Page 1: Risk Management in Sprint Environment

IEE Risk IdentificationTask-level Risk for Sprint Planning

Nov 19 2013

RISK MANAGEMENT

raquo Purpose Add risk planning to the sprint planning meetings

raquo This deck includes

bull Refresher of risk management process

bull Understand steps necessary for risk planning at the task-level

bull Understand how to create and write a risk

bull Define mitigation vs contingency plans

bull Identify expectations for tracking and monitoring

Sprint Planning

RISK DEFINITION

raquo What is risk

bull Risk is exposure to a problem an uncertain event that if occurs will

impact the success of the project (functionality cost schedule etc)

raquo Whatrsquos the difference between risk and an issue

bull Risk is unknown and an issue is known An issue may result from

risk andor create new risk

raquo If lsquouncertainty Xrsquo happens lsquoimpact Yrsquo will result

RISK MANAGEMENT PROCESSTask Level for Sprint Planning

Perform Risk

Identification

Perform Risk

Analysis

Plan Risk

Response

Monitor and

Control RisksClose Risks

Review Risk

Areas

Identify

Potential Risks

Write Risk

Statements

Analyze List of

Risk

Statements

Identify Risks

to Track

Enter Risks in

TFS

Complete

Description amp

Data

Plan

Mitigation

Create tasks

ID Triggers

Plan

Contingencies

Execute

Mitigation

Tasks

Communicate

with Team

Track Changes

in TFS

Triggers

Expired

Tasks

Completed

Breakdowns

Resolved

Score

Probability amp

Impact

Breakdowns

Trigger

Contingencies

Record

Lessons

Learned

CATEGORIES OF RISKFocus of Task Risks Release

Project

Technical

Technology

Integration

Performance

Quality

External

Vendors

Regulations

Market

Customer

Org

Dependencies

Resources

Budget

Priority

Proj Mgmt

Estimates

Plan

Control

Communication

Requirements

Experience

Mgmt Advocacy

Process

Schedule

RISK OWNERS

raquo External and Business Risks PLM Directors Sales

raquo Organizational Risks Directors Managers

raquo Project Management Risks Project Managers Managers

raquo PBI Risks Product Owners Sprint Teams

raquo Tasks Risks Sprint Teams

PBIsTasks are Focus of Sprint Teams

CREATING A RISK ITEM

raquo From the Task create the

linked Risk item

raquo The Task will be Affected

by the Risk

TFS Risk WIT

1

2

3

CREATING A RISK ITEMTFS Risk WIT (Cont)

raquo Will be linked to the task if you

started it from the task links

menu

raquo Probability allows 1 ndash 100 For

simplicity use 25() for Low 50

for Med and 75 for High Wersquoll get

more precise over time

raquo Likewise Impact allows 1

through 10 but just use 10 for

High 5 for Medium and 1 for Low

raquo Stick with Dev Doc and SQA

lsquoRisk torsquo options

raquo Leave Severity on default Wersquore

not going to use it for now

These options are changing soon

UPCOMING WIT CHANGESTFS Risk WIT (Cont)

raquo Priority Remove Priority from the form

raquo Severity Remove Severity from the form

raquo Risk to Replace current dropdown menu options with Requirements

Performance Customer Release Test Dependency

raquo Probability Remove lsquo(1-100)rsquo from the tag change the field to be a

dropdown with options of High Medium and Low set default to

Medium

raquo Impact Replace all current dropdown options with of High Medium

and Low set default

to Medium

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 2: Risk Management in Sprint Environment

RISK MANAGEMENT

raquo Purpose Add risk planning to the sprint planning meetings

raquo This deck includes

bull Refresher of risk management process

bull Understand steps necessary for risk planning at the task-level

bull Understand how to create and write a risk

bull Define mitigation vs contingency plans

bull Identify expectations for tracking and monitoring

Sprint Planning

RISK DEFINITION

raquo What is risk

bull Risk is exposure to a problem an uncertain event that if occurs will

impact the success of the project (functionality cost schedule etc)

raquo Whatrsquos the difference between risk and an issue

bull Risk is unknown and an issue is known An issue may result from

risk andor create new risk

raquo If lsquouncertainty Xrsquo happens lsquoimpact Yrsquo will result

RISK MANAGEMENT PROCESSTask Level for Sprint Planning

Perform Risk

Identification

Perform Risk

Analysis

Plan Risk

Response

Monitor and

Control RisksClose Risks

Review Risk

Areas

Identify

Potential Risks

Write Risk

Statements

Analyze List of

Risk

Statements

Identify Risks

to Track

Enter Risks in

TFS

Complete

Description amp

Data

Plan

Mitigation

Create tasks

ID Triggers

Plan

Contingencies

Execute

Mitigation

Tasks

Communicate

with Team

Track Changes

in TFS

Triggers

Expired

Tasks

Completed

Breakdowns

Resolved

Score

Probability amp

Impact

Breakdowns

Trigger

Contingencies

Record

Lessons

Learned

CATEGORIES OF RISKFocus of Task Risks Release

Project

Technical

Technology

Integration

Performance

Quality

External

Vendors

Regulations

Market

Customer

Org

Dependencies

Resources

Budget

Priority

Proj Mgmt

Estimates

Plan

Control

Communication

Requirements

Experience

Mgmt Advocacy

Process

Schedule

RISK OWNERS

raquo External and Business Risks PLM Directors Sales

raquo Organizational Risks Directors Managers

raquo Project Management Risks Project Managers Managers

raquo PBI Risks Product Owners Sprint Teams

raquo Tasks Risks Sprint Teams

PBIsTasks are Focus of Sprint Teams

CREATING A RISK ITEM

raquo From the Task create the

linked Risk item

raquo The Task will be Affected

by the Risk

TFS Risk WIT

1

2

3

CREATING A RISK ITEMTFS Risk WIT (Cont)

raquo Will be linked to the task if you

started it from the task links

menu

raquo Probability allows 1 ndash 100 For

simplicity use 25() for Low 50

for Med and 75 for High Wersquoll get

more precise over time

raquo Likewise Impact allows 1

through 10 but just use 10 for

High 5 for Medium and 1 for Low

raquo Stick with Dev Doc and SQA

lsquoRisk torsquo options

raquo Leave Severity on default Wersquore

not going to use it for now

These options are changing soon

UPCOMING WIT CHANGESTFS Risk WIT (Cont)

raquo Priority Remove Priority from the form

raquo Severity Remove Severity from the form

raquo Risk to Replace current dropdown menu options with Requirements

Performance Customer Release Test Dependency

raquo Probability Remove lsquo(1-100)rsquo from the tag change the field to be a

dropdown with options of High Medium and Low set default to

Medium

raquo Impact Replace all current dropdown options with of High Medium

and Low set default

to Medium

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 3: Risk Management in Sprint Environment

RISK DEFINITION

raquo What is risk

bull Risk is exposure to a problem an uncertain event that if occurs will

impact the success of the project (functionality cost schedule etc)

raquo Whatrsquos the difference between risk and an issue

bull Risk is unknown and an issue is known An issue may result from

risk andor create new risk

raquo If lsquouncertainty Xrsquo happens lsquoimpact Yrsquo will result

RISK MANAGEMENT PROCESSTask Level for Sprint Planning

Perform Risk

Identification

Perform Risk

Analysis

Plan Risk

Response

Monitor and

Control RisksClose Risks

Review Risk

Areas

Identify

Potential Risks

Write Risk

Statements

Analyze List of

Risk

Statements

Identify Risks

to Track

Enter Risks in

TFS

Complete

Description amp

Data

Plan

Mitigation

Create tasks

ID Triggers

Plan

Contingencies

Execute

Mitigation

Tasks

Communicate

with Team

Track Changes

in TFS

Triggers

Expired

Tasks

Completed

Breakdowns

Resolved

Score

Probability amp

Impact

Breakdowns

Trigger

Contingencies

Record

Lessons

Learned

CATEGORIES OF RISKFocus of Task Risks Release

Project

Technical

Technology

Integration

Performance

Quality

External

Vendors

Regulations

Market

Customer

Org

Dependencies

Resources

Budget

Priority

Proj Mgmt

Estimates

Plan

Control

Communication

Requirements

Experience

Mgmt Advocacy

Process

Schedule

RISK OWNERS

raquo External and Business Risks PLM Directors Sales

raquo Organizational Risks Directors Managers

raquo Project Management Risks Project Managers Managers

raquo PBI Risks Product Owners Sprint Teams

raquo Tasks Risks Sprint Teams

PBIsTasks are Focus of Sprint Teams

CREATING A RISK ITEM

raquo From the Task create the

linked Risk item

raquo The Task will be Affected

by the Risk

TFS Risk WIT

1

2

3

CREATING A RISK ITEMTFS Risk WIT (Cont)

raquo Will be linked to the task if you

started it from the task links

menu

raquo Probability allows 1 ndash 100 For

simplicity use 25() for Low 50

for Med and 75 for High Wersquoll get

more precise over time

raquo Likewise Impact allows 1

through 10 but just use 10 for

High 5 for Medium and 1 for Low

raquo Stick with Dev Doc and SQA

lsquoRisk torsquo options

raquo Leave Severity on default Wersquore

not going to use it for now

These options are changing soon

UPCOMING WIT CHANGESTFS Risk WIT (Cont)

raquo Priority Remove Priority from the form

raquo Severity Remove Severity from the form

raquo Risk to Replace current dropdown menu options with Requirements

Performance Customer Release Test Dependency

raquo Probability Remove lsquo(1-100)rsquo from the tag change the field to be a

dropdown with options of High Medium and Low set default to

Medium

raquo Impact Replace all current dropdown options with of High Medium

and Low set default

to Medium

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 4: Risk Management in Sprint Environment

RISK MANAGEMENT PROCESSTask Level for Sprint Planning

Perform Risk

Identification

Perform Risk

Analysis

Plan Risk

Response

Monitor and

Control RisksClose Risks

Review Risk

Areas

Identify

Potential Risks

Write Risk

Statements

Analyze List of

Risk

Statements

Identify Risks

to Track

Enter Risks in

TFS

Complete

Description amp

Data

Plan

Mitigation

Create tasks

ID Triggers

Plan

Contingencies

Execute

Mitigation

Tasks

Communicate

with Team

Track Changes

in TFS

Triggers

Expired

Tasks

Completed

Breakdowns

Resolved

Score

Probability amp

Impact

Breakdowns

Trigger

Contingencies

Record

Lessons

Learned

CATEGORIES OF RISKFocus of Task Risks Release

Project

Technical

Technology

Integration

Performance

Quality

External

Vendors

Regulations

Market

Customer

Org

Dependencies

Resources

Budget

Priority

Proj Mgmt

Estimates

Plan

Control

Communication

Requirements

Experience

Mgmt Advocacy

Process

Schedule

RISK OWNERS

raquo External and Business Risks PLM Directors Sales

raquo Organizational Risks Directors Managers

raquo Project Management Risks Project Managers Managers

raquo PBI Risks Product Owners Sprint Teams

raquo Tasks Risks Sprint Teams

PBIsTasks are Focus of Sprint Teams

CREATING A RISK ITEM

raquo From the Task create the

linked Risk item

raquo The Task will be Affected

by the Risk

TFS Risk WIT

1

2

3

CREATING A RISK ITEMTFS Risk WIT (Cont)

raquo Will be linked to the task if you

started it from the task links

menu

raquo Probability allows 1 ndash 100 For

simplicity use 25() for Low 50

for Med and 75 for High Wersquoll get

more precise over time

raquo Likewise Impact allows 1

through 10 but just use 10 for

High 5 for Medium and 1 for Low

raquo Stick with Dev Doc and SQA

lsquoRisk torsquo options

raquo Leave Severity on default Wersquore

not going to use it for now

These options are changing soon

UPCOMING WIT CHANGESTFS Risk WIT (Cont)

raquo Priority Remove Priority from the form

raquo Severity Remove Severity from the form

raquo Risk to Replace current dropdown menu options with Requirements

Performance Customer Release Test Dependency

raquo Probability Remove lsquo(1-100)rsquo from the tag change the field to be a

dropdown with options of High Medium and Low set default to

Medium

raquo Impact Replace all current dropdown options with of High Medium

and Low set default

to Medium

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 5: Risk Management in Sprint Environment

CATEGORIES OF RISKFocus of Task Risks Release

Project

Technical

Technology

Integration

Performance

Quality

External

Vendors

Regulations

Market

Customer

Org

Dependencies

Resources

Budget

Priority

Proj Mgmt

Estimates

Plan

Control

Communication

Requirements

Experience

Mgmt Advocacy

Process

Schedule

RISK OWNERS

raquo External and Business Risks PLM Directors Sales

raquo Organizational Risks Directors Managers

raquo Project Management Risks Project Managers Managers

raquo PBI Risks Product Owners Sprint Teams

raquo Tasks Risks Sprint Teams

PBIsTasks are Focus of Sprint Teams

CREATING A RISK ITEM

raquo From the Task create the

linked Risk item

raquo The Task will be Affected

by the Risk

TFS Risk WIT

1

2

3

CREATING A RISK ITEMTFS Risk WIT (Cont)

raquo Will be linked to the task if you

started it from the task links

menu

raquo Probability allows 1 ndash 100 For

simplicity use 25() for Low 50

for Med and 75 for High Wersquoll get

more precise over time

raquo Likewise Impact allows 1

through 10 but just use 10 for

High 5 for Medium and 1 for Low

raquo Stick with Dev Doc and SQA

lsquoRisk torsquo options

raquo Leave Severity on default Wersquore

not going to use it for now

These options are changing soon

UPCOMING WIT CHANGESTFS Risk WIT (Cont)

raquo Priority Remove Priority from the form

raquo Severity Remove Severity from the form

raquo Risk to Replace current dropdown menu options with Requirements

Performance Customer Release Test Dependency

raquo Probability Remove lsquo(1-100)rsquo from the tag change the field to be a

dropdown with options of High Medium and Low set default to

Medium

raquo Impact Replace all current dropdown options with of High Medium

and Low set default

to Medium

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 6: Risk Management in Sprint Environment

RISK OWNERS

raquo External and Business Risks PLM Directors Sales

raquo Organizational Risks Directors Managers

raquo Project Management Risks Project Managers Managers

raquo PBI Risks Product Owners Sprint Teams

raquo Tasks Risks Sprint Teams

PBIsTasks are Focus of Sprint Teams

CREATING A RISK ITEM

raquo From the Task create the

linked Risk item

raquo The Task will be Affected

by the Risk

TFS Risk WIT

1

2

3

CREATING A RISK ITEMTFS Risk WIT (Cont)

raquo Will be linked to the task if you

started it from the task links

menu

raquo Probability allows 1 ndash 100 For

simplicity use 25() for Low 50

for Med and 75 for High Wersquoll get

more precise over time

raquo Likewise Impact allows 1

through 10 but just use 10 for

High 5 for Medium and 1 for Low

raquo Stick with Dev Doc and SQA

lsquoRisk torsquo options

raquo Leave Severity on default Wersquore

not going to use it for now

These options are changing soon

UPCOMING WIT CHANGESTFS Risk WIT (Cont)

raquo Priority Remove Priority from the form

raquo Severity Remove Severity from the form

raquo Risk to Replace current dropdown menu options with Requirements

Performance Customer Release Test Dependency

raquo Probability Remove lsquo(1-100)rsquo from the tag change the field to be a

dropdown with options of High Medium and Low set default to

Medium

raquo Impact Replace all current dropdown options with of High Medium

and Low set default

to Medium

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 7: Risk Management in Sprint Environment

CREATING A RISK ITEM

raquo From the Task create the

linked Risk item

raquo The Task will be Affected

by the Risk

TFS Risk WIT

1

2

3

CREATING A RISK ITEMTFS Risk WIT (Cont)

raquo Will be linked to the task if you

started it from the task links

menu

raquo Probability allows 1 ndash 100 For

simplicity use 25() for Low 50

for Med and 75 for High Wersquoll get

more precise over time

raquo Likewise Impact allows 1

through 10 but just use 10 for

High 5 for Medium and 1 for Low

raquo Stick with Dev Doc and SQA

lsquoRisk torsquo options

raquo Leave Severity on default Wersquore

not going to use it for now

These options are changing soon

UPCOMING WIT CHANGESTFS Risk WIT (Cont)

raquo Priority Remove Priority from the form

raquo Severity Remove Severity from the form

raquo Risk to Replace current dropdown menu options with Requirements

Performance Customer Release Test Dependency

raquo Probability Remove lsquo(1-100)rsquo from the tag change the field to be a

dropdown with options of High Medium and Low set default to

Medium

raquo Impact Replace all current dropdown options with of High Medium

and Low set default

to Medium

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 8: Risk Management in Sprint Environment

CREATING A RISK ITEMTFS Risk WIT (Cont)

raquo Will be linked to the task if you

started it from the task links

menu

raquo Probability allows 1 ndash 100 For

simplicity use 25() for Low 50

for Med and 75 for High Wersquoll get

more precise over time

raquo Likewise Impact allows 1

through 10 but just use 10 for

High 5 for Medium and 1 for Low

raquo Stick with Dev Doc and SQA

lsquoRisk torsquo options

raquo Leave Severity on default Wersquore

not going to use it for now

These options are changing soon

UPCOMING WIT CHANGESTFS Risk WIT (Cont)

raquo Priority Remove Priority from the form

raquo Severity Remove Severity from the form

raquo Risk to Replace current dropdown menu options with Requirements

Performance Customer Release Test Dependency

raquo Probability Remove lsquo(1-100)rsquo from the tag change the field to be a

dropdown with options of High Medium and Low set default to

Medium

raquo Impact Replace all current dropdown options with of High Medium

and Low set default

to Medium

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 9: Risk Management in Sprint Environment

UPCOMING WIT CHANGESTFS Risk WIT (Cont)

raquo Priority Remove Priority from the form

raquo Severity Remove Severity from the form

raquo Risk to Replace current dropdown menu options with Requirements

Performance Customer Release Test Dependency

raquo Probability Remove lsquo(1-100)rsquo from the tag change the field to be a

dropdown with options of High Medium and Low set default to

Medium

raquo Impact Replace all current dropdown options with of High Medium

and Low set default

to Medium

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 10: Risk Management in Sprint Environment

MITIGATION AND CONTINGENCY PLANS

raquo Wersquove identified risks Now what Mitigation Planning

bull Avoid the consequences of a risk by having a mitigation plan This plan should be added

to your current task (design dev etc) to ensure the risk doesnrsquot materialize

raquo It happened anyway Now what Declare a breakdown and perform the Contingency Plan

bull The mitigation plan wasnrsquot enough Now fall back on Plan B the Contingency Plan This

is the plan you enable AFTER the risk has become a real issue Your task is now in a

state of breakdown

raquo Example

bull Risk If my pants are too big they will fall down causing embarrassment and offense

bull Mitigation Plan I shall wear a belt to keep my pants up

bull Contingency Plan If they still fall down Irsquom going to need to wear suspenders

bull Trigger Event

bull Cost of contingency Estimated $20 - $40

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 11: Risk Management in Sprint Environment

MONITOR AND CONTROLRisk Breakdown Handling

Sprint Planning Task Execution Demo Retrospective

Risk ID Analysis Response Planning Risk Monitor and Control Risk Closing Lessons Learned

Major breakdowns impact

other teams components

or the release Team must

report up to PO Mgr PMMonitor for breakdowns

handle task breakdowns

within the Sprint Team

ID Analyze and Plan early

PBI

Task or

WR

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 12: Risk Management in Sprint Environment

UPDATING WITH EXCEL

raquo Use Excel to track update status and publish back to TFS ndash your preference

raquo Scrum Master can query all related risks and update en masse during status meetings

raquo Risks should have a lifecycle within the sprint They should be closed once the trigger passes

(usually a date or event) or the contingency corrects the breakdown

raquo Monitor all risks until closed Keep the overall risk assessment lsquogreenrsquo by improving the

average risk exposure Mitigating should lessen the probability and impact so updates should

improve the Risk Item status

Expectations for monitoring

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 13: Risk Management in Sprint Environment

RISK AREAS

raquo Extended Data Risk High-level Identification (Web view) Risk High-level

Identification (OneNote)

raquo IDM IDM Risk Area Identification (Web view) IDM Risk Area Identification

(OneNote)

THANK YOU

wwwitroncom

Page 14: Risk Management in Sprint Environment

THANK YOU

wwwitroncom