
+
+
1 Pro forma figures for current organisational structure.
-
Operating result in the order of last year’s level:
Absence of positive one-off items compared to 2011
Improved efficiency enhancement
Lower income from investments from participations
RWE Deutschland AG | Board meets Investors | 27 November 2012 6
Grid regions of RWE Deutschland Group
> RWE Deutschland group owns 342,000 km electricity and 38,000 km gas distribution grids.
> For operating local distribution grid (low and medium voltage) concessions from individual municipalities are needed.
> Municipalities assign these concessions for electricity,gas, water and distant heating. In return they receive a regulated concession fee.
> We supply electricity, gas and/or water to almost every fourth German municipality. Distribution grid area
electricity, natural gas and/or water
Distribution
München
StuttgartSaarbrücken
Mainz
Hannover
Hamburg
Berlin
Essen
DüsseldorfKöln
Augsburg
FrankfurtWiesbaden
Dresden
RWE Deutschland AG | Board meets Investors | 27 November 2012 7
Germany’s regulatory framework of incentive-based regulation offers additional profit potential
Distribution
Cost-based regulation Incentive-based regulation
> A grid operator’s revenue cap is determined by its CAPEX and a specified rate of return: Revenue = CAPEX + RoE
> Efficiency gains resulting from cost reductions are passed through to theend consumer without delay.
> Problem: Since grid operators are always reimbursed for their costs, they do nothave any incentive to reduce costs.
> Principle: Decoupling of revenue from costs> Incentive: Grid operators may temporarily
generate higher profits if they disclose efficiency reserves and reduce costs.
> Efficiency profits are transmitted to the customer only time-delayed.
Grid revenueGrid revenue
CAPEXCAPEX Regulated rate of return(always constant)
Time
€ €
1st period 2nd period
CostsCosts
Grid revenueGrid revenueNew cost audit resultsin new starting point Profit
Gas: 2013 – 2017Electricity: 2014 – 2018
RWE Deutschland AG | Board meets Investors | 27 November 2012 8
Financial performance of distribution grid business oriented at highest European benchmarks
Distribution
RWE’s target setting on regulatory outperformance3
Outperformance target
WACC [%] (regulatory conceded)
Return on RAB [%]
RWE European Comparables
> Strategic return on RAB1 goals for RWE distribution business based on ambitious outperformance target
> Outperformance target derived from European competitor analysis > Country-specific regulatory WACC2 adjusted for different regulatory regimes> Outperformance achieved by operative and regulatory management
Target achieved for current regulatory period until 2012/13
1 RAB = Regulated Asset Base 2 WACC = Weighted Average Cost of Capital 3 Outperformance = Return on RAB minus WACC
RWE Deutschland AG | Board meets Investors | 27 November 2012 9
Regulator confirms highest efficiency of RWE gridDistribution
EXAMPLE: Electricity distribution
Source: Polynomics 2008.
RWE DSO:100% efficient
Effi
cien
cy v
alue
Industry average
Companies in order of efficiency
RWE Deutschland AG | Board meets Investors | 27 November 2012 10
Our investment strategy yields high performance gridDistribution
110/10-kV-Substation10/0,4-kV-Substation
10-kV-Kabel/Freileitung
Brücke110/10-kV-Station10/0,4-kV-Station
10-kV-Kabel/Freileitung
1 km1 km
BrückeBridge10-kV-Cable/Overhead line
EXAMPLE: Typical grid area
Investment and maintenance strategy:Specific investments reduce long term CAPEX of the grid and optimise O&M costs
Grid topology after investment
Grid length 220 kmNo. of mid voltage fields 76Degree of cabling 60%
Grid topology before investment
Optimisation(investments, operation, O&M costs)
200 km Grid length56 No. of mid voltage fields90% Degree of cabling
Source: RWTH Aachen.
RWE Deutschland AG | Board meets Investors | 27 November 2012 11
Smart Grids: „Smart“ solutions for profitable investmentsDistribution
Quelle: ZSW
RWE Deutschland AG | Board meets Investors | 27 November 2012 12
Strong market position in German retail market: No. 1 in Electricity and No. 3 in Gas
Sales
Strategic aspiration
> Increase of turnover and EBITper customer due to differentiated products/services and the continuous utilisation of cross-selling potentials
Market position
> 16 % market share in electricity> 9 % market share in natural gasRWE could retain customersmore successfully than competitors
Household
> Value-oriented customer service, growth beyond pure commodity sales
> 13 % market share in electricity> 10 % market share in natural gas
> "Be excellent" in customer careand market oriented products
> 16 % market share in electricity> 6 % market share in natural gas
Business
Utilities/Reseller
RWE Deutschland AG | Board meets Investors | 27 November 2012 13
German household segment in an excellent value driver position
Sales
Margin and cost analysis indicates our excellent performance compared to our competitors
> Average demand per household and small commercial customer in Germany is 3,500 kWh/a
> RWE household and small commercial customers with 3,600 kWh/a above average
> Together with high sales margins RWE Deutschland has most attractive customer base
> Service costs benchmarked regularly> 22 % of the German household customers
are considered in the benchmark> RWE is at average cost level with further
improvement potential
Sales Margins
Customer Base
Operative Costs
Average margin
RWE Large Utilities
Small/Medium Utilities
% aboveaverage
> RWE margins for tariff customers(household and small commercial) for electricityand gas are among the highest in Germany
> To maintain margin level and low churn rates,value oriented retention schemes are set up
EXAMPLE: Tariff customers electricity
w xRWE
3.600
Average
3.500kWh/a
Company
EXAMPLE: Customer service costs
RWE
Average costs
- 40 %
+80%
EXAMPLE: Average customer electricity demand
% aboveaverage
RWE Deutschland AG | Board meets Investors | 27 November 2012 14
Energy services: approx. €500 million revenue and €40 million operating result in 2011; Expansion investment: 40 million € in 2011 to over 60 million € in 2012, further growth planned for the next years
RWE is the largest German energy service provider
Smart Markets: we use the potential of energy serviceswith distributed generation
Sales
- Energy services CAPEX [€ million] - - Energy services business with diversified portfolio -
> Major source of revenue> Classical district as "cash
cow"
> Strategic growth area> Main part of CAPEX
dedicated to contracting solutions
> Strike to initiate asset-based transactions and special products
> Importance of innovative products is steadily increasing
40
60
2013+
Energy servicesgrowth in implementation
RWE Deutschland AG | Board meets Investors | 27 November 2012 15
Research & Development for markets of tomorrowR&D
Smart metering> Project "Mülheim Counts":
Provision of more than 100,000 smart electricity meters
> Investment volume: 30 € m
Smart grids> Development and expansion
of smart electricity grids > Investment: approx. 500 € m until 2020
Smart home> "inHaus2": Carbon-free
housing project in Duisburg > Provision of innovative
energy applications> Partnership with
Fraunhofer Institute
Superconductor > Energy transmission without
losses and saving space> Planned construction of the
world's longest superconductortest line in Essen (1.0 km)
E-mobility> Development and operation
of 1,300 charging pointsthroughout Germany
> Provision of electricity from renewable sources
> Cooperation partners:Daimler, Renault, Siemens,ADAC and others
Essen
DuisburgMülheim
RWE Deutschland AG | Board meets Investors | 27 November 2012 16
Based on changing energy marketswe have three basic strategic pillars
Summary
RWE Deutschland AG yields continuously high contribution to RWE group’s value
Distribute Sale Develop
Outperform regulatory targets by optimised investment strategyand highest operating efficiency
Maintain position as top performer with high value customer base
Develop and success-fully implement new business models for a smart energy world with value enhancing growth potential