road construction impacts on stream suspended sediment loads in a nested catchment system in nepal
TRANSCRIPT
land degradation & development
Land Degrad. Develop. 17: 343–351 (2006)
Published online in Wiley InterScience (www.interscience.wiley.com). DOI: 10.1002/ldr.717
ROAD CONSTRUCTION IMPACTS ON STREAM SUSPENDEDSEDIMENT LOADS IN A NESTED CATCHMENT SYSTEM IN NEPAL
J. MERZ,1* P. M. DANGOL,2 M. P. DHAKAL,2 B. S. DONGOL,2 G. NAKARMI2
AND R. WEINGARTNER1
1Hydrology Group, University of Bern, Switzerland2People and Resource Dynamics in Mountain Watersheds of the Hindu Kush-Himalayas (PARDYP)/International Centre for Integrated
Mountain Development (ICIMOD), Kathmandu, Nepal
Received 18 February 2005; Revised 4 April 2005; Accepted 16 September 2005
ABSTRACT
In terms of erosion and elevated suspended sediment concentrations, road construction has a major impact on the environment,which is described in this paper. In the Andheri Khola catchment, Nepal, the sediment regime of a stream at different locationswithin the catchment suddenly changed between 1999 and 2000. The only explanation for this change was the construction ofthe Bardibas-Dhulikhel highway, which was initiated in this area in January 2000 and completed in March 2000. The changes insuspended sediment concentration could be shown both visually as well as statistically at three different locations in thecatchment with a catchment without any impact of the road as a control. Other possible reasons for the change could beexcluded by using the available data from the catchment. The impact of the road was estimated to range from 300 to500 per cent in terms of change in sediment yield per annum. Copyright # 2006 John Wiley & Sons, Ltd.
key words: road construction; sediment regime; middle mountains; Nepal
INTRODUCTION
The focus of watershed-management projects in Nepal, which aim to reduce sediment outputs from rural
catchments, has mostly been on agricultural land-use systems. While irrigated land is generally accepted to act as
a sediment sink (Carver, 1995), the steep, often marginal and rain-fed, agricultural land is believed to be one of the
main sediment sources with highest delivery mainly during the pre-monsoon season (Carver and Schreier, 1995).
In terms of soil-fertility loss in these areas, erosion poses a risk for farmers (Brown et al., 1999). However, in terms
of sediment output, degraded areas (i.e. barren areas, landslide scars, gullies and badlands, mainly located on red
soils in the catchment) can produce larger amounts of sediment (Carver and Nakarmi, 1995; Carver, 1995;
Nakarmi et al., 2000). In addition to this, rural roads and highways are proven sediment sources, often causing
slope instabilities and concentration of runoff, which can be hazardous if not properly managed (Deoja, 1994).
Careless maintenance of a mountain road can result in erosion rates of 100 t ha�1 y�1 according to the same author.
Tschanz et al. (1999) document a large landslide in a steep and forested area of the Yarsha Khola catchment in
the Dolakha district, Nepal, which was entirely caused by inappropriate road construction. A good overview of the
impact of roads, and rural roads in particular, in Northern Thailand is given in Ziegler and Giambelluca (1997).
In general they identify roads as having a major impact on the sediment regime and flood generation of a
Copyright # 2006 John Wiley & Sons, Ltd.
�Correspondence to: J. Merz, Hydrology and Water Resources, University of Bern, PARDYP, GPO Box 8975, EPC 2736, Kathmandu, NepalE-mail: [email protected]
Contract/grant sponsor: Swiss Agency for Development and Cooperation (SDC).Contract/grant sponsor: International Development Research Centre (IDRC).
catchment. Thus, in the context of the expanding road network in the region they need to be addressed with greater
emphasis. Merz and Mosley (1998) suggest that rural roads have a major impact on runoff as well as sediment
movement in a micro-scale catchment in New Zealand by intercepting subsurface flow and concentrating flow.
Froehlich and Walling (1997) conclude that unmetalled roads in a Polish catchment are a dominant sediment
source and contribute the majority of the suspended sediment to the local stream. They also show that on
unmetalled roads flow is initiated earlier than on other land surfaces. Gucinski et al. (2000) review the scientific
information on forest roads in the United States and conclude that the ‘geomorphic effects of roads range from
chronic and long-term contributions of fine sediment into streams to catastrophic mass failures of road cuts and
fills during large storms’. The hydrological effects are threefold according to the same authors: (1) roads intercept
rainfall directly; (2) they concentrate flow; and (3) they divert or reroute flow. The impact of roads on peak flows
are scale dependent. While in small catchments roads can effectively dewater the catchment and thereby increase
the peak flow considerably, in large catchments roads comprise only a small area of the entire catchment. However,
overall, the impacts of roads are road- (and site-) specific due to different geological, topographic, climatic,
vegetation and other conditions. Ives and Messerli (1989) provide an overview of the impact of roads on sediment
production in the Indian Himalayas with a particular focus on landslides.
A particularly vulnerable time is during construction. Road construction is a massive interference with the
environment (Schaffner, 1987). The main impact is felt by the removal of vegetation, mass wasting along the cut
slopes, and runoff over bare areas formed by excavation and by deposition of spoil material (Schuster and Huebl,
1995). This vulnerability only ends once the bare surfaces have overgrown and the, often loose, spoil material has
settled and is kept in place by vegetation. As the construction time is very short, and the impacts are often not
foreseen by the project’s hydrological services or research projects, quantitative impact studies of this effect are
limited. Sharma (1993) reports a total of 40 000 to 80 000m3 of debris generated during the construction of 1 km of
road in the mountains of Nepal. Deoja (1994) mentions 8000 t ha�1 y�1 of soil loss as a result of careless
construction. However, how much of this debris is washed out of the area is difficult to assess. Ives and Messerli
(1989) argue that there is no accurate assessment of how much sediment from road construction actually reaches
the stream.
Data from the People and Resource Dynamics in Mountain Watersheds of the Hindu Kush–Himalayas
(PARDYP) project’s site in the Jhikhu Khola catchment, Nepal, allows us to draw some quantitative and
qualitative conclusions on the direct impact of road construction in mountainous terrain of Nepal on the sediment
regime of the drainage network of this catchment. This paper aims to present the facts that show the impact as well
as the potential reasons behind such an impact.
BACKGROUND
His Majesty’s Government of Nepal supported by the Government of Japan is building a road from Dhulikel via
Bokundebesi-Nepalthok to Bardibas in Central Nepal. The total length of the road will be 158 km. About 9 km of
the road is within the Jhikhu Khola catchment, the PARDYP study catchment in Nepal, and is located at its
southern boundary. Excavation and construction work in this area was done in 1999 and 2000 mainly by means of
excavators and jack hammers (B. S. Rana, pers. comm., 2003) to rehabilitate and widen the existing alignment of a
village road. Only limited use of explosives was required. The excavated material was brought to deposition sites,
and not (as often happens in other cases) deposited downslope of the road. Significant efforts were put into proper
stabilization of the road slopes using both traditional engineering and bio-engineering methods.
One stretch of the new road lies within the catchment area of the Upper Andheri Khola (about 1�2 km) and the
Kukhuri Khola (0�8 km), where PARDYP Nepal maintains hydrological stations (sites 7 and 8 as well as site 2
further downstream).
A sudden change in the sediment regime at these sites indicated the major impact of the construction work.
According to H. Katagiri (pers. comm., 2003), construction work between kilometres 35 and 37 (in the catchment
area of the Upper Andheri Khola and Kukhuri Khola) were initiated in January 2000 and concluded in March
2000. The dates of the construction period were confirmed by the local readers monitoring the hydrological
344 J. MERZ ET AL.
Copyright # 2006 John Wiley & Sons, Ltd. LAND DEGRADATION & DEVELOPMENT, 17: 343–351 (2006)
stations downstream of the road. Not only did the sediment regime at the gauging stations change in this period,
but also the bed material in the streams changed dramatically. Before 2000 the river bed in the Kukhuri Khola was
mainly composed of boulders, but after 2000 it was sandy and of a finer texture.
STUDY SITE AND DATA
The Andheri Khola catchment is located within the Jhikhu Khola catchment about 45 km east of Kathmandu
(Figure 1). Rain-fed agricultural land (in Nepali bari) dominated the land-use system in the catchments with
36�7 per cent in the catchment area of site 2, 55�4 per cent in the area of site 7 and 62�9 per cent in the area of site 8.Forest accounted for 39�9 per cent, 21�3 per cent and 14�9 per cent in the catchment areas of sites 2, 7 and 8,
respectively. The road alignment passes through the upper part of this catchment at an altitude of about
1450m a.s.l. Sediment data are available from hydrological stations below the intersection of the new road
with the monitored tributaries. The first sites are at a distance of 1�3 to 1�4 km from the road (Table I and Figure 1).
These stations, sites 7 and 8, monitor two separate catchments draining into the Andheri Khola catchment, which
is being monitored by site 2 at a distance of 5�2 km. The Andheri Khola is a tributary of the Jhikhu Khola, which
has a station at the outlet of the catchment at a distance of 10�8 km. Site 13 has been included in these analyses for
the purpose of control. The road impact potential is a function of the location of the measurement site in relation to
the road and the distance from the road.
The observations include manual staff gauges and automatic water level recording using floaters and pressure
transducers connected to loggers at natural, but stabilized cross-sections. Regular discharge measurements for
establishing water level–discharge relationships are done by the area–velocity method using a current meter and
the dilution method using salt as the tracer. Sediment sampling is done regularly as well as during flood events by
means of USDH-79 depth integrating sediment samplers at locations with turbulent flow and assume that the water
Figure 1. Location of the study area.
ROAD CONSTRUCTION IMPACTS ON SEDIMENT LOADS 345
Copyright # 2006 John Wiley & Sons, Ltd. LAND DEGRADATION & DEVELOPMENT, 17: 343–351 (2006)
and sediment is well mixed at this location. The samples are taken at the stream line approximately in the middle of
the stream. Regular samples were initially taken weekly as well as during flood events. An attempt was made to
take samples during both the rising and the falling limb of the hydrograph. After two complete seasons only flood
events were sampled. The samples obtained in the field were taken to the field laboratory, where they were filtered
using Whatman 40 filter papers and then oven-dried before weighing. Errors are mainly expected and associated
with the sampling location in the river. As the samples are always taken the same way, however, it is assumed to be
acceptable to compare the results relatively between the time before road construction and after road construction.
RESULTS
The comparison of the sediment-rating curves suggests a major change in the sediment regime between 1999 and
2000. This change can be clearly observed in the data from sites 7 and 8 (Figures 2a and b). In both cases the
suspended sediment concentrations in grams per litre at a certain discharge are on average higher after the road
construction in winter 2000 than before this intervention. This is true for the discharge amounts of the entire
range, although values at higher discharge levels are convergent partly due to the limited sample numbers at that
level. At site 2 (Figure 2c) the suspended sediment concentration of the samples after the construction
intervention are consistently above the concentrations sampled before. The impact of the construction is
Table I. Spatial parameters of the hydrological stations in the Jhikhu Khola catchment
Site Part of the AKC Down- Road impact Catchment Distance from the roadstream of AKC potential area [km2] (along Andheri Khola) [km]
Site 1 No Yes Limited 111�4 10�8Site 2 Yes Medium to high 5�4 5�2Site 7 Yes High 0�7 1�3Site 8 Yes High 1�8 1�4Site 13 No No None 1�5 —
AKC: Andheri Khola catchment.Source: PARDYP.
Figure 2. Sediment rating curves for four sites in the Jhikhu Khola catchment: (a) site 2; (b) site 7; (c) site 8; and (d) site 1 (logarithmic scale).
346 J. MERZ ET AL.
Copyright # 2006 John Wiley & Sons, Ltd. LAND DEGRADATION & DEVELOPMENT, 17: 343–351 (2006)
therefore still visible at this scale and distance from the road. At site 1, the outlet of the entire 111�4 km2
catchment, no distinct difference can be observed on the basis of the sample points at a given discharge (Figure
2d). However, the samples from before the construction time reflect generally higher discharges than the samples
after construction.
It is also important to note that the range of suspended sediment concentrations for any given discharge is much
greater after road construction than before. In addition all the peak concentrations for each discharge are elevated
Figure 2. Continued
ROAD CONSTRUCTION IMPACTS ON SEDIMENT LOADS 347
Copyright # 2006 John Wiley & Sons, Ltd. LAND DEGRADATION & DEVELOPMENT, 17: 343–351 (2006)
after the construction. This suggests that there is not only more sediment available, but that some of the underlying
processes have been changed after the road was in place.
For comparison, the sediment rating curves of site 13, which is on the other side of the Jhikhu Khola catchment
and has no road impact potential, are shown in Figure 3. No obvious difference can be observed between the data
from before the construction of the road on the other side of the catchment and afterwards. This result would be
Figure 2. Continued
Figure 3. Sediment rating curve of site 13 without impact of the road (logarithmic scale).
348 J. MERZ ET AL.
Copyright # 2006 John Wiley & Sons, Ltd. LAND DEGRADATION & DEVELOPMENT, 17: 343–351 (2006)
expected if the influence of the road were being put forward as the reason for the change in the sediment regime. It
can be presented as a control, and indicates no significant change in hydrology in the ‘before’ and ‘after’ periods.
These observations can also be supported by field observations in the river. It was observed that the upper
streambeds after road construction were filled with relatively coarse sediment of the sand fraction. Before the road
construction the bed was basically covered with pebbles and cobbles that were quite stable except during storm
events.
OTHER POSSIBLE REASONS
Up to now the only reason discussed for the sediment regime change has been the construction of the road. Other
possible reasons could be dramatic differences in rainfall pattern, major mass movements in the area or major land-
use changes.
A difference in the rainfall pattern between the period before and after 31 December 1999 cannot be observed on
the basis of the rainfall data from sites around the Andheri Khola catchment (Table II). The year 1999 was the year
with the highest rainfall, mainly due to the large event in October, which produced about 10 per cent of the annual
rainfall. The remaining years are all in the same range (1100–1300mm). The number of rainfall events does not
differ greatly either. In general, the number of events before 2000 was even higher. In terms of the largest events, at
all sites the October event of 1999 tops all the others. Otherwise there is no distinct difference between years with
the largest events usually around 55–65mm rainfall.
There appears to be no sudden increase in surface runoff and erosion, as can be seen at the 100m2 plot
(5m� 20m) scale within the catchment (Table III). The years 1997 to 2001 all show similar runoff values of about
345m3 ha�1. Soil loss varies in these years from 3 t ha�1 to 20 t ha�1. However, years with high values of annual
erosion are observed both before and after the end of 1999. It can therefore be concluded that the reason for the
changing sediment regime in the river was not based on a changing surface-erosion regime on agricultural land in
the catchment.
There were no major mass movements recorded in the area after 1999; these could have been responsible for the
sediment regime change. Land use was stable and no major changes occurred in the study period.
Table II. Rainfall parameters for the study period.
Site Annual rainfall [mm] Rainfall events [No] Largest rainfall event [mm]
1998 1999 2000 2001 1998 1999 2000 2001 1998 1999 2000 2001
4 1111�4 1442�5 1068�6 1203�0 114 94 71 92 52�2 149�1 69�9 58�46 1288�2 1545�6 1213�0 1208�1 114 106 95 82 65�3 170�7 54�8 65�312 1265�2 1418�8 1167�2 1109�8 95 62 92 109 65�6 129�4 51�4 46�414 1291�6 1481�3 1187�7 1259�7 79 91 88 102 60�5 133�0 64�0 47�816 1217�4 1464�3 1296�0 1214�7 85 na na 109 58�3 168�8 na 61�0na, not available.Source: PARDYP.
Table III. Annual runoff and soil loss from erosion plot within the affected catchment
1993 1994 1995 1996 1997 1998 1999 2000 2001
Runoff [m3 ha�1] 231�1 166�2 166�3 256�6 343�9 341�9 351�3 355�6 346�7Soil loss [t ha�1] 37�18 6�96 1�89 18�70 8�35 20�05 2�82 13�85 6�49Source: PARDYP.
ROAD CONSTRUCTION IMPACTS ON SEDIMENT LOADS 349
Copyright # 2006 John Wiley & Sons, Ltd. LAND DEGRADATION & DEVELOPMENT, 17: 343–351 (2006)
IMPACT
The change in suspended sediment concentration has a major impact on the sediment regime in the catchments of
the Andheri Khola and the Kukhuri Khola (Table IV). The difference in suspended sediment yield between
undisturbed conditions (i.e. the sediment rating curve before the road construction was used to calculate the
sediment yield) and disturbed conditions (i.e. the sediment rating curve for 2000 and 2001 was used for
calculation) was estimated to be about 300 per cent at site 2, with increased sediment yield after the construction of
the road. The difference at site 7 is 400–600 per cent and at site 8 about 440 per cent with reference to the
undisturbed conditions.
The difference between sediment yields in the undisturbed conditions, and the conditions after road construction
was about 10 000 t y�1 (135 t ha�1 y�1) at site 7 and 17 000 t y�1 (95 t ha�1 y�1) at site 8. This was related to the
road length within the two catchments: about 0�8 km within catchment 7 and about 1�2 km within catchment 8,
resulting in a unit area sediment yield of about 170 t ha�1 y�1 per 1 km road at site 7 and 80 t ha�1 y�1 per 1 km
road at site 8. At site 2 the unit area sediment loss due to the road impact decreased to about 25 t ha�1 y�1 per 1 km
of road. The impact at the scale of the Jhikhu Khola catchment is limited to negligible, as shown with the rating
curve in Figure 2d and is therefore assumed to be less than 1 t ha�1 y�1. Plotting the sediment yields per kilometer
against catchment area, an inverse power function is observed in the form sediment yield per 1 km road
[t ha�1 y�1]¼ 15965� catchment area [ha]�1�0351.Compared with the figures indicated by Deoja (1994) of 8000 t ha�1 y�1 for careless road construction these
values show that the impact of road construction was limited in this case. However, for a few people, the Andheri
Khola and its tributaries are a lifeline. Seventy-two irrigation diversions receive their water from these streams
(Nakarmi, 1995). An increase in sediment load might block the intakes and change the river ecology. An increase
in the level of the riverbed will further endanger the irrigated fields along the river. Again it must be stressed that
the constructors did a commendable job in terms of environmentally friendly road construction by proper
deposition of the excavated material and engineering and bio-engineering stabilizations of the road cuts. However,
the impact of the construction cannot be fully mitigated.
CONCLUSIONS
The visual comparison of sediment rating curves before and after the road construction shows a clear impact of the
road on the sediment regime. The same is shown in the field by means of the changing stream beds and increased
deposits in the streams. However, statistical analysis of the means and the rating curve parameters cannot be
treated rigorously as the suspended sediment concentrations are too variable in nature and small changes on
the basis of other minor factors are also likely to have an impact on the regime. Other potential reasons, such as
Table IV. Sediment load of the Andheri Khola and its tributaries
Site Parameter Undisturbed Disturbed Difference 2000 Difference 2001
2000 2001 2000 2001 [t] [%] [t] [%]
2 Average annual flow [m3 s�1] 0�068 0�066 0�068 0�066 No diff. No diff.Average yield [t ha�1 y�1] 24�9 21�0 77�1 65�7 52�2 310�1 44�7 312�3Total yield [t y�1] 13 394 11 337 41 542 35 402 28 148 24 065
7 Average annual flow [m3 s�1] 0�012 0�011* 0�012 0�011 No diff. No diff.Average yield [t ha�1 y�1] 27�0 43�0 160�8 180�8 133�8 595�6 137�8 420�9Total yield [t y�1] 1997 3179 11 897 13 382 9900 10 203
8 Average annual flow [m3 s�1] 0�032 0�030 0�032 0�030 No diff. No diff.Average yield [t ha�1y�1] 28�9 27�4 129�7 120�1 100�8 448�1 92�7 438�8Total yield [t y�1] 5151 4870 23 080 21 372 17 929 16 502
*Due to a major shift in the discharge rating curve without observed discharge measurements at site 7, the post-monsoon flow of 2001 had tobe estimated on the basis of previous years.
350 J. MERZ ET AL.
Copyright # 2006 John Wiley & Sons, Ltd. LAND DEGRADATION & DEVELOPMENT, 17: 343–351 (2006)
change in precipitation pattern, increased surface runoff and erosion, land-use changes, or mass wasting, can be
excluded as possible reasons for the change in sediment regime.
According to the consulting engineers all measures were taken to minimize the sediment mobilization. So the
current impact of 200–400 per cent increase in sediment yield at the three sites would have been even higher if
these measures had not been taken. This was also shown by comparing the calculated sediment yields for the sites
in the catchment with values for sediment yields due to careless road construction reported in the literature.
In order to monitor the effectiveness of the erosion and landslide control measures along the road it will
be interesting to review the data over the next 5–10 years until the vegetation stabilizes both the road slopes and the
excavation deposits. This analysis also needs to consider hydrological parameters with questions about the
potential of changing hydrological processes over this period.
acknowledgements
The authors would like to acknowledge the financial support of the donors Swiss Agency for Development and
Cooperation (SDC), the International Development Research Centre (IDRC) and ICIMOD. Many thanks to
Pravakar B. Shah, former country coordinator PARDYP Nepal, Bhuban Shrestha, country coordinator PARDYP
Nepal, and the entire PARDYP team for their support. The data collection would not have been possible without
the efforts of the local readers. A very special thanks therefore goes to them.
references
Brown S, Schreier H, Shah PB, Lavkulich LM. 1999. Modelling of soil nutrient budgets: an assessment of agricultural sustainability in Nepal.Soil Use Management 15: 101–108.
Carver M. 1995. How do indigenous management techniques affect soil and water movement? In Challenges in Mountain ResourceManagement in Nepal. Processes, Trends, and Dynamics in Middle Mountain Watersheds, Schreier H, Shah PB, Brown S (eds). InternationalCentre for Integrated Mountain Development: Kathmandu; 193–202.
Carver M, Nakarmi G. 1995. The effect of surface conditions on soil erosion and stream suspended sediments. In Challenges in MountainResource Management in Nepal. Processes, Trends, and Dynamics in Middle Mountain Watersheds, Schreier H, Shah PB, Brown S (eds).International Centre for Integrated Mountain Development: Kathmandu; 155–162.
Carver M, Schreier H. 1995. Sediment and nutrient budgets over four spatial scales in the Jhikhu Khola watershed: implications for land usemanagement. InChallenges in Mountain Resource Management in Nepal. Processes, Trends, and Dynamics in Middle Mountain Watersheds,Schreier H, Shah PB, Brown S (eds). International Centre for Integrated Mountain Development: Kathmandu; 163–170.
Deoja BB. 1994. Sustainable approaches to the construction of roads and other infrastructure in the Hindu Kush-Himalayas. InternationalCentre for Integrated Mountain Development: Kathmandu.
Froehlich W, Walling DE. 1997. The role of unmettalled roads as a sediment source in the fluvial systems of the Polish Flysch Carpathians. InThe Response of Sediment Yield to Environmental Change. Human Impact of Erosion and Sedimentation, Walling DE (ed.). IAHS PublicationNo. 245; 159–168.
Gucinski H, Furniss MJ, Ziemer RR, Brookes MH. (eds) 2000. Forest roads: A synthesis of scientific information. United States Department ofAgriculture Forest Service.
Ives DJ, Messerli B. 1989. The Himalayan Dilemma–Reconciling Development and Conservation. Routledge: London.Merz J, Mosley MP. 1998. Hydrological behaviour of pastoral hill country modified by extensive landsliding, northern Hawke’s Bay, NewZealand. Journal of Hydrology (NZ) 37: 113–139.
Nakarmi G. 1995. Indigenous water management systems in the Andheri Khola sub-watershed. In Challenges in Mountain ResourceManagement in Nepal. Processes, Trends, and Dynamics in Middle Mountain Watersheds, Schreier H, Shah PB, Brown S (eds). InternationalCentre for Integrated Mountain Development: Kathmandu; 211–225.
Nakarmi G, Schreier H, Merz J, Mathema P. 2000. Erosion dynamics in the Jhikhu and Yarsha Khola watersheds in Nepal. In The People andResource Dynamics Project. The First Three Years (1996–1999), Allen R, Schreier H, Brown S, Shah PB (eds). International Centre forIntegrated Mountain Development: Kathmandu; 209–217.
Schaffner U. 1987. Soil erosion control in road construction and maintenance. In Expert Workshop on Road Curricula and Training for SoilErosion Control and Watershed Management (Part 1). ICIMOD-UNEP-UNEPCOM: Kathmandu.
Schuster M, Huebl J. 1995. Impact of road construction of the Pokhara-Baglung highway, Kaski district, Nepal. In Sustainable Reconstructionof Highland and Headwater Regions: Proceedings of Third International Symposium on Headwater Control, Singh RB, Haigh MJ (eds).Oxford & IBH Publications: New Delhi; 175–182.
Sharma HP. 1993. Environment friendly rural hill roads in Nepal. Bulletin of the Department of Geology 3: 109–117.Tschanz B, Vuillemin D, Droz M, Jaggi M. 1999. Hydrological and Degradation Investigations. Publikation Gewaesserkunde No. 217.Department of Geography, University of Bern.
Ziegler AD, Giambelluca TW. 1997. Importance of rural roads as source area for runoff in mountainous areas of northern Thailand. Journal ofHydrology 196: 204–229.
ROAD CONSTRUCTION IMPACTS ON SEDIMENT LOADS 351
Copyright # 2006 John Wiley & Sons, Ltd. LAND DEGRADATION & DEVELOPMENT, 17: 343–351 (2006)