river engineering flood design
TRANSCRIPT
@ McGraw-Hill Education
1
7.11 - DESIGN FLOOD For economic consideration, it’s not practical to
design the hydraulic structure for safety purpose
against maximum possible flood all the times
Culverts / storm drainage can be designed for less severe
flood
This section show the procedure to select the
flood magnitude for the design of hydraulic
structure
3 Types
Spillway design flood
Standard project flood (SPF)
Probable maximum flood (PMF)
@ McGraw-Hill Education
2
• Spillway design flood
Design flood specific for designing spillway of storage
structure
This term is used to donate maximum discharge that can
passed in hydraulic structure without causing damage or
threat to the stability of structure
• Standard project flood (SPF)
Flood that result from combination of meteorological &
hydrological factors
Extreme rare combination of factors are excluded
Used in situation where failure would cause less damage
40% - 60% of PMF for same drainage basin
@ McGraw-Hill Education
3
•Probable maximum flood (PMF)
Extreme flood that physically possible from severe
combination,
including rare combination of meteorological &
hydrological combination
Used in situation where failure of structure cause life
and severe damage
Table 7.8
Guideline for selecting design flood
Adopted by CWC India
@ McGraw-Hill Education
4
@ McGraw-Hill Education
5
INDIAN STANDARD GUIDELINE
FOR DESIGN OF FLOOD FOR
DAMS
Classification of dams
According to size (table 7.9(a))
By using hydraulic heads & gross storage
• Hydraulic head define as
Difference between maximum water level on
upstream & normal annual average flood level
downstream
• For safety of dam
The inflow design flood (IDF) is considered
Given by Table 7.9 (b)
@ McGraw-Hill Education
6
@ McGraw-Hill Education
7
7.12 – DESIGN STORM
To estimate the design flood by using unit
hydrograph
• Computation of design storm
By hydrometeorologist by using meteorological data
Various method use which depend on availability of
reliable data and expertise
2 method
Storm-producing probable maximum
precipitation (PMP) derived from PMF
Standard project storm (SPS) for SPF calculation
@ McGraw-Hill Education
8
Below show procedure from India
1. Find the critical rainfall.
This will be the basin lag if the flood peak is of
interest
If flood volume is of interest, find duration of the
longest storm experienced in the basin
2. Find the past major storm
DAD analysis is performed and the enveloping
curve represent max depth-duration relation for
the study is obtained
@ McGraw-Hill Education
9
3. From enveloping curve
Find the rainfall depth for convenient time
intervals (eg. 6 hr)
Increment to be arranged in order to find critical
sequence which produce max flood peak when
applied to unit hydrograph
Critical sequence find by
trail & error
Increment of precipitation arranged by
I. Maximum rainfall increment is against
maximum unit hydrograph ordinate
II. Second highest rainfall increment is against
the second largest unit hydrograph ordinate
III. The sequence of rainfall increment
arranged from I & II is reversed ( eg 7.8)
@ McGraw-Hill Education
10
4. Combine design storm & abstraction most
conducive to high runoff
Low initial loss & lowest infiltration rate to get to
hyetograph of rainfall excess to operate on unit
hydrograph
@ McGraw-Hill Education
11
Eg 7. 10
The ordinates of cumulative rainfall from
the enveloping maximum depth-duration
curve of a basin are given below. Also given
are the ordinates of a 6-h unit hydrograph.
Design the critical sequence of rainfall
excesses by taking the ø index to be 0.15
cm/h
@ McGraw-Hill Education
12
@ McGraw-Hill Education
13
Given data
Column 1,2 & 4
• Column 2
Row 2 – row 1 = 15 – 0 = 15
Row 3 – row 2 = 24.1 – 15 = 9.1
• Column 5
Max data in col. 3 is pair with col.4
• Column 6
Reversed of column 5
• Column 7
Given data infiltration loss = 0.15 cm/h x 6h
= 0.9 cm/6h
• Column 8
Column 6 – column 7
@ McGraw-Hill Education
14
7.13 – RISK, RELIABILITY AND SAFETY FACTORS
Design of hydraulic structure involve uncertainty &
such involve risk of failure
Risk, Rˉ is the probability of occurrence of an
event (x≥xt) at least once over n successive year
Rˉ = 1 – (probability of non-occurrence of the
event x ≥ xt in n years )
P = probability P (x ≥ xt) = 1/T
T = return period
• Reliability, Re = 1 - Rˉ = (1 – 1/T)^n
Rˉ = 1 – ( 1 – P ) ^ n ( equ 7.29)
= 1 – ( 1 - 1/ T) ^ n
@ McGraw-Hill Education
15
Safety factor
Due to uncertainty in water resource development project such as during constructional of the building or from economic causes
A safety factor with parameter M is apply to the development project
Parameter, M
Includes items such as flood discharge magnitude, max. river stage, reservoir capacity and free board
Safety margin is the difference between Cam & Chm (Cam – Chm)
Actual values of parameter
M adopted in the
Safety factor = (SF)m = design of projects . = Cam
( for parameter M) Values of parameters M Chm
obtained from
hydrological consideration
@ McGraw-Hill Education
16
Eg. 7.11 A bridge has an expected life of 25 years and is
designed for flood magnitude of return period 100
years
a) what is the risk of this hydrological design
b) if a 10% risk is acceptable, what return period
will have to be adopted
• Solution :
a) Given n = 25 years
T = 100 years
Using equation 7.29
@ McGraw-Hill Education
17
.
R = 1 – ( 1 - 1/ T) ^ n
= 1 – ( 1 – 1/100) ^ 25
= 0.222
Hence, inbuilt risk design is 22.2 %
.
b) Given R = 10% = 0.10
0.10 = 1 – ( 1 – 1/T)^25
T = 238 years ≈ 240 years
Hence, for 10 % risk, the bridge must be design with
240 years of return period
@ McGraw-Hill Education
18
Eg. 7. 12 Analysis of annual flood series of a river yielded a
sample mean of 1000 m^3/s and standard deviation
of 500m^3/s. estimate the design flood of a
structure on this river to provide 90% assurance
that the structure will not fail in the next 50 years.
Use Gumbel method and assume samples size is
large
@ McGraw-Hill Education
19
Solution:
Given
xˉ = 1000 m^3/s
σn-1 = 500 m^3/s
Reliability, Re = 90% = 0.9
n = 50 year
We need to find xt
xt = xˉ + Kσn-1
yt = - (ln x ln( T /( T -1) )
K = (yt – 0.588) / 1.2825
@ McGraw-Hill Education
20
Re = ( 1 – 1/T)^n
0.90 = (1 – 1/T)^50
T = 0.998 = 475 years
yt = - (ln x ln( T /( T -1) )
= - (ln x ln ( 475 / (475 – 1))
= 6.16226
K = (yt – 0.588) / 1.2825
= 4.355
xt = xˉ + Kσn-1 = 3177 m^3/s
@ McGraw-Hill Education
21
Eg 7.13 Annual flood data of the river Narmada at
Garudeshwar covering the period of 1948 to 1979
yield for annual flood discharge a mean of 29,600
m^3/s & standard deviation of 14,860 m^3/s. For a
proposed bridge on this rover this site it is decided
to have an acceptable risk of 10% in its expected
life of 50 years
a) estimate flood discharge by Gumbel Method
b) if the actual flood values in this design is
125,000m^3/s, what are the safety factor and safety
margin relating to the maximum flood discharge
@ McGraw-Hill Education
22
Solution
Given
Rˉ= 10% = 0.1
n = 50 year
N = 32 years (1948 – 1979)
Hence R ˉ = 1 – ( 1 - 1/ T) ^ n
0.1 = 1 – ( 1 - 1/ T) ^ 50
T =475 years
From tables 7.3 & 7.4
y ˉn =0.5380
S n = 1.1193
@ McGraw-Hill Education
23
yt = - (ln x ln( T /( T -1) )
= - (ln x ln ( 475 / (475 – 1))
= 6.16226
K = (yt – y ˉn ) / Sn
= 5.0248
xt = xˉt + Kσn-1 = 29600 + ( 5.0248 x 14860)
= 104568 ≈ 105000m^3/s
Safety factor, (SF)flood = 125000/105000 = 1.19
Safety margin = 12500 - 105000 = 20000m^3/s